7/27/2019 Central Luzon Regional Development Report 2011
1/38
CENTRAL LUZON
REGIONAL DEVELOPMENT REPORT
Central Luzon Regional Development Council2/F Hyatt Garden Building, DoloresCity of San Fernando, Pampanga
2011
Photo credits:Photos were taken from various sources in the internet
7/27/2019 Central Luzon Regional Development Report 2011
2/38
Central Luzon Regional Development Report
2011
i
FOREWORD
The Regional Development Report is intended to measure the progress of attainment of goals
and objectives relative to the Regional Development Plan. The year 2011 marks the first year of
implementation of the Central Luzon Regional Development Plan 2011-2016 and therefore is
significant in monitoring government performance under the current administration.
The preparation of this years Regional Development Report is a collaborative effort of various
regional line agencies identified as main stakeholders towards the realization of the Plan. The
report is divided into five chapters: Chapter I - High Sustained and Inclusive Growth, Chapter II -
Globally Competitive, Progressive, and Resilient Citizenry, Chapter III - World-Class Passenger
Mobility and Cargo Distribution Network, Chapter IV - Sustainable Land-Using Activities, and
Chapter V - Socially Responsible Property Rights. The information on the indicators identifiedunder each chapter were provided by the corresponding regional line agencies and were then
integrated by the secretariat upon crafting of the report. The agency reports also provided for
the substantive explanation of the results and values for each indicator.
Although the 2011 Regional Development Report is an attempt to measure the level of
accomplishment of plan targets, it would be worth noting that the previously identified indicators
may not necessarily be sufficient to characterize or capture the existing situation at that
particular period. Therefore, as there will be a regular review and updating of the Central Luzon
Regional Development Plan, the Regional Development Report shall also be reviewed and
formulated according to such manner.
SEVERINO C. SANTOSRegional DirectorNEDA Regional Office 3
7/27/2019 Central Luzon Regional Development Report 2011
3/38
Central Luzon Regional Development Report
2011
ii
MESSAGE
Monitoring is an equally important and crucial part of the planning cycle. It provides for aneffective avenue for checking accomplishments relative to the targets thereby setting the
rationale for the review and updating of the existing plan.
The 2011 Regional Development Report serves as a scorecard of the regions performance on
the multisectoral objectives as embodied in the Central Luzon Regional Development Plan
2011-2016. Its preparation is a combined effort of the different National Government Agencies
being part of the Regional Development Council.
With a clear and efficient monitoring system in place, everyones effort in the regional
development scene can be effectively accounted and areas for improvement and
recommendations for better implementation can as well be identified. Through the continuedsupport and cooperation of the various stakeholders, an atmosphere of shared development
vision shall make Central Luzon closer to achieving inclusive growth.
OSCAR S. RODRIGUEZRDC 3 ChairmanMayor, City of San Fernando
7/27/2019 Central Luzon Regional Development Report 2011
4/38
Central Luzon Regional Development Report
2011
iii
TABLE OF CONTENTS
Foreword i
Message ii
List of Tables iv
List of Figures v
Abbreviations and Acronyms vi
Executive Summary vii
I. High Sustained and Inclusive Growth 1
A. High GRDP per capita 1
B. High Employment and Family Income Level 1
C. Make food cheap and plentiful 2
D. Improve the profitability and sustainability of MSMEs 5
E. Increase rural farming and fisher folk family incomes 6
F. Upgrade tourism establishments 10
G. Develop Clark-Subic regional tourism hub 10
II. Globally Competitive, Progressive, and Resilient Citizenry 11
A. Minimize natural disaster casualties and economic losses 11
B. Improve basic education achievement rates 12
C. Improve access to health services 14
D. Support the development of world-oriented higher education institutions 17
E. High employable technical and vocational skills 20
III. World-Class passenger mobility and cargo distribution network 21
A. Improve land transport access from the urban core to the east and west
coasts
22
B. Increase the level of service of strategic roads and north-south arterial
links
23
C. Integrate the three modes of transportation (land, air, and sea) 25
IV. Sustainable Land-Using Activities 25
A. Ensure that mining operations are environment-friendly 25
V. Socially-Responsible Property Rights 26
A. Security over property rights 26
7/27/2019 Central Luzon Regional Development Report 2011
5/38
Central Luzon Regional Development Report
2011
iv
List of Tables
Table 1. Household Population 15 years old and over by employment status:
Central Luzon 2009-2011 (in thousands)
2
Table 2. Production, area harvested, and yield per hectare of palay by province,
2010-2011
2
Table 3. Production, area harvested, and yield per hectare of corn by province,
2010-2011
3
Table 4. Production, area harvested, and yield per hectare of yellow and white
corn in Central Luzon, 2010-2011
4
Table 5. Production of high value commercial crops in Central Luzon, 2010-2011 4
Table 6. Production of plantation crops in Central Luzon, 2009-2010 4
Table 7. Livestock and poultry production in Central Luzon, 2010-2011 5
Table 8. Fishery production in Central Luzon, 2010-2011 5
Table 9. Percentage of LGUs with full compliance to the BPLS Streamlining
Project
6
Table 10. Visitor Arrivals, Central Luzon, 2007-2011 10
Table 11. Regional Achievement Test Results, SY 2009-2010 and SY 2010-2011 13
Table 12. Regional Achievement Test Results for Fourth Year Students, SY 2009-
2010 and SY 2011-2012
14
Table 13. 2011 Prevalence of Severely Underweight and Underweight
Preschoolers in Central Luzon
16
Table 14. Summary of enrollees and graduates for SUCs and Private HEIs in
Central Luzon, SY 2010-201217
Table 15. Table 15. Average Percent Passing in Licensure Exams: Central Luzon,
2008-2010
18
Table 16. Accomplishment on Enrolled, Graduated, Assessed, Certified andEmployed (EGACE), Central Luzon 20
Table 17. Inventory of existing national roads, as of June 2012 21
Table 18. Regional summary of length and type of national roads and bridges, as of
June 2012
22
7/27/2019 Central Luzon Regional Development Report 2011
6/38
Central Luzon Regional Development Report
2011
v
List of Figures
Figure 1. Performance Indicators in Government Elementary Schools 13
Figure 2. Performance Indicators in Government Secondary Schools 14
7/27/2019 Central Luzon Regional Development Report 2011
7/38
Central Luzon Regional Development Report
2011
vi
ABBREVIATIONS AND ACRONYMS
AMAS Agribusiness and Marketing Assistance ServiceARB Agrarian Reform BeneficiariesBAS Bureau of Agricultural StatisticsBDRRMC Barangay Disaster Risk Reduction and Management CouncilBHW Barangay Health WorkerBLES Bureau of Labor and Employment StatisticsBPLS Business Permits and Licensing SystemCARP Comprehensive Agrarian Reform ProgramCHED Commission on Higher EducationCPX Communication ExerciseDA Department of AgricultureDENR Department of Environment and Natural ResourcesDEPED Department of EducationDOT Department of TourismDPWH Department of Public Works and HighwaysDTI Department of Trade and IndustryEGACE Enrolled, Graduated, Assessed, Certified and EmployedEP Exploration PermitEPEP Environmental Protection and Enhancement ProgramGRDP Gross Regional Domestic ProductHDPE High Density PolyethyleneICS Incident Command SystemIEC Information and Education CampaignINCDP Integrated Non-Communicable Disease ProgramISAGP Industrial Sand and Gravel PermitLDRRMC Local Disaster Risk Reduction and Management CouncilLDRRMO Local Disaster Risk Reduction and Management OfficeLGU Local Government Unit
LMS Land Management ServiceMGB Mines and Geosciences BureauMOET Minus One Element TechniqueMPS Mean Percentage ScoreMRFC Mines Rehab Fund CommitteeMSME Micro Small and Medium EnterprisesNBS Newborn ScreeningNDRRMC National Disaster Risk Reduction and Management CouncilNNC National Nutrition CouncilOPT Operation TimbangPAL Private Agricultural LandsPCIC Philippine Crop Insurance Corporation
RAT Regional Achievement TestREDAS Rapid Earthquake Damage AssessmentRTESDP Regional Technical Educations and Skills Development PlanSCADC Subic Clark Alliance Development CouncilSMAW NC II Shielded Metal Arc Welding National Certificate IITESDA Technical Education and Skills Development AuthorityTVET Technical and Vocational Education and TrainingTVI Technical Vocational Institutions
7/27/2019 Central Luzon Regional Development Report 2011
8/38
Central Luzon Regional Development Report
2011
vii
EXECUTIVE SUMMARY
In general, the various sectoral programs and projects identified and included in the Central
Luzon Regional Development Plan 2011-2016 are geared towards the attainment of sustained
inclusive growth. The 2011 Central Luzon Regional Development Report likewise integrates the
different development indicators to measure the level of accomplishment of the plans first yearof implementation.
The 2011 Central Luzon Regional Development Report is composed of five chapters: (i) High
Sustained and Inclusive Growth, (ii) Globally Competitive, Progressive, and Resilient Citizenry,
(iii) World-Class Passenger Mobility and Cargo Distribution Network, (iv) Sustainable Land-
Using Activities, and (v) Socially Responsible Property Rights.
Chapter I High Sustained and Inclusive Growth presents several economic indicators that
aims to ensure equal growth for all and a sustained significant regional contribution to the
national economy. In 2011, Central Luzons economy slowed down to a 7.5 percent growth rate
from a 10.7 percent growth in 2010. This is due to the decelerated growth rate of the industrysector which accounts for 42.5 percent of the regions economy. Meanwhile, a 5.49 percent
increase in GRDP per capita was recorded for the region, ranking it fourth among other regions
in the country.
Employment rate in the region exhibited an increasing trend from 2009 levels. In 2010,
employment rate was recorded at 91.2 percent while in 2011 it was recorded at 91.5 percent.
The recovery of the global economy from the recent economic recession is expected to
contribute in sustaining the positive increases.
In 2011, the MSMEs which are an important part of the local economy has generated an
additional 106,103 jobs while contributing1,128.7 million in total sales, $ 42 million in exportsales and 9,774 million in investments.
Also in the same year, agricultural production has suffered major setbacks due to typhoons that
caused flooding in most parts of Central Luzon. Palay production for the year dropped by 11.57
percent while corn production decreased by 4.75 percent. The same can be observed in the
fishery sector which has suffered a decrease of 3.37 percent in production. Meanwhile, the
production of high value commercial crops and livestock and poultry recorded an increase of
4.54 and 2.89 percent respectively.
Tourism which is targeted to be one of the key contributors in the regional economy exhibited a
good performance, more specifically it enjoyed a 189 percent increase in tourist arrivals from
the 2010 levels. This was due to a more precise accounting of visitors from accommodation
establishments. Of the about 1.7 million visitor arrivals, 1.5 million or about 91 percent are
domestic visitors.
Some of the efforts of the different agencies of the government to revitalize the tourism industry
in Central Luzon included the expansion of operations of the Clark International Airport and
prioritization of infrastructure support projects for full implementation in the next five years such
7/27/2019 Central Luzon Regional Development Report 2011
9/38
Central Luzon Regional Development Report
2011
viii
as roads leading to identified tourist destinations in each of the seven provinces. Furthermore,
the Clark-Subic hub was identified as one of the featured tourism clusters in the recently crafted
National Tourism Development Plan.
Chapter IIGlobally Competitive, Progressive, and Resilient Citizenry characterizes the future
population as those having world-class technical skills responsive to local and global labor
demands. It also aims to capacitate the stakeholders against possible events of natural
disasters brought about by climate change.
The major strategies employed to strengthen community resilience to disasters involved
massive information dissemination campaigns and capacity development programs. In
particular, Local Disaster Risk Reduction Management Councils (LDRRMCs) in the region were
oriented on the salient features of Republic Act 10121 otherwise known as An Act
Strengthening The Philippine Disaster Risk Reduction And Management System, Providing For
The National Disaster Risk Reduction And Management Framework And Institutionalizing The
National Disaster Risk Reduction And Management Plan. In 2011, 20 summits were
conducted to this effect and as a result, 61 LDRRMCs and 20 Barangay Disaster RiskReduction Management Councils (BDRRMCs) were organized.
To equip local policy and decision-makers of the technical know-how in disaster management,
capacity building on the use of Rapid Earthquake Damage Assessment (REDAS) through
Phivolcs was also conducted in Olongapo City. In addition, at the regional level, technical
assistance is extended to the seven provinces in the integration of disaster risk reduction and
climate change adaptation in land use planning.
On the education sector, the primary measure of quality of services is the results of the
Regional Achievement Test (RAT) in the elementary and secondary levels. For SY 2010-2011,
results of the RAT for the elementary division showed that among the five learning areas,English and Science and Health recorded a decrease from the previous school year by 0.23 and
0.91 percent respectively. All the other learning areas recorded an increase with Makabayan
having the highest of 4.25 percent. On the other hand, results of the RAT for the fourth year
students revealed a declining trend from the previous three years.
Improving access to health services is also one of the developmental strategies of Central
Luzon. In terms of maternal and newborn health, family planning still remains to be the main
approach. For 2011, contraceptives and other family planning commodities were distributed to
two (2) provinces, five (5) cities, and 37 municipalities in the region. This was accompanied by
Family Planning Competency-based Trainings. Moreover, Barangay Health Workers were also
made to undergo Newborn Screening Orientations.
Meanwhile, under the Garantisadong Pambata Strategy of Universal Vitamin A
supplementation, a 92.65 percent coverage in 2011 was recorded for Central Luzon. In addition,
advocacies on improved nutrition practices such as breastfeeding and complementary feeding
were implemented in both public and private hospitals. Moreover, the average prevalence of
underweight preschoolers across the region was 4.18 percent with the Province of Aurora
having the highest prevalence of 11.25 percent.
7/27/2019 Central Luzon Regional Development Report 2011
10/38
Central Luzon Regional Development Report
2011
ix
Control and treatment of leading communicable diseases including malaria and tuberculosis has
also been implemented. In 2011, a 70 percent reduction in malaria morbidity rate, and a 58
percent and 75 percent case detection rate and cure rate respectively for tuberculosis was
recorded for Central Luzon.
For non-communicable diseases which include lifestyle related illnesses such as cardiovascular
disease, cancer, chronic obstructive pulmonary disease, and diabetes, frontline health workers
were given training on the Integrated Non-Communicable Disease Program (INCDP).
Job mismatch has been a lingering employment challenge not only in Central Luzon but for the
whole country. Consequently, capitalization on skills development has been another strategy for
increasing employability of graduates. In 2011, an increase of 144 percent from 2010 levels has
been achieved in terms of enrollees from the four training delivery modes conducted by the
TESDA 3: school-based, center-based, community-based and enterprise-based programs.
These account for 154,213 enrollees for the current year. Meanwhile, certification rate for the
region remained high at 84 percent.
Chapter III World Class Passenger Mobility and Cargo Distribution Network. The
accomplishments in 2011 are geared towards the realization of the plan and strategy of the
infrastructure sector of the Regional Development Plan. The region continuously builds up
strategies to be resilient amidst the appalling effect of calamities in infrastructures to sustain
development and inclusive growth. The Public-Private-Partnership still stand out as the principal
means to attain the goals of the Region.
Chapter IVSustainable Land-Using Activities aims to ensure sustainable mining operations in
the region. Regular monitoring and auditing of approved mining contracts/permits including
areas within mineral reservations as to compliance to the implementation of approved Work
Program and Safety, Health, Environment and Social Programs is conducted by the Mines andGeosciences Bureau. In 2011, a total of 40 Work Programs and 18 Safety, Health, Environment
and Social Programs were monitored. In addition, 35 complaints/cases/conflicts were
investigated and resolved.
On the other hand, in the issuance of mining rights/contracts/permits, a total of five (5) permits
ranging from Exploration Permit (EP), Industrial Sand and Gravel Permit (ISAGP), and Mineral
Processing Permit were issued by the MGB. In ensuring environmental protection two (2)
Environmental Protection and Enhancement Program (EPEP) were endorsed to the Mines
Rehab Fund Committee (MRFC) and at the same time, two (2) Social Development
Management Programs (SDMP) were approved.
Chapter VSocially Responsible Property Rights primarily aims to increase tenurial security for
the marginalized sector of the society including farmers and indigenous peoples. For the
Comprehensive Agrarian Reform Program, the working scope for Central Luzon which is
registered at 450,904 hectares until 2014 has been trimmed down to only about 16,803
hectares or 3.7 percent of the total working scope for the next three years since the region had
already parceled and handed out 434,101 hectares to qualified agrarian reform beneficiaries
7/27/2019 Central Luzon Regional Development Report 2011
11/38
Central Luzon Regional Development Report
2011
x
(ARBs) as of December 31, 2011. Large portions of the remaining working scope are located in
the provinces of Bulacan, Nueva Ecija North, and Tarlac.
Meanwhile, under the DENR-Land Management Service (LMS), a total of 1,043 patents have
been accomplished on the Patent Processing and Issuances. The patent issuances under RA
10023 (Residential Free Patent Law) totaled to 3,993 representing 60 percent of the annual
target. The relatively low accomplishment is due to some factors such as difficulty in securing
zoning certification.
7/27/2019 Central Luzon Regional Development Report 2011
12/38
Central Luzon Regional Development Report
2011
1
I. High Sustained and Inclusive Growth
A. High GRDP per capita
Central Luzons economy slowed down from a 10.7 percent growth rate in 2010 to
7.5 percent in 2011. This can be attributed to the decelerated growth of the Industry
Sector which accounts for 42.5 percent of the regions economyand can be further
explained by the notable decrease in export and domestic sales and investments.
In 2011, the region suffered from a 32.08 percent decrease in export sales
amounting to US$ 20.015 million while a 46.94 percent decrease in domestic sales
amounting to 998.5 million was recorded. Likewise, a 23.09 percent decrease in
investments corresponding to 2,934.07 million was also observed.
Per capita GRDP at 2000 constant prices increased from 50,563.00 in 2010 to
53,339 in 2011 or an increase of 5.49 percent.
B. High Employment and Family Income Level
The employment rate of the region in 2009 is at 90.8 percent and is targeted to
increase by 2.0-3.0 percent for the next six years. The regions employment rate in
2011 reflected a 0.7 percent increase from 2009 levels, almost a quarter from the
high level target of 3.0 in 2016.
In 2011, the estimated household population aged 15 years old and over in Central
Luzon is 6.828 million, an increase of about 0.146 million or 2.18 percent from 2010
levels (see Table 1). Labor force participation rate in 2011 is 61.3 percent and
exhibited a steady increase for the last three years.
Of the 4,188 million persons in the labor force, 91.5 percent were employed
corresponding to a three percent increase from the previous year. This can be partly
due to the employment creation program embodied in the Economic Resiliency Plan
of the government in 2009. Meanwhile, underemployment rate remarkably increased
to 11.1 percent from the previous years rate of 9.1 percent indicating the quality of
jobs generated by the economy.
Unemployment rate in the region is still higher than the national average but however
remained on a decreasing trend and is placed at 8.5 percent in 2011, a slight
decrease of 0.3 percent from the previous year. Furthermore, the number of
unemployed persons in Central Luzon also decreased steadily from about 363,952persons in 2009 to about 355,980 persons in 2011.
7/27/2019 Central Luzon Regional Development Report 2011
13/38
Central Luzon Regional Development Report
2011
2
Table 1. Household Population 15 years old and over by employment status: CentralLuzon 2009-2011 (in thousands)
Indicator 2009 2010 2011
HH population 15 years old and over 6,531 6,682 6,828
Labor Force 3,956 4,047 4,188
Employed 3,592 3,716 3,831Underemployed 281 339 425
Unemployed 364 358 358
Labor Force Participation Rate (%) 60.6 61.0 61.3
Employment Rate (%) 90.8 91.2 91.5
Underemployment Rate (%) 7.8 9.1 11.1
Unemployment Rate (%) 9.2 8.8 8.5Source: Current Labor Statistics, BLES
C. Make food cheap and plentiful
In 2011, the regions agricultural sector was greatly affected by several weatherdisturbances such as typhoons Pedring and Quiel which ravaged large portions of
agricultural lands in the lowland plains of Nueva Ecija, Pampanga, Bulacan, and
Tarlac. Consequently, palay production of the region significantly decreased
alongside corn and fishery production. Meanwhile, high value commercial crops and
livestock and poultry production slightly increased over 2010 levels.
Crop Product ion
Palay
Central Luzon is known as the rice granary of the Philippines. However, palayproduction like other agricultural commodities is dependent on the prevailing
climate and weather condition. Due to the typhoons that razed the region this
year, the volume of palay produced dropped by 11.57 percent as compared over
last year, from 2,958,415 mt to 2,616,083 mt. On the other hand, area harvested
also decreased by 9.53 percent from 681,901 hectares in 2010 to 616,887 in
2011. Consequently, the average yields per hectare for rice also dropped from
4.34 mt/ha to 4.24 mt/ha or a reduction of 0.10 percent (see Table 2).
Table 2. Production, area harvested, and yield per hectare of palay by province, 2010-2011.Production
(mt)
Area harvested
(ha)
Yield per hectare
(mt/ha)
Increase/
Decrease2010 2011 2010 2011 2010 2011
Central Luzon 2,958,415 2,616,083 681,901 616,887 4.34 4.24 (0.10)
Aurora 84,994 85,433 23,252 22,885 3.66 3.73 0.07
Bataan 131,610 123,511 31,604 31,117 4.16 3.10 (1.60)
Bulacan 298,376 227,607 79,161 60,219 3.77 3.78 0.01
Nueva Ecija 1,374,173 1,313,487 299,844 286,821 4.58 4.58 0.00
Pampanga 393,328 310,456 84,746 68,826 4.64 4.51 (0.13)
Tarlac 562,180 450,757 133,424 116,734 4.21 3.86 (0.35)
7/27/2019 Central Luzon Regional Development Report 2011
14/38
Central Luzon Regional Development Report
2011
3
Zambales 113,754 104,832 29,870 30,285 3.81 3.46 (0.35)Source: Basic data from BAS
Nueva Ecija, the rice bowl of Central Luzon registered the highest production of
palay in the region with 1,313,487 mt or 50 percent of the regions total
production while Aurora only shared 85,433 mt or three percent. At the same
time, the former was the highest yielder of palay per hectare with 4.58 mt/ha.
For the value of production for 2010 at constant prices, the region shared 20
percent or 26,418.69 million to the countrys total value of palay produced
which is the highest among all other regions. In terms of production, the region
contributed 15.68 percent to national output, a notable decrease from the 2010
contribution of 18.76 percent.
Corn
In 2011, the volume of corn produced decreased by 4.75 percent, from 197,890
mt to 188,494 mt. This is due to shifting of corn farmers to rice, sugarcane andother cash crops and to the typhoons that visited the region during the 3 rdand 4th
quarter. One of the provinces that was hard hit was Aurora. Although production
decreased, yield per hectare for corn slightly increased by 0.25 percent (see
Table 3.) and this can be attributed to the intensified utilization of BT corn hybrid
variety.
The Province of Tarlac maintained its position as the biggest producer of corn
with 100,888 mt production or 53.52 percent of the total corn produced in the
region. On the other hand, Zambales contributed the smallest production of 625
mt or a share of 0.33 percent of the regions total production. Farmers in
Zambales concentrated on mango production and are hesitant to plant corn.
Table 3. Production, area harvested, and yield per hectare of corn by province, 2010-2011.Production
(mt)Area harvested
(ha)Yield per hectare
(mt/ha)Increase/Decrease
2010 2011 2010 2011 2010 2011
Central Luzon 197,890 188,494 42,977 38,836 4.60 4.85 0.25
Aurora 18,395 13,386 3,983 3,003 4.62 4.46 (0.16)
Bataan 9,361 8,814 1,934 1,837 4.84 4.80 (0.04)
Bulacan 2,532 2,267 919 938 2.76 2.42 (0.34)
Nueva Ecija 15,103 15,135 6,064 5,987 2.49 2.53 0.04
Pampanga 49,447 47,478 11,212 10,442 4.41 4.55 0.14
Tarlac 102,666 100,888 18,720 16,467 5.48 6.13 0.64Zambales 386 526 145 162 2.66 3.25 0.58
Source: Basic data from BAS
The region reached an average yield per hectare of 5.78 mt/ha for yellow corn
and 2.15 mt/ha for white corn. Furthermore, there was a decrease in yield of
7,769 mt or 4.44 percent for yellow corn and 1,627 mt or 7.09 percent for white
corn as compared over last year (see Table 4).
7/27/2019 Central Luzon Regional Development Report 2011
15/38
Central Luzon Regional Development Report
2011
4
Table 4. Production, area harvested, and yield per hectare of yellow and white corn inCentral Luzon, 2010-2011
2010 2011 % Change
Product ion (mt)
Yellow Corn 174,942 167,173 (4.44)White Corn 22,948 21,321 (7.09)
Area Harvested (ha)
Yellow Corn 32,304 28,926 (10.46)White Corn 10,673 9,910 (7.15)
Yield per hectare (mt/ha)
Yellow Corn 5.42 5.78 6.64White Corn 2.15 2.15 0.00
Source: Basic data from BAS
High Value Commercial Crops
High Value Commercial Crops production excluding plantation crops totaled
518,029.08 mt. An increase of 4.54% or 22,513.70 mt. was achieved despite thethe calamities that greatly affected the region (see Table 5).
Table 5. Production of high value commercial crops in Central Luzon, 2010-2011.Commodity Production (MT) % Change
2009 2010
Vegetables 115,863.33 117,184.94 1.14Legumes 39,225.71 39,238.28 0.03Rootcrops 38,991.25 38,862.61 (0.33)Fruits 227,246.79 246,402.56 8.43Spices 74,188.30 76,340.69 2.90Total 495,515.38 518,029.08 4.54Source: DA III
Production of plantation crops on the other hand, declined as the production of
sugarcane decreased by 18.69 percent or 193,221.31 mt.
Table 6. Production of plantation crops in Central Luzon, 2009-2010.Plantation Crops Production (MT) % Change
2009 2010
Abaca 99.50 109.00 9.55Coconut (with husk) 199,730.08 210,442.31 5.36Coffee (dried
berries)
3,411.32 3,536.52 3.67
Sugarcane 1,034,084.30 840,862.99 (18.69)Tobacco 202.15 195.06 (3.51)Total 1,237,527.35 1,055,145.88 (14.74)Source: DA III
7/27/2019 Central Luzon Regional Development Report 2011
16/38
Central Luzon Regional Development Report
2011
5
Livestock and Poultry
For the livestock and poultry sector, production grew by 2.89 percent from 3,744.77
thousand metric tons in 2010 to 3,853.08 in 2011. Dairy and chicken production had
the highest increase with 4.77 and 4.52 percent, respectively. Meanwhile, carabao
and goat production had exhibited decrease from 2010 levels by 0.34 and 0.32
percent.
Table 7. Livestock and poultry production in Central Luzon, 2010-2011.Production (thousand mt) Percent Change
(%)2010 2011
1. Carabao 148.02 147.52 (0.34)2. Cattle 251.3 256.26 1.973. Hog 1,898.16 1,940.35 2.224. Goat 78.45 78.2 (0.32)5. Dairy 15.71 16.46 4.776. Chicken 1,353.13 1,414.29 4.52
TOTAL 3,744.77 3,853.08 2.89Source: Bureau of Agricultural Statistics
Fishery
In 2011, aquaculture accounts for 82 percent of fisheries production in the region.
However, due to the typhoons that hit during the year, aquaculture production
decreased by 3.37 percent from 219,783.65 MT in 2010 to 212,370.90 in 2011. On
the other hand, commercial and municipal fisheries production increased by 4.92 and
3.67 percent respectively.
Table 8. Fishery production in Central Luzon, 2010-2011.Production (mt) % Change
2010 2011
Commercial Fisheries 4,335.78 4,548.99 4.92Municipal Fisheries 40,559.61 42,047.05 3.67Aquaculture 219,783.65 212,370.87 (3.37)TOTAL 264,679.04 258,966.91 (2.16)
Source: Bureau of Agricultural Statistics
D. Improve the profitability and sustainability of MSMEs
The profitability and sustainability of MSMEs in the region were improved through
improvements in the business environment and increases in productivity.
Business environment was improved by simplifying the requirements for Business
Name Registration process which resulted to a more shortened processing time from
60 minutes in 2010 to a maximum of 20 minutes in 2011. Consequently, there was a
2.62 percent increase in the registration of new MSMEs. In 2011, a total of 33,945
new MSMEs were registered compared to 33,079 in 2010.
7/27/2019 Central Luzon Regional Development Report 2011
17/38
Central Luzon Regional Development Report
2011
6
Continuous efforts on streamlining the Business Permits and Licensing System
(BPLS) were also carried out in the region. As of the end of 2011, 67 percent of the
LGUs in the region have complied with the four standard reforms in the BPLS
Streamlining Project, the most number of implementers in the country. The Province
of Tarlac has the highest percentage of compliance among its constituent LGUs with
94.44 percent while the Province of Bulacan has the lowest with 4.17 percent (seeTable 9).
Table 9. Percentage of LGUs with full compliance to the BPLS Streamlining Project.
Province
TotalNo.of
LGUs
UnifiedForm*
StandardSteps**
StandardProcessing
Time***Signatories****
LGUs withComplete
Compliance
% ofCompliance
New Renewal New Renewal New Renewal
Aurora 8 5 8 8 8 8 8 8 5 62.50
Bataan 12 11 12 12 12 12 12 12 11 91.67
Bulacan 24 1 21 22 24 23 17 17 1 4.17
NuevaEcija 32 27 26 26 31 31 29 29 25 78.13
Pampanga 22 16 21 21 21 21 21 21 16 72.73
Tarlac 18 18 18 18 18 17 18 18 17 94.44
Zambales 14 13 13 13 12 12 13 13 12 85.71
TOTAL 130 91 119 120 126 124 118 118 87 66.92Source: DTI III
The region through the Department of Trade and Industry (DTI) was also able to
assist 4,257 MSMEs on services ranging from registration of their business name to
conduct of capability building seminars such as Managerial, Entrepreneurship,
Quality and Productivity, Values and Skills Training Programs, Product Development,Market Promotion through Trade Fairs, Pasalubong Centersand Market Matching,
Financing Facilitation and Business Consultancy. In 2011, total sales generated by
the DTI-assisted MSMEs totaled 1,128.7 Million while export sales reached $ 42
Million and investments at 9,774 Million. Furthermore, an additional 106,103 new
jobs were generated.
E. Increase rural farming and fisher folk family incomes
Technical, financial, and market support programs were extended by the Department
of Agriculture to improve agricultural productivity of the region and in the process
enhancing income of farmers.
Production Support Services
As the Department of Agriculture temporarily suspended the seed subsidy
program, the region had implemented the Palay Crop Insurance activity which
provides a comprehensive form of assistance to farmers in collaboration with the
Philippine Crop Insurance Corporation (PCIC) and LGUs. In 2011,
7/27/2019 Central Luzon Regional Development Report 2011
18/38
Central Luzon Regional Development Report
2011
7
4,321,462.27 was expensed for the insurance of 6,370.08 hectares of palay
benefiting 7,311 farmers.
In the distribution of Biological Control Agents, 2,700 bags and 200 sachets of
metarhizium which covered 1,370 hectares and 40,722 sachets of trichoderma
which covered 2,777.40 hectares of rice land were distributed.
To aid in determining the fertilizer needs of rice areas, 120 Minus-One Element
Technique (MOET) were distributed and 3,828 Leaf Color Charts were given to
different municipalities in Central Luzon. In addition to this, 57 fertility guide maps
were produced, 55 of which are municipal level maps while 2 are provincial level
maps.
The region has also successfully distributed 396 units of on-farm machinery and
equipment to the qualified recipients. A total of 130 units of rice drum seeder, 142
units of hand tractor, 9 units of four-wheel mini tractor, 21 units of rice thresher,
and 14 units of combine harvester were dispensed.
Another area with which production support services were extended is on
cassava. Cassava is considered as one of the staple food crops in the country. It
also has an increasing demand as food, as feed ingredients, and as a promising
feedstock for the production of bio-ethanol. Consequently, the Department of
Agriculture implemented the Cassava Project under the Corn Program to
strengthen the support services for the commercial production of root crops in the
country. In support to the project, the region distributed 3,607 seed pieces of
planting materials with a disbursed budget of 2.5 Million.
Under the Biological Control Program, 200,000 trichogramma cards were given
in the whole region while 250,000 earwigs were produced and handed out to
corn farmers. Six (6) units of farm tractors were also allocated for selected
provinces in the region to address the Farm Mechanization Program of the
Department.
On the High Value Crops Development Program, a total of 690 kilograms of
assorted seeds were distributed in the whole region. These included onion
seeds, malunggay cuttings, seedlings of various fruit trees, coffee seedlings, and
suckers of banana. In support of production, 230 units of farm equipment and
machineries were also distributed. These included sprayers, hand-tractors, multi-
tilling machines, and mango dehydrators. A total of 53 heads of draft animals and
127 farm implements such as plows and harrows were also distributed. Lastly,
193 units of pH meter were also allotted to selected beneficiaries.
In the Livestock Program, 31 heads of breeder sheeps were maintained
producing 25 heads of lambs. A pasture land covering 1.5 hectares was also
developed. Moreover, a total of 106 heads of breeder animals (cattle, goat and
sheep) and 72 heads of poultry were maintained in livestock production centers.
7/27/2019 Central Luzon Regional Development Report 2011
19/38
Central Luzon Regional Development Report
2011
8
From calves, 16 kids, 60 lambs, and 3,890 chicks were produced and distributed
to 55 farmers/raisers. Through the artificial insemination program, 1,047 calves,
1,399 caracalves and 55 kids were produced. In addition, 7,031 piglets were
produced benefitting 5,333 farmers and raisers.
Infrastructure Development
In support to agricultural production through improved infrastructure, 29 farm-to-
market roads were upgraded/rehabilitated amounting to 105,264,000.00 with a
total length of 66.07 kilometers. Based on constructed length, 86.41 percent or
57.09 kilometers were located in the Province of Nueva Ecija.
Irrigation Development Services
High Density Polyethylene (HDPE) hose and plastic drums are designed to be
used for irrigation of vegetable production areas. Likewise, Small Farm Reservoir
and Spring Development were also constructed for the same purpose. In 2011,
the region awarded 600 rolls or 60,000 meters of HDPE hose and 688 plasticdrums to the seven provinces that benefited 144 farmer cooperatives and
associations.
Postharvest Development Services
Infrastructure and postharvest facilities are believed to give long-term and greater
contribution and impact to the national goal of attaining rice self-sufficiency. In
2011, a total of 176 postharvest facilities were distributed in the whole region. In
summary, 108 units or 61 percent are multi-purpose drying pavements, 57 units
or 32 percent are flatbed dryers, seven (7) units or 4 percent are moisture meters
while three (3) units or 2 percent are warehouses and one (1) unit is a ricemill.
Under the High Value Crops Development Program, nine (9) units of processing
equipment including vegetable and fruit juicers and three (3) postharvest
equipment were distributed in the region. Six (6) household level processing
facilities including vegetable noodle machine, chipping machine, and fruit
dehydrator were awarded to Cooperatives and RICs in Bataan, Bulacan,
Pampanga, Tarlac and Zambales and one (1) unit village level processing plant
was given to the municipality of Dingalan, Aurora. Lastly, nine (9) units of hanger
storage for onion were constructed in the Province of Nueva Ecija
Marketing and Development Services
Market matching and investment forums/seminars were conducted to improve
profitability of agricultural production. In 2011, five (5) market matching for corn,
fruits and vegetables were accomplished and attended by 156 farmers in
selected municipalities of Aurora, Bulacan, and Pampanga. On the other hand,
three (3) investment for a were organized in Iba, Zambales, City of San
7/27/2019 Central Luzon Regional Development Report 2011
20/38
Central Luzon Regional Development Report
2011
9
Fernando, Pampanga, and Cabanatuan City, Nueva Ecija. This activity was
attended by 400 government employees and private individuals.
A market research study for squash in three (3) municipalities of Nueva Ecija was
administered in collaboration with the DA-AMAS.
Extension Support, Education and Training Services
Technology demonstration is one of the long-standing activities in the rice
program. This served as the way of disseminating information on new packages
of technologies on agricultural productivity. In 2011, 85 Integrated Techno-demo
sites were established while 922 AEWs (hybrid-inbred techno-demo) sites were
launched.
Still under the rice program, 85 batches of Farmers Field School were conducted
in the region. A total of 2,485 farmers participated. Two (2) batches of training of
trainors were also conducted. This aims to train rice farmers to act as
facilititators/trainors on new packages of rice farming technologies. A total of 61farmers from different provinces benefited from the training.
Meanwhile, under the Corn Program, 50 Farmers Field School and five (5)
Entrepreneurial Trainings were conducted in the region. Through this, corn
farmers learned new packages of technologies in corn production while their
wives can also help in income generation through production of handicrafts from
corn husks.
Rehabilitation Program
Several typhoons hit the region this year. Consequently, the departmentimmediately executed a rehabilitation program to restore agricultural activity and
region productivity on damaged areas. Under the rehabilitation program, the
region has distributed a total of 220,804 bags of seeds (hybrid and certified
seeds) worth 368,797,380 which benefited a total of 138,836 rice farmers. In
addition, 580 kilograms of assorted vegetable seeds, 1,428 papaya seedlings,
and 8,929 assorted seedlings of fruit bearing trees were distributed.
Research and Development Services
In 2011, the terminal report on the research study on Farmers Participatory
Evaluation of Corn Production was submitted to the Bureau of Agricultural
Research. The study determined that the best fertilizer treatment application of
120-40-50 (NPK) per hectare was recommended to be used by corn farmers in
the provinces of Pampanga and Tarlac. Furthermore, the study resulted to an
average yield of 10 tons/ha obtained through actual farming condition or
controlled condition.
7/27/2019 Central Luzon Regional Development Report 2011
21/38
Central Luzon Regional Development Report
2011
10
Under the Cassava Project, 4,000 cuttings of cassava were produced through
tissue culture and adoption of two-node technology. These were given out to
farmer beneficiaries. Trial of 13 cassava varieties were also planted in the lahar
areas of Sta. Barbara, and Bacolor, Pampanga. Based on the study, five (5)
varieties including Rayong 5, Lakan 1, CV 34, CV 29, and CV 40 were
recommended for cassava farmers in Pampanga. These varieties were proven tobe edible and gave yields of 30-40 tons/ha.
F. Upgrade tourism establishments
The tourism industry is fast becoming a major contributor to Central Luzons
economic development. Specifically, the presence of the Clark International Airport in
Pampanga and the planned expansion of its operations are expected to bring in
more international and domestic visitor arrivals. In 2011, a total of 360,388 air
passengers arrived in the Clark International Airport. Among the airlines that
generated visitor traffic include Cebu Pacific, SeAir, Tiger Airways, and Air Asia.
In 2011, a notable increase of about 189 percent in visitor arrivals was recorded for
the region. This translates to an increase of more than one million visitors over the
previous year. The remarkable increase in statistics generated was due to a more
precise accounting of visitors through surveys generated from accommodation
establishments. Of the about 1.7 million visitor arrivals, 1.5 million or about 91
percent are domestic visitors (see Table 10).
Table 10. Visitor Arrivals, Central Luzon, 2007-2011Year Domestic Foreign Total
2007 282,438 137,199 419,6372008 365,463 165,339 530,8022009 399,224 151,228 550,4522010 447,599 145,767 593,3662011 1,557,746 159,581 1,717,327
Source: DOT III
Promotion of Central Luzon as a tourist destination was spearheaded by the DOT
through representation and participation to international events such as the Honolulu
Festival in February and the International Hot Air Balloon Festival in Clark. Other
activities initiated by the regional office for tourism promotion included the conduct of
the 1stCentral Luzon Health and Wellness Expo in October, and Isang Lahi, Isang
Musika Concert in June.
G. Develop Clark-Subic Regional Tourism Hub
The development of the Clark-Subic Regional Tourism Hub was initiated by the Subic
Clark Alliance for Development Council (SCADC). The charter of the SCADC
provides for the collaboration between Clark and Subic in matters of investment,
promotion and marketing including infrastructure development with the end in view of
transforming the two freeport zones into a major tourist destination and investment
7/27/2019 Central Luzon Regional Development Report 2011
22/38
Central Luzon Regional Development Report
2011
11
hub. The creation of the Special Committee on Tourism under the Regional
Development Council of Central Luzon in 2011 paved the way for the formulation of a
tourism roadmap for both Clark and Subic. The roadmap was prepared in cooperation
with a host of government agencies and private stakeholders in the travel community.
As a result, Clark-Subic hub became a featured cluster in the DOT-crafted National
Tourism Development Plan where a host of tourism road infrastructure projects wereidentified and proposed to the DOT-DPWH Convergence Team for full
implementation within the next five years.
The road projects identified will form part of the work program of DPWH in 2013 and
are meant to provide road links/connectivity between national roads and the tourism
service centers and/or gateways (airports and seaports). The following are the list of
projects included in the program:
1. Widening of the West Circumferential Road, Angeles City
2. Rehabilitation of the Olongapo-San Fernando Road, Olongapo City
3. Widening and concreting of Paseo del Congreso, Malolos City4. Widening of Clark-Angeles-Magalang Road, Angeles City
5. Widening of road leading to DMIA Route 1, Angeles City and City of San
Fernando
6. Road leading to DMIA Route 2, Angeles City
7. Road leading to DMIA Route 3, Angeles City
8. Lourdes Road-Clark Air Base, Bamban, Tarlac
9. East Circumferential Road, Angeles City
II. Globally Competitive, Progressive and Resilient Citizenry
A. Minimize natural disaster casualties and economic losses
Enhanced knowledge on Disaster Risk and Vulnerabilities
For the period of 2011, 41 disaster records compiled covering the period from
September 1998 to December 2011. Capacity building on the use of the Rapid
Earthquake Damage Assessment (REDAS) software was conducted at
Olongapo City.
Strengthened Civil Protection and Community Resilience to Disaster
Strategies on strengthening community resilience to disasters centered on
information dissemination activities and capacity development programs. One of
the major activities done on this matter is the massive information and advocacy
campaigns regarding RA 10121 An Act Strengthening The Philippine Disaster
Risk Reduction And Management System, Providing For The National Disaster
Risk Reduction And Management Framework And Institutionalizing The National
Disaster Risk Reduction And Management Plan. Orientation regarding the
salient features of the law was conducted among 36 Local Disaster Risk
7/27/2019 Central Luzon Regional Development Report 2011
23/38
Central Luzon Regional Development Report
2011
12
Reduction and Management Councils (LDRRMCs) in the region. In addition, 20
summits were also conducted regarding RA 10121. Furthermore, technical
assistance was given to aid in the establishment and operationalization of
LDRRMOs. In 2011, 15 LDRRMOs were assisted. Likewise, 61 LDRRMCs and
20 BDRRMCs were organized. In support to the information campaigns, 6,774
IEC materials were also distributed.
Other trainings conducted included Training on Incident Command System (ICS)
and Earthquake and Fire Drills. For the period of 2011, one (1) Basic
Intermediate Training Course on Incident Command, 67 Earthquake Drills and 21
Fire Drills were conducted within the region. Additional activities included
WASAR Exercise, Communication Exercise (CPX) and 1 Swift Water SAR.
Lastly, 39 Contingency Plans were reviewed and revisited.
Enhanced Coordination, Supervision and Monitoring of Disaster Response,
Recovery and Rehabilitation
In terms of enhancing coordination, supervision and monitoring of disaster
response, recovery, and rehabilitation, six (6) LDRRMCs were oriented on proper
data gathering and consolidation of reports. Likewise, three (3) Early Recovery
and Post-Disaster Needs Assessment were conducted.
On the other hand, in the field of supervision and monitoring of infrastructure
projects in particular, 10 projects implemented by LGUs were validated and
endorsed to the NDRRMC for funding assistance.
Lastly, the region through the Rehabilitation and Recovery Committee of the
Regional Disaster Risk Reduction and Management Council (RDRRMC)prepared a Strategic Action Plan for the Rehabilitation and Recovery of the areas
affected by Typhoons Pedring and Quiel to steer and direct rehabilitation efforts
to priority areas.
B. Improve basic education achievement rates
Early Childhood Care and Development
A slight increase in kindergarten enrolment was observed in SY 2011-2012.
Enrolment rate is expected to increase in the coming school year due to the full
swing implementation of the program for Early Childhood Education. Early Childhood
Education is being implemented by virtue of Executive Order 8980/DepEd Order s.
1997. In 2011, 91 pre-school buildings were turned over to 17 divisions across the
region.
Elementary Division
For the SY 2011-2012, a 5.09 percent increase in elementary participation rate was
recorded for the region. Likewise, cohort survival rate increased by 10.55 percent
7/27/2019 Central Luzon Regional Development Report 2011
24/38
Central Luzon Regional Development Report
2011
13
Fi ure 1. Performance Indicators in Government Elementar Schools
from SY 2010-2011. Furthermore, there is a slight decrease in the transition rate and
retention rate of 0.97 percent and 1.1 percent respectively (see Figure 1). Teacher to
pupil ratio for the region is at 1:37 for SY 2011-2012.
The administration of Regional Achievement Test (RAT) towards the end of the
school year aims to assess the level of knowledge of students and further propose
concrete actions and recommendations to improve the quality of education in
government elementary schools. For SY 2010-2011, results of the RAT showed that
among the five learning areas, English and Science and Health recorded a decrease
from the previous school year by 0.23 and 0.91 percent respectively (see Table 11).
All the other learning areas recorded an increase with Makabayan having the highest
of 4.25 percent.
Table 11. Regional Achievement Test Results, SY 2009-2010 and SY 2010-2011
Learning AreasMPS
SY 2009-2010MPS
SY 2010-2011
English 77.32 77.09Filipino 78.77 79.22Mathematics 77.45 77.64Science and Health 74.67 73.76Makabayan 74.85 79.10OVERALL 76.61 77.36Source: DEPED III
Secondary Division
On the other hand, for government secondary schools, a remarkable increase in
cohort survival rate was realized. A 14.3 percent increase in cohort survival rate was
observed from SY 2010-2011 to SY 2011-2012. Moreover, participation rate and
7/27/2019 Central Luzon Regional Development Report 2011
25/38
Central Luzon Regional Development Report
2011
14
transition rate exhibited slight decreases of 0.28 percent and 1.62 percent
respectively (see Figure 2). Secondary teacher to pupil ratio is at 1:39 for SY 2011-
2012.
Similar to the elementary division, achievement tests are also regularly administered
in government secondary schools. However it can be noticed that the results of the
RAT for fourth year students has been in a declining trend for the past three years
with Filipino having the highest decrease of 11.64 percent from SY 2009-2010 rate
(see Table 12). Likewise, the overall RAT results for Central Luzon decreased from67.26 percent in SY 2009-2010 to SY 2011-2012.
Table 12. Regional Achievement Test Results for Fourth Year Students, SY 2009-2010 and SY 2011-2012
Learning AreasMPS
SY 2009-2010MPS
SY 2011-2012
English 68.23 60.41Science 64.61 56.48Mathematics 62.71 59.02Filipino 71.06 59.42
Araling Panlipunan 69.70 61.62OVERALL 67.26 59.39Source: DEPED III
C. Improve access to health services
Health Operations Programs intended to maintain a healthy citizenry focused on
three key areas: family health, communicable diseases and non-communicable
diseases.
Fi ure 2. Performance Indicators in Government Secondar Schools
7/27/2019 Central Luzon Regional Development Report 2011
26/38
Central Luzon Regional Development Report
2011
15
Family Health
Family health places emphasis on maternal and newborn health. One of the
strategies implemented to reduce maternal deaths is through advocacy of family
planning. Under the family planning program, contraceptives and other family
planning commodities were distributed to 2 provinces, 5 cities, and 37
municipalities. Family Planning Competency-based Trainings were also
conducted to reinforce advocacy of the program. However, there was a decrease
in contraceptive prevalence rate from 30.00 percent in 2010 to 23.96 percent in
2011.
Another advocacy being promoted by the DOH is about Newborn Screening
(NBS). In the advocacy program, selected Barangay Health Workers (BHW) are
trained on the three (3) courses of Newborn Screening Orientation. In 2011,
three (3) batches of BHW Newborn Screening Orientation were conducted in the
Province of Pampanga while NBS cluster meeting of hospital coordinators was
done for the provinces of Aurora, Nueva Ecija, and Tarlac. Meanwhile, infantmortality rate slightly increased for Central Luzon from 4.54 percent in 2010 to
5.90 percent in 2011.
Aside from maternal and newborn health, improved nutrition and intensified
immunization was also a key strategy of the department. Improving nutrition
practices such as breastfeeding and complementary feeding capability building
were implemented for both the private and public sector. In 2011, a total of 134
participants underwent the Infant and Young Child Feeding and Lactation
Management Training. For the Universal Vitamin A Supplementation under the
Garantisadong PambataStrategy, the regional coverage for Central Luzon was
92.65 percent including the provinces of Pampanga, Tarlac, and Zambales andthe cities of Angeles, Cabanatuan, Meycauayan, Olongapo, San Jose, and
Tarlac City.
Furthermore, results of the 2011 Operation Timbang Program of the National
Nutrition Council (NNC) revealed a 4.18 percent prevalence rate of underweight
preschoolers (see Table 13). In terms of provincial ranking, the Province of
Aurora has the highest prevalence rate of 11.25 percent while the Province of
Bulacan has the lowest of 2.17 percent. The Operation Timbang Program of the
NNC is a yearly activity in partnership with the Barangay Nutrition Scholars.
7/27/2019 Central Luzon Regional Development Report 2011
27/38
Central Luzon Regional Development Report
2011
16
Table 13. 2011 Prevalence of Severely Underweight and Underweight Preschoolers in CentralLuzon
% OPTCoverage
Normal % Overweight %Underweight Prevalence
RateSEV % UW % Total
CentralLuzon
93.91 1,388,844 94.58 18,242 1.24 11,683 0.80 49,651 3.38 61,334 4.18
Aurora 100.00 21,976 86.39 600 2.36 719 2.83 2,143 8.42 2,862 11.25Zambales 97.02 62,599 89.52 669 0.96 1,488 2.13 5,169 7.39 6,657 9.52
Tarlac 94.91 147,281 92.87 2,516 1.59 1,774 1.12 7,015 4.42 8,789 5.54
Bataan 88.73 83,333 93.07 1,297 1.45 876 0.98 4,029 4.50 4,905 5.48
NuevaEcija
100.00 174,500 93.78 2,666 1.43 1,566 0.84 7,344 3.95 8,910 4.79
Pampanga 89.78 227,657 94.13 4,282 1.77 1,894 0.78 8,017 3.31 9,911 4.10
Bulacan 94.66 272,014 97.07 2,145 0.77 646 0.23 5,425 1.94 6,071 2.17Source: National Nutrition Council III
For the immunization program, the main activity conducted for the year was
concentrated on the Measles Rubella Supplemental Immunization. This was an
offshoot of the previous years measles outbreak. The activity was conductedfrom April 4 to May 31, 2011 while program review and assessment is on-going
to improve immunization coverage.
In improving access to safe water and sanitary toilet facilities, the region has
achieved positive increase for the latter. The proportion of households with
access to sanitary toilet facilities increased from 81.94 percent in 2010 to 83.35
percent in 2011. Meanwhile, the proportion of households with access to safe
water decreased from 93.54 percent in 2010 to 84.04 percent in 2011.
Communicable and Non-Communicable Diseases
Some of the communicable diseases that are being closely monitored and
controlled in the region are rabies, dengue, malaria, leprosy, and tuberculosis.
Trainings and seminars are continuously conducted to inform and educate the
public on the nature of these diseases, how to avoid them and treatments for
such.
In 2011, the Dengue Prevention and Control Program aimed at reducing
morbidity and mortality from dengue mosquito bites launched the first Asean
Dengue Day Celebration last June 15, 2011 in the City of San Fernando, Tarlac
City, and Municipality of Subic. This activity aims to increase awareness on the
proper prevention and control of the disease. In addition, a regional-basedproject entitled Establishing Dengue Free School Initiatives in Central Luzon
has covered a total of 4,797 classrooms in 279 different schools protecting
193,980 children.
Meanwhile, under the Malaria Control Program, a reduction of 9.82 percent in
morbidity rate from 25.09 percent in 2010 to 15.27 percent in 2011. Furthermore
the total number of confirmed cases in 2010 is 2,575 while in 2011 is at 1,597.
7/27/2019 Central Luzon Regional Development Report 2011
28/38
Central Luzon Regional Development Report
2011
17
This is can be attributed to the conduct of various trainings including Basic
Malaria Microscopy Training for Medtechs and Barangay Health Workers,
training on Basic Malaria Management for Rural Health Midwives and the training
on Indoor Residual Spraying. However, two (2) deaths due to malaria was
recorded in 2011.
For the Leprosy Control Program, the prevalence rate of less than one case per
10,000 population has been sustained. Aside from orientation activities on Basic
Leprosy, efforts has been focused on the provision of quality leprosy services at
all levels.
Another program under Communicable Diseases Cluster is the National
Tuberculosis Control Program. In 2011, the region has achieved a Case
Detection Rate (CDR) of 58 percent and a Cure Rate (CR) of 75 percent.
Meanwhile mortality rate increased from 1.09 percent in 2010 to 3.70 percent in
2011.
The prevention and control of non-communicable diseases on the other hand has
been focused on four (4) lifestyle-related diseases namely: cardiovascular
disease, cancer, chronic obstructive pulmonary disease and diabetes. Selected
health workers in the region were made to undergo a comprehensive training
module on Integrated Non-Communicable Disease Program (INCDP). This is
done to equip and capacitate frontline health workers and other key partners on
the prevention of non-communicable diseases which are commonly associated
with tobacco use, unhealthy diet, and physical inactivity.
D. Support the development of world-oriented higher education institutions
There are a total of 12 State Universities and Colleges in Central Luzon. Total
enrolment for SY 2011-2012 increased by 21.61 percent from SY 2010-2011 levels
while total number of graduates increased by 10.69 percent. On the other hand, total
number of enrollees for Private Higher Education Institutions slightly increased by
6.37 percent from the previous school year while an 11.86 percent decrease in the
total number of graduates was also recorded (see Table 14).
Table 14. Summary of enrollees and graduates for SUCs and Private HEIs in Central
Luzon, SY 2010-2012
2010-2011 2011-2012 % Increase
/DecreaseState Universi ties and Colleges
Total number of enrollees 94,418 114,820 21.61Total number of graduates 15,600 17,268 10.69
Private Higher Education
Institu tion s (HEIs)
Total number of enrollees 114,933 122,249 6.37Total number of graduates 17,586 15,500 -11.86
Source: CHED 3
7/27/2019 Central Luzon Regional Development Report 2011
29/38
Central Luzon Regional Development Report
2011
18
In terms of student population, Bulacan State University remains to be the largest
SUC with 28,273 students in 2011 while the smallest is the Philippine Merchant
Marine Academy. This can be explained by the number of programs offered by each
SUC, the more diverse the programs are, the larger the number of students. For the
Private HEIs per province, Bulacan tops the list with a total of 26,377 students for SY
2011-2012 while Aurora has the least number of students with a total of 2,860students.
Most of the private HEIs experienced decrease in the total number of graduates from
SY 2010-2011 to SY 2011-2012. Among geographical distribution, Angeles City
exhibited the highest decrease in the total number of graduates corresponding to
38.73 percent followed by Olongapo City with 36.82 percent and the Province of
Zambales with 23.90 percent.
Meanwhile, the regions performance in terms of average percent passing in different
licensure exams exhibited decline in 11 out of the 21 disciplines. These included
programs mostly on engineering and education. On the other hand, five (5)
disciplines including Accountancy, Agricultural Engineering, Geodetic Engineering,
Architecture and Guidance Counseling posted increases in average percent passing
over the last three years (see Table 15).
Table 15. Average Percent Passing in Licensure Exams: Central Luzon, 2008-2010
Discipline Average Percent Passing Increase/Decrease2008 2009 2010
1. Accountancy 34.87 39.60 46.912. Agricultural Engineering 27.39 47.9 60.96
3. Agriculture 36.46 26.22 28.644. Architecture 26.37 26.91 41.235. Chemistry 22.41 21.11 22.426. Civil Engineering 40.78 50.55 40.547. Electrical Engineering 41.21 37.27 31.228. Electronics and
Communication Engineering41.29 24.18 27.65
9. Fisheries Technology 66.67 36.36 23.8110. Forestry 46.15 55.56 25.0011. Geodetic Engineering 13.89 62.855 80.7712. Guidance Counseling 50.00 50.00 62.5013. LET-Elementary 47.20 32.62 26.3314. LET-Secondary 34.99 23.95 23.3915. Library Science 29.17 21.74 22.2216. Marine Engineering 90.00 79.31 90.5417. Marine Transportation 63.58 60.44 61.918. Mechanical Engineering 69.40 42.79 54.0219. Midwifery 73.68 92.26 89.1020. Nursing 53.06 47.55 43.5921. Veterinary Medicine 41.03 31.02 26.98
7/27/2019 Central Luzon Regional Development Report 2011
30/38
Central Luzon Regional Development Report
2011
19
Source: CHED
Access to Quality Higher Education
There are 5,294 on-going grantees under the Scholarship, Grants-in-Aid and Loan
programs in the region. Based on the data for the last five years, the success rate of
graduates vs. the total number of grantees are: 84% for the Scholarship program,72% for the Grant-in-Aid program and 73% for the Loan program. For 2011, 133
grantees successfully completed their respective courses which are under the priority
programs of the Commission on Higher Education (CHED).
Three (3) general assemblies and orientations on Revised Implementing Guidelines
for the CHED Student Financial Assistance Programs (STuFAPs) were conducted in
2011. The orientations were done on October 25-27, 2011 on three venues: Lyceum
of Subic Bay, SBMA, Olongapo City, Tarlac State University, Tarlac City and Holy
Angel University, Angeles City.
In continuing pursuit to raise the efficiency and effectiveness levels in the delivery ofservices and financial assistance to student-grantees, monitoring and assessment of
the administration of the programs by the partner HEIs were done. Six (6) HEIs were
visited to determine compliance to pertinent policies and guidelines. Implementation
of other scholarship and loan programs such as STUFAP SAFE-4SR, Student
Assistance Fund for Education (SAFE) and PGMA Help were likewise included in the
monitoring activity.
Collection of Study Now Pay Later Plan (SNPLP) repayments for FY 2011 increased
by 167% from collections made on FY 2010. From last years collection of Php
98,714.26, CHEDROIII was able to collect Php 263,097.61 in 2011.
A total of 2,387 Special Order numbers were issued to 11,469 graduates while 8,081
students/graduates were issued Certification, Authentication and Verification (CAV)
for FY 2011.
National Service Training Program (NSTP) serial numbers issued on 2011 totals
5,407 for graduates of AY 2003-2004 to 2010-2011.
Thirty-seven (37) HEIs applied for a tuition fee increase effective AY 2011-2012. Out
of this number, 28 HEIs were given favorable action or 14.66% of the total HEIs in
the region implemented a tuition fee increase for AY 2011-2012. The rest of the 163HEIs or 83.77% of the total HEIs in the region maintained tuition fee levels. The
average rate of increase is 12.81% with a peso equivalent of Php 50.27. On the
other hand, 49 HEIs implemented increases on other school fees wherein the
average rate of increase is 18.98%.
7/27/2019 Central Luzon Regional Development Report 2011
31/38
Central Luzon Regional Development Report
2011
20
One of the Alternative Learning System available in the region is Expanded Tertiary
Education Equivalency and Accreditation Program (ETEEAP). Six HEIs are currently
offering the said program of the Commission, namely: Angeles University
Foundation, Araullo University, Central Luzon State University, Holy Angel
University, Pampanga Agricultural College and University of the Assumption.
Lastly, twelve (12) faculty members were granted scholarships in masters/doctoral
studies under the CHED Faculty Development Program.
E. High employable technical and vocational skills
The number of Technical Vocational Institutions (TVIs) in the region has remarkably
increased over a relatively short period of time as a response for the increase in
demand for skilled workers in the country and in the global labor market. Technical
and vocational skills training is seen as one of the vehicles in increasing employment
not only in Central Luzon but in the country as a whole.
In 2011, an increase of 144 percent from 2010 levels has been achieved in terms of
enrollees from the four training delivery modes conducted by the TESDA 3: school-
based, center-based, community-based and enterprise-based programs. These
account for 154,213 enrollees for the current year (see Table 16). Of the total,
139,943 or 91 percent graduated. Meanwhile, for the 58,884 graduates who
underwent assessment, 72,012 were given certification which translates to an 84
percent certification rate accomplishment for the region.
Table 16. Accomplishment on Enrolled, Graduated, Assessed, Certified andEmployed (EGACE), Central Luzon
PerformanceIndicator 2011Output Increasefrom 2010Target (%)
Enrolled 154,213 144Graduated 139,943 144Assessed 85,884 81Certified 72,072 -*Employed 74,012 272
Source: TESDA III
The top five qualifications with the highest number of employed graduates include
Shielded Metal Arc Welding National Certificate II (SMAW NC II), Massage Therapy
NC II, Computer Hardware Servicing NC II, Contact Center Services NC II, andCommercial Cooking NC II.
Furthermore, the formulation of the Central Luzon Regional Technical Educations
and Skills Development Plan (CL-RTESDP) 2011-2016 embodies the strategies to
address the challenges confronting TVET to further enhance the relevance of
technical education in the region. More specifically, the strategies focuses on policy
reiteration and implementation, rejuvenation of the Dual Training System, nurturing
7/27/2019 Central Luzon Regional Development Report 2011
32/38
Central Luzon Regional Development Report
2011
21
and expanding partnerships, capability enhancement programs, on-line jobs
facilitation thru TESDA Blue Desk Program, technical assistance to the DepEds K to
12 Program, and promotion of the Ladderized Education, among others.
III. World-Class passenger mobility and cargo distribution network
The Regional Development aimed to attain the Central Luzons vision by adopting
the enhanced W Growth Corridor spatial strategy which emphasized the
importance of an effective urban-rural link as a vehicle for inclusive growth. The
means to advance the gear for economic development in the region is the efficient
access of transport system through roads, airports and seaports.
Central Luzon is a natural gateway linking the National Capital Region (NCR) and
the rest of Northern Luzon via the Cagayan Valley Road and the Manila North Road.
Its proximity to Metro Manila provided opportunities to regions fast development.The Central Luzons infrastructure such as airport, sea ports and road networks
have an advantage to access products and tourist destinations not only in the region
but also in the neighbor regions.
The Central Luzon has a total of 2,269.450 kms. of national roads (Arterial
1026.412 kms, Secondary 1243.038kms) as of June 2012. 92.62% of the total
length are already paved and only 7.38% remaining unpaved (Table 1.1).
Table 17. Inventory of existing national roads, as of June 2012Road Paved Unpaved Total length
(km)(Length in km) (Length in km)
Arterial 942.5410 83.8710 1026.412
Secondary 1,159.4076 83.6304 1243.038
Total 2,101.9486 167.5014 2,269.450
Source:
The efforts on roads and bridges development in the region in 2011 is shown in the
Table 1.2. 92.62%of the national roads and bridges are already permanent and the
rest are functional road and bridges made of gravel and earth.
7/27/2019 Central Luzon Regional Development Report 2011
33/38
Central Luzon Regional Development Report
2011
22
Table 18. Regional summary of length and type of national roads and bridges, as of June2012
ProvinceTotal
length(L.M.)
Roads
Surface type (L.M.)
Concrete Asphalt Gravel Earth
Aurora 254,927.85 162,030.00 - 92,897.86 -Bataan 327,384.00 153,472.00 142,795.00 19,776.00 11,341.00
Bulacan 327,916.00 136,465.00 171,742.00 19,694.00 15.00
NuevaEcija
519,548.00 269,251.60 235,552.40 14,744.00 -
Pampanga 316,475.00 174,809.02 130,938.98 10,727.00 -
Tarlac 334,964.00 156,848.60 170,679.40 7,436.00 -
Zambales 191,732.00 19,232.60 172,499.40 - -
Total 2,272,946.85 1,072,108.82 1,024,207.18 165,274.86 11,356.00
Source: DPWH
Improvement and construction of various DPWH projects were completed in 2011
with 8,993.80 km of roads and 1,662.1 LM of bridges with total cost of about P2.5
billion pesos. Later in 2011, the Central Luzon was declared under state of calamity
due to the series of heavy typhoons that caused serious damages to the
infrastructure in the region. The DPWH has prioritized setting up a system in
identifying road sections and flood control structures vulnerable to inundations,
landslides and damages. To prevent interruption in the intra and inter-regional traffic
within Central Luzon and to ensure preparedness and damage control, about P536
million pesos were allotted for construction of 61 flood control and drainage projects.
A. Improve land transport access from the urban core to the east and west
coasts.
Physical connectivity of the regions urban core to the agricultural and tourist areas
promotes efficiency of production, consumption process and integrate product
markets. The east-west lateral connection also facilitate access to development
opportunities. The main east-west lateral connection is provided by the Subic Clark
Tarlac Expressway (SCTEX) -Sta. Rosa Cabanatuan Bongabon Baler Road.
The Construction of Iba-Tarlac Expressway is still under study at it still lacks the
required traffic demand to implement the project.
North Rail Project. Railway is an important mass transport system that provides fast
and convenient way of moving people and goods, it also accelerate socio-economic
development in Metro Manila and Central Luzon. The Construction of North Rail
Project with length of 31.938 railway line that would connect Caloocan City and
Malolos City, Bulacan. However, the construction was suspended in 2011for further
contract review.
7/27/2019 Central Luzon Regional Development Report 2011
34/38
Central Luzon Regional Development Report
2011
23
Tarlac-Pangasinan-La Union Expressway (TPLEX). TPLEX will provide direct access
from Tarlac interconnecting SCTEX up to Carmen, Rosales, Pangasinan Section 1
reducing the travel time from two hours to 30 minutes. It will also provide easy
access to Cordillera and Central Luzon regions as it will be linked to the North Luzon
and Subic-Clark-Tarlac expressways. The section 1, which runs 48.6 kms. is 71.18
percent finished and will be completed by May 31, 2013. Construction of the othertwo sectionsCarmen-Urdaneta, Pangasinan section, and Pangasinan-Rosario, La
Union sectionare still ongoing. The road is initially planned to have two lanes and
subsequently expanded to four when capacity reaches 25,000 vehicles per day.
There are other major project under the Public-Private partnership (PPP) scheme
that are already scheduled for implementation starting 2014. These projects would
enhance the connectivity of east and west coast, namely:
1) Central Luzon Expressway (CLEx) - Phase I, Tarlac-Cabanatuan. This
project is tentatively scheduled on September 2014 with the construction of
a 4-Lane expressway with a total length of 30.7 kms to decongest traffic at
Daang Maharlika . This will support development of regional urban centers
in Central Luzon and the Pacific Ocean Coastal Areas in order to decrease
over concentration of socio-economic activities in Metro Manila. CLEX forms
an important lateral (east-west) link of overall High Standard Highway (or
Expressway) Network within the 200 km radius from Metro Manila. It
diverges from SCTEx at 2.5 km north of Luisita Interchange and traverses
flat plain of Central Luzon in the east-west direction, then passes
Cabanatuan City and ends at San Jose City in Region III. Phase I ends at
Cabanatuan City and Phase II at San Jose City. The estimated total project
cost is PhP 15.92 Billion.
2) Central Luzon Expressway (CLEx) - Phase II, Cabanatuan-San Jose.
Tentatively scheduled for implementation on September 2015. The project is
an extension of CLEx Phase I and will connect Cabanatuan City to San Jose
City in Nueva Ecija Province. The construction of a 2-Lane expressway with
a total length of 35.7 km. will contribute to the development of the regional
growth centers in Central and Northern Luzon areas and also aims to
decrease overconcentration of transport system and will provide faster
access to Region II. The estimated total project cost is PhP 14.2 Billion.
B. Increased the level of service of strategic roads and north-south arterial links
The strategic connection of the regions road network system, being the transit point
from the urban metropolis and the resourcerich agricultural areas to the north will
provide that needed boost for economic growth.
7/27/2019 Central Luzon Regional Development Report 2011
35/38
Central Luzon Regional Development Report
2011
24
The DPWH has implemented various projects that further develop the north-south
arterial links. In 2011, the DPWH completed the improvement and construction of
111 projects with equivalent of 111.764 Km of roads and highways. There are at
least 18 major on-going projects worth about 2.6 billion pesos. One of the major on-
going projects is the Manila North Road (MNR) Project which cover improvement,
widening and concreting of roads in Tarlac : 1st
district (Paniqui-Moncana Section),2ndDistrict (Tarlac CityGerona Section), 3rdDistrict (Bamban-Capas Section). The
upgrading of MNR would lessen traffic congestion and control flooding in the area.
The Widened MNR plus the effective traffic management implemented by the LGUs
also advance the logistics and transshipment hub agenda of the region.
Cagayan Valley Road (CVR) Widening and Upgrading. The CVR is one main north-
south arterial connection of Central Luzon to the Northern Luzon Regions. The
congestion of CVR is particularly evident in i) Palridel-Baliuag, ii) Cabanatuan City
and, iii) San Jose City Sections. The Arterial Road By-Pass Project (Phase I) is a
part of envisioned upgrading of the inter-urban highway system along the CVR to
ease the traffic congestion along Plaridel-Baliuag. The Plaidel Bypass sectionpasses through four (4) municipalities in Bulacan namely Balagtas, Guiginto,
Palridel and Bustos with total length of 17.05 kms is already 78.98 percent complete
as of last quarter of 2011.
The rehabilitation, construction and upgrading of damaged paved National Roads
such as Roman Expressway; Angeles-Porac-Floridablanca-Dinalupihan Road;
NCR/Bulacan Boundary-Bigte-Ipo Dam Road; Daang Maharlika Road; Gapan-Fort
Magsaysay Road would facilitate accessibility and travel time. DPHW project also
includes the construction of Balagtas and North Food Exchange Interchange, San
Juan, Balagtas Bulacan; upgrading to paved of Baler-Casiguran Road; Apalit-Arayat
Levee, Phase I&II, Pampanga; Rehabilitation/improvement of Pampanga Delta dike;construction of Camiling Bridge and approaches in Tarlac; restoration of Temporary
bridge Approaches A of Bravo Bridge along Palayan City, General Natividad
Road, NE; and asphalt overlay of City of San Fernando GSO Road.
Gapan-San Fernando-Olongapo (GSO) Road Development Project (Phase I&II).
GSO I & II are basically upgrading/widening of roads and bridges with dredging
component which would benefit the City of San Fernando, Municipalities of Bacolor,
Lubao, Sta. Rita, and Guagua in Pampanga and Dinalupihan in Bataan. The phase
I of this project was completed in 2011 that includes the widening of 20 KM existing
2-lanes to 4-lanes road, reconstruction of Sta. Cruz Bridge 1 from 2-lanes to 4-lanePC Girder Bridges with total length of 280 m. GSO II involves the widening of the
existing 11.30 km road of GSO section from Sta. Cruz, Lubao to Layac,
Dinalupihan, Bataan. The Lubao bypass which is originally part of the project was
constructed using the local funds and was opened to traffic in the first quarter of
2011. The project contract has been approved on December 2011 with expected
implementation on February 2012. The completion of these projects would reduce
7/27/2019 Central Luzon Regional Development Report 2011
36/38
Central Luzon Regional Development Report
2011
25
transportation constraints, maintain transportation routes during flooding and ease
traffic congestion thus promote economic development in the region.
C. Integrate the three modes of transportation (land, air, and sea)
Air and sea transport serves an equally important role in passenger and goodsmovement within and outside the region and the country. The integration of the
three transport modes would create the needed synergy to strengthen the regions
drive to become a global gateway between Asia and rest of the world. The central
Luzon has two International Airport namely the Clark International Airport located in
Clarkfield, Pampanga and the Casiguran-Baler International Airport in Aurora. The
Subic Clark Sea Ports is an asset of the region that has developed into a
competitive transshipment hub in the Asia-Pacific Region.
Aurora Pacific Economic Zone (Apeco) Facilities Developement. The construction of
Port and Airport facilities and corporate center buildings within the proclaimed
APECO area magnifies the economic development in Central Luzon. The Casiguran-
Baler International with upgraded runway of 1.5 km provide inter regional air
connection and international access. The Casiguran airport also interlink with the
airport in San Luis town, Cauayan and Palanan, also in airport in Tuguegarao City in
Cagayan. The construction of a 198-meter port for the roll-on, roll-off ferry by the
Philippine Ports Authority is being fast-tracked for full implementation.
IV. Sustainable land-using activities
A. Ensure that mining operations are environment-friendly
Among the seven provinces in Central Luzon, Zambales is considered as the one
with the most number of mining operations. Minerals abundantly located in the
province include chromite, gold, iron, and nickel. Mineral production, administration
and other related activities in the region are being coordinated by the Mines and
Geosciences Bureau (MGB). Under their jurisdiction, services and programs are
centered on Mineral Lands Administration and Geosciences Development Services.
Regular monitoring and auditing of approved mining contracts/permits including
areas within mineral reservations as to compliance to the implementation ofapproved Work Program and Safety, Health, Environment and Social Programs is
conducted by the MGB. In 2011, a total of 40 Work Programs and 18 Safety, Health,
Environment and Social Programs were monitored. In addition, 35
complaints/cases/conflicts were investigated and resolved.
On the other hand, in the issuance of mining rights/contracts/permits, a total of five
(5) permits ranging from Exploration Permit (EP), Industrial Sand and Gravel Permit
7/27/2019 Central Luzon Regional Development Report 2011
37/38
Central Luzon Regional Development Report
2011
26
(ISAGP), and Mineral Processing Permit were issued by the MGB. In ensuring
environmental protection two (2) Environmental Protection and Enhancement
Program (EPEP) were endorsed to the Mines Rehab Fund Committee (MRFC) and
at the same time, two (2) Social Development Management Programs (SDMP) were
approved.
Communication Plan for Minerals Development focused on information campaigns
including activities such as Stakeholders Forum, Radio/TV guestings, and press
releases. Capacity building on mining laws, rules, and regulations through trainings
were also conducted. In 2011 alone, 15 small-scale miners/operators were trained.
Meanwhile, in the identification and mapping of critical areas for geohazard survey
and assessment, there were 15 municipalities and 23 barangays assessed. In the
field of groundwater resources vulnerability assessment, one (1) area was covered
which is the Municipality of Mariveles, Bataan.
V. Socially-Responsible Property Rights
A. Security over property rights
Land Tenure Improvement seeks to secure the tenurial status of the farmers and
farm workers in the lands they till. This is operationalized by the Department of
Agrarian Reform either through land acquisition and distribution and leasehold
operations.
In 2011, there was a 101.67 percent accomplishment or 4,018 hectares was attained
over the target of 3,952 hectares. This has benefited 4,997 farmer-beneficiaries.
Lands distributed for the year comprised of 88 percent or 3,677 hectares privateagricultural lands (PAL), and 12 percent non-PAL. In terms of provincial
performance, Zambales posted the highest percentage of accomplishment of 101.92
percent while the Province of Pampanga distributed the most with 1,028 hectares.
As a result of this, the working scope of CARP for Central Luzon which is registered
at 450,904 hectares until 2014 has been trimmed down to only abo