Work/Service New plan Revised plan Cancelled plan Deputy Governor- POWER PLANT DEVELOPMENT AND RENEWABLE ENERGY Cost Estimate ( Baht) Bid Issue Bid Opening Letter of Intent 1/2564- SRTP SURAT THANI POWER PLANT BLOCK 1-2 PROJECT - Engineering, Procurement and Construction work (EPC) 30,110,800,000 Aug-21 Jan-22 Jan-23 - Long Term Service Agreement (LTSA) 16,674,000,000 Aug-21 Jan-22 Jan-27 Remark : Please fill in all columns in English. Procurement Plan Year 2564 with the Cost Estimate exceeding 5,000,000 Baht Under Section 7(1) of Government Procurement and Supplies Management Act B.E.2560 No. Bid No. Description Tentative Plan Remark

Work/Service - EGATfprocurement.egat.co.th/documents/supplyandworkservice64/...Work/Service New plan Revised plan Cancelled plan Deputy Governor- POWER PLANT DEVELOPMENT AND RENEWABLE

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

  • Work/Service New plan

    Revised plan

    Cancelled plan

    Deputy Governor- POWER PLANT DEVELOPMENT AND RENEWABLE ENERGYCost Estimate

    ( Baht) Bid Issue Bid Opening Letter of Intent1/2564- SRTP SURAT THANI POWER PLANT BLOCK 1-2 PROJECT

    - Engineering, Procurement and Construction work (EPC) 30,110,800,000 Aug-21 Jan-22 Jan-23- Long Term Service Agreement (LTSA) 16,674,000,000 Aug-21 Jan-22 Jan-27

    Remark : Please fill in all columns in English.

    Procurement Plan Year 2564 with the Cost Estimate exceeding 5,000,000 Baht Under Section 7(1) of Government Procurement and Supplies Management Act B.E.2560

    No. Bid No. Description Tentative Plan Remark

  • Work/ServiceR New plan Revised plan Cancelled plan

    North Bangkok Power Plant Deputy Governor - GenerationCost Estimate

    ( Baht) Bid Issue Bid Opening Letter of Intent1 - งานปรับปรุงระบบควบคุม DCS โรงไฟฟ้าพระนครเหนือชุดที่ 1 49,220,000.00 Jan-21 Feb-21 Mar-21

    Remark : Please fill in all columns in English.

    Meaning

    Bid No. Bid / Enquiry No. EGAT…

    Description Description of Work or Service / Project's name

    Cost Estimate Cost Estimate / Medium Cost (Including VAT)

    Bid Issue Bid Annoucement Issuance Date / Enquiry Issuance Date

    Bid Opening Bid Opening Date / Proposal Submission DateLetter of Intent Date of Issuance of Letter of Intent / P.O.

    Procurement Plan Year 2564 with the Cost Estimate exceeding 5,000,000 Baht Under Section 7(1) of Government Procurement and Supplies Management Act B.E.2560

    No. Bid No. Description Tentative Plan Remark

  • Work/Service New plan Revised plan Cancelled plan

    Deputy Governor - GenerationCost Estimate

    ( Baht) Bid Issue Bid Opening Letter of Intent

    1 -

    Maintenance Service of SR::SPC for South Bangkok Combined Cycle Power Plant unit 4 (SB-C4) and Mae Moh Thermal Power Plant unit 1 (MM-T1)

    2,366,428.05 Jan 2021 Feb 2021 Mar 2021

    Remark : Please fill in all columns in English.

    Meaning

    Bid No. Bid / Enquiry No. EGAT…

    Description Description of Work or Service / Project's name

    Cost Estimate Cost Estimate / Medium Cost (Including VAT)

    Bid Issue Bid Annoucement Issuance Date / Enquiry Issuance Date

    Bid Opening Bid Opening Date / Proposal Submission DateLetter of Intent Date of Issuance of Letter of Intent / P.O.

    Procurement Plan Year 2564 with the Cost Estimate exceeding 5,000,000 Baht Under Section 7(1) of Government Procurement and Supplies Management Act B.E.2560

    No. Bid No. Description Tentative Plan Remark

    P

  • Work/ServiceR New plan Revised plan Cancelled plan

    Deputy Governor - GenerationCost Estimate

    ( Baht) Bid Issue Bid Opening Letter of Intent

    1Software for Performance Monitoring and Loss Diagnostic System (PMDS)

    17,120,000 Jan-20 Feb-20 Mar-20

    Remark : Please fill in all columns in English.

    Meaning

    Bid No. Bid / Enquiry No. EGAT…

    Description Description of Work or Service / Project's name

    Cost Estimate Cost Estimate / Medium Cost (Including VAT)

    Bid Issue Bid Annoucement Issuance Date / Enquiry Issuance Date

    Bid Opening Bid Opening Date / Proposal Submission DateLetter of Intent Date of Issuance of Letter of Intent / P.O.

    Procurement Plan Year 2564 with the Cost Estimate exceeding 5,000,000 Baht Under Section 7(1) of Government Procurement and Supplies Management Act B.E.2560

    No. Bid No. Description Tentative Plan Remark

  • Work/Service New plan Revised plan Cancelled plan

    Deputy PB.Cost Estimate

    ( Baht) Bid Issue Bid Opening Letter of Intent1 N/A Repair Gas Turbine Parts V94.3A 8,063,000 Jan-21 Feb-21 Mar-21

    Remark : Please fill in all columns in English.

    Meaning

    Bid No. Bid / Enquiry No. EGAT…

    Description Description of Work or Service / Project's name

    Cost Estimate Cost Estimate / Medium Cost (Including VAT)

    Bid Issue Bid Annoucement Issuance Date / Enquiry Issuance Date

    Bid Opening Bid Opening Date / Proposal Submission DateLetter of Intent Date of Issuance of Letter of Intent / P.O.

    Procurement Plan Year 2564 with the Cost Estimate exceeding 5,000,000 Baht Under Section 7(1) of Government Procurement and Supplies Management Act B.E.2560

    No. Bid No. Description Tentative Plan Remark

    P

  • Work/Service New plan Revised plan Cancelled plan

    Deputy ….Fuel............

    Bid Issue Bid Opening Letter of Intent

    1 Berth & Jetty, Mooring and Pipielines System 11,890,000,000 *May 2021 *August 2021 *December 2021**-

    (หก.ตก./ชชห.)

    2Floating Storage and Regasification Unit (FSRU)(EGAT Leasing FSRU 10 years)

    22,248,700,000 *May 2021 *August2021 *December 2021*

    Included Operation & Maintenance and Terminal

    Services Cost for 10 years(หก.ตก./ชชห.)

    Meaning

    Bid No. Bid / Enquiry No. EGAT…

    Description Description of Work or Service / Project's name

    Cost Estimate Cost Estimate / Medium Cost (Including VAT)

    Bid Issue Bid Annoucement Issuance Date / Enquiry Issuance Date

    Bid Opening Bid Opening Date / Proposal Submission Date

    Letter of Intent Date of Issuance of Letter of Intent / P.O.

    * Shall be made after:-1. EGAT obtains the Environmental Health Impact Assessment or Environmental Impact Assessment approval from the Office of Natural Resources and Environmental Policy and Planning and National Environment Board.2. EGAT obtains the Project approval from the Government of Thailand, and the approval for Project implementation from the Government’s authority and/or other related entities as required (if any) by Thai laws.

    Procurement Plan Year 2564 with the Cost Estimate exceeding 5,000,000 Baht Under Section 7(1) of Government Procurement and Supplies Management Act B.E.2560

    No. Bid No. DescriptionCost Estimate

    (Baht)Tentative Plan Remark

    P

  • Work/Service New plan Revised plan Cancelled plan

    Deputy Transmission SystemCost Estimate

    ( Baht) Bid Issue Bid Opening Letter of Intent1 CONSULTANCY SERVICES ON TECHNICAL REQUIREMENT 48,920,000 Jan-2021 Mar-2021 Jun-2021 This hiring procurement is

    FOR NEW COMPUTER SYSTEM PROJECT Consultant Hiring for theEGAT CONTROL CENTER SCADA/EMS Computer

    Control System project.

    Remark : Please fill in all columns in English.

    Meaning

    Bid No. Bid / Enquiry No. EGAT…

    Description Description of Work or Service / Project's name

    Cost Estimate Cost Estimate / Medium Cost (Including VAT)

    Bid Issue Bid Annoucement Issuance Date / Enquiry Issuance Date

    Bid Opening Bid Opening Date / Proposal Submission DateLetter of Intent Date of Issuance of Letter of Intent / P.O.

    Procurement Plan Year 2564 with the Cost Estimate exceeding 5,000,000 Baht Under Section 7(1) of Government Procurement and Supplies Management Act B.E.2560

    No. Bid No. Description Tentative Plan Remark

  • Work/Service New plan

    Revised plan

    Cancelled plan

    Deputy รวธ.Cost Estimate

    ( Baht) Bid Issue Bid Opening Letter of Intentอค-บส.Cleaning Service Hongsa Mine Mouth Power Plant 7,000,000.00 Oct-21 Nov-21 Dec-21

    Security Service 60 persons 7,000,000.00 Oct-21 Nov-21 Dec-21

    Hire Passenger Van for Worker 8,200,000.00 Oct-21 Nov-21 Dec-21

    Hire Passenger Van for Shift Operator 5,000,000.00 Oct-21 Nov-21 Dec-21

    Maintenance HVAC (Heat Ventilation Air Conditioning System) 7,800,000.00 Mar-21 Apr-21 May-21

    Maintenance Service 20 person 16,000,000.00 Mar-21 Apr-21 May-21

    Remark : Please fill in all columns in English.

    Meaning

    Bid No. Bid / Enquiry No. EGAT…

    Description Description of Work or Service / Project's name

    Cost Estimate Cost Estimate / Medium Cost (Including VAT)

    Bid Issue Bid Annoucement Issuance Date / Enquiry Issuance Date

    Bid Opening Bid Opening Date / Proposal Submission Date

    Letter of Intent Date of Issuance of Letter of Intent / P.O.

    Procurement Plan Year 2564 with the Cost Estimate exceeding 5,000,000 Baht Under Section 7(1) of Government Procurement and Supplies Management Act B.E.2560

    No. Bid No. Description Tentative Plan Remark

    P

  • Work/Service New plan

    Revised plan

    Cancelled plan

    Deputy Transmission System

    Cost Estimate

    (Baht) Bid Issue Bid Opening Letter of Intent

    1 TIPE-L-03 Supply and Construction of Transmission Line

    500 kV Bang Lamung 2 - Pluak Daeng, DC,

    4x1272 MCM ACSR, 31 km.

    646,300,000.00 - Jan 21 Apr 21 Sep 21

    2 TIEC-L-03 Supply and Construction of Transmission Line

    500 kV Tha Tako - Sam Khok (From Tha Tako

    to KM.92)

    1,353,000,000.00 ∕ Jan 21 Mar 21

    Jul 21

    Nov 21

    3 TIEC-L-11 Supply and Construction of Transmission Line

    500 kV Tha Tako - Sam Khok (From KM.92 to

    Sam Khok)

    1,648,000,000.00 ∕ Jan 21 Mar 21

    Jul 21

    Nov 21

    4 TIPN-L-03 Supply and Construction of Transmission Line

    500 kV Mae Moh 3 - Lamphun 3

    1,915,000,000.00 ∕ Apr 21 Jul 21

    Nov 21

    Mar 22

    5 TIEC-L-12 Supply and Construction of Transmission Line

    for Sectionalizing of 500 kV Sai Noi - Chaeng

    Watthana to Sam Khok Substation

    284,000,000.00 ∕ Apr 21 Jul 21 Dec 21

    6 TS12-L-22 Supply and Construction of Transmission Line

    for Sectionalizing of 230 kV Rangsit - Nava

    Nakhon to Sam Khok Substation

    168,000,000.00 ∕ Apr 21 Jul 21 Dec 21

    7 TIWS-L-04 Supply and Construction of Transmission Line

    500 kV Bang Saphan 2 - Surat Thani 2 (From

    Bang Saphan 2 to KM.155)

    1,821,000,000.00 ∕ May 21 Aug 21

    Dec 21

    Apr 22

    8 TIWS-L-11 Supply and Construction of Transmission Line

    500 kV Bang Saphan 2 - Surat Thani 2 (From

    KM.155 to Surat Thani 2)

    1,386,000,000.00 ∕ May 21 Aug 21

    Dec 21

    Apr 22

    9 TS12-L-24 Supply and Construction of Transmission Line

    230 kV Bang Lamung 2 - Chom Tien

    140,000,000.00 - Jul 21 Oct 21 Mar 22

    10 SEZ1-L-01 Supply and Construction of Transmission Line

    230 kV Tak 2 - Mae Sot

    300,000,000.00 - Aug 21 Nov 21 Apr 22

    11 TIPE-L-04 Supply and Construction of Transmission Lines

    230 kV Rayong 2 - Bang Lamung 2 Junction,

    230 kV Ao Phai - Bo Win, and 230 kV Bang

    Lamung 2 Junction - Bang Lamung 2

    347,000,000.00 - Oct 21 Jan 22 Jun 22

    12 TIPE-L-05 Supply and Construction of Transmission Line

    230 kV Ban Khai Junction - Pluak Daeng

    586,000,000.00 - Nov 21 Feb 22 Jul 22

    13 SEZ2-L-01 Supply and Construction of Transmission Line

    230 kV Chiang Rai - Mae Chan

    214,000,000.00 - Dec 21 Mar 22 Aug 22

    Remark : Please fill in all columns in English.

    Meaning

    Bid No. Bid / Enquiry No. EGAT…

    Description Description of Work or Service / Project's name

    Cost Estimate Cost Estimate / Medium Cost (Including VAT)

    Bid Issue Bid Annoucement Issuance Date / Enquiry Issuance Date

    Bid Opening Bid Opening Date / Proposal Submission Date

    Letter of Intent Date of Issuance of Letter of Intent / P.O.

    Procurement Plan Year 2564 with the Cost Estimate exceeding 5,000,000 Baht

    Under Section 7(1) of Government Procurement and Supplies Management Act B.E.2560

    No. Bid No. DescriptionPre-

    Qualification

    Tentative PlanRemark

  • Work/Service New plan

    Revised plan

    Cancelled plan

    Deputy Transmission System

    Cost Estimate

    (Baht) Bid Issue Bid Opening Letter of Intent

    1 TILS-S-02 Supply and Construction of 500/230 kV

    Songkhla 3 Substation (GIS) and Improvement

    of 230 kV Khlong Ngae Substation

    1,193,000,000.00 - Jan 21 Apr 21

    Aug 21

    Dec 21

    2 TIEC-S-03 and

    TS12-S-20

    Supply and Construction of 500/230/115 kV

    Sam Khok Substation (GIS) and Improvement of

    500 kV Sai Noi (GIS), 500 kV Chaeng Watthana

    (GIS), 230 kV Rangsit and 230 kV Nava Nakhon

    Substations

    2,009,000,000.00 ∕ Mar 21 Jun 21

    Oct 21

    Feb 22

    3 RTS2-S-25 Supply and Construction of 69 kV South

    Bangkok Substation (GIS)

    232,000,000.00 ∕ Feb 21 May 21 Oct 21

    4 TIEC-S-04 Supply and Construction for Expansion of 500

    kV Tha Thako Substation

    352,000,000.00 - May 21 Aug 21 Jan 22

    5 RTS2-S-10(R) Supply and Construction of 115 kV Khon Kaen

    1 Substation (GIS) and Improvement of 115 kV

    Khon kaen 2 Substation

    696,000,000.00 - Jun 21 Sep 21 Feb 22

    6 RTS2-S-09 Supply and Construction of 230/115 kV

    Bhumibol Substation (GIS)

    493,000,000.00 - Jul 21 Oct 21 Mar 22

    7 TIEC-S-05 Supply and Construction of Static Var System

    at 230 kV Chaiyaphum 2 Substation

    1,017,000,000.00 - Oct 21 Jan 22

    Jun 22

    Oct 22

    8 TIPN-S-05 Supply and Construction of 500/230 kV

    Lumphun 3 Substation (GIS) and Expansion of

    500 kV Mae Moh 3 Substation

    1,150,000,000.00 ∕ Nov 21 Feb 22

    Jul 22

    Nov 22

    Remark : Please fill in all columns in English.

    Meaning

    Bid No. Bid / Enquiry No. EGAT…

    Description Description of Work or Service / Project's name

    Cost Estimate Cost Estimate / Medium Cost (Including VAT)

    Bid Issue Bid Annoucement Issuance Date / Enquiry Issuance Date

    Bid Opening Bid Opening Date / Proposal Submission Date

    Letter of Intent Date of Issuance of Letter of Intent / P.O.

    Procurement Plan Year 2564 with the Cost Estimate exceeding 5,000,000 Baht

    Under Section 7(1) of Government Procurement and Supplies Management Act B.E.2560

    No. Bid No. DescriptionPre-

    Qualification

    Tentative PlanRemark