JAL INTERNATIONAL CAPACITOR BANK DIVISION PROCESS FLOW
Basic Design Assessment &
Approval by Customer?
Receipt of P.O. from Customer by Sales & Proposals
Estimation of Budget for the Project, Getting approval from management
Transfer to Project Execution
Project Execution team assigns Project Engineer who completes the following :
Study of the Contract Interaction with Vendors Preparation of Project Schedule Preparation of Revised Budget Preparation of Basic Design
Documentation
List Corrections & Resubmissions for Base Design.
Approved
Not Approved
Preparation of Bill of Materials Initiate actions for Procurement Submission of Detailed Design
Documentation
Process A
X
JAL INTERNATIONAL CAPACITOR BANK DIVISION PROCESS FLOW
Upon completion of manufacturing, submitting the Test Reports to Customer and offer the equipments for Inspection/ Inspection Waiver to Customer.
Placement of Order for Capacitor Units + Series Reactors + Neutral current Transformers + Surge Arrestors + Structure Materials + Accessories.
Fabrication of Substation Mounting Structure at JAL Workshop –
Process B.
Process B
Obtain Completion Certificate
X
Factory Tests conducted satisfactorily
Repeat the Testing Process
CLOSE
JAL INTERNATIONAL CAPACITOR BANK DIVISION PROCESS FLOW
Capacitor Bank Structural Assembly Fabrication File with complete Approved for
Fabrication documentation All assembly and QA/QC checklists Project Schedule QA/QC Schedule
QA/QC Inspection to check approvals & documentation. Is
everything as per standard?
Determine shortfall, prepare MDR & follow-up for expected delivery date
Prepare Fabrication & Integration plan and commence with Structural fabrication of the SYSTEM
Attach Yellow flag to System Staging Attach Blue flag to System Wiring
Production Engineer to check all material
present?
No
No
Yes
Commence with Structural Assembly Stage,
Attach Orange flag on completion of System Fabrication & Assembly Stage signifying that SYSTEM is ready for QA/QC inspection
Yes
List Non-Conformance in the Log Book.
Rectify Non-Conformance
C
JAL INTERNATIONAL CAPACITOR BANK DIVISION PROCESS FLOW
QA/QC Packing & Shipment Inspection
Passed?
Define Non-conformance,
Attach RED flag to the System Rectify non-conformance.
Deliver the System according to the date provided by the Customer on the Delivery clearance.
C
Arrange for Inspection of the Capacitor Units + Series Reactors + Neutral current Transformers + Surge Arrestors + Structural Assembly in JAL Factory