    CADANGAN PEMBANGUNAN DI ATAS TANAH SELUAS 15.40 EKAR DI MUKIM BATU,

    DAERAH GOMBAK. SELANGOR DARUL EHSAN. (PHASE 1)

    4.0 ESTIMATED DEVELOPMENT COST

    ELEMENT AMOUNT (RM)

    A. PRELIMINARIES ( 6%) 501,931.20

    B. PILING WORKS (anticipated depth of 36.00m)

    i. Double Storey Link House -

    ii. Shop Office - 2 Blocks @ 57,857sq.ft / block @ RM 4.50/ sq.ft 520,713.00

    520,713.00

    C. BUILDING WORKS

    i. Double Storey Link House (6 Blocks)

    a) Corner lot : 6 Blocks x 1 unit @ 1,600 sq.ft. /unit @ RM 58/sq.ft 556,800.00

    b) Interm. lot : 6 Blocks x 6 units @ 1,400 sq.ft./unit @ RM 54/sq.ft 2,721,600.00

    c) End lot : 6 Blocks x 1 unit @ 1,400 sq.ft./unit @ RM 55/sq.ft 462,000.00

    3,740,400.00

    ii. 3-Storey Shop Office (1 Block Only)

    a) Corner lot :

    G Flr : 1 unit @ 1,804 sq.ft / unit @ RM 44/sq.ft. 79,376.00

    1st Flr: 1 unit @ 2,478 sq.ft / unit @ RM 44/sq.ft. 109,032.00

    2nd Flr : 1 unit @ 2,478 sq.ft / unit @ RM 44/sq.ft. 109,032.00

    b) Interm. lot :

    G Flr : 11 unit @ 1,401sq.ft / unit @ RM 42/sq.ft. 647,262.00

    1st Flr: 11 unit @ 1,401sq.ft / unit @ RM 42/sq.ft. 647,262.00

    2nd Flr : 11 unit @ 1,401sq.ft / unit @ RM 42/sq.ft. 647,262.00

    c) End Lot :

    G Flr : 1 unit @ 1,401sq.ft / unit @ RM 42/sq.ft. 58,842.00

    1st Flr: 1 unit @ 1,401sq.ft / unit @ RM 42/sq.ft. 58,842.00

    2nd Flr : 1 unit @ 1,401sq.ft / unit @ RM 42/sq.ft. 58,842.00

    2,415,752.00

    SUB-TOTAL BUILDING WORKS (i) + (ii) 6,156,152.00

    D. MECHANICAL & ELECTRICAL WORKS

    i. Link Houses @ 68,400sq.ft. @ RM 12/ sq.ft 820,800.00

    ii. Shop Office (1 block) @ 57,857sq.ft. @ RM 15/ sq.ft 867,855.00

    1,688,655.00

    E. INFRASTRUCTURE

    i. Earthworks 636,000.00

    ii. Roadworks & Carparks 476,000.00

    iii. Surface Drainage 350,000.00

    iv. Sewerage 70,000.00

    v. Water Reticulation 113,000.00

    vi. Retaining Wall 503,000.00

    vii. Landscaping 50,000.00

    viii.Upgrading of Water Pump 200,000.00

    ix. TNB Sub-Station 60,000.00

    x. Street Lighting 150,000.00 2,608,000.00

    F. CONTINGENCIES 443,372.56

    ESTIMATED CONSTRUCTION COST C/F 11,918,823.76

    7

  • 7/28/2019 Viability Study 3(20.04.04)

    2/14

    CADANGAN PEMBANGUNAN DI ATAS TANAH SELUAS 15.40 EKAR DI MUKIM BATU,

    DAERAH GOMBAK. SELANGOR DARUL EHSAN. (PHASE 1)

    4.0 ESTIMATED DEVELOPMENT COST (Cont'd)

    ELEMENT AMOUNT (RM)

    B /F 11,918,823.76

    G. PROFESSIONAL FEE (8.0% of Const. Cost plus 5% Service Tax) 1,001,181.20

    H. LAND COST 4,200,000.00

    J. DEVELOPER'S MANAGEMENT & SUPERVISION

    24 Months @ RM 30,000 Per month 720,000.00

    K. PRE-DEVELOPMENT COST (ALLOW)

    i. Planning and submission fee 10,000.00

    ii. Soil Investigation 10,000.00

    iii. Strata title 64,200.00

    iv. Survey Engineering 15,000.00

    v Capital Contribution

    - TNB Contribution 150,000.00

    - Telephone Services 100,000.00- IWK 200,000.00

    - PUAS 20,000.00

    569,200.00

    L. SALES AND MARKETING EXPENSES 300,000.00

    M. FINANCING CHARGES (From Cashflow)) 400,000.00

    ESTIMATED DEVELOPMENT COST 19,109,204.96

    7

  • 7/28/2019 Viability Study 3(20.04.04)

    3/14

    CADANGAN PEMBANGUNAN DI ATAS TANAH SELUAS 15.40 EKAR DI MUKIM BATU,

    DAERAH GOMBAK, SELANGOR DARUL EHSAN. (PHASE 1)

    6.06 ANTICIPATED INCOME FROM SALES

    BUILDING UNIT AMOUNT (RM) AMOUNT (RM)

    A. Double-Storey Link House

    a) Corner Lot, 6 units @ RM 350,000.00 per unit 2,100,000.00

    b) Intermediate Lot, 36 units @ RM 290,000.00 per unit 10,440,000.00

    c) End Lot, 6 units @ RM 310,000.00 per unit 1,860,000.00

    14,400,000.00

    B. Shop Office

    a) Corner lot :G Flr : 1 unit @ 1,804 sq.ft / unit @ RM 300/sq.ft. 514,140.00

    1st Flr: 1 unit @ 2,478 sq.ft / unit @ RM 130/sq.ft. 322,140.00

    2nd Flr : 1 unit @ 2,478 sq.ft / unit @ RM 120/sq.ft. 297,360.00

    b) Interm. lot :

    G Flr : 11 unit @ 1,401sq.ft / unit @ RM 285/sq.ft. 4,392,135.00

    1st Flr: 11 unit @ 1,401sq.ft / unit @ RM 120/sq.ft. 1,849,320.00

    2nd Flr : 11 unit @ 1,401sq.ft / unit @ RM 110/sq.ft. 1,695,210.00

    c) End Lot :

    G Flr : 1 unit @ 1,401sq.ft / unit @ RM 290/sq.ft. 406,290.00

    1st Flr: 1 unit @ 1,401sq.ft / unit @ RM 120/sq.ft. 168,120.00

    2nd Flr : 1 unit @ 1,401sq.ft / unit @ RM 110/sq.ft. 154,110.00

    9,798,825.00

    TOTAL ANTICIPATED SALES 24,198,825.00

    10

  • 7/28/2019 Viability Study 3(20.04.04)

    4/14

    CADANGAN PEMBANGUNAN DI ATAS TANAH SELUAS 15.40 EKAR DI MUKIM BATU,

    DAERAH GOMBAK, SELANGOR DARUL EHSAN. (PHASE 1)

    MISCELLANEOUS WORK IN PHASE 1

    (Loss of Anticipated Profit)

    AMOUNT (RM)

    1 Land Premium 2,800,000.00

    2 Earthwork and Retaining Wall 400,000.00

    3 Piling for 2nd Block of Shop Office 250,000.00

    Total 3,450,000.00

    Development Cost 15,660,000.00

    Loss of Anticipated Profit 22% margin

    10

  • 7/28/2019 Viability Study 3(20.04.04)

    5/14

    CADANGAN PEMBANGUNAN DI ATAS TANAH SELUAS 15.40 EKAR, MUKIM BATU, DAERAH GOMBAK.

    SELANGOR DARUL EHSAN (PHASE 1)

    INCOME FROM INSTALLMENT PAYMENT (RM) FOR TOWNHOUSES

    Sales Value

    % RM Q1 Q2 Q3 Q4

    10% 50% 30% 20%

    1st Payment On signing of formal agreement 1,440,000 720,000 432,000 288,000

    2nd Payment On completion of work below grd. 10% 30% 40% 30%

    level incl. piling, foundation of the

    said bld. comprising of the said 1,440,000 432,000 576,000 432,000

    parcel

    3rd Payment On completion of reinforced 15% 70% 30%

    concrete framework and floor

    slab of the said parcel 2,160,000 1,512,000 648,000

    4th Payment on completion of the walls of the 10% 40% 60%

    said parcel with door and window

    frames placed in position 1,440,000 576,000 864,000

    5th Payment On completion of roofing/ceiling, 10% 30% 60% 10%

    elec. wiring and plumbing

    (without fittings) to the said 1,440,000 432,000 864,000 144,0

    parcel

    6th Payment On completion of internal and 10% 70% 30%

    external plastering of the said

    parcel 1,440,000 1,008,000 432,0

    7th Payment On completion of roads drains 15% 100%

    and sewerage work serving the

    said building 2,160,000 2,160,0

    8th Payment On handing over of vacant 15% 100%

    possession and connection of

    water and electricity supply 2,160,000 2,160,0

    to the said parcel

    9th Payment a) At the expiry of six months 2.50%

    after handing over of vacant

    possession 360,000.00

    b) At the expiry of twelve 2.50%

    months after handing over

    of the vacant possession 360,000.00

    14,400,000 1,152,000 3,528,000 4,104,000 4,896,0

    YEAR 1SCHEDULE OF PAYMENT

    APP/C/5

  • 7/28/2019 Viability Study 3(20.04.04)

    6/14

    CADANGAN PEMBANGUNAN DI ATAS TANAH SELUAS 15.40 EKAR, MUKIM BATU, DAERAH GOMBAK.

    SELANGOR DARUL EHSAN (PHASE 1)

    INCOME FROM INSTALLMENT PAYMENT (RM) FOR SHOP OFFICES

    Sales Value

    % RM Q1 Q2 Q3 Q4

    10% 60% 40%

    1st Payment On signing of formal agreement 979,883 587,930 391,9

    2nd Payment On completion of work below grd. 10% 50% 50%

    level incl. piling, foundation of the

    said bld. comprising of the said 979,883 489,941 489,9

    parcel

    3rd Payment On completion of reinforced 15% 70%

    concrete framework and floor

    slab of the said parcel 1,469,824 1,028,8

    4th Payment on completion of the walls of the 10% 40%

    said parcel with door and window

    frames placed in position 979,883 391,9

    5th Payment On completion of roofing/ceiling, 10% 30%

    elec. wiring and plumbing

    (without fittings) to the said 979,883 293,9

    parcel

    6th Payment On completion of internal and 10%

    external plastering of the said

    parcel 979,883

    7th Payment On completion of roads drains 15%

    and sewerage work serving the

    said building 1,469,824

    8th Payment On handing over of vacant 15%

    possession and connection of

    water and electricity supply 1,469,824

    to the said parcel

    9th Payment a) At the expiry of six months 2.50%

    after handing over of vacant

    possession 244,970.63

    b) At the expiry of twelve 2.50%

    months after handing over

    of the vacant possession 244,970.63

    9,798,825 - - 1,077,871 2,596,6

    SCHEDULE OF PAYMENTYEAR 1

    APP/C/6

  • 7/28/2019 Viability Study 3(20.04.04)

    7/14

    Q4

    -

    APP/C/7

  • 7/28/2019 Viability Study 3(20.04.04)

    8/14

    Q4

    -

    APP/C/8

  • 7/28/2019 Viability Study 3(20.04.04)

    9/14

    CADANGAN PEMBANGUNAN DI ATAS TANAH SELUAS 15.40 EKAR, MUKIM BATU, DAERAH GOMBAK.

    SELANGOR DARUL EHSAN (PHASE 1)

    PROJECTED CASH FLOW (WITHOUT FINANCING CHARGES)

    TOTAL re-Developme YEAR 1 (RM) Period Q1 Q2 Q3 Q4 Q1

    CASH INFLOW (3 Months)

    A. Sales Income

    i. Town House 14,400,000 1,152,000 3,528,000 4,104,000 4,896,000 -

    ii. Shop Office 9,798,825 - - 1,077,871 2,596,689 2,302,724

    TOTAL CASH INFLOW 24,198,825 1,152,000 3,528,000 5,181,871 7,492,689 2,302,724

    CASH OUTFLOW

    a) Construction Cost 11,918,824 1,787,824 ########## ########## 2,383,765 2,979,706

    b) Professional Fees 1,001,181 100,118 500,591 50,059 50,059 50,059 50,059 c) Land Cost 4,200,000 4,200,000

    d) Management & Supervision 720,000 110,000 110,000 110,000 110,000 110,000

    e) Pre-Development Cost - - - - - - -

    f) Sales & Marketing Expenses 300,000 300,000 120,000 120,000 120,000 - -

    TOTAL CASH OUTFLOW 18,140,005 4,600,118 2,518,414 1,471,941 2,067,883 2,543,824 3,139,765

    CURRENT SURPLUS/-DEFICIT (4,600,118.12) ########### 2,056,058.56 3,113,988.13 4,948,864.82 (837,041.12) 2

    CUMULATIVE SURPLUS/-DEFICIT (4,600,118.12) ########### ########### (796,485.59) 4,152,379.23 3,315,338.10 5

    CON

    APP/B/9

  • 7/28/2019 Viability Study 3(20.04.04)

    10/14

    Q4

    - 14,400,000

    - 9,798,825

    -

    - 11,918,823.75

    1,001,181.204,200,000.00

    900,000.00

    - -

    - 660,000.00

    -

    -

    -

    -

    -

    - 18,680,004.95

    0.00

    #REF!

    APP/B/10

  • 7/28/2019 Viability Study 3(20.04.04)

    11/14

    CADANGAN PEMBANGUNAN DI ATAS TANAH SELUAS 15.40 EKAR, MUKIM BATU, DAERAH GOMBAK.

    SELANGOR DARUL EHSAN.

    - PROJECTED CASHFLOW BASED ON PROPOSED LOAN DRAWDOWN AND REPAYMENT

    TOTAL Pre-Development YEAR 1

    (RM) Period Q1 Q2 Q3 Q4

    CASH INFLOW (3 Months)

    A) Sales Income

    i. Bridging Loan 5,350,000 2,350,000 3,000,000 - - -

    ii. Town House 14,400,000 1,152,000 3,528,000 4,104,000 4,896,000

    ii. Shop Office 9,798,825 - - 1,077,871 2,596,689

    Total Cashinflow 29,548,825 2,350,000 4,152,000 3,528,000 5,181,871 7,492,689

    CASH OUTFLOW

    a) Construction Cost 11,918,824 1,787,824 1,191,882.38 1,787,823.56 2,383,765

    b) Professional Fees 1,001,181 100,118 500,591 50,059 50,059 50,059

    c) Land Cost 4,200,000 4,200,000

    d) Mgt & Supervision Expenses 720,000 110,000 110,000 110,000 110,000

    f) Pre-Development Cost - - - - - -

    e) Sales & Marketing Expenses 300,000 300,000 120,000 120,000 120,000 -

    SUB-TOTAL 18,140,005 4,600,118 2,518,414 1,471,941 2,067,883 2,543,824

    Loan Repayment 5,350,000 - - 1,800,000 3,550,000

    Loan Interest (7.50% P.A) 210,938 44,063 100,313 66,563 -

    TOTAL CASH OUTFLOW 23,700,942 4,644,181 2,618,727 3,338,504 5,617,883 2,543,824

    Cash Inflow/-Outflow 5,307,883 2,294,181- 1,533,273 189,496 (436,012) 4,948,865

    Surplus/-Deficit c/f 2,294,181- 760,907- 571,411- 1,007,423- 3,941,442

    APP/A/11

  • 7/28/2019 Viability Study 3(20.04.04)

    12/14

    Q4

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    APP/A/12

  • 7/28/2019 Viability Study 3(20.04.04)

    13/14

    CADANGAN PEMBANGUNAN DI ATAS TANAH SELUAS 15.40 EKAR, MUKIM BATU, DAERAH GOMBAK.

    SELANGOR DARUL EHSAN (PHASE 1)

    EXECUTIVE SUMMARY

    ITEM ELEMENT TOTAL

    (RM)

    A Preliminaries (6% of B,C & D) 501,931.20

    B Piling Works 520,713.00

    C Building Works 6,156,152.00

    D Mechanical & Electrical Works 1,688,655.00

    E Infrastructure 2,608,000.00

    F Contingencies (5% of A,B,C & D) 443,372.56

    ESTIMATED CONSTRUCTION COST 11,918,823.76

    G Professional Fees (8.0% of Const. Cost plus 5% Service Tax) 1,001,181.20

    H Land Cost 4,200,000.00

    I Developer's Management & Supervision 720,000.00

    (RM30,000.00 Per Month x Construction Period)

    J Pre-Development Cost (Allowance) 569,200.00

    - Including Planning and Submission Fee, Soil Investigation, Strata Title

    Survey Engineering, Capital Contribution, etc.

    K Sales and Marketing Expenses 300,000.00

    L Financing Charges (From Cashflow) 400,000.00

    ESTIMATED DEVELOPMENT COST 19,109,204.96

    PROJECTED REVENUE 24,198,825.00

    PRE-TAX PROFIT 5,089,620.04

    RETURN ON DEVELOPMENT 26.63%

    COST EXCLUSION

    i) Development Charges, if any

    Note :

    The above estimate is very preliminary pending more detail drawings and information

  • 7/28/2019 Viability Study 3(20.04.04)

    14/14

    . , ,

    DAERAH GOMBAK. SELANGOR DARUL EHSAN (PHASE 1)

    EXECUTIVE SUMMARY FOR ALTERNATIVE PROPOSAL

    DEVELOPMENT ANTICIPATED PRE-TAX RETURN

    COST SALES PROFIT MARGIN

    A. ORIGINAL PROPOSAL

    i. 96 Units Town House 11,282,288.00 18,240,000.00 6,957,712.00 61.66%

    3 15,675,874.48 16,967,680.00 1,291,805.52 8.24%

    TOTAL (RM) 26,958,162.48 35,207,680.00 8,249,517.52 30.60%

    B. ALTERNATIVE PROPOSAL A

    i. 48 Units 2 - Storey Terrace 7,406,000.00 10,560,000.00 3,154,000.00 42.59%

    ii. 3 Storey Shop Office 9,504,000.00 13,776,000.00 4,272,000.00 44.95%

    TOTAL (RM) 16,910,000.00 24,336,000.00 7,426,000.00 43.91%

    C. ALTERNATIVE PROPOSAL B

    i. 54 Units 2 Storey Terrace 7,681,000.00 11,880,000.00 4,199,000.00 54.66%

    ii. 5-7 Storey Business Centre 19,025,000.00 27,790,000.00 8,765,000.00 46.07%

    TOTAL (RM) 26,706,000.00 39,670,000.00 12,964,000.00 48.54%

    DEVELOPMENT