7/24/2019 Weekly Accomplishment Report #6
1/1
PROJECT : PGMH - MAHOGANY TOWER
LOCATION : Peafrancia, Paco, Manila
SUBJECT : SUMMARY OF ACCOMPLISHMENT
As Of : 15-Feb-16
CEMENT READY MIX CONCRETE
DESIGN MIX PREVIOUS
DELIVERY LAST DELIVERY TOTAL DELIVERY
QUANTITY UNITS QUANTITY UNITS QUANTITY UNITS 5000 PSI 166 72 238
53931 bulks 1944 bulks 51987 bulks 3.60 4000 PSI 255 14 269
24980 bags 600 bags 24380 bags 2.40 SUM TOTAL 507
CONCRETING (GROUND FLOOR) FORMWORKS (FOUNDATION/GROUND FLOOR)
DESCRIPTION TOTAL NO. PREVIOUS
(CONCRETED)
TO DATE
(CONCRETED)
TOTAL
(CONCRETED) % DESCRIPTION TOTAL NO.
PREVIOUS
(INSTALLED)
TO DATE
(INSTALLED)
TOTAL
(INSTALLED) %
PILE CAP 34 26 5 31 91.18% PILE CAP 34 28 3 31 91.18%
FTB 43 29 8 37 86.05% FTB 43 29 8 37 86.05%
COLUMNS 34 23 2 25 73.53% COLUMNS 34 25 3 28 82.35%
PEDESTAL 34 26 1 27 79.41%
RCW(PERIMETER) 24 10 7 17 70.83%
CONCRETING (2ND FLOOR) FORMWORKS (2ND FLOOR)
DESCRIPTION TOTAL NO. PREVIOUS
(CONCRETED)
TO DATE
(CONCRETED)
TOTAL
(CONCRETED) % DESCRIPTION TOTAL NO.
PREVIOUS
(INSTALLED)
TO DATE
(INSTALLED)
TOTAL
(INSTALLED) %
SLAB 9 4 0 4 44.44% SLAB 9 4 0 4 44.44%
BEAMS 66 28 0 28 42.42% BEAMS 66 28 0 28 42.42%
COLUMNS 34 14 0 14 41.18% COLUMNS 34 14 0 14 41.18%
CONCRETING (3RD FLOOR) FORMWORKS (3RD FLOOR)
DESCRIPTION TOTAL NO. PREVIOUS
(CONCRETED)
TO DATE
(CONCRETED)
TOTAL
(CONCRETED) % DESCRIPTION TOTAL NO.
PREVIOUS
(INSTALLED)
TO DATE
(INSTALLED)
TOTAL
(INSTALLED) %
SLAB 9 0 3 3 33.33% SLAB 9 0 0 0 0.00%
BEAMS 66 0 0 0 0.00% BEAMS 66 0 0 0 0.00%
COLUMNS 34 0 0 0 0.00% COLUMNS 34 0 5 5 14.71%
EXCAVATION BACKFILLING
DESCRIPTION TOTAL NO. PREVIOUS
(EXCAVATED)
TO DATE
(EXCAVATED)
TOTAL
(EXCAVATED) % DESCRIPTION
TOTAL AREA
TO BE
BACKFILLED
(sq.m)
PREVIOUS
(BACKFILLED
AREA)
TO DATE
(BACKFILLED
AREA)
TOTAL
BACKFILLED
AREA (sq.m)
%
PILE CAP 34 28 3 31 91% GROUND FLOOR 715 237.9 79.3 317.2 44.36%
FTB 43 39 3 42 98%
CISTERN TANK 1 0 0 0 0%
AGA SONS
CONST. AND DEV'T. CORP.
GMQ DELIVERED ON SITE BALANCE%