y Dominion PowerWarren County Power Station Project

Douglas P. StanleyCounty AdministratorOctober 16, 2013

Page 2: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y Location, Location, Location

Page 3: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y History

• Project originated in 2000 with a power development company called Competitive Power Ventures (CPV)

• State going through Electric Industry Deregulation

• 520 MW project

• Backed by investment firm

• CPV was scouting sites in Maryland and Virginia for potential development

Page 4: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y History

• The County has been working on this project since December 2000. The plant is located in an industrially zoned and developed area, compatible with adjoining and nearby uses.

• The site has been identified for industrial land use since the County’s first Comprehensive Plan was adopted in 1975.

Page 5: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y History

• Dominion purchased the project in 2008.

• Increased the plant size from 520MW to 1,329MW or enough energy to power approximately 325,000 homes.

• The station will have three combustion turbines and a steam turbine.

• The station will be powered solely by natural gas and will be among the cleanest fossil-fuel fired facilities in the nation.

Page 6: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y History• Project is within

the airshed of Shenandoah National Park

Page 7: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y History

• Based on available air quality data, Warren County is designated as an attainment area which indicates the proposed project site must meet the federal and state standards for each criteria pollutant in the National Ambient Air Quality Standards.

• Worked with the National Park service to address the impacts on Shenandoah National Park.

• Project has required 115% of NOx offsets that directly benefit our airshed to mitigate that impact.

Page 8: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y History• Project has just

passed the 50% completion milestone.

• Commercial operation is scheduled for late 2014 or early 2015.

Page 9: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y Employment ImpactTotal employment on-site as of October 7, 2013 - 1,524 employees. Original estimate was 600-800.

Total Hires – 2,506 (100%) Broken down as follows:

• Local (50mi) – 492 (20%)

• Non-Local VA – 176 (7%)

• Out-of-State – 1,838 (73%)

Page 10: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y Community Impact

Impact on Housing:– Some construction workers camping in

the County’s existing commercial campgrounds.

– Project has helped to occupy vacant housing units and numerous hotels.

– At one point 12 of the 14 smaller motels were at capacity with weekly rentals

Page 11: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y Fiscal ImpactSince the start of construction in March 2012, the County has seen an increase in tax collections in the following categories:• BPOL License Fees • Sales Tax• Lodging Tax • Meals Tax• Significant portion can be attributed to

the Dominion project and Regional Jail Project.

• Does not include revenue collected by the Town of Front Royal

Page 12: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y Fiscal Impact

Page 13: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y Fiscal Impacts

Page 14: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y Fiscal Impacts

Page 15: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y Fiscal Impact

Page 16: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y Fiscal Impact“I truly feel that the Dominion Project has provided a significant boost to the local

economy of Warren County.  We have seen a significant and positive financial impact at the Holiday Inn & Suites and at Houlihan’s

Restaurant + Bar.  A number of sub-contractors and employees working on the site have chosen to make the Holiday Inn

their home away from home while working on the site for the past year or so and our

staff has forged a number of great friendships with them.”

Brent C. Jackson, CHAGeneral Manager - Holiday Inn & Suites Front Royal Blue Ridge ShadowsDirector of Operations - Blue Ridge Shadows Resort

Page 17: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y Fiscal Impact• Original 520 MW CPV project was

estimated to generate $1.9 million in gross revenue.

• 1,329 MW project is now estimated to generate $5.8 million.

• County will lose approximately 20% in a shift in the composite index for school funding.

• Current estimate is a net of $4.5 million that will depreciate over the next 25 years based on SCC schedule.

Page 18: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y Community Impact

Dominion/Zachry picked 2 Community Projects to work on:• Riverton boat landing• Elementary School playground

project

Page 19: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y Community Impact

Page 20: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y Community Impact

Page 21: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y Community Impact

Page 22: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y

Page 23: Warren County Dominion Power Warren County Power Station Project Douglas P. Stanley County Administrator October 16, 2013

W

arre

n C

ount

y

END OF PRESENTATION