Weekly Accomplishment Report #6

Embed Size (px)

Citation preview

  • 7/24/2019 Weekly Accomplishment Report #6

    1/1

    PROJECT : PGMH - MAHOGANY TOWER

    LOCATION : Peafrancia, Paco, Manila

    SUBJECT : SUMMARY OF ACCOMPLISHMENT

    As Of : 15-Feb-16

    CEMENT READY MIX CONCRETE

    DESIGN MIX PREVIOUS

    DELIVERY LAST DELIVERY TOTAL DELIVERY

    QUANTITY UNITS QUANTITY UNITS QUANTITY UNITS 5000 PSI 166 72 238

    53931 bulks 1944 bulks 51987 bulks 3.60 4000 PSI 255 14 269

    24980 bags 600 bags 24380 bags 2.40 SUM TOTAL 507

    CONCRETING (GROUND FLOOR) FORMWORKS (FOUNDATION/GROUND FLOOR)

    DESCRIPTION TOTAL NO. PREVIOUS

    (CONCRETED)

    TO DATE

    (CONCRETED)

    TOTAL

    (CONCRETED) % DESCRIPTION TOTAL NO.

    PREVIOUS

    (INSTALLED)

    TO DATE

    (INSTALLED)

    TOTAL

    (INSTALLED) %

    PILE CAP 34 26 5 31 91.18% PILE CAP 34 28 3 31 91.18%

    FTB 43 29 8 37 86.05% FTB 43 29 8 37 86.05%

    COLUMNS 34 23 2 25 73.53% COLUMNS 34 25 3 28 82.35%

    PEDESTAL 34 26 1 27 79.41%

    RCW(PERIMETER) 24 10 7 17 70.83%

    CONCRETING (2ND FLOOR) FORMWORKS (2ND FLOOR)

    DESCRIPTION TOTAL NO. PREVIOUS

    (CONCRETED)

    TO DATE

    (CONCRETED)

    TOTAL

    (CONCRETED) % DESCRIPTION TOTAL NO.

    PREVIOUS

    (INSTALLED)

    TO DATE

    (INSTALLED)

    TOTAL

    (INSTALLED) %

    SLAB 9 4 0 4 44.44% SLAB 9 4 0 4 44.44%

    BEAMS 66 28 0 28 42.42% BEAMS 66 28 0 28 42.42%

    COLUMNS 34 14 0 14 41.18% COLUMNS 34 14 0 14 41.18%

    CONCRETING (3RD FLOOR) FORMWORKS (3RD FLOOR)

    DESCRIPTION TOTAL NO. PREVIOUS

    (CONCRETED)

    TO DATE

    (CONCRETED)

    TOTAL

    (CONCRETED) % DESCRIPTION TOTAL NO.

    PREVIOUS

    (INSTALLED)

    TO DATE

    (INSTALLED)

    TOTAL

    (INSTALLED) %

    SLAB 9 0 3 3 33.33% SLAB 9 0 0 0 0.00%

    BEAMS 66 0 0 0 0.00% BEAMS 66 0 0 0 0.00%

    COLUMNS 34 0 0 0 0.00% COLUMNS 34 0 5 5 14.71%

    EXCAVATION BACKFILLING

    DESCRIPTION TOTAL NO. PREVIOUS

    (EXCAVATED)

    TO DATE

    (EXCAVATED)

    TOTAL

    (EXCAVATED) % DESCRIPTION

    TOTAL AREA

    TO BE

    BACKFILLED

    (sq.m)

    PREVIOUS

    (BACKFILLED

    AREA)

    TO DATE

    (BACKFILLED

    AREA)

    TOTAL

    BACKFILLED

    AREA (sq.m)

    %

    PILE CAP 34 28 3 31 91% GROUND FLOOR 715 237.9 79.3 317.2 44.36%

    FTB 43 39 3 42 98%

    CISTERN TANK 1 0 0 0 0%

    AGA SONS

    CONST. AND DEV'T. CORP.

    GMQ DELIVERED ON SITE BALANCE%