Wood Green Town Centre Major Scheme Construction Progress Update 008 6 October 2014

Wood Green Town Centre Major Scheme Construction Progress … · 2014. 12. 22. · o Phase 5 - North east, north west, south west corners of Turnpike Lane Junction ... signage (including

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Wood Green Town Centre Major Scheme Construction Progress … · 2014. 12. 22. · o Phase 5 - North east, north west, south west corners of Turnpike Lane Junction ... signage (including

Wood Green Town Centre Major Scheme

Construction Progress Update

008 6 October 2014

Page 2: Wood Green Town Centre Major Scheme Construction Progress … · 2014. 12. 22. · o Phase 5 - North east, north west, south west corners of Turnpike Lane Junction ... signage (including
Page 3: Wood Green Town Centre Major Scheme Construction Progress … · 2014. 12. 22. · o Phase 5 - North east, north west, south west corners of Turnpike Lane Junction ... signage (including

Current Status / Progress Week Ending 03/10/2014 In total works completed to date are:

o Phase 1 - All paving, except access road at Morrison’s o Phase 2 - Paving behind High Road retaining wall (east side) o Phase 4 - High Road north side of Whymark Avenue paving o Phase 4 - Whymark Avenue paving o Phase 5 - Westbury Avenue north side paving o Phase 5 - North east, north west, south west corners of Turnpike Lane Junction o Phase 5 - Turnpike Lane paving o Phase 5 - Turnpike Lane bus station parade and adjacent islands

Works continuing to:

o Phase 1 – Spouter’s Corner granite mats 90% complete o Phase 3 - West side, south of Alexandra Road paving o Phase 3 - West side paving between Brampton Park Road and Courcy Road o Phase 5 - Outside Turnpike Lane Underground Station 90% complete o Granite quadrants placed across site (15%)

Weekly Forecast:

o Phase 2 - Continuing east side, south of retaining wall o Phase 3 - Continuing west side, south of Alexandra Road o Phase 3 – Continuing west side between Brampton Park Road and Courcy Road o Phase 5 - Continuing outside Turnpike Lane underground station o Phase 1 / 5 - Granite quadrants installation o 2-way lights program to continue on High Road

See page 7 of this document for further details

Upcoming Key Milestones (Next 4 weeks)

o Turnpike Lane islands to be completed

Page 4: Wood Green Town Centre Major Scheme Construction Progress … · 2014. 12. 22. · o Phase 5 - North east, north west, south west corners of Turnpike Lane Junction ... signage (including

Photo Journal Paving and retaining wall demolition at The Mall

Page 5: Wood Green Town Centre Major Scheme Construction Progress … · 2014. 12. 22. · o Phase 5 - North east, north west, south west corners of Turnpike Lane Junction ... signage (including

Granite quadrants placed with heavy duty suction lifter

Granite quedrants beng lifted in place

Page 6: Wood Green Town Centre Major Scheme Construction Progress … · 2014. 12. 22. · o Phase 5 - North east, north west, south west corners of Turnpike Lane Junction ... signage (including

Granite quadrants being placed

Page 7: Wood Green Town Centre Major Scheme Construction Progress … · 2014. 12. 22. · o Phase 5 - North east, north west, south west corners of Turnpike Lane Junction ... signage (including

Footway excavation south of Lymington Avenue

Footway installation opposite Lymington Avenue

Page 8: Wood Green Town Centre Major Scheme Construction Progress … · 2014. 12. 22. · o Phase 5 - North east, north west, south west corners of Turnpike Lane Junction ... signage (including

Birds-eye view towards Alexandra Road junction

Page 9: Wood Green Town Centre Major Scheme Construction Progress … · 2014. 12. 22. · o Phase 5 - North east, north west, south west corners of Turnpike Lane Junction ... signage (including

Dramatically altered kerb lines at the Alexandra Road junction

Levelling the sand ahead of laying the paving slabs

Page 10: Wood Green Town Centre Major Scheme Construction Progress … · 2014. 12. 22. · o Phase 5 - North east, north west, south west corners of Turnpike Lane Junction ... signage (including

Footways completed at the junction with Alexandra Road

Page 11: Wood Green Town Centre Major Scheme Construction Progress … · 2014. 12. 22. · o Phase 5 - North east, north west, south west corners of Turnpike Lane Junction ... signage (including

Standard Supplemental The text below is a standard supplemental to the programme of works shown on page 2 that forms this update regarding construction progress. Construction Strategy The initial phases of construction will consist of footway renewal and kerb works. Other elements of the scheme will follow, which will consist of street furniture renewal, new signage (including “Legible London”), SUDS (Sustainable Urban Drainage Systems), street lighting upgrade, new trees and tree pits and all special features. All of these elements will be completed on an “area by area” basis as opposed to rolling out each element globally throughout the scheme. Carriageway resurfacing will be the last element of the scheme to be implemented. Bus Stops will be temporarily closed as construction progresses to the areas shown on page 2. There will be several phases of construction that will require 2-way temporary traffic lights on the High Road. Traffic will be severely disrupted during these times. Schedule of dates shown below: Wood Green - Two Way Temporary Signal Programme

Location Duration Start Finish

Islands on High Road 4 days 01 September 2014 04 September 2014

Phase 2A & B - Library to the Mall (East) 13 days 04 September 2014 16 September 2014

Phase 3B - The Mall to Brampton Park Road 34 days 17 September 2014 20 October 2014

Phase 3A - The Mall to Dovecote Avenue 19 days 21 October 2014 07 November 2014

Phase 4B - Brampton Park Road to Coleraine Road 20 days 10 November 2014 28 November 2014

Christmas Embargo period

Phase 2C - Library (West) 11 days 06 January 2015 16 January 2015

Phase 2D - The Mall (West) 11 days 19 January 2015 29 January 2015

Phase 4B - Brampton Park Road to Coleraine Road 37 days 30 January 2015 07 March 2015

All dates subject to change

Page 12: Wood Green Town Centre Major Scheme Construction Progress … · 2014. 12. 22. · o Phase 5 - North east, north west, south west corners of Turnpike Lane Junction ... signage (including

Strategy for waste management Residential waste is usually deposited on the footway on the High Road. Our contractor will provide gangways to each doorway (business and resident) to allow entry/exit from premises. Residents should leave their waste at the carriageway end of these gangways (on the footway, within and near to the barriers), which will allow rubbish to be collected as usual.

Businesses with their own individual contracts for waste disposal will need to inform their contractor of construction to allow preparation for their continued management of waste disposal.

If you have any enquiries regarding waste collection, Veolia can be contacted on their general enquiries number: 020 8885 7700.

Provision of access to shops/businesses/restaurants/residential There will be disruption during the construction period; and we will try our best to keep this to a minimum. Access to business will be maintained for the majority of the construction period, but there will be short durations when access will be fully blocked. Our contractor will individually liaise with properties to agree the most convenient time for this to occur. Disabled access Access will be maintained to residences / businesses. A minimum width walkway of 1.2m will be maintained at all times. Working Hours

General operations Standard: Monday to Friday - 08:00 to 18:00 Saturday: 08:00 to 13:00 Sunday: None Allowable out of hours works Construction work may be undertaken outside of the hours shown above, only if the works do not affect traffic flows and are quiet works such as site clearance or material deliveries. Working hours constraints No construction works will be undertaken during the Christmas Embargo, which is from 1 December 2014 to 4 January 2015.