20
27/05/2015 Dr. ing. Joris Lemmens What are the local system challenges? DSO point of view from Belgium

What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

27/05/2015

Dr. ing. Joris Lemmens

What are the local system challenges?

DSO point of view

from Belgium

Page 2: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

Introducing Infrax

1/06/2015 2

Utility in 4 disciplines Electricity distribution (MV & LV)

Natural gas distribution

Sewerage

Cable (TV, internet)

126 municipalities in Belgium

2.192.000 connections (Electricity+gas+sewerage+cable)

1.554 employees

778 million EUR turnover*

250 million EUR investments*

*(2013)

Page 3: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

Evolution of wind and PV generation in the Infrax distribution grid

1/06/2015 3

0

100

200

300

400

500

600

700

800

Installed PV capacity (MW)

0

50

100

150

200

250

300

Installed wind capacity (MW)

Page 4: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

The rise of RES and new technologies is changing the grid’s loading pattern

Wind and PV generation Direct: Infeed to the local grid (reverse power flows)

Indirect: Load follows production => demand peaks during “happy hour”

Electric vehicles (EV)

Heat pumps and airconditioning

1/06/2015 4

Challenge = Increased simultaneity Risk = Local grid congestion

Page 5: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

Conventional design rules for distribution grids

MV grid n-1 (switching required)

Simultaneity = 0.8

Constraint = Overload (S>Snom)

LV grid No redundancy

Simultaneity = 0.2–0.3

Constraint = Over- and undervoltage

1/06/2015 5

Preconditions (not valid anymore…) • Only load - no generation • Stochastic distribution of loads in time and place (low simultaneity)

Page 6: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

Evolution of distribution transformer load pattern due to PV and EV

1/06/2015 6

Infeed to MV grid in summer months

Page 7: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

Evolution of distribution transformer load pattern due to PV and EV

1/06/2015 7

7

EV charging peak in evening (after-work)

Infeed to MV grid due to PV generation at noon

Page 8: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

PV and wind characteristics

Required grid capacity is determined by peak consumption/generation

PV/wind power peaks have short duration

Low value in terms of energy content

High societal cost in terms of required grid capacity

Low utilization factor of grid assets = cost inefficient

1/06/2015 8

Last 20% power contains only 1-2% energy!

Page 9: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

Different solutions…

1/06/2015 9

Page 10: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

Conventional investments

1/06/2015 10

Grid reinforcement: New cables + transformers

Page 11: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

Incentives

1/06/2015 11

Feed-in tariff to encourage self-consumption

Capacity tariff to reduce peak demand/production

Page 12: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

Controllable grid assets

1/06/2015 12

Distribution transformer with on-load tap changer for voltage regulation

Storage

Voltage support with reactive power from PV inverters

Page 13: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

Example: Solving voltage problems in a rural LV grid with an OLTC

1/06/2015 13

3 long LV feeders (open air lines)

99 connections

140 kVA PV

Page 14: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

Voltage quality at feeder end

STAV-method (standard deviation and average per week)

1/06/2015 14

EN50160: 10 min avg values per week • 95% inside Unom+-10% • 100% inside Unom-15%+10%

1 point per week

boundary C-D = Norm

Page 15: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

Voltage quality at feeder end

1/06/2015 15

Significant improvement with OLTC

EN50160: 10 min avg values per week • 95% inside Unom+-10% • 100% inside Unom-15%+10%

1 point per week

boundary C-D = Norm

Page 16: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

Flexible loads/generation

1/06/2015 16

Demand-side management

Curtailment

Coordinated EV charging

Storage

Page 17: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

Flexibility: Solution or threat?

Balancing products R3DP and SDR (Elia)

Flex service providers (FSP) contract dispatchable loads and generation in the distribution grid

Flexibility services help Elia to keep global balance

Flexibility services can cause local problems due to the high simultaneity factor

1/06/2015 17

Network Flexibility Study (NFS)

• DSO checks if requested flex services cause congestion problems in the distribution grid

• Interval: • Now: Every 3 months • Future: Towards real-time?

Page 18: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

Smart or conventional? Which way to go?

Smart + Defer/avoid grid reinforcement

+ Better utilization of the existing grid infrastructure

-Relatively expensive

-More complex

-Uncertainty regarding security, reliability, lifetime,…

Conventional (cable) +High lifetime

+Relatively cheap

+More copper reduces losses

(not negligible!)

-Nuisance of works in public space

-Low utilization of grid capacity

1/06/2015 18

A DSO will only apply smart solutions if they prove to be feasible and cost-effective

Page 19: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

Conclusion

The rise of RES and new technologies has a big impact on the distribution grid’s loading pattern

The distribution grid was not designed for high simulaneity

At this moment, congestion is not problematic (yet) for the Infrax grids

Infrax invests in innovative projects to investigate the feasibility of smart solutions

Smart solutions are promissing, but conventional solutions (grid upgrades) have their benefits as well…

It is key to keep costs for society at an acceptable level

1/06/2015 19

Page 20: What are the local system challenges? · Evolution of wind and PV generation in the Infrax distribution grid 1/06/2015 3 0 100 200 300 400 500 600 700 800 Installed PV capacity Installed(MW)

Thank you for your attention

[email protected]

1/06/2015 20