14
Presented by: Dan Coyne, CHBWV March 27, 2013 West Valley Demonstration Project Phase I Decommissioning Project Status One Project. One Team. One Goal.

West Valley Demonstration Project Phase I Decommissioning ... · West Valley Demonstration Project Phase I Decommissioning Project Status ... Material (ACM) Removal – 100% ... Vit-OOS

  • Upload
    vuthuy

  • View
    216

  • Download
    1

Embed Size (px)

Citation preview

Page 1: West Valley Demonstration Project Phase I Decommissioning ... · West Valley Demonstration Project Phase I Decommissioning Project Status ... Material (ACM) Removal – 100% ... Vit-OOS

Presented by: Dan Coyne, CHBWV

March 27, 2013

West Valley Demonstration Project Phase I Decommissioning

Project Status

One Project. One Team. One Goal.

Page 2: West Valley Demonstration Project Phase I Decommissioning ... · West Valley Demonstration Project Phase I Decommissioning Project Status ... Material (ACM) Removal – 100% ... Vit-OOS

Safety Performance

•  CHBWV has worked 135 days without a lost-time work accident or illness

•  WVDP has worked approximately 184,402 work hours (136 days) without a lost-time work accident or illness

2

Page 3: West Valley Demonstration Project Phase I Decommissioning ... · West Valley Demonstration Project Phase I Decommissioning Project Status ... Material (ACM) Removal – 100% ... Vit-OOS

Milestone 1 Accomplishments

3

•  Completed 100% Design Review for the High-Level Waste (HLW) Storage System

Sample Storage Photo

Page 4: West Valley Demonstration Project Phase I Decommissioning ... · West Valley Demonstration Project Phase I Decommissioning Project Status ... Material (ACM) Removal – 100% ... Vit-OOS

•  DOE-WVDP and NYSERDA agencies agreed with the soil management plans and lay-down location; planning for pad spoils underway

•  Nuclear Assurance Corp. (NAC) awarded the fabrication of WVDP storage cask liners to subcontractor

•  Commenced bid package preparation for slab construction and roadway improvements

Milestone 1 Accomplishments

4

Page 5: West Valley Demonstration Project Phase I Decommissioning ... · West Valley Demonstration Project Phase I Decommissioning Project Status ... Material (ACM) Removal – 100% ... Vit-OOS

Milestone 1 Accomplishments

5

•  Canister Decontamination Test Plan issued/completed mockup of the canister dry vacuum

•  Finalizing Hanford return of grapple and welding equipment for significant savings

CPC PaR Wrist Repair Fabrication

Page 6: West Valley Demonstration Project Phase I Decommissioning ... · West Valley Demonstration Project Phase I Decommissioning Project Status ... Material (ACM) Removal – 100% ... Vit-OOS

Milestone 2 Accomplishments

•  Low-Level Waste (LLW) Sampling and Repackaging –  Three work packages were sampled in

the Waste Processing Area (WPA) in Lag Storage Area (LSA) -4 as follows: –  High-moisture work package 5 out of

5 samples have been collected. –  WPA Processing work package 33

samples out of 47 have been completed.

–  Ready to Ship to Vendor work package 28 out of 34 samples have been taken.

–  Characterization work package will begin sampling in March.

SR-13 Inspection

6

Page 7: West Valley Demonstration Project Phase I Decommissioning ... · West Valley Demonstration Project Phase I Decommissioning Project Status ... Material (ACM) Removal – 100% ... Vit-OOS

•  Continued evaluation and disposition of LLW containers stored outside –  Kistner box inspection does not indicate any

accumulation of water

Milestone 2 Accomplishments

Degrading Top of SP Box on LS 2 Hard Stand

7

Page 8: West Valley Demonstration Project Phase I Decommissioning ... · West Valley Demonstration Project Phase I Decommissioning Project Status ... Material (ACM) Removal – 100% ... Vit-OOS

Main Plant Process Building (MPPB) - Deactivation

  Radio/Analytical Chem Lab – Asbestos Containing Material (ACM) Removal – 100% Complete

  Liquid Waste Cell – Interference Removal in Overhead of Lower Extraction Aisle and Chemical Operating Aisle

Milestone 3 Accomplishments

ACM Glovebag in Analytical Aisle

8

Page 9: West Valley Demonstration Project Phase I Decommissioning ... · West Valley Demonstration Project Phase I Decommissioning Project Status ... Material (ACM) Removal – 100% ... Vit-OOS

Vitrification (Vit) Facility - Deactivation   Instrument Rack Piping Systems - Operating Aisles –

Lower, Middle, & Upper West (20 of 26 complete)   Vit Cell Clean Out – Hazardous Waste Removal

(batteries

Vit-OOS Piping Air-Gapping

Milestone 3 Accomplishments

9

Page 10: West Valley Demonstration Project Phase I Decommissioning ... · West Valley Demonstration Project Phase I Decommissioning Project Status ... Material (ACM) Removal – 100% ... Vit-OOS

Milestone 4 Accomplishments

10

01-14 Building •  Completed Step 2

Demolition of Facility. Commencing Step 3 Demolition

Balance of Site Facilities (BOSF) •  Vit. Fab Shop, Counting

Lab, & Old Warehouse West Foundation Demo Debris Load-out and removal continues

01-14 Building Demolition After Phase 2

Old Warehouse Debris Loadout

Page 11: West Valley Demonstration Project Phase I Decommissioning ... · West Valley Demonstration Project Phase I Decommissioning Project Status ... Material (ACM) Removal – 100% ... Vit-OOS

•  February New Generation Waste Shipments

  9,585 ft3 Construction Debris Industrial Waste

  65,070 ft3 to date

•  Remote-Handled Waste Facility (RHWF) –  3C-2 processing is

approximately 90%. Bottom base and debris remains.

–  Thirteen Boxes of LLW Surveyed and Packaged approximately 95% has been packaged as LLW.

–  Four RH-TRU drums packaged and loaded into a Kistner box.

Loading LLW Shipment in LSA 3

Preparing Intermodals for D&D Activities and Loading of Newly Generated LLW

Milestone 4 Accomplishments

11

Page 12: West Valley Demonstration Project Phase I Decommissioning ... · West Valley Demonstration Project Phase I Decommissioning Project Status ... Material (ACM) Removal – 100% ... Vit-OOS

Milestone 4 Accomplishments

12

•  In-Progress Maintenance Activities –  Hydrant 6 repaired/fab parts for

Hydrants #4/plan for Hydrant #1 –  Continued planning repairs for Lake

2’s 36-in Gate Valve •  Other Initiatives

–  Updating Fire Hazard Analysis documents for site facilities

–  Completed Rail Inspection –  Continue installation of electrical

heater to replace steam –  Continue with shutdown of Waste

water treatment plant

Rail Spur Inspection

Page 13: West Valley Demonstration Project Phase I Decommissioning ... · West Valley Demonstration Project Phase I Decommissioning Project Status ... Material (ACM) Removal – 100% ... Vit-OOS

Milestone 4 Accomplishments

13

Cold, Dark, and Dry Initiatives

•  Interim MS 04-65 complete w/relocation of tanks 8D-3 and 8D-4 instruments

•  Work planning for Waste Tank Farm (WTF) Equipment Shelter, condensers, and Con-Ed building end points

•  Work planning for Cooling Tower end points 8D-3 and 8D-4

New Instrument Location

Page 14: West Valley Demonstration Project Phase I Decommissioning ... · West Valley Demonstration Project Phase I Decommissioning Project Status ... Material (ACM) Removal – 100% ... Vit-OOS

Questions?

14