214
TUCANNON RIVER PROJECT AREA 28 Phase III 100 PERCENT DESIGN TECHNICAL SPECIFICATIONS

snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

TUCANNON RIVER PROJECT AREA 28Phase III

100 PERCENT DESIGN TECHNICAL SPECIFICATIONS

Page 2: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

Index of Sections - ii

INDEX OF SECTIONSTUCANNON RIVER PA-28 100 PERCENT DESIGN

TECHNICAL SPECIFICATIONS

DIVISION 01—PROCUREMENT AND CONTRACTING REQUIREMENTS01 11 00 Summary of Work

01 14 00 Work Restrictions

01 22 00 Measurement and Payment

01 32 13 Progress Schedules

01 33 10 Submittals

01 35 29 Health and Safety

01 42 00 References

01 45 00 Quality Control

01 50 00 Temporary Facilities and Controls

01 57 13 Temporary Erosion and Sediment Control

01 57 19 Temporary Environmental Pollution Control

01 57 24 Temporary Water Pollution Control

01 60 00 Product Requirements

01 71 13 Mobilization

01 71 23 Field Engineering and Surveying

01 74 00 Cleaning

01 76 00 Protection of Existing Facilities

01 78 00 Project Closeout

DIVISION 05—METALS05 17 00 Structure Connections

DIVISION 06—WOOD06 13 43 Large Woody Materials

Page 3: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

Index of Sections - ii

DIVISION 31—EARTHWORK31 10 00 Site Clearing

31 23 00 Excavation and Fill

31 23 19 Dewatering

31 37 00 Boulders

31 50 00 Excavation Support and Protection

DIVISION 32—EXTERIOR IMPROVEMENTS32 93 10 Vegetation Protection and Restoration

DIVISION 35—WATERWAY AND MARINE CONSTRUCTION35 44 00 Waterway Habitat Structures

Page 4: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 11 00—Summary of Work

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 11 00 - 1

P AR T 1 – GENER A L

1.01 SECTION INCLUDES

A. This section covers the Scope of Work describing the construction activities that shall take place at the Project site as included in the Contract Documents.

B. This section covers the general requirements for the Work completed as described in the Scope of Work and as shown on the Contract Drawings.

1.02 INTENT

A. The general intent of this Work is to enhance and improve fish habitat conditions along the Tucannon River main channel and side channels.

B. The above Work is to be performed for the Columbia Conservation District, hereafter referred to as the “Contracting Agency.” The Contracting Agency will appoint a Project staff member, hereafter referred to as “Project Manager,” who will have the responsibility to issue a Contract to construct the above Work and will administer the Contract Documents and funds for the Project.

C. The Project Engineer, hereafter referred to as the “Engineer,” is the Contracting Agency’s representative who has designed the Project and provides oversight during construction. The Contracting Agency will provide additional in-house engineering support during the construction phase. The Engineer makes recommendations to the Project Manager regarding whether all the Work is in compliance with the construction Specifications and Contract Drawings. The Engineer also reviews all construction changes and makes recommendations to the Project Manager prior to the Project Manager’s approval of the changes.

1.03 GENERAL REQUIREMENTS

A. Construct and complete in accordance with the provisions of the ContractDocuments, these Specifications, and the Contract Drawings.

B. Governing Regulations

1. Perform Work in accordance with all applicable laws, codes, ordinances, and regulations. Work shall be completed in accordance with the following:

a) The Contract Documents

b) Applicable permits, laws, codes, ordinances, and regulations

c) According to the manufacturer’s recommendations

Page 5: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 11 00—Summary of Work

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 11 00 - 2

2. The Contractor shall have an approved set of the Contract Documents on site at all times. The Contractor shall also have a copy of applicable permits and licenses on the site at all times.

3. Protection of natural resources: All Work should be carried out in a manner consistent with the goal of achieving proposed development with the least possible disturbance to vegetation, wildlife, steep slopes, wetlands, streams, and their buffers. No disturbance, including access or storage of materials, is to occur within designated wetlands or below ordinary high water, with the exception of those areas as shown on the Contract Drawings, which are permitted disturbances.

C. Contractor Responsibilities

1. Coordinate, furnish, and pay for all items, articles, materials, and operations listed, including all labor, materials, equipment, and incidentals required for their completion, except as noted in Part 1.03 D. The Contractor is responsible for all construction means and methods and for the general coordination of the Work of all trades.

2. Pay the required taxes.

3. Secure and pay for the following, as necessary for proper execution and completion of the Work:

a) Work permits from local jurisdictions, not including regulatory permits that are obtained by the Contracting Agency

b) Fees

c) Licenses

d) Bonds

4. Give required notices.

5. Enforce strict discipline and good order among employees and coordination of the Work by subcontractors.

6. Use new materials, except as noted or otherwise approved by theProject Manager and/or designee.

7. Maintain required ingress and egress and other access as required by the Contracting Agency in accordance with governing Codes and Ordinances throughout the Work.

8. Comply with all requirements noted in approved permits. Advise the Project Manager and/or designee of any conflicts between permit conditions and the Contract Documents.

Page 6: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 11 00—Summary of Work

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 11 00 - 3

9. The Contractor is, in general, the custodian of the site of the Project and it is his/her responsibility to provide access, storage, sanitation facilities, safety and environmental protection supplies, parking, and work space for all those engaged in the Work. The site shall be maintained in an orderly manner with debris and trash removed daily.

10. All materials, methods, and equipment shall comply with the requirements of applicable codes and the Contract Documents, including requirements of all incorporated standards. The Contractor shall furnish, as a part of the Contract, certification of code compliance if requested by the Contracting Agency, Project Manager, or Code Enforcing Agency.

11. Personal safety: Protect personnel, passers-by, occupants, or visitors to the site from harm and injury.

12. Construction: Protect existing and adjoining structures and site features where noted, including: vegetation, access points, utilities, and Work of any kind which is to remain from damage, defacement, or interruption of service, except as may be specially directed or authorized. All streets and access roads shall be repaired according to municipal standards, if damaged, and left in a condition equal to or better than the original condition.

13. Existing utilities: Protect existing underground and overhead utilities from any damage or interruption of service and call for location markings before ground disturbance. If necessary, obtain permission from utility owners and relocate as required for completion of the Work.

D. Materials and Services Supplied by the Contracting Agency

1. The Contracting Agency may supply materials and/or services for the Work; these materials and supplies shall be identified on one or a combination of the following: the Contract Drawings, Specifications, and Contract Documents.

2. The Contractor shall not be reimbursed for materials and/or services supplied by the Contracting Agency.

3. The Contractor shall coordinate with the Contracting Agency supplying materials and/or service, as necessary, to complete the Work.

Page 7: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 11 00—Summary of Work

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 11 00 - 4

1.04 SCOPE OF WORK

A. This Contract includes work as described below. The description is summarized and may not include specific reference to all incidental work elements required to complete the Contract. Include all labor, materials, equipment, and incidentals required for completion of the Work as shown on the Contract Drawings and specified herein.

1. Mobilization and demobilization

2. Site preparation, including:

a) Establishing staging areas and Work access routes as indicated on the Contract Drawings; includes limited clearing and grubbing.

b) Contractor to develop and implement elements of an approvedWater Quality Management Plan.

c) Contractor to develop and implement an approved Traffic ControlPlan, where applicable.

d) Contractor to develop and implement elements of an approved Care of Water Plan in preparation for excavation required for various elements of the Work.

3. Diversion and control of water during construction in accordance with the approved Care of Water Plan and other construction permit conditions.

4. Installing, maintaining during construction, and removing at construction completion temporary erosion and sediment control measures.

5. Installation of multiple large woody debris (LWD) and engineered log jam (ELJ) structures as shown on the Contract Drawings and as described in the Specifications.

6. Excavation of portions of existing spoils piles as shown on the ContractDrawings and as described in the Specifications.

1.05 SCHEDULE

A. Contractor shall attend a pre-construction meeting prior to commencement of the construction. Meeting location, date, and time shall be determined by the Contracting Agency.

Page 8: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 11 00—Summary of Work

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 11 00 - 5

B. In-water work must be constructed during limited work windows, and all work must be performed under permit requirements.

C. The Contractor shall complete all construction activities within and adjacent to the Tucannon River and its floodplain within ordinary high water line in accordance with construction permits. Work in the channels shall not begin before water control is in place in case of high water, unless otherwise allowed by the construction permits and approved by the Project Manager and/or designee.

D. Unless otherwise indicated in the Contract, the following shall apply:

1. The Work of this Contract shall commence immediately upon the receipt of Notice to Proceed, and shall be substantially complete within the Contract time defined in the General Conditions of the Contract Documents. Completion of Final Punch List shall be achieved within the time period required in the Certificate of Substantial Completion.

2. Contract time may be changed by Contracting Ageny only. Contract time shall be amended to account for weather-related delays.

E. In-stream work will start no earlier than permitted in the Contract Documents.

1.06 CONTRACTS

A. There will be one Contract for the Project, which includes the Work described in the Specifications and Contract Drawings.

1.07 CONTRACTOR’S USE OF PREMISES

A. Hours of Work

1. The Contractor shall limit their work to between the hours of 7:00 am and6:00 pm, Monday through Saturday, except federal holidays. The Contractor shall plan and schedule work activities to conform to and allow time for notifications, approvals, reviews, and other conditions of the Contract. Any other times of work shall only be by written approval of the Contracting Agency.

B. Minimum Area

1. Construction impacts will be confined to the clearing limits indicated on the Contract Drawings, unless otherwise approved by the Project Manager. All material stockpiles, equipment storage, employee parking, and other

Page 9: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 11 00—Summary of Work

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 11 00 - 6

related construction support activities shall be confined to the limits shown on the Contract Drawings, unless otherwise approved by the Project Manager.

C. Parking

1. Parking for personnel on the Project site will be limited to an area within the Project boundaries. The Contracting Agency will designate this area and coordinate with the Contractor. The Contractor shall be responsible for ensuring that no nuisance is created for the Property Owner or for adjacent properties through use of the streets for parking for workers.

D. Staging

1. The Contractor shall submit a staging plan to show locations of materials, trailers, and fencing layouts for approval by the Contracting Agency.

E. Maintaining Normal Flow of Water

1. Work shall not impede the natural flow of water, except as indicated in the Specifications and Contract Drawings, or as authorized by the approved Care of Water Plan and construction permit conditions.

F. Contractor’s additional responsibilities while using the premises include the following:

1. Maintaining pedestrian and vehicular access to and around the site.

2. Not unreasonably encumbering the site with materials or equipment.

3. Assuming full responsibility for protection and safekeeping of products stored on the premises.

4. Obtaining and paying for use of additional storage or work areas needed for operation.

5. Keeping roads and other areas clean of dirt and other debris.

6. Protecting any above- or below-ground utilities to remain on site, including those that are crossed in order to access the site from land.

1.08 STORAGE AND PROTECTION

A. Store products in accordance with their manufacturer’s instructions, with seals and labels intact and legible.

1. Store products subject to damage by the elements in weather-tight enclosures.

Page 10: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 11 00—Summary of Work

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 11 00 - 7

2. Maintain temperature and humidity within the ranges required by manufacturer’s instructions.

3. Storage of hazardous materials and wastes shall be in accordance with local, state, and federal fire codes and regulations.

4. Note requirements on Safety Data Sheets (SDS).

B. Exterior Storage

1. Store fabricated products above ground. Position such products on blocking or skids, and prevent soiling or staining. Cover products subject to deterioration with impervious sheet coverings. Provide adequate ventilation to avoid condensation.

2. Store loose granular materials in well-drained areas, on solid surfaces.Prevent mixing with foreign matter.

C. Do not store materials for other projects on site.

D. Waste Material Disposal: Refer to Section 01 74 00 – Cleaning.

1.09 HAZARDOUS MATERIAL

A. No toxic or hazardous chemicals or materials are expected to be encountered during scheduled construction activities. Should any Work activities by this Contract discover/disturb any hazardous material, the Contractor is directed to immediately cease Work activity in the area found to be potentially hazardous, notify the Project Manager, and await the Project Manager’s direction.

1.10 SALVAGED MATERIALS

A. Salvage only those items that are noted in the Contract Documents. The Contracting Agency retains first right of refusal to all salvaged materials, equipment, and/or products identified or not identified in the Contract Documents that are affected as part of the Contract Work.

1.11 DISPOSAL OF DEBRIS

A. All disposal of debris resulting from the Work, unless specifically allocated to another scope of work, shall be the responsibility of the Contractor. This includes scheduling, costs, and interference in the use of trash collecting, containers, trucks, etc. The Contractor is responsible for awareness of, understanding of, and compliance with all local, state, and federal regulations regarding the disposal of any hazardous and non-hazardous wastes.

Page 11: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 11 00—Summary of Work

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 11 00 - 8

1.12 SAFETY AND ENVIRONMENTAL CONCERNS

A. MSDS for all chemicals, including paints, used in the performance of the Contractor’s duties must be identified in advance to the Contracting Agency, be posted on a specified bulletin board at least 10 working days before first using the material, and comply with SDS recommended practice.

B. The Contractor shall provide barricades, safety guards, temporary fencing, signage, and/or other methods to secure trenches, open excavations, and other unsafe conditions resulting from this construction. The Contractor shall adhere to all safety regulations.

1.13 WORK QUALITY STANDARDS

A. The Project Work is expected to be performed by qualified journey-level workers or apprentice-level workers under the supervision of experienced journey-level individuals. The Contract Drawings and Specifications require that the highest standard of workmanship and care be performed in the execution of this Project.

B. All activities must be the subject of immediate, ongoing cleanup and attention to detail. Dirt, debris, materials, tools, and equipment must be treated in such a manner as to have minimum possible effect on visitors’ perception of the facility and the professionalism of the Contractor’s effort.

1.14 CUTTING AND PATCHING

A. General: The Contractor shall be responsible for all cutting and fitting or patching that may be required to complete the Work or to make several parts fit together properly. This includes executing cutting, fitting, and patching required to uncover Work; providing for installation of ill-timed Work; removing and replacing defective Work; removing and replacing Work not conforming to requirements of the Contract Documents; removing samples of Work as specified for testing; and installing specified Work in existing construction.

1.15 CONTRACT DRAWINGS AND PROJECT MANUAL

A. The Contractor shall be required to keep the Project Record Documents at the Project site, maintained in good condition and fully updated, reflecting all approved and/or noted changes for the Work at the Project site. At Final Completion, the Contractor shall submit the Project Record Documents to the Contracting Agency for review and acceptance.

1.16 DEFINITIONS

A. Abandonment: Contractor failing to be present at job site for 7 calendar days without prior notice (not to be confused with abandoned utilities).

Page 12: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 11 00—Summary of Work

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 11 00 - 9

B. Addenda: The written notices of modification of the Contract Drawings, Specifications, or other Contract Documents, which may be issued by the Contracting Agency to holders of Contract Documents prior to the opening of Proposals. The singular of Addenda is Addendum.

C. Engineer: The person or firm designated as the Engineer.

D. As approved: Unless otherwise qualified, shall be understood to be followed by the words “by the Project Manager.”

E. As shown and as indicated: Unless otherwise qualified, shall be understood to be followed by the words “on the Contract Drawings.”

F. Authorized Designee: The individual(s) designated by the Contracting Agency or Project Manager to serve as its representative in dealings with the Contractor.

G. Contract Documents: Include these Specifications, Contract Drawings, and theContract between the Contracting Agency and the Contractor.

H. Contract Drawings: Refers to the official Drawings, profiles, cross-sections, elevations, details, and other working drawings and supplementary drawings, or reproductions thereof, which show the location, character, dimensions, and details of the Work to be performed. Contract Drawings may either be bound in the same book as the balance of the Contract Documents or bound in separate sets, and are a part of the Contract Documents, regardless of the method of binding.

I. Contracting Agency: The Agency that is a party to the Contract, ColumbiaConservation District.

J. Contractor: The entity that is awarded the Contract.

K. Contractor Representative: The individual designated by the Contractor to serve as its representative.

L. Days: Unless otherwise specifically stated, will be understood to mean calendar

days. M. Drawings: (see “Contract Drawings”).

N. Notice or the requirement to notify: As used in the Contract Documents or applicable state or federal statutes, shall signify a written communication delivered in person or by certified or registered mail to the individual, or to a member of the firm, or to an officer of the corporation for whom it is intended. Certified or registered mail shall be addressed to the last business address known to him who gives the notice.

Page 13: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 11 00—Summary of Work

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 11 00 - 10

O. Observer: Individual(s) designated by the Contracting Agency to serve as its observer(s) of the Work.

P. Or equal: Shall be understood to indicate that the “equal” product is the same or better than the product named in function, performance, reliability, quality, and general configuration. Determination of equality in reference to the Project design requirements will be made by the Project Manager. Such “equal” products shall not be purchased or installed by the Contractor without the Project Manager’s written approval.

Q. Plans: (see “Contract Drawings”).

R. Project Manager: The individual designated by the Contracting Agency to serve as its representative.

S. Property Owner: The land owner or group of land owners for the property or properties that the Project covers.

T. Provide: Means to “furnish and install” as specified in the Specifications and as shown on the Contract Drawings.

U. Satisfactory: Satisfactory to the Contracting Agency or the Engineer.

V. Specifications: The terms, provisions, and requirements contained herein. Where standard specifications, such as those of ASTM, AASHTO, etc., have been referred to, the applicable portions of such standard specifications shall become a part of these Contract Documents.

W. Substantial Completion: Shall be that degree of completion of the Project or adefined portion of the Project, sufficient to provide the Project Manager, at his discretion, the full-time use of the Project or defined portion of the Project for the purposes for which it was intended. Notice of acceptance by the Project Manager shall not be deemed granted until provided to the Contractor in writing.

X. The Work: The entire undertaking, including all labor, materials, plant, tools, supplies, equipment, transportation, supervision, design, services, goods, and other things necessary, appropriate, or incidental to the carrying out and completion of all tasks described in the Contract Documents, in full conformity with the Contract Documents.

Page 14: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 11 00—Summary of Work

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 11 00 - 11

1.17 PROJECT TEAM

A. Lines of Communication:

1. The Contractor and the Contractor’s Representative are to communicate directly with the Project Manager or the Project Manager’s Designee unless authorized in writing to contact other listed Project personnel.

B. Contracting Agency

1.Columbia Conservation District

Office Address:Columbia Conservation District202 S. Second StreetU.S. Post Office Building, Dayton, Washington 99328Phone: (509) [email protected]

Project Manager: Terry Bruegman, CCD Phone: (509) 382-4273Mobile: (509) 520-8532

Project Manager’sDesignees:Lance Horning, P.E., Project Engineer

Kris Buelow, SRSRBJustin Pearson, CCD

P AR T 2 – PR ODUC TS

Not used

P AR T 3 – EXEC UT ION

Not used

END OF SECTION

Page 15: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 14 00—Work Restrictions

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 14 00 - 1

PAR T 1 – GENER A L

1.01 USE OF PREMISES

A. Use of Site: Limit use of premises to Work in the areas indicated. Do not disturb portions of the site beyond the areas in which the Work is indicated. Disturbance outside the limits of disturbance (as shown on the Contract Drawings) is limited to designated access points and storage areas as shown on the Contract Drawings or specified herein.

1. Limits: Confine construction operations as shown on the Contract Drawings. In those locations where existing vegetation is to remain, the Contractor must work around the material.

2. Property Owner occupancy: Allow for Property Owner occupancy of site, but the public may be restricted.

3. Driveways and entrances: Keep driveways and entrances serving premises clear and available to residents, Property Owner, Property Owner’s employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

a) Schedule deliveries to minimize obstruction of driveways and entrances.

b) Schedule deliveries to minimize space and time requirements of driveways and entrances.

4. Coordinate use of premises under the direction of the Contracting Agency.

5. Move any stored products, under the Contractor’s control, that interfere with the operations of the Property Owner or access to residents.

B. If private land is used for construction facilities or other construction purposes, the Contractor shall make necessary arrangements and pay rental and other costs associated with use of private land. At the end of the project, provide a copy of a release from the Property Owner that rents have been paid and lease conditions fulfilled.

C. Use of public right-of-way may require permits from local and/or state agencies.It is the responsibility of the Contractor to acquire the necessary permits before the start of the Work.

D. Location, construction, operation, maintenance, and removal of construction facilities on the designated staging areas and access routes will be subject to approval of the Project Manager.

Page 16: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 14 00 - 2

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 14 00—Work Restrictions

E. Housing for construction personnel will not be permitted on the Project site.

F. Protected Areas: The following areas within the project limits are to be protected from any and all negative impacts during construction including Contractor access (vehicular and pedestrian), materials storage, and silt-laden runoff.

1. Wetlands, and streams outside construction limits.

1.02 ACCESS ROUTES, STAGING, AND STOCKPILE AREAS

A. The staging areas and access routes, indicated on the Contract Drawings, may be used for construction support activities. Additional or different areas are available for staging and/or access routes. The Contractor may request, in writing to the Project Manager, the use of alternate staging areas and/or access routes. The request may be approved, at the discretion of the Project Manager.

B. Staging areas and access routes shall be in compliance with applicable permit conditions.

C. Access routes through water are limited to routes described in the permits, unless otherwise approved by the Project Manager and/or designee.

D. Use only established roadways, parking areas, and haul routes, or temporary roadways, parking areas, or haul routes constructed by the Contractor when and as authorized by the Project Manager and/or designee.

E. Unavailability of access routes or limitations thereon shall not become a basis for claims for damages or extension of time for completion of Work.

F. Staging and stockpile areas are limited to the areas shown on Contracting Agency approved staging plan. The Contractor’s use of these areas shall be limited to purposes directly related to the construction of this project. Prior to mobilization, the Contractor shall submit a proposal for review by the Contracting Agency of these (and other) areas indicating specific use, access, restoration, and anticipated duration of use. No use of these areas is permitted until the Contracting Agency provides written approval of the Contractor’s proposal.

G. The Contractor may provide legal staging and storage areas off site at the Contractor’s discretion. The Contractor shall provide the Contracting Agency with locations for approval and shall protect downstream areas by covering or otherwise containing stockpiles of loose materials.

Page 17: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 14 00—Work Restrictions

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 14 00 - 3

1.03 RESTORATION CLAUSE

A. Restore all areas disturbed by the construction process. All ingress or egress points that are disturbed and that are to remain shall be regraded, reseeded, replanted, or repaved to restore them to original or better conditions.

B. Unless otherwise designated, protect all fencing on site from potential Contractor damage above and below grade. If unavoidable damage occurs, notify the Designer immediately and a decision will be rendered as to how the Contractor is to replace or repair the damage at the Contractor’s expense.

C. Unless otherwise designated, protect all existing trees on site in accordance withSection 32 93 10 – Vegetation Protection and Restoration.

1.04 NEW AND EXISTING WORK

A. Unless otherwise noted, new Work in extension of existing conditions shall correspond to similar existing conditions in material, workmanship, and finish. Existing work shall be cut, drilled, altered, removed or temporarily removed, and replaced for performance of Work under the Contract. Work replaced shall match similar existing work. Work remaining in place damaged during this Contract shall be restored to the condition at time of award of Contract, or replaced with new Work as determined by the Engineer and/or designee. Patch existing Work as required for proper interface.

1.05 SUSPENSION OF WORK BY CONTRACTING AGENCY

A. The Contracting Agency may order all or any part of the Work suspended for such period as deemed proper because of unsuitable weather or such other conditions beyond the control of the Contractor that prevent satisfactory and timely performance of the Work, or because of the failure of the Contractor to perform any provisions of the Contract or orders given to him/her. The Contractor shall not suspend Work unless ordered or authorized to do so by the Contracting Agency, and the Contractor shall immediately comply with such an order when given. The Contractor shall resume the suspended Work when ordered by the Contracting Agency to do so.

1.06 EQUIPMENT STANDARDS

A. All equipment furnished or installed under this Contract shall meet safety requirements of all applicable codes.

1.07 PARKING

A. Parking for personnel on the project site will be limited to an area within the project boundaries. The Contracting Agency shall designate this area and coordinate with the Contractor. The Contractor will be responsible for ensuring that no nuisance is

Page 18: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 14 00—Work Restrictions

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 14 00 - 4

created for the Property Owner or for adjacent properties through use of the streets for parking for workers.

1.08 TRUCK AND EQUIPMENT ACCESS

A. To avoid traffic conflict with local residents, and to avoid overloading of streets and driveways elsewhere on the project property, access of trucks and equipment will be limited to a route as approved by the Property Owner prior to mobilization.

B. Vehicular traffic is limited to the area within the project limits except areas designated for access.

C. The Contractor shall meet jurisdictional conditions for use of existing roadways and haul routes, including seasonal or other limitations or restrictions, payment of excess size and weight fees, and posting of bonds conditioned upon repair of damage.

D. The Contractor shall comply with applicable local regulations for haul routes over public highways, roads, or bridges.

1.09 PERMIT RESTRICTIONS

A. The Contractor shall comply with all conditions in approved permits.

P A R T 2 – PR ODU C TS

2.01 MATERIALS

A. Materials to maintain and repair existing roadways, parking areas, and haul routes will be used in accordance with the requirements of the jurisdictional authority.

B. Materials to construct, maintain, and repair temporary roadways, parking areas, and haul routes will be used as approved by the Project Manager.

P AR T 3 – EXEC UT ION

3.01 EXAMINATION

A. Investigate condition of available public or private roads for clearances, restrictions, bridge-load limits, bond requirements, and other limitations that affect or may affect access and transportation operations to and from the job site.

3.02 ESTABLISHED ROADWAYS AND PARKING AREAS

A. Established roadways and parking areas are available for the Contractor’s use subject to existing restrictions and approval of the Project Manager.

Page 19: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 14 00 -5

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 14 00—Work Restrictions

B. Designated areas of existing parking facilities may be used by construction personnel. Temporary parking areas shall meet the following requirements:

1. Arrange for temporary parking areas to accommodate use of construction personnel.

2. Provide additional off-site parking when site space is not adequate.

3. Locate as approved by the Project Manager.

3.03 HAUL ROUTES

A. Perform Work on rights-of-way established by the Project Manager as necessary to construct and maintain any roads, bridges, or drainage structures required for establishment and use of haul routes for construction operations.

B. Use existing available public highways, roads, or bridges as haul routes subject to applicable local regulations.

C. Minimize interference with or congestion of local traffic.

3.04 MAINTENANCE

A. Maintain roadways, driveways, parking areas, and haul routes in a sound, reasonably serviceable condition.

B. Maintain roadways, driveways, and parking areas until completion and acceptance of all Work under this Contract.

C. Maintain surfacing of gravel-surfaced roads and parking areas in a serviceable condition until completion and acceptance of all Work under this Contract.

3.05 REPAIR

A. Promptly repair ruts, broken pavement, potholes, low areas with standing water, and other deficiencies to maintain roadway and driveway surfacing and drainage in original or specified condition.

3.06 REMOVAL

A. Remove materials used to construct temporary roadways, parking areas, and haul routes prior to Contract completion and stabilize the soil.

END OF SECTION

Page 20: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

0122 00-1

DIVISION 01- GENERAL REQUIREMENTSSection 01 22 00 –Measurement and Payment

GENE R A L

1.01 SUMMARY

A. This section includes administrative and procedural requirements for Measurement and Payment, including unit prices.

1.02 PROCEDURES

A. Measurement and Payment

1. Refer to individual specification sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those sections. Unit priced items shall be separately identified and reimbursed in the Schedule of Values and Pay Estimate forms, in accordance with applicable Contract requirements.

B. The Contracting Agency reserves the right to reject the Contractor’s measurement of work-in-place that involves use of established unit prices and to have this Work measured, at the Contracting Agency’s expense, by an independent surveyor acceptable to the Contractor.

PR ODU C TS

Not used

EXEC UT ION

Not used

END OF SECTION

Page 21: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 32 13-1

DIVISION 01- GENERAL REQUIREMENTSSection 01 32 13 –Progress Schedules

P AR T 1 – GENER A L

1.01 SCHEDULE

A. General Requirements

1. Scheduling the Work shall be the responsibility of the Contractor. The construction of this Project shall be planned and tracked by use of a schedule, which shall be prepared, maintained, and regularly updated by the Contractor.

2. The Contracting Agency’s review and acceptance of any schedule shall not transfer any of the Contractor’s responsibilities to the Contracting Agency or to the Engineer. Acceptance implies only that the Contracting Agency has determined that the Schedule submittal, with any noted exceptions, is within reasonable conformity to the requirements of the Contract. Acceptance of any schedule shall not relieve the Contractor ofits responsibility to complete the Work within the required Contract Time.

3. All schedules shall meet these general requirements.

END OF SECTION

Page 22: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 33 10—Submittals

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 33 10 - 1

P AR T 1 – GENER A L

1.01 DESCRIPTION

A. This section includes administrative and procedural requirements for submittal of Shop Drawings, Product Data, Samples, the Submittal Schedule, and other miscellaneous administrative and quality control submittals.

1.02 RELATED SECTIONS

A. The following sections contain requirements that relate to this section:

01 32 13 – Progress Schedules01 35 29 – Health and Safety01 57 19 – Temporary Environmental Pollution Control01 57 24 – Temporary Water Pollution Control01 71 23 – Field Engineering and Surveying01 78 00 – Project Closeout05 17 00 – Structure Connections06 13 43 – Large Woody Materials31 23 00 – Excavation and Fill31 23 19 – Dewatering

1.03 SUMMARY

A. Submittal Schedule: The Submittal Schedule shall document the Contractor’s planning for the timely execution of the Work, in accordance with the Construction Contract and submittal requirements set forth in this section.

B. Shop Drawings include, but are not limited to, the following:(Note: standard information prepared without specific reference to the Project is not Shop Drawings).

1. Fabrication drawings

2. Installation drawings

3. Setting diagrams

4. Shopwork manufacturing instructions

5. Templates and patterns

6. Schedules

Page 23: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 33 10 - 2

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 33 10—Submittals

C. Product Data include, but are not limited to, the following:

1. Manufacturer’s product data

2. Manufacturer’s installation instructions

3. Catalog cuts

4. Roughing-in diagrams and templates

5. Standard wiring diagrams

6. Printed performance curves

7. Operational range diagrams

8. Mill reports

9. Standard product operating and maintenance manuals

D. Samples include, but are not limited to, the following:

1. Partial sections of manufactured or fabricated components

2. Components used for independent inspection and testing

E. Quality control submittals include, but are not limited to, the following:

1. Design data

2. Certifications

3. Manufacturer’s instructions

4. Manufacturer’s field reports

F. Administrative Submittals: Refer to other Division 01 sections and other Contract Documents for requirements for administrative submittals. Such submittals include, but are not limited to, the following:

1. Permits

2. Applications for payment

3. Performance and payment bonds

4. Insurance certificates

5. Listing of subcontractors

Page 24: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 33 10—Submittals

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 33 10 - 3

1.04 DEFINITIONS

A. Days: Calendar days.

B. Required Submittal Number (RSN): RSN identifies items to be submitted together as a complete submittal.

C. Field Samples are full-size physical examples erected on site to illustrate finishes, coatings, or finish materials. Field Samples are used to establish the standard by which the Work will be judged.

D. Mock-ups are full-size assemblies for review of construction, coordination, testing, or operation; they are not Samples.

1.05 SUBMITTAL REQUIREMENTS

A. In case of conflict between the requirements of this section and requirements included elsewhere in these Specifications, requirements listed elsewhere shall take precedence.

B. Professional Certifications

1. Sign and seal submittals requiring certification by a Washington State registered professional, in accordance with Washington State codes and laws.

C. Contract Drawings and Data

1. Prepare Contract Drawings and data in written English and U.S. customary units.

2. Label Contract Drawings and data with the Bid Document Number, ProjectTitle, and Bid Schedule item number(s).

3. Mark items to be furnished on manufacturer’s data for commercial products or equipment, such as catalog cut sheets. Identify manufacturer’s name, type, model, size, and characteristics. Illustrate that the product or equipment meets the requirements of these Specifications.

4. Contract Drawings

a) Minimum identification in title block:

1) Bid Document Number and Project title2) Contractor’s or supplier’s title and Contract Drawing

number

Page 25: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 33 10—Submittals

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 33 10 - 4

b) Size: D size or smaller

c) Draw to scale with neat lettering using drafting equipment or computer-aided drafting equipment.

d) Measurement units: U.S. customary units

1.06 SUBMITTAL SCHEDULE

A. Prepare a complete Submittal Schedule and submit it at the Pre-constructionMeeting for the Contracting Agency’s and Engineer’s review.

1. Coordinate the Submittal Schedule with the List of Subcontractors and the List of Material Suppliers, as the well as the Contractor’s Construction Schedule.

2. Incorporate the Submittal Schedule in the Contractor’s ConstructionSchedule.

B. Prepare the Submittal Schedule in chronological order. Provide the following information:

1. Schedule date for the first submittal

2. Related section number

3. Submittal category (e.g., Shop Drawings, Product Data)

4. Name of the subcontractor

5. Description of the part of the Work covered

6. Scheduled date for resubmittal

7. Scheduled date for the Contracting Agency’s final release or approval

C. Distribution

1. Following the Contracting Agency’s response to the initial Submittal Schedule, print and distribute copies to the Engineer, Contracting Agency, subcontractors, and other parties required to comply with submittal dates indicated. When revisions are made, distribute to the same parties.Delete parties from distribution when they have completed their assigned part of the Work and are no longer involved in construction activities.

Page 26: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 33 10—Submittals

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 33 10 - 5

D. Schedule Updating

1. Revise the Schedule after each meeting or other activity where revisions have been recognized or made. Issue the updated Schedule prior to the next regular project meeting.

1.07 SUBMITTAL PROCEDURES

A. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column of Table 013310A – List of Submittals. A complete set includes all listed items for RSNs with multiple parts. Note:

1. If a submittal is required for a product or material not proposed for use in this Contract by the Contractor, the Contractor shall submit a letter with the correct RSN and indicate that the product or material is not proposed for use in this Contract.

B. Coordination

1. Coordinate preparation and processing of submittals with performance of construction activities. Transmit each submittal to the Contracting Agency sufficiently in advance of schedule performance of related construction activities to avoid delay.

a) Coordinate each submittal with other submittals and related activities that require sequential activity, including the following:

1) Testing

2) Purchasing

3) Fabrication

4) Delivery

5) Other submittals and related activities that require sequential activity

b) Coordinate transmittal of different types of submittals for the same element of the Work and different elements of related parts of the Work to avoid delay in processing because of the Contracting Agency’s need to review submittals concurrently for coordination.

1) The Contracting Agency reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

Page 27: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 33 10—Submittals

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 33 10 - 6

c) Processing: To avoid the need to delay installation as a result of the time required to process submittals, allow sufficient time for Contractor’s review prior to submittal to the Contracting Agency, and for Contracting Agency’s review of submittal, including time for re-submittals.

1) Allow 10 working days for the Contracting Agency’s review. Allow additional time if the Contracting Agency must delay processing to permit coordination with subsequent submittals. The Contracting Agency will advise the Contractor when a submittal being processed must be delayed for coordination.

2) Where necessary to provide an intermediate submittal, process the intermediate submittal in the same manner as the initial submittal.

3) Allow 5 additional working days for reprocessing each submittal.

4) No extension of contract time will be authorized because of the Contractor’s failure to transmit submittals to the Contracting Agency sufficiently in advance of the Work to permit processing.

C. Submittal Preparation

1. Place a permanent label or title block on each submittal for identification:

a) Indicate the name of the firm or entity that prepared each submittal on the label or title block.

b) Provide a space approximately 4 by 5 inches (100 by 125 mm) on the label or beside the title block to record the Contractor’s review and approval markings and the action taken by the Contracting Agency.

c) Include the following information on the label for processing and recording action taken:

1) Project name

2) Date

3) RSN for each attached submittal

4) Name and address of the Contracting Agency

Page 28: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 33 10—Submittals

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 33 10 - 7

5) Name and address of the Contractor

6) Name and address of the subcontractor

7) Name and address of the supplier

8) Name of the manufacturer

9) Number and title of appropriate Specification section

10) Contract Drawing number and detail references, as appropriate

11) Similar definitive information as necessary

D. Submittal Transmittal

1. Package each submittal appropriately for transmittal and handling.Transmit each submittal from the Contractor to the Engineer and Project Manager. The Contracting Agency will return submittals received from sources other than the Contractor.

a) Record relevant information and requests for data on the transmittal form. On the form, or an attached separate sheet, record deviations from the requirements of the Contract Documents, including minor variations and limitations.

b) Include the Contractor’s certification stating that information submitted complies with requirements of the Contract Documents.

E. Placement of Orders for Materials and Components: Do not place orders for materials or components before receipt of reviewed and accepted submittal for same from the Contracting Agency.

Table 013310A – List of Submittals

RSN Submittal title

SubmittalRequirements

Summary Submittal DueNo. of Sets to Provide

01 32 13-1 Progress Schedule Not more than 10 days afterContract is executed

5 or ElectronicPDF Format

01 35 29-1 Health and SafetyPlan

See Section 01 35 29 Not less than 5 days following notice to proceed

5 or ElectronicPDF Format

01 57 13-1 Temporary Erosion and Sediment Control Plan

See Section 01 57 13, if required by permits

Not less than 10 days prior to mobilization

5 or ElectronicPDF Format

Page 29: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 33 10—Submittals

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 33 10 - 8

RSN Submittal title

SubmittalRequirements

Summary Submittal DueNo. of Sets to Provide

01 57 19-1 Temporary Environmental Pollution Control Plan

Air quality control and noise pollution control

Not less than 10 days prior to mobilization

5 or ElectronicPDF Format

01 57 24-1 Temporary Water Pollution Control Plan

See Section 01 57 24 Within 10 working days of the pre-con meeting

5 or ElectronicPDF Format

06 13 43-1 Large WoodyMaterials

Material sources and species list, see Section

Not less than 10 days prior to delivery to site

5 or ElectronicPDF Format

31 23 00-1 Earthwork Plan See Section 31 23 00 Not less than 10 days prior to mobilization

5 or ElectronicPDF Format

31 23 19-1 Care of Water Plan See Section 31 23 19 Not less than 10 days prior to mobilization

5 or ElectronicPDF Format

1.08 PRODUCT DATA

A. Collect Product Data into a single submittal for each element of construction or system. Mark each copy to show which choices and options are applicable to the project.

1. Where Product Data includes information on several similar products, some of which are not required for use on the Project, mark copies clearly to indicate which products are applicable.

2. Where Product Data must be specially prepared for required products, materials, or systems because standard printed data are not suitable for use, submit as Shop Drawings, not Product Data.

3. Include the following information in Product Data:

a) Manufacturer’s printed recommendations

b) Compliance with recognized trade association standards

c) Compliance with recognized testing agency standards

d) Application of testing agency labels and seals

e) Notation of dimensions verified by field measurement

f) Notation of coordination requirements

Page 30: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 33 10—Submittals

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 33 10 - 9

4. Do not submit Product Data until compliance with requirements of the Contract Documents has been confirmed. Include a signed certificate of compliance with each Product Data submittal.

B. Submittals

1. Submit up to five copies, or an electronic PDF format document, of each required Product Data submittal. One copy will be returned to the Contractor. If the Contractor desires more than one copy back, submit additional copies. Unless the Engineer or Contracting Agency observes noncompliance with provisions of the Contract Documents, the submittal may serve as the final submittal.

C. Distribution

1. Furnish copies of final Product Data submittal to the manufacturers, subcontractors, suppliers, fabricators, installers, governing authorities, and others as required for performance of the construction activities. Show distribution on transmittal forms.

2. Do not proceed with installation of materials, products, and systems until a copy of reviewed and accepted Product Data applicable to the installation is in the Installer’s possession.

3. Do not permit use of unmarked copies of Product Data in connection with construction.

1.09 SAMPLES

A. Submit full-size, fully fabricated Samples, cured and finished in the manner specified, and physically identical with the material or product proposed for use.

1. Mount, display, or package Samples in the manner specified to facilitate review of qualities indicated. Prepare Samples to match the Engineer’s sample where so indicated. Include the following information:

a) Generic description of the Sample

b) Size limitations

c) Sample source

d) Product name or name of manufacturer

e) Compliance with recognized standards

f) Compliance with governing regulations

Page 31: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 33 10—Submittals

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 33 10 - 10

g) Availability

h) Delivery time

2. Submit Samples for review of kind, color, pattern, and texture for a final check of these characteristics with other elements and for a comparison of these characteristics between the final submittal and the actual component as delivered and installed.

a) Where variation in color, pattern, texture, or other characteristic is inherent in the material or product represented by a Sample, submit at least three multiple units that show approximate limits of the variations.

b) Refer to other Specification sections for requirements for Samples that illustrate workmanship, fabrication techniques, and details of assembly, connections, operation, and similar construction characteristics.

c) Samples not incorporated into the Work are the property of the Contractor and shall be removed from the site prior to Substantial Completion.

B. Preliminary Submittals

1. Where Samples are specified for selection of color, pattern, texture, or similar characteristics from a manufacturer’s range of standard choices, submit a single, full set of available choices for the material or product.

a) Preliminary submittals will be reviewed and returned with theEngineer’s marking indicating selection and other action taken.

C. Submittals

1. Except for Samples intended to illustrate assembly details, workmanship, fabrication techniques, connections, operation, and other characteristics, submit three sets of Samples. The Engineer will return one set to the Contractor marked with the action taken, retain one set, and transmit one set to the Contracting Agency.

a) Maintain sets of Samples, as returned by the Contracting Agency, at the Project site, available for quality control comparisons throughout the course of construction activity.

b) Unless the Engineer or Contracting Agency observes noncompliance with the provisions of the Contract Documents, the submittal may serve as the final submittal.

Page 32: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 33 10—Submittals

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 33 10 - 11

c) Sample sets may be used to obtain final acceptance of the construction associated with each set.

D. Distribution of Samples: Distribute additional sets of Samples to the subcontractors, suppliers, fabricators, manufacturers, installers, governing authorities, and others as required for performance of the Work. Show distribution on transmittal forms.

E. Field Samples specified in individual Specification sections are special types of Samples. Comply with Sample submittal requirements to the fullest extent possible. Process transmittal forms to provide a record of activity.

1.10 QUALITY ASSURANCE SUBMITTALS

A. Submit quality control submittals, including design data, certifications, manufacturer’s instructions, manufacturer’s field reports, and other quality control submittals as required under other sections of the Specifications.

B. Certifications: Where other sections of the Specifications require certification that a product, material, or installation complies with specified requirements, submit a notarized certification from the manufacturer certifying compliance with the specified requirements.

1. Signature: Certification shall be signed by an officer of the manufacturer or other individual authorized to sign documents on behalf of the company.

C. Inspection and Test Reports: Requirements for submittal of inspection and test reports from independent testing agencies are specified in Section 01 45 00 – Quality Control.

1.11 ENGINEER’S ACTION

A. Except for submittals for the Record or for information, where action and return of submittals is required, the Contracting Agency will review each submittal, mark to indicate the action taken, and return to the Contractor within 10 working days of receipt of the submittal.

1. Compliance with specified characteristics is the Contractor’s responsibility and not considered part of the Contracting Agency’s review and indication of action taken.

2. If the submittal involves either changes to the Contract Drawings and/or Specifications or contains information not reviewed and approved as part of the Contract Drawings and/or project manual by the Contracting Agency, the Contracting Agency shall also review and approve the submittal. An additional 5 working days will be required for the Engineer’s review.

Page 33: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 33 10—Submittals

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 33 10 - 12

B. Action Stamp: The Engineer will stamp each submittal with a uniform action stamp. The Engineer will mark the stamp appropriately to indicate the action taken, as follows:

1. Final Unrestricted Release: Where submittals are marked “No Exceptions Taken,” the Work covered by the submittal may proceed, provided it complies with the requirements of the Contract Documents. Final acceptance will depend on that compliance.

2. Final-but-Restricted Release: Where submittals are marked “Make Corrections Noted,” the Work covered by the submittal may proceed provided it complies with both the Engineer’s notations and corrections on the submittal and requirements of the Contract Documents. Final acceptance will depend on that compliance.

3. Returned for Resubmittal: When submittal is marked “Revise and Resubmit,” do not proceed with the Work covered by the submittal, including purchasing, fabrication, delivery, or other activity. Revise or prepare a new submittal according to the Engineer’s notations. Resubmit without delay. Repeat if necessary to obtain an action mark that will allow the Work to Proceed.

a) Do not permit submittals marked “Revise and Resubmit” or “Rejected” to be used at the project site or elsewhere where construction is in progress.

4. Other Actions: Where a submittal is primarily for informational or Record purposes or for special processing or other activity, the submittal will be returned, marked “Action Not Required,” or “Not Reviewed.”

END OF SECTION

Page 34: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 35 29—Health and Safety

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 35 29 - 1

GENE R A L

1.01 DESCRIPTION

A. This section covers the requirements for compliance with health and safety precautions.

1.02 RELATED SECTIONS

A. Section 01 33 10 – Submittals

1.03 HEALTH AND SAFETY PLAN

A. Within 5 days after receipt of Notice to Proceed, the Contractor shall submit a site-specific Health and Safety Plan (HASP) addressing health and safety management methods specific to the project. The HASP shall, at a minimum, include the following:

1. The name of the individual at the job site responsible for implementation and compliance with this Plan

2. Protection of the public

3. A description of tasks to be undertaken and equipment mobilized for this project

4. A list of all known safety or health hazards, problems, and proposed control mechanisms

5. Safety data sheets (SDS) of and procedures for using, disposing of, or storing all chemicals, products, or materials regulated by Washington Administrative Code (WAC) 296-62 to be used by the Contractor

6. A list of personal protective equipment, monitoring devices, andhazard-specific plans or permits as appropriate and required by state and federal regulations

7. A description of emergency response measures, equipment available for emergency response to address accidents and releases of materials, including, but not limited to, first aid, eye wash/showers, and fire extinguishing equipment, and location of this equipment at the job site

8. Emergency phone numbers, contacts, and location of the nearest medical facility

9. A monitoring and inspection plan and record-keeping measures to ensure that equipment and work practices comply with this Plan

Page 35: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 35 29 - 2

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 35 29—Health and Safety

10. Personnel names and training and notification procedures as appropriate to ensure that all job site personnel are familiar with the Plan elements, including copies of training certificates

11. Procedures for safe storage and handling of flammable liquids, in accordance with WAC 296-24-330

12. If applicable, procedures for safe storage and handling of compressed gasses in accordance with WAC 296-24-295, Compressed Gas General Requirement

13. Accident prevention measures specific to large woody debris (LWD) and engineered log jam (ELJ) structures (Section 35 44 00 – Waterway Habitat Structures). Include details of how the connection material will be handled, cut to length, and installed; how the large woody materials will be handled, assembled, and installed; and how boulders will be positioned and drilled, to minimize the risk to personnel.

14. Other issues that the Contractor determines are appropriate and necessary to protect worker safety and health

1.04 ACCIDENT REPORTING

A. The Contractor shall report to the Project Manager within 24 hours of occurrence any serious accidents such as those resulting in treatment of an injury at a medical facility, response to the site by emergency medical personnel, or damage to property other than that of the Contractor.

B. A copy of each accident report, which the Contractor or subcontractors have submitted to their insurance carriers, shall be forwarded to the Contracting Agency as soon as possible, but in no event later than 5 working days after the accident occurred.

1.05 HEALTH AND SAFETY REPRESENTATIVE

A. The Contractor shall designate a Health and Safety Representative (HSR) and shall ensure that each subcontractor designates a subcontractor’s HSR. The HSR shall be capable of identifying all hazards and have the authority to stop work and take immediate action to correct the hazard.

B. The Contractor shall authorize each such HSR to resolve safety-related issues raised by the Contracting Agency or any of its employees.

C. The Contractor shall ensure that such HSR is present on the Project site whenever the Contracting Agency is present on the Project Site.

Page 36: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 35 29—Health and Safety

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 35 29 - 3

D. Each Contractor’s or subcontractor’s HSR shall identify himself or herself to theProject Manager and/or designee at the daily job briefing conference.

E. The HSR shall verify that all Work is performed in accordance with the HASP.

F. At the daily job briefing conference, the Contractor shall provide the Project Manager and/or designee in attendance at the meeting all relevant information on the Work to be performed, its location, and the equipment to be used.

G. The Contractor shall provide all safety equipment required for the Work.

H. At a minimum, Contractor and subcontractor personnel directly involved in theWork shall have training in the following:

1. First aid, for each Contractor’s and subcontractor’s HSR

2. Confined space work, if the employees will be working in or around confined spaces

3. Shoring and trenching, if Work will be in excavations

4. The Contractor’s procedures for confined space rescues

I. Nothing in this Contract shall be construed as imposing any duty upon the Contracting Agency or any of its employees with regard to, or as constituting any express or implied assumption of control or responsibility over, Project site safety, or over any other safety conditions relating to employees or agents of the Contractor or any of its subcontractors, or the public.

PR ODU C TS

Not used

EXEC UT ION

Not used

END OF SECTION

Page 37: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 42 00—References

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 42 00 - 1

P AR T 1 – GENER A L

1.01 REFERENCES

A. Referenced editions of standard specifications, codes, and manuals form a part of these Specifications to the extent they are referenced.

B. These Specifications take precedence when conflicting requirements occur between these Specifications and a referenced standard.

1.02 JOB SITE REFERENCES

A. The Contractor shall maintain a copy (paper or PDF) of referenced standard Specifications, codes, and manuals required for Work in progress at the site or fabrication site.

1.03 AVAILABILITY

A. Industrial and Governmental Documents

1. Addresses for obtaining some industrial and governmental specifications, standards, and codes are listed in Table 014200A – Addresses for Specifications, Standards, and Codes.

Table 014200A – Addresses for Specifications, Standards, and Codes

Acronym Name and Address Telephone

AASHTO American Association of State Highway and Transportation Officials444 North Capitol Street, NW, Suite 249Washington, DC 20001www.aashto.org

(202) 624-5800 (800) 231-3475

ASTM ASTM International100 Barr Harbor Dr.West Conshohocken, PA 19428-2959www.astm.org

(601) 832-9585

FF and RR Federal Specifications Unit General Services Administration Federal Supply ServiceFSS Acquisition Management CenterEnvironmental Programs and Engineering Policy DivisionWashington, DC 20406

(703) 305-5682

Page 38: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 42 00 - 2

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 42 00—References

Acronym Name and Address Telephone

WSDOT Washington State Department of Transportation Administrative and Engineering Publications P.O. Box 47304Olympia WA 98504-7304www.wsdot.wa.gov/

(360) 705-7430

P AR T 2 – PR ODUC TS

Not used

P AR T 3 – EXEC UT ION

Not used

END OF SECTION

Page 39: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 45 00—Quality Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 45 00 - 1

P AR T 1 – GENER A L

1.01 SUMMARY OF WORK

A. All rejected materials and Work shall be promptly removed by the Contractor from the premises and adjacent surroundings.

B. All rejected Work or materials shall be promptly replaced to the satisfaction of theContracting Agency.

C. When identified in the Technical Specifications, notification shall be provided to the Contracting Agency 48 hours in advance of the time the inspections are needed.

1.02 INSPECTION AND TESTING

A. The Contractor shall furnish samples of materials for testing, if requested by the Contracting Agency, at no additional cost. Tests by the Contracting Agency will be made in accordance with commonly recognized standards of national materials testing organizations and any such other special methods as deemed necessary.

B. Any and all materials necessary for the construction of any part of the Work and associated improvements not specified shall be of the best available quality acceptable to the Contracting Agency.

1.03 SAMPLES

A. The Contractor shall prepare and submit such samples as are required elsewhere in these Specifications at such time as is necessary to allow sufficient time for retesting or modification of the Work, at the Contracting Agency’s discretion, based on evaluation of the samples.

P AR T 2 – PR ODUC TS

Not used

P AR T 3 – EXEC UT ION

Not used

END OF SECTION

Page 40: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 50 00—Temporary Facilities and Controls

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 50 00 - 1

P AR T 1 – GENER A L

1.01 SECTION INCLUDES

A. This Work includes furnishing, installing, operating, maintaining, and removing temporary construction facilities.

1.02 TEMPORARY ELECTRICITY

A. Electric power is not available at the site.

B. Provide generators, transmission lines, distribution circuits, transformers, and other electrical equipment and facilities required for obtaining power and distributing power to points of use.

C. Remove temporary equipment and facilities upon completion of Work under thisContract.

D. Refueling of generators shall be done in spill control areas outside of the ordinary high water line with appropriate spill prevention and containment measures, as designated by the Project Manager.

1.03 TEMPORARY FACILITIES

A. The Contractor shall make all necessary arrangements for temporary water service.All costs thereof shall be borne by the Contractor.

B. Toilet Facilities

1. The Contractor shall provide and maintain adequate chemical toilet facilities for all individuals connected with the Work.

2. The Contractor shall keep the toilet facilities in sanitary condition, in accordance with the County Health Department.

3. The Contractor shall remove the toilet facilities at completion of theContract and shall disinfect the premises.

C. The Contractor shall maintain the construction area in a neat and orderly condition throughout the Contract. Food and garbage shall be stored properly to prevent attracting animals. Remove food and garbage from the site during non-work hours. Practice controls to stop rodent infestation of temporary facilities and the job site.

Page 41: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 50 00 - 2

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 50 00—Temporary Facilities and Controls

D. Staging and stockpiling areas will be determined in the pre-construction conference. Upland site access shall be gained through a stabilized construction access route as shown on the Contract Drawings. Establishment of the primary construction access routes is not a part of this contract. Establishment of additional temporary access routes to reach work items shall be the responsibility of the Contractor.

E. Temporary Buildings: The Contractor may provide temporary buildings, at an approved or designated location, as may be necessary for the performance of the Work. Before Substantial Completion, the Contractor shall remove all temporary buildings.

F. After completion of Work, the Contractor shall remove all temporary facilities and shall restore the temporary facilities area to its original state.

1.04 MATERIAL DELIVERY AND STORAGE

A. Delivery of materials shall be made only during the Contractor’s working hours and at such times as they have a representative available.

B. The Contractor shall store materials within the Work site area in a place determined during the pre-construction conference or designated by the Contracting Agency.

1.05 SUBMITTALS

A. None

P AR T 2 – PR ODUC TS

Not used

P AR T 3 – EXEC UT ION

Not used

END OF SECTION

Page 42: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 13—Temporary Erosion and Sediment Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 57 13 - 1

P AR T 1 – GENER A L

1.01 SECTION INCLUDES

A. This section describes Work consisting of the furnishing, installing, maintaining, removing, and disposing of temporary erosion and sediment control (TESC) and construction stormwater pollution prevention.

B. The TESC shall be designed and implemented to prevent erosion and scour, to treat sediment-laden water for acceptable discharge, and to prevent the conveyance of sediment into surface waters, drainage systems, and environmentally critical areas. It shall be consistent with the Washington State Department of Ecology regulations.

1.02 RELATED WORK

A. Section 01 57 24 – Temporary Water Pollution Control

B. Section 31 10 00 – Site Clearing

C. Section 31 23 00 – Excavation and Fill

1.03 GENERAL

A. During construction, the Contractor shall incorporate practices that prevent erosion, or control erosion when prevention is unavoidable, and shall make every effort to maintain effective erosion and sediment controls throughout the Work, including implementing timely corrective actions as may be necessary. Sediment shall be prevented from entering any surface water, drainage facility, and natural drainage system, and shall be prevented from transport to beyond the Project site. Work shall comply with all permit conditions.

B. If required by the Project permits, the Contractor shall submit to the Contracting Agency for review a Stormwater Pollution Prevention Plan (SWPPP) prepared in accordance with the above regulations and as specified in this section. The TESC Plan shall name and confirm qualifications for the Contractor’s Certified Erosion and Sediment Control Lead (CESCL). The Plan shall be compatible with and shall be coordinated with the Work and Work phasing, ensuring a continuance of protection.

1.04 SUBMITTALS

A. The following submittals shall be provided and approved as required by the Project permits.

B. TESC Plan

Page 43: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 57 13 - 2

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 13—Temporary Erosion and Sediment Control

1. At the preconstruction conference, the Contractor shall be prepared to discuss TESC. Following the outcome of these discussions, the CESCL shall prepare and submit a TESC Plan as indicated in Table 015713A, or unless agreed to otherwise at the preconstruction conference.

2. In Table 015713A, NTPD = Notice to Proceed Date.

3. Time allowed for TESC Plan submittal and Engineer review:

Table 015713A – TESC Plan Submittal and Engineer Review

TESC Plan Submittal Comment

TESC Plan for all Work is due within 10 working days of NTPD

Allow 5 working days for Engineer review

4. Content of the TESC Plan:

a) The TESC Plan shall show, as it relates to the Contractor’s Schedule, the scheduling of installation, maintenance, phasing, and removal of erosion and sedimentation controls as they relate to the Work. Work areas to be addressed in this plan include as applicable:

1) The Project Site, identifying staging, storage, stockpiling, non-Work boundaries, and other construction-related areas

2) Areas beyond the Project site

3) Transportation facilities, including construction traffic routes and access/exit control areas on and off the Project site

4) Environmentally critical areas within or near the Project site, such as geologic hazard areas, flood-prone areas, riparian corridors, wetlands, fish and wildlife habitat conservation areas, and abandoned landfills

5) Inlets, catch basins, ditches, and channels whether dry or water filled, and other surface-drainage facilities

6) Surface waters such as streams, lakes, and other bodies of water

7) Areas of erodible soil not being worked that may be exposed that exceed 4,000 square feet, or may be unprotected or uncovered for more than 2 calendar days

Page 44: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 13—Temporary Erosion and Sediment Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 57 13 - 3

5. Maintaining TESC Plan Current:

a) During the course of the Work, the Contractor and CESCL shall be prepared to discuss with the Engineer the status of TESC controls in progress and to come as they relate to the Work, to the progress schedule, to permits, to Change Order, and as may be required in the Contract.

b) When revisions to the current TESC Plan are required by the Contracting Agency, the Contractor and CESCL shall be prepared to update the TESC Plan as discussed and shall submit the updated TESC Plan to the Contracting Agency within 5 working days unless the Contracting Agency agrees to other arrangements.

P AR T 2 – PR ODUC TS

2.01 STABILIZED CONSTRUCTION ENTRANCE

A. The temporary stabilized construction entrance shall be constructed in accordance with State Standards, prior to beginning any clearing, grubbing, earthwork, or excavation. When the stabilized entrance no longer prevents track out of sediment or debris, the Contractor shall either rehabilitate the existing entrance to original condition, or construct a new entrance.

P AR T 3 – EXEC UT ION

3.01 GENERAL CONSTRUCTION REQUIREMENTS

A. Guiding Regulations, Codes, and Rules

1. Work involving erosion and sedimentation control shall also comply with the requirements of Washington State Department of Ecology’s “Stormwater Management Manual for Eastern Washington” (2004).

B. General Guidelines and Measures for Doing the Work

1. In general, in doing the Work, the Contractor shall address measures that provide the following:

a) Prevent and control erosion and sedimentation processes.

b) Prevent and control scour and scour processes in water-bearing channels.

c) Prevent transport of sediment.

Page 45: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 13—Temporary Erosion and Sediment Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 57 13 - 4

d) Protect surface waters and drainage systems from entry of sediment and other construction byproduct.

e) Prevent erosion and sedimentation impacts to areas not designated for Work.

f) Coordinate erosion and sedimentation controls with scheduling of the Work.

2. Such measures may include, but not be limited to, one or more of the following:

a) Installing temporary ditches, berms, culverts, and other measures to control and redirect surface waters

b) Installing temporary dams, settling basins, energy dissipaters, and other measures to detain water, prevent scour, and allow for sediment drop and controlled removal

c) Installing measures controlling surfacing groundwater and dewatering discharges

d) Installing temporary covers or otherwise protecting slopes, stockpiles, and exposed or disturbed soils from erosion and sediment-producing processes

e) Installing temporary work area perimeter and sediment transport prevention measures, such as silt fence, wattle, filter, and berm

f) Treating sediment-laden waters and removing and disposing of sediment

g) Installing sediment and debris removal controls for equipment entering and leaving designated work areas

h) Installing temporary fencing, flagging, and other markings at boundaries of areas identified as not part of the Work

3.02 STRUCTURAL AND BIOMECHANICAL EROSION CONTROLS

A. Equipment Wash Area

1. Where equipment and vehicular traffic may contribute to the transport of sediment and other debris beyond a work area within the Project site, and beyond the Project site, the Contractor shall have in place a stabilized construction wash area at a location or locations to remove sediment, mud, and other debris from tires and the entire piece of equipment and vehicle.

Page 46: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 13—Temporary Erosion and Sediment Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 57 13 - 5

2. Stabilized construction wash areas shall be in place and ready for operation before the potential for transporting such material occurs.

3. The wash area shall consist of one or more of the following as the Work requires and as the Contract may require:

a) A graded entrance and exit water trough that all equipment and vehicles must pass through. The Contractor may require a water trough for each direction. The depth of water in the trough shall be maintained at a level adequate for the size of equipment and vehicles expected. The length and width of the trough shall be sized to ensure that the entire length and width of equipment and vehicles can be acceptably cleaned.

b) Hose, hose brush, long-handled brush, and similar supplies, and adequate labor to acceptably handle the size and volume of traffic.

c) An adequate source of water and means to contain the water within the designated wash area.

d) Regular removal and disposal of sediment and debris.

e) Removal and disposal of non-debris and non-sediment pollutants and contaminants.

f) A drain, as may be necessary, with controls in place to discharge water complying with regulations, laws, permits, and as the Contract may require.

g) As may be necessary, an area before and after the wash area of sufficient size with quarry spall or other coarse aggregate to allow for after-wash drip collection.

3.03 TEMPORARY SEDIMENT CONTROLS

A. The Contractor shall take measures to prevent the introduction of pollutants, contaminants, sediment, and other material from entering Storm Drain, combined Sewer, and other drainage systems via any entrance vehicle. Sediment prevention for drainage Structures may require one or more sediment sumps, a cover filter, or an outlet pipe cover filter.

B. Filters shall allow the passage of water into or from the drainage Structure without unreasonable backup or ponding, and shall prevent the passage of sediment and other debris.

C. Filters shall be secured to the opening and shall be protected to withstand all loadings and to resist movement, including sediment and debris build-up, flows

Page 47: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 13—Temporary Erosion and Sediment Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 57 13 - 6

typical for the drainage Structure and the local drainage conditions, and the potential for disturbance from construction and traffic activity.

D. Filters covering large areas not having adequate structural support shall be reinforced with and secured to a plastic or wire mesh support backing system.

E. Where filters are expected to be in place for a considerable period of exposure, ultraviolet light resistance and other climate and environmental strengths shall be adequate.

F. Frequency of maintenance shall include removal of sediment and other debris when either the sump build-up reaches approximately 1/3 capacity, or when obstructed filtration or the allowance for the passage of water is causing water backup.

G. Sediment and debris removal shall require additional care to prevent the escape of these materials into the drainage system.

3.04 CONSTRUCTION STORMWATER CONTROL MAINTENANCE

A. The Contractor shall keep a record of the TESC and best management practice (BMP) measures during the entire duration of the Work. Construction Stormwater Control measures shall also be inspected at regular intervals and immediately following significant runoff-producing rainfall events. The individual functions and the whole shall be verified to be performing acceptably, and they shall be maintained until they are no longer needed, or are to be converted as part of a permanent erosion and sediment control when specified in the Contract. The various devices shall be inspected for damage, bypass, undercutting, and non- performance, and shall be promptly repaired. Sediment buildup shall be removed as specified or more frequent intervals when performance becomes questionable. Debris and contaminated sediment shall be properly disposed of. Clean sediments may be stabilized on site as the TESC Plan indicates.

3.05 REMOVAL AND REUSE OF CONSTRUCTION STORMWATER CONTROLS

A. When a TESC feature is no longer required, the Contractor shall remove themeasure or measures.

B. Reuse of a control measure may be acceptable under the following conditions:

1. The measure or device has been thoroughly cleaned of all debris.

2. The measure or device is free of tears, holes, or other damage.

3. The measure is verified it can perform as intended.

Page 48: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 13—Temporary Erosion and Sediment Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 57 13 - 7

3.06 SWEEPING AND WASHING

A. The Contractor shall ensure that soil, debris, or other material tracked and deposited is removed by sweeping or by washing and properly disposed of. In particular, when wet weather is forecast, the CESCL shall verify that all measures are in place and are functioning effectively.

END OF SECTION

Page 49: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 19—Temporary Environmental Pollution Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 57 19 -1

P AR T 1 – GENER A L

1.01 SECTION INCLUDES

A. This section covers the requirements for compliance with environmental precautions and controls.

1.02 RELATED SECTIONS

A. Section 01 33 10 – Submittals

B. Section 01 57 13 – Temporary Erosion and Sediment Control

1.03 SUBMITTALS

A. Within 10 working days of the preconstruction meeting, the Contractor shall submit an Environmental Pollution Control Plan. The Plan shall include:

1. Air quality control, including dust control

2. Noise pollution control

1.04 NOTIFICATIONS RELATIVE TO CONTRACTOR’S ACTIVITIES

A. The Contractor shall plan and schedule Contractor Work activities to conform to and allow time for notifications, approvals, reviews, and other conditions of the Contract Documents.

1.05 REGULATORY REQUIREMENTS

A. Comply with federal, state, and local laws and regulations.

B. Conform to the most stringent requirement in cases of conflict between theSpecifications and regulatory requirements.

C. The Project Manager may stop any construction activity in violation of federal, state, or local laws, and all additional expenses resulting from Work stoppage will be the sole responsibility of the Contractor.

1.06 FIRE ABATEMENT AND SUPPRESSION

A. Comply with federal, state, and local laws and regulations.

B. Provide environmentally compatible fire suppression and abatement during construction.

Page 50: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 19—Temporary Environmental Pollution Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 57 19 -1

1.07 AIR QUALITY

A. The Contractor shall identify those portions of the Work that have the greatest potential to impact air quality.

1. Specific means and methods to prevent and/or control impacts to air shall be described for each such portion of the Work.

B. Do not operate equipment and vehicles that show excessive exhaust gas emissions until corrective repairs or adjustments reduce such emissions to acceptable levels.

C. The Contractor shall maintain air quality within the National Emission Standards for Hazardous Air Pollutants. Air pollutants are defined as that part of the atmosphere to which no ambient air quality standard is applicable, and which, in the judgment of the Administrator of the Environmental Protection Agency Clean Air Act, may cause or contribute to an increase in mortality or an increase in serious irreversible or incapacitating reversible illness.

D. The Contractor shall minimize the potential for air pollution by the use of emission control devices on Contractor-operated equipment and by the shut-down of motorized equipment when not in use.

E. The Contractor shall control dust throughout the Project.

F. No burning, including trash or vegetation, will be permitted.

1.08 LIGHT CONTROL

A. Direct stationary floodlights to shine downward at an angle less than horizontal.

B. Shield floodlights so that floodlights will not be a nuisance to surrounding areas.

C. Direct lighting so that residences are not in direct beam of light.

D. Correct lighting control problems when they occur as approved by the ContractingOfficer.

1.09 NOISE

A. Follow the most stringent of noise restrictions in permits, or state or local regulations.

1. Do not exceed 80 decibels (daytime), as measured at noise-sensitive areas such as residences and schools during the hours of 7:00 a.m. to 7:00 p.m. Do not exceed noise levels of 65 decibels (nighttime) during the hours of7:00 p.m. to 7:00 a.m.

Page 51: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 19—Temporary Environmental Pollution Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 57 19 -1

2. Only construction activities approved by the Project Manager will be allowed during the hours of 7:00 p.m. to 7:00 a.m.

3. Provide specialty mufflers for continuously running generators, pumps, and other stationary equipment to meet the decibel requirements above.

4. Compression brakes are not allowed.

5. Perform operations producing high intensity impact noise only on weekdays during the hours of 7:00 a.m. to 7:00 p.m.

1.10 LIABILITY AND PAYMENT

A. The Contractor shall be liable for the payment of all fines and penalties resulting from failure to comply with the federal, state and local pollution control regulations even though the Contracting Agency and its representatives are on the job at the time of the violation.

B. Except as may be otherwise provided for in the Contract, costs pertaining to the prevention of environmental pollution and the preservation of public natural resources as outlined in the Contract shall be considered as incidental to the Work and such costs shall be included in the Lump Sum Bid.

1.11 DUST CONTROL

A. Use water sprinkling, temporary enclosures, and other methods to limit dust and dirt migration. Comply with all local regulations.

B. Prevent, control, and abate dust pollution on rights-of-way provided by theProject Manager or elsewhere during performance of Work.

C. Provide labor, equipment, and materials, and use efficient methods wherever and whenever required to prevent dust nuisance or damage to persons, property, or activities, including, but not limited to, crops, orchards, cultivated fields, wildlife habitats, dwellings and residences, agricultural activities, recreational activities, traffic, and similar conditions.

D. The Contractor shall be responsible for damages resulting from dust originating from Contractor operations.

P AR T 2 – PR ODUC TS

Not used

Page 52: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 19—Temporary Environmental Pollution Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 57 19 -1

P AR T 3 – EXEC UT ION

3.01 POLLUTION CONTROLS

A. Construction Site Management

1. Contractor construction operations:

a) Perform construction activities by methods that will prevent entrance or accidental spillage of solid matter, contaminants, debris, or other pollutants or wastes into streams, flowing or dry watercourses, lakes, wetlands, reservoirs, or underground water sources. Such pollutants and wastes include, but are not restricted to, refuse, garbage, cement, sanitary waste, industrial waste, hazardous materials, radioactive substances, oil and other petroleum products, aggregate processing tailings, mineral salts, and thermal pollution.

2. Oil/fuel storage tanks management:

a) Storage tank placement: Place oil or other petroleum product (hereinafter referred to collectively as oil) storage tanks or containers at least 20 feet from streams, flowing or dry watercourses, lakes, wetlands, reservoirs, and any other water source in a discharge area.

b) Storage area dikes: Construct storage area dikes at least 12 inches high or graded and sloped to permit safe containment of leaks and spills equal to the capacity located in each area plus a sufficient amount of freeboard to contain the 25-year rainstorm.

c) Diked area barriers: Provide diked areas with an impermeable barrier at least 30 mils (1 mil = 0.001 inches) thick. Provide areas used for refueling operations with an impermeable liner at least 30 mils thick buried under 2 to 4 inches of soil.

d) Underground tank prohibitions: Do not use underground storage tanks.

e) Provide a petroleum product spill clean-up kit in oil storage areas for use by workers in the event of a spill. Report all spills immediately to the Project Manager.

END OF SECTION

Page 53: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 24—Temporary Water Pollution Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 57 24 - 1

P AR T 1 – GENER A L

1.01 SECTION INCLUDES

A. This section covers the requirements for compliance with environmental precautions and controls.

1.02 RELATED SECTIONS

A. Section 01 33 10 – Submittals

B. Section 01 57 13 – Temporary Erosion and Sediment Control

C. Section 31 23 19 – Dewatering

1.03 SUBMITTALS

A. Within 10 working days of the preconstruction meeting, the Contractor shall submit a Water Pollution Control Plan for construction activities in the vicinity of any stream, flowing or dry watercourse, lake, wetland, reservoir, or underground water source. The Plan shall include the following:

1. Name of person who will be responsible for implementing and carrying out the Plan

2. Relationship of methods and descriptions herein to conditions of required permits specified in herein

3. Precautions that will be taken to avoid discharge or accidental spills of pollutants into a river, stream, watercourse, or lake

4. Demonstrated compliance with state and local waste disposal, sanitary sewer, or septic regulations. Methods for preventing or controlling runoff and erosion for construction sites, both during and after construction, including the following:

a) Access and haul roads

b) Stockpile, borrow, and waste areas

c) Construction plant and equipment yards

d) All excavated surfaces

e) Buffer zones

f) Other impacted areas

Page 54: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016Print Date: 12/16/2014

01 57 24 - 2

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 24—Temporary Water Pollution Control

5. Information on vegetative practices, structural control, silt fences, straw dikes, sediment and operator controls, stormwater controls, and solid waste controls. Address stormwater controls for appropriate stormwater management measures including velocity dissipaters. Address solid waste controls for building materials and off-site tracking of sediment.

1.04 NOTIFICATIONS RELATIVE TO CONTRACTOR’S ACTIVITIES

A. The Contractor shall plan and schedule Contractor work activities to conform to and allow time for notifications, approvals, reviews, and other conditions of the Contract Documents.

1.05 REGULATORY REQUIREMENTS AND PERMITS

A. Perform construction operations in such a manner to comply, and ensure subcontractors comply, with the following:

1. Applicable federal, state, and local laws, orders, regulations, and WaterQuality Standards concerning control and abatement of water pollution

2. Terms and conditions of applicable permits issued by permit issuing authority. If conflict occurs between federal, state, and local laws, regulations, and requirements, the most stringent shall apply.

B. The Project Manager, or others, will apply for all necessary environmental permits. A copy of the permits will be provided to the Contractor. The Contractor shall become familiar with permit conditions prior to starting Work and comply with all permit conditions through completion of Work. Any penalties related to violation of permit conditions shall be the sole responsibility of the Contractor.

1.06 WATER QUALITY

A. The Water Pollution Control Plan shall identify the on-site individual responsible for water quality, and specific activities and locations and specific means and methods to prevent and/or control impacts to water quality.

B. The Contractor shall comply with County ordinances, state and federal laws, and other regulations or rules applicable to water pollution occurring in waters of the State and in interstate waters. The Contractor shall:

1. Exercise precautions throughout the life of the Contract to prevent pollution, erosion, siltation, and damage to property.

2. Provide for the flow of all watercourses, including but not limited to streams, ditches, sewers, and drains intercepted during the progress of the Work.

Page 55: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 24—Temporary Water Pollution Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016Print Date: 12/16/2014

01 57 24 - 3

3. Completely restore disturbed watercourses in as good condition as the Contractor found them, or make such final provisions for them as the Contracting Agency may direct.

4. Not obstruct the gutter of any street.

5. Use all proper measures to provide for the free passage of surface water.

6. Remove and dispose of all surplus water, mud, silt, slicking, or other runoff pumped from excavations or resulting from sluicing or pavement cleaning or other operations.

C. The Contractor shall comply with the water quality criteria required by theWashington State Department of Ecology and regulations of the following:

1. Washington Department of Fish and Wildlife

2. Those federal statutes on oil spills enacted under the federal Water Pollution Control Act Amendments of 1972 (a copy of which may be obtained from the U.S. Environmental Protection Agency)

3. The water quality standards of the State of Washington as set forth inChapter 173-201A Washington Administrative Code (WAC)

4. Any local statutes, regulations, ordinances, or rules, which stipulate the various types of discharge prohibited in public sewer systems or any drainage ditch in the local jurisdiction

D. State statutes on water pollution covering liability of the Contractor, penalty for violation, liability and damages for injury or death of fish, animals, or vegetation are set forth in Chapter 90.48 RCW. As an aid to the Contractor, some, though not all, of the rules set forth by the various State departments are summarized below. The Contractor is cautioned, however, that each department of the State may add other restrictions, as they deem necessary, to protect fish and to prevent air or water pollution:

1. Washington Department of Fish and Wildlife: In doing the Work, theContractor shall:

a) Not degrade water quality in a way that would harm fish. (The Washington State Water Quality Regulations will serve as water quality criteria for the Work.)

b) Release into a flowing stream or open water any fish stranded by theWork.

Page 56: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 24—Temporary Water Pollution Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016Print Date: 12/16/2014

01 57 24 - 4

c) Replant any stream bank or shoreline areas if the Work has disturbed the vegetative cover. (Any trees, brush, and grasses used in replanting shall resemble the type and concentration of surrounding vegetation, unless the Contract provides otherwise.)

d) Provide an open-water channel at the lowest level of any isolated pothole remaining when the Work is complete.

e) Protect fish by preventing harmful siltation on the bed or bottom of any body of water.

f) Not block stream flow or fish passage.

g) Keep all equipment out of any flowing stream or other body of water (except as the Contract may permit).

h) Not remove gravel or other bottom material from within thehigh-water flow channel bed of any stream nor from the bottom of any other body of water (except as the Contract may permit).

i) Dispose of any Project debris beyond high-water flows.

2. Washington State Department of Ecology: In doing the Work, theContractor shall:

a) Obtain a waste discharge permit from the Washington StateDepartment of Ecology before:

1) Washing aggregate

2) Discharging water into a ground or surface waterway from pit sites or excavations when the water contains turbidity, silt, or foreign materials

b) Provide the Contracting Agency with a copy of each waste discharge permit before starting the Work.

c) Control drainage and erosion to minimize the pollution of any waterway.

d) Dispose of all toxicants, including creosote, oil, cement, concrete, and water used to wash equipment, in ways that will prevent them from entering State waters.

e) Dispose of all debris, overburden, and other waste materials in ways that will prevent them from entering State waters.

Page 57: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 24—Temporary Water Pollution Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016Print Date: 12/16/2014

01 57 24 - 5

E. The Contractor shall perform such temporary work as may be necessary to effectively control water pollution, erosion, and related damage within the Project site or which might be necessary at work areas located outside the Project site. These outside areas may include, but are not limited to, equipment, material, and other storage sites. When temporary control facilities or measures are no longer needed, they shall be removed and the areas restored or finished as designated by the Project Manager and/or designee.

F. If Work is suspended for an extended period of time, the Contractor shall be responsible for controlling erosion, pollution, sedimentation, and runoff during the shutdown period.

G. In addition to other requirements in the Contract, this temporary work shall include, but is not limited to, the following water quality considerations:

1. Diversion of Stormwater: Stormwater shall be diverted around the Project to prevent pickup of silt. This may be accomplished by pumping; improvising ditches; lining channels or by placing metal, plastic, or concrete gravity pipe; constructing ditches, berms, culverts, etc., to control surface water; or constructing dams, settling basins, or energy dissipaters to control downstream flows.

2. Intercepting Groundwater: Surfacing groundwater shall be intercepted and routed around the Project site to prevent silt erosion by the use of gravel trenches, French drain tiles, well points, or interceptor ditch. The Contractor shall provide means of controlling underground water that may be encountered during the Work.

3. Turbid Water Treatment before Discharge: Determination of turbidity in surface waters shall be at the discretion of the Project Manager and/or designee.

a) The term turbidity means the optical property of a sample demonstrating the scattering and absorption of light caused by suspended material, as expressed in Nephelometric Turbidity Units (NTUs) and measured with a calibrated turbidimeter.

b) Discharges to a State waterway caused by aggregate washing, drainage from aggregate pit sites, and stockpiles or dewatering of pits and excavations shall not increase the existing turbidity of the receiving waters.

c) Turbid water from the Project site shall be treated before being discharged into stream or other State waters. Turbidity may be removed by the use of lagoons or holding ponds, settling basins, overflow weir, polymer water treatment, discharging to ground

Page 58: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 24—Temporary Water Pollution Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016Print Date: 12/16/2014

01 57 24 - 6

surface, by percolation, evaporation, or by passing through gravel, sand, or fiber filters.

4. Temporary Erosion Control: Temporary erosion control shall be exercised by minimizing exposed areas and slopes until permanent measures are effective. Plastic sheet covering shall be placed over exposed ground areas to protect from rain erosion. Other alternative methods for erosion control under certain situations may include netting, mulching with binder, and seeding. Should rutting and erosion occur, the Contractor shall be responsible for restoring damaged areas and for cleanup of eroded material, including that in ditches, catch basins, manholes, and culverts and other pipes.

5. Vehicle and Equipment Washing: Water used for washing vehicles and equipment shall not be allowed to enter storm drains, streams, or other State waters unless separation of petroleum products, fresh concrete products, or other deleterious material is accomplished prior to discharge. Detergent solution may be discharged into sanitary sewers or held on the ground for percolation. A recirculation system for detergent washing is recommended. Steam-cleaning units shall provide a device for oil separation.

6. Sewage: If a sanitary sewer line is encountered and repair or relocation work is required, the Contractor shall provide blocking and sealing of the sanitary sewer line. Sanitary sewer flow shall be pumped out, collected, and conveyed or pumped directly to a sanitary sewer system manhole for discharge. The existing sewers shall be maintained by the Contractor without interruption of service by the use of temporary sewer bypasses. In addition, the excavated materials adjacent to and around a rupture of a sanitary or combined sewer pipeline shall be removed to a disposal site. Equipment and tools in contact with the above materials shall be washed by pressure water lines and the attendant wash water discharged into a sanitary sewer line for transmission to a sewage treatment plant.

7. Sawcutting, Planing, and Grinding By-products: The Contractor shall take special precautions to ensure that no concrete, asphalt, concreteby-products, or asphalt by-products from, or used in, the saw-cutting, grinding, or planing of asphalt cement or cement concrete pavements, sidewalks, curbs, etc. are discharged into any storm drain or surface water system. Such discharge is prohibited by Washington State Department of Ecology. If saw-cutting by-products increase the pH of the wastewater, filtering prior to discharge will not be acceptable. Impervious surfaces contaminated with sediment and grit from saw-cutting, planing, or pulverizing operations shall be cleaned by sweepers to prevent contaminants from entering the storm drainage system or surface waters when it rains.

Page 59: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 24—Temporary Water Pollution Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016Print Date: 12/16/2014

01 57 24 - 7

8. Gutters and other Surface Drainage Channels: All construction, demolition, and land-clearing waste and by-product entering gutters and other pavement-surface drainage channels shall be prevented from entering any inlet, catch basin, or other drainage structure or feature. Material shall be removed from drainage channels on a regular basis. If necessary, temporary filters or filter materials shall be placed in drainage channels to prevent the passage of material.

1.07 LIABILITY AND PAYMENT

A. If noncompliance occurs, report noncompliance to the Project Manager immediately (verbally), with specific information submitted in writing within2 calendar days.

B. Nonconformance with applicable federal, state, or local laws, orders, regulations, or Water Quality Standards may result in the Project Manager stopping all site activity until compliance is ensured.

C. The Contractor shall not be entitled to any extension of time, claim for damage, or additional compensation by reason of such a Work stoppage.

D. The Contractor shall be liable for the payment of all fines and penalties resulting from failure to comply with the federal, state and local pollution control regulations even though the Contracting Agency and its representatives are on the job at the time of the violation.

E. Except as may be otherwise provided for in the Contract, costs pertaining to the prevention of environmental pollution and the preservation of public natural resources as outlined in the Contract shall be considered as incidental to the Work and such costs shall be included in the Lump Sum Bid.

1.08 TEMPORARY WATER POLLUTION, EROSION, AND SEDIMENTATION CONTROL

A. Temporary water pollution, erosion, and sedimentation control work shall comply with all applicable permit conditions and the County Stormwater Design Manual, which consist of temporary measures that may be indicated in the Contract, that may be proposed by the Contractor and approved by the Project Manager, or may be ordered by the Project Manager during performance of the Work. This temporary work is intended to provide prevention, control, and abatement of water pollution, erosion, and sedimentation within the limits of the Project, and to minimize damage to the Work, adjacent property, streams, and other bodies of water.

B. Controlling and preventing pollution, erosion, runoff, sedimentation, and related damage may require the Contractor to perform temporary work items including, but not limited to, any of the following:

Page 60: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 24—Temporary Water Pollution Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016Print Date: 12/16/2014

01 57 24 - 8

1. Providing ditches, berms, culverts, and other measures to control surface water

2. Building dams, settling basins, energy dissipaters, and other measures, to control downstream flows

3. Controlling underground water found during construction

4. Covering or otherwise protecting slopes until permanent erosion-control measures are working

C. The Contractor is hereby notified that compliance with these requirements may necessitate performance of certain items of work at a different time or in a different manner than has been considered normal construction practices in the past and that such revisions in scheduling of Work may interfere with said normal construction practices.

D. Therefore, if required by the Contract, the Contractor shall, before starting the Work, submit to the Contracting Agency for approval an effective Temporary Water Pollution, Erosion, and Sedimentation Control Plan. The Plan shall show the scheduling, as it relates to the Contractor’s critical path schedule, for permanent pollution, sedimentation, and erosion control work and for temporary erosion, pollution, and sedimentation prevention control measures the Contractor proposes to take due to the Work on the following:

1. Areas within the limits of the Project site

2. Other work areas outside the Project site

3. Haul roads

4. Adjacent property

5. Streams and other bodies of water

E. The Contractor shall not perform clearing, grubbing or any other earthwork on the Project, other than that specifically authorized in writing by the Contracting Agency, until the Plan has been approved. The Contractor shall revise and bring the Plan up to date whenever the Contracting Agency provides Written Notice requesting revision. The Contractor shall allow the Contracting Agency not less than 5 working days for the review of a submitted Plan, whether the original or revised. The Contracting Agency will not be liable to the Contractor for failure to approve all or any portion of an originally submitted or revised Water Pollution, Erosion, and Sedimentation Control Plan, nor for any delays to the Work due to the Contractor’s failure to submit an acceptable Plan.

Page 61: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 24—Temporary Water Pollution Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016Print Date: 12/16/2014

01 57 24 - 9

F. The Contractor shall coordinate temporary water pollution, erosion, and sedimentation control work with the permanent drainage, sedimentation, and erosion control work that may be specified in the Contract to ensure continuous water pollution, erosion, and sedimentation control is maintained during performance of the Work.

G. If the Contracting Agency orders the Work suspended for an extended time, the Contractor shall make, before the Contracting Agency assumes maintenance responsibility, every effort to control erosion, pollution, sedimentation, and runoff during shutdown.

H. The extent of excavation, borrow, and embankment operations in progress will be limited commensurate with the Contractor’s capability and progress in keeping the finish grading, mulching, seeding, and other permanent pollution, erosion, and sedimentation control measures current according to the accepted critical path schedule. If the Project Manager determines that water pollution or erosion or sedimentation could occur due to seasonal limitations, the nature of the material, or the Contractor’s progress, temporary water pollution, erosion, and sedimentation control measures shall be taken immediately. The Project Manager may require the Contractor’s operations to be scheduled so those permanent pollution, erosion, and sedimentation control features will be installed concurrently with or immediately following grading operations.

I. Under no conditions shall the amount of surface area of erodible earth material exposed at one time by clearing and grubbing, excavation, borrow, or fill within the right of way exceed 18,000 square feet without prior approval by the Project Manager.

J. Permanent pollution, erosion, and sedimentation control work ordered by the Project Manager and not covered in the Bid will be considered extra work and paid for as such. Only pollution, erosion, and sedimentation control included in the Bid Form or designated by the Project Manager and ordered as extra work will be considered permanent control measures.

K. Temporary erosion control, temporary sedimentation control, and temporary water pollution control shall be the Contractor’s responsibility. Costs for temporary erosion control, for temporary sedimentation control, and for temporary water pollution control work will be considered incidental to the Work and such costs shall be included in the Lump Sum Bid.

L. Records of submitted and actual pollution, erosion, and sedimentation controls and plans shall be retained for a period of 3 years after the Completion Date and shall be available at reasonable times and places for inspection by the Project Manager and, when applicable, other entities providing funds for the Work.

Page 62: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 24—Temporary Water Pollution Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016Print Date: 12/16/2014

01 57 24 - 10

1.09 DEWATERING

A. The Contractor shall operate and maintain all pumps, tanks, and other equipment necessary for the environmentally safe removal and disposal of water from the various parts of the work.

B. When discharge of water from the site is subject to approval of any federal, state, or local agency, the Contractor shall be responsible for obtaining such approval before commencing any pumping or de-watering operation.

C. The Contractor shall include a plan to control and treat any wastewater created from dewatering activities in the Water Pollution Control Plan.

P AR T 2 – PR ODUC TS

Not used

P AR T 3 – EXEC UT ION

3.01 WATER POLLUTION CONTROLS

A. Control water pollution by use of sediment and erosion controls, wastewater and stormwater management controls, construction site management practices, and other controls including state and local control requirements.

B. Water Management Controls

1. Use methods of dewatering, excavating, or stockpiling earth and rock materials, which include prevention measures to control silting and erosion, and which will intercept and settle any runoff of sediment-laden waters.

2. Prevent wastewater from general construction activities such as drainwater collection, aggregate processing, concrete batching, drilling, grouting, or other construction operations, from entering flowing or dry watercourses without the use of approved turbidity control methods.

3. Divert stormwater runoff from upslope areas away from disturbed areas.

C. Turbidity Prevention Measures

1. Use methods for prevention of excess turbidity, which include, but are not restricted to, intercepting ditches, settling ponds, gravel filter entrapment dikes, flocculating processes, recirculation, combinations thereof, or methods that are not harmful to aquatic life.

2. Wastewaters discharged into surface waters shall contain the least concentration of suspended material practicable.

Page 63: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 57 24—Temporary Water Pollution Control

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016Print Date: 12/16/2014

01 57 24 - 11

3. If monitoring or inspection shows that the erosion controls are ineffective, mobilize work crews immediately to make repairs, install replacements, or install additional controls as necessary.

4. Remove and properly dispose of sediment from erosion controls once it has reached one-third of the exposed height of the control.

END OF SECTION

Page 64: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 60 00—Product Requirements

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016Print Date: 12/16/2014

01 60 00- 3

P AR T 1 – GENER A L

1.01 DEFINITIONS

Not used

1.02 DELIVERY, STORAGE, AND HANDLING

A. Transport and handle manufactured products in accordance with the manufacturer’s instructions.

B. Store and protect manufactured products in accordance with the manufacturer’s instructions. Obtain these instructions from the manufacturer before delivery of materials to the job site. Maintain a copy of these instructions at the job site.

C. Protect materials subject to adverse effects from moisture, sunlight, ultraviolet light, or weather during storage at the job site.

D. Store curing compounds, sealants, adhesives, paints, coatings, sealers, joint compounds, grouts, and similar products at the temperature and environmental conditions recommended by manufacturer.

1.03 MAINTENANCE

A. Extra Materials

1. Furnish additional maintenance materials specified as “extra materials” in the Specifications. Provide maintenance material identical to installed material and provide from the same manufacture’s production lot as installed material.

2. Package extra materials for storage and label with complete product information on packaging.

3. Deliver extra materials to the job site and place in storage as required by theProject Manager.

P AR T 2 – PR ODUC TS

2.01 MATERIALS

A. Provide materials required for completion of the Work.

B. Provide type and quality described in these Specifications. Make a diligent effort to procure specified materials from any and all sources.

C. Furnish new materials conforming to referenced standard unless otherwise specified.

Page 65: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 60 00—Product Requirements

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016Print Date: 12/16/2014

01 60 00- 3

D. For materials not covered by federal or other specifications, furnish materials of standard commercial quality.

E. If materials to be used deviate from or are not covered by recognized specifications and standards, submit, for approval, justification for and exact nature of the deviation, and complete specifications for materials proposed for use.

F. Make parts accurately to standard gauge where possible.

G. Permanently mark fasteners with a symbol identifying the manufacturer and with symbol(s) indicating grade, class, type, and other identifying marks in accordance with reference or applicable standard.

2.02 SUBSTITUTIONS

A. If materials required by these Specifications become unavailable because ofGovernment priorities or other causes, substitute materials may be used.

B. Obtain written approval to use substitute materials from the Project Manager.State in the request for substitution the amount of the adjustment, if any, to be made in favor of the Project Manager.

C. The Project Manager’s determination as to whether substitution will be permitted, and what substitute materials may be used, shall be final and conclusive.

D. If approved substitute materials are of less value to the Project Manager or involve less cost to the Contractor than specified material, a Contract Documents adjustment will be made in favor of the Project Manager. Where the amount involved or the importance of substitution warrants, a deductive modification to the Contract Documents will be issued.

E. No payments in excess of prices bid in the schedule will be made because of substitution of one material for another or because of use of one alternate material in place of another.

2.03 WORKMANSHIP

A. Accurately manufacture and fabricate materials in accordance with best modern practice and requirements of these Specifications, notwithstanding minor errors or omissions therein.

B. Use liberal factors of safety and adequate shock-absorbing features in designs, especially for parts subjected to variable stress or shock, including alternating or vibrating stress or shock.

C. Include provisions that prevent components from loosening for shock-absorbing

Page 66: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 60 00—Product Requirements

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016Print Date: 12/16/2014

01 60 00- 3

features and parts subject to vibration.

2.04 SOURCE QUALITY ASSURANCE

A. Materials will be subject to inspection at any one or more of the following locations, as determined by the Project Manager:

1. At the place of production or manufacture

2. At the shipping point

3. At the job site

B. To provide for inspection, provide at the time of issuance copies of purchase orders, including Contract Drawings and other pertinent information, covering material on which inspection will be made as advised by the Project Manager, or provide other evidence if such purchase orders are issued verbally or by letter.

C. Inspection of materials at any location specified above or waiving of inspection shall not be construed as being conclusive as to whether materials and equipment conform to Contract Documents requirements, nor shall the Contractor be relieved thereby of the responsibility for furnishing materials meeting the requirements of these Specifications.

D. Acceptance of materials will be made only at the job site.

P AR T 3 – EXEC UT ION

3.01 FIELD QUALITY CONTROL

A. Final inspection and acceptance of materials will be made only at the job site after installation and testing.

END OF SECTION

Page 67: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 71 13—Mobilization

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 71 13 - 1

P AR T 1 – GENER A L

1.01 SCOPE

A. The Work shall consist of mobilizing equipment and supplies and securing bonds and permits necessary to do the Work as stated in the Contract Documents and/or agreement and demobilization of excess materials and equipment from the Work site.

1.02 PAYMENT

A. Mobilization/Demobilization

1. Payment: Lump-sum price offered in the schedule.

1.03 FORCES AND EQUIPMENT

A. Mobilization may include costs for transporting personnel, equipment, operating supplies to the site, establishment of necessary facilities for the Contractor’s operation and any permits, insurance, and/or bonds required to do the Work.

B. Demobilization may include the removal of equipment and facilities that were necessary to do the Work.

P AR T 2 – PR ODUC TS

Not used

P AR T 3 – EXEC UT ION

Not used

END OF SECTION

Page 68: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 71 23—Field Engineering and Surveying

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 71 23 - 1

PART 1 – GENERAL

1.01 GENERAL

A. The Drawings reflect data available at the time of design and may not include all utili-ties, surface features, structures, and other Project site-specific information. Work under this contract occurs in a natural riverine environment; as such, the final location and ele-vation of Work items may differ from that shown on the Contract Drawings and is sub-ject to the discretion of the Engineer and/or Project Manager.

B. The Contracting Agency shall host a site visit for bidders prior to the bid due date. The Contracting Agency shall stake Project elements and Work items at their ap-proximate location prior to the site visit.

C. It is the Contractor’s responsibility to take the necessary measures to avoid damage to existing site elements and to provide protection for and not interrupt utilities that may be present and not accounted for on the Contract Drawings.

D. The Contracting Agency is responsible for surveying that is necessary to complete the Work.

E. Final elevations shall be placed under the direction of the Engineer and/or the Project Manager at locations as shown on the Contract Drawings or as modified by the Engineer and/or the Project Manager.

F. The Contracting Agency is responsible for completing As-Built drawings for the project.

END OF SECTION

Page 69: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 74 00—Cleaning

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 74 00 - 1

PART 1 – GENERAL

1.01 PAYMENT

A. Include prices offered in the Schedule for other items of Work.

1.02 REFERENCES

A. Code of Federal Regulations (CFR)

1. 40 CFR 261.3: Definition of Hazardous Waste

2. 49 CFR 171-179: Transportation – Hazardous Waste Regulations

1.03 DEFINITIONS

A. Hazardous waste: Defined as hazardous by 40 CFR 261.3 or by other federal, state, or local laws or regulations.

1.04 REGULATORY REQUIREMENTS

A. Comply with federal, state, and local laws and regulations.

B. Conform to the most stringent requirement in cases of conflict between the Specifi-cations and regulatory requirements.

1.05 PROJECT CONDITIONS

A. Report waste materials discovered at the job site to the Project Manager.

1. If waste is hazardous, the Project Manager may order delays in time of per-formance or changes in Work, or both.

2. If such delays or changes are ordered, an equitable adjustment will be made in the Contract Documents in accordance with applicable clauses of the Con-tract Documents.

PART 2 – PRODUCTS

Not used

PART 3 – EXECUTION

3.01 TESTS

A. Test unknown waste materials found at the job site that may be hazardous.

Page 70: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 74 00—Cleaning

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 74 00 - 2

3.02 PROGRESS CLEANING

A. Keep the Work and storage areas free from accumulations of waste materials and rubbish.

3.03 FINAL CLEANUP

A. Remove temporary plant facilities, temporary buildings, concrete footings and slabs, rubbish, unused materials, concrete forms, and other similar waste materials that are not part of the permanent Work.

3.04 NONHAZARDOUS WASTE DISPOSAL

A. Combustible waste materials: Dispose by removal from job site. If permitted by local regulatory agencies, landowner, and Project Manager, combustible materials can be burned on site.

B. Noncombustible waste materials: Dispose by removal from the job site.

C. Disposal by Removal

1. Dispose of waste materials at a permitted landfill. Make arrangements with the Project Manager for use of a landfill and pay the required fees.

D. Disposal by burning: Not allowed

3.05 HAZARDOUS WASTE DISPOSAL

A. Recycle hazardous waste whenever possible.

B. Dispose of waste materials known or found to be hazardous at permitted treatment or disposal facilities.

C. Transport hazardous waste in accordance with 49 CFR 171-179.

END OF SECTION

Page 71: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 76 00—Protection of Existing Facilities

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 76 00 - 1

P AR T 1 – GENER A L

1.01 SECTION INCLUDES

A. This section covers the requirements for Contractor’s protection of existing facilities.

1.02 PROTECTION AND RESTORATION OF PRIVATE AND PUBLIC PROPERTY

A. The Contractor shall protect from damage or destruction of private and publicproperty located on or near the Work that is not designated for repair, replacement, or removal. The Contractor shall ensure that interference with the use of such property is minimized.

B. Property includes land; improvements; trees, shrubbery, and landscaping; electric distribution and transmission systems; water distribution and transmission systems; survey markers and monuments; buildings and structures; conduits and pipes; fences; lighting systems, signs, guardrails, pavements, curbs, driveways,sidewalks, traffic buttons, paint striping; and other property of all descriptions whether shown on the Contract Drawings or not.

C. The Contractor shall, at no additional cost to the Contracting Agency, provide and install safeguards acceptable to the Contracting Agency to protect public and private property.

1. If public or private property is damaged or destroyed or its use interfered with by the Contractor, the Contractor’s agents, or the Contractor’s employees, such interference shall be terminated, and damaged or destroyed property shall be repaired and restored immediately to its former condition by the Contractor at the Contractor’s expense.

1.03 PROTECTION AND RESTORATION OF TREES, SHRUBS, AND PLANT MATERIAL

A. Refer to Section 32 93 10 – Vegetation Protection and Restoration.

1.04 PROTECTION AND RESTORATION OF MISCELLANEOUS ITEMS

A. The Contractor shall enclose the Work area by installing and maintaining temporary fencing when Work is within easements or abuts private property.

1.05 UTILITIES AND SIMILAR FACILITIES

A. Contract Drawings included in these Specifications show existing features and equipment but may not show all equipment and materials existing at the job site.

Page 72: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 76 00 - 2

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 76 00—Protection of Existing Facilities

B. Locations and dimensions shown on the Contract Drawings for existing facilities are in accordance with available information obtained without uncovering, measuring, or other verification.

C. Public and private utilities, or their contractors, will furnish all work necessary to adjust, relocate, repair, or construct their facilities, unless otherwise provided for in the Contract.

1. Where it is necessary to remove or relocate private utilities in order to accommodate the Work, the removal or relocation will normally be accomplished in advance of construction.

2. Under some circumstances, however, this removal or relocation may have to be performed concurrent with the Work. In this case, the Contractor shall coordinate the Contract Work with that of the utilities so as to cause the least possible interference with both kinds of work.

3. Where a private utility should have been removed or relocated prior to the Contractor beginning the Work at the point affected, and such work by the utility was not accomplished, the Contractor shall note the presence of the facility and immediately notify the Contracting Agency in writing.

D. Attention is directed to the possible existence of underground facilities that are not shown in the Contract.

1. When the relocation of these facilities is necessary to accommodate the Work, the Contracting Agency will provide for the relocation of these facilities by other forces, or the relocation shall be performed by the Contractor as extra work pursuant to a Change Order.

E. The Contractor is also alerted to the existence of Revised Code of Washington Chapter 19.122, an act relating to underground utilities and prescribing penalties herein prescribing certain notification to be made by the Contractor.

1. Any cost or scheduling impact incurred by the Contractor by reason of Contractor’s required compliance with these statutory and contractual provisions shall be borne by the Contractor.

2. No excavation shall begin until all known facilities near the excavation area have been located and marked.

F. The right is reserved to the Contracting Agency and the owner of utilities, or their authorized agents, to enter upon the right of way for the purpose of making changes, connections, or repairs to their facilities.

Page 73: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 76 00—Protection of Existing Facilities

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 76 00 - 3

1. The Contractor shall cooperate with forces engaged in this work and shall avoid any unnecessary delay or hindrance to work being performed by other forces.

2. It shall be the Contractor’s responsibility to make all notifications and applications needed to effectively coordinate utility and Contractor work.

G. Should the Contractor desire to have an adjustment in line or grade made on a utility or other improvement for the Contractor’s convenience and the rearrangement is in addition to, or different from, that indicated in the Contract, the Contractor shall make all necessary notifications and applications with the owner of the utility for such rearrangement and bear all expenses in connection with that work.

H. Except as otherwise provided herein, all costs incurred by the Contractor in complying with requirements of this section shall be included in the Lump Sum Bid.

I. The Contractor shall call the Utility Location Request Center (One Call Center) at1-800-424-5555 (or 811) for field location of existing utilities not fewer than 2 and not more than 10 business days before the scheduled date for commencement of excavation that may affect underground utility facilities, unless otherwise agreed upon by the parties involved. If the One Call Center is not reachable, notice shall be provided to the individual utility owners of the Contractor’s intent to excavate.

J. Before an excavation begins, the Contractor shall notify the Contracting Agency.

P A R T 2 – PR ODU C TS

Not used

P AR T 3 – EXEC UT ION

3.01 REPAIR

A. Repair, at the Contractor’s expense, damage to existing installations due to the Contractor’s operations or the Contractor’s failure to provide proper protection. At the Project Manager’s option, damage may be repaired by the Project Manager, and the Contractor will be back-charged the repair costs.

B. All areas disturbed by construction shall be returned to the original ground topography before construction ends, unless otherwise shown on the Contract Drawings.

C. If disturbance of private irrigation pipe or installations is required to complete theWork, the Contractor shall replace or repair the existing pipe or installation. The

Page 74: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 76 00—Protection of Existing Facilities

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 76 00 - 4

Contractor shall coordinate replacement, repair, relocation, or removal of existing installations with the private Property Owner and the Project Manager.

3.02 PROTECTION

A. Provide protection for personnel and existing facilities from harm due to the Contractor’s operations. Protection shall be subject to approval of the Project Manager.

B. Arrange protective installations to permit operation of existing equipment and facilities while Work is in progress.

3.03 REMOVAL OF PROTECTIVE INSTALLATIONS

A. Remove protective installations after their purpose has been served. Materials furnished by the Contractor to provide protection remain the property of the Contractor.

END OF SECTION

Page 75: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 78 00 -1

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 78 00—Project Closeout

P AR T 1 – GENER A L

1.01 GENERAL

A. Prior to commencing demobilization, the Contractor shall review all construction elements with the Project Manager and/or designee, who will give approval of the final site review.

B. Final site review approval is contingent on the successful completion of: construction of design elements, cleaning of the site, removal of all construction access routes and staging areas, restoration of areas disturbed by construction activities, and other tasks as outlined in these Specifications and on the Contract Drawings.

1.02 PAYMENT

A. Include prices offered in the Schedule for other items of Work.

1.03 REGULATORY REQUIREMENTS

A. Comply with federal, state, and local laws and regulations.

B. Comply with all construction and Project permits, as applicable.

C. Conform to the most stringent requirement in cases of conflict between theSpecifications and regulatory requirements.

1.04 SUBMITTALS

A. Not Used.

1.05 AS-BUILT DOCUMENTS

A. Not Used

P A R T 2 – PR ODU C TS

Not used

P AR T 3 – EXEC UT ION

A. Final site review shall not commence until the Contractor has satisfactorily completed the construction of all of the design elements as described in these Specifications and as shown on the Contract Drawings or as approved by the Project Manager.

B. Once final site review is approved by the Project Manager, the Contractor may commence demobilization activities.

Page 76: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

01 78 00 -1

D I V I S I ON 01 — GENE R A L R E QU I R EMENTS Section 01 78 00—Project Closeout

END OF SECTION

Page 77: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 05—M E T A LS Section 05 17 00—Structure Connections

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

05 17 00 - 1

P AR T 1 – GENER A L

1.01 DESCRIPTION OF WORK

A. The work described in this section includes furnishing all labor, materials, tools, equipment, and incidentals required for making connections within engineered log jams and for large woody debris features as shown on the Contract Drawings.

B. Note that much of the Work will take place away from existing infrastructure and may require the use of self-powered or generator-powered equipment; all equipment operated in or near natural waterways may be subject to hydraulic permit conditions.

1.02 PAYMENT

A. Include the lump-sum prices in the Schedule for items requiring connections as indicated on the Contract Drawings and described in the Specifications.

B. Includes all labor, equipment, tools, and materials required to drill logs and install rebar for connections as indicated on the Contract Drawings and described in the Specifications, or as required by the Project Manager and/or Engineer.

C. A connection that is judged non-approved by the Project Manager and/or Engineer shall be re-worked by the Contractor at no additional cost, except where the non-approved connection is the fault of the Project Manager and/or Engineer.

1.03 REFERENCES

A. None

1.04 RELATED WORK

A. Work related to this section is described in Section 35 44 00 – Waterway HabitatStructures

1.05 SUBMITTALS

A. Safety Plan

1. The work area, conditions, and type of work required create considerable potential for accidents. See Section 01 35 29 – Health and Safety, for submittal requirements.

Page 78: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

05 17 00 - 2

D I V I S I ON 05—M E T A LS Section 05 17 00—Structure Connections

END OF SECTION

Page 79: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 06— W OOD Section 06 13 43—Large Woody Materials

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

06 13 43 - 1

P AR T 1 – GENER A L

1.01 DESCRIPTION OF WORK

A. Furnish all materials, equipment, and labor necessary to install the large woody materials (LWM) members included in the various structures and features as indicated on the Contract Drawings and as described in the Specifications. Work includes:

1. At the option of the Contracting Agency, the Contracting Agency has elected to do the following:

a) Purchase the full quantity of large woody materials to be used in the Contract.

b) Transport the full quantity of large woody materials to be used in the Contract.

c) Deliver the full quantity of large woody materials to be used in theContract.

2. Where the Contracting Agency has elected to complete the Work described in Part 1.01 A 1, above, those associated costs will not be reimbursed to the Contractor.

3. The Contractor shall be responsible for the care and installation of the large woody materials, once the large woody materials are in his/her possession. Possession of the large woody materials is assumed once the following is accomplished:

a) The Contractor and Project Manager have conducted an inspection and inventory of large woody materials furnished by the Contracting Agency.

4. The Contractor is responsible for ensuring the total quantity of large woody materials is available to complete the Work prior to mobilization, regardless of the quantities that may be provided by the Contracting Agency.

B. Large woody materials are required on the multiple structures, as indicated on theContract Drawings.

C. Large woody materials include the following:

1. Rootwad logs

2. Log poles

Page 80: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

06 13 43 - 2

D I V I S I ON 06— W OOD Section 06 13 43—Large Woody Materials

1.02 MEASUREMENT AND PAYMENT

A. Payment

1. Payment will be made for costs associated with furnishing large woody materials that are accepted. No payment will be made for large woody materials that do not meet the acceptance criteria, except as otherwise approved by the Contracting Agency.

2. Payment includes all labor, equipment, tools, and materials required to furnish and manage the inventory of satisfactory large woody materials.

3. Costs for installation of the large woody materials is covered under the lump-sum prices for items requiring large woody materials, as indicated on the Contract Drawings and described in the Specifications.

4. The Contracting Agency shall replace members of large woody material, at no additional cost to the Contractor, that do not meet the requirements as indicated on the Contract Drawings and as described in the Specifications and have been rejected by the Project Manager.

B. Measurement

1. Large woody materials will be measured based upon the number of members accepted in accordance with the Specifications.

2. Unit of measure shall be “per each.”

1.03 REFERENCES

A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

1. United States Department of Agriculture (USDA)

USDA NRS-38 (2009) Specific Gravity and Other Properties of Wood and Bark for 156 Tree Species Found in North America

B. Abbreviations and Acronyms

1. LWM = large woody material

2. RW = rootwad

3. DBH = diameter at breast height

4. dia. = diameter

Page 81: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 06— W OOD Section 06 13 43—Large Woody Materials

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

06 13 43 - 3

C. Definitions

1. Large woody material: Natural logs meeting the dimensions and characteristics indicated on the Contract Drawings and described in the Specifications.

2. Members: Individual pieces of large woody material.

3. Bole: The trunk of a tree.

4. Rootwad mass: The roots and the flared portion of the tree transitioning between the rootwad mass and the bole.

5. Rootwad log: Large woody material that includes an intact rootwad mass connected to a portion of the bole of the tree. Rootwad logs are typically produced by removing an entire tree including the rootwad mass from the ground, removing the limbs, and cutting the log to a specified length. The principal features and dimensions of a rootwad log are shown below:

6. Log pole: Large woody material consisting of a tree bole with the limbs removed. Log poles include bark and are untreated. The principal features and dimensions of a log pole are shown below:

Page 82: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 06— W OOD Section 06 13 43—Large Woody Materials

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

06 13 43 - 4

1.04 RELATED WORK

A. Work related to this section is described in Section 35 44 00 – Waterway HabitatStructures.

1.05 SUBMITTALS

A. Submit the following in accordance with Section 01 33 10 – Submittals:

1. Product Data

a) Large Woody Materials Sources

1) Source(s) of large woody materials and an inventory of members from the source(s) showing that members meet the requirements for large woody materials, as indicated on the Contract Drawings and as described in the Specifications. Photo documentation of the materials proposed to be furnished is required to be included in the inventory. Submit no later than 21 calendar days prior to mobilization.

b) Species List

1) A list of tree species from which the large woody materials will be harvested shall be submitted to the Contracting Agency prior to transport to the Project site. Prior written approval is required for tree species not listed in the Specifications or indicated on the Contract Drawings.

2. If all large woody materials required under this Contract are furnished by the Contracting Agency and there is no need for the Contractor to furnish additional large woody materials, the Contracting Agency shall provide an inventory of the large woody materials provided for the project to the Contractor.

3. The inventory shall include the length and diameter at breast height or diameter of the large woody material.

1.06 QUALITY ASSURANCE

A. The Contracting Agency reserves the right to inspect the large woody materials at their source(s) prior to purchase of the materials. Purchase shall not proceed if access for inspection by the Project Manager is not granted by the source(s).

B. Large woody materials furnished by the Contracting Agency shall be inspected and inventoried by the Project Manager and Contractor.

Page 83: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 06— W OOD Section 06 13 43—Large Woody Materials

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

06 13 43 - 5

1. Materials that do not meet the requirements indicated on the Contract Drawings and described in the Specifications shall be rejected, unless otherwise approved by the Engineer.

2. Following the inspection, the Contractor shall be responsible for the care and management of the approved inventory of large woody material.

1.07 DELIVERY, STORAGE, AND HANDLING

A. The Contractor shall store large woody materials within the designated staging and/or stockpile areas indicated on the Contract Drawings and as described in the Specifications, or as approved by the Contracting Agency.

B. The Contractor shall protect the large woody materials from theft and damage from fire, breakage during handling, vandalism, and other means that result in the large woody materials not meeting the requirements indicated on the Contract Drawings and as described in the Specifications.

C. The Contractor shall replace, at no additional cost to the Contracting Agency, members of large woody materials that are damaged during handling or placement that had met the requirements indicated on the Contract Drawings and as described in the Specifications.

D. The Contractor is responsible for notifying the Contracting Agency if the total quantity of large woody materials is not available to complete the Work.

E. The Contractor shall handle the large woody material with equipment appropriate for the task. H a ndling s h a ll not d a m a ge the l a r ge woo d y m a t er i a l.

F. The Contractor shall place large woody material into position using appropriate equipment and methods, and shall not drop large woody material into position.

G. Handling and moving large woody material shall not damage existing features or landscapes.

P AR T 2 – PR ODUC TS

Not Used

P AR T 3 – EXEC UT ION

3.01 INSTALLATION

A. Installation of large woody materials involves placing member(s) in accordance with the Contract Drawings and Specifications. Refer to the following sections:

1. Section 35 44 00 – Waterway Habitat Structures

Page 84: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 06— W OOD Section 06 13 43—Large Woody Materials

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

06 13 43 - 6

3.02 ORDERLY WORK AREA AND SITE CLEANUP

A. Maintain neat and orderly storage and work areas, as much as possible. The Contract will not be considered complete until all of the Contractor’s tools, equipment, and property have been removed from the Project site, and the Contractor’s storage and work areas have been properly cleaned up.

B. The Contractor shall collect and properly dispose of remaining materials, debris, and rubbish resulting from stockpiling of large woody materials.

END OF SECTION

Page 85: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 10 00—Site Clearing

Tucannon River PA-24 – 100% DesignPrint Date: 12/16/2014

31 10 00 - 1

P AR T 1 – GENER A L

1.01 DESCRIPTION OF WORK

A. The Work described in this section includes, but is not limited to, site clearing; removal of trees and brush; grubbing, stripping, and stockpiling of native topsoil and groundcover plants; and removal of other miscellaneous items needed to complete construction of the Project.

1.02 RELATED SECTIONS

A. Section 01 50 00 – Temporary Facilities and Controls

B. Section 01 57 13 – Temporary Erosion and Sediment Control

C. Section 01 57 19 – Temporary Environmental Pollution Control

D. Section 01 57 24 – Temporary Water Pollution Control

E. Section 31 10 00 – Site Clearing

F. Section 31 23 00 – Excavation and Fill

G. Section 32 93 10 – Vegetation Protection and Restoration

1.03 EXISTING CONDITIONS

A. It is the responsibility of the Contractor to determine the location of all existing utilities adequately to avoid damage to utilities prior to initiating Work related to this section.

P AR T 2 – PR ODUC TS

Not used

P AR T 3 – EXEC UT ION

3.01 CLEARING

A. Mark clearing units for approval by the Contracting Agency prior to commencing clearing.

B. Preserve and provide protection for the following:

1. Adjacent facilities: Exercise extreme care to prevent damage to adjacent facilities that are to remain.

Page 86: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 10 00 - 2

D I V I S I ON 31 — EA R T H W O R K Section 31 10 00—Site Clearing

2. Monuments: Carefully maintain benchmarks, monuments, and other reference points. If disturbed or destroyed, replace the monument or other reference point at no cost to the Contracting Agency, as directed by the Contracting Agency or representative of the monument agency.

3. Flag existing vegetation to remain: The Contractor shall notify the Contracting Agency 7 calendar days prior to beginning clearing or grading activities. The Project Manager and/or designee will flag existing trees/vegetation to remain within the clearing limits. Any living woody plant that is damaged during construction shall be treated within 24 hours of occurrence. The Contracting Agency shall be notified immediately of any damage incident. Immediately after damage occurs, the Contractor shall perform wound-shaping treatment, which includes, but is not limited to, evenly cutting broken branches, exposed roots, and damaged tree bark. Injured plants shall be thoroughly watered, and additional measures shall be taken, as appropriate, to aid in plant survivability.

4. Salvaged vegetation and materials: The Contractor shall salvage for reuse riparian plants within the project limit lines as shown on the Contract Drawings. Logs may also be salvaged for reuse. The Contractor shall carefully stockpile salvaged materials for later relocation. The Contractor shall exercise care when moving plant materials to avoid breaking branches or breaking roots. Salvaged materials will be reviewed by the Project Manager and/or designee prior to final placement. Any materials deemed unsatisfactory by the Project Manager (due to damage during relocation) shall be replaced with imported material at the Contractor’s expense. If salvaged materials cannot be moved directly to permanent locations, the Contractor shall ensure that stockpile areas are large enough to accommodate materials, and plants are maintained.

C. It is the Contractor’s responsibility to visit the Project site during the pre-bid meeting to generally ascertain vegetation to be removed for construction.

D. Remove vegetation only as required. Do not do an initial general clearing and grubbing of the Project site that leaves areas exposed that will not have immediate follow-up construction.

Page 87: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 10 00—Site Clearing

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 10 00 - 3

E. Clear vegetation and debris adjacent to cut-and-fill sections to a minimum distance of 1 foot outside of slope lines. Do not clear beyond clearing limits shown on the Contract Drawings.

F. All temporary erosion and sediment control measures must be in place prior to clearing and grubbing.

3.02 CHEMICAL CONTROL OF VEGETATION

A. Herbicide application on nuisance vegetation will be allowed with written authorization by the Contracting Agency only. All herbicide applications shall be applied per manufacturer’s instructions.

B. A minimum of two herbicide applications shall occur prior to planting.Applications shall be made a minimum of 2 weeks prior to planting and a minimum of 6 weeks apart.

3.03 GRUBBING

A. In areas indicated for clearing and grubbing on the Contract Drawings, the Contractor shall grub deep enough to remove all roots and other vegetative material or to the depth shown on the Contract Drawings, whichever is greater. This material shall not be used for topsoil. Grub to a minimum of 6 inches below subgrade and remove organic matter from the Project site.

B. Any material not specifically approved by the Contracting Agency for reuse on site shall be removed from the site within 48 hours or less.

3.04 DISPOSAL OF CLEARED MATERIAL AND NATIVE TOPSOIL

A. Remove all cleared material at an approved location. The Contractor, in a manner consistent with all government regulations, shall dispose of the refuse resulting from clearing and grubbing. In no case shall refuse material be left on the Project site or be buried in embankments or trenches on the Project site unless directed otherwise by the Contracting Agency.

B. Native topsoil shall be reused as directed in Part 3.06. Native topsoil removed from existing wetland shall be legally disposed of at an approved off-site location.

Page 88: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 10 00—Site Clearing

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 10 00 - 4

3.05 USE OF CLEARED WOODY VEGETATION

A. Vegetation that is entirely free of weeds, weed seed, or other deleterious material may be reused on site as mulch when and where approved by the Contracting Agency.

3.06 USE OF NATIVE TOPSOIL

A. Use of native topsoil shall be approved by the Contracting Agency.

B. Do not use native topsoil removed by stripping for backfill or constructing embankments.

C. Segregate and stockpile native topsoil for use in restoration work, unless otherwise approved by the Contracting Agency. Spread remaining native topsoil over disturbed construction areas upon completion and acceptance of grading activities. Native topsoil may be used as approved by the Contracting Agency in site grading.

3.07 STOCKPILE

A. Transport and stockpile topsoil as necessary prior to final hauling and placing.

B. Do not compact topsoil in stockpile.

C. Do not stockpile topsoil to be reused on site higher than 3 feet.

D. Protect stockpile from contamination and erosion.

3.08 TREE AND SHRUB PROTECTION

A. Protect trees and shrubs in accordance with Section 32 93 10 – VegetationProtection and Restoration.

END OF SECTION

Page 89: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 23 00—Excavation and Fill

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 23 00 - 1

P AR T 1 – GENER A L

1.01 DESCRIPTION OF WORK

A. The Work described in this section includes, but is not limited to, the following:

1. Site excavation, grading, filling, and compaction as required to achieve the lines and grades shown on the Contract Drawings above the ordinary high water mark (OHWM)

2. Site excavation, grading, and filling as required to achieve the subgrades shown on the Contract Drawings below the OHWM

3. Site excavation, placement, and compaction of backfill material for installation of various structures

4. Other miscellaneous earthwork required to complete the Project

1.02 PAYMENT

A. Include costs for earthwork in the prices offered for other items of Work requiring excavation, backfill, and material disposal. Work includes the following:

1. Excavation, placement of backfill, and compaction of backfill for installation of the various structures

2. Distribution and disposal of excess excavated materials

1.03 RELATED SECTIONS

A. Section 01 33 10 – Submittals

B. Section 01 57 13 – Temporary Erosion and Sediment Control

C. Section 01 57 19 – Temporary Environmental Pollution Control

D. Section 01 57 24 – Temporary Water Pollution Control

E. Section 31 10 00 – Site Clearing

F. Section 31 50 00 – Excavation Support and Protection

G. Section 35 44 00 – Waterway Habitat Structures

Page 90: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 23 00 - 2

D I V I S I ON 31 — EA R T H W O R K Section 31 23 00—Excavation and Fill

1.04 REFERENCES

A. Washington State Department of Transportation (WSDOT) – Standard Specifications for Road, Bridge, and Municipal Construction; and Amendments (current edition)

B. ASTM International (ASTM) D 422 – Standard Test Method for Particle-SizeAnalysis of Soils

C. ASTM D 1557 – Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 pounds per square foot [lb/ft2])

D. ASTM D 2922 – Standard Test Methods for Density of Soil and Soil Aggregate inPlace by Nuclear Methods

E. Occupational Safety and Health Act (OSHA)

1. Construction Industry Standards

2. Occupational Safety and Health Standards

F. Washington Industrial Safety and Health Act (WISHA)

G. Chapter 296-155, Part N, Washington Administrative Code (WAC) – WashingtonSafety Standards for Construction Work; Excavation, Trenching, and Shoring

1.05 DEFINITIONS

A. Additional excavation: Excavation performed for the convenience, fault, or operation of the Contractor beyond specified or directed excavation lines.

B. ELJ: Engineered log jam. ELJ structures (various types) that typically require excavation and backfill/compaction to install the structures to the designelevations shown on the Contract Drawings and as described in the Specifications.

C. Footprint elevation: The design elevation for the bottom of a proposed structure as noted on the Contract Drawings.

D. LWD: Large woody debris. LWD features (various types) that may require excavation and backfill/compaction to install the feature to the design elevations shown on the Contract Drawings and as described in the Specifications.

E. Optimum Moisture Content: Shall be determined in accordance with ASTM D1557 to determine maximum dry density for relative compaction. Determine field moisture content on basis of fraction passing 3/4-inch sieve.

Page 91: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 23 00—Excavation and Fill

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 23 00 - 3

F. Relative Compaction: The ratio, in percent, of as-compacted field dry density to laboratory maximum dry density as determined by ASTM D 1557. Apply corrections for oversize material to either as-compacted field dry density or maximum dry density, as determined by the Project Manager.

1.06 QUALITY ASSURANCE

A. Where compaction is required, the Contractor is responsible for verifying the quality of the Work and shall perform compaction and density tests at the request of the Contracting Agency to check compliance with these Specifications. A copy of the test reports shall be furnished to the Contracting Agency.

B. The Contracting Agency may perform compaction and density tests to verify compliance with these Specifications.

C. The Contractor shall ensure that imported materials are approved by the Project Manager and/or designee before hauling to the site. The Contractor shall ensure that native soils excavated on site are approved by the Project Manager and/or designee before being used as backfill. The Contracting Agency reserves the right to reject materials that, in the opinion of the Project Manager and/or designee, are determined to be substandard for any reason. In the event material is hauled to the site without prior approval and is determined by the Project Manager and/or designee to be unacceptable, all materials shall be removed from the site at no additional cost to the Contracting Agency.

D. The Contracting Agency may require that an independent testing laboratory test imported materials at any time. If the material is found to be non-compliant with the Contract, the Contractor shall bear the cost of testing and removal of all non- compliant materials from the Project site and replacement of the materials with those meeting the requirements of the Contract.

E. It is the responsibility of the Contractor to verify the accuracy of all survey information provided by the Contracting Agency prior to commencing excavations or filling operations. Commencement of these operations constitutes acceptance of the survey information as appropriate to meet the intent of the Contract.

F. Transportation of known or potentially contaminated materials shall be performed by properly licensed, insured, and registered waste haulers that are acceptable to the Contracting Agency and in accordance with applicable local, state, and federal regulations for transportation. Transportation contractors shall submit documentation that demonstrates proper licensing and compliance with applicable WSDOT regulations, as well as a copy of contingency and spill control plans describing measures to be implemented in the event of spills or discharges during material handling and transporting.

Page 92: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 23 00—Excavation and Fill

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 23 00 - 4

G. The Contractor shall schedule a minimum of two inspection times for grading inspection of planting areas by the Project Manager. The first inspection shall occur when approximately one-third of the area is graded to elevations shown on the Contract Drawings. The second inspection shall occur when the grading within the planting area is complete but before grading equipment has been removed from the Project site.

1.07 EXISTING CONDITIONS

A. In the event previously unknown chemical contamination is suspected or detected during excavation, the Contractor shall immediately notify the Contracting Agency.

B. Excavated soils may be used as fill for areas within the project limits only as approved by the Project Manager and/or designee. Soils used as fill for upland areas shall be free of concrete, rubble, asphalt, metal, plastic, glass, or other debris at the discretion of the Project Manager. Soils containing objectionable debris shall either be screened to remove debris or hauled off site for disposal at an approved facility as directed by the Project Manager. Soils placed on site shall be graded and stabilized so as to prevent stormwater runoff from becoming impounded.

C. No documentation regarding existing conditions, in addition to the current survey supplied on the Contract Drawings, is available. It is the Contractor’s responsibility to be familiar with site conditions.

Suspect soils or materials, if encountered in place, shall be left in place until further direction is received from the Contracting Agency. If excavated, the suspect soils or materials shall be carefully segregated and kept in a separate, isolated stockpile that is fully protected against the elements (precipitation,surface water, and wind) until the Contracting Agency has determined appropriate handling and disposal options for the materials. “Suspect soils” are evidenced by one or more of the following:

1. Characteristics (waste drums, tanks, etc.)

2. Visual evidence (discoloration or staining of soil)

3. Odor

4. Development of oily sheen on water in contact with the soil

Page 93: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 23 00—Excavation and Fill

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 23 00 - 5

5. Position near or adjacent to discovered suspect debris, features, items, or structures

1.08 SUBMITTALS

A. The Contractor shall submit the following for approval by the Contracting Agency, in accordance with Section 01 33 10 – Submittals, and as further specified in this section:

1. Earthwork Plan

a) Prior to commencing Work associated with Section 31 10 00 – SiteClearing, Section 32 93 10 – Vegetation Protection and Restoration, and Section 35 44 00 – Waterway Habitat Structures, the Contractor shall prepare and submit an Earthwork Plan for approval by the Contracting Agency. Approval of the plan by the Contracting Agency shall not relieve the Contractor of the responsibility for full compliance with the Contract Documents. The Earthwork Plan shall include, at a minimum, detailed descriptions of the following items:

1) Methods and equipment that will be used for excavation

2) Methods and equipment that will be used for grading and filling to achieve subgrades and grades

3) Methods and equipment that will be used for transport and hauling of excavated materials

4) Sequence and estimated duration of excavation activity, including anticipated cubic yards of excavated materials handled daily

5) Means by which limits and cut depths will be checked and verified by the Contractor

6) Plan for determining the categorization of excavated fill as reusable or non-reusable fill, including the methods for proper moisture conditioning and compaction

7) Means by which the Contractor shall ensure that temporary stockpiles shall be located and controlled, including isolation of stockpiled soil from the environment and preventing unfiltered runoff water from entering site waters

Page 94: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 23 00—Excavation and Fill

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 23 00 - 6

8) Means by which the Contractor shall ensure that sediment and soil stockpiles are protected from erosion, wind, and spillage

b) If the Earthwork Plan is judged unsatisfactory to the Contracting Agency, then it will be returned to the Contractor for amendment and resubmission. No physical work at the site shall be started until the Earthwork Plan is accepted.

2. Imported Materials: The Contractor shall submit a particle gradation analysis in graph and table form, based on applicable standard sieve sizes, for each product imported. Imported products shall be approved by the Contracting Agency prior to being imported to the Project site.

P AR T 2 – PR ODUC TS

2.01 GENERAL

A. Imported materials shall be as shown on the Contract Drawings from sources arranged for by the Contractor and approved by the Contracting Agency.

B. Materials shall be of the quality, size, shape, gradation, or equal to that of the manufacturer as specified herein. During the course of importing materials, the Contractor shall be responsible for continually checking the materials to ensure that they continue to meet the Specifications. The Contracting Agency may request proof of these material checks.

2.02 EXCAVATED MATERIALS

A. The Contractor’s operations in excavations shall be such that excavations will yield as much suitable material for use in permanent construction required under these Specifications as practicable.

B. Place excavated materials that are too wet for immediate compaction temporarily in stockpiles until moisture content is reduced sufficiently to permit them to be placed in embankments.

C. Segregate excavated materials; segregations shall be based on variation of substrate size, shape, and gradation as indicated on the Contract Drawings and described in the Specifications, or at the discretion of the Project Manager and/or Engineer.

2.03 GENERAL BACKFILL MATERIALS

A. Type and amount of material used for backfill, and the manner of placing material, shall be subject to approval by the Project Manager and/or Engineer.

Page 95: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 23 00—Excavation and Fill

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 23 00 - 7

B. Use suitable backfill material from material excavated in required excavations for structures, where possible, and at the discretion of the Project Manager and/or engineer. If sufficient suitable material is not available from on-site excavations, obtain additional material from commercial borrow sources as approved by the Project Manager. The Contracting Agency makes no guarantee that the specified backfill materials are available from materials obtained fromexcavations for structures.

C. Do not use material removed in stripping or high in organic matter for backfill material. Stockpile instead for use as topsoil.

D. Backfill for Structures

1. Backfill to be placed around or within structures shall be suitable native material free of vegetation and other large organics, frozen lumps, wood, concrete, other debris, and rock larger than 24 inches in maximum dimension, unless otherwise approved by the Project Manager and/or engineer. Final backfill shall be approved by the Project Manager/ and/or engineer before placement.

E. Boulders for Backfill and Ballasting of Structures

1. Refer to Section 31 37 00 – Boulders.

P A R T 3 – EXE C U T I ON

3.01 CLEARING AND GRUBBING

A. Clear vegetation within the excavation footprint prior to excavation, in accordance with Section 31 10 00 – Site Clearing.

3.02 STRIPPING

A. Strip areas to remove topsoil prior to excavation, in accordance withSection 31 10 00 – Site Clearing.

3.03 SITE EXCAVATION, GRADING, AND BACKFILL

A. Earthwork – General

1. The Contractor shall notify the Contracting Agency at least 48 hours prior to any excavation.

2. The Contractor shall excavate material encountered within the limits, lines, and grades specified on the Contract Drawings. The Contractor

Page 96: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 23 00—Excavation and Fill

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 23 00 - 8

shall maintain side slopes of excavations so that they remain stable and free of sloughing soil.

3. The Project Manager and/or engineer reserves the right, during progress of Work, to vary slopes, grades, and dimensions of excavations from those specified on the Contract Drawings.

4. Excavation on slopes shall proceed downward, working from the top of slope to toe of slope. As the Work progresses, it is anticipated that some slope material will slough into the cut area. The Contractor shall remove this material and make a final pass with the excavator bucket along the sections’ edges when the excavation is completed to help ensure that proper grades are achieved.

5. The Contractor shall not store any equipment within 5 horizontal feet ofthe upper edge of any excavation or further as deemed necessary for safety reasons. Locate and retain soil materials away from the edge of excavations and drip lines of trees to remain.

6. The Contracting Agency does not represent that excavation performed under these Specifications can be made to or maintained at paylines shown on the Contract Drawings or described in these Specifications.

7. Do not excavate in frozen material without the written approval of theContracting Agency.

8. In performing the excavation, the Contractor shall pay particular attention to the conditions of issued permits and authorizations requiring the minimization of turbidity and siltation and adherence to water quality requirements.

9. Blasting: Not allowed.

B. Over-excavation

1. Removal of materials beyond indicated subgrade elevations or dimensions without specific direction of the Contracting Agency is not authorized. Unauthorized excavation, as well as remedial work directed by the Contracting Agency, shall be at the Contractor’s expense.

C. Grading – General

1. General: Rough grade areas within the limits of grading under this section, including adjacent transition areas. Roughen the finished surface within specified areas. Roughen the finished surface within specified tolerances; create meandering swales and curved slopes between points where

Page 97: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 23 00—Excavation and Fill

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 23 00 - 9

elevations area shown on the Contract Drawings, or between such points and existing grades.

3.04 DEBRIS

A. It is possible that the Contractor may encounter previously buried large debris or riprap that extends above or below the planned excavation grades. Depending upon the factors observed, including the type of the debris and its estimated size, the Project Manager and/or designee may or may not require its removal. Removal volume of this previously buried debris (as opposed to surficial debris) may be treated as an Unforeseen Condition under this contract.

B. Such large debris, other than riprap, shall be disposed at an appropriate off-site location.

C. Riprap shall be incorporated into the interior of the structures, as approved by theProject Manager and/or designee, or disposed of at an appropriate off-site location.

3.05 REUSE OF EXCAVATED SOILS AS ON-SITE FILL

A. Reusable fill shall meet the requirements for General Backfill as defined inPart 2.03 of this section.

B. It is the responsibility of the Contractor to properly store the stockpiled materials.The Contractor shall be responsible for the protection of stockpiled reusable fill from erosion and the effects of inclement weather.

C. It is the responsibility of the Contractor to properly moisture-condition the fill so that it may be reused.

3.06 DISPOSAL OF EXCESS EXCAVATED MATERIALS

A. Excess excavated material from required excavations not suitable for or required for backfill, embankment, and topsoil shall be stockpiled on site above the OHWL or distributed in locations approved by the Contracting Agency.

B. The location of any off-site disposal shall be approved by the Project Manager prior to excavation and disposal of material.

C. Waste areas for excavated materials shall be approved by the Project Manager

and/or designee.

D. Do not waste material by dumping from the top of slope.

E. Grade waste banks to reasonably even and uniform surfaces that blend with the natural terrain.

Page 98: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 23 00—Excavation and Fill

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 23 00 - 10

1. Minimum slope: 2%.

2. Maximum slope: 4 horizontal to 1 vertical (4H:1V).

3.07 PLACING BACKFILL

A. Place backfill to the lines and grades shown on the Contract Drawings or as required by the Project Manager and/or engineer.

B. Place native material backfill within and around structures and features to the depth and lines shown on the Contract Drawings.

C. Where applicable and at the discretion of the Project Manager and/or designee, topsoil shall be replaced to match the grades and lines of the existing bank on either side of the excavation.

3.08 COMPACTION

A. The Contractor shall compact backfill by means of an appropriately sized static, vibratory, or impact type compactor suited to the soil and physical restrictions of the area to be compacted. Although the Contractor is responsible for the selection of the method of compaction, selection of an inappropriate method shall not relieve the Contractor of the responsibility to achieve the specified result. Jetting, sluicing, or water settling will not be permitted.

B. Topsoil shall not be compacted.

C. Compaction testing performed by the Contracting Agency shall not relieve the Contractor of the obligation to place, compact, and test backfill materials as required in accordance with these Specifications.

D. Control soil compaction during construction so as to provide a minimum percentage of density specified for area classification. Do not allow equipment traffic to compact areas beyond specified percentages. Correct over-compaction as directed by the Project Manager and/or designee, including ripping, re-grading, and re- compaction or over-excavation and in-kind replacement per the Contract Drawings.

E. Unless otherwise specified for a specific backfill or fill material, place backfill and fill materials in layers not more than 12 inches in loose depth for material compacted by heavy compaction equipment and not more than 6 inches in loose depth for material compacted by hand-operated tampers.

F. Do not place backfill on surfaces that are frozen, overly wet, or graded inconsistently.

Page 99: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 23 00—Excavation and Fill

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 23 00 - 11

G. Percentage of Maximum Density Requirements: Compact soil to not less than the following percentages for maximum dry density for soils determined in accordance with ASTM 1557 (Modified Proctor).

1. Backfill

a) Structure Backfill – 85 percent

b) Topsoil – N/A

H. Moisture Control

1. Where subgrade or lift of soil material must be moisture conditioned before compaction, uniformly apply water to surface of subgrade, or layer of soil material, to prevent free water appearing on surface during or subsequent to compaction operations.

2. Before compaction, moisten or aerate each layer as necessary to provide optimum content. Compact each layer to required percentages of maximum dry density or relative dry density for each area classification.

3. Do not perform compaction operations on excessively wetted soils.

3.09 PROTECTION

A. To provide adequate protection for compacted backfill around a structure, the Project Manager and/or designee reserves the right to direct the Contractor to place a sufficient amount of backfill or embankment material over compacted backfill within 72 hours after completion of compacting backfill.

3.10 TEMPORARY STOCKPILES

A. The Contractor may elect to establish an area for temporary stockpiling of excavated soils, in preparation for their reuse as on-site fill or their transport from the Project site. The location of this area shall avoid any interference with ongoing traffic and activities at and around the Project site and shall be subject to the written approval of the Contracting Agency.

B. The Contractor shall not stockpile contaminated material on the Project site.

C. Stockpiles shall not be placed within 5 horizontal feet of the upper edge of any excavation. Stockpiles and stockpile areas shall be maintained in good condition and constructed of materials that are compatible with the material being stored.

Page 100: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 23 00—Excavation and Fill

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 23 00 - 12

D. The Contractor shall implement the provisions of the Temporary Erosion and Sediment Control Plan as necessary to prevent loss of stockpiled materials by such events as erosion, spillage, or wind. The Contractor shall also prevent loss of material during transfer of materials to and from the stockpile area from trucks or other selected excavation and hauling equipment.

E. Stockpile excavated native materials meeting the material requirements for products specified as backfill until placed as backfill material.

F. Place, grade, and shape all stockpiles for proper drainage. Protect from wind and moisture with plastic sheeting, and secure sheeting with sand bags or other approved material.

G. Do not compact stockpiled material.

END OF SECTION

Page 101: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 23 19—Dewatering

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 23 19 - 1

P AR T 1 – GENER A L

1.01 GENERAL

A. No geologic or groundwater information is available at the site. The Contractor shall make his/her own investigations and shall determine the extent and difficulty of removal of water from excavations. Surface water is expected to be encountered in portions of the proposed Work along the river and locations along the floodplain.

B. In-stream Work is required for portions of this Contract. The Contractor shall take all necessary precautions for the safety and protection of the construction team, the Public, and the environment.

C. Fish rescue and recovery will be required under this Contract, where fish populations may become detained as a result of the diversion necessary for the proposed Work.

1. The Contractor shall install an approved temporary fish-exclusion fence and construct a native gravel berm to keep fish out of the Work area. Additional and/or other measures may be necessary to meet construction permit conditions.

2. The Contractor shall coordinate Work with the Contracting Agency and its authorized agents and representatives to allow for the timely and proper rescue and recovery efforts of fish within the confines of the Work.

D. Fish rescue and recovery will be completed by the Contracting Agency and/or designee.

E. Should the diversion be removed or breached, fish rescue and recovery must be repeated.

1.02 REFERENCES

A. Section 01 50 00 – Temporary Facilities and Controls

B. Section 01 57 24 – Temporary Water Pollution Control

1.03 PAYMENT

A. Include in applicable prices offered in the schedule for items of Work related to excavation for installation of the various structures and diversion of water.

B. Also include Work coordinated for fish rescue and recovery, by others. Work includes placement of approved fish exclusion measures including, but not limited to, the following:

Page 102: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 23 19 - 2

D I V I S I ON 31 — EA R T H W O R K Section 31 23 19—Dewatering

1. Temporary fish-exclusion fence

2. Contractor’s time to coordinate efforts during fish rescue and recovery, to be done by Others. Time not to exceed 2 days.

1.04 REQUIREMENT

A. Furnish, install, maintain, and operate all necessary pumping and other equipment for removal of water from the various parts of the Work and for maintaining the footprint elevations and other parts of the Work free from water as required for constructing each part of the Work. All water control shall meet the appropriate construction permit conditions and requirements.

1.05 DEFINITIONS

A. Dewatering may include the following:

1. Removal and control of groundwater from pores or other open spaces in soil or rock formations to allow construction activities to proceed as intended; includes relief of groundwater pressure

2. Control and removal of ponding, seeping, or flowing surface water, except as otherwise provided, and emerging subsurface water from excavated surfaces and from precipitation within and adjacent to excavations and construction zones using channels, ditches, gravel drains, gravel blankets, pipes, sumps, pumps, and discharge lines

3. Controlled discharge of effluent waters

1.06 SUBMITTALS

A. Submit in accordance with Section 01 33 00 – Submittals, RSN 31 23 19-1, Care of Water Plan, as follows:

1. Detailed Care of Water Plan for Work related to diverting groundwater and surface water in support of construction activities that will or may encounter and impact groundwater and surface water

2. Name of person who will be responsible for implementing and carrying out plan

3. Relationship of methods and descriptions herein to conditions of required permits specified in herein

4. Detailed sketches or drawings indicating the specific location(s) for the diversion of surface waters and management of groundwater and surface water during excavation and, where applicable, backfill

Page 103: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 23 19—Dewatering

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 23 19 - 3

5. Description of methods to manage diversion of surface waters and groundwater, including methods of discharge for dewatering activities

6. Plan shall be coordinated with the Water Pollution Control Plan or, if required, the Stormwater Pollution Prevention Plan

7. Identify portions of the Care of Water Plan that require coordination with others to complete fish rescue and recovery

P AR T 2 – PR ODUC TS

Not used

P AR T 3 – EXEC UT ION

3.01 DEWATERING

A. Dewatering, when necessary, will be conducted over a sufficient period of time to allow species to naturally migrate out of the Work area and will be limited to the shortest linear extent practicable.

B. Provide, maintain, and operate necessary pumps and other equipment for removal of water from excavations and trenches for the various structures that are to be constructed.

C. Accomplish dewatering, as needed, by use of motor or engine-driven pumps with adequate lift capacity, discharge piping, hoses and piping, valves, and intakes.

D. If a generator is to be used to operate pumping equipment, the generator shall be placed above the high-water line within an approved spill protection area.

E. Monitor and control discharge in accordance with Section 01 57 24 – TemporaryWater Pollution Control and the permits required under that section.

F. Diversion around the construction site may be accomplished with a coffer dam (eco-blocks, bulk bags) and a bypass ditch. Where gravity feed is not possible, a pump may be used but must be operated in such a way as to avoid repetitive dewatering and rewatering of the site. Impoundment behind the coffer dam must occur slowly through the transition, while constant flow is delivered to the downstream reaches.

G. All pumps will have fish screens to avoid juvenile fish impingement or entrainment, and will be operated in accordance with the National Marine Fisheries Service’s (NMFS’s) current fish screen criteria (NMFS 2011, or most recent version). If the pumping rate exceeds 3 cubic feet per second (cfs), a NMFS Hydro fish passage review will be necessary.

Page 104: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 23 19—Dewatering

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 23 19 - 4

H. Dissipation of flow energy at the bypass outflow will be provided to prevent damage to riparian vegetation or stream channel.

I. Safe re-entry of fish into the stream channel will be provided, preferably into pool habitat with cover, if the diversion allows for downstream fish passage.

3.02 DEWATERING BELOW GROUNDWATER LEVEL

A. Where excavation and trenching extends below the groundwater level, dewater the portion below the groundwater level in advance of excavation or as otherwise approved by the Project Manager and/or designee.

B. Dewater to prevent loss of fines from the footprint elevations, maintain the stability of the excavation, and allow construction Work to be performed in the dry.

C. Seepage water will be pumped to a temporary storage and treatment site or into upland areas to allow water to percolate through soil or to filter through vegetation prior to re-entering the stream channel.

3.03 SEEPAGE CONTROL

A. Before excavating to final grade for structures, bring the water level to an elevation at least 1 foot below the required subgrade elevation or as otherwise approved by the Project Manager and/or Engineer.

B. Maintain this water level until structures have been placed, structures have been completed, and backfill has been placed or as otherwise required by the Project Manager and/or Engineer.

C. After backfill has been placed, with approval of the Project Manager and/or designee, allow groundwater to rise to natural levels.

D. Control pumping and dewatering operations so that the groundwater level rises slowly and uniformly along the extents of excavation for each structure.

END OF SECTION

Page 105: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 37 00—Boulders

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 37 00 - 1

P AR T 1 – GENER A L

1.01 DESCRIPTION OF WORK

A. Section includes the following:

B.

1. Boulders, imported

2. Boulders, on-site reuse

A portion of the boulders will be imported to the staging areas by the ContractingAgency. The Contractor will be required to disperse to final placement locationson the construction site.

C. A portion of the boulders will be salvaged from on-site sources.

D. Furnish all materials, equipment, and labor necessary to install boulders included in the various structures and features as indicated on the Contract Drawings and as described in the Specifications. Work includes the following:

1. At the option of the Contracting Agency, the Contracting Agency has elected to do the following:

a) Purchase the full quantity of imported boulders to be used in theContract.

b) Transport the full quantity of imported boulders to be used in theContract.

c) Deliver the full quantity of imported boulders to be used in theContract.

2. Where the Contracting Agency has elected to complete the Work described in Part 1.01 B 1, above, those associated costs will not be reimbursed to the Contractor.

E. All rock shall be placed as described in these Specifications and as shown on theContract Drawings.

1.02 PAYMENT

A. Include “applicable prices offered” in the Schedule for items of Work requiring placement of imported and on-site rock.

B. Include reimbursement of costs for labor, materials, and equipment required to place imported and on-site rock as shown on the Contract Drawings, described in these Specifications, and at the direction of the Project Manager.

Page 106: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 37 00 - 2

D I V I S I ON 31 — EA R T H W O R K Section 31 37 00—Boulders

C. Payment for Work involving placement of native material backfill is described inSection 31 23 00 – Excavation and Fill.

1.03 RELATED SECTIONS

1. Section 05 17 00 – Structure Connections

2. Section 31 23 00 – Excavation and Fill

3. Section 35 44 00 – Waterway Habitat Structures

1.04 REFERENCES

A. Washington State Department of Transportation (WSDOT) – Standard Specifications for Road, Bridge, and Municipal Construction; and Amendments (current edition)

1.05 SUBMITTALS

A. Product Data: The Contracting Agency shall provide the Contractor with a copy of the product data sheet for imported boulders showing they meet the Specifications herein.

P AR T 2 – PR ODUC TS

2.01 IMPORTED BOULDERS

A. Boulders shall be hard, dense, and durable.

1. Minimum specific gravity, ASTM C 97: 2.65

2. Maximum absorption, ASTM C 97: 2%

3. Maximum loss, sulfate soundness, ASTM C 88: 10%

B. Either quarried rock or boulders may be used.

C. Shape

1. Predominantly rounded

2. Predominantly equidimensional or cylindrical

D. Weight

1. The dry weight of the boulder shall meet the dry weight requirements shown on the Contract Drawings for the application.

Page 107: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 37 00—Boulders

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 37 00 - 3

P AR T 3 – EXEC UT ION

3.01 FEATURES TO RECEIVE IMPORTED ROCK

A. Single LWD, TRI LWD, Multi LWD, CH LWD, APEX LWD, SILL LWD and CG Structures

3.02 PLACING

A. Place rock ballast as shown on the Contract Drawings or as directed by theProject Manager and/or designee.

B. Dump and smooth by moving rocks into position so that material when in place is stable and does not tend to slide.

C. Drop height, maximum: 1 foot

D. Leave no unreasonably large, unfilled spaces within any structure.

E. Gaps left between large rocks shall be filled with smaller rock as approved by theProject Manager and/or designee.

END OF SECTION

Page 108: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 31 — EA R T H W O R K Section 31 50 00—Excavation Support and Protection

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 50 00 - 1

P AR T 1 – GENER A L

1.01 GENERAL

A. Section includes requirements for excavation support and protection for trenches and open excavations greater than 4 feet in depth.

1.02 PAYMENT

A. Include cost for excavation support and protection in applicable prices offered in the Schedule for items of Work requiring excavation support and protection.

1.03 REFERENCES

A. The following is a list of standards that may be referenced in this section:

1. Occupational Safety and Health Act (OSHA)

a) Construction Industry Standards

b) Occupational Safety and Health Standards

2. Washington Industrial Safety and Health Act (WISHA)

3. Chapter 296-155, Part N, Washington Administrative Code (WAC) – Washington Safety Standards for Construction Work; Excavation, Trenching, and Shoring

1.04 REQUIREMENTS

A. The Contractor shall be responsible for planning, designing, installing, maintaining, and removing support and protection for excavations and trenches in accordance with Chapter 296-155, Part N, WAC and applicable OSHA and WISHA requirements.

B. Excavation support systems shall be designed and installed to protect surrounding property and structures. Excavation support systems shall also be designed sothat installation and removal of the support systems does not disturb soil adjacent to or below the required excavation or trench section. Excavation and trenching shall be to the lines shown on the Contract Drawings and as specified inSection 31 23 00 – Excavation and Fill.

C. Excavation support systems shall be designed to meet water control requirements, as specified in Section 31 23 19 – Dewatering.

P AR T 2 – PR ODUC TS

Not used

Page 109: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

31 50 00 - 2

D I V I S I ON 31 — EA R T H W O R K Section 31 50 00—Excavation Support and Protection

P AR T 3 – EXEC UT ION

3.01 GENERAL

A. Construct the excavation to the lines and grades shown on the Contract Drawings and as specified in Section 31 23 00 – Excavation and Fill. Install and remove support systems in a manner that avoids disturbing soil adjacent to the trench or below the trench or excavation.

B. Unless otherwise indicated, remove all sheeting, shoring, and bracing after placement and compaction of backfill.

END OF SECTION

Page 110: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 32 — EXTE R I OR I M PR OVEM E NTS Section 32 93 10—Vegetation Protection and Restoration

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

32 93 10 - 1

P AR T 1 – GENER A L

1.01 SUMMARY

A. The Work described in this section includes administrative and procedural requirements for the protection of trees, shrubs, and plant material not designated for removal. Such trees, shrubs, and plant materials shall be left in place and protected from damage or injury by the Contractor during construction using full and adequate methods of protection.

1.02 RELATED SECTIONS

A. Section 31 10 00 – Site Clearing

B. Section 31 23 00 – Excavation and Fill

P AR T 2 – PR ODUC TS

Not used

P AR T 3 – EXEC UT ION

3.01 PRESERVATION AND PROTECTION

A. Preserve natural landscape, and preserve and protect existing vegetation not required or otherwise authorized to be removed.

B. Conduct operations to prevent unnecessary destruction, scarring, or defacing of natural surroundings in the vicinity of the Work.

C. Move crews and equipment within the rights-of-way and over routes provided for access to the Work in a manner to prevent damage to grazing land, crops, or property.

D. Minimize, to the greatest extent practicable, clearings and cuts through vegetation. Irregularly shape authorized clearings and cuts to soften undesirable aesthetic impacts.

E. Do not use trees for anchorages except in emergency cases or as approved by the Project Manager. For such use, wrap the trunk with a sufficient thickness of approved protective material before any rope, cable, or wire is placed.

3.02 PROTECTION WITHIN THE DRIPLINE

A. Where existing trees are within the area of Work or where existing trees outside the area of Work have driplines extending into the area of Work, the Contractor shall employ all methods to minimize adverse impact to these existing trees,

Page 111: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28- Final DesignPrint Date: 3/6/2016

32 93 10 - 2

D I V I S I ON 32 — EXTE R I OR I M PR OVEM E NTS Section 32 93 10—Vegetation Protection and Restoration

including limbs and roots. The Contractor shall notify the Project Manager and/or designee of any construction work within the dripline of trees at least 1 working day before the scheduled activity. These methods may include, but are not limited to, the following:

1. Temporary tie-up of low limbs

2. Application of a 4- to 6-inch-thick layer of mulch (or wood chips salvaged from clearing and grubbing operations) within the dripline of trees

3. Timber or steel planking for protection of surface roots from equipment

4. Tree root pruning or other tree root treatment as directed by theProject Manager

B. No storage of equipment or materials shall be allowed within the dripline of trees not designated for removal. Steel planking, or timber planking made of 4-inch- thick material, each plank covering a minimum of 8 square feet, shall be used to support backhoe and other equipment stabilizers when set within the dripline of a tree or sodded planting strip.

3.03 ABOVE-GRADE WORK

A. When the Contractor anticipates construction operations that will unavoidably affect tree limbs, the Contractor shall notify the Project Manager and/or designee at least 5 working days in advance of commencing such operations.

1. Before trimming any trees, the Contractor shall notify the Project Manager and/or designee of the proposed method and the amount of trimming required.

2. Trimming shall be done in accordance with National Arborist Association tree-pruning standards.

3. Use safety ropes where tree climbing is necessary; do not use climbing spurs.

3.04 TRENCHING AND TUNNELING WITHIN THE DRIPLINE

A. Excavation or tunneling of any kind within the “critical root zone,” as defined by the tree dripline, will not be allowed unless the Contractor requests permission to do so at least 5 working days in advance and receives approval from the Project Manager.

B. Treatment of Roots: Excavation around roots 2 inches in diameter and greater requires handwork.

Page 112: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 32 — EXTE R I OR I M PR OVEM E NTS Section 32 93 10—Vegetation Protection and Restoration

Tucannon River PA-28- Final DesignPrint Date: 3/6/2016

32 93 10 - 3

1. Individual tree roots 2 inches or greater in diameter shall not be cut but, rather, protected when within the dripline of the tree.

2. Tree roots smaller than 2 inches in diameter shall be cleanly cut flush with the edge of the trench or tunnel.

3. Ripping or tearing of tree roots will not be allowed.

3.05 REPAIR, REPLACEMENT, AND PAYMENT FOR DAMAGE

A. Restore construction roads to original contours and make impassable to vehicular traffic when no longer required.

B. Scarify and re-grade, after completion of Work, land used for construction purposes and not required for completed installation so that surfaces blend with natural terrain and are in a condition that will facilitate re-vegetation, provide proper drainage, and reduce erosion potential.

C. Trees authorized to be cut down, in the opinion of the Project Manager, that are damaged or injured beyond saving by Contractor operations, personnel, or equipment must remain on the floodplain where or near where they were felled. Replace removed tree or shrub with tree or shrub approved by the Project Manager.

D. Repair or treat injured vegetation without delay and as recommended by and under direction of an experienced horticulturist or licensed tree surgeon approved by the Project Manager.

E. Trees or other plant material not ordered or designated to be removed but that are destroyed or irreparably damaged by Contractor operations, as determined by the Project Manager, shall be repaired or replaced by the Contractor in accordance with the Project Manager’s recommendations.

1. Replacements shall be of the same species and, as nearly as possible, of the same size as the trees to be replaced.

2. The Contractor shall allow 1 working day advance notice for inspection of nursery stock replacements by the Project Manager.

F. Payment

1. In addition to the Contractor’s restoration approved by the Project Manager, the Contractor will be assessed damages for the difference in the dollar value of the damaged tree, shrub, or other plant material, and the dollar value of the replacement.

Page 113: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 32 — EXTE R I OR I M PR OVEM E NTS Section 32 93 10—Vegetation Protection and Restoration

Tucannon River PA-28- Final DesignPrint Date: 3/6/2016

32 93 10 - 4

2. The dollar value will be determined by the Contracting Agency from the Guide for Establishing Values of Trees and Other Plants (current edition), prepared by the Council of Tree and Landscape Appraisers. Damages assessed will be deducted from moneys due or that may become due to the Contractor.

G. Planting of replacement stock shall be done in accordance with the requirements of the Contract Documents during the first fall or spring planting period, whichever comes first.

END OF SECTION

Page 114: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 35— W AT E RW AY AND MA R I NE C ON S T R U C T I ON Section 35 44 00—Waterway Habitat Structures

Tucannon River PA-28- Final Design Print Date: 3/06/2016

35 44 00 - 1

P AR T 1 – GENER A L

1.01 DESCRIPTION OF WORK

A. In general, the various large woody debris (LWD) and engineered log jam (ELJ) structures provide habitat enhancement and promote desirable geomorphic processes. Specific benefits include but are not limited to hydraulic refuge, cover, food, and shading for the benefit of fish species. The features are composed of large woody materials that interact with the waterway at various stages of flow. The features add roughness to flows and increase hydraulic variability.

B. Note that much of the Work will take place away from existing infrastructure and may require the use of self-powered or generator-powered equipment; all equipment operated in or near natural waterways may be subject to hydraulic permit conditions.

C. The Contractor shall furnish all materials, equipment, and labor necessary for the construction of the LWD and ELJ structures as indicated on the Contract Drawings and as described in the Specifications. Work includes the following as applicable:

1. Working along the river banks, floodplain, and side channels.

2. Clearing and grubbing and stripping areas to be excavated as indicated on the Contract Drawings and described in the Specifications, or as required by the Project Manager and/or designee.

3. Where applicable, excavation to partially bury the LWD or ELJ structure as indicated on the Contract Drawings and described in the Specifications, or as required by the Project Manager and/or designee.

4. Installing the large woody material members to the locations, extents, elevations, lines, and grades indicated on the Contract Drawings and as described in the Specifications. Installation includes the following:

a) Cutting large woody material members, as necessary, to the dimensions indicated on the Contract Drawings and as described in the Specifications, or as approved by the Engineer and /or designee.

b) Placing large woody material members in the locations and positions and to the dimensions and elevations indicated on the Contract Drawings and as described in the Specifications, or as approved by the Engineer and/or designee.

c) Connecting overlapping and/or overlying large woody material members together and to boulders or trees as indicated on the Contract Drawings and as described in the Specifications, or as

Page 115: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 35— W AT E RW AY AND MA R I NE C ON S T R U C T I ON Section 35 44 00—Waterway Habitat Structures

Tucannon River PA-28- Final Design Print Date: 3/06/2016

35 44 00 - 1

approved by the Engineer and/or designee.

Page 116: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

35 44 00 - 2

D I V I S I ON 35— W AT E RW AY AND MA R I NE C ON S T R U C T I ON Section 35 44 00—Waterway Habitat Structures

5. Placing boulders within or around the Structures to the positions and to the elevations indicated on the Contract Drawings and as described in the Specifications, or as approved by the Engineer and/or designee.

6. Placing logging slash and small woody debris within the structure and along the exterior rootwad masses as indicated on the Contract Drawings and as required by the Project Manager and/or designee.

7. Backfilling to the elevations, lines, and grades indicated on the Contract Drawings and as described in the Specifications, or as approved by the Engineer and/or designee.

8. Restoration of areas disturbed by construction as directed by theProject Manager and/or designee.

1.02 MEASUREMENT AND PAYMENT

A. Include the “per each” prices in the Schedule for Installation of the following Single LWD, BE LWD, TRI LWD, Multi LWD, APEX LWD, CG and CH LWD. The “per each” price shall include all Work indicated on the Contract Drawings and described in the Specifications herein with the following exceptions:

1. Clearing and grubbing and stripping are covered under Site Preparation.

2. Restoration of areas disturbed by construction is covered under SiteRestoration.

1.03 REFERENCES

A. None

1.04 RELATED WORK

A. The provisions and intent of the Contract, including the General Conditions, Supplementary Conditions, and General Requirements, apply to this Work as is specified herein. Work related to Waterway Habitat Structures is described in the following sections:

01 57 13 – Temporary Erosion and Sediment Control01 57 19 – Temporary Environmental Pollution Control01 57 24 – Temporary Water Pollution Control01 71 23 – Field Engineering and Surveying01 76 00 – Protection of Existing Facilities05 17 00 – Structure Connections06 13 43 – Large Woody Materials

Page 117: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 35— W AT E RW AY AND MA R I NE C ON S T R U C T I ON Section 35 44 00—Waterway Habitat Structures

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

35 44 00 - 3

31 10 00 – Site Clearing31 23 00 – Excavation and Fill31 23 19 – Dewatering31 37 00 – Boulders31 50 00 – Excavation Support and Protection

1.05 SUBMITTALS

A. Submit the following in accordance with Section 01 33 10 – Submittals:

1. Safety Plan: The work area, conditions, and type of work required create considerable potential for accidents. Refer to Section 01 35 29 – Health and Safety for submittal requirements.

1.06 QUALITY ASSURANCE

A. The Contracting Agency reserves the right to inspect the LWD and ELJ structures throughout the construction process.

P AR T 2 – PR ODUC TS

2.01 LARGE WOODY MATERIALS

A. The Contractor shall meet the requirements indicated on the Contract Drawings and as described in the Specifications. Refer to Section 06 13 43 – Large Woody Materials.

2.02 LOGGING SLASH AND SMALL WOODY DEBRIS

A. Logging slash and small woody debris shall be sourced and furnished from locally available materials meeting the following requirements:

1. Cut limbs, small trees, and tops with branches that are generally long, slender, and branched.

2. Material ranging in diameter between 1 and 12 inches.

3. Material ranging in length between 2 and 12 feet.

B. Waste woody material generated during the construction may be used. Waste woody material generated during the construction may include but is not limited to the following:

1. Field cutting of individual large woody materials, as required for the proper fit in accordance with the Contract Drawings and Specifications, herein.

Page 118: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 35— W AT E RW AY AND MA R I NE C ON S T R U C T I ON Section 35 44 00—Waterway Habitat Structures

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

35 44 00 - 4

2. Surplus materials or rejected materials that do not meet the dimensions indicated on the Contract Drawings and described in the Specifications, herein. Surplus materials must be approved by the Project Manager and/or designee for placement as logging slash and small woody debris.

C. The Project Manager and/or Engineer shall approve the logging slash and small woody debris for placement within the features described, herein.

2.03 CONNECTION HARDWARE

A. The Contractor shall meet the requirements indicated on the Contract Drawings and as described in the Specifications. Refer to Section 05 17 00 – Structure Connections.

2.04 BOULDERS

A. The Contractor shall meet the requirements indicated on the Contract Drawings and as described in the Specifications. Refer to Section 31 37 00 – Boulders.

2.05 BACKFILL

A. The Contractor shall meet the requirements indicated on the Contract Drawings and as described in the Specifications. Refer to Section 31 23 00 – Excavation and Fill.

P AR T 3 – EXEC UT ION

3.01 SITE PREPARATION

A. The Engineer is responsible for surveying and staking the location of the Waterway Habitat Structures in accordance with the Contract Drawings and Section 01 71 23 – Field Engineering and Surveying.

B. Implement diversion and care of water measures, as necessary, to remain in compliance with construction permit conditions and requirements. Measures may include, though are not limited to, surface water diversion and dewatering for excavation. Refer to Section 01 57 24 – Temporary Water Pollution Control.

C. Clear and grub and strip the feature excavation footprint as necessary. Vegetation removal shall be minimized to the extent practicable. Removal of trees largerthan 3 inches in diameter at breast height shall require approval from theProject Manager. Refer to Section 31 10 00 – Site Clearing.

Page 119: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 35— W AT E RW AY AND MA R I NE C ON S T R U C T I ON Section 35 44 00—Waterway Habitat Structures

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

35 44 00 - 5

3.02 EXCAVATION

A. General

1. Excavate the structure footprint as indicated on the Contract Drawings to the bottom design elevation. Native materials excavated shall be stockpiled separately from stripped topsoil. Refer to Section 31 23 00 – Excavation and Fill.

2. The Contractor is responsible for dewatering the excavation. Refer toSection 01 57 24 – Temporary Water Pollution Control.

3. The Contractor is responsible for excavation support and protection.Refer to Section 31 50 00 – Excavation Support and Protection.

4. Excavation into the channel bank shall be minimized to the extent practical. Trenching for the placement of large woody materials is one method to minimize disturbance to the bank.

5. Native materials excavated, if suitable, shall be used to backfill the feature, unless otherwise indicated on the Contract Drawings or described in the Specifications, or as required by the Project Manager and/or designee.

B. Single, TRI, MULTI, APEX and CH LWD

1. Placement of the rootwad and boulders may require limited excavation.

2. Excavation is generally required for features in areas not located adjacent to existing trees. Excavation is required to bury the pole end of the rootwad log as indicated on the Contract Drawings.

3. Features located adjacent to existing trees do not require excavation as long as they can be secured to the adjacent trees as indicated on the Contract Drawings.

C. Channel Grade (CG) and BE LWD

1. Excavate to the design elevation for the bottom of the structure as indicated on the Contract Drawings or as approved by the Engineer.

Page 120: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 35— W AT E RW AY AND MA R I NE C ON S T R U C T I ON Section 35 44 00—Waterway Habitat Structures

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

35 44 00 - 6

2. If bed rock is observed at the structure location or is encountered during excavation, the Contractor shall immediately notify the Project Manager and/or designee. Adjustments to the structure configuration where bedrock is encountered shall be as approved by the Engineer.

3. A large depression shall be excavated (as depth to bedrock allows) from existing grade at the upstream end of the structure and continue along the sides of the structure; the depression shall be excavated to the elevations, grades, and lines as indicated on the Contract Drawings.

3.03 INSTALLATION

A. General

1. The Contractor is responsible for installing the structures at the location, elevations, and extents indicated on the Contract Drawings; the location of the structures may vary from the Contract Drawings under the direction of the Engineer and/or designee.

2. The structures shall be installed to the elevations staked in the field

3. Place the individual members of large woody material comprising the bottom layer of the structures to the bottom design elevations indicated on the Contract Drawings. Variations in diameter of the large woodymaterial members may require localized adjustments to the bottom grade.

4. The natural variations in large woody material may cause members to roll, pitch, and/or yaw when placed atop another member. Dry-fit placement of members prior to preparing the connection shall be performed to ensure a snug and stable fit.

5. Individual members of large woody material may require field cutting to maintain the structure alignment and design elevations. Field cutting of rootwad logs shall be allowed only as approved by the Project Manager and/or engineer.

6. The natural variations in large woody material may cause members to roll, pitch, and/or yaw when placed atop another member. Dry-fit placement of members prior to preparing the connection shall be performed to ensure a snug and stable fit.

7. Complete all connections as approved by the Contracting Agency.

Page 121: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 35— W AT E RW AY AND MA R I NE C ON S T R U C T I ON Section 35 44 00—Waterway Habitat Structures

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

35 44 00 - 7

B. Single, TRI, Multi, APEX and CH LWD

1. All TRI LWD, MULTI LWD will be field-located by the Engineer and/or Project Manager at the time of construction.

2. For features in areas adjacent to existing trees:

a) The feature shall be placed at existing grade and the large woody material members shall contact the existing trees on alternating sides in at least two locations along the member. The log end closest to the center of flow line shall be placed on the upstream side of the tree.

b) The feature shall be anchored as directed by the Engineer and/or designee.

C. CG and BE LWD

1. Place the bottom members of the structure at the design elevations.

2. Place proceeding layer members, maintaining the spacing indicated on theContract Drawings.

3. Make rebar connections between the members at the corners of the structure as indicated on the Contract Drawings.

4. Continue to place, then connect subsequent layer members.

5. Complete the placement of members to meet the design elevation of the structure or as otherwise approved by the Project Manager and/or Engineer.

6. Complete the connections on the top corners of the structure. Finish the connection as indicated on the Contract Drawings and described in the Specifications. Project Manager and/or Engineer shall approve the connections.

7. Finish backfilling the structure; refer to Part 3.04, Backfill.

3.04 BACKFILL

A. Backfill the structures in accordance with Section 31 23 00 – Excavation and Fill.

B. Native materials excavated shall be used to backfill the structure, unless otherwiseindicated on the Contract Drawings or described in the Specifications, or as directed by the Contracting Agency.

Page 122: snakeriverboard.orgsnakeriverboard.org/wpi/wp-content/uploads/2018/03/Tu... · Web viewDIVISION 01- GENERAL REQUIREMENTS. Section 01 22 00 –Measurement and Payment. DIVISION 01—GENERAL

D I V I S I ON 35— W AT E RW AY AND MA R I NE C ON S T R U C T I ON Section 35 44 00—Waterway Habitat Structures

Tucannon River PA-28 – 100% DesignPrint Date: 3/06/2016

35 44 00 - 8

C. Backfill of the structure shall occur in sequences, as the structure is completed in layers.

1. Backfill level shall not at any time be more than two layers below the uppermost working layer, unless otherwise approved by the Project Manager and/or designee.

D. The Contractor is advised to backfill only following completion of an approved connection.

1. Backfilling prior to completion of an approved connection may affect the alignment and effectiveness of a connection.

2. If the Contractor elects to backfill the structure prior to the approval of connection(s),the Project Manager and/or designee may require the Contractor to remove the backfill to rework the connection, at no additional cost to the Contracting Agency.

E. Backfill structure with the material to the lines, elevations, and grades as indicated on the Contract Drawings and described in the Specifications.

F. Remaining excavated native materials shall be distributed locally, unless otherwise approved by the Engineer and/or Project Manager.

3.05 COMPLETION

Not Used

3.06 ORDERLY WORK AREA AND SITE CLEANUP

A. Maintain neat and orderly storage and work areas, as much as possible. The Contract will not be considered complete until all of the Contractor’s tools, equipment, and property have been removed from the Project site, and the Contractor’s storage and work areas have been properly cleaned up.

B. The Contractor shall collect and properly dispose of remaining materials, debris, and rubbish resulting from stock piling of large woody materials.

C. Special care shall be taken to ensure that no foreign materials fall into or contaminate project waters.

END OF SECTION