Upload
tracy-lounds
View
218
Download
2
Embed Size (px)
Citation preview
Agenda
• Preconstruction Services– Brian Toevs, PE
• Construction Services– Rusty Ross, PE, LEEDTM, CxA
• Client Relationship– Mark Leafstedt, PE CCP CxA
Commissioning Process
Project Timeline
PLANNING DESIGN CONSTRUCTION ACCEPTANCE OPERATIONS
Design Intent/ Owners Project Requirements
Functional Testing
CxReport
O & M Document Review
Construction Checklists
Submittal Review
Basis of DesignReview
SpecReview
Design DocumentReview
TrainingReview
SeasonalTesting
WarrantyReview
Pre-Functional Testing
Start-up
Owner’s Requirements
•Owners need help defining their needs We can help
•Get in early - During Predesign•Attend meetings during Schematic Phase•Attend more than one meeting•Be an active member of the team•Write the OPR for the owner
Owner’s Requirements
• Help the Architect write the OPR
• Initiate 1st draft of the Basis of Design Then turn it over to the designers
• Be Proactive, Invite your self to the party
OR
• Better yet - have your own party
Owner’s Requirements
Have a “Core Values” party
• Participants should Include:– Owner– User Group Members and Leaders– Maintenance staff– Architect / Engineer– Contractors / CM
• Plan for ½ to full day, for the exercise
Owner’s Requirements
• Participants are educated• We get "buy in"• Educational process accelerated• Decisions verified• Adversity diminished• Nuances of organization learned• Design process expedited
Remember: The OPR is a non technical document, that describes what needs to happen for the Owner to call this project a success.
Owner’s Requirements
Small groups to work out concepts
• Get input up front• Un-Ravel the Owners
Requirements• Eliminate Preconceived Ideas
Have Break-out Sessions
• Ask questions• Unpack issues • Work through ideas• Discard bad ideas
Create Concepts for discussion
Owner’s Requirements
• Present Ideas to group• Not Complete Designs• Better Direction for team• Owner Requirements better DefinedTwo Solutions
Existing Conditions
Design Review
• Minimum-Review Systems Commissioned
• Best Practice Review Should Include:– Mechanical– Electrical – Architectural– Specifications– Coordination among trades
Design Review
• To do a good HVAC review you have to look at the Architecture
• Many HVAC problems are Architectural Problems
• High performance buildings are failing:– Designing smaller HVAC systems– Normal Architectural Detailing
No details on this project address acoustical corrugated decking
While this detail does not show it, there is
batts insulation required under the decking
Acoustical decking allows air to pass into building on both sides of the corrugations
Batts insulation won’t seal the ends, only filter the air
Roof Insulation
Corrugated Acoustical Roof Decking
Batts Insulation
Concrete Block Wall Air Pathways
Thermal Envelop ?
If the Architectural details are unclear the contractor has free
reign to do as much or as little as they want
Cx Specifications
• We’re not the designers but we can help
• Cx spec writing is more than writing Cx specs– Review Division 1 specs– Review Mechanical specs – Review Electrical specs– Review / Write / Edit Cx Specs
Cx Specifications
• Request electronic specifications in electronic format, i.e. MS Word, Word Perfect
• Edit specs with “Track Changes”
• Return electronic specs to designer, for review and approval– Engineer or Architect-of-record owns the
specs, we are only making suggestions
Cx Specifications
• Review Division 1 specs:– Review submittal requirements
• Add submittal requirements for Commissioning• Review O&M Requirements, modify submittal date to be just
after submittal approval
– Review payment application requirements• Tie payment application to completion of checklist tracking
form
– Review substantial completion requirements• Tie Cx completion to substantial completion
– Write Division 1 Cx Requirements Spec
Cx Specifications
• Review Mechanical Specs:– Edit general requirements to reference Cx– Edit Controls specs
• Review quality assurance requirements to be more Cx friendly
• Tighten-up contractor qualifications – List specific individuals assigned to project– Temporary programming / global commands– Trending requirements / memory availability– instrument calibrations
Cx Specifications
• Review Mechanical Specs:– Edit TAB Specs
• Review quality assurance requirements to be more Cx friendly
• Tighten-up contractor qualifications– List specific individuals assigned to project
– Write the Mechanical Cx requirements spec– Develop SVC sheets and checklist tracking
form– Write the Mechanical testing requirements
Bidding
• Cx Plan needs to be specific enough to provide guidance but open enough for updating
• Cx Plan should mirror the spec requirements
• Keep it short, 15 to 20 pages plus diagrams
• Define flow of Cx Process, documentation, et cetera. Use Flow diagrams
Bidding
To: System Readiness
Cx Coordination Meeting
Update Cx Plan
Review Contractor Schedule
CxA to Receive
Approved
Shop Drawing Submittals
EOMM and SOMM Submittal
Architect Will Review and Approve
EOMM and SOMM provided to CxA
Review Construction Checklist and Update as Required
Architect and Owner Will Review and Approve
Develop Functional Test Procedures
Startup
Witnesses Construction Checklist Completion
Equipment Training Plan Submittal
Completed Checklists Submitted
Equipment Training Sessions
CxA Will Review and Approve
To: Acceptance
System Readiness
Commissioning Process Flow Chart – Construction Phase
Bidding
Acceptance
Systems Training Sessions
Pass
FT’s Performed Reports Written
Functional Completion
Deficiency Resolution
No
Yes
To: Warranty & Deferred Testing
Warranty Period and Operations Review
Deficiency Resolution
Deferred FT’s Pass
Final Cx Report
No
Yes
Warranty and Deferred Testing
Commissioning Process Flow Chart – Construction Phase
Construction Services
• Construction Phase– Document Installation– Prepare for acceptance phase
• Acceptance Phase– Functional testing– Owner training– Final report/systems manual
• Post Occupancy and Warranty– Opposed season functional testing– Warranty review
Construction Services
• Construction Phase– KO meeting for all team members – Review shops
• Update Cx plan, PFCs and FPTs
– Integrate Cx into construction schedule– Plan for owner preparation
• Training – Develop execution plan and schedule
• Record Documents – Review as project progresses
• O&Ms/Systems manual – Available early
– Document installation – execute PFCs
Prefunctional Checklists (PFCs)Chilled Water Piping yes/no
Humidifier Piping
There is adequate room to pull the chilled water coil per M3.3A
Piping arrangement per the detail: CHS hdr - iso valve, pete's plug, thermometer; coil branch - flange, offset connection for coil pull, B&G circ setter, pete's plug, gauge cock, coil, pete's plug, gauge cock, flange, offset; return hdr - pete's plug, con
Piping system properly pressure tested for 6 hours at 125PSI per 15050-3.09
Piping system cleaned and properly flushed 15050-3.08
Piping system properly pressure tested for 6 hours at 125PSI per 15050-3.09
Steam piping 2" per sched on M1.1A
Chilled water coil manual air vents installed per coil per the detail on M5.1A
Chilled water coil drains installed per coil per the detail on M5.1A
Thermometers installed 9" 15515-2.02-K
CHS & R piping at the coil is 4 inch per the schedule on sheet M1.1A.
Piping: Iso valve, strainer, union, control valve, union, humidifier, condensate w/ dirtleg(w/ blow down valve). A cold condensate shut off sensor attached between the control valve & humidifier before the unit and downstream of the humidifier on the cond
Chilled water coil clean
Steam piping properly connected per the detail on M5.3A
Piping system blown down w/ 5PSI steam and condensate wasted for 8 hours per 15050-3.08
Chilled water piping installed per the detail on M5.1A
Master Deficiency List
Date
Item
#
EQUIP #
/Spec
Section
DATE
REVIEWEDFIV/ FPT/O&M DEFICIENCY RESP. ACTION TAKEN
DATE Cx
VERIFIED
1 Panel HCR2 8/9/2004 FIVThe electrical working clearance for Panel HCR2 is not per NEC 110. Panel LCR2 blocks the right portion of the panel width within the 42" reqmt.
CEC
2 Panel LCR2 8/9/2004 FIV
The electrical working clearance for Panel LCR2 is not per NEC 110. The conduits at the floor in front of the panel, penetrate the floor in front of the plane of the panel can.
CEC
3 Panel HN3 8/9/2004 FIV
The electrical working clearance for Panel HN3 may not be per NEC 110. The transformer and flexible conduits @ the floor must be 42" from the panel (exposed live parts).
CEC
4 Panel LCR5 8/9/2004 FIVThe electrical working clearance for Panel LCR5 is not per NEC 110. The adjacent panel can blocks the right portion of the panel width within the 36" reqmt.
CEC
5 AHU 1 8/9/2004 FIVThe chilled water coil pull is blocked by the header at the coil.
B&KFlanged connections have been provided in the piping above the coil for piping removal for coil pull.
JAH9/20/04
6 RF 5A 8/9/2004 FIVThe relief duct is tapped into the back of the 90 degree silencer.
B&KPCA
Relief duct tap into 90o silencer approved and designed by M&I Systems.
JAH9/20/04
7 RF 5A and B 8/9/2004 FIV
The FSDs at the floor entering the return (see sheet M406) are not accessible without dismantling a section of the fabricated return plenum. An access door is not shown to be installed.
B&KPCA
Removable access panels have been provided in the return plenum for access to FSDs.
JAH9/20/04
Master Deficiency List
February 3, 2005(latest deficiencies in bold text)
Construction Services
• Acceptance Phase– Start-up– Functional testing
• Verify controls
• Simple to complex
• Single to integrated
• Coordinate w/ subs – controls, T&B
– Owner training• Execute and monitor
• Systems training
– Final report/systems manual
Functional Performance Tests (FPTs)
Mode Test Procedure Expected Response Pass Y/N/NoteCommand the Chiller on by the EMS WCM-4 to lead 1. CHW pump started by EMS Note 3
2. CW isolation valve opens; CW pump starts (interlocked w/ CHP)3. Cooling tower isolation valve opens and CT is enabled
4. Chiller enabled by EMS
5. Chiller starts when water flows are proven
6. Chiller controls on internal chiller LCHW stpt
7. Valve in CWR modulates to control chiller condenser pressure
Staging sequence WCM 1 >WCM 2 >WCM 3 >WCM 4
Tons = .0417*GPM*(CHWRT-CHWRST)
1. SCHW flow from EMS __________ GPM Load _______ tons Note 4&72. When lead chiller is at 90% full load amps, lag chiller#1 begins start sequence after 15 minutes. YES
Staging sequence WCM 1 >WCM 2 >WCM 3 >WCM 4
Tons = .0417*GPM*(CHWRT-CHWRST)
1. SCHW flow from EMS __________ GPM Load _______ tons Note 4&72. When the average amperage of all operating chillers is above 90% full load amps, lag chiller#2 begins start sequence after 15 minutes.
YES
Open preheat valves to increase the load above the capacity of two chillers
Open preheat valves to increase the load above the capacity of one chiller
Construction Services
• Post Occupancy and Warranty– Opposed season functional testing
• Peak summer
• Peak winter
– Warranty review• Review building performance w/ owner & O&M staff
• Note any deficiencies
• Plan of action
Client Relationships
• WHO ARE THE CLIENTS?– Owner? General Contractor? A/E
Consultants?..............Yes– Does the client always hold the Cx contract?
• WHAT KIND OF CLIENTS?– Participative or Non-Involved?– Demanding or Relaxed?– Sophisticated or Not?– Clear on Cx Expectations or Not?
• HOW DO YOU HANDLE DIFFERENCES?
Client Relationships
• IMPORTANCE OF COMMUNICATION– Enlistment of an advocate– Prevent surprises– Build a cooperative environment– Reduce misunderstandings– Speed resolution– Must be clear, concise, factual, non-blaming– Professional use of all forms:
• Verbal or written• Cx documents
Client Relationships
• WHY DO WE DOCUMENT?– Communication– Set Expectations– Record and track events and results– Legacy
• WHAT MAKES OUR DOCUMENTATION DIFFERENT?– Independent Perspective– Detail– Resolution oriented rather than blame oriented
Client Relationships
• WHAT DEFICIENCIES DO YOU BRING TO THE CLIENT?– All? Cost impact ones? Design ones? Construction
ones? Long Term ones?– Are all logged issues actually deficiencies?
• HOW DO WE GET RESOLUTION?– Participate or pull away?– Resolve during or after discovery?– Get Client involved?– Can we reduce the number or deficiencies or time it
takes to resolve them?