Week 12,1-2 Dan 13 Capacity Planning

Embed Size (px)

Citation preview

  • 8/12/2019 Week 12,1-2 Dan 13 Capacity Planning

    1/13

    12/9/20

    Capacity Planning

    Week 12,1-2 dan 131

    Capacity definition2

    Capacity is the amount of work that can be done in

    a specified time period.

    capacity is defined as the capability of a worker,

    machine, work center, plant, or organization to

    produce output per time period.

    Capacity is a rate of doing work, not the quantity of

    work done.

  • 8/12/2019 Week 12,1-2 Dan 13 Capacity Planning

    2/13

    12/9/20

    Basic Capacity Definitions

    Capacity Requiredcapacity needed toproduce a desired output in a given time period

    Capacity Planningdetermining the resourcesand methods needed to meet the priority plan

    Capacity Controlmonitoring production,comparing with the capacity plan, and takingappropriate corrective actions

    Capacity Managementdetermining capacity

    needed as well as providing, monitoring, andcontrolling the capacity

    Capacity versus Load

  • 8/12/2019 Week 12,1-2 Dan 13 Capacity Planning

    3/13

    12/9/20

    Capacity Planning Levels

    Resource PlanningLong range resource

    requirements linked to the production plan

    Rough-cut Capacity PlanningUsed to check

    feasibility of MPS

    Capacity Requirements PlanningDetailed

    work center capacity plans linked to MRP

    Capacity Planning Levels

  • 8/12/2019 Week 12,1-2 Dan 13 Capacity Planning

    4/13

    12/9/20

    Capacity Requirements Planning (CRP)

    Inputs

    Open Order Filefound as scheduled receipts on

    MRP

    Planned order releases from MRPPotential

    future orders

    Work Center file

    Information on capacity in the work center

    Move, wait, and queue time information

    Capacity Requirements PlanningInputs - Continued

    Routing filethe path that the work will follow

    Operations to be performed

    Operation sequence

    Work centers used

    Potential alternative work centers

    Tooling needed Standard setup times and run times

  • 8/12/2019 Week 12,1-2 Dan 13 Capacity Planning

    5/13

    12/9/20

    Sample Routing File

    Figure 5.3 Routing file

    Capacity Available

    Impacted by:

    Product specification

    Product mix

    Methods used to make product

    Pace of work

  • 8/12/2019 Week 12,1-2 Dan 13 Capacity Planning

    6/13

    12/9/20

    Planning calender11

    Finding Capacity Available

    Rated Capacity = (available time) x (utilization) x

    (efficiency)

    Available timenumber of hours a work center can be

    used

    Utilization = [(hours worked)/(available hours)] x

    100%

    Efficiency = [(actual production rate)/(standard

    production rate)] x 100%

  • 8/12/2019 Week 12,1-2 Dan 13 Capacity Planning

    7/13

    12/9/20

    Soal (rated capacity)13

    A work center consists of 4 machines and is

    operated 8 hours per day for 5 days a week.

    Historically, the utilization has been 85% and the

    efficiency 110%. What is the rated capacity?

    Demonstrated capacity14

    Over the previous 4 weeks, a work center produced

    120, 130, 150, and 140 standard hours of work.

    What is the demonstrated capacity of the work

    center?

  • 8/12/2019 Week 12,1-2 Dan 13 Capacity Planning

    8/13

    12/9/20

    Capacity required (load)15

    Capacity required (load)16

  • 8/12/2019 Week 12,1-2 Dan 13 Capacity Planning

    9/13

    12/9/20

    Capacity LoadSum of all time required for

    orders on a work center - Example

    Example Load Profile

  • 8/12/2019 Week 12,1-2 Dan 13 Capacity Planning

    10/13

    12/9/20

    Scheduling Orders

    Back scheduling (the typical approach)Start

    with the due date, use lead time to find the

    proper start date for each operation

    Forward schedulingLaunch the order into

    the first (gateway) work center, then use the lead

    times to find when the order will be completed at

    each work center

    Back Scheduling Example

    An order for 150 of a component is due on day

    135

    An order starts at the beginning of a day and

    finished at the end of a day

    Operation times for the 150 ordered: Operation 104 days in work center 12

    Operation 205 days in work center 14

    Operation 301 day in work center 17

    Operation 402 days in work center 03

  • 8/12/2019 Week 12,1-2 Dan 13 Capacity Planning

    11/13

    12/9/20

    Data from the work center file

    The resulting work schedule

  • 8/12/2019 Week 12,1-2 Dan 13 Capacity Planning

    12/13

    12/9/20

    The work schedule shown graphically

    Making the plan

  • 8/12/2019 Week 12,1-2 Dan 13 Capacity Planning

    13/13

    12/9/20

    Managing the PlanAdjusting Capacity

    Use Overtime or Undertime

    Adjust the number of workers

    Shift workers from other work centers

    Use alternative work centers to shift load

    Subcontract work

    26