28
Presented by: Matthew Kwong, Yarra Trams (Keolis Downer) Tony Makowsky, LB Foster Rail Technologies Wayside Top of Rail Friction Control: An embedded track solution in a high density tram network A presentation to: AusRAIL PLUS 2019 ICC Sydney, RTAA Stream, Wed 4 th December 2019

Wayside Top of Rail Friction Control

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Wayside Top of Rail Friction Control

Presented by: Matthew Kwong, Yarra Trams (Keolis Downer) Tony Makowsky,LB Foster Rail Technologies

Wayside Top of Rail Friction Control:An embedded track solution in a high density tram network

A presentation to: AusRAIL PLUS 2019ICC Sydney, RTAA Stream,Wed 4th December 2019

Page 2: Wayside Top of Rail Friction Control

Presentation Overview

1. Introduction / Problem background

2. Initial remediation measures

3. Top-of-Rail (TOR) friction modifiers as a solution

− Preliminary investigation tasks and results

4. Embedded track TOR equipment solution− Equipment design

− Installation details

5. Noise monitoring− Data collection methodology

− Noise reduction results

6. Conclusions / Next steps2

Page 3: Wayside Top of Rail Friction Control

Trams in Melbourne

3

200 million+passenger trips per year

5,000+services per day

2,000+employees

1,750+tram stops

475+trams

250kmof double track

Ninedepots

• Yarra Trams (Melbourne, VIC) - World’s largest operational tram network

• Current tram franchise operated and maintained by Keolis Downer

• 75% of tram network shares operating space with other vehicles

Page 4: Wayside Top of Rail Friction Control

Trams in Melbourne

• St. Kilda Road - Busiest tram corridor with head ways approximately every minute during peak hours

• Mixed tram types operating through eight routes:

– High floor Comeng fleets (A, B and Z Class trams)

− Low floor Siemens fleets (D Class trams)

4B CLASS D CLASS

A CLASS Z CLASS

Page 5: Wayside Top of Rail Friction Control

Problem Background

• Emergence of atypical wheel squeal events following St. Kilda Road track realignment accommodating new underground station project

• Predominantly occurring in longer and shallower 80-90m radius curves in both Inbound and Outbound tracks along St. Kilda Road

• Noise events were not linked to a specific tram type or number

5

* Problem noise locations shown in orange *

Page 6: Wayside Top of Rail Friction Control

Initial Remediation Measures

• Water spray cart to temporarily wet and lubricate the tracks

• Rail grinding restoring the rail head to the target design profile

• Crack sealant application introducing flexibility into the embedded track structure

6

Lack of success with initial remediation measures lead to investigation of TOR

friction modifiers as a possible solution

Rail GrindingCrack Sealant

Page 7: Wayside Top of Rail Friction Control

TOR Friction Modifiers as a Noise Solution

• Top-of-Rail (TOR) squeal - Use a friction modifier (FM) to:

− Reduce coefficient of friction (CoF) on the TOR to 0.3 - 0.4

− Create positive friction conditions to eliminate stick-slip oscillations

• KELTRACK® Trackside Transit (KTT) nominated as the FM for use:

− Water-based product with proven positive friction characteristics

− No adverse impacts to vehicle braking or traction

− Water component rapidly evaporates, leaving a thin dry film on the top of rail surface

− Environmentally friendly, non-volatile and non-flammable

− Noise abatement effectiveness range typically 250-300m

7

10L PAIL

19L PAIL

Page 8: Wayside Top of Rail Friction Control

Common Causes of Wheel / Rail Noise

1. Gauge Face (GF) Flanging

I. ‘Buzzing’ or ‘hissing’ sound

II. Broadband high frequency = 5000 – 20,000 Hz

III. Caused by friction between the wheel flange and rail gauge face

2. Top-of-Rail (TOR) Squeal

I. High pitched, tonal squeal

II. Predominantly 1000 – 5000 Hz frequency

III. Caused by stick-slip oscillations due to creep forces and negative friction

8

Page 9: Wayside Top of Rail Friction Control

“Dry” Wheel / Rail Interface

9

Body 1 (Wheel)

Body 2 (Rail)

3RD Body Interface

Transition

Transition

Relative Motion (Accumulating Creepage)

Brittle “High Hardness” Wear Particles (Fe3O4)

Fric

tion

Forc

e

“DRY” Wheel / Rail

(not to scale)

1 2 3 4

1 4

slipadhRolling

Direction

• Relative wheel/rail motion (creepage) accommodated by:

1. Rolling2. Elasticity3. Breaking4. Void collapse

Creepage

Page 10: Wayside Top of Rail Friction Control

“KELTRACK® treated” Wheel / Rail Interface

10

Body 1 (Wheel)

Body 2 (Rail)

3RD Body InterfaceTransition

Transition

Relative Motion (Accumulating Creepage)

Fric

tion

Forc

e

Creepage

“DRY” Wheel / Rail

KELTRACK®

Conditioned

• KELTRACK® creates a composite deformation mechanism

• Pliable FM particles provide an elastic shear displacement accommodation mechanism that negates/arrests brittle particle breaking and void collapse

Brittle “High Hardness” Wear Particles (Fe3O4)Pliable “Soft” FM Particles

Reduced wear particle generation

(not to scale)

Page 11: Wayside Top of Rail Friction Control

Preliminary Investigation Tasks

Phase 1: FM Impacts to Tram Braking and Traction

• KTT manually applied to top of rail of New Preston Depot Stabling track (tangent segment)

• B and D Class trams tested under the following conditions:1. Dry conditions without KTT

2. Dry conditions with KTT manually applied

3. Wet conditions - Water sprayed on top of manually applied KTT to mimic heavy rainfall conditions

• Several test runs conducted applying service and emergency braking at different tram speeds

• No adverse impacts to tram stopping distance or tractive effort observed during testing

11

Friction Modifier Manual Application Method

New Preston Depot Stabling Track

Page 12: Wayside Top of Rail Friction Control

Preliminary Investigation Tasks

Phase 2: FM Effectiveness on Wheel Squeal Reduction

• One D Class Tram tested on mainline track at St. Kilda Road -Outbound track reverse curve segment used as trial location

• FM manual application method and three test conditions identical to Phase 1 Tram braking and traction investigation

• KTT manually applied in dry conditions demonstrated immediate benefit - No wheel squeal events

• KTT in wet conditions produced similar favourable results –Indicated suitable resiliency under heavy rainfall conditions

• Business case funded for an automated application system

12

Manual Application of KTT on St. Kilda Rd

Page 13: Wayside Top of Rail Friction Control

Preliminary Investigation Results

0

10

20

30

40

50

60

70

80

90

1000

1250

1600

2000

2500

3150

4000

5000

6300

8000

1000

0

L Zeq

, 1s

(dB)

Frequency (Hz)

64

66

68

70

72

74

76

78

80

82

84

1 2 3 4 5 6 7

L AFm

ax(d

BA)

Noise collection number

Phase 2 success leads to approval of an embedded track TOR application system as a permanent noise solution for St. Kilda Rd

Red - Pre-mitigation Blue - Post-manual KELTRACK® TT application Yellow - Post-manual KELTRACK® TT application + water

13

Maximum A-weighted Noise Levels for a 1 sec Period- D Class Test Tram

1/3 Octave Frequency Spectra - D Class Test Tram

Page 14: Wayside Top of Rail Friction Control

TOR Equipment Design

• Incorporation of an embedded track TOR application system type-approved as the permanent noise solution

• Includes robust steel enclosures and lids protecting key system components (TOR bars, Tram sensor, etc.) after embedded concrete to surface track structure is restored

• Customized site design accommodated customer-specific operating conditions:

− Track structure design

− Vehicle wheel circumference

− Design and construction standards

− Road vehicle, Bicycle, Pedestrian Traffic

14

Page 15: Wayside Top of Rail Friction Control

TOR Equipment Design

• 95 litres FM product tank capacity

• 4ea. TOR distribution bars mounted on field side

− 915mm length

– 2ea. per rail side

• Solar-DC powered (80W solar panel + 12amp VR)

• Field side-mounted Tram sensor – Vibration triggers one FM discharge (X seconds) per Tram

• Remote Performance Monitoring (RPM) hardware for offsite system status health checks

LB Foster PROTECTOR® IV (PIV) DC Solar TOR unit selected for use:

15

Page 16: Wayside Top of Rail Friction Control

TOR Equipment Installation

• St. Kilda Road wayside TOR equipment installation work was performed in three main phases:

– Phase 1: Pre-installation site mock-up review

– Phase 2: Inbound track installation and commissioning

– Phase 3: Outbound track installation and commissioning

• Phase 1 work proven to be a critical pre-installation knowledge-sharing exercise amongst project stakeholders:

– Confirmed as-designed locations for TOR equipment components were suitable for use

– Identified minor enclosure design issues requiring correction

– Improved understanding of responsibilities between work crews

– Partial assembly of TOR equipment also completed

16

SITE MOCK-UP

Page 17: Wayside Top of Rail Friction Control

TOR Equipment Installation – Inbound Track

• Phase 2 (Inbound Track) and Phase 3 (Outbound Track) installation works each completed over a four day period

• Main scope of works:

– Site excavation

– TOR equipment fitting

– Concrete restoration

– Final commissioning

• Work performed primarily during regularly scheduled non-operating night time hours

DAY 1

17

DAY 2

DAY 3

DAY 4

Page 18: Wayside Top of Rail Friction Control

TOR Equipment – Completed Installations

INBOUND TRACK

18

OUTBOUND TRACK

STAGE ONE REALIGNMENT

Page 19: Wayside Top of Rail Friction Control

Noise Monitoring

Data Collection Methodology

• Information recorded for each data collection cycle:

− Tram type - A/Z, B or D class

− Direction of travel: Citybound (Inbound) or Southbound (Outbound)

− Weather conditions

• Wayside noise measurements recorded in increments of 1 second to capture both Tram approach and pass-by

• The following acoustic parameters were used when analyzing noise data:1. LAFmax: The maximum A-weighted sound pressure level, measured on “fast” time-weighting

2. LZeq, 1s: The un-weighted equivalent continuous sound pressure level at which the LAFmax occurred

19

Sound Measurement Locations for Noise MonitoringNote: Satellite image is outdated and does not reflect the Inbound and Outbound as-built track alignment in place during testing.

Page 20: Wayside Top of Rail Friction Control

Noise Monitoring

Other Noise Data Collection Considerations

• Only tram passes audible over ambient noise sources were used for analysis

• Tram speed not measured

• Concurrent tram pass-bys on both tracks not included in analysis i.e. Unable to assign recorded data to specific tram type

• Precise noise reduction threshold determining measure of success was not assigned within analysis work scope

20

Page 21: Wayside Top of Rail Friction Control

Noise Reduction Results

• Focus on D Class Tram results for symmetry to manual TOR application trial results

• 11-19 dB noise reduction achieved for frequencies previously associated with tram squeals during pre-mitigation noise monitoring for D Class trams (i.e. 3150 Hz and 5000 Hz)

• A drop of 10 dB typically considered to reflect a 50% reduction in subjectively perceived noise loudness (i.e. volume).

21

3150 Hz 5000 Hz 3150 Hz 5000 Hz

Pre-mitigation(Average Lzeq) 63 dB 62 dB 62 dB 63 dB

Post-FM via TOR unit(Average Lzeq) 51 dB 46 dB 51 dB 44 dB

Noise level difference -12 dB -16 dB -11 dB -19 dB

SOUTHBOUNDCITYBOUND

Lzeq,1s of D Class Trams During Pre-mitigation(no TOR) vs Wayside TOR Test Phases

Embedded TOR unit significantly reduced noise levels for all tram types in both directions

Page 22: Wayside Top of Rail Friction Control

Noise Reduction Results – Preliminary Investigation

0

10

20

30

40

50

60

70

80

90

1000

1250

1600

2000

2500

3150

4000

5000

6300

8000

1000

0

L Zeq

, 1s

(dB)

Frequency (Hz)

64

66

68

70

72

74

76

78

80

82

84

1 2 3 4 5 6 7

L AFm

ax(d

BA)

Noise collection number

Red - Pre-mitigation Blue - Post-manual KELTRACK® TT application Yellow - Post-manual KELTRACK® TT application + water

22

Maximum A-weighted Noise Levels for a 1 sec Period- D Class Test Tram

1/3 Octave Frequency Spectra - D Class Test Tram

Page 23: Wayside Top of Rail Friction Control

Noise Reduction Results – TOR Equipment Solution

0

10

20

30

40

50

60

70

80

90

1000

1250

1600

2000

2500

3150

4000

5000

6300

8000

1000

0

L Zeq

, 1s

(dB)

Frequency (Hz)

0

10

20

30

40

50

60

70

80

90

1000

1250

1600

2000

2500

3150

4000

5000

6300

8000

1000

0

L Zeq

, 1s

(dB)

Frequency (Hz)

1/3 Octave Frequency Spectra for Citybound (Inbound) D Class Trams

1/3 Octave Frequency Spectra for Southbound (Outbound) D Class Trams

Wayside TOR application eliminated extreme noise events (i.e. those > 65dB) for Citybound and Southbound D Class Trams

Red - Pre-mitigation Blue - Post-manual KELTRACK® TT application

23

Page 24: Wayside Top of Rail Friction Control

Results Summary

• A problem wheel squeal issue has been successfully resolved using an embedded track TOR equipment solution dispensing a water-based friction modifier (KELTRACK® Trackside Transit)

− Initial manual application of KTT demonstrated immediate benefit, with no wheel squeal events recorded

− TOR equipment solution effectively reduced noise levels for all tram types in both operating directions

− 11-19 dB noise reduction achieved for D Class trams = ~50% reduction in subjectively perceived noise loudness

• No adverse impacts to Tram braking or traction observed during all project phases

• Prior initial remediation measures failed to achieve similar noise abatement success(i.e. Water spray, Rail grinding, Crack sealant)

24

Page 25: Wayside Top of Rail Friction Control

Project Update

• St. Kilda Road track alignment recently revised as part of ongoing construction works for underground station

• Inbound TOR site remains the same – Outbound TOR unit has been relocated slightly during construction occupation

INBOUND TRACK

OUTBOUND TRACK

25

STAGE TWO REALIGNMENT

Page 26: Wayside Top of Rail Friction Control

Next Steps

Evaluate additional benefits of KELTRACK® TT use:

1. Rolling Contact Fatigue (RCF) / Corrugation Abatement• Wheel squeal generation mechanisms similar to those

producing RCF and corrugation defects

− Similar abatement potential and rail grinding efficiencies therefore possible through using TOR friction control

2. Rail Wear Reduction• Wear rates accelerate with increased contact pressure,

creepage and friction levels

• TOR friction control reduces curving and flanging forces, thereby decreasing contact pressure at the wheel / rail interface to reduce rail wear

High lateral force due to high creepage / friction forces

Track Spreading Forces

TRAFFICAoA

Lateral force reduced through low rail TOR

friction control

1

2

26

Page 27: Wayside Top of Rail Friction Control

Acknowledgments

The presenters wish to thank the following organizations and individuals for their valuable contributions to this project:

• Yarra Trams (Keolis Downer): Renée Frossinakis / John Uiterwijk / Brian Maddock Yih Hoong Chew / Charlie Bottino / David Laird

• Fulton Hogan Australia: Shaun Kent / Rocky Sam / Mustafa Kamel / Rob Stopic

• Rail Projects Victoria: Simon Adams / Martin Alvarez / Charlie Cantwell

• Aurecon Jacobs Mott MacDonald Joint Venture: David Larner

• Airlube Rail: Cliff Northwood / Jeff O’Grady / Stephen Lupi

27

Page 28: Wayside Top of Rail Friction Control

Thank you

Level 3, 555 Bourke Street,Melbourne VIC 3000yarratrams.com.au

Matthew Kwong, Yarra Trams (Keolis Downer) Email: [email protected]

Tony Makowsky, LB Foster Rail TechnologiesEmail: [email protected]