15
[1985–1986]  SLR(R) SINGAPORE LAW REPORTS (REISSUE) 503 Woh Hup (Pte) Ltd and another v Turner (East Asia) Pte Ltd [1986] SGHC 3 High Court — Suit No 3599 of 1985 F A Chua J 14 January 1986 Arbitration — Stay of court proceedings — Defendant applying for stay of proceedings on basis that contract contained arbitration clause — Defendant resident within jurisdiction — Whether stay should be granted on condition that defendant provide security — Whether Court has power to impose conditions when granting stay of proceedings under s 7 Arbitration Act (Cap 16, 1970 Rev Ed) Civil Procedure — Summary judgment — Claim by subcontractor against main contractor for sums outstanding on subcontract — Whether value of subcontractor’s outstanding claims sufficiently established — Order 14 r 1 The Rules of the Supreme Court 1970 Facts The defendant (“Turner”) was appointed the main contractor for a development (“the Gateway Project”), and subcontracted some of the works on the Gateway Project (“the subcontract”) to the plaintiffs (“Woh Hup”). The subcontract between Turner and Woh Hup was terminated after Turner’s employment under the main contract was determined. Under cl 21 of the subcontract, upon the determination of the main contract, Woh Hup would be entitled to be paid the value of the subcontract works completed at the date of such determination, calculated according to cl 10. These three appeals arose out of claims brought by Woh Hup against Turner for outstanding sums due under the subcontract totalling some $23m. Woh Hup initially applied for summary judgment against Turner under O 14 r 1 of The Rules of the Supreme Court 1970 (“the Rules”). Woh Hup’s application for summary judgment only related to two out of their four heads of claims against Turner (“heads (i) and (ii)”). Woh Hup was prepared to refer the other two heads of claims against Turner (“heads (iii) and (iv)”) to arbitration provided that Turner furnished adequate security. Turner opposed Woh Hup’s application for summary judgment and instead sought an order that all further proceedings be stayed pursuant to s 7 of the Arbitration Act (Cap 16, 1970 Rev Ed) (“the Act”). According to Turner, the parties had, by the subcontract, agreed to refer the present dispute to arbitration. Both applications were heard by a senior assistant registrar (“the SAR”). The SAR made no order on Woh Hup’s application for summary judgment. As regards Turner’s application for a stay, the SAR ordered that all further proceedings be stayed pursuant to s 7 of the Act on condition that Turner should furnish security in the form of a banker’s guarantee, and that judgment be entered in Woh Hup’s favour in default thereof. Woh Hup appealed against the

Woh Hup (Pte) Ltd and another v Turner (East Asia) …1985...[1985–1986] SLR(R) SINGAPORE LAW REPORTS (REISSUE) 503 Woh Hup (Pte) Ltd and another v Turner (East Asia) Pte Ltd [1986]

  • Upload
    buithuy

  • View
    219

  • Download
    0

Embed Size (px)

Citation preview

[1985–1986]  SLR(R) SINGAPORE LAW REPORTS (REISSUE) 503

Woh Hup (Pte) Ltd and another v

Turner (East Asia) Pte Ltd

[1986] SGHC 3

High Court — Suit No 3599 of 1985F A Chua J14 January 1986

Arbitration — Stay of court proceedings — Defendant applying for stay ofproceedings on basis that contract contained arbitration clause — Defendant residentwithin jurisdiction — Whether stay should be granted on condition that defendantprovide security — Whether Court has power to impose conditions when grantingstay of proceedings under s 7 Arbitration Act (Cap 16, 1970 Rev Ed)

Civil Procedure — Summary judgment — Claim by subcontractor against maincontractor for sums outstanding on subcontract — Whether value of subcontractor’soutstanding claims sufficiently established — Order 14 r 1 The Rules of the SupremeCourt 1970

Facts

The defendant (“Turner”) was appointed the main contractor for a development(“the Gateway Project”), and subcontracted some of the works on the GatewayProject (“the subcontract”) to the plaintiffs (“Woh Hup”). The subcontractbetween Turner and Woh Hup was terminated after Turner’s employmentunder the main contract was determined. Under cl 21 of the subcontract, uponthe determination of the main contract, Woh Hup would be entitled to be paidthe value of the subcontract works completed at the date of such determination,calculated according to cl 10. These three appeals arose out of claims brought byWoh Hup against Turner for outstanding sums due under the subcontracttotalling some $23m.

Woh Hup initially applied for summary judgment against Turner under O 14 r 1of The Rules of the Supreme Court 1970 (“the Rules”). Woh Hup’s applicationfor summary judgment only related to two out of their four heads of claimsagainst Turner (“heads (i) and (ii)”). Woh Hup was prepared to refer the othertwo heads of claims against Turner (“heads (iii) and (iv)”) to arbitrationprovided that Turner furnished adequate security. Turner opposed Woh Hup’sapplication for summary judgment and instead sought an order that all furtherproceedings be stayed pursuant to s 7 of the Arbitration Act (Cap 16, 1970 RevEd) (“the Act”). According to Turner, the parties had, by the subcontract, agreedto refer the present dispute to arbitration.

Both applications were heard by a senior assistant registrar (“the SAR”). TheSAR made no order on Woh Hup’s application for summary judgment. Asregards Turner’s application for a stay, the SAR ordered that all furtherproceedings be stayed pursuant to s 7 of the Act on condition that Turner shouldfurnish security in the form of a banker’s guarantee, and that judgment beentered in Woh Hup’s favour in default thereof. Woh Hup appealed against the

paginator.book Page 503 Sunday, September 20, 2009 1:00 AM

504 SINGAPORE LAW REPORTS (REISSUE) [1985–1986]  SLR(R)

SAR’s orders in respect of both the applications, whilst Turner appealed solelyagainst the condition in the SAR’s order granting a stay of proceedings.

Held, setting aside both the SAR’s orders: (1) Woh Hup was entitled to summary judgment for heads (i) and (ii). Thesetwo sums were indisputably due. According to cl 21 of the subcontract, in thecase of determination of the subcontract, not the full subcontract sum waspayable but only the value of works up to the point of determination. The valueof the subcontract works completed at the date of the determination of thesubcontract for heads (i) and (ii) had already been calculated. It was not the casethat these works had to be revalued on determination of the subcontract as ifthey were variations: at [24], [25], [30], [31] and [44].

(2) Conversely, Woh Hup’s claims under heads (iii) and (iv) should go forarbitration and there should be a stay of proceedings in respect of those twoheads of claims. A thorough investigation needed to be made regarding theseheads of claims as Turner’s allegations in this regard were neither vague norgeneral: at [54].

(3) The stay of proceedings in respect of heads (iii) and (iv) would be grantedwithout condition. The exercise of the jurisdiction to stay proceedings wasdiscretionary, but if the court was satisfied that there was no sufficient reasonwhy the matter should not be referred to arbitration in accordance with anarbitration agreement, the court would seldom refuse a stay. The court’s powerto impose conditions when granting leave to defend was expressly provided forunder O 14 of the Rules. However, where the court granted a stay of proceedingsunder s 7 of the Act, no such power was provided at all. Woh Hup cited noauthority in which a stay of proceedings was granted on condition that thedefendant provided security for the sum claimed when the party seeking thearbitration was not a foreigner: at [53], [56], [60] and [61].

Case(s) referred toBjornstad and The Ouse Shipping Co, Re [1924] 2 KB 673 (distd)Ellis Mechanical Services Ltd v Wates Construction Ltd (1976) 2 Build LR 57;

[1978] 1 Lloyd’s Rep 33 (folld)

Legislation referred toArbitration Act (Cap 16, 1970 Rev Ed) s 7 (consd)Rules of the Supreme Court 1970, The O 14 r 1 (consd)Arbitration Act 1889 (c 49) (UK) s 5

Giam Chin Toon (Wee Swee Teow & Co) for the plaintiff; Wong Meng Meng (Shook Lin & Bok) for the defendant.

paginator.book Page 504 Sunday, September 20, 2009 1:00 AM

[1985–1986]  SLR(R) Woh Hup (Pte) Ltd v Turner (East Asia) Pte Ltd 505

14 January 1986 Judgment reserved.

F A Chua J:

1 There are three appeals against the decisions of the senior assistantregistrar given on 20 August 1985. These appeals arise out of the claims bythe plaintiffs against the defendants for sums due under a buildingsubcontract totalling $23,150,331.

2 The plaintiffs are a joint-venture firm engaged in the building worksrequired in the construction of a development known as the Gatewayproject. The defendants were building contractors engaged as the maincontractors for the construction of the Gateway project development andwhose employer under the main contract was Gateway Land (“theemployer”). By a subcontract dated 2 November 1983 (“the subcontract”)supplemental to the main contract the plaintiffs agreed to carry out andcomplete the subcontract works in accordance with the subcontractdocuments, upon the terms and conditions contained therein. Theplaintiffs’ accepted tender sum for the subcontract works was $45,620,000.

3 The subcontract works essentially comprised the following:

(a) air-conditioning and mechanical ventilation services;

(b) electrical services;

(c) plumbing and sanitary services; and

(d) fire services.

4 The plaintiffs duly commenced the subcontract works and proceededwith the same, receiving interim payments from the defendants from timeto time. By letter dated 3 January 1985, the defendants informed theplaintiffs that the amount payable under certificate number 18 issued by thearchitects dated 14 December 1984, had been withheld from the defendantsby the employer and that as soon as the defendants had received theamounts due from the employer they would forward to the plaintiffs theamounts certified by the architects for payment to the plaintiffs. By letterdated 19 January 1985, the defendants informed the plaintiffs that they hadformally rescinded the main contract on 18 January 1985, on the advice oftheir lawyers. By letter dated 5 February 1985, to the plaintiffs thedefendants confirmed that the main contract had been determined.Consequently the subcontract was determined with effect from 18 January1985. In April 1985 the plaintiffs commenced the present proceedingsagainst the defendants.

5 On 2 May 1985 the plaintiffs applied for summary judgment underO 14 r 1 to be entered against the defendants for the sum of $23,150,331and $700 costs. On 8 May 1985, the defendants applied for an order that allfurther proceedings in the action be stayed pursuant to s 7 of the

paginator.book Page 505 Sunday, September 20, 2009 1:00 AM

506 SINGAPORE LAW REPORTS (REISSUE) [1985–1986]  SLR(R)

Arbitration Act (Cap 16, 1970 Rev Ed), the plaintiffs and the defendantshaving by the subcontract agreed to refer to arbitration the matter inrespect of which this action is brought, and for costs.

6 The two applications were heard together by the senior assistantregistrar and, after two days of hearing, on 20 August 1985, he made noorder on the application of the plaintiffs for summary judgment under O 14r 1, and on the application of the defendants he ordered that all furtherproceedings in this action be stayed pursuant to s 7 of the Arbitration Acton condition that the defendants furnish within 30 days from 20 August1985, security in the form of a banker’s guarantee for the sum of $7.5m, indefault thereof judgment be entered for the plaintiffs in that sum and thatthe costs of and occasioned by the action be reserved with liberty to theparties to restore the application.

7 The plaintiffs now appeal against both orders and the defendantsappeal against the condition in the second order.

Application under O 14 r 1

8 The plaintiffs say that their claim for summary judgment totalling$23,150,331 is made up as follows:

(a) a sum of $1,822,724 which is the amount included in certificatenumber 18 issued by the architects dated 14 December 1984;

(b) a sum of $2,696,457 which is the amount included in certificatenumber 19 issued by the architects dated 15 January 1985;

(c) a sum of $2,007,012 due under their payment applicationnumber 20; and

(d) a sum of $16,624,138 due as costs of materials or goods properlyordered for the subcontract works.

9 The plaintiffs ask for summary judgment in respect of the claimsunder (a) and (b). The plaintiffs are now prepared to have the claim under(c) referred to arbitration on condition that sufficient security is ordered tobe furnished. As regards the claim under (d) the sum is now reduced to$14,942,560 as two suppliers have settled their claims with the plaintiffs andthe plaintiffs are now prepared to have the claim referred to arbitration oncondition that sufficient security is ordered to be furnished.

10 The plaintiffs submit that their claim for summary judgment is inrespect of sums which are indisputably due to them now, sums to whichthere can be no dispute.

11 It is useful to give the background facts. The plaintiffs are mechanicaland electrical specialist subcontractors. The plaintiffs’ works commenced inthe middle of 1983, before the subcontract documents were signed and the

paginator.book Page 506 Sunday, September 20, 2009 1:00 AM

[1985–1986]  SLR(R) Woh Hup (Pte) Ltd v Turner (East Asia) Pte Ltd 507

subcontract ran its normal course until the end of 1984. The plaintiffs madeapplication for payment on “Progress Claim” forms. These were valued bythe services engineers named in the subcontract, JR Preston & Partners(“the engineers”). The engineers’ valuations were in turn submitted to theappointed quantity surveyors, Rider Hunt Levett and Bailey (“the quantitysurveyors”) who in turn would recommend payment to the architects –Chua Ka Seng and Partners (“the architects”).

12 The architects issued “Certificates of Payment” as the contract worksproceeded which were honoured by the employer and paid to thedefendants who in turn paid the plaintiffs that portion of the certified sumswhich were due to them in respect of the subcontract. The certificates werein standard terms and attached to these were the quantity surveyors’valuation statements. All the forms were provided for in the main contract.

13 Everything went normally until certificate number 18 was issued on14 December 1984. By that time a substantial dispute had arisen betweenthe defendants and the employer. After receipt of the notice of terminationof the main contract the plaintiffs had to carry on work to finish off untilthe time they applied for payment under application number 20.

14 The plaintiffs’ claims are for sums due under cl 21 of the subcontractwhich provides:

DETERMINATION OF THE MAIN CONTRACT

If for any reason the Contractor’s employment under the MainContract is determined (whether by the Contractor or by the Employerand whether due to any default of the Contractor or otherwise), thenthe employment of the Subcontractor under this Subcontract shallthereupon also determine and the Subcontractor shall be entitled to bepaid:

(i) The value of Subcontract Works completed at the date of suchdetermination, such value to be calculated according to cl 10 hereof.

(ii) The value of work begun and executed but not completed at thedate of such determination, such value to be calculated according tocl 10 hereof.

(iii) The value of any unfixed materials and goods delivered upon theSite for use in the Subcontract Works, the property in which has passedto the Employer under the terms of the Main Contract.

(iv) The cost of materials or goods properly ordered for theSubcontract Works for which the Subcontractor shall have paid or ofwhich he is legally bound to accept delivery. On such payment by theContractor any materials or goods so paid for shall become theproperty of the Contractor.

(v) Any reasonable cost of removal from the Site of his temporarybuildings, plant, machinery, appliances, goods and materials.

paginator.book Page 507 Sunday, September 20, 2009 1:00 AM

508 SINGAPORE LAW REPORTS (REISSUE) [1985–1986]  SLR(R)

15 The relevant provisions of cl 10 read:

SUBCONTRACT SUM — VALUATION OF VARIATIONS

(a) The price of the Subcontract Works (hereinafter referred to as‘the Subcontract Sum’) shall be the sum named in or determined by theprovisions of Pt IV App I to this Subcontract (and) such other sum asshall become payable by reason of any authorised variations or amountascertained under cl 8(h) hereof.

(b) The valuation of all variations authorised under cl 7 hereof andall work executed by the Subcontractor in accordance with theinstructions of the Contractor as to the expenditure of provisionalsums or provisional items shall be determined by the Contractor andwhere such valuations shall require any measurement or re-measurement of the Subcontract Works the Contractor shall give tothe Subcontractor an opportunity of being present at the time of suchmeasurement and of taking such notes and measurements as theSubcontractor may require. Such valuation (unless otherwise agreed bythe Contractor and Subcontractor) shall be in accordance with thefollowing rules: –

(1) …

(2) …

(3) …

(c) Any amount ascertained under the provisions of sub-cl (b) shallbe added to or deducted from the Subcontract Sum.

16 The relevant provisions of cl 8(h) read:

(ii) If the regular progress of the Subcontract works is materiallyaffected by any act, omission or default of the Contractor, his servantsor agents, or any subcontractors employed on the Works theSubcontractor shall as soon as such material effect becomes apparentgive written notice thereof to the Contractor with details of any directloss or expense thereby caused to the Subcontractor for theContractor’s evaluation and the Subcontract Sum shall be adjusted bythe amount agreed upon between the Subcontractor and theContractor.

17 The submission of the defendants is as follows:

(a) Clause 21 has a condition precedent in that a valuationcalculated according to cl 10 is required before the plaintiffs areentitled to be paid and therefore the plaintiffs’ claim is prematuresince such valuation has not been made.

(b) The amount of $1,822,724 is not payable because of cl 11(b) ofthe subcontract.

(c) The architect’s certificates are not conclusive.

paginator.book Page 508 Sunday, September 20, 2009 1:00 AM

[1985–1986]  SLR(R) Woh Hup (Pte) Ltd v Turner (East Asia) Pte Ltd 509

(d) Both the amounts allegedly due under certificates numbers 18and 19 are the plaintiffs’ own calculations. They have failed to accountfor the gross deduction of $2,840,000 from certificates numbers 18and 19.

(e) The claim of $2,007,012 is without verification or certification ofthe engineers or architects.

(f) The claim under the suppliers’ contracts need investigation asthe goods may not be properly ordered.

(g) The defendants have a counterclaim in that:

(i) materials have been removed by plaintiffs;

(ii) no as-built drawings have been supplied; and

(iii) work by the plaintiffs’ subcontractors Fu Tsu weredefective. (The defendants now concede that Fu Tsu were notthe plaintiffs’ subcontractors.)

18 There are actually no certificates for the sums of $1,822,724 and$2,696,457. The certificates numbers 18 and 19 are certificates in which thearchitects certified a global figure for all moneys which they consideredfairly represented the amounts due to the defendants. The plaintiffs beingone of the subcontractors would have their claims falling within the globalcertificates.

19 Mr Wong, for the defendants, submits that the plaintiffs’ case mustfail or succeed on whether or not the condition precedent set out in cl 21has been fulfilled. He says the condition precedent is the valuationcalculated according to cl 10.

20 His argument is shortly this. Under cl 21(i) it is provided that on thedetermination of the main contract the plaintiffs are entitled to be paid thevalue of the subcontract works completed at the date of such determination.How does one arrive at the value? It is to be found in the words “such valueto be calculated according to cl 10”. The value of the subcontract worksmust be calculated according to the method or formula set out in cl 10.

21 The heading of cl 10 reads:

Subcontract Sum – Valuation of Variations.

22 Mr Wong says that on the face of it it seems to apply to variations butone has to look at the word “valuation” rather than the word “variations”.This is because cl 10(b) sets out a formula for the valuation of variationsand if cl 21 is applicable then cl 10(b) is the valuation procedure that isenvisaged under cl 21 and is adopted for the purpose of valuing all theworks. He, therefore, submits that the figures appearing under certificatesnumbers 18 and 19 are not figures valued according to cl 10 and are not

paginator.book Page 509 Sunday, September 20, 2009 1:00 AM

510 SINGAPORE LAW REPORTS (REISSUE) [1985–1986]  SLR(R)

figures showing the true value of the works completed at the date ofdetermination. As there has been no valuation done under cl 21 theplaintiffs are not entitled to payment.

23 I am unable to accept Mr Wong’s submission. Clause 10 provides forthe valuation of the entire subcontract works, including the calculation ofthe value of the authorised variations. Interim certificates are the valuationof work done on account of the subcontract sum and represent a valuationcarried out in a manner consistent with cl 10. Because cl 10 provides acomplete code for the valuation of the subcontract works including thevaluation of authorised variations and amounts due under cl 8(h) it isexpressly referred to in cl 21(i) and cl 21(ii).

24 As Mr Giam for the plaintiffs says cl 21 does not talk of “valuation”; itsays “Value of the Subcontract Works completed” which is different from“Valuation”. Clause 21 says “to be calculated according to cl 10” and not “inaccordance with cl 10”. Works had already been done and it is not a casethat the works had to be revalued on determination of the subcontract as ifthey were variations. Nor is it a case that works had begun and executed butnot completed and have to be valued as if they were variations.

25 In the present case the value of the subcontract works completed atthe date of the determination of the subcontract has already been calculatedby the issue of certificates numbers 18 and 19.

26 Then Mr Wong says that the architects’ certificates are issued undercl 11 and that by cl 11(b) the defendants are under obligation to pay theplaintiffs only 14 days after the defendants themselves have been paid by theemployer, and that, since the defendants have not been paid, the plaintiffsare not entitled to be paid under the architects’ certificates.

27 I don’t think Mr Wong’s argument is correct.

28 Under cl 11(a) the defendants apply to the architects for certificate ofpayment, which certificate will include the total value of the subcontractworks done plus variations authorised and executed plus the amountsascertained under cl 8(h)(i) plus 75% of the value of materials and goodsdelivered upon the site for use in the subcontract works plus 75% of thevalue of off-site materials and goods for use in the subcontract works.

29 Clause 11(b) provides that within 14 days of the receipt by thedefendants of any interim payment from the employer the defendants shallnotify and pay to the plaintiffs “the value in respect of the sub-contractworks and in respect of any authorised variations thereof and amountsascertained under cl 8(h) hereof” less retention money and the amountspreviously paid.

30 Clauses 21(i) and 21(ii) simply provide calculations according tocl 10, which means in a manner consistent with cl 10. That means that in

paginator.book Page 510 Sunday, September 20, 2009 1:00 AM

[1985–1986]  SLR(R) Woh Hup (Pte) Ltd v Turner (East Asia) Pte Ltd 511

the case of determination of the subcontract not the full subcontract sum ispayable but only the value of the works up to the point of determination.Interim certificates are the result of the valuation of the works executed upto a point on account of the subcontract sum and such valuation isnecessarily carried out in a manner consistent with cl 10. Clause 10provides a complete code of valuation of the subcontract sum including thevaluation of variations and it provides the machinery for valuation by thearchitects when they issue interim certificates. The interim certificate is notissued under cl 11 but under the main contract. The plaintiffs are notclaiming under certificates numbers 18 and 19 but they are evidence of theamounts due to them under cl 21 as the value of the works that had beendone. It is therefore wrong to say that the certificates were issued undercl 11 as if they were valued differently and that only when the defendantsare paid will the plaintiffs be paid. The interim certificates are issuedaccording to the valuation method set out in cl 10 and that is concreteevidence that works worth that amount has been done up to that date.

31 In the case of determination of the subcontract there is a lapse of timebetween the last certificate and the date of determination when work wascarried out by the plaintiffs. The plaintiffs have in fact done more work afterthe last certificate up to the date of determination. This amount has notbeen calculated by the architects as yet but the two sums claimed by theplaintiffs are indisputably due. The plaintiffs are entitled under cll 21(i) and21(ii) to be paid those sums.

32 The question that next arises is should judgment be given for theplaintiffs in the sums of $1,822,724 and $2,696,457.

33 Mr Giam urges me to follow the case of Ellis Mechanical Services vWates Construction (1976) 2 Build LR 57; [1978] 1 Lloyd’s Rep 33 andorder that final judgment be entered against the defendants for the sums of$1,822,724 and $2,696,457.

34 Ellis’s case concerned a big building project at the old HendonAerodrome. Two local authorities, the Greater London Council (“GLC”)and the Barnet Council, combined in it. The GLC were to build a largenumber of dwelling houses for individuals to occupy and the BarnetCouncil were to build a comprehensive school and other buildings for theuse of the community as a whole. Each of those two local authoritiesemployed Wates Construction Ltd as the main contractors for each of thecontracts. Wates Construction Ltd in their turn employed as subcontractorsEllis Mechanical Services Ltd. Ellis were to provide the heating system andall the mechanical services which were required for both the contracts. Themain contract between the GLC and Wates granted in June 1970 was for anestimated sum of £9½m. The subcontract with regard to that by Wates toEllis was for over £1m. The work went ahead; but on 22 February 1974 theWates and GLC contract was determined. It came to an end, each of the two

paginator.book Page 511 Sunday, September 20, 2009 1:00 AM

512 SINGAPORE LAW REPORTS (REISSUE) [1985–1986]  SLR(R)

parties saying that the other had repudiated it. That was no concern of Ellisexcept in so far as it entitled them to be paid.

35 The main contract and the subcontract were in the usual RIBA formwith some slight variations, but on this main contract being determined, thesubcontractors became entitled to be paid in accordance with cl 21 of thesubcontract (which is similar to cl 21 of the subcontract).

36 Ellis had been doing the works to the order and under the supervisionof the GLC architects. Certificates had been given by the GLC architectsand engineers and interim certificates by the architects under the GLC wereissued.

37 Ellis claimed four items: (a) the value of the subcontract works in sofar as they had been completed at the date of determination; (b) the value ofthe work begun and executed, but not completed; (c) the value of theunfixed materials on the site, in which the property passed to the employer;and (d) the cost of materials off-site ordered, for which the subcontractorshad paid or been charged. Ellis asked for payment. Wates refused to pay.

38 Ellis sued for the sums due and proceeded under O 14 for summaryjudgment. They did not claim for the whole amount. The master gavesummary judgment for £52,437, being the retention money held in respectof Ellis’s work and stayed the rest of the action pending arbitration. Onappeal Kilner-Brown J set aside the judgment for £52,437 and referred thewhole matter to arbitration. Ellis appealed to the Court of Appeal.

39 Lord Denning MR in the course of his judgment said (at 60–61):

… it is quite plain on cl 21 that the sub-contractor was entitled to bepaid in effect for all the work they had done and all the materials theyhad there available at the date 22 February 1974.

There is a point in the contract which I might mention upon this.There is a general arbitration clause. Any dispute or difference arisingon the matter is to go to arbitration clause. It seems to me that if a casecomes before the court in which, although a sum is not exactlyquantified and although it is not admitted, nevertheless the court isable, on an application of this kind, to give summary judgment forsuch sum as appears to be indisputably due, and to refer the balance toarbitration. The defendants cannot insist on the whole going toarbitration by simply saying that there is a difference or a dispute aboutit. If the court sees that there is a sum which is indisputably due, thenthe court can give judgment for that sum and let the rest go toarbitration, as indeed the master did here.

40 At 62, after dealing with the argument of counsel for Wates,Lord Denning said:

paginator.book Page 512 Sunday, September 20, 2009 1:00 AM

[1985–1986]  SLR(R) Woh Hup (Pte) Ltd v Turner (East Asia) Pte Ltd 513

That is all very well; but, as all of us with experience of building andconstruction cases are aware, there is inevitably something due. Inmost cases it can be said with certainty that £x is due. In such a case thecourt gives judgment for the £x and gives leave to defend as to thebalance. Otherwise it would mean that the builders and contractorcould be kept out of a great portion of their money indefinitely by theemployers simply saying ‘I want to investigate the accounts’. Theemployer could force the builder into bankruptcy by saying that hewants to sort out the accounts. So the court does not allow a builder orcontractor to be kept out of the whole of his money on such an excuse.It gives judgment for such sums as it is reasonably seen is due.

41 Lawton LJ agreed with the judgment delivered by the Master of theRolls and he said (at 63):

One of the perils of commercial life for sub-contractors in the buildingtrade is that there may develop between the main contractor and thebuilding owner a serious dispute which leads to one or other of themrepudiating the main contract. When that happens the lifeblood of thebuilding trade, namely money, stops. The sub-contractor finds himselfwithout the periodic payments which he receives, subject to retentionmoney, on the architect’s certificate.

Under the form of contract used in this case, and used in many cases ofthis kind, all the sub-contractor can do is to look to the maincontractor for payment for the work that he has done, and thematerials he has supplied under cl 21 of that contract.

If the main contractor can turn round, as the main contractor has donein this case, and say ‘Well, I don’t accept your account; therefore thereis a dispute’, that dispute must be referred to arbitration and thearbitration must take its ordinary long and tedious course. Then thesub-contractor is put into considerable difficulties; he is deprived of hiscommercial lifeblood. It seems to me that the administration of justicein our courts should do all it can to restore that lifeblood as quickly aspossible. One of the demerits of our system of justice is that in this classof case, because of our rules of procedure, an arbitration under abuilding contract of this size is likely to take years. For example, MrKeating said that the defendants would be entitled to have discovery ofall the documents. Indeed they would. He said that they would beentitled to examine them and see what they could find from them;indeed they would. That would take a very long time and the delaymight do injustice to the plaintiffs.

The courts are aware of what happens in these building disputes; casesgo either to arbitration or before an official referee; they drag on andon and on; the cash flow is held up. In the majority of cases, becauseone party or the other cannot wait any longer for the money, there issome kind of compromise, very often not based on the justice of thecase but on the financial situation of one of the parties. That sort ofresult is to be avoided if possible. In my judgment it can be avoided if

paginator.book Page 513 Sunday, September 20, 2009 1:00 AM

514 SINGAPORE LAW REPORTS (REISSUE) [1985–1986]  SLR(R)

the courts make a robust approach, as the master did in this case, to thejurisdiction under O 14.

42 Bridge LJ in his judgment said (at 65):

For my part I would hesitate to use the epithet ‘robust’. That might bethought to imply that the court’s approach to a case of this kind,because of the undoubted difficulties and injustices which can arisefrom the length of building arbitrations, ought to lean heavily in favourof the claimant builder or sub-contractor. To my mind the test to beapplied in such a case is perfectly clear. The question to be asked is: is itestablished beyond reasonable doubt by the evidence before the courtthat at least £x is presently due from the defendant to the plaintiff? If itis, then judgment should be given for the plaintiff for that sum,whatever £x may be; and in a case where, as here, there is an arbitrationclause, the remainder in dispute should go to arbitration.

The reason why arbitration should not be extended to cover the area ofthe £x is indeed because there is no issue, or difference, referable toarbitration in respect of that amount.

43 The effect of the judgment of the Court of Appeal was that judgmentwas entered for Ellis in the sum of £52,437 and the rest of the action wasstayed and was referred to arbitration.

44 Following Ellis’s case ([33] supra) I am of the view that the plaintiffsare entitled to judgment in the sum of $1,822,724 and $2,696,457.

45 As to the third item of the plaintiffs’ claim of $2,007,012, Mr Giamsays that would have resulted in certificate number 20 if the main contracthad not been determined. He says that the plaintiffs would not pursue thisclaim for judgment as it has not been certified but he submits and asks forsecurity to be furnished for 50% of the claim by a banker’s guarantee.

46 As to the last claim for $14,942,560, which relates to goods andmaterials ordered for the subcontract works and supplied by the plaintiffs’suppliers, Mr Giam says that some of these goods on-site and off-site havealready been certified under certificates numbers 18 and 19 and theplaintiffs are entitled to judgment. As to the goods and materials notcertified, they were already ordered and the plaintiffs were legally bound toaccept delivery.

47 Mr Giam says that the plaintiffs are not asking for judgment for the$14,942,560 but submits that the senior assistant registrar’s decisionordering security amounting to 50% of the total claim under this head is acorrect decision.

48 Mr Wong in reply to Mr Giam says this as regards the plaintiffs’ thirdhead of claim for $2,007,012. This is not an amount which falls into anycertificate at all. It is an amount for which the plaintiffs have asked paymentof as being the value of works done up to the date of their application. At

paginator.book Page 514 Sunday, September 20, 2009 1:00 AM

[1985–1986]  SLR(R) Woh Hup (Pte) Ltd v Turner (East Asia) Pte Ltd 515

the hearing before the senior assistant registrar the plaintiffs reduced theirclaim for judgment to $947,605 and agreed that the balance be referred toarbitration. Now before me the plaintiffs are not asking for judgment forthe entire sum and instead ask the defendants to provide security for thesum claimed.

49 As to the plaintiffs’ last head of claim for costs of materials and goodsordered for the subcontract works, Mr Wong has this to say. The claim isfor $16,624,138 in the statement of claim and now reduced to $14,942,560as two suppliers have settled their claims with the plaintiffs. This sum willprobably be reduced further as there is evidence that the plaintiffs are, quiteproperly, seeking to mitigate damages by trying to reduce their liabilities. Ifthe plaintiffs are successful in their negotiations with their suppliers thenthe sum claimed by the plaintiffs would be less than $14.9m and wouldprobably be reduced to an indeterminate sum.

50 Mr Giam submits that the correct order to make on the plaintiffs’application under O 14 is that judgment be entered against the defendantsfor the sum of $4,519,181 and $700 costs and that the defendants do haveleave to defend the balance of the plaintiffs’ claim amounting to$16,949,572 upon the condition that the defendants do furnish security byway of a banker’s guarantee in the sum of $9,000,000, within 14 days fromthe date of the order, failing which the plaintiffs may be at liberty to enterfinal judgment against the defendants in the sum $9,000,000 and thedefendants may defend the action as to the residue of the plaintiffs’ claim.

51 Mr Wong submits that the defendants should not be ordered toprovide security as asked for by the plaintiffs. As to the plaintiffs’ head ofclaim for costs of materials and goods ordered for the subcontract works,Mr Wong says that the plaintiffs’ claim is wholly unsubstantiated. Further,materials already ordered as at the date of determination have in allprobability already been claimed by the plaintiffs in their application up toapplication number 20. The plaintiffs have not in these proceedings shownany documents which show the plaintiffs’ liabilities to pay for the materialsthe value of which is now being claimed. It is clear that there is no certaintyas to any amount that can be said to be indisputably due and that is why theplaintiffs quite rightly have not asked for judgment. There is no reason whythe defendants should be asked to furnish security.

52 Mr Wong says that the defendants have a counterclaim against theplaintiffs and one of the counterclaims is that the plaintiffs have removedmaterials from the site for which they had already been paid. A thoroughinvestigation of what had been removed or what had not been removed is amatter for the arbitration and not for the court.

53 Mr Wong further says that the plaintiffs do not deny that there aretriable disputes between the employer and the defendants and these triable

paginator.book Page 515 Sunday, September 20, 2009 1:00 AM

516 SINGAPORE LAW REPORTS (REISSUE) [1985–1986]  SLR(R)

disputes also involve the plaintiffs and it is only a matter of degree as to theplaintiffs’ involvement. He submits that the matter in dispute between theplaintiffs and the defendants should be referred to arbitration. In this caseyou have disputes involving different parties at different levels and if thereare separate proceedings involving some of the parties and not the othersthere may be inconsistent findings of facts in the two tribunals of the sameissues and that is a situation that should best be avoided. The defendants areproceeding in their arbitration against the employer. The plaintiffs have notat any time before the senior assistant registrar or before this courtcontended that the defendants’ defences and counterclaim are a sham. Thefurthest Mr Giam has gone is to say that the defences and the counterclaim“raised so far are weak and shadowy”. Even where the defences are shadowythe court will grant conditional leave to defend where there is no arbitrationclause but the court should not impose conditions where it grants a stay ofproceedings to allow the matter to go to arbitration. The court’s power toimpose conditions for granting leave to defend is expressly provided forunder O 14 whereas under s 7 of the Arbitration Act (Cap 16) no suchpower is provided at all.

54 There is substance in what Mr Wong says. As to the third and fourthheads of claim of the plaintiffs, I am satisfied that the defendants are notthrowing out vague and general allegations and that a thoroughinvestigation needs to be made. I am of the view that these two heads ofclaim should go for arbitration and that there should be a stay ofproceedings in respect of those two heads of claim.

55 Mr Giam says that the defendants should be ordered to providesecurity in the sum of $9,000,000 in respect of these two heads of claimamounting to $16,949,572.

56 The court’s power to impose conditions when granting leave todefend is expressly provided for under O 14. But where the court grants astay of proceedings under s 7 of the Arbitration Act no such power isprovided at all.

57 Mr Giam relies on Re Bjornstad and The Ouse Shipping Co [1924]2 KB 673. In that case two Norwegian subjects made contracts with anEnglish shipbuilding firm for the purchase of four ships. Each contractcontained an arbitration [clause]. The contracts are English contracts andthe Norwegians have provided an agent in England on whom process maybe served. They have dissolved partnership; and they desire to proceed toarbitration on the contract in England. The shipbuilders refuse to appointany arbitrator and the Norwegians apply to the court to appoint anarbitrator under s 5 of the Arbitration Act, 1889.

58 The master made an order appointing an arbitrator. The shipbuildersappealed and applied for an order that the purchasers should give security

paginator.book Page 516 Sunday, September 20, 2009 1:00 AM

[1985–1986]  SLR(R) Woh Hup (Pte) Ltd v Turner (East Asia) Pte Ltd 517

for costs. Talbot J dismissed the appeal but gave leave to appeal to the Courtof Appeal. It was held that on an application under s 5 of the ArbitrationAct 1889, to appoint an arbitrator the court has a discretion whether itshould or should not make the appointment and the court has power toorder security for costs of the arbitration.

59 That case does not help the plaintiffs. It is not a case of an applicationfor judgment under O 14 and furthermore the applicants in that case wereforeigners out of the jurisdiction of the court. If they were bringing anaction they would as a matter of course be ordered to give security for costs.The court, therefore, refused to appoint an arbitrator until the necessarysecurity was found.

60 The exercise of the jurisdiction to stay proceedings is discretionary,but if the court is satisfied that there is no sufficient reason why the mattershould not be referred to arbitration in accordance with the agreement thecourt will seldom refuse a stay (see Halsbury’s Laws of England vol 2(Butterworths, 4th Ed) at para 555). No authority has been cited byMr Giam where a stay of proceedings was granted on condition that thedefendant provide security for the sum claimed when the party seeking thearbitration was not a foreigner.

61 I am of the view that in this case the stay of proceedings should begranted without condition.

62 In the result I set aside the two orders of the senior assistant registrarmade on 20 August 1985 and I make the following orders:

(a) On the application of the plaintiffs in Summons in ChambersNo 4208 of 1985 – final judgment be entered against the defendant forthe sum of $4,519,181 and $700 costs and the balance of the plaintiffs’claim amounting to $16,949,572 be stayed pending arbitration.

(b) On the application of the defendants in Summons in ChambersNo 4446 of 1985 – all further proceedings in this action relating to thebalance of the plaintiffs’ claim amounting to $16,949,572 be stayedpursuant to s 7 of the Arbitration Act (Cap 16).

63 I will now hear the parties on the question of costs and ancillaryorders.

Headnoted by Melanie Chng Ai Ling.

paginator.book Page 517 Sunday, September 20, 2009 1:00 AM