Ashroy Foundation 16, Ahsan Ahmed Road, Khulna Baseline Survey Plan (Tentative) on Disaster Preparedness and Coping Mechanisms in SDBC-Sundarbans Pilot Areas Project title: Sustainable Development and Biodiversity Conservation in Coastal Protection Forests (SDBC-Sundarbans)” a project of GIZ. Summary Plan Activity Week 1 Week 2 Week 3 Week 4 Planning & Training  FGD Stakeholder Selection FGD & KII Conduction Data Compilation Reporting  Specific Plan SL Date Activity Location Time Remarks 01 10/04/13- 11/04/13 Planning & Training Head Office N/A 02 13/04/13 FGD Stakeholder selection and invitation Nalian, Dacope N/A 03 15/04/13 FGD Conduction Nalian, Dacope 09.00-1.00 pm & 3.00 -5.00 pm 04 16/04/13 FGD Conduction Nalian, Dacope 09.00-1.00 pm & 3.00 -5.00 pm 05 17/04/13 KII Conduction Nalian, Dacope 09.00-3.00 pm 06 18/04/13 Data Compilation Dacope 09.00-5.00 pm 07 19/04/13 FGD Stakeholder selection and invitation Soutkatamthola, Shamnagor N/A 08 20/04/13 FGD Conduction Soutkatamthola, Shamnagor 09.00-1.00 pm & 3.00 -5.00 pm 09 21/04/13 FGD Conduction Soutkatamthola, Shamnagor 09.00-1.00 pm & 3.00 -5.00 pm 10 22/04/13 KII Conduction Soutkatamthola, Shamnagor 09.00-3.00 pm 11 23/04/13 Data Compilation Munshigonj, Shamnagor 09.00-5.00 pm 12 24/04/13 FGD Stakeholder selection and invitation Southkhali, Sarankhola N/A

Work Plan of a Survey on CCA

Embed Size (px)

DESCRIPTION

This is a field research/ survey workplan

Citation preview

  • 5/28/2018 Work Plan of a Survey on CCA

    1/3

    Ashroy Foundation16, Ahsan Ahmed Road, Khulna

    Baseline Survey Plan (Tentative)on

    Disaster Preparedness and Coping Mechanisms in SDBC-Sundarbans Pilot Areas

    Project title: Sustainable Development and Biodiversity Conservation in Coastal Protection Forests

    (SDBC-Sundarbans) a project of GIZ.

    Summary Plan

    Activity Week 1 Week 2 Week 3 Week 4

    Planning & Training

    FGD Stakeholder

    Selection

    FGD & KII Conduction

    Data CompilationReporting

    Specific Plan

    SL Date Activity Location Time Remarks

    01 10/04/13-

    11/04/13

    Planning & Training Head Office N/A

    02 13/04/13 FGD Stakeholder selection

    and invitation

    Nalian, Dacope N/A

    03 15/04/13 FGD Conduction Nalian, Dacope 09.00-1.00 pm &

    3.00 -5.00 pm04 16/04/13 FGD Conduction Nalian, Dacope 09.00-1.00 pm &

    3.00 -5.00 pm

    05 17/04/13 KII Conduction Nalian, Dacope 09.00-3.00 pm

    06 18/04/13 Data Compilation Dacope 09.00-5.00 pm

    07 19/04/13 FGD Stakeholder selection

    and invitation

    Soutkatamthola,

    Shamnagor

    N/A

    08 20/04/13 FGD Conduction Soutkatamthola,

    Shamnagor

    09.00-1.00 pm &

    3.00 -5.00 pm

    09 21/04/13 FGD Conduction Soutkatamthola,Shamnagor

    09.00-1.00 pm &3.00 -5.00 pm

    10 22/04/13 KII Conduction Soutkatamthola,

    Shamnagor

    09.00-3.00 pm

    11 23/04/13 Data Compilation Munshigonj,

    Shamnagor

    09.00-5.00 pm

    12 24/04/13 FGD Stakeholder selection

    and invitation

    Southkhali,

    Sarankhola

    N/A

  • 5/28/2018 Work Plan of a Survey on CCA

    2/3

    13 25/04/13 FGD Conduction Southkhali,

    Sarankhola

    09.00-1.00 pm &

    3.00 -5.00 pm

    14 26/04/13 FGD Conduction Southkhali,

    Sarankhola

    09.00-1.00 pm &

    3.00 -5.00 pm

    15 27/04/13 KII Conduction Southkhali,

    Sarankhola

    09.00-3.00 pm

    16 28/04/13 Data Compilation Sarankhola 09.00-5.00 pm

    17 02/05/13 Draft Report submission