WELCOMETo
Country Presentation
on
Facilitation of International Railway
Transportby
Bangladesh DelegationMd. Nazrul Islam, Deputy Chief (Planning)
Ministry of Railways
1
2
Bangladesh has signed the
“ Inter-governmentalAgreement on Trans-AsianRailway (TAR) Network ”
as 20th Signatory on09.11.2007 and ratificationwas also proposed on11.08.2010
Bangladesh has x Bi-lateral (Working)Agreements with Indiaand Inter GovernmentRailway Meetings (IGRM)are being held on regular(yearly) basis. ForRegional & sub-regionalConnectivity steps arefollowing ;
3
TRANS-ASIAN RAILWAY (TAR) NETWORK,
REGIONAL COOPERATION FRAMEWORK & BI-
LATERAL AGREEMENTS ON RAILWAY
TRANSPORT.
PM’S COMMITMENT & INSTRUCTIONS
➢ Hon’ble PM has given emphasis on Railway transportand instructed to connect each District in Rail-Network.Ministry of Railway is created separately and budgetallocation in railway sector is increased tremendously(N.B-USD1.6 b in 2017-18, 4th highest of NB).
➢ Hon’ble PM’s instruction is to construct either BG orDG considering Trans-Asian, Regional and sub-regionalconnectivity. And accordingly,
➢ Railway Master Plan (2015-2030) is going to be updatedand Projects are being taken in 7th FYP & ADPs in lightof SDG.
4
Existing MG, BG
& DG Lines
of
Bangladesh
Railways
5Source: BR Information Book, 2016
Covers 44 out of 64 adm. districts of the country
BANGLADESH RAILWAYDivided into 2 Zones;
1. East Zone (Eastern part of River Jamuna)
&
2. West Zone (Western part of River Jamuna)
1. East Zone -1308.27 km route (MG-1273.38 & DG-34.89km)
(i) Dhaka-Tongi-Chittagong MG double line 249.55km (out of 322.00 km.)
a) Akhaura - Laksam DG double line is under construction with ADB finance (cost-USD800 m).
b) 2nd Bhairab & 2nd Titas Bridges (cost-USD 112 m) are already constructed , besides Dhaka-Tongi3rd & 4th line (cost-USD123 m) is under construction with Indian 1st LOC finance.
c) Secondary route Laksam -Chandpur ,Laksam-Noakhali , Chittagong–Shuloshohor -Duhazari , Fatehabad-Nazirhat
d) Tertiary route Chittagong University
(ii) (Dhaka) Akhaura-Sylhet-Chhatak route
a) Kulaura - Shahbajpur BG line (cost-USD 95 m) is under construction with Indian 1st LOC finance.
b) Akhaura-Sylhet DG line is adopted to implement under G to G finance.
(iii) (Dhaka-)Tongi-Joydebpur-Mymensingh-Jamalpur MG line .
a) Secondary route Bhairab- Mymensingh, Mymensingh –Shyamgonj-Muhongonj
Shyamgonj-JariaJanjail,Jamalpur-Jogonnathgonj Ghat , Tarakandi –BBE & Jamalpur-Bahadurabad Ghat
(iv) Padma Rail Link Project (Dhaka – Bhanga – Jessore-Benepole is adopted under G to G finance (cost-USD 4.20 b). .
(v) Duhazari – Cox’sbazar – Ramu-Gundhum DG line is under construction with ADB finance (cost-USD 2.00 b).
(MG- Meter Gauge 1000m, BG-Broad Gauge 1635m, DG- Dual Gauge)
6
2. West zone -1568.83 km route (MG-534.67 km, BG-659.33 & DG-374.83km)
(i) Joydebpur- Iswardi- Darshona BG line, [Bangabandhu Sheik Mujib Rail Bridge (cost-USD 1.2 b)on Jamuna
with JICA fund, besides Joydebpur- Iswardi- Darshona BG double line project is adopted to implement under
G-G finance ]
a) Darshona -Abdulpur BG double line
b) Khulna –Darshona (Border)BG line [BG double line is adopted (cost-USD 460 m)under Indian
2nd LOC c) Khulna –Mongla BG line is under construction (cost USD 535 m) with Indian 1st LOC finance.
d) Secondary route Jessore – Benapole BG line (Border line), Kustia- Gualonda Ghat BG line,
e) Tertiary route Kalukhali – Bhatiapara BG line, Pachuria- Faridpur- Bhanga BG line.
(ii) Abdulpur- Chilahati BG line (Chilahati – Chilahati Border line project is adopted to implement with own
resources)
a) Abdulpur – Rohanpur BG line (Border line)
b) Amnura – Chapainawabgonj BG line .
c) Panchagarh – Kanchan - Birol BG line (Border line)
d) Dinajpur – Parbatipur BG line
e) Chilahati – Chilahati Border BG line (30 km) is adopted with GOB finance.
f) Tertiary line, Parbatipur – Madhyapara & Parbatipur – Barapukuria BG line (30 km)
(iii) Parbatipur- Kawnia – Lalmonirhat-Burimari MG line, [ Parbatipur- Kawnia DG line is adopted (cost-USD 216
m) under Indian 2nd LOC finance. ]
a) Lalmonirhat – Burimari MG line
b) Lalmonirhat – Mugalhat MG line
c) Tista – Ramnabazar MG line
iv) Kawnia - Santahar MG line
a) Bonarpara - Phulchharighat MG line
7
i) Route km: 2,877.10 BG: 659.33 km
❖ MG: 1,808.05 km
➢ DG: 409.72 km
Track km: 4,185.06
ii) Stations: 459
iii) Passenger: 67.34m, Pass-km: 8,711.31m
Tonnes: 2.55m ,Ton-km: 693.84m
iv) Daily pass. trains: 349 & freight trains: 37
v) Rolling stock: 282, Coaches: 1,639
Operating ratio: 170.5
vi) Revenue :
per pass-km: BDT 77.6 & ton-km: 2.38
vii) Employees: 27,620 (55,825 in 1971)
8
BANGLADESH RAILWAYS
FACTS & FIGURES
Source: BR Information Book, 2016
Covers 44 out of 64 adm. districts of the country
1. 165 BG tank wagons & 6 bogie brake vans (1st LOC USD 16.45m) -procured
2. 16 BG DE Locomotives (USD 51.13m) -procured
3. 50 MG Flat wagons & 5 van with air brake(1st LOC USD 3.3m) -procured
4. 10 BG DE Locomotives (USD 31.83m) -procured
5. 81 MG bogie tank wagons & 3 brake van (1st LOC USD 7.16m) -procured
6. 170 MG Flat wagons &11brake van with air(1st LOC USD 10.73m) -procured
7. 120 BG coaches air brake (1st LOC USD 125.5m) -procured
8. Modernization of signaling & inter locking systems - on going
9. DG line from Bogra to Sirajgonj (3rd LOC USD 519m) - Taken
10. Rail and road based ICD at Iswardi (3rd LOC USD 35m) - Taken
11. Khulna –Darshona BG double line is adopted (USD 460m Indian2nd LOC)- on going
12. Parbatipur- Kawnia DG line (USD 216 m Indian 2nd LOC) - on going
Cont./next
9
PROJECTS IMPLEMENTED, ON GOING & TAKEN (ON
GOING-43 PROJECTS & 4TH HIGHEST OF NATIONAL DEV. BUDGET-
USD1.6 B )
13 Construction of Akhaura- Agortala DG line (Indian grant USD 51m)- on going
14 Construction of Akhaura- Laksam DG double line(ADB,EIB USD 800 m)- on going
15 Kulaura - Shahbajpur BG line (1st LOC USD 95m) -on going
16 2nd Bhairab & 2nd Titas Bridges (1st LOC USD 112m) –almost completed
17 Dhaka-Tongi 3rd & 4th line (1st LOC USD 123m) -on going
18 Dhaka-Narayangonj DG parallel to MG line (DRGA-USD 47 m) -on going
19 Panchagor-Kanchon-Birol –Border BG line (DRGA fund) - completed
20 Modernization of signaling & inter locking systems (EDCF, ADB & LOC)- on going
21 Khulna–Mongla BG line(Indian 1st LOC USD 535m) - On going
22 Padma Rail Link Project (G-G, USD 4.2 b) - on going
23 Duhazari–Cox’sbazari–Ramu-Gundhum DG line(ADB,USD 2 b) – on going
24 Bangabandhu Sheik Mujib Rail Bridge on River Jamuna (JICA, USD1.2 b) – on going
25 Chilahati- Chilahati Border BG line (USD 10m GOB) - on going
Cont./next
10
PROJECTS IMPLEMENTED, ON GOING & TAKEN (ON GOING-43 PROJECTS & 4TH HIGHEST OF NATIONAL DEV.
BUDGET-USD1.6 B )
Birol
Trans-Asian Railway network Bangladesh Perspective
TAR-3Radhikapur
(India)
Mohishasan
(India)
Myanmar
Shahbazpur
Akhaura
Tongi
Chittagong
Gundum
Dohazari
Darsana
TAR-2Singabad
(India)
Dhaka
Ishurdi
Abdulpur
RohanpurTAR ROUTE – 1 :Gede (West Bengal, India) – Darsana –
Ishurdi – Jamtoil – Joydebpur – Tongi –
Akhaura – Chittagong – Dohazari –
Gundum – (Mynmar border station).
Sub-route – I : Tongi – Dhaka.
Sub-route – II : Akhaura – Kulaura –
Shahbazpur – Mahisasan (India)
TAR ROUTE – 2 :Singabad (West Bengal, India) –
Rohanpur – Rajshahi – Abdulpur –
Ishurdi and thereafter following the rest
of the route/sub-routes of Route – I.
TAR ROUTE – 3 :Radhikapur (West Bengal, India) – Birol
– Dinajpur – Parbatipur – Abdulpur –
Ishurdi and thereafter following the rest
of the route/sub-routes of Route – I.
TAR-1Gede (India)
Ramu
Dinazpur
Parbatipur
Kulaura
11 11
Existing Regional Connectivity
At present Closed Connectivity
Proposed new connectivity
Agartala
Singhabad
Radhikapur
Existing Rail Connectivity with India:(1) Benapole – Petrapole
(2) Darsana – Gede (TAR-1)
(3) Rohanpur – Singhabad (TAR-2)
(4) Birol – Radhikapur (TAR-3)
Closed to Connectivity:(1) Shahbazpur – Mohishasan (TAR-1)
(2) Chilahati – Holdibari
(3) Akhaura - Agartala
(4) Feni - Bilonia
Possible new Connectivity:
(1) Burimari – Chengrabandha
(2) Dohazari – Cox’s Bazar – Gundum
Connectivity with Nepal (through India) :
(1) Rohanpur – Singhabad.
(2) Birol–Radhikapur
Connectivity with Bhutan ( through India) :
(1) Chilahati–Holdibari (Link & MOU)
(2) Burimari – Chengrabandha (trans-ship & MOU).
Possible Connectivity with Myanmar:(1) Dohazari – Cox’s Bazar – Gundum (Agreement)
REGIONAL RAILWAY CONNECTIVITY and BANGLADESH RAILWAY
1212
FREIGHT OPERATION INDIA – BANGLADESH➢ Working Agreements govern Train operations between India and Bangladesh :
➢ Broad Gauge links at four locations provide traffic interchanging viz;
1. Petrapole-Benapole
2. Gede-Darshana
3. Singhabad-Rohanpur and
4. Radhikapur-Birol (recently)
➢ Rolling stock in good condition (covered wagons) is provided by IR&BR
➢ Joint Train Checking in both directions takes place at a single point
➢ Customs clearance is arranged by IR and BR in respective territory (now it will be end
to end).
13
PASSENGER TRAIN SERVICES INDIA - BANGLADESH
➢ Working of trains governed by the Fundamental and
subsidiary Rules and Running Power Agreement for
interchange of Traffic ;
➢ Both IR and BR contribute equally towards the rolling
stock–Locomotives provided by IR and BR in respective territory
➢ Each Railway provides primary maintenance of its rake.
➢ The crews and guards of IR and BR man the trains in respective territory
➢ Customs and Immigration clearance arranged by IR and
BR on respective border stations (Now end to end)
➢ Revenue apportionment on KM basis
14
Thank You All