Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
This project has received funding from the European Union’s Horizon 2020 research and innovation
programme under grant agreement No 764452
Deliverable D3.1: Effective large distribution solar PV penetration
validation framework
Work Package 3
iDistributedPV: Solar PV on the Distribution Grid: Smart
Integrated Solutions of Distributed Generation based on Solar
PV, Energy Storage Devices and Active Demand Management Horizon 2020-LCE-2017-RES-CSA
Project Number 764452
June 30, 2018
Consortium members: Fraunhofer-Institute for Solar Energy Systems ISE (Task lead)
Asociación de Empresas de Energías Renovables
Institute of Power Engineering
Enea Operator Sp. z o.o.
ExideTechnologies
Kostal Solar Electric Iberia, S.L.
Deloitte Advisory, S.L.
Institute of Communication and Computer Systems - National Technical University of Athens
Hellenic Electricity Distribution Network Operator S.Α
Lietuvos energetikos institutas
Renerga UAB
Novareckon S.R.L.
Deutsche Energie-Agentur GmbH (dena) – German Energy Agency
Page: 1 Date: 30/06/2018
Contents 1. Assessment methodology and simulation tools ................................................................... 4
1.1. Distributed solar photovoltaic sizing ............................................................................. 5
1.1.1. Prosumer Solution Simulation Tool ....................................................................... 6
1.1.2. Economic Analysis Tool ......................................................................................... 7
1.2. Analysis of the penetration of renewable generation into power networks ............... 9
1.2.1. N-1 contingency analysis ..................................................................................... 10
1.2.2. Voltage analysis ................................................................................................... 12
1.2.3. Frequency analysis .............................................................................................. 12
2. Case studies ......................................................................................................................... 13
2.1. Germany ...................................................................................................................... 13
2.1.1. Solutions .............................................................................................................. 13
2.1.2. Gathered data ..................................................................................................... 14
2.1.3. Grid analysis information .................................................................................... 16
2.1.4. Assessable KPIs .................................................................................................... 17
2.2. Greece ......................................................................................................................... 18
2.2.1. Solutions .............................................................................................................. 18
2.2.2. Gathered data ..................................................................................................... 19
2.2.3. Grid analysis information .................................................................................... 22
2.2.4. Assessable KPIs .................................................................................................... 23
2.3. Lithuania ...................................................................................................................... 24
2.3.1. Solutions .............................................................................................................. 24
2.3.2. Gathered data ..................................................................................................... 25
2.3.3. Grid analysis information .................................................................................... 32
2.3.4. Assessable KPIs .................................................................................................... 32
2.4. Poland .......................................................................................................................... 33
2.4.1. Solutions .............................................................................................................. 33
2.4.2. Gathered data ..................................................................................................... 34
2.4.3. Grid analysis information .................................................................................... 40
2.4.4. Assessable KPIs .................................................................................................... 40
2.5. Spain ............................................................................................................................ 41
Page: 2 Date: 30/06/2018
2.5.1. Solutions .............................................................................................................. 41
2.5.2. Gathered data ..................................................................................................... 42
2.5.3. Grid analysis information .................................................................................... 49
2.5.4. Assessable KPIs .................................................................................................... 52
3. References ........................................................................................................................... 53
Page: 3 Date: 30/06/2018
Index of tables
Table 1. Input data for the country comparison ........................................................................... 8
Table 2. Average yearly consumption for the German Case studies .......................................... 14
Table 3. Electricity tariffs data for the German Case studies ...................................................... 14
Table 4. Electricity market framework data for the German Case studies ................................. 14
Table 5. Panels and inverters data for the German Case studies ............................................... 15
Table 6. Storage systems data for the German Case studies ...................................................... 15
Table 7. Simulation drivers data for the German Case studies ................................................... 15
Table 8. Assessable KPIs for the German Case studies ............................................................... 17
Table 9. Electricity tariffs data for homeowners for the Greek Case studies ............................. 20
Table 10. Electricity tariffs data for companies for the Greek Case studies ............................... 20
Table 11. Electricity tariffs data for municipal buildings for the Greek Case studies ................. 20
Table 13. Electricity market framework data for the Greek Case studies .................................. 21
Table 14. Panels and inverters data for the Greek Case studies ................................................. 21
Table 15. Storage systems data for the Greek Case studies ....................................................... 22
Table 16. Simulation drivers data for the Greek Case studies .................................................... 22
Table 17. Assessable KPIs for the Greek Case studies ................................................................. 23
Table 18. Average yearly consumption for the Lithuanian Case studies .................................... 27
Table 19. Electricity tariffs data for the Lithuanian Case studies ................................................ 28
Table 20. Electricity market framework data for the Lithuanian Case studies ........................... 29
Table 21. Panels and inverters data for the Lithuanian Case studies ......................................... 30
Table 22. Storage systems data for the Lithuanian Case studies ................................................ 31
Table 23. Simulation drivers data for the Lithuanian Case studies ............................................. 31
Table 24. Assessable KPIs for the Lithuanian Case studies ......................................................... 32
Table 25. Average yearly consumption for the Polish Case studies ........................................... 35
Table 26. Electricity tariffs data in 2018 for the Polish Case studies .......................................... 37
Table 27. Electricity market framework data for the Polish Case studies .................................. 38
Table 28. Panels and inverters data for the Polish Case studies ................................................. 38
Table 29. Simulation drivers data for the Polish Case studies .................................................... 39
Table 30. Assessable KPIs for the Polish Case studies ................................................................. 40
Table 31. Average yearly consumption for the Spanish Case studies ......................................... 43
Table 32. Electricity tariffs data for the Spanish Case studies .................................................... 45
Table 33. Electricity market framework data for the Spanish Case studies ............................... 47
Table 34. Panels and inverters data for the Spanish Case studies .............................................. 47
Table 35. Storage systems data for the Spanish Case studies .................................................... 48
Table 36. Simulation drivers data for the Spanish Case studies ................................................. 49
Table 37. Assessable KPIs for the Spanish Case studies .............................................................. 52
Page: 4 Date: 30/06/2018
This document is a deliverable of the project “iDistributedPV: Solar PV on the Distribution Grid:
Smart Integrated Solutions of Distributed Generation based on Solar PV, Energy Storage Devices
and Active Demand Management”. In this document, the methodology employed to the
simulation of the distributed solar PV solutions in the different countries is explained in the first
chapter. Furthermore, in the second chapter, the case study environments are described
including the different characteristics of the countries where they will be developed as well as
the approaches that should be tested in the simulations.
1. Assessment methodology and simulation tools
The most promising distributed solar PV solutions identified in deliverable 2.1. will be evaluated
by analysing technical and economic criteria.
Regarding economic terms, the following aspects will be assessed:
The estimation of the cost of the solutions (investments, operation and maintenance costs,
etc.),
The identification of the economic flows among the different players,
The revenue model,
The analysis of the return of the investment,
The profitability of the projects,
The calculation of the LCOE of the solution,
The comparative evaluation with the current supply solutions.
In technical terms, which will be based on dynamic and static assessments, the following issues
will be analysed:
The reliability and security grid analysis,
The contingency assessment,
The voltage control,
The maximum solar PV capacity that could be integrated in safe conditions,
The impact of the solutions on the frequency control.
Additionally, the feasibility of the solutions will be evaluated according to the key performance
indicators defined in the deliverable 2.2. “Assessment methodology based on Evaluation
Procedures and Indicative Key Performance Indicators”.
Hence, an accurate methodology must be designed to carry out the case studies that will be
developed including the issues addressed below:
The different roles of the players in the case studies,
The operational procedure that should be tested,
The system security and feasibility criteria that should be evaluated,
The necessary information to develop the case studies,
Page: 5 Date: 30/06/2018
The information flows that must be implemented,
The economic flows that must be taken into consideration,
The tools that will support the assessment and the configuration criteria.
1.1. Distributed solar photovoltaic sizing
With the aim of evaluating the proper size of the solution, several simulations will be carried out
analysing different power capacities of the installed PV solution as well as different capacities of
the storage system, if applicable. Apart from the capacities, other technical aspects of both the
PV installation and the storage system may as well be tuned in order to make a deeper analysis.
After the simulations are carried out, these studied capacities will be compared to each other
taking into account a set of KPIs in order to assess which one is the most suitable in the different
solutions.
The five partners involved in the simulations will choose which ones of the proposed solutions
fits better with the regulatory criteria and procedures of their country, and will carry out several
simulations in order to size those installations according to their specific needs. Therefore, the
irradiation of the location, the consumption profile of the consumers, the electricity tariff, the
electricity market price, technical characteristics of the devices as well as their costs among
other parameters will play an important role in the results. The first step to carry out the
simulation will be gather all the data related to the consumers in order to customize the tool
with the real data of each solution. Once the data is recovered, the simulation will be ready to
start.
Figure 1. PV sizing simulation methodology
Data gathering
• Irradiance of the location
• Electricity consumption, share of self-consumption
• Contracted electricity tariff
• Electricity market price and taxes on self-consumption and / or electricity exported
• Technical characteristics of the installed devices: panels, inverters and energy storage
• Data related to maintenance costs, useful life, rate of carbon emissions avoided, etc
Simulation
• Set the main parameters related to the simulation process: number of simulations, decision-making horizon, study horizon, etc
Results analysis
• Analysis of the resulted KPIs and cash flows
• Study and comparison of the different simulated sized
Page: 6 Date: 30/06/2018
1.1.1. Prosumer Solution Simulation Tool
The Prosumer Solution Simulation tool developed by Deloitte performs a technical and
economic analysis about integrating photovoltaic (PV) systems into households, shops, offices,
industries and other type of buildings. Every case is addressed differently, since energy
consumption and the demand profile varies from case to case. Moreover, hourly discrimination
tariffs must comply with the technical aspects of these PV systems and usually depend on the
size of the system.
The tool needs the hourly irradiation profile and the area covered by the panels to calculate the
hourly energy production, along with the location of the simulated installation. The irradiation
profile can be obtained directly from weather stations or from estimations found in the
Photovoltaic Geographical Information System (PVGIS). The former data is more precise;
however, it is not always possible to have free access to data stored in weather stations or they
may be too far from the location studied to deploy the PV panels. If this is the case, PVGIS offers
data precise enough to perform reliable assessments and it is already integrated in the tool to
acquire the radiation data by introducing coordinates.
Solar irradiation data is not constant throughout the simulation. Data from previous years is
studied, and a mean and an uncertainty are obtained. Random profiles are generated and then
the probability of each generated profile to take place is assessed. Therefore, solar irradiation
values slightly differ from one year to another in the simulation.
Technical characteristics of the different devices comprising the PV system are included. For
instance, efficiency of the panels, inverters and batteries; life cycling of batteries; ageing of
panels leading to a reduction in the peak power they exhibit; capacity of the battery; and so on.
This aims to perform simulations as realistic as possible.
The tool evaluates the abovementioned parameters, energy production, demand profile,
characteristics of the system, hourly electricity price etc., and determines whether the best
option is self-consume the electricity generated, store it, sell it or buy energy from the grid to
store it. The last case may occur when the price per kWh is low but it is expected to increase in
the upcoming hours, and there is available capacity in the battery.
Together with the income and savings this system yields, a cost analysis is also conducted. The
complete economic analysis offers the internal rate of return (IRR) of the project, the net present
value (NPV) and the payback period among other KPIs.
Page: 7 Date: 30/06/2018
1.1.2. Economic Analysis Tool
In the iDistributedPV project, case studies in five European countries will be analysed in detail.
However, to make the results comparable to the conditions in other European countries, a rough
overview on the economic viability of several solutions in all European countries will be done.
Due to the fact that a large data set is needed for the economic conditions but the technical
calculations do not need to be detailed, a separate tool was developed by Fraunhofer ISE for
this purpose. The tool is set up in Excel and calculates the following values for each country (see
also the description of the KPIs in Deliverable 2.2):
Degree of self-sufficiency
Payback period
Net present value
Internal rate of return
LCOE
LCOS
Avoided CO2 emissions
Reduced network usage fee
Reduced cost of network losses
Table 1 shows the input data of the tool; filled with the German data as an example. Values in
red are to be filled for each country, while values in black are kept constant among the different
countries. Values in grey are calculated by the tool when the data is entered.
Electricity flow is separated into physical and accounting to be able to present the case of net
metering. In the case of feed-in tariff (FIT), physical and accounting electricity flows are the
same: If 30 % of the electricity flow is consumed directly and 70 % is provided to the grid, then
on the accounting side 30 % is considered as own consumption and 70 % will be rewarded with
FIT. In the case of net metering with 30 % physical own consumption, yet 100 % of the electricity
may be rewarded with the savings of the household electricity price, due to the energy balance
over the billing period (often a year). Thus, for accounting, own consumption will be 100 % with
no grid feed-in. The accounting values are therefore used to calculate the cash flow and
economic parameters. The physical flow is used to calculate the avoided network losses.
Due to the large variety of electricity pricing mechanisms, this simplified tool does not consider
variable electricity prices. The amount of savings calculated in the tool may therefore be lower
than the actual values. The purpose is to give a rough comparison between the situations in
various European countries; detailed analyses need to be done in order to obtain exact values
for the economic viability of the solutions.
Page: 8 Date: 30/06/2018
Table 1. Input data for the country comparison
PV system Capacity 5.8 kWp
Lifetime 20 years
Annual electricity generation 743 kWh/(kWp*a)
Degradation rate 0.25% per year
Battery system Battery Capacity / PV Power ratio 1.00 kWh/kWp Calendar life 10 years
System efficiency (round trip) 90%
Consumption Annual consumption 4,800 kWh/year
electricity flow - accounting
Direct self-consumption 30% Self-consumption from battery 60% Feed-in 10%
electricity flow - physical
Direct self-consumption 30% Self-consumption from battery 60% Feed-in 10%
Investment cost PV system cost 1,300 €/kWp
Battery system 860 €/kWh
Battery replacement 516 €/kWh
CAPEX PV system 7556 €
Battery system 4998 €
replacement Battery replacement cost 2999 €
OPEX Fixed operating costs (depends on CAPEX) 32.50 €/kWp
Insurance (% of CAPEX per year) 0%
Total annual costs 188.90 €/year
Residual Residual value for PV - €
Capital Structure
share Debt 80%
Equity 20%
interest rate (real) Debt 1.50%
Equity 3.00%
WACC real 1.80% Electricity price generation 0.0725 €/kWh
transmission and distribution 0.0657 €/kWh
total without VAT 0.1382 €/kWh
VAT 0.0487 €/kWh
total with VAT (household price el.) 0.3048 €/kWh
Support schemes feed-in tariff 0.12 €/kWh
FiT duration 20 years
Subsidy on PV system 0% of investment
Subsidy on battery system 0% of investment
Environmental CO2 emissions of electricity mix 615 gCO2eq./kWh
Grid losses In transmission and distribution grid 4 %
Page: 9 Date: 30/06/2018
1.2. Analysis of the penetration of renewable generation into power
networks
Electricity networks can be divided into two major subsections: transmission networks and
distribution networks.
The transmission network consists of high to very high voltage power lines designed to transfer
bulk power from major generators to areas of demand; in general, the higher the voltage, the
larger the capacity. Only the largest customers are connected to the transmission network.
Transmission network voltages are typically above 100 kV. The networks are designed to be
extremely robust, so they can continue to fulfil their function even in the event of several
simultaneous network failures. Failure of a single element, such as a transformer or transmission
line, is referred to as an “N-1” event, and transmission systems should be capable of
withstanding any such event. Loading of components and voltage levels should be kept under
the established permissible levels in case of contingences [1].
Transmission consists mainly of overhead lines. Although underground lines offer the advantage
of being less visually intrusive and raising less environmental objections, they incur higher initial
investment costs and have a lower transmission capacity.
Transmission systems are operated by transmission system operators (TSOs). They are actively
managed through power system control centres, also known as dispatch centres. Balancing
power entering and leaving the high voltage network, and reconfiguring the network to cope
with planned and forced outages, is a 24-hour activity.
On the other hand, distribution networks are usually below 100 kV and their purpose is to
distribute power from the transmission network to customers. However, at present, with the
presence of PV and other renewable power plants, more generation is being connected to
distribution networks. Generation connected to distribution networks is known as distributed
generation. Distribution networks contains more customers than transmission networks and
their reliability decreases as voltage levels decrease [1]. As with transmission networks,
distribution networks are operated by distribution system operators (DSOs).
Furthermore, low-voltage network is a part of the electric power distribution that carries electric
energy from distribution transformers to electricity meters of end customers. They are operated
at a low voltage level, which is typically equal to the main voltage of electric appliances.
The integration of solar PV power can result in improvements of the grids or can have negative
impacts on the steady state system operation parameters. The effects/impacts cannot be
generalized for all types of grids across Europe. For effective understanding of the effects before
integration, studies are needed to be carried out for a particular grid in countries in which there
is need to integrate more solar PV system to their power transmission or distribution grids. The
impact of photovoltaics integration has potential to cause [2, 3]:
Page: 10 Date: 30/06/2018
Changes to the feeder voltage level, voltage profile, line loading, power quality of the
system, system losses, power factor, fault currents, system stability (transient and voltage
stability), inertia of the system and mismatch in generation and load.
Changes in operations of voltage-control and regulation devices (frequent operations). This
can in turn, impact on maintenance costs, reliability and life span of the devices.
Change in direction of power flow. There is a very high chance of reverse power flow and
this can impact on protections relays (directional).
The analysis will cover the integration of solar power to an existing grid and study of the impacts
that the integration can cause on an existing grid at different levels of voltage: transmission,
distribution and low voltage. In the integration process, different penetration levels (10%, 30%,
60% and 90%, although these values may be changed) of the solar PV power will be implemented
and analysed, being compared with a baseline scenario. This scenario is set to the current grid
status, or its status in a determined period of time. It involves the modelling of power grids in
power system simulation software without including the solar PV solutions. The loading capacity
and voltage profile/stability of buses at the point of connection will be studied not only in steady
state but also in dynamic state. Solar PV power in combination with different operation
strategies (e.g. peak saving) will be modelled and added to the grid at different penetration
levels as mentioned before. In addition, the possible impacts will be investigated.
It must be pointed out that several software programmes are available to test the stability of
the grid, among others, PSSE, OpenDSS and PowerFactory can be found. The different case
studied will not be developed employing the same software as not all the partners have available
the same licenses. However, the analysis to be tested will comply with the same requirements
in all the case studied, no matter which software will be employed.
1.2.1. N-1 contingency analysis
Contingency means the identified and possible or already occurred faults that grid elements can
undergo, within or outside a transmission system operator's (TSO's) Responsibility Area,
including not only the transmission system elements, but also significant grid users and
distribution network elements if relevant for the transmission system operational security.
Therefore, internal contingency is a contingency within the TSO's responsibility area and
external contingency is a contingency outside the TSO's responsibility area, with an influence
factor higher than the contingency influence threshold.
Regarding chapter 5 of the Network Code on System Operation, which makes reference to the
contingency analysis and handling, each TSO has the following duties [4]:
Each TSO shall establish a contingency list, including the internal and external contingencies
of its observability area, by assessing whether any of those contingencies endangers the
operational security of the TSO’s control area. The contingency list shall include both
Page: 11 Date: 30/06/2018
ordinary contingencies and exceptional contingencies identified by application of the
methodology developed pursuant to Article 75.
Each TSO shall perform contingency analysis in its observability area in order to identify the
contingencies which endanger or may endanger the operational security of its control area
and to identify the remedial actions that may be necessary to address the contingencies,
including mitigation of the impact of exceptional contingencies.
Each TSO shall ensure that potential violations of the operational security limits in its control
area which are identified by the contingency analysis do not endanger the operational
security of its transmission system or of interconnected transmission systems.
Each TSO shall perform contingency analysis based on the forecast of operational data and
on real time operational data from its observability area. The starting point for the
contingency analysis in the N-Simulation shall be the relevant topology of the transmission
system which shall include planned outages in the operational planning phases.
Each TSO shall assess the risks associated with the contingencies after simulating each
contingency from its contingency list and after assessing whether it can maintain its
transmission system within the operational security limits in the (N-1) situation.
When a TSO assesses that the risks associated with a contingency are so significant that it
might not be able to prepare and activate remedial actions in a timely manner to prevent
non-compliance with the (N-1) criterion or that there is a risk of propagation of a disturbance
to the interconnected transmission system, the TSO shall prepare and activate remedial
actions to achieve compliance with the (N-1) criterion as soon as possible.
In case of an (N-1) situation caused by a disturbance, each TSO shall activate a remedial
action in order to ensure that the transmission system is restored to a normal state as soon
as possible and that this (N-1) situation becomes the new N-Situation.
Hence, a contingency analysis is a must in order to assess the level of penetration of solar PV
within the grid and analyse its operational security, as well as identify the remedial actions that
may be necessary to address. The following figure shows the traditional N-1 analysis
methodology.
Page: 12 Date: 30/06/2018
Figure 2. N-1 analysis methodology
Where:
Base case: the power system in its normal steady-state, operation, with all elements in
service that are expected to be in service.
Primary contingency: a loss of one or more system elements that occurs first. A primary
contingency may be a planned or unplanned event.
System adjustments: a set of corrective actions executed automatically by a control system
or manually by a system operator to mitigate the effects of a contingency or strengthen the
system to withstand a possible future contingency. System adjustments may include the
opening or closing of a transmission element; the opening, closing, or redispatch of a
generator; the changing of a phase shifting transformer angle; the opening, closing, or
changing of a switched shunt set point; or the curtailment of load. System adjustments may
include actions that occur every time a certain contingency occurs or actions that occur only
when certain system conditions are met.
1.2.2. Voltage analysis
Voltage levels will be assessed both at transmission and distribution level to analyse the
influence of new solar PV generation on the grid.
1.2.3. Frequency analysis
Dynamic simulations to evaluate the impact of solar PV and battery storage penetration will be
performed at distribution level.
Page: 13 Date: 30/06/2018
2. Case studies
The methodology explained in the previous chapter will be implemented in all the case studies
were the simulations will be developed: Germany, Greece, Lithuania, Poland, and Spain.
Each country will choose the most appropriate solutions to be analysed within its borders.
Therefore, each country must gather the necessary data to develop the different simulations as
a first step to achieve the goal of the work. In the following subchapters, the solutions together
with the necessary data for the distributed solar PV sizing simulation and the analysis of
penetration of renewable generation into power networks simulation are stated. Once the data
is gathered, the inputs of the simulation will be set and the process will be ready to run.
2.1. Germany
2.1.1. Solutions
Homeowner as PV Battery Systems
Many residential battery systems (> 80 000) are installed in Germany already and further growth
of the number of systems is expected. Therefore the impact of a massive rollout on the
electricity system is to be analysed. Also various operational strategies should be analysed to
compare their system impact and to be able to develop recommendations for which operational
strategies to incentive. On the economic side, the impact of grid fees and their possible future
change will be analysed
Controllable load as Homeowner with PV Battery Systems and Electrical Vehicles
When buying an electrical vehicle many customers also think about building a PV system on their
roof to charge the EV battery with green and local electricity. A stationary storage system can
help to further increase the share of local and green electricity for transportation and reduce
gird stress due to high charging powers from the grid. General and seasonal effects are to be
analysed.
Multifamily house
After the introduction of a support scheme for tenant's electricity in Germany, this concept may
be followed by more and more investors. The effect of a massive rollout in Germany cities on
the grid will be examined.
Virtual power plant (VPP) as pool of PV Battery Systems providing Frequency Control Reserve
Pooling of PV home storage systems to virtual power plants for the provision of frequency
control is under discussion in Germany. From an economic and grid point of view this
development will be examined.
Page: 14 Date: 30/06/2018
2.1.2. Gathered data
Radiation profiles
Next to radiation profiles, PV generation measured on the AC side in the flied will be used as
input, depending in the simulation tool used (different for different KPIs).
Demand profiles
Demand profiles will mainly come from Synpro, a tool developed at Fraunhofer ISE to provide
synthetic load profiles. Partly measured profiles will be used.
Table 2. Average yearly consumption for the German Case studies
Parameters Homeowner Controllable
load
Multifamily
house VPP
Average yearly consumption [MWh] ≈ 6 10 20 6* X
Electricity tariffs
In Germany, for the solutions addressed, tariffs are equal for the whole year (no peak and
baseload prices).
Table 3. Electricity tariffs data for the German Case studies
Parameters Homeowner Controllable
load
Multifamily
house VPP
Tariff prices [€/kWh] 0.234 0.234 0.234 0.234
Electricity market framework
Table 4. Electricity market framework data for the German Case studies
Parameters Homeowner Controllable
load
Multifamily
house VPP
Feed in -
Revenues
Electricity market
price [€/MWh]
Feed in premium
[€/MWh]
Feed in tariff
[€/MWh] 122 122 122 / 118.7 122
Self-
consumption
tax
Fixed
term per
year
[€/kW]
Peak 2.716
Shoulder
Off-peak
Peak
Page: 15 Date: 30/06/2018
Usage
charge
[€/kWh]
Shoulder
Off-peak
Tax on energy
exported to
the grid
Toll [€/MWh]
Tax on benefits [%]
Panels and inverters
Table 5. Panels and inverters data for the German Case studies
Parameters Homeowner Controllable
load
Multifamily
house VPP
Total efficiency [%] 15 15 15 15
PV panel size [m2] 1.7 1.7 1.7 1.7
Nominal power per panel [W] 250 250 250 250
PV degradation rate per year [%] 0.5 0.5 0.5 0.5
Installed power capacity [kW] 2-10 2-10 5-40 2-10 * X
Price Fixed price [€]
Estimated price [€/kW] 1500 1500 1500 1500
Storage systems
Table 6. Storage systems data for the German Case studies
Parameters Homeowner Controllable
load
Multifamily
house VPP
Technology [-] Lithium ion Lithium ion Lithium ion Lithium ion
Cycle efficiency [%] 90 90 90 90
Charge / discharge rate [%] 50 50 50 100
Capacity [kWh] 0-12 0-12 0-25 0-125
Depth of discharge [%] 80 80 80 80
Life cycles [-] 8000 8000 8000 8000
Degradation rate per year [%] 0.5 0.5 0.5 0.5
Price Fixed price [€]
Estimated price [€/kWh] 1060 1060 1060 1060
Simulation drivers
Table 7. Simulation drivers data for the German Case studies
Parameters Homeowner Controllable
load
Multifamily
house VPP
Operational parameters
Panels and
inverters 2 2 2 2
Page: 16 Date: 30/06/2018
Annual
maintenance
costs [%]
Storage system 0 0 0 0
Depreciation
[useful years]
Panels and
inverters 20 20 20 20
Storage system 10 10 10 10
Financial and tax rates
Corporate tax rate [%] 0 0 0 0
WACC [%] 1.8 1.8 1.8 1.8
Inflation rate [%] 0 0 0 0
Simulation parameters
Study horizon [years] 20 20 20 20
Nº of simulations [-] 1000 1000 1000 1000
Decision-making horizon [hours] 23 23 23 23
Rate of avoided carbon dioxide
emissions [kg/kWh] 0.615 0. 615 0. 615 0. 615
2.1.3. Grid analysis information
In order to investigate possible future grid loads, in the iDistributedPV project a probabilistic
load-flow analysis is carried out for a synthetic MV distribution grid including underlying LV
distribution grids, see Figure 3. All in all the investigated grid contains 1074 nodes and 1012
lines. 1027 are located in the LV level 46 in medium voltage and one in high voltage level (HV).
Figure 3. 20 kV medium voltage distribution grid with 36 underlying low voltage grids
Page: 17 Date: 30/06/2018
The probabilistic load-flow calculations are carried out for different scenarios concerning RES
penetration and changes in operation of storage technologies. For each scenario several
combinations are calculated in which size and position of RES is changed as well as the places of
EV and heat pumps and batteries.
Since voltage variations of the HV grid are not taken into account for this simulations, 2 % voltage
deviation in each direction are reserved for it. Consequently in this investigations voltage band
violations are defined as a deviation of 8 % percent from nominal voltage of the respectively
voltage level. An asset is thermally overloaded when the actual current exceeds its rated current.
Due to computational restrictions it is not possible to store all line usage rates and voltage
magnitudes. Hence for characterizing general grid behaviour characteristic nodes and lines were
defined. Their usage rates and voltage magnitudes were stored over time. Additionally thermal
overloads or voltage band violations were stored. In order to evaluate the necessity of additional
effort in inverter technology, inverter operating points are stored.
2.1.4. Assessable KPIs
With probabilistic load flow simulation of the distribution grid it is possible to calculate for all
scenarios nodal voltages and usage of grid elements. Every scenario is defined by a certain
amount of installed renewables. For every penetration the KPI marked below will be evaluated.
Table 8. Assessable KPIs for the German Case studies
Key Information Indicators Homeowner Controllable
load
Multifamily
house
Virtual power
plant
Economic – on site
Reduced network usage fee
Net Present Value (NPV)
Internal Rate of Return (IRR)
Paybak time
Reduced exposure to volatility of electricity
prices
Levelized Cost of Electricity (LCOE)
Technical – on site
Degree of self-sufficiency
Reduction peak demand ratio
Technical – grid
Energy exchange with the grid
Hosting capacity of solar PV
Reduction in solar PV production cut-off due to
congestion
Voltage stability Vmax
Voltage stability Vmin
Reduction of over voltage in the grid
Reduction of under voltage in the grid
Increase frequency quality performance
Page: 18 Date: 30/06/2018
Time of a certain frequency variation
Average outage duration for each customer
served (SAID)
Average number of interruptions in the supply
of a customer (SAIFI)
Increased efficiency in preventive control and
emergency control
Increased demand side participation
Actual availability of network capacity
Regulative
Reduction in time to connect new user
Increase in coordinated operation between
TSOs and DSOs
Environmental
Quantified reduction of carbon emissions
2.2. Greece
2.2.1. Solutions
Three different solutions will be tested in Greece and the main reason for choosing them is that
they are typical type of consumers.
Homeowner
For the analysis of this solution a typical single-family detached house has been chosen. The
household is located at the Meltemi summer camp, which is an area of 200 houses in Rafina, a
province of Athens.
One of the reasons for choosing this solution was to evaluate the impact of large scale PV
penetration of PV in the frame of the new regulations about net-metering scheme. Furthermore,
the availability of the energy consumption data of this household makes it an ideal solution for
simulation purposes.
Company as investor
Typical type of consumer in Greece.
HEDNO (Hellenic Electricity Distribution Network Operator) is one of the project partners and
will provide the necessary data to ICCS in order to perform the simulations. HEDNO’s
department of information and telecommunications has been chosen for this solution because
of the availability of electric consumption data. The building is located at the area of Mesogeia,
Athens.
Page: 19 Date: 30/06/2018
Municipal building
The town hall of Rafina, a province of Athens as already mentioned, will be analysed for this
solution. It’s a typical municipal building in Greece, which mainly consumes electric power in the
daytime. Consumption pattern from this type of building is quite interesting also due to the
inactive hours of the weekend.
Another reason for choosing this solution is that municipal buildings will play a major role in the
localized energy policy that the new law about Energy Communities in Greece is trying to
establish.
2.2.2. Gathered data
Radiation profiles
The radiation data that will be used were obtained from the solar radiation database CMSAF-
PVGIS and they contain data in an hourly resolution from the year 2007 to the year 2016. The
irradiation of year 2016 is presented as an example IN Figure 4.
Figure 4 Yearly irradiance profile of Meltemi, Athens, Greece (2016)
Demand profiles
For the homeowner solution, data from three different households were obtained. The time
period that these houses were monitored was from 11 July 2017 until 1 June 2018. The houses
that were chosen for the simulations are occupied on a year-round basis.
For the other two solutions the available data is for a much longer period of time. The energy
consumption of the HEDNO’s building has been meausured from 29 July 2014 until 31 December
2017 and the Town Hall of Rafina from September 2015 until April 2018.
Page: 20 Date: 30/06/2018
Electricity tariffs
There are five different electricity suppliers in Greece, PPC S.A., Elpedison, Protergia, NRG,
Voltera. Each of these suppliers has different electricity tariffs based on the energy consumption
of the customer. Electricity tariffs also vary by type of customer by residential, commercial, and
municipal building connections. The three tables below shows the tariff prices for each of the
three solutions that have been chosen.
Table 9. Electricity tariffs data for homeowners for the Greek Case studies
Parameters Homeowner
Tariff prices
[€/kWh]
Upper price
[€cent/kWh]
PPC : Energy consumption in a 4
months period is 0 – 2000 kWh 9.460
PPC : Energy consumption in a 4
months period is > 2000 kWh
10,252
(for every kWh that
exceeds 2000kW)
Lower price
[€cent/kWh] Elpedison 8.950
Night tariff
[€cent/kWh] PPC, Protergia, Elpedison 6.610
Table 10. Electricity tariffs data for companies for the Greek Case studies
Parameters
Time zone Energy fee (€/kWh) Fixed rate (€/kW)
8:00-22:00 during the whole year 0.11346
0.053 22:00-8:00 during the whole year 0.06610
Table 11. Electricity tariffs data for municipal buildings for the Greek Case studies
Parameters
Time zone Power fee
(€/kW/month) Energy fee
(€/kWh) Fixed rate
The whole year 1.1 0.08259 0.53
Page: 21 Date: 30/06/2018
Electricity market framework
Table 12. Electricity market framework data for the Greek Case studies
Parameters Homeowner Company as
investor
Municipal
building
Feed in -
Revenues
Electricity market price
[€/MWh]
Feed in premium
[€/MWh]
Feed in tariff [€/MWh]
Self-
consumption
tax There aren’t taxes and levies for own-consumption or for the energy
exported to the grid Tax on energy
exported to the
grid
Panels and inverters
In the next categories, mean values for the panels, the inverters and the storage systems that
are in the market and are representative in each country will be used in order to achieve some
typical results during the simulation process.
Table 13. Panels and inverters data for the Greek Case studies
Parameters Homeowner Contractor
concept
Municipal
building
Total efficiency [%] 15 15 15
PV panel size [m2] 1.7 1.7 1.7
Nominal power per panel [W] 250 250 250
PV degradation rate per year [%] 0.5 0.5 0.5
Installed power capacity [kW] 2-6 10-60 10-40
Price
Fixed price [€]
Estimated price [€/kW] 1000 1000 1000
Storage systems
In the next categories, mean values for the panels, the inverters and the storage systems that
are in the market and are representative in each country will be used in order to achieve some
typical results during the simulation process.
Page: 22 Date: 30/06/2018
Table 14. Storage systems data for the Greek Case studies
Parameters Homeowner Contractor
concept
Municipal
building
Technology [-] Lithium ion Lithium ion Lithium ion
Cycle efficiency [%] 90 90 90
Charge / discharge rate [%] 60 60 60
Capacity [kWh] 0-3 10.5-30 5-25
Depth of discharge [%] 80 80 80
Life cycles [-] 8000 8000 8000
Degradation rate per year [%] 0.5 0.5 0.5
Price Fixed price [€]
Estimated price [€/kWh] 600 600 600
Simulation drivers
Table 15. Simulation drivers data for the Greek Case studies
Parameters Homeowner Contractor
concept
Municipal
building
Operational parameters
Annual
maintenance
costs [%]
Panels and inverters 2 1 1
Storage system 2 1 1
Depreciation
[useful years]
Panels and inverters 20 20 20
Storage system 10 10 10
Financial and tax rates
Corporate tax rate [%] 0 25 25
WACC [%] 6.5 6.5 6.5
Inflation rate [%] 0 0 0
Simulation parameters
Study horizon [years] 20 20 20
Nº of simulations [-] 1000 1000 1000
Decision-making horizon [hours] 23 23 23
Rate of avoided carbon dioxide
emissions [kg/kWh] 0.36 0.36 0.36
2.2.3. Grid analysis information
The simulation process will be carried out in low voltage and medium voltage level. The tool that
will be used in order to develop these simulations is the PowerFactory software. HEDNO will
Page: 23 Date: 30/06/2018
provide the necessary grid information, while ICCS will analyse these data and perform the
simulations on PowerFactory.
The low voltage grid that will be simulated is the summer camp Meltemi, an area of 200 houses
at the municipality of Rafina, a province of Athens. Some of the houses are not yearly occupied
and are used only as summer residences and this will give us the opportunity to test different
options of PV penetration.
For the medium voltage analysis, the distribution grid of Mesogeia in Athens will be simulated.
One medium voltage line which ends at the low voltage grid mentioned above, a second one
which includes the Town Hall of Rafina, one of the solutions that will be also analysed and
another one which includes the HEDNO’s building, which has also already been mentioned will
be simulated.
2.2.4. Assessable KPIs
Table 16. Assessable KPIs for the Greek Case studies
Key Information Indicators Homeowner Company as
investor
Municipal
building
Economic – on site
Reduced network usage fee
Net Present Value (NPV)
Internal Rate of Return (IRR)
Paybak time
Reduced exposure to volatility of electricity
prices
Levelized Cost of Electricity (LCOE)
Technical – on site
Degree of self-sufficiency
Reduction peak demand ratio
Technical – grid
Energy exchange with the grid
Hosting capacity of solar PV
Reduction in solar PV production cut-off due to
congestion
Voltage stability Vmax
Voltage stability Vmin
Reduction of over voltage in the grid
Reduction of under voltage in the grid
Increase frequency quality performance
Time of a certain frequency variation
Average outage duration for each customer
served (SAID)
Average number of interruptions in the supply
of a customer (SAIFI)
Increased efficiency in preventive control and
emergency control
Page: 24 Date: 30/06/2018
Increased demand side participation
Actual availability of network capacity
Regulative
Reduction in time to connect new user
Increase in coordinated operation between
TSOs and DSOs
Environmental
Quantified reduction of carbon emissions
2.3. Lithuania
2.3.1. Solutions
When deciding which solutions from those given in deliverable 2.1 should be tested in Lithuania,
several factors were considered in order to analyse the most promising ones to be implemented
in the country. Among the different reasons to decide, regulative criteria, data availability,
specific characteristics of the demand profile, etc. were some of the main reasons. Special
attention is paid to the new initiative described in new Energy strategy (approved by Parliament;
2018). It provides some new initiatives:
1) To have 34 000 energy prosumers in 2020;
2) 30 % of consumers will be active and participate in the energy market in 2030;
3) 50 % of consumers will be active and participate in the energy market in 2050.
Homeowner
A single-family house with solar PV and storage system, which is a popular business model in
Europe, will be analysed. PV electricity will be consumed when possible and excess electricity
will be either stored for later use or exported to the public grid. Two storage options will be
analysed: batteries and use of net metering scheme available today in Lithuania. Therefore,
savings will be generated by the avoidance of purchasing electricity from a supplier and possibly
by selling the excess electricity. Despite of the fact that limited information from family-
members houses located in Lithuania were available now it is expected that during
implementation new energy strategy homeowners will become main players in prosumers
market.
Company as investor
The case of the hotel “Grand SPA Lietuva“, which is located in Druskininkai city will be analysed.
The case of the hotel The hotel belongs (same as project participant UAB Renerga) to the same
UAB koncernas ACHEMOS GRUPĖ, which is one of the largest national capital business groups in
Lithuania. It seeks to become green energy hotel in near future. Data on electricity consumption
Page: 25 Date: 30/06/2018
at hotel is available and possibility to invest in PV and storage solution or use net metering
scheme is under consideration by hotel owners
Contractor concept
Lithuanian Energy Institute, Lithuania, will be analysed. This solution is quite widespread in
Europe especially among companies that are not interested in owning physical assets. This fact,
together with the availability of real data for the simulation, makes this solution highly
interesting.
The consumption profile shows also some features that can play an attractive role in electricity
market as it has almost no consumption during the weekends, the use of batteries and net
metering scheme will be analysed.
Controllable load
When buying an electrical vehicle many customers also think about building a PV system on their
roof to charge the EV battery with green and local electricity. A stationary storage system can
help to further increase the share of local and green electricity for transportation and reduce
gird stress due to high charging powers from the grid. General and seasonal effects are to be
analysed. Fast charging station for electrical vehicles near hotel “Druskininkai” will be analysed.
The station was introduced into market at September 22th, 2017. It is produced by DELTA
Electronics. The power of the station is up to 120 kW, which allows fast charging for up to 4
vehicles at the time.
2.3.2. Gathered data
Examples of the data gathered for the simulations are shown in the tables below. It must be
mentioned that installation of electricity consumption monitoring in an hourly resolution for the
non-industry users were actively started in the middle of 2017. Data for Homeowner and
Controllable load are still in gathering stage in order to have better statistics for precise
modelling calculations.
Radiation profiles
Different solutions which are in two cities of Lithuania will be studied during project
implementation. Objects for Homeowner and contractor concepts will be in Kaunas, Lithuania
and objects for Company as investor and Controllable load will be located in international all-
year-round therapeutic resort of mineral water, mud and climate - Druskininkai, Lithuania. The
radiation profiles were obtained from the solar radiation database CMSAF-PVGIS.
Page: 26 Date: 30/06/2018
Figure 5. Yearly irradiance of Kaunas and Druskininkai, Lithuania.
Demand profiles
The consumption profiles were obtained from the monitoring over a year in an hourly
resolution. The monitoring system for Contractor concept which will be implemented in
Lithuanian Energy Institute starts from 18/05/2017 than monitoring over a year in an hourly
resolution was installed. For the Company as investor concept data starts from 01/01/2007 till
12/30/2017.
Page: 27 Date: 30/06/2018
Table 17. Average yearly consumption for the Lithuanian Case studies
Parameters Homeowner Company as
investor
Contractor
concept
Controllable
load
Average yearly consumption
[MWh] 6 551 892 4.2
Figure 6. Company as investor yearly consumption profile
Figure 7. Contractor concept yearly consumption profile
Page: 28 Date: 30/06/2018
Figure 8. Controllable load concept consumption profile
Electricity tariffs
The price of the electricity that each solution demands will depend on the electricity tariff that
each consumer has contracted with electricity retailer. In cases of Homeowner, the consumers
pay fixed tariff price. In cases of Company as investor and Controllable load the consumers pay
fixed tariff price + additional tax on the tariff which is 0.7502 €/kW/month (One-time zone
energy component). In case of Contractor concept, consumer has tariff which is split in three
main subcategories: peak, shoulder and off peak (which is additionally split in two parts: off
peak, which is between 23:00-7:00 hours and off peak, which is calculated for Sunday, Saturday
and National Weekends between 0-24:00; in order to simplify calculation we selected higher
tariff price for off peak calculations – 0.0664 €/kWh). There is additional tax on the tariff for
Contractor concept consumer which is 0.9559 €/kW/month.
Table 18. Electricity tariffs data for the Lithuanian Case studies
Parameters Homeowner
Company
as
investor
Contractor
concept
Controllable
load
Tariff
prices
[€/kWh]
Summer
Peak 0.113 0.1025 0.09004 0.1025
Shoulder 0.113 0.1025 0.0974 0.1025
Off-peak 0.113 0.1025 0.0664 0.1025
Winter
Peak 0.113 0.1025 0.09004 0.1025
Shoulder 0.113 0.1025 0.0974 0.1025
Off-peak 0.113 0.1025 0.0664 0.1025
Page: 29 Date: 30/06/2018
Tariff
periods [h]
Summer
Peak 0-24 0-24
8-11 (Oct-Mar)
18-20 (Apr; Sep)
9-12 (May-Aug)
0-24
Shoulder 0-24 0-24 others 0-24
Off-peak 0-24 0-24 23-7 0-24
Winter
Peak 0-24 0-24
8-11 (Oct-Mar)
18-20 (Apr; Sep)
9-12 (May-Aug)
0-24
Shoulder 0-24 0-24 others 0-24
Off-peak 0-24 0-24 23-7 0-24
Electricity market framework
According new Energy strategy (approved by Parliament; 2018), net metering scheme will be
used for energy storage which will be produced by renewables and is expected to bring around
200 MW of PV power online by 2020. Prior to the approval of new Energy strategy, only public
institutions were entitled to install PV systems between 10 and 100 kW and now it is additionally
expanding for the businesses and farmers. Residential PV installations could be up to 10 kW for
homeowners. Several algorithms for energy storage were proposed by national distribution
company ESO (AB Energijos Skirstymo Operatorius). The main of them are related to 0.4 kV grid:
fixed payment for energy storage – 0.03876 €/kWh or prosumer could leave 38 % of produced
electricity to ESO and use 68 % for own use free of charge.
As additional support scheme, The Environmental Project Management Agency under the
Ministry of Environment of the Republic of Lithuania announced call for proposals for residential
PV installations which could compensate up to 336 €/kW installed.
Table 19. Electricity market framework data for the Lithuanian Case studies
Parameters Homeowner Company
as investor
Contractor
concept
Controllable
load
Feed in -
Revenues
Electricity market
price [€/MWh]
Feed in premium
[€/MWh]
Feed in tariff
[€/MWh]
Self-
consumption
tax
Electricity storage
charge [€/kWh] 0.03876 0.03876 0.03876 0.03876
Toll [€/MWh]
Page: 30 Date: 30/06/2018
Tax on energy
exported to
the grid
Tax on benefits [%]
Panels and inverters
Polycrystalline PV modules will be employed in the different solutions. This technology has a
major cost than others but also its efficiency is higher, standing between 17 and 18%. However,
the presence of inverters will decrease the total efficiency of the installation to 15%.
The sizing assessment of the solution is one of the main aims of this study. Therefore, several
installed capacities will be simulated in order to see which one should be implemented or
suggested.
Table 20. Panels and inverters data for the Lithuanian Case studies
Parameters Homeowner Company
as investor
Contractor
concept
Controllable
load
Total efficiency [%] 15 15 15 15
PV panel size [m2] 1.7 1.7 1.7 1.7
Nominal power per panel [W] 270 270 270 270
PV degradation rate per year [%] 0.5 0.5 0.5 0.5
Installed power capacity [kW] 5-10 100 100 30-100
Price Fixed price [€]
Estimated price [€/kW] 1000 1000 1000 1000
Storage systems
Lithium-ion batteries will be employed in the different solutions. They exhibit high energy and
power density and show a high efficiency.
The number of cycles is stablished as 8000 and, therefore, by the end of the horizon study they
will possible not have be realized. However, based on real cases and experiences, it will be
considered to replace the battery after ten years of use.
As in the previous case, several capacities will be analysed to carry out the sizing assessment of
the solutions.
Additionally, to Lithium batteries, hydrogen energy technologies for electricity storage will be
evaluated for the possible cases based on available information on worldwide market.
Page: 31 Date: 30/06/2018
Table 21. Storage systems data for the Lithuanian Case studies
Parameters Homeowner Company
as investor
Contractor
concept
Controllable
load
Technology [-] Lithium ion Lithium ion Lithium ion Lithium ion
Cycle efficiency [%] 90 90 90 90
Charge / discharge rate [%] 60 60 60 60
Capacity [kWh] 0-3 10.5-30 5-25 50-150
Depth of discharge [%] 80 80 80 80
Life cycles [-] 8000 8000 8000 8000
Degradation rate per year [%] 0.5 0.5 0.5 0.5
Price Fixed price [€]
Estimated price [€/kWh] 600 600 600 600
Simulation drivers
To carry out the simulations, some extra data related to both the economic and technical aspects
is needed. The data is shown in the table below and follows the template of the Prosumer
Solution Simulation tool, see Annex I for detailed information of the different parameters.
To achieve a higher accuracy, the number of simulations will be set as 1000, which is supposed
to be a large enough number to avoid outliers. Moreover, the decision making will be stablished
as 23 to let the algorithm analyse a completely day ahead when taking a decision. It must also
be pointed out that the inflation will not be considered in the study as it is quite unpredictable
in the electricity markets and therefore the simulation will be carry out in real values.
Table 22. Simulation drivers data for the Lithuanian Case studies
Parameters Homeowner
Company
as
investor
Contractor
concept
Controllable
load
Operational parameters
Annual
maintenance
costs [%]
Panels and
inverters 2 1 1 1
Storage system 2 1 1 1
Depreciation
[useful years]
Panels and
inverters 20 20 20 20
Storage system 10 10 10 10
Financial and tax rates
Corporate tax rate [%] 0 0 0 0
WACC [%] 6.5 6.5 6.5 6.5
Inflation rate [%] 0 0 0 0
Page: 32 Date: 30/06/2018
Simulation parameters
Study horizon [years] 20 20 20 20
Nº of simulations [-] 1000 1000 1000 1000
Decision-making horizon [hours] 23 23 23 23
Rate of avoided carbon dioxide
emissions [kg/kWh] 0.36. 0.36 0.36 0.36
2.3.3. Grid analysis information
Simulations at transmission and distribution levels will be carried out based on national
regulation for the connections of new prosumers to the existing grid. Small power producers (<
10 kW) are obliged to connect to the 0.4 kV distribution grid therefore simulations for
Homeowner and Controllable load scenarios will be performed for the whole 0.4 kV distribution
grid. Simulations will analyse case then newly connected prosumer as well as other energy plants
(both installed and with valid permissions to connect to the grid) are generating power at
projected capacities and at the same time power demand from the corresponding transformer
station is equal to 0 kW. Simulations will analyse the influence for the stability of voltage levels,
loading of components and other standard characteristics specified by the grid operator.
Company as investor and Contractor concept scenarios include installation of 100 kW generation
power which will be connected to 0.4/10 kV transformer stations accordingly similar simulations
will be performed for both 0.4 kV and 10 kV distribution grid voltage levels.
All calculation will be performed strictly following the methodologies and recommendations
issued by the national grid operator and using PSS/E and/or EA-PSM software.
2.3.4. Assessable KPIs
Due to the analysed solutions and the different simulations (static, quasi-static and Dynamic)
that will be carried out, it is expected to evaluate most of the key performance indicators
presented in the table in below.
Table 23. Assessable KPIs for the Lithuanian Case studies
Key Information Indicators Homeowner Company as
investor
Contractor
concept
Controllable
load
Economic – on site
Reduced network usage fee
Net Present Value (NPV)
Internal Rate of Return (IRR)
Paybak time
Reduced exposure to volatility of electricity
prices
Levelized Cost of Electricity (LCOE)
Technical – on site
Degree of self-sufficiency
Page: 33 Date: 30/06/2018
Reduction peak demand ratio
Technical – grid
Energy exchange with the grid
Hosting capacity of solar PV
Reduction in solar PV production cut-off due to
congestion
Voltage stability Vmax
Voltage stability Vmin
Reduction of over voltage in the grid
Reduction of under voltage in the grid
Increase frequency quality performance
Time of a certain frequency variation
Average outage duration for each customer
served (SAID)
Average number of interruptions in the supply
of a customer (SAIFI)
Increased efficiency in preventive control and
emergency control
Increased demand side participation
Actual availability of network capacity
Regulative
Reduction in time to connect new user
Increase in coordinated operation between
TSOs and DSOs
Environmental
Quantified reduction of carbon emissions
2.4. Poland
2.4.1. Solutions
Main factors taken into account which solutions are most promising in Poland:
- regulative criteria
- data availability
- specific characteristic of the demand profile
Homeowner
A double-family terrace house with solar PV. PV electricity will be consumed according to current
demand and its surplus will be exported to the public grid. Due to specific regulations it’s
possible to get back 80% of exported energy (in installations smaller than 10kWp). Hence,
savings will be generated by the avoidance of purchasing electricity from a supplier.
This solution will not only be analysed in Poland but also in the other countries that will carry
out simulations. However, due to the existence of specific regulations which treat DSO’s network
as virtual storage system it will be very interesting to analyse this solution here.
Page: 34 Date: 30/06/2018
Company as investor
Company based in Poznań with 8kWp PV installation will be an example of Company as investor
solution. Accessible demand profile is representative for average medium business in Poland.
Conducted simulations would reflect generation/demand dependencies.
Municipal building
The Culture Center in Śmigiel will be an example of municipal building. The most exceptional
characteristic of this building is its non – regular demand profile depended on both typical needs,
organized cultural events and different needs through a year (ex. school holidays).
2.4.2. Gathered data
The data needed for the simulations are shown in the tables below. Software used to analyse
the solutions will be the Prosumer Solution Simulation tool and DNV Synergi.
Radiation profiles
Radiation profiles will be used for each chosen locations. Example chart for Poznań for one year
period (2007) is shown below:
Figure 9. Yearly irradiance profile of Poznań, Poland
The radiation profiles were obtained from the solar radiation database CMSAF-PVGIS and they
contain data in an hourly resolution from the year 2007 to the year 2016
Demand profiles
The average yearly consumption is shown in figures below. As it can be observed in the following
figures, they show a very different pattern of consumption.
Page: 35 Date: 30/06/2018
Table 24. Average yearly consumption for the Polish Case studies
Parameters Homeowner Company as
investor
Municipal
building
Average yearly consumption [MWh] 4 93 8
Figure 10. Company as Investor consumption profile
Figure 11. Homeowner consumption profile
0
10
20
30
40
01
.20
17
02
.20
17
03
.20
17
04
.20
17
05
.20
17
06
.20
17
07
.20
17
08
.20
17
09
.20
17
10
.20
17
11
.20
17
12
.20
17
01
.20
18
Ener
gy (
kWh
)
Company as Investor
0
2
4
6
8
02
.17
03
.17
04
.17
05
.17
06
.17
07
.17
08
.17
09
.17
10
.17
11
.17
12
.17
01
.18
02
.18
Ener
gy (
kWh
)
Homeowner
Page: 36 Date: 30/06/2018
Figure 12. Municipal building consumption profile
Electricity tariffs
Energy companies independently prepare tariffs according to the scope of activity (held
licenses). In the Ordinance of the Minister of Energy of December 29, 2017, regarding detailed
rules for formation and calculation of tariffs and settlements in trading in electricity (Journal of
Laws of 2017, item 2500), the following rules were defined: shaping tariffs for electricity, prices
and fees calculation, settlements with customers and between energy companies.
Tariffs for electricity are subject to approval by the President of the Energy Regulatory Office.
After conducting administrative proceedings, the President of the Energy Regulatory Office
approves or refuses to approve the tariff. However, the President of the Energy Regulatory
Office may exempt an energy company (seller) from obligation to submit tariffs for approval, if
finds that it works under competitive conditions. Currently, most sellers are required to submit
tariffs to approval.
Regardless of the above duty, sellers can present market offers (prices for consumers defined in
price lists not approved by the President of the Energy Regulatory Office, hence can offer better
and more personalised deals to wide customer groups. Whereas distributors - enterprises
operating in conditions of a natural monopoly, have the obligation to submit tariffs to full
validation, i.e. for all tariff groups.
0
1
2
3
4
5
01
.17
02
.17
03
.17
04
.17
05
.17
06
.17
07
.17
08
.17
09
.17
10
.17
11
.17
12
.17
01
.18
Ener
gy (
kWh
)
Municipal building
Page: 37 Date: 30/06/2018
An electricity consumer bears the following fees:
Purchase of electricity,
Energy distribution services, and other fees provided for in the tariff energy company.
Types of tariffs accepted for calculations of Polish case study:
G11 - tariff dedicated to households, (average household metered daily),
C11 - tariff dedicated to small and medium-sized companies and agricultural holdings, is
supplied from low-voltage power grids with a contracted capacity below 40 kW,
C21 - tariff dedicated to medium-sized companies with a connection capacity of over 40 kW.
In this case, price for energy is negotiable.
All the above tariffs are single-zone variants - a rate for price of electricity is immutable, it does
not depend on the given hour during a day or a day of a week.
Table 25. Electricity tariffs data in 2018 for the Polish Case studies
Tariffs G11 C11 C21
Energy prices (net) PLN/kWh 0.2432 0.3999 0.3095
€/kWh 0.0571 0.0939 0.0727
Energy prices ( gross) PLN/kWh 0.2991 0.4919 0.3807
€/kWh 0.0703 0.1155 0.0894
Energy prices with distribution fee (net) PLN/kWh 0.4186 0.3999
negotiable €/kWh 0.0983 0.0939
Energy prices with distribution fee (gross) PLN/kWh 0.5149 0.6668
negotiable €/kWh 0.1209 0.1566
Network fee PLN/kWh 3.74 3.74 3.74
€/kWh 0.8784 0.8761 0.8761
Subscription fee PLN/kWh 4.72 34.44 75
€/kWh 1.1086 8.0890 17.6156 Sources: Cennik ogólny ENEA.
Yearly average rates January-December 2017 – 1EUR – 4,2576PLN
Electricity market framework
Regarding the Polish regulation net-metering is the system for micro-installation in Poland. The
surplus of produced energy may be feed to the electricity grid, and may be balanced with the
energy consumed from the electricity network in relation:
1 to 0.7 for PV systems with the power between 10 kW and 40 kW and
1 to 0.8 for PV systems with less than 10 kW.
If the installation does not exceed 40 kW, but produces energy for the needs of the business an
owner may sell surplus produced, on the prices of competitive market, which is announced by
the President of the Regulatory Office Energy.
Page: 38 Date: 30/06/2018
In 2016, the average annual price of sales of electricity on the competitive market was 38.90
EUR/ MWh (169.70 PLN/MWh), in 2017 - 38.45 EUR/ MWh, (163.70 PLN/MWh), and for I quarter
of 2018 41.98 EUR/ MWh (174.95 PLN/MWh).
Table 26. Electricity market framework data for the Polish Case studies
Parameters Homeowner Company as
investor
Municipal
building
4Feed in -
Revenues
Electricity market
price [€/MWh]
Feed in premium
[€/MWh]
Feed in tariff
[€/MWh]
Self-
consumption
tax
Fixed
term per
year
[€/kW]
Peak
Shoulder
Off-peak
Usage
charge
[€/kWh]
Peak
Shoulder
Off-peak
Tax on energy
exported to
the grid
Toll [€/MWh]
Tax on benefits [%]
Panels and inverters
Table 27. Panels and inverters data for the Polish Case studies
Parameters Homeowner Company as
investor
Municipal
building
Total efficiency [%] 15 15 15
PV panel size [m2] 1.7 1.7 1.7
Nominal power per panel [W] 130 250 250
PV degradation rate per year [%] 0.5 0.5 0.5
Installed power capacity [kW] 4.16 8 3
Price Fixed price [€] 4510€1 6013€2 2255€3
Estimated price [€/kW]
1- (32pieces*600zł)/4.2576zł = 4510€
2- (32pieces*800zł)/ 4.2576zł = 6013€
3 - (12 pieces*800zł)/ 4.2576zł = 2255€
Page: 39 Date: 30/06/2018
Storage systems
Regarding the Polish regulation net-metering is the system for micro-installation in Poland. The
surplus of produced energy may be feed to the electricity grid, and may be balanced with the
energy consumed from the electricity network in relation:
1 to 0.7 for PV systems with the power between 10 kW and 40 kW and
1 to 0.8 for PV systems with less than 10 kW.
If the installation does not exceed 40 kW, but produces energy for the needs of the business an
owner may sell surplus produced, on the prices of competitive market, which is announced by
the President of the Regulatory Office Energy.
In view of the above we may treat distributed network as a virtual storage system with infinite
capacity.
Simulation drivers
Table 28. Simulation drivers data for the Polish Case studies
Parameters Homeowner Company as
investor
Municipal
building
Operational parameters
Annual
maintenance
costs [%]
Panels and
inverters 1% 2% 2%
Storage system None – grid
storage
None – grid
storage
None – grid
storage
Depreciation
[useful years]
Panels and
inverters 5% 5% 5%
Storage system None – grid
storage
None – grid
storage
None – grid
storage
Financial and tax rates
Corporate tax rate [%] 19 19 19
WACC [%] 6 6 6
Inflation rate [%] 2 2 2
Simulation parameters
Study horizon [years] 20 20 20
Nº of simulations [-] 1 1 1
Decision-making horizon [hours] 23 23 23
Rate of avoided carbon dioxide
emissions [kg/kWh] 0.36 0.36 0.36
Page: 40 Date: 30/06/2018
2.4.3. Grid analysis information
Grid analysis will be performed considering the following factors:
- Low voltage network limitations for PV highly saturated grid segments
- Impact of PV generation on medium voltage network
- Any possible grid limitations (overvoltage, over frequency) that can occur at low voltage and
medium voltage level.
2.4.4. Assessable KPIs
Table 29. Assessable KPIs for the Polish Case studies
Key Information Indicators Homeowner Company as
investor
Municipal
building
Economic – on site
Reduced network usage fee
Net Present Value (NPV)
Internal Rate of Return (IRR)
Paybak time
Reduced exposure to volatility of electricity
prices
Levelized Cost of Electricity (LCOE)
Technical – on site
Degree of self-sufficiency
Reduction peak demand ratio
Technical – grid
Energy exchange with the grid
Hosting capacity of solar PV
Reduction in solar PV production cut-off due to
congestion
Voltage stability Vmax
Voltage stability Vmin
Reduction of over voltage in the grid
Reduction of under voltage in the grid
Increase frequency quality performance
Time of a certain frequency variation
Average outage duration for each customer
served (SAID)
Average number of interruptions in the supply
of a customer (SAIFI)
Increased efficiency in preventive control and
emergency control / /
Increased demand side participation
Actual availability of network capacity
Regulative
Reduction in time to connect new user
Increase in coordinated operation between
TSOs and DSOs
Environmental
Quantified reduction of carbon emissions
Page: 41 Date: 30/06/2018
2.5. Spain
2.5.1. Solutions
When deciding which solutions from those given in deliverable 2.1 should be tested in Spain,
several factors were taken into account in order to analyse the most promising ones to be
implemented in the country. Among the different reasons to decide, some examples are
regulative criteria, data availability, specific characteristics of the demand profile, etc.
Homeowner
A single-family house with solar PV and storage system, which is a popular business model in
Europe, will be analysed. PV electricity will be consumed when possible and excess electricity
will be either stored for later use or exported to the public grid. Therefore, savings will be
generated by the avoidance of purchasing electricity from a supplier and possibly by selling the
excess electricity.
This solution will not only be analysed in Spain but also in the other countries that will carry out
simulations. However, analysing this solution in Spain can be very interesting, given the high
degree of specificity of the Spanish self-consumption regulation. The simulation will also assess
what impact this regulation have over the profitability of those projects.
Furthermore, real consumption data is available from a four family-members house located in
Madrid, Spain. The demand profile shows a 50% lower consumption during summer, when the
PV production is higher.
Contractor concept
Deloitte’s headquarters in Madrid, Spain, will be analysed. This solution is quite widespread in
Europe especially among companies that are not interested in owning physical assets. This fact,
together with the availability of real data for the simulation, makes this solution highly
interesting. The regulation against PV self-consumption also affects this type of consumers.
In addition, the consumption profile shows some features that can play an attractive role in
electricity market as it has almost no consumption during the weekends, which means that
almost all the energy produced by the solution could be exported to grid during that time.
Municipal building
A public school in Getafe, Madrid, Spain, will be employed to assess the municipal building
solution. The most prominent characteristic of this building is its consumption profile. Schools
do not always have electricity demand during the summer period, as well as during the
weekends. Therefore, as the revenues are higher from avoiding to buy energy from the grid than
Page: 42 Date: 30/06/2018
from selling energy to the grid, it will be interesting to test the profitability and scalability of this
solution.
Furthermore, municipal buildings are also quite interesting due to the lighthouse effect that they
may have. This case is not exempt from this adverse regulation and therefore it would be a good
way to compare its impact.
Community storage
This is one of the newest and promising solutions that can have a huge penetration in the future,
as the concept of smarts grid grows and matures. For this reason, evaluating this case study may
be highly enriching. Nowadays, there are no real cases of this solution implemented in the
country, although a reduced number of case studies at a small scale have been developed.
Additionally, the number of self-consumption communities without storage is also very limited
to date, given that self-consumption in communities was prohibited by law until 2017.
The community storage will be understood as a group of houses that share a storage device.
Therefore, regarding the demand profile of the different houses, the same demand
characteristics of the homeowners will be assumed for the different houses of the community.
2.5.2. Gathered data
The data gathered for the simulations are shown in the tables below. As the software employed
to size the solutions will be the Prosumer Solution Simulation tool, these tables follows the same
pattern than the input windows of the tool.
Radiation profiles
The different solutions will be tested in Madrid, Spain. The region where they are located
presents an average annual irradiance of 1.75 MWh/m2, reaching its maximums values during
the summer season. The radiation profiles were obtained from the solar radiation database
CMSAF-PVGIS and they contain data in an hourly resolution from the year 2007 to the year 2016.
As an example, data from year 2007 in Madrid is shown in the Figure below.
Page: 43 Date: 30/06/2018
Figure 13. Yearly irradiance profile of Madrid, Spain
Demand profiles
The consumption profiles were obtained by monitoring the hourly demand of electricity over a
year in real installations. As it can be observed in the following figures, the different case studies
show a very different pattern of consumption. While the office and schools have a huge
consumption during the week, they show few consumption during the weekend. However, the
higher demand peak in a household appears around 13 and 20 hours. It can be also observed in
the following table that the average yearly consumption is highly different when evaluating the
different types of solutions.
Table 30. Average yearly consumption for the Spanish Case studies
Parameters Homeowner Contractor
concept
Municipal
building
Community
storage
Average yearly consumption [MWh] 6 198 158 130
Page: 44 Date: 30/06/2018
Figure 14. Household consumption yearly profile
Figure 15. Contractor concept consumption yearly profile
Page: 45 Date: 30/06/2018
Figure 16. Municipal building consumption yearly profile
Electricity tariffs
The price of the electricity that each solution demands will depend on the electricity tariff that
the solution has contracted with the electricity retailer. For example, the homeowner is
associated to a 2.0 DHS tariff, while the office and the school is associated to a 3.0 A. These
tariffs, with hourly discrimination, correspond to a contracted power capacity lower than 10 kW
and higher than 15 kW, respectively. The different prices and hours for each period are shown
in the table below.
Table 31. Electricity tariffs data for the Spanish Case studies
Parameters Homeowner Contractor
concept
Municipal
building
Community
storage
Tariff prices
[€/kWh]
Summer
Peak 0.17 0.11 0.11 0.17
Shoulder 0.11 0.10 0.10 0.11
Off-peak 0.08 0.07 0.07 0.08
Winter
Peak 0.17 0.11 0.11 0.17
Shoulder 0.11 0.10 0.10 0.11
Off-peak 0.08 0.07 0.07 0.08
Tariff periods
[h]
Summer
Peak 13-23 11-15 11-15 13-23
Shoulder Others Others Others Others
Off-peak 1-7 0-8 0-8 1-7
Winter
Peak 13-23 18-22 18-22 13-23
Shoulder Others Others Others Others
Off-peak 1-7 0-8 0-8 1-7
Page: 46 Date: 30/06/2018
Electricity market framework
According to the Spanish regulation, this type of solutions must pay a tax on self-consumption,
except the cases when the total installed power is lower than 10 kW, which may only be
applicable to the homeowner case study.
The self-consumption tax is composed of two terms: a fixed term and a variable term. The first
one is related to the power of the installation, while the second one affects to the self-consumed
energy. According to the tariff contracted by the user, the law sets the different costs for these
two terms.
It must be noted that in the vast majority of cases the fixed term is not billed, given that it is only
applicable to the difference between the contracted power and the billed power, and it is
common that the billed power corresponds to the contracted power (in tariffs with a contracted
power lower than 15 kW it is inevitable). Therefore, the most important tax is the one related
to the self-consumed energy. The equation which allows to calculate the cost of the variable
term is the following:
𝑇𝑠−𝑐 = 𝐸𝑠−𝑐 ∙ 𝑉𝑇𝑠−𝑐
Where:
Ts-c: Total tax billed (€)
Es-c: Total self-consumed energy (kWh)
VTs-c: Self- consumption tax applicable to each tariff (€/kWh)
In tariffs with more than one hourly discrimination period, the self-consumption taxes are billed
for each term.
When the solutions exports energy to the grid, its revenues will be determined by the Electricity
Market Price (EMP). This data is obtained from the Spanish division of the Iberian Market
Operator (OMIE) website and it corresponds to a five-year period, as required by the simulation
tool.
Furthermore, according to the Royal Decree 1544/2011 of the Spanish regulation, a toll of 0.5
€/MWh must be paid for all the energy exported. Moreover, there is a tax of 7%, applicable on
the benefits obtained for selling this energy, which must also be considered.
The table below summarizes the different sources of income, taxes and tolls that play a role on
the profitability of the solutions.
Page: 47 Date: 30/06/2018
Table 32. Electricity market framework data for the Spanish Case studies
Parameters Homeowner Contractor
concept
Municipal
building
Community
storage
Feed in -
Revenues
Electricity market price
[€/MWh]
Feed in premium
[€/MWh]
Feed in tariff [€/MWh]
Self-
consumption
tax
Fixed term
per year
[€/kW]
Peak 7.10 32.00 32.00 7.10
Shoulder 7.10 5.20 5.20 7.10
Off-peak 7.10 4.13 4.13 7.10
Usage
charge
[€/kWh]
Peak 0.05 0.02 0.02 0.05
Shoulder 0.01 0.01 0.01 0.01
Off-peak 0.06 0.01 0.01 0.01
Tax on energy
exported to
the grid
Toll [€/MWh] 0.5 0.5 0.5 0.5
Tax on benefits [%] 7 7 7 7
Panels and inverters
Monocrystalline PV modules will be employed in the different solutions. This technology has a
major cost than others but its efficiency is also higher, standing between 17 and 18%. However,
the presence of inverters, as well as all the possible losses that might affect the installation
(temperature, shading, soiling, etc.) will decrease the total efficiency of the installation to 15%.
The sizing assessment of the solution is one of the main aims of this study. Therefore, several
installed capacities will be simulated in order to see which one should be implemented or
suggested. In the table below, the different characteristics of the installation can be observed,
which includes panels and inverters, together with the range of installed power capacity that
will be studied.
Table 33. Panels and inverters data for the Spanish Case studies
Parameters Homeowner Contractor
concept
Municipal
building
Community
storage
Total efficiency [%] 15 15 15 15
PV panel size [m2] 1.7 1.7 1.7 1.7
Nominal power per panel [W] 250 250 250 250
PV degradation rate per year [%] 0.5 0.5 0.5 0.5
Installed power capacity [kW] 2-6 10-60 10-40 50-100
Price Fixed price [€]
Estimated price [€/kW] 1000 1000 1000 1000
Page: 48 Date: 30/06/2018
Storage systems
Lithium-ion batteries will be employed in the different solutions. They provide high energy and
power density and also show a high efficiency.
The number of cycles of operation of the batteries is established at 8,000, which by the end of
the simulated lifetime of the installation might not have been reached. However, based on real
cases and experiences, even though the total life cycles of the battery have not been exceeded,
the tool simulates a battery replacement rate of ten years.
As in the case of the PV installation, several capacities will be analysed in order to carry out the
sizing assessment of the solutions. In the table below, the different characteristics of the storage
systems together with the range capacities that will be studied are presented.
Table 34. Storage systems data for the Spanish Case studies
Parameters Homeowner Contractor
concept
Municipal
building
Community
storage
Technology [-] Lithium ion Lithium ion Lithium ion Lithium ion
Cycle efficiency [%] 90 90 90 90
Charge / discharge rate [%] 60 60 60 60
Capacity [kWh] 0-3 10.5-30 5-25 50-150
Depth of discharge [%] 80 80 80 80
Life cycles [-] 8000 8000 8000 8000
Degradation rate per year [%] 0.5 0.5 0.5 0.5
Price Fixed price [€]
Estimated price [€/kWh] 600 600 600 600
Simulation drivers
In order to carry out the simulations, some extra data related to both the economic and technical
aspects is needed.
In order to achieve a higher accuracy, the number of simulations will be set at 1,000, which is
supposed to be large enough to avoid outliers. Moreover, the decision making will be stablished
at 23, in order to let the algorithm analyse a complete day ahead when taking a decision. It must
also be pointed out that the inflation rate will not be considered in the study, as it is quite
unpredictable in the electricity markets, and therefore the simulation will be carried out
considering current values.
Page: 49 Date: 30/06/2018
Table 35. Simulation drivers data for the Spanish Case studies
Parameters Homeowner Contractor
concept
Municipal
building
Community
storage
Operational parameters
Annual
maintenance
costs [%]
Panels and inverters 2 2 2 2
Storage system 0 0 0 0
Depreciation
[useful years]
Panels and inverters 20 20 20 20
Storage system 10 10 10 10
Financial and tax rates
Corporate tax rate [%] 0 25 25 0
WACC [%] 6.5 6.5 6.5 6.5
Inflation rate [%] 0 0 0 0
Simulation parameters
Study horizon [years] 20 20 20 20
Nº of simulations [-] 1000 1000 1000 1000
Decision-making horizon [hours] 23 23 23 23
Rate of avoided carbon dioxide
emissions [kg/kWh] 0.36 0.36 0.36 0.36
2.5.3. Grid analysis information
Simulations at transmission and distribution level will be carried out. The peninsular Spanish
transmission system will be employed in the simulations. Interconnections with France, Portugal
and Morocco must be also considered due to the impact that they have in the electricity
interconnecting grid performance. A distribution grid in the region of Madrid was built and
connected to the transmission system. This distribution grid is shown in the figure below and it
consists of five voltage levels: 400, 220, 132, 45 and 15 kV.
In order to develop the simulations, PowerFactory will be used, which is a leading power system
analysis software application for use in analysing generation, transmission, distribution and
industrial systems. An example of the Madrid grid model is depicted in the figure below.
Several levels of demand will be considered and different levels of solar PV penetration will be
assessed. This PV generation will be deployed in 43 nodes at 15 kV and 1 node at 45 kV.
The parameters evaluated will be grid losses, voltage levels and loading of components. N-1
contingency analysis will be performed to assess the behaviour of the system before and after
the PV solution is introduced. Security criteria must be met.
Page: 50
Date: 30/06/2018
Figure 17. Distribution grid of Madrid, Spain (part of the transmission grid is included)
Page: 51
Date: 30/06/2018
Figure 18. Example of PowerFactory grid modelling (one part of the distribution grid of Madrid
Page: 52
Date: 30/06/2018
At low voltage level, yearly simulations with an hourly time resolution will be performed. The PV
solutions proposed are mainly connected at low voltage level (< 1 kV). Therefore, assessing the
local impact these systems exerts on the low voltage grid is a key output of this project. Through
these quasi-static simulations, it can be appreciated when and where there could be
overloading, overvoltage or under-voltage in the grid.
The integration of batteries opens up the possibility to assess the improvement in the transient
behaviour of the system in case of faults and disturbances.
2.5.4. Assessable KPIs
Given the analysed solutions and the different simulations (static, quasi-static and dynamic) that
will be carried out, it is expected to evaluate the key performance indicators presented in the
table below.
Table 36. Assessable KPIs for the Spanish Case studies
Key Information Indicators Homeowner Contractor
concept
Municipal
building
Community
storage
Economic – on site
Reduced network usage fee
Net Present Value (NPV)
Internal Rate of Return (IRR)
Paybak time
Reduced exposure to volatility of electricity
prices
Levelized Cost of Electricity (LCOE)
Technical – on site
Degree of self-sufficiency
Reduction peak demand ratio
Technical – grid
Energy exchange with the grid
Hosting capacity of solar PV
Reduction in solar PV production cut-off due to
congestion
Voltage stability Vmax
Voltage stability Vmin
Reduction of over voltage in the grid
Reduction of under voltage in the grid
Increase frequency quality performance
Time of a certain frequency variation
Average outage duration for each customer
served (SAIDI)
Average number of interruptions in the supply
of a customer (SAIFI)
Page: 53
Date: 30/06/2018
Increased efficiency in preventive control and
emergency control
Increased demand side participation
Actual availability of network capacity
Regulative
Reduction in time to connect new user
Increase in coordinated operation between
TSOs and DSOs
Environmental
Quantified reduction of carbon emissions
3. References
1. No Title. Available at: https://www.wind-energy-the-facts.org/european-transmission-
and-distribution-networks.html (Accessed: 30 June 2018)
2. M. Bollen och H. Fainan, "Integration of Distributed Generation in the Power System",
Hoboken, New Jersey: John Wiley and Sons, Inc, 2011.
3. Enernex, ”Integration Issues and Simulation Challenges of High Penetration PV,” Enernex,
Knoxville, 2011.
4. No Title. Available at: https://www.entsoe.eu/publications/system-operations-reports/
(Accessed: 10 July 2018)