Page 1: ASPERA-3 Mar. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 1 Monthly Status Report Report due 3/25/01 Schedule statused

ASPERA-3

Mar. 25, 01

Monthly Status Report

ASPERA Monthly Status Report Monthly 3_25/ Page 1

Monthly Status ReportReport due 3/25/01

Schedule statused as of Mar. 16, 2001

Page 2: ASPERA-3 Mar. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 1 Monthly Status Report Report due 3/25/01 Schedule statused

ASPERA-3

Mar. 25, 01

Monthly Status Report

ASPERA Monthly Status Report Monthly 3_25/ Page 2

Project Status Summary

Technical

Jan Feb Mar

Detailed Description: (for items identified as yellow or red)

Programmatic

Jan Feb Mar

Schedule

Jan Feb Mar

Resources

Jan Feb Mar

•We successfully held a Pre-Ship Review for ELS on March 1. The ELS flight unit was delivered to IRF on March 5. DD250s have been received for ELS and IMA.

•Following delivery of the ELS flight unit, it was found that there was an error in the fabrication of the flight, flight spare, and prototype ELS amp board. The fix will be slightly in excess of this years reserves. We are still working the new delivery schedule with the Europeans.

•We successfully held a Software Requirements Review at the ASPERA team meeting. Comments to the requirements document are now being incorporated.

•Latest project photos and videos are available on Aspera-3 web site.

Page 3: ASPERA-3 Mar. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 1 Monthly Status Report Report due 3/25/01 Schedule statused

ASPERA-3

Mar. 25, 01

Monthly Status Report

ASPERA Monthly Status Report Monthly 3_25/ Page 3

Problem and Concern Summary

P=Problem C=Concern R=Resolved

Description Item Month ID'D Dec Jan Feb MarFine alignment of ELS April RFunding for ELS board fix Mar C

Page 4: ASPERA-3 Mar. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 1 Monthly Status Report Report due 3/25/01 Schedule statused

ASPERA-3

Mar. 25, 01

Monthly Status Report

ASPERA Monthly Status Report Monthly 3_25/ Page 4

Accomplishments of the Last Month -ELS

•Completed measurement of the mass properties of the flight unit.

•Finalized characterization testing of the flight spare.

•Completed the ELS Acceptance Data Package and successfully held the ELS Pre-ship Review with JPL QA.

•Delivered ELS flight unit to IRF and held acceptance meeting with IRF project personnel.

•Received the DD250 from NMO for ELS.

•Attended ASPERA-3 team meeting.

Page 5: ASPERA-3 Mar. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 1 Monthly Status Report Report due 3/25/01 Schedule statused

ASPERA-3

Mar. 25, 01

Monthly Status Report

ASPERA Monthly Status Report Monthly 3_25/ Page 5

Accomplishments of the Last Month - IMA

• We received the DD250 for the IMA flight and flight spare delivery. IMA hardware activities are now complete.

Page 6: ASPERA-3 Mar. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 1 Monthly Status Report Report due 3/25/01 Schedule statused

ASPERA-3

Mar. 25, 01

Monthly Status Report

ASPERA Monthly Status Report Monthly 3_25/ Page 6

Accomplishments of the Last Month - Data Reduction Software

• Attended ASPERA-3 Team Meeting March 6-7 in Kiruna, Sweden– Conducted APAF Software Requirements Review– Presented ELS Packet Definitions– Established Additional Contacts with Appropriate ASPERA-3 Team

Members for Information Exchange Relevant to Ground Data System Development

• Continued Working on APAF Software Requirements Specification (SRS)– Software Requirements Review Minutes to be Released by the End of

March, 2001– Began Changes to SRS Based on Review

• ELS Packet Definitions Done for Now– Waiting on More Definitive Feedback from FMI Before Proceeding

• Continued Providing Technical Assistance for EPO Web Information• Continued Defining and Implementing IDFS Web Tools• Held monthly ASPERA-3 Software Status Meeting (March 23, 2001)

Page 7: ASPERA-3 Mar. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 1 Monthly Status Report Report due 3/25/01 Schedule statused

ASPERA-3

Mar. 25, 01

Monthly Status Report

ASPERA Monthly Status Report Monthly 3_25/ Page 7

Planned Activities for the Next Month - ELS

• Get ELS flight unit back from IRF.• Assemble new flight and flight spare amplifier

boards.• Bench test and thermal test new amp boards.• Reassemble flight and flight spare with new

boards.• Vibe and characterize flight unit.

Page 8: ASPERA-3 Mar. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 1 Monthly Status Report Report due 3/25/01 Schedule statused

ASPERA-3

Mar. 25, 01

Monthly Status Report

ASPERA Monthly Status Report Monthly 3_25/ Page 8

Planned Activities for the Next Month - IMA

• None.

Page 9: ASPERA-3 Mar. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 1 Monthly Status Report Report due 3/25/01 Schedule statused

ASPERA-3

Mar. 25, 01

Monthly Status Report

ASPERA Monthly Status Report Monthly 3_25/ Page 9

Planned Activities for the Next Month - Data Reduction Software

Tasks

• Continue Working on APAF Software Requirements Specification (SRS)– Send Version 1.0 to ASPERA-3 Team for Final Review

by April 13, 2001– Begin Sign-off Process in Preparation for Delivery by

May 1, 2001

• Begin Packet Definitions for IMA and NPI• Continue Providing Technical Assistance for EPO

Web Information• Continue Defining and Implementing IDFS Web

Tools

Page 10: ASPERA-3 Mar. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 1 Monthly Status Report Report due 3/25/01 Schedule statused

ASPERA-3

Mar. 25, 01

Monthly Status Report

ASPERA Monthly Status Report Monthly 3_25/ Page 10

Problem and Concern Status

Funding for ELS board fix: Just after delivery of the ELS flight unit, it was found that there was an error in the fabrication of each of the ELS amplifier boards. The via from the anodes to the charge amplifier was not connected. This was a very subtle error that caused varying sensitivity from channel to channel. We have since worked up a new plan to order new boards and to build-up, reassemble and re–verify the ELS flight units. We are currently iterating this plan with IRF and MSSL. While we do not see any technical problems, we are concerned that this problem will exceed this years funding reserves causing us to use a small portion of next years funds.

Page 11: ASPERA-3 Mar. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 1 Monthly Status Report Report due 3/25/01 Schedule statused

ASPERA-3

Mar. 25, 01

Monthly Status Report

ASPERA Monthly Status Report Monthly 3_25/ Page 11

Schedule Summary

ELS: As stated previously, the ELS flight unit was delivered on schedule. We are currently working on the schedule for the re-delivery of ELS. We have held a telcon with IRF and are only waiting on agreement from MSSL. We are proposing delivery to MSSL May 7 for flight calibration. We have already ordered the replacement boards with a 10-day delivery.

Software: Due to the problems with the flight processor, some software activities have been delayed. The overall delivery of the software to support mission operations however continues to be on schedule. We are currently in the process of refining the software schedule adding increased definition.

• The full-up schedule is available on the ASPERA-3 Web site.

Page 12: ASPERA-3 Mar. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 1 Monthly Status Report Report due 3/25/01 Schedule statused

ASPERA-3

Mar. 25, 01

Monthly Status Report

ASPERA Monthly Status Report Monthly 3_25/ Page 12

ASPERA-3 PHASE B/C/D MASTER SCHEDULEJ J A S O N D2003

J J A S O N D J F M A M2002

J J A S O N D J F M A M2001

J J A S O N D J F M A M2000

J J A S O N D J F M A M

MAJOR MILESTONES / REVIEWS

Southwest Research Institute Approval: John Scherrer, Project Mgr.

Orig Approval: 6/25/99 Last Change: 12/15/00 Status As Of: 3/16/01

MA1999

INSTRUMENT DEVELOPMENTELS

Rev: A - ELS STM Delivery Revised to 9/05/00

9/29/00 B - ELS & IMA Deliveries Revised to 12/18/00 & 1/29/01

12/15/00 C – IMA & ELS Deliveries Revised to 1/11 & 2/27/01

ESA LAUNCH

- Electron Spectrometer Imager

MCPs Avail

ELSPDR

Denotes a Change/Slip

MechanicalDesignDetail DesignMechanical FabricationMicrochannel Plates (MCP’s)

MCP ProcurementMCP Characterization

Structural Thermal Model (STM) FabricationSTM Test & Delivery

IRF ELS & IMADelivery to ESA

CDRKEY

MAJOR MILESTONE

SCHEDULED START

SCHEDULED COMPLETION

EARLY START/COMPLETIONLATE START/COMPLETION

RESERVES

CRITICAL PATH

SUMMARY

STM

STM DeliveryElectrical

HVPS DesignHVPS LayoutHVPS FabricationHVPS Testing

HV Power Supply (HVPS)

Anode Board Design ModificationsAnode PWA LayoutAnode FabricationAnode Testing

Anode Assemby

Sensor Integration & TestSensor AssemblySensor Bench TestSensor Testing & Characterization (@ SwRI)

ELS FM/Flt. SpareDelivery to IRF

ELS Calibration (@ IRF) & Delivery to ESA

IMA- Ion Mass Analyzer ImagerIMAPDR

Prototype DevelopmentIMA Definition

CDR

ELS FM/FSDeliv

Prototype DesignPrototype LayoutPrototype Fabrication & Testing

Flt. Model / Flt. Spare DevelopmentFM/FS Design ModificationFM/FS LayoutFM/FS Fabrication & AssemblyMCP Need Date MCP’s

Req’dIMA FM/FS Deliveryto ASPERA / ESA

IMA FM/FSDelivery

FM Sensor Characterization (@ SwRI)IMA Calibration (@ IRF) & Delivery to ESA

Processing SoftwareSoftware Concept & RequirementsVirtual Instrument DesignVirtual Instrument S/W CodingVirtual Instrument S/W TestingS/W Integration w/Sensor Calibration

SwRI IMA &ELS Deliv

to IRF

Instrument SupportEngineering SupportScience Planning & SupportSoftware Development & Support

IMA FM/FS I&T

FP

F

FP

P

P

FP

FP

FSP

FSP

FP

FP

FP

P

F

F

P PROTOTYPE

F FLIGHT

P

Deliver IMA Prototype

F

ASPERAICDR

ASPERAPDR

ELS FM/FS Deliveryto ASPERA / ESA

IMA FM/Flt. SpareDelivery to IRF less MCP’s

9/30/07

P

P

F

MCP’s Returned to IRF for Rework

ELS Anode PWA Rework Pending