5/28/2018 Work Plan of a Survey on CCA
1/3
Ashroy Foundation16, Ahsan Ahmed Road, Khulna
Baseline Survey Plan (Tentative)on
Disaster Preparedness and Coping Mechanisms in SDBC-Sundarbans Pilot Areas
Project title: Sustainable Development and Biodiversity Conservation in Coastal Protection Forests
(SDBC-Sundarbans) a project of GIZ.
Summary Plan
Activity Week 1 Week 2 Week 3 Week 4
Planning & Training
FGD Stakeholder
Selection
FGD & KII Conduction
Data CompilationReporting
Specific Plan
SL Date Activity Location Time Remarks
01 10/04/13-
11/04/13
Planning & Training Head Office N/A
02 13/04/13 FGD Stakeholder selection
and invitation
Nalian, Dacope N/A
03 15/04/13 FGD Conduction Nalian, Dacope 09.00-1.00 pm &
3.00 -5.00 pm04 16/04/13 FGD Conduction Nalian, Dacope 09.00-1.00 pm &
3.00 -5.00 pm
05 17/04/13 KII Conduction Nalian, Dacope 09.00-3.00 pm
06 18/04/13 Data Compilation Dacope 09.00-5.00 pm
07 19/04/13 FGD Stakeholder selection
and invitation
Soutkatamthola,
Shamnagor
N/A
08 20/04/13 FGD Conduction Soutkatamthola,
Shamnagor
09.00-1.00 pm &
3.00 -5.00 pm
09 21/04/13 FGD Conduction Soutkatamthola,Shamnagor
09.00-1.00 pm &3.00 -5.00 pm
10 22/04/13 KII Conduction Soutkatamthola,
Shamnagor
09.00-3.00 pm
11 23/04/13 Data Compilation Munshigonj,
Shamnagor
09.00-5.00 pm
12 24/04/13 FGD Stakeholder selection
and invitation
Southkhali,
Sarankhola
N/A
5/28/2018 Work Plan of a Survey on CCA
2/3
13 25/04/13 FGD Conduction Southkhali,
Sarankhola
09.00-1.00 pm &
3.00 -5.00 pm
14 26/04/13 FGD Conduction Southkhali,
Sarankhola
09.00-1.00 pm &
3.00 -5.00 pm
15 27/04/13 KII Conduction Southkhali,
Sarankhola
09.00-3.00 pm
16 28/04/13 Data Compilation Sarankhola 09.00-5.00 pm
17 02/05/13 Draft Report submission
5/28/2018 Work Plan of a Survey on CCA
3/3