What is a WBS?

PMCoE Lunch & Learn – October 29, 2015

Page 2: What is a WBS? - PMI Metrolina Chapter - Home Pagepmi-metrolina.com/downloads/Lunch_and_Learn/pmcoelnlwbs.pdf · PMCoE Lunch & Learn 7 What is the Work Breakdown Structure? Level

Safety

The PMCoE

Why Lunch -n- Learns

10/29/2015 PMCoE Lunch & Learn 2

Page 3: What is a WBS? - PMI Metrolina Chapter - Home Pagepmi-metrolina.com/downloads/Lunch_and_Learn/pmcoelnlwbs.pdf · PMCoE Lunch & Learn 7 What is the Work Breakdown Structure? Level

PMCoE Lunch & Learn 3

Topics Covered So Far. . .

Understanding Project KPIs

Earned Value Management

Basics

What is the PMCoE

Scope Management

WBS

10/29/2015

Page 4: What is a WBS? - PMI Metrolina Chapter - Home Pagepmi-metrolina.com/downloads/Lunch_and_Learn/pmcoelnlwbs.pdf · PMCoE Lunch & Learn 7 What is the Work Breakdown Structure? Level

PMCoE Lunch & Learn 4

Project Scope Management

Agreement on What the Project is

About (big picture)

Collect Scope Requirements

Understanding the Particulars

(details)

Define Scope

Breaking Down the Activities

(the work)

Create WBS

10/29/2015

Page 5: What is a WBS? - PMI Metrolina Chapter - Home Pagepmi-metrolina.com/downloads/Lunch_and_Learn/pmcoelnlwbs.pdf · PMCoE Lunch & Learn 7 What is the Work Breakdown Structure? Level

PMCoE Lunch & Learn 5

What is the Work Breakdown Structure?

Visual Representation of the Deliverables and Corresponding

Activities to ensure their Completion

• Perform thorough Planning • Cost, Time Performance • Monitor & Report • Assign Resources & Responsibilities

Project

Deliverable #1

Activity

Sub-Activity

Sub-Task

Sub-Activity

Sub-Task

Deliverable #2

Activity Activity

Sub-Activity

Sub-Activity

Sub-Activity

Deliverable #3

Activity

Sub-Activity

10/29/2015

Page 6: What is a WBS? - PMI Metrolina Chapter - Home Pagepmi-metrolina.com/downloads/Lunch_and_Learn/pmcoelnlwbs.pdf · PMCoE Lunch & Learn 7 What is the Work Breakdown Structure? Level

PMCoE Lunch & Learn 6

What is the Work Breakdown Structure?

Home Construction

Complete Plumbing

Finishing

Masonry Work

External Finishes

Foundation External Internal

Excavate

Frame Home

Install Roofing

Install Lighting

Build Deck

Complete Landscaping

Walls

Beams

Joists

Pour Concrete

Cure & Strip Forms

Lay Cinder Block

Lay Home Masonry

Lay Sidewalk Brick

Lay Patio Stone

Install Electrical

Rough-in Electrical

Install and Terminate

Install HVAC

Rough-in Plumbing

Install Fixtures & Trim

Test and Clean

Complete Punch list

Pass Inspections

10/29/2015

Page 7: What is a WBS? - PMI Metrolina Chapter - Home Pagepmi-metrolina.com/downloads/Lunch_and_Learn/pmcoelnlwbs.pdf · PMCoE Lunch & Learn 7 What is the Work Breakdown Structure? Level

PMCoE Lunch & Learn 7

What is the Work Breakdown Structure?

Level 1 Level 2 Level 3 Level 4

Home Construction Foundation Excavate Pour Concrete

Lay Cinder Block

Cure & Strip Forms

Frame Home Frame Walls

Attach Beams

Mount Joists

External Masonry Work Lay Home Masonry

Lay Sidewalk Brick

Lay Patio Stone

External Finishes Install Roofing

Install Lighting

Build Deck

Complete Landscaping

Internal Install Electrical Rough-in Electrical

Install and Terminate

Install HVAC

Complete Plumbing Rough-in Plumbing

Install Fixtures & Trim

Test and Clean

Finishing Complete Punch list

Pass Inspections

10/29/2015

Page 8: What is a WBS? - PMI Metrolina Chapter - Home Pagepmi-metrolina.com/downloads/Lunch_and_Learn/pmcoelnlwbs.pdf · PMCoE Lunch & Learn 7 What is the Work Breakdown Structure? Level

PMCoE Lunch & Learn 8

WBS: A Critical Component of Every Project

WBS

Gather Requirements

Define Scope

Other

10/29/2015

Page 9: What is a WBS? - PMI Metrolina Chapter - Home Pagepmi-metrolina.com/downloads/Lunch_and_Learn/pmcoelnlwbs.pdf · PMCoE Lunch & Learn 7 What is the Work Breakdown Structure? Level

4/6/2016 PMCoE Lunch & Learn 9

WBS: A Critical Component of Every Project

WBS

Gather Requirements

Define Scope

Other

Project Management Plan

Defined Activities

Accurate Schedule Estimates

Accurate Budget Estimates

Risk Identification

Page 10: What is a WBS? - PMI Metrolina Chapter - Home Pagepmi-metrolina.com/downloads/Lunch_and_Learn/pmcoelnlwbs.pdf · PMCoE Lunch & Learn 7 What is the Work Breakdown Structure? Level

4/6/2016 PMCoE Lunch & Learn 10

WBS: A Critical Component of Every Project

Gather Requirements

Define Scope

Other

Project Management Plan

Defined Activities

Accurate Schedule Estimates

Accurate Budget Estimates

Risk Identification

Validate Scope

WBS

Page 11: What is a WBS? - PMI Metrolina Chapter - Home Pagepmi-metrolina.com/downloads/Lunch_and_Learn/pmcoelnlwbs.pdf · PMCoE Lunch & Learn 7 What is the Work Breakdown Structure? Level

PMCoE Lunch & Learn 11

WBS Development

Project

Deliverable #1

Activity

Sub-Activity

Sub-Task

Sub-Activity

Sub-Task

Deliverable #2

Activity Activity

Sub-Activity

Sub-Activity

Sub-Activity

Deliverable #3

Activity

Sub-Activity

10/29/2015

Deliverable/Phase

Nouns; “THE”

Activities/Tasks

Verbs; Actions broken down to ‘estimable’ tasks

Utilize the TEAM; SMEs, etc.

Page 12: What is a WBS? - PMI Metrolina Chapter - Home Pagepmi-metrolina.com/downloads/Lunch_and_Learn/pmcoelnlwbs.pdf · PMCoE Lunch & Learn 7 What is the Work Breakdown Structure? Level

PDUs: email Jennifer Baker: [email protected]

WBS eLearning Module: PMWBS2

Classroom: Project Management: the Duke Energy Way - PMTPM

10/29/2015 PMCoE Lunch & Learn 12

Further Information

Examples: [email protected]