Upload
bryan-bradley
View
217
Download
1
Tags:
Embed Size (px)
Citation preview
www.btwholesale.com
Standard Contract Forum 22 Jul 2008
AGENDA
1 Introduction and Notes of Previous Meeting
2 Consult 21
3 International Originated NTS Calls
4 AIT Review
5 SIA 2008 General Contract Review
6 Special Phone Book Charges
7 Review of New and Amended Schedules
8 Annex A Update
9 Any Other Business
Consult21 – Key aspects
•Plan of Record
•Refresh & Ofcom interest
•Pathfinder
•17 on the 17th
•Future plans
•Voice strategy
•WVC as the 21CN new product
Consult21 WG updates
Systems & Processes
Network Structure
Implementation & Migration
Communications
Interconnect & Portfolio
Point to Point
Broadband Line Access
Wo
rkin
g G
rou
p M
ana
gem
ent
STEERING BOARD
Exp
ert
Gro
ups
TDM ProductsInternationally originated 0844/0871
• Access now available.
• Commercial Terms.
• DMA template and New Services manual
updated.
03 Billing
• Automated billing delayed.
• Temporary manual solution in place – being extended to include transit calls.
www.btwholesale.com
Standard Contract Forum 22 July 2008
SIA GENERAL CONTRACT REVIEW 2008
• Review called June 2008• Agreed target for exchanging issues 18 July • 23 issues identified (16 by CPs; 7 by BT); possibly a few more if a further CP confirms its issues for industry rather than bilateral negotiation• Agreed plan on basis of MSA Contract Review Process• BT to prepare issue list; arrange scoping meeting; brief wider industry• Target for completion: end of the year• Parallel exercise for PPC and MSA – look to co-ordinate review activity as appropriate
www.btwholesale.com
Special Phone Book Charges
All current charges raised to date are billed up to the 30th September 2008
New contract being negotiated with industry group
Charges in latest draft contract are:
PB800 National ListingsCharging remains as now – billed for records on OSIS
atend of September for 1 Year until end September
2009 or part year for any new listings entered on OSIS.
Non-National Listings (PB codes and Bold Type)Charge will be raised in line with Phone Book
Production date as an annual charge.
www.btwholesale.com
Special Phone Book Contract
• A Version 12 with industry sub-group for comment
• Plan to issue a final draft by end of July
• Plan to offer Version 1 for signature by mid-August
• Will include a discount rate on BT retail rates
www.btwholesale.com
Schedule 11 Update
Data Quality
Accuracy of data bought from CP is key
Data integrity reports offered but low take-up
An Annual Audit is a fall-back option; however:
Plan to issue Operational contacts data quality reportsFrom September to address the key faults with data:
Commencing with invalid post-codes and telephone numbers
of the wrong length
Seeking support from CPs to ensure the accuracy of their
data is addressed
www.btwholesale.com
Schedule 11 Update
Pricing note to be issued to clarify:
• With GC19 determination, BTWDS will no longer pay for
PB style listings (as they are only relevant to Phone Book &
covered under earlier discussion
• A ported record does not currently attract a payment.
Records ceased & then re-activated (with no amendment to
data) will not attract a payment
Review
• The value to downstream market of Additional Core data
will be reviewed and whether payments to suppliers will be
made (as not GC19 data, BTWDS would only pay for such
listings if there was demand) – the facility to enter such a listing
will remain in place
www.btwholesale.com
Standard Contract Forum 22 Jul 2008
SIA CONTRACT DOCUMENTATION
UPDATED SCHEDULES
Schedule 07 – Reciprocal Non-Geographic Number Portability
Schedule 167 – BT Imported NTS Service Calls and BT Imported 03 UK-wide Number Calls
Schedule 367 – Operator Imported NTS Service Calls and Operator Imported 03 UK-wide Number Calls
Schedule 225 – Emergency Calls
www.btwholesale.com
Standard Contract Forum 22 Jul 2008
Interconnect Circuits – Lead Time Reductions
Interconnect Notification (Ref: 122/08)
• Response to customer SoR• With effect from 18th August 2008• New standard lead times for:
• Capacity dependant on new transmission infrastructure not requiring new duct• New routes
• Timescale applicable will be shown on the agreed ACO
www.btwholesale.com
Standard Contract Forum 22 Jul 2008
New PoC - Duct, Fibre/Splicing & Transmission
New PoC – Fibre/Splicing & Transmission
New PoC - Transmission only
New Route
Route Augment
25 85 110Working Days
New PoC - Lead-time (6 months)
New Route
45
Existing New
6 months
www.btwholesale.com
Standard Contract Forum 22 Jul 2008
SIA Annex A changes
11.1.1 Capacity Provision at a Switch Connection for a Traffic Route passing through a new Point of Connection on an Interconnect Link using PDH or SDH, one of the following as appropriate:a). 85 Working Days following the date of receipt of the relevant Capacity Order where provision of such new Point Of Connection requires new transmission terminating equipment only to be provided; b). 110 Working Days following the date of receipt of the relevant Capacity Order where provision of such new Point Of Connection requires new transmission terminating equipment to be provided and new fibre/cable to be provided and/or fibre splicing;c). 6 months following the date of receipt of the relevant Capacity Order where provision of such new Point Of Connection requires new transmission terminating equipment to be provided, new fibre/cable to be provided and/or fibre splicing and new duct to be provided.
11.1.2 Capacity Provision or Capacity Re-arrangement at a Switch Connection requiring a change of technology from PDH to SDH or SDH to PDH for a new or existing Traffic Route at an existing Point of Connection…….) - amended likewise
www.btwholesale.com
Standard Contract Forum 22 Jul 2008
SIA Annex A changes
11.1.3 New Traffic Routes between Switch Connections through an established Point of Connection using the same technology, including the provision of new Traffic Routes by way of additional Customer Sited Interconnect from a particular Operator site:25 Working Days following the date of receipt of the relevant Capacity Order.
11.1.5 New Traffic Routes over IECs at a Switch Connection using the same technology:25 Working Days following the date of receipt of the relevant Capacity Order.
11.1.7 Capacity Re-arrangements involving the provision of new Traffic Routes using the same technology or a new technology already in service at the relevant Switch Connection:25 Working Days following the date of receipt of the relevant Capacity Order.
11.1.9 Capacity Re-arrangements involving the provision of new Traffic Routes requiring IECs using the same technology or a new technology already in service at the relevant Switch Connection:25 Working Days following the date of receipt of the relevant Capacity Order.
www.btwholesale.com
Standard Contract Forum 22 Jul 2008
Clarification re TDM Traffic Overflow
Text to parallel that developed for NGN CC draft Planning and Operations documentation:
5.4.3 Overflow TrafficTraffic overflowing as part of an agreed routing plan will be deemed to be included in the provisions of paragraphs 5.4.1 and 5.4.2 and shall be considered to be primary traffic. Unless otherwise agreed in writing between the Parties, Traffic overflowing shall be handed over at an alternative Traffic Route provided under this Agreement. For the avoidance of doubt, such overflowing Traffic shall not be subject to TDM to IP conversion before handover via interconnection provided under separate Agreement.
www.btwholesale.com
Standard Contract Forum 22 Jul 2008
Clarification of Responsibilities for 03 UK-wide
Number CallsTRAFFIC TYPE PARTY HAVING THE
RESPONSIBILITIES SET OUT IN PARAGRAPH 5.1.3 OF ANNEX A
Number Translation Services Calls or 03 UK-wide Number Calls (for termination not Transit)
BT to Operator (termination of BT originated Calls and Calls transitting the BT System)
Operator to BT (termination of Operator originated Calls and Calls transitting the Operator System)
Operator
BT
Standard Contract Forum
AIT – Consultation Update
and
MSA – Contract Review Process
Erica Cumming
Senior Commercial Lawyer
22 July 2008
Standard Contract Forum – AIT UpdateAIT Annex E (Artificial Inflation of Traffic) – ConsultationProposals made available to industry 31 January/1 February following long-term industry discussions.
Formal process:1 Feb: Interconnection Notification 077/08 – consultation, 7 responses.
BT responded individually on the matters raised and made amendments where appropriate; amendments discussed with industry group 23 April14 May:Interconnection Notification 121/08 27 May:Emailed documents for signature (to 130+ CPs) – 4 weeks to sign12 June: 1st chasing email17 June: 2nd chasing email24 June: 3rd chasing email
Current Status: Writing individually to 30 CPs, only handful of rejections. As a formal dispute is established, BT proposes to refer to Ofcom
Standard Contract Forum – AIT Update
NOTE: QUERIES ON SUPPLEMENTAL
Queries dealt with on a bilateral basis – has generally led to signature
Concern by some CPs regarding BT’s role in transit disputes – concern that paragraph 4.2 somehow allows BT to “drop out” of a dispute – this is not correct, rather is simply enables the ONO and TNO to speak directly where it is reasonable to do so. Even in these cases BT is still copied into all notices between the parties.
This concern was previously raised by CPs and in April BT extensively redrafted paragraph 4.2 following the consultation exercise to address those concerns. The revised text added to the proposed new Annex E added provision that BT would remain active in transit dispute if it would be unreasonable for it not to be involved.
www.btwholesale.com
Standard Contract Forum – MSA Contract Review 10 Step Process – aim for 23 weeks
Step 1: BTW MSA Contract Review Briefing - officially start process
Step 2: Submissions from CPs - collective or individual
Step 3: Issues Document - BTW collate all issues
Step 4: Classification & Workstream Meeting to classify issues:
Cat A (Minor) – BTW issues its position 2 weeks laterCat B (Major) – BTW issues its position 4 weeks laterCat C (agree-to-disagree) – BTW issues position 1
week later
Step 5: Classification Document – BTW issues after Step 4 meeting
Step 6: Category A, B & C meetings/audios held over 7 week period
Step 7: Consolidated Issues Response – BTW prepares for CPs to consider and respond within 3 weeks
Step 8: Interim Revised MSA issued by BTW
Step 9: Final Meeting to discuss revised MSA
Step 10: Publish Revised MSA
Standard Contract Forum – MSA Contract Review
Guiding Principles•CPs may submit collective or individual initial submissions – collective responses are encouraged for expediency and to lessen duplication of issues;
•Individual responses will be merged with main review wherever possible and/or alternative review timescale may be agreed between BTW and CPs
•Issues will be dealt with collectively on a non-confidential basis – any confidential CP submissions will be dealt with outside of the main contract review process.
•If an issue is agreed by BTW and a simple majority of CPs in attendance (quorum of 4) it may be formally closed.
•BTW will (with assistance of CPs) prepare draft notes of meetings/audios and send to CP representatives for comment within 1 week of circulation, after which BTW will publish. These will be agreed if no comments received with 1 week of publication.
Standard Contract Forum – MSA Contract Review
Variations to Timeline
• Ambitious 23 week timeline but parties may agree to amend if necessary, or may be necessary due to circumstances (i.e., shorten if only a few minor issues or lengthen if expert opinion required, for example)
Document Recording Principles
• Templates for recording issues and giving summary snapshots will be developed at start of each review in consultation with CPs.
Issues document (word) – list issue/sub-issues, relevant clause(s), CPs’ and BTW’s opinions, discussions,
suggested redrafts etc..
In-life Summary document (excel) – updated and circulated regularly, contains basis information on ALL issues forming part of the review, lists party/parties raising issue, last activity and party responsible, next activity etc
Standard Contract Forum – MSA Contract Review
Dispute Resolution
At any stage in the process if there is an impasse, a party may invoke an Escalation, the CMM or ADR:
Escalation - Can escalate an issue provided it has reached Step 6 (i.e., the meetings to negotiate and resolve issues). - Send “Escalation Notice” to other party’s commercial contact requesting escalation and advising who it has been escalated to in the initiating organisation. Acknowledge in 1 week. - 45 days to resolve issue using appropriate senior managers and respond within 45 days of Escalation Notice.
Contract Management Mechanism- See CMM process on BTW website
Alternative Dispute Resolution- May include early neutral evaluation, expert non-binding determination or mediation, as provided by Chartered Institute of Arbitrator’s Independent Resolution Scheme.
Standard Contract Forum
http://www.btwholesale.com/pages/downloads/service_and_support/contractual_information/docs/MSIL/
MSA_Contract_Review_Guideline_Issue1_3July2008.rtf