    STATEWIDE BUSINESS PROCESS PROCEDURE

    Project Management Status Reporting

    Draft

    Office of the Chief Information Officer

    Department of Administration

    State Information Technology Services Division

    PO Box 200113

    Helena, MT 59620-0113

    Tel: (406) 444-2700

    FAX: (406) 444-2701

    DEPARTMENT OF ADMINISTRATION

    Janet R. Kelly, Director

    STATE INFORMATION TECHNOLOGY SERVICES DIVISION

    Richard B. Clark, Chief Information Officer

    Brian Schweitzer

    Governor

    State of Montana

  • 7/29/2019 Draft Status Report New

    2/17

  • 7/29/2019 Draft Status Report New

    3/17

    S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S

    R E P O R T I N G

    P A G E 3

    DRAFT STATEWIDE PROCEDURE:PROJECT MANAGEMENT STATUS REPORTING

    EFFECTIVE DATE: APPROVED:

    I. Procedure Purpose

    This Statewide Procedure defines the steps that agencies shall follow to deliver status information

    of an agency reported project to the State IT PMO. The information shall be presented to

    enterprise funding authorities and other interested parties with the results of the project.

    This Procedure implements the requirements of the State of Montana Information Technology

    Project Management Policy and MCA 2-17-521(4)(c).

    II. Applicability

    This Procedure applies to agencies and third-parties (such as contractors or other service

    providers), who provide project management services related to the planning, implementation and

    closeout of IT projects.

    III. Scope

    This Procedure applies to IT projects funded through the Long Range IT Plan (LRITP) or as

    required by the State of Montana Chief Information Officer (CIO), Office of Budget and ProgramPlanning (OBPP), or Legislative Finance Committee (LFC).

    IV. Definitions

    Term Definition

    Status Report A report required during the course of a project which documents the

    current status of the project.

    Data A subset of information in an electronic format that allows it to be retrieved

    or transmitted. Reference theNational Information Assurance (IA)

    Glossary.Variance A quantifiable deviation, departure, or divergence away from a known

    baseline or expected value. For the purpose of this procedure, Variance

    shall be graphically depicted with a (triangle) or delta symbol.

    Reference theGuide to the Project Management Body of Knowledge

    (PMBOK Guide)-Fourth Edition.

    http://www.cnss.gov/Assets/pdf/cnssi_4009.pdfhttp://www.cnss.gov/Assets/pdf/cnssi_4009.pdfhttp://www.cnss.gov/Assets/pdf/cnssi_4009.pdfhttp://www.cnss.gov/Assets/pdf/cnssi_4009.pdfhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.cnss.gov/Assets/pdf/cnssi_4009.pdfhttp://www.cnss.gov/Assets/pdf/cnssi_4009.pdf
  • 7/29/2019 Draft Status Report New

    4/17

    S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S

    R E P O R T I N G

    P A G E 4

    Term Definition

    Variance Criteria Criteria established for measurement of Variance.

    Organizational

    Process Assets

    Any or all process-related assets, from any or all of the organizations

    involved in the project that are or can be used to influence the projects

    success. These process assets include formal and informal plans, policies,

    procedures, and guidelines. The process assets also include the

    organizations knowledge bases such as lessons learned and historical

    information.

    Reference theGuide to the Project Management Body of Knowledge

    (PMBOK Guide)-Fourth Edition.

    Refer to the separate document, Asset Usage Handling Instructions: Confidential Information

    for information-related definitions.

    Refer to theStatewide Information System Policies and Standards Glossaryfor a list of local

    definitions.

    Refer to the Guide to the Project Management Body of Knowledge (PMBOK Guide)-Fourth

    Editionand the Dictionary of Project Management Terms published by ESI International for

    project management definitions. Where terminology is in conflict, the definitions within the

    PMBOK Guide shall take precedence.

    V. Roles and Responsibilities

    The following roles and responsibilities support this procedure:

    Agency Project

    Manager

    Project manager as defined in the agencys Project Management Plan. The

    Project Manager submits the Status Report to the IT PMO.

    State IT Project

    Management

    Office (IT PMO)

    Tracks, reviews, and retains Status Reports for use in other enterprise

    documents; analyzes for process improvement; and identifies potential

    training needs and facilitates as appropriate.

    VI. Requirements

    Information contained in the Status Report delivered to the IT PMO shall be used in the

    development of enterprise-required documents.

    Reference the separate document, Asset Usage Handling Instructions: Confidential

    Information for guidance on originating, securing, transmitting, and storing non-public

    information which may be included in the deliverables identified in this procedure.

    http://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://itsd.mt.gov/content/policy/policies/Administration/Statewide_Glossary_IS_Policies_and_Standards.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Statewide_Glossary_IS_Policies_and_Standards.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Statewide_Glossary_IS_Policies_and_Standards.pdfhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://itsd.mt.gov/content/policy/policies/Administration/Statewide_Glossary_IS_Policies_and_Standards.pdfhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspx
  • 7/29/2019 Draft Status Report New

    5/17

    S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S

    R E P O R T I N G

    P A G E 5

    A. Information Management

    The information within individual Status Reports are Information Assets1, owned by individuals

    within their respective agencies. Unless specified otherwise by the agency, the agency head or

    equivalent executive officer is the Information Owner2.

    IT PMO-operated information system usage and performance data, information, and statistics

    shall be owned and maintained by IT PMO.

    B. Reporting

    Agencies shall develop and submit Status Reports to the IT PMO for all reported projects in

    accordance with the requirements defined in Appendix A. Project status shall signify current

    status of the schedule, scope and budget of the project. The Status Reportshall:

    Describe the results variance (i.e., the difference) between the current status and

    the last status report based on the information requirements published by the IT PMO

    (See Appendix A).

    1 Reference Asset Usage Handling Instructions: Confidential Information.

    2 Ibid.

  • 7/29/2019 Draft Status Report New

    6/17

    S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S

    R E P O R T I N G

    P A G E 6

    VII. Enterprise Review Process

    The goal of Status Reporting is to provide the stakeholders with information by which the current

    results of the project can be evaluated and approved, and if needed, courses of action can be

    developed, recommended, and implemented. The Enterprise Review Process (Figure 1)

    establishes the procedural relationship between reporting project results and review by

    executives. This process is the basis for IT PMO reporting requirements and actions.

    Figure 1 Enterprise Review Process

    The process has six phases, four of which are addressed within this procedure:

    1 - Establish Information Requirements (This procedure)

    2 - Collect Information (This procedure)

    3 - Analyze Information(This procedure)

    4 - Distribute Finished Analysis(This procedure)

    5 - Evaluate Results

    6 - Deliberations

    This procedure specifies the actions taken to accomplish Phases 1 through 4, above.

  • 7/29/2019 Draft Status Report New

    7/17

    S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S

    R E P O R T I N G

    P A G E 7

    VIII. Procedure

    A. Phase 1Information Requirements

    The IT PMO shall maintain and publish a list (Appendix A) of information required within

    agency Status Reports. This list shall be updated as required. The required information shall bebased upon the documentation defined within the PMBOK Guide.

    Figure 2 Information Requirements Phase

    State IT PMO procedural steps:

    1. Develops information requirements.

    2. Reviews requirements with the CIO and the PMOAG.

    3. Disseminates final information requirements via email to all project managers of

    record and the PMOAG.

  • 7/29/2019 Draft Status Report New

    8/17

    S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S

    R E P O R T I N G

    P A G E 8

    B. Phase 2Collect Information

    Figure 3 Collection Phase

    The following procedure shall be used to develop and deliver an agency project Status Report. In

    accordance with the requirements defined in Appendix A, the project manager on behalf of the

    agency shall:

    1. Classify the information within the Status Report according to the agencys

    information management requirements.

    2. Deliver the Status Report to the IT PMO, which meets the information requirements

    published by the IT PMO as Appendix A.

    3. Deliver Asset Usage Handling Instructions for any confidential information3.

    4. Deliver the Status Reportvia email to the IT PMO [email protected].

    Upon receipt of the Status Reportthe IT PMO shall:

    1. Verify that the report meets the information requirements:

    a. If it does, the report state is accepted.

    b.

    If it does not, the report state is not accepted.2. Acknowledge receipt of an accepted report, and the Collection Phase is complete.

    3. On error, or if the report is not accepted, resolve discrepancies with the submitter.

    3 Ibid.

    http://c/Local_Documents/My_MT_Documents/8-Policy%20Projects/Proj_Mgmt/Closeout%20Procedure/[email protected]://c/Local_Documents/My_MT_Documents/8-Policy%20Projects/Proj_Mgmt/Closeout%20Procedure/[email protected]://c/Local_Documents/My_MT_Documents/8-Policy%20Projects/Proj_Mgmt/Closeout%20Procedure/[email protected]://c/Local_Documents/My_MT_Documents/8-Policy%20Projects/Proj_Mgmt/Closeout%20Procedure/[email protected]
  • 7/29/2019 Draft Status Report New

    9/17

    S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S

    R E P O R T I N G

    P A G E 9

    Upon completion of the Collection Phase, the information shall be analyzed within the Analysis

    Phase.

    C. Phase 3Analyze Information

    Figure 4 Analysis Phase

    State IT PMO procedural steps:

    1. Enter report data into the database.

    2. Perform trend analysis based on the criteria in Appendix B.

    3. Identify (any) anomalies needing clarification from project managers.

    4. Resolve any anomalies with project managers, and update database.

    5. Review the database looking for items that were efficient/effective in the process of

    managing the IT projects.

    6. Identify areas for potential improvement.

    7. Identify items for inclusion within the public Project Management Knowledge Base.

    8. Periodically review the data base and Knowledge Base to identify trends:

    a. Areas where efficiencies could be gained

    b. Potential problems

    c. Best practices

    9. If an area for improvement is noted, work with the process owners and other

    stakeholders to formulate recommendations for process changes.

  • 7/29/2019 Draft Status Report New

    10/17

    S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S

    R E P O R T I N G

    P A G E 1 0

    D. Phase 4Distribute Finished Analysis

    Figure 5 Distribution Phase

    State IT PMO procedural steps:

    1. Assemble finished analysis reports.

    a. Provide for CIO review of report information.

    b. Correct factual errors.

    c. Obtain CIO approval of the finished reports.

    2. Present to stakeholders.

    a. Reports will be submitted to the CIO Office.

    b. For LFC reportable projects, CIOs Office will submit reports to the LFC

    3. Post finished analysis as required.

    a. Hard copy of reports shall be archived within the IT PMO in accordance with

    Records and Information Management Procedures

    b. Electronic copy of reports will be parsed and presented to mature PM

    practices within the state.

  • 7/29/2019 Draft Status Report New

    11/17

    S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S

    R E P O R T I N G

    P A G E 1 1

    IX. Change Control and Exceptions

    TheStatewide Procedure: Development of Statewide Information Technology Procedures and

    Guidelines Procedureshall govern procedure changes or exceptions. Submit requests for a

    review or change to this instrument by Action Request form (at

    http://itsd.mt.gov/content/policy/policies/Administration/action_request.doc ). Submit requests

    for exceptions by anException Request form (at

    http://itsd.mt.gov/content/policy/policies/Administration/exception_request.doc ). Changes to

    policies and standards will be prioritized and acted upon based on impact and need.

    X. Closing

    Direct questions or comments about this instrument to the State of Montana Chief Information

    Officer atSITSD Service Desk(athttp://servicedesk.mt.gov/ess.do ), or:

    PO Box 200113

    Helena, MT 59620-0113(406) 444-2700

    FAX: (406) 444-2701

    XI. References

    A. Legislation

    Title 2, Chapter 17, Part 5, MCA, et al.

    B. Policies, Directives, Regulations, Rules, Procedures,

    Memoranda

    DRAFT Statewide Policy: Information Technology Project Management

    Statewide Policy: Establishing and Implementing Statewide Information

    Technology Policies and Standards

    Statewide Procedure: Development of Statewide Information TechnologyProcedures and Guidelines

    Procedurehttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Procedure.pdf

    C. Standards, Guidelines

    Guide to the Project Management Body of Knowledge (PMBOK Guide)-

    Fourth Edition

    http://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/action_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/action_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/action_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/exception_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/exception_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/exception_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/exception_request.dochttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://data.opi.mt.gov/bills/mca_toc/2_17_5.htmhttp://data.opi.mt.gov/bills/mca_toc/2_17_5.htmhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Policy.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Policy.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Policy.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Policy.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Policy.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Procedure.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Procedure.pdfhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards-Projects.aspxhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Procedure.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Policy.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Enabling_IT_Policy.pdfhttp://data.opi.mt.gov/bills/mca_toc/2_17_5.htmhttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://itsd.mt.gov/content/policy/policies/Administration/exception_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/exception_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/action_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/action_request.dochttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdfhttp://itsd.mt.gov/content/policy/policies/Administration/Procedure_and_Guideline_Development.pdf
  • 7/29/2019 Draft Status Report New

    12/17

    S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S

    R E P O R T I N G

    P A G E 1 2

    XII. Administrative Use

    Product ID: PROC-20101129a

    Proponent: Chief Information Officer

    Publisher Office of the Chief Information Officer

    Published Date:

    Version Date: 11/29/2010

    Custodian: State of Montana Chief Information Officer

    Approved Date:

    Effective Date:

    RIM Class: Record

    Disposition Instructions: Retain for Record

    Change & Review

    Contact:

    SITSD Service Desk(athttp://servicedesk.mt.gov/ess.do )

    Review: Event Review: Any event affecting this instrument may

    initiate a review. Such events may include a change in

    statute, key staff changes or a request for review or change.

    Scheduled Review Date:

    http://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.dohttp://servicedesk.mt.gov/ess.do
  • 7/29/2019 Draft Status Report New

    13/17

    S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S

    R E P O R T I N G

    P A G E 1 3

    A P P E N D I X A

    These requirements are established starting MMmm DD, YYYY. All prior versions are

    superseded.

    Status Report Information Requirements

    Each Status Report shall contain information to satisfy the following:

    Project Management Process Performance

    Project Baseline ()

    Summary of changes from current and previous project baseline during report period

    Scope Performance Variance ()

    Scope variance from the last Baseline Project Management Plan.

    Statement of forecasting method(s) used to derive the Variance(s)

    Summary of approved project changes

    Current status of high issues and risks

    Schedule Performance Variance ()

    Schedule variance from the last Baseline Project Management Plan.

    Statement of forecasting method(s) used to derive the Variance(s)

    Work completed during the period

    Work to be completed next

    Cost Performance Variance ()

    Cost variance from the last Baseline Project Management Plan.

    Statement of forecasting method(s) used to derive the Variance(s)

    Costs incurred.

    Performance Variance ()

    Analysis of past performance,

    Current status of high issues and risks

    Health of the project where:

  • 7/29/2019 Draft Status Report New

    14/17

    S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S

    R E P O R T I N G

    P A G E 1 4

    o Green signifies project is on track and/or minimal variance from project

    management plan.

    o Yellow signifies warning to stakeholders, consider corrective actions or

    monitor previously determined corrective actions and/or moderate

    variance from project management plan.

    o Red signifies problem to stakeholders, immediate corrective action(s)

    required and/or major variance from project management plan.

    Include the Lessons Learned that were identified by the agency during period:

    o Causes of Variance(s)

    o Root Cause of issues

    o Reasoning behind chosen corrective action(s)

    o Information distribution/communication

    Report Delivery

    Project managers shall meet the following delivery requirements:

    1. Reporting Deadline: Close of business the first Monday of each month.

    2. Project managers shall provide the report in an electronic format readable by the state

    standard application.

    3. Project managers shall provide the report in an electronic format that allows for word

    processor merging or cut-and-paste of discrete data items.

  • 7/29/2019 Draft Status Report New

    15/17

    S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S

    R E P O R T I N G

    P A G E 1 5

    State IT Project Management Office

    Report Requirements

    The IT PMO shall deliver reports to meet the following reporting and analysis requirements.

    Executive Process

    This information is developed to meet State of Montana executive decision-maker and

    stakeholder requirements.

    1. Legislative Finance Committee (LFC) on a quarterly basis or as required.

    a. Project Baselineb. Key Project Individuals

    c. Project Phased. Healthe. Funding

    2. Office of Budget and Program Planning (OBPP)

    a. Key Project Metrics during the reporting period

    3. State of Montana Chief Information Officer (CIO) on a monthly basis or as required.

    a. Key Project Metrics during the reporting period.

    b. Lessons learned during the reporting period

    i. Causes of Variance(s)

    ii. Root Cause of issues

    iii. Reasoning behind chosen corrective action(s)

    iv. Information distribution/communication

    Originating-Agency Quality Process

    These requirements originate with one or more agencies to support (any) agency quality

    management programs, and shall be individually defined by those agencies.

    1. Comparison of Agency standing vis--vis the mean/average in agency-define criteria.

    2. Other, in agency-defined criteria.

  • 7/29/2019 Draft Status Report New

    16/17

    S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S

    R E P O R T I N G

    P A G E 1 6

    Information Risk Management

    The Project Status Report shall include;

    1. On exception significant changes to the initial Statement of Impact to the overall risk

    posture of the organization. These changes (if any) to the Statement of Impact shallbe used to inform the overall statewide information risk posture.

    a. Included in the changes to the Statement of Impact, assurance that the

    organization has adjusted the information risk management program

    appropriately.

    Note: A significant change in impact is a change that could reasonably be expected to be

    of concern to the funding and political approvers. This information is obtained in

    consultation with the agencys Information Security Manager. ReferenceSection 2-15-

    114, MCA, and Statewide Policy: Information Security Programs.

    http://data.opi.mt.gov/bills/mca/2/15/2-15-114.htmhttp://data.opi.mt.gov/bills/mca/2/15/2-15-114.htmhttp://data.opi.mt.gov/bills/mca/2/15/2-15-114.htmhttp://data.opi.mt.gov/bills/mca/2/15/2-15-114.htmhttp://data.opi.mt.gov/bills/mca/2/15/2-15-114.htmhttp://data.opi.mt.gov/bills/mca/2/15/2-15-114.htm
  • 7/29/2019 Draft Status Report New

    17/17

    S T A T E W I D E P R O C E D U R E : P R O J E C T M A N A G E M E N T S T A T U S

    R E P O R T I N G

    P A G E 1 7

    A P P E N D I X B

    Trend Analysis CriteriaLast Update: MMmm, DD, YYYY

    The following represents the criteria used to analyze the project closeout reports by the IT PMO

    for use in its deliverables.

    1. Baseline Measures

    a. Number of approved baselines during period.

    2. Scope Measures

    a. Number of planned deliverables during period.b. Number of deliverables delivered during period.

    c. Number of scope changes during period.

    3. Schedule Measures

    a. Number of milestones in original schedule during period.

    b. Number of baseline milestones delivered on time to baseline during period.

    4. Cost Measures

    a. % difference between the cost and the cost estimate during period.b. Number of approved changes to cost estimate during period.

    c. Number of re-baseline budget estimates during period.

    5. Performance Measures