Transcript

Hot Topics

CH (9)

1

Resource Management

CH ( 9 ) Resource Management 2

2

Introduction

This knowledge requires you to understand six processes, as described

in the book PMP®

Exam prep: Plan Resource Management, Estimate Activity Resources,

Acquire Resources, Develop Team, Manage Team, and Control

Resources.

The term resources has a broad meaning here, including both the

people involved in the project (inside and outside the organization)

and the materials , equipment, and supplies needed to complete the

work.

For example, resource management includes developing team

members ̓ skill creating recognition and reward systems for them.

CH ( 9 ) Resource Management 3

3

What is the process of resource management?

Plan Resource Management

Estimate Activity Resources

Acquire Resources

Develop team

Manage team

Control Resources

What are the key outputs of the plan Resource Management Process?

Resource management plan

Team charter

Project documents updates

CH ( 9 ) Resource Management 4

4

What are the key outputs of Estimate activity

Resources?

Resource requirements

Resource breakdown structure

What are the key outputs of the Acquire Resources

process?

Physical resource assignments

Project or work assignments

Resource calendars

CH ( 9 ) Resource Management 5

5

What are the key outputs of the Develop Team Process?

Team performance assessments

Change requests

Project management plan updates

Project documents updates

Organizational process assets updates

What are the outputs of the manage team process?

Change requests

Project management plan updates

Project document updates

Enterprise environmental factors updates

CH ( 9 ) Resource Management 6

6

What are the key outputs of the control Resources

Process?

Work performance information

Updates to project documents and project

management plan

Change requests

CH ( 9 ) Resource Management 7

7

What are the resource responsibilities for project managers?

Determine human and physical resources needed

Negotiate with resource managers and confirm availability of assigned

resources

Create a project team directory and job descriptions for team members

Make sure all roles and responsibilities are clearly assigned

Create a resource management plan

See the full list in the Resource Management chapter of the PMP®

Exam Prep, Ninth Edition

CH ( 9 ) Resource Management 8

8

What is the difference between a RAM chart and a RACI chart?

What does RAM stand for?

What does RACI stand for?

The Responsibility Assignment Matrix (RAM) chart cross-references team

members with the activities or work packages they are to accomplish

The RACI chart defines role assignments more clearly by noting how team

members are to be involves with four categories: Responsible, Accountable,

consulted, informed (RACI)

CH ( 9 ) Resource Management 9

9

What is the purpose of an organizational breakdown

structure?

To assign project responsibilities to division or

departments within the organization, such as

marketing, product development, or IT

CH ( 9 ) Resource Management 10

10

What are the key elements of a resource management plan?

Human resources

Identification of human resource requirements

Roles and responsibilities

Project organizational chars

Process for acquiring human resources

Training, team development, and recognition

Project team management

Compliance

Safety

Release of human resources

CH ( 9 ) Resource Management 11

11

What is the purpose of a team charter?

A working agreement developed by the members of the

project team; it describes the approach the team will take

regarding communications, decision-making, and conflict

resolution, as well as ground rules for team meetings

CH ( 9 ) Resource Management 12

12

What is Preassignment ?

When is negotiation necessary?

Preassignment : Resources, both physical and team, that are assigned

before the project begins

Negotiation is necessary when resources are not preassigned ; this includes

gaining resources from within your organization and in procurement

situations

What is multicriteria decision analysis?

Using a set of criteria (such as availability, cost, experience, location, skill

set, knowledge, or training) to evaluate potential team members

CH ( 9 ) Resource Management 13

13

Name and explain the four motivation theories.

McGregor's theory of X and Y:

Managers believe workers are incapable (X) or employees can direct their

own efforts (Y)

Maslow's Hierarchy of Needs: people are motivated by using their skills

and contributing to the project

McClelland's Theory of needs: people are motivated by one of three

needs (achievement, affiliation, power)

Herzberg's Two-Factor Theory of Motivation: Hygiene factors are not

sufficient to motivate people; motivating agents will keep people

energized and engaged

CH ( 9 ) Resource Management 14

14

What are the responsibilities of the project manager when it comes to

team building?

What are some characteristics of team building?

Guide, manage, and improve the interactions of team members

Improve trust and cohesiveness among team members

Incorporate team-building activities into project activities

Team building requires a concerted effort and continued attention

throughout the life of the project

WBS creation is a team-building activity because it allows team

members to actively engage in the planning and ownership of the

project

CH ( 9 ) Resource Management 15

15

Team building should start early in the life of the project

According to the Tuckman ladder, what are the stages of team

formation and development?

Forming

Storming

Norming

Performing

Adjourning

CH ( 9 ) Resource Management 16

16

Why is influencing an important part of the project manager's

role?

By listening to differing viewpoints, acknowledging them, and

then using communication and persuasive skills,

A project manager can develop mutual trust, and, eventually,

agreement within the team

CH ( 9 ) Resource Management 17

17

What is a team performance assessment?

What are project performance appraisals?

Team performance assessment: an assessment by the

project manager meant to evaluate and enhance the

effectiveness of the project team

Project performance appraisals:

Evaluations of the performance of individual team

members

CH ( 9 ) Resource Management 18

18

How can the training of team members positively impact the project?

Training can help decrease the overall project cost and schedule by

increasing efficiency

What is colocation?

What are the challenges of a virtual team?

Colocation: the entire team has offices together in one place or one room

Challenge of virtual teams: Extra efforts will be required to keep everyone on

a virtual team informed, engaged, and committed to the project work;

there is an emphasis on communication

CH ( 9 ) Resource Management 19

19

Name some communications technology tools that can help a team keep in

touch during a project.

A shared portal

Video or audio conferencing

Email and online chat

Why is it valuable to provide recognition and rewards to a team or individual

team members?

In addition to recognizing past accomplishments, rewards provide incentive

for ongoing achievement and efforts

CH ( 9 ) Resource Management 20

20

What are some of the key actions a project manager can take to help challenge

team members to be part of a high-performing team?

Track and evaluate team performance

Provide leadership

Deal with team issues and facilitate conflict resolution

Negotiate and influence

Adjust plans based on performance data

Manage risks to team success

Observe what is happening

Use an issue log to track resolution

Actively look for and help resolve conflicts among team members

CH ( 9 ) Resource Management 21

21

What is an issue log?

A record that lists the project issues, their causes and

impact on the project, the person(s) responsible for

resolving each issue, the issue status, and target

resolution dates

CH ( 9 ) Resource Management 22

22

What are some of the different types of leadership and management

styles?

Directing Democratic

Facilitating (Participative)

Coaching Analytical

Supporting Charismatic

Influencing Laissez-faire

Delegating Driver

Consultative Autocratic

Consensus consultative-autocratic

Bureaucratic

CH ( 9 ) Resource Management 23

23

What are the different types of power?

Formal (legitimate)

Reward

Penalty (coercive)

Expert

Referent

CH ( 9 ) Resource Management 24

24

List the most common sources of conflict on projects,

in order of most to least common

1. Schedules

2. Project priorities

3. Resources

4. Technical opinions

5. Administrative procedures

6. Cost

7. Personality

CH ( 9 ) Resource Management 25

25

Name some conflict resolution techniques.

Collaborating (problem-solving)

Compromising (reconciling)

Withdrawal (avoidance)

Smoothing (accommodating)

Forcing (directing)

CH ( 9 ) Resource Management 26

26

Define collaborating (problem-solving).

Define compromising (reconciling).

Collaborating: openly discussing differences and

incorporating multiple viewpoints to achieve

consensus (a win-win solution)

Compromising: finding an outcome that brings some

degree of satisfaction to all parties involved

(a lose-lose solution)

CH ( 9 ) Resource Management 27

27

Define withdrawal (avoidance).

Define smoothing (accommodating).

Define forcing (directing).

Withdrawal: postponing a decision or avoiding the

problem

Smoothing: Emphasizing agreement rather than

differences of opinion

Forcing: pushing one viewpoint at all expense of

another (a win-lose solution)

CH ( 9 ) Resource Management 28

28

What is emotional intelligence?

The ability to recognize and express ones emotions

appropriately, and to perceive and manage the emotions

being expressed by others using observation,

communication, and interpersonal skills

The End Thank You

29