Neighborhood Meeting No.2 Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid -Day Bus Parking Facility. Contract No . 2013-BT-1 • March 20, 2013. March 20th Presentation. Project Status Update: Traffic Signal Update: Sound Wall Design Concepts - PowerPoint PPT Presentation
Citation preview
Neighborhood Meeting No.2Golden Gate Bridge, Highway and Transportation District’sSan Francisco Mid-Day Bus Parking FacilityContract No. 2013-BT-1 • March 20, 2013
Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility
March 20th Presentation
1. Project Status 2. Update: Traffic Signal3. Update: Sound Wall Design Concepts 4. Update: Modular Units and Security Fencing5. Update: Landscaping Planting Concepts6. Next Steps
Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility
Proposed Site Plan
Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility
Bus Ingress at Perry and 4th Streets
Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility
Bus Egress at Perry and 3rd Streets
Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility
New Traffic Signal and Pavement Delineation at Perry and 3rd Streets
Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility
Existing Midblock Crosswalk Downtown San Francisco
Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility
UpdatedSound Wall Elevations and Sections
Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility
Selected OptionSound Wall Option 1 – “Diagonal Pattern”
Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility
Variation on Selected OptionAlt. Sound Wall Option 2 – “Stripe Pattern”
Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility
Sound Wall Steel Closure Plates – “Diagonal Pattern”
Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility
Sound Wall Steel Closure Plates – “Stripe Pattern”
Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility
Modular Units/Security FencingOriginal Concept
Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility
Modular Units/Security FencingUpdated Concept
Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility
Landscape Planting
Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility
Landscape Planting
Neighborhood Meeting Golden Gate Bridge, Highway and Transportation District’s San Francisco Mid-Day Bus Parking Facility
Project Schedule
• Comments: April 1, 2013• Complete Design Documents – estimated May 2013• Award Construction Contract – estimated July 2013• Complete Construction – estimated January 2014• Start Bus Parking – February 2014
Q&A