Upload
raffiai-abdullah
View
217
Download
0
Embed Size (px)
Citation preview
7/28/2019 Viability Study 3(20.04.04)
1/14
CADANGAN PEMBANGUNAN DI ATAS TANAH SELUAS 15.40 EKAR DI MUKIM BATU,
DAERAH GOMBAK. SELANGOR DARUL EHSAN. (PHASE 1)
4.0 ESTIMATED DEVELOPMENT COST
ELEMENT AMOUNT (RM)
A. PRELIMINARIES ( 6%) 501,931.20
B. PILING WORKS (anticipated depth of 36.00m)
i. Double Storey Link House -
ii. Shop Office - 2 Blocks @ 57,857sq.ft / block @ RM 4.50/ sq.ft 520,713.00
520,713.00
C. BUILDING WORKS
i. Double Storey Link House (6 Blocks)
a) Corner lot : 6 Blocks x 1 unit @ 1,600 sq.ft. /unit @ RM 58/sq.ft 556,800.00
b) Interm. lot : 6 Blocks x 6 units @ 1,400 sq.ft./unit @ RM 54/sq.ft 2,721,600.00
c) End lot : 6 Blocks x 1 unit @ 1,400 sq.ft./unit @ RM 55/sq.ft 462,000.00
3,740,400.00
ii. 3-Storey Shop Office (1 Block Only)
a) Corner lot :
G Flr : 1 unit @ 1,804 sq.ft / unit @ RM 44/sq.ft. 79,376.00
1st Flr: 1 unit @ 2,478 sq.ft / unit @ RM 44/sq.ft. 109,032.00
2nd Flr : 1 unit @ 2,478 sq.ft / unit @ RM 44/sq.ft. 109,032.00
b) Interm. lot :
G Flr : 11 unit @ 1,401sq.ft / unit @ RM 42/sq.ft. 647,262.00
1st Flr: 11 unit @ 1,401sq.ft / unit @ RM 42/sq.ft. 647,262.00
2nd Flr : 11 unit @ 1,401sq.ft / unit @ RM 42/sq.ft. 647,262.00
c) End Lot :
G Flr : 1 unit @ 1,401sq.ft / unit @ RM 42/sq.ft. 58,842.00
1st Flr: 1 unit @ 1,401sq.ft / unit @ RM 42/sq.ft. 58,842.00
2nd Flr : 1 unit @ 1,401sq.ft / unit @ RM 42/sq.ft. 58,842.00
2,415,752.00
SUB-TOTAL BUILDING WORKS (i) + (ii) 6,156,152.00
D. MECHANICAL & ELECTRICAL WORKS
i. Link Houses @ 68,400sq.ft. @ RM 12/ sq.ft 820,800.00
ii. Shop Office (1 block) @ 57,857sq.ft. @ RM 15/ sq.ft 867,855.00
1,688,655.00
E. INFRASTRUCTURE
i. Earthworks 636,000.00
ii. Roadworks & Carparks 476,000.00
iii. Surface Drainage 350,000.00
iv. Sewerage 70,000.00
v. Water Reticulation 113,000.00
vi. Retaining Wall 503,000.00
vii. Landscaping 50,000.00
viii.Upgrading of Water Pump 200,000.00
ix. TNB Sub-Station 60,000.00
x. Street Lighting 150,000.00 2,608,000.00
F. CONTINGENCIES 443,372.56
ESTIMATED CONSTRUCTION COST C/F 11,918,823.76
7
7/28/2019 Viability Study 3(20.04.04)
2/14
CADANGAN PEMBANGUNAN DI ATAS TANAH SELUAS 15.40 EKAR DI MUKIM BATU,
DAERAH GOMBAK. SELANGOR DARUL EHSAN. (PHASE 1)
4.0 ESTIMATED DEVELOPMENT COST (Cont'd)
ELEMENT AMOUNT (RM)
B /F 11,918,823.76
G. PROFESSIONAL FEE (8.0% of Const. Cost plus 5% Service Tax) 1,001,181.20
H. LAND COST 4,200,000.00
J. DEVELOPER'S MANAGEMENT & SUPERVISION
24 Months @ RM 30,000 Per month 720,000.00
K. PRE-DEVELOPMENT COST (ALLOW)
i. Planning and submission fee 10,000.00
ii. Soil Investigation 10,000.00
iii. Strata title 64,200.00
iv. Survey Engineering 15,000.00
v Capital Contribution
- TNB Contribution 150,000.00
- Telephone Services 100,000.00- IWK 200,000.00
- PUAS 20,000.00
569,200.00
L. SALES AND MARKETING EXPENSES 300,000.00
M. FINANCING CHARGES (From Cashflow)) 400,000.00
ESTIMATED DEVELOPMENT COST 19,109,204.96
7
7/28/2019 Viability Study 3(20.04.04)
3/14
CADANGAN PEMBANGUNAN DI ATAS TANAH SELUAS 15.40 EKAR DI MUKIM BATU,
DAERAH GOMBAK, SELANGOR DARUL EHSAN. (PHASE 1)
6.06 ANTICIPATED INCOME FROM SALES
BUILDING UNIT AMOUNT (RM) AMOUNT (RM)
A. Double-Storey Link House
a) Corner Lot, 6 units @ RM 350,000.00 per unit 2,100,000.00
b) Intermediate Lot, 36 units @ RM 290,000.00 per unit 10,440,000.00
c) End Lot, 6 units @ RM 310,000.00 per unit 1,860,000.00
14,400,000.00
B. Shop Office
a) Corner lot :G Flr : 1 unit @ 1,804 sq.ft / unit @ RM 300/sq.ft. 514,140.00
1st Flr: 1 unit @ 2,478 sq.ft / unit @ RM 130/sq.ft. 322,140.00
2nd Flr : 1 unit @ 2,478 sq.ft / unit @ RM 120/sq.ft. 297,360.00
b) Interm. lot :
G Flr : 11 unit @ 1,401sq.ft / unit @ RM 285/sq.ft. 4,392,135.00
1st Flr: 11 unit @ 1,401sq.ft / unit @ RM 120/sq.ft. 1,849,320.00
2nd Flr : 11 unit @ 1,401sq.ft / unit @ RM 110/sq.ft. 1,695,210.00
c) End Lot :
G Flr : 1 unit @ 1,401sq.ft / unit @ RM 290/sq.ft. 406,290.00
1st Flr: 1 unit @ 1,401sq.ft / unit @ RM 120/sq.ft. 168,120.00
2nd Flr : 1 unit @ 1,401sq.ft / unit @ RM 110/sq.ft. 154,110.00
9,798,825.00
TOTAL ANTICIPATED SALES 24,198,825.00
10
7/28/2019 Viability Study 3(20.04.04)
4/14
CADANGAN PEMBANGUNAN DI ATAS TANAH SELUAS 15.40 EKAR DI MUKIM BATU,
DAERAH GOMBAK, SELANGOR DARUL EHSAN. (PHASE 1)
MISCELLANEOUS WORK IN PHASE 1
(Loss of Anticipated Profit)
AMOUNT (RM)
1 Land Premium 2,800,000.00
2 Earthwork and Retaining Wall 400,000.00
3 Piling for 2nd Block of Shop Office 250,000.00
Total 3,450,000.00
Development Cost 15,660,000.00
Loss of Anticipated Profit 22% margin
10
7/28/2019 Viability Study 3(20.04.04)
5/14
CADANGAN PEMBANGUNAN DI ATAS TANAH SELUAS 15.40 EKAR, MUKIM BATU, DAERAH GOMBAK.
SELANGOR DARUL EHSAN (PHASE 1)
INCOME FROM INSTALLMENT PAYMENT (RM) FOR TOWNHOUSES
Sales Value
% RM Q1 Q2 Q3 Q4
10% 50% 30% 20%
1st Payment On signing of formal agreement 1,440,000 720,000 432,000 288,000
2nd Payment On completion of work below grd. 10% 30% 40% 30%
level incl. piling, foundation of the
said bld. comprising of the said 1,440,000 432,000 576,000 432,000
parcel
3rd Payment On completion of reinforced 15% 70% 30%
concrete framework and floor
slab of the said parcel 2,160,000 1,512,000 648,000
4th Payment on completion of the walls of the 10% 40% 60%
said parcel with door and window
frames placed in position 1,440,000 576,000 864,000
5th Payment On completion of roofing/ceiling, 10% 30% 60% 10%
elec. wiring and plumbing
(without fittings) to the said 1,440,000 432,000 864,000 144,0
parcel
6th Payment On completion of internal and 10% 70% 30%
external plastering of the said
parcel 1,440,000 1,008,000 432,0
7th Payment On completion of roads drains 15% 100%
and sewerage work serving the
said building 2,160,000 2,160,0
8th Payment On handing over of vacant 15% 100%
possession and connection of
water and electricity supply 2,160,000 2,160,0
to the said parcel
9th Payment a) At the expiry of six months 2.50%
after handing over of vacant
possession 360,000.00
b) At the expiry of twelve 2.50%
months after handing over
of the vacant possession 360,000.00
14,400,000 1,152,000 3,528,000 4,104,000 4,896,0
YEAR 1SCHEDULE OF PAYMENT
APP/C/5
7/28/2019 Viability Study 3(20.04.04)
6/14
CADANGAN PEMBANGUNAN DI ATAS TANAH SELUAS 15.40 EKAR, MUKIM BATU, DAERAH GOMBAK.
SELANGOR DARUL EHSAN (PHASE 1)
INCOME FROM INSTALLMENT PAYMENT (RM) FOR SHOP OFFICES
Sales Value
% RM Q1 Q2 Q3 Q4
10% 60% 40%
1st Payment On signing of formal agreement 979,883 587,930 391,9
2nd Payment On completion of work below grd. 10% 50% 50%
level incl. piling, foundation of the
said bld. comprising of the said 979,883 489,941 489,9
parcel
3rd Payment On completion of reinforced 15% 70%
concrete framework and floor
slab of the said parcel 1,469,824 1,028,8
4th Payment on completion of the walls of the 10% 40%
said parcel with door and window
frames placed in position 979,883 391,9
5th Payment On completion of roofing/ceiling, 10% 30%
elec. wiring and plumbing
(without fittings) to the said 979,883 293,9
parcel
6th Payment On completion of internal and 10%
external plastering of the said
parcel 979,883
7th Payment On completion of roads drains 15%
and sewerage work serving the
said building 1,469,824
8th Payment On handing over of vacant 15%
possession and connection of
water and electricity supply 1,469,824
to the said parcel
9th Payment a) At the expiry of six months 2.50%
after handing over of vacant
possession 244,970.63
b) At the expiry of twelve 2.50%
months after handing over
of the vacant possession 244,970.63
9,798,825 - - 1,077,871 2,596,6
SCHEDULE OF PAYMENTYEAR 1
APP/C/6
7/28/2019 Viability Study 3(20.04.04)
7/14
Q4
-
APP/C/7
7/28/2019 Viability Study 3(20.04.04)
8/14
Q4
-
APP/C/8
7/28/2019 Viability Study 3(20.04.04)
9/14
CADANGAN PEMBANGUNAN DI ATAS TANAH SELUAS 15.40 EKAR, MUKIM BATU, DAERAH GOMBAK.
SELANGOR DARUL EHSAN (PHASE 1)
PROJECTED CASH FLOW (WITHOUT FINANCING CHARGES)
TOTAL re-Developme YEAR 1 (RM) Period Q1 Q2 Q3 Q4 Q1
CASH INFLOW (3 Months)
A. Sales Income
i. Town House 14,400,000 1,152,000 3,528,000 4,104,000 4,896,000 -
ii. Shop Office 9,798,825 - - 1,077,871 2,596,689 2,302,724
TOTAL CASH INFLOW 24,198,825 1,152,000 3,528,000 5,181,871 7,492,689 2,302,724
CASH OUTFLOW
a) Construction Cost 11,918,824 1,787,824 ########## ########## 2,383,765 2,979,706
b) Professional Fees 1,001,181 100,118 500,591 50,059 50,059 50,059 50,059 c) Land Cost 4,200,000 4,200,000
d) Management & Supervision 720,000 110,000 110,000 110,000 110,000 110,000
e) Pre-Development Cost - - - - - - -
f) Sales & Marketing Expenses 300,000 300,000 120,000 120,000 120,000 - -
TOTAL CASH OUTFLOW 18,140,005 4,600,118 2,518,414 1,471,941 2,067,883 2,543,824 3,139,765
CURRENT SURPLUS/-DEFICIT (4,600,118.12) ########### 2,056,058.56 3,113,988.13 4,948,864.82 (837,041.12) 2
CUMULATIVE SURPLUS/-DEFICIT (4,600,118.12) ########### ########### (796,485.59) 4,152,379.23 3,315,338.10 5
CON
APP/B/9
7/28/2019 Viability Study 3(20.04.04)
10/14
Q4
- 14,400,000
- 9,798,825
-
- 11,918,823.75
1,001,181.204,200,000.00
900,000.00
- -
- 660,000.00
-
-
-
-
-
- 18,680,004.95
0.00
#REF!
APP/B/10
7/28/2019 Viability Study 3(20.04.04)
11/14
CADANGAN PEMBANGUNAN DI ATAS TANAH SELUAS 15.40 EKAR, MUKIM BATU, DAERAH GOMBAK.
SELANGOR DARUL EHSAN.
- PROJECTED CASHFLOW BASED ON PROPOSED LOAN DRAWDOWN AND REPAYMENT
TOTAL Pre-Development YEAR 1
(RM) Period Q1 Q2 Q3 Q4
CASH INFLOW (3 Months)
A) Sales Income
i. Bridging Loan 5,350,000 2,350,000 3,000,000 - - -
ii. Town House 14,400,000 1,152,000 3,528,000 4,104,000 4,896,000
ii. Shop Office 9,798,825 - - 1,077,871 2,596,689
Total Cashinflow 29,548,825 2,350,000 4,152,000 3,528,000 5,181,871 7,492,689
CASH OUTFLOW
a) Construction Cost 11,918,824 1,787,824 1,191,882.38 1,787,823.56 2,383,765
b) Professional Fees 1,001,181 100,118 500,591 50,059 50,059 50,059
c) Land Cost 4,200,000 4,200,000
d) Mgt & Supervision Expenses 720,000 110,000 110,000 110,000 110,000
f) Pre-Development Cost - - - - - -
e) Sales & Marketing Expenses 300,000 300,000 120,000 120,000 120,000 -
SUB-TOTAL 18,140,005 4,600,118 2,518,414 1,471,941 2,067,883 2,543,824
Loan Repayment 5,350,000 - - 1,800,000 3,550,000
Loan Interest (7.50% P.A) 210,938 44,063 100,313 66,563 -
TOTAL CASH OUTFLOW 23,700,942 4,644,181 2,618,727 3,338,504 5,617,883 2,543,824
Cash Inflow/-Outflow 5,307,883 2,294,181- 1,533,273 189,496 (436,012) 4,948,865
Surplus/-Deficit c/f 2,294,181- 760,907- 571,411- 1,007,423- 3,941,442
APP/A/11
7/28/2019 Viability Study 3(20.04.04)
12/14
Q4
-
-
-
-
-
-
-
-
-
-
-
APP/A/12
7/28/2019 Viability Study 3(20.04.04)
13/14
CADANGAN PEMBANGUNAN DI ATAS TANAH SELUAS 15.40 EKAR, MUKIM BATU, DAERAH GOMBAK.
SELANGOR DARUL EHSAN (PHASE 1)
EXECUTIVE SUMMARY
ITEM ELEMENT TOTAL
(RM)
A Preliminaries (6% of B,C & D) 501,931.20
B Piling Works 520,713.00
C Building Works 6,156,152.00
D Mechanical & Electrical Works 1,688,655.00
E Infrastructure 2,608,000.00
F Contingencies (5% of A,B,C & D) 443,372.56
ESTIMATED CONSTRUCTION COST 11,918,823.76
G Professional Fees (8.0% of Const. Cost plus 5% Service Tax) 1,001,181.20
H Land Cost 4,200,000.00
I Developer's Management & Supervision 720,000.00
(RM30,000.00 Per Month x Construction Period)
J Pre-Development Cost (Allowance) 569,200.00
- Including Planning and Submission Fee, Soil Investigation, Strata Title
Survey Engineering, Capital Contribution, etc.
K Sales and Marketing Expenses 300,000.00
L Financing Charges (From Cashflow) 400,000.00
ESTIMATED DEVELOPMENT COST 19,109,204.96
PROJECTED REVENUE 24,198,825.00
PRE-TAX PROFIT 5,089,620.04
RETURN ON DEVELOPMENT 26.63%
COST EXCLUSION
i) Development Charges, if any
Note :
The above estimate is very preliminary pending more detail drawings and information
7/28/2019 Viability Study 3(20.04.04)
14/14
. , ,
DAERAH GOMBAK. SELANGOR DARUL EHSAN (PHASE 1)
EXECUTIVE SUMMARY FOR ALTERNATIVE PROPOSAL
DEVELOPMENT ANTICIPATED PRE-TAX RETURN
COST SALES PROFIT MARGIN
A. ORIGINAL PROPOSAL
i. 96 Units Town House 11,282,288.00 18,240,000.00 6,957,712.00 61.66%
3 15,675,874.48 16,967,680.00 1,291,805.52 8.24%
TOTAL (RM) 26,958,162.48 35,207,680.00 8,249,517.52 30.60%
B. ALTERNATIVE PROPOSAL A
i. 48 Units 2 - Storey Terrace 7,406,000.00 10,560,000.00 3,154,000.00 42.59%
ii. 3 Storey Shop Office 9,504,000.00 13,776,000.00 4,272,000.00 44.95%
TOTAL (RM) 16,910,000.00 24,336,000.00 7,426,000.00 43.91%
C. ALTERNATIVE PROPOSAL B
i. 54 Units 2 Storey Terrace 7,681,000.00 11,880,000.00 4,199,000.00 54.66%
ii. 5-7 Storey Business Centre 19,025,000.00 27,790,000.00 8,765,000.00 46.07%
TOTAL (RM) 26,706,000.00 39,670,000.00 12,964,000.00 48.54%
DEVELOPMENT