VDOT / VTCA Hampton Roads District DialogueDecember 1, 2016
2
AGENDAOpening Remarks and Overview – James S. Utterback, PMPProgram Overviews• SMART SCALE Update - Dawn Odom• Preliminary Engineering - Pete Reilly, PE, DBIA• Construction - John Jacobs, PE, PMP• Maintenance - Mike Corwin, PE• Operations - Dwayne Cook
Question and Answer
3
HAMPTON ROADSDISTRICT
Overview of Programs and Upcoming Work
4
District Overview9 Counties/12 Cities/2 Islands
• Approximately 830 positions• Approximately 10,000 Total Lane Miles
Tunnels/Facilities• I-64 Hampton Roads Bridge-Tunnel (HRBT)• I-664 Monitor Merrimac Memorial Bridge-Tunnel (MMMBT)
• Jamestown-Scotland Ferry• Transportation Operations Center (TOC)
Major Bridges• James River Bridge• High Rise Bridge• Berkley Bridge • Coleman Bridge• Willoughby Bay Bridge
Residencies•Accomac•Franklin•Williamsburg
Interstate Management Office (IMO) • Interstate Maintenance Contracts• Urban Construction
5
District Performance Report
6
Hampton Roads District Program SYIP Allocation Trends3
(000’s)
System FY12-17 FY13-18 FY14-19 FY15-20 FY16-21 FY17-22
Interstate $187,653 $178,863 $323,136 $341,604 $378,606 $715,640 Primary $196,472 $960,431 $907,241 $730,434 $470,637 $284,171 Secondary $32,197 $36,845 $60,951 $35,018 $42,747 $115,780 Urban $533,319 $442,000 $385,724 $344,048 $340,108 $352,483 Enhancement1 $12,215 $12,250 $14,051 $6,168 Transit2 $90,879 $80,015 $50,110 $52,912 $38,051 $34,156 Rail $300 $16
Other $57,512 $40,139 $27,694 $30,055 $119,827 $187,366
Total $1,098,332 $1,738,293 $1,767,087 $1,546,321 $1,404,027 $1,695,764
Notes:1. Includes Enhancement (Transportation Alternatives Program) programmed through the
HRTPO.
2. Excludes transit projects administered through DRPT/FTA, which are in a separate SYIP document for Rail and Public Transportation (beginning with FY14-19 SYIP).
7
VDOT - HRTAC AgreementsProject Phase CTB Action HRTAC Action Executed Agreement Notes Fed/State
Funding HRTAC Funding
I-64 Seg I-104905 PE/RW/CN N/A N/A - MOU executed $100,000,000 $44,000,000
I-64 Seg II-106665
PE 4/15/2015 4/16/2015 4/23/2015 - $6,000,000
RW/CN 9/16/2015 8/20/2015 10/19/2015 - $207,592,853
I-64 Seg III-106689
PE 3/16/2016 3/17/2016 3/17/2016 - $10,000,000
RW/CN - - - On CTB and HRTAC Dec 2016 agenda's $144,927,753 $156,376,066
I-64/I-264 Phase I- 57048/108042
PE/RW 1/14/2015 1/8/2015 4/16/2015 $5,047,700 $15,071,063
CN 2/17/2016 12/16/2015 3/17/2016 - $137,023,653
I-64/I-264 Phase II- 17630/108041
PE/RW 1/14/2015 1/8/2015 4/16/2015 $11,602,900 $53,592,576
CN - - - To be requested 1st quarter of 2017 - -
I-64/I-264 Phase III- 106693 PE - - - On CTB and HRTAC
Dec 2016 agenda's - $10,000,000
I-64 Southside-High Rise Br-
106692/104366
PE 1/14/2015 1/8/2015 4/16/2015 $5,000,000 $20,000,000
RW/CN 7/28/2016 6/16/2016 11/9/2016 - $580,000,000
HRCS SEIS-106724 PE 1/14/2015 1/8/2015 4/16/2015 $6,352,527 $5,000,000
Rte 460/58/13 Connector-
106694PE 7/28/2016 6/16/2016 11/9/2016 - $5,000,000
Total prior to Dec CTB and HRTAC Meetings $128,003,127 $1,083,280,145
Total after Dec CTB and HRTAC Meetings $272,930,880 $1,249,656,211
8
9
10
HAMPTON ROADS DISTRICT
SMART SCALE Update
Dawn V. OdomADA-Planning and Investment
11
Name Email Phone #
Dawn Odom [email protected] (757) 925-1581
Eric Stringfield [email protected] (757) 925-3669
Steve Rowan [email protected] (757) 925-2459
Karen Bourne [email protected] (757) 925-2481
HAMPTON ROADS DISTRICTPLANNING AND INVESTMENT TEAM
12
Passed by the General Assembly, and signed by the Governor in 2014
Requires a data-driven scoring process for certain projects in the Six-Year Improvement Program (SYIP)
SMART: System for the Management and Allocation of Resources for Transportation
SCALE: Safety, Congestion, Accessibility, Land Use, Economic Development and Environmental, all of which are factors used to evaluate a project’s benefit
What is Smart Scale?
13
Smart Scale Process
.
Eligibility/FundingVDOT, OIPI, DRPT
Project ApplicationsLocalities and Eligible
Entities
Project ScreeningVDOT, OIPI, DRPT
Evaluation/ScoringVDOT & DRPT
Prioritization/ Programming
CTB
14
Eligible Project Types are Highway Capacity and Operational Improvements
o Widening projectso Access Managemento Transit and Rail Capacity Expansiono Transportation Demand Management (Park & Ride
facilities) Project Types Not Eligible
o Bridge Repair/Replacement o Pavement Repair/Replacement o Guardrail Repair/Replacemento Planning Studies
Smart Scale Eligibility
15
Smart Scale Scoring
Factors are weighted differently across the Commonwealth.
Factor Congestion Mitigation
EconomicDevelopment Accessibility Safety Environmental
QualityLand Use
Category A 45% 5% 15% 5% 10% 20%
Category B 15% 20% 25% 20% 10% 10%Category C 15% 25% 25% 25% 10%Category D 10% 35% 15% 30% 10%
16
District Grants Program (DGP) o Open only to localitieso Funding is distributed to the 9 construction districtso Hampton Roads receives 20% of funding availableo Projects compete with other projects from the
same construction district High-Priority Projects Program (HPP)
o Projects applying for HPP funds compete with projects from across the Commonwealth
A project sponsor may request funding under both programs
Smart Scale Funding
Smart Scale Funding
HB1887 new construction formula established, effective FY 2021 State of Good Repair – 45% High-Priority Projects Program – 27.5% District Grant Programs – 27.5%
17
Subject to Smart Scale
High-Priority Program
District Grant Program
Exempt from Smart Scale
State of Good Repair
RSTP, CMAQ, TAP
Revenue Sharing
Regional Revenues
18
Smart Scale Summary
Approximately $1.0 billion is available for Round 2
Smart Scale Total#Apps Requested Project Value
Round 1Statewide Submitted 321 $6.95 billion $13.17 billionStatewide Funded 163 $1.72 billion $3.25 billion
Hampton Roads Submitted 45 $1.86 billion $4.66 billionHampton Roads Funded 21 $0.33 billion $1.07 billion
Round 2 SubmittedStatewide 436 $9.25 billion $12.09 billionHampton Roads 60 $1.07 billion $1.99 billion
19
#Projects Smart Scale Total ValueRound 1 Funded 21 $332.4 million $1.07 billion
Smart Scale Round 1 DeliveryHampton Roads District
VDOT60%
DRPT2%
Local38%
$332.4 million
VDOT33%
DRPT10%
Local57%
21 Projects
Smart Scale Cycle
20
SMART SCALE cycle will transition to a bi-annual process beginning in 2017
22
Name Email Phone #
Emmanuel Darko, PEDistrict L&D Engineer [email protected] (757) 925-2561
Bruce Duvall, PEDistrict Project Management Office Manager
[email protected] (757) 494-5480
Jack McCambridgeDistrict Environmental Manager
[email protected] (757) 925-2631
Jason FowlerDistrict Land Use Manager [email protected] (757) 925-2628
Mark GrassDistrict Regional Operations Projects Manager
[email protected] (757) 925-2203
HAMPTON ROADS DISTRICTPRELIMINARY ENGINEERING TEAM
23
HAMPTON ROADS DISTRICTVDOT Managed Program Overview (Funded Projects to Advertisement)
YEAR(Calendar)
Number of Projects Scheduled to be Advertised
Estimated Value
2017 39 $ 409 M
2018 12 $ 83 M
2019 8 $ 70 M
2020 6 $ 41 M
24
HAMPTON ROADS DISTRICTSelect CY 2017 Projects To Be Advertised(Estimated Construction Value > $ 1,000,000.00
25
HAMPTON ROADS DISTRICTPROJECT DEVELOPMENT (Tier 2 Projects)
Total Estimated Construction Cost = $372.4 Million
Project Est AdI-64/Northampton Blvd Ramp ImprovementsNorfolk
$ 8M Mar 2017
Statewide ITS Maintenance – Hampton RoadsHampton Roads District Wide
$ 14.1M Apr 2017
I-64 Peninsula Widening – Segment III $ 156.4M Mar 2017RFQ
I-264/Witchduck Interchange ImprovementsNorfolk/Virginia Beach
$ 123.8M Jun 2017
Laskin Road Bridge ReplacementVirginia Beach
$ 21.2M Nov 2017
26
HAMPTON ROADS DISTRICTPROJECT DEVELOPMENT (Tier 1 Projects)
Total Estimated Construction Cost = $ 37.2 Million
Project Est AdOn-Call Structural RepairsDistrict Wide
$ 4.0 M Feb 2017
High Rise Bridge Center Lock RepairChesapeake
$ 4.25M Feb 2017
Rt 58 Over Nottoway & Overflow OverlaySouthampton County
$ 1.75 M Mar 2017
Safety Improvements – Route 143York County
$ 2.5 M Sep 2017
Route 635 Over N&W RR and VA State Rt 6042Southampton County
$ 2.4M Sep 2017
27
HAMPTON ROADS DISTRICTPROJECT DEVELOPMENT (Locally Adm. Projects)
Total Estimated Construction Cost = $219.6 Million
Project Est AdAMTRAK Station Site Grading and DrainageCity of Newport News
$ 5.7M Feb 2017
Atkinson BoulevardCity of Newport News
$ 61M May 2017
Rosemont RoadCity of Virginia Beach
$ 12.9M Jun 2017
AMTRAK Station, Platform, and Parking LotCity of Newport News
$ 15.7M Jul 2017
Ft Eustis Boulevard Bridge ReplacementCity of Newport News
$ 22M Dec 2017
28
Project Est AdDenbigh Boulevard Bridge ReplacementVDOT
$ 28.4M Mar 2018
Deep Creek Bridge ReplacementUSACE
$ 34M Mar 2018
Longhill Road WideningVDOT
$ 14.8M Apr 2018
Rt 58/Holland Road Corridor ImprovementsCity of Suffolk
$ 39.5M May 2018
Route 164 Bridge Fender ReplacementVDOT
$ 8M Jul 2018
HAMPTON ROADS DISTRICTSelect CY 2018 Projects Scheduled for Advertisement
HAMPTON ROADS DISTRICTPROJECT DEVELOPMENT(Potential Consultant Design/Service Opportunities)
I-64/264 Interchange “Phase 3” Project Specific Support Contract
Major Projects Program Support Contract• Purpose: Provide Overall Program Management and Technical
Support• Integrated, Dedicated On-Site Support from Key Contract Staff• Projected Services:
• Engineering and Technical Support• Financial Management and Programming Support• Project Controls (Development and Delivery)• Design Build Delivery Alignment• Programmatic Traffic Engineering• Project Schedules (Engineering and Construction)• Specialized Technical Expertise as Needed
29
30
HAMPTON ROADS DISTRICT
CONSTRUCTIONOVERVIEW
John F. Jacobs III, PE, PMPDistrict Construction Engineer
31
Name Email Phone #
John Jacobs, PE, PMP [email protected] (757) 925-2514
Mike Davis, PE, CCM [email protected] (757) 925-2680
John Arms, PE [email protected] (919) 605-7861
Mitch Conner, PE [email protected] (757) 925-7906
Jim Klotz, PE [email protected] (757) 274-2552
Joe Ludwig, PE [email protected] (757) 648-0894
Paul Moose, PE [email protected] (757) 705-3797
Bud Morgan, PhD, PE [email protected] (757) 494-5472
Giles Njumbe, PE [email protected] (757) 253-5367
James Poff, PE [email protected] (757) 925-2581
Chung Wu, PhD, PE [email protected] (757) 925-2674
HAMPTON ROADS DISTRICTCONSTRUCTION TEAM
32
HAMPTON ROADS DISTRICTUS-17, YORK COUNTY
Contractor: E.V. WilliamsContract: $25.2 MNTP: July 12, 2013FCD: Dec 31, 2016
32
33
Contractor: Branscome Contract: $4.34 MNTP: April 11, 2016 FCD: Dec 31, 2016
HAMPTON ROADS DISTRICTPROJECT- DRONE RUNWAY,WALLOPS ISLAND
Photo taken by NASA Wallops Flight Facility33
34 October 2016Photo taken by NASA Wallops Flight Facility
35
HAMPTON ROADS DISTRICTSR-642, NORTHAMPTON COUNTY
Purpose. Safety improvements and enhance access to the Cape Charles Harbor.
Overview. Two 12’ lanes and 8’ width shoulders with 4’ being paved, which will accommodate bicycles and pedestrians.
Contractor: Kevcor ContractingContract: $3.98 MCN Start: Aug 3,2016Complete: Dec 1, 2017
36
HAMPTON ROADS DISTRICTTURNPIKE, PORTSMOUTH
Contractor: E.V. WilliamsContract: $28.3 MNTP: May 13, 2015Complete: May 11, 2018
Photos taken June 14, 2016
37
Contractor: Allan MyersContract: $18.9 MNTP: Dec 20, 2013Ben Occup: Nov 17, 2016Complete: May 15, 2017
Photo taken October 2016
Photo taken July 2015
HAMPTON ROADS DISTRICTLYNNHAVEN PARKWAY, VIRGINIA BEACH
38
HAMPTON ROADS DISTRICTHOLLAND ROAD, VIRGINIA BEACH
NimmoParkway
Damneck
Contractor: Allan MyersContract: $30.9 MNTP: Nov 23, 2014Complete: Jan 31,2018
HAMPTON ROADS DISTRICTTERMINAL BOULEVARD, NORFOLK
39Screen Shot taken by Lane Construction
Contractor: Virginia PavingContract: $ 4.98 MCN Start: May 20, 2016Complete: Nov 18, 2016 FCD: Jan 13, 2017
40 Photos taken by Lane Construction
HAMPTON ROADS DISTRICTTERMINAL BOULEVARD, NORFOLK
41
Replace and widen the existing structurally deficient bridge built in 1936 which crosses over the CSX Railroad and Route 632.
HAMPTON ROADS DISTRICTREPLACE US-58B BRIDGE OVER SR-632 AND CSX RAIL, ISLE OF WIGHT
Contractor: Bryant Contracting Contract: $ 9.4 MCN Start: Feb 22, 2016Complete: Nov 27, 2017
41
42
HAMPTON ROADS DISTRICTUS-301 BRIDGE REPLACEMENT, GREENSVILLE COUNTY
Contractor: Curtis ContractingContract: $ 4.91 MCN Begin: Feb 2, 2015FCD: July 31, 2017
Replace the US-301 southbound Bridge over the CSX railroad tracks.
43
HAMPTON ROADS DISTRICTCOURTLAND INTERCHANGE
Eliminate the existing signalized intersection at US-58 and US-58B.
Improvements will consist of:• Two bridges on a realigned Route 742;
• Two roundabouts will be constructed; and
• Three ramps.
Contractor: Curtis ContractingContract: $14.99 MNTP: Feb 25, 2016Complete: Dec 12, 2018
43
44
Replace bridges with functionally obsolete shoulder widths.
Construction Sequence: o Build new southbound (SB) bridge.o Shift SB traffic to new bridge.o Shift NB traffic to old SB Bridge.o Demolish NB Bridge.o Build new NB Bridge.o Shift NB traffic to be NB Bridge.
Contractor: Wagman Contract: $22.2 MillionNTP: Jan 18, 2016FCD: Oct 1, 2019 Photo taken July 2016
by Wagman
Photo looking South
HAMPTON ROADS DISTRICTI-95 MEHERRIN RIVER BRIDGE REPLACEMENT, GREENSVILLE COUNTY
44
45
I-95Meherrin River
Bridge Replacement
Looking South
LookingNorth
Photos taken by Wagman Sept 2016
HAMPTON ROADS DISTRICTDistrict-wide CEI Contracts
46
Term 2016 2017 2018 2019 2020 2021
Alpha 3 of 3
AMT 3 of 3
NXL 2 of 3
Quinn 2 of 3
MBP(Finals)
2 of 3
In AdIn AdFutureFutureFuture(Finals)
“In Ad” Contracts are advertised with selection date of February 6, 2017
HAMPTON ROADS DISTRICTStand-alone CEI Contracts and Inspections
47
Stand-Alone Consulting Services• I-64 / I-264 Interchange: Volkert • I-64/Witchduck: Currently in advertisement with
selection set for February 2017.
Construction Staff Workload• VDOT has 21 Senior Inspectors, 17 Inspectors, and 8
Inspector Trainees for a total of 46.• Consultant Firms are supplying 4 Construction
Managers, 51 Senior Inspectors, 23 Inspectors, 7 Inspector Trainees for a total of 85.
HAMPTON ROADS DISTRICTConstruction
48
Challenges• Utilities• Constructability• Field Decision-making
Teamwork Accolades• Wallops Drone Runway - Branscome• Terminal Boulevard – Virginia Paving / Lane
49
The Citizens of Virginia expect:• Safe Work Zones• On-time• On-budget• Quality• Environmental Stewardship
Performance Metrics
50
HAMPTON ROADS DISTRICT
Maintenance
Mike Corwin, PEActing District Maintenance Engineer
51
Name Email Phone #
Mike Corwin, PE [email protected] 757-925-2506
Brian Mosier [email protected] 757-925-1648
William Collier [email protected] 757-494-2447
Christopher Eggleston, PE [email protected] 757-925-2689
Andrew McGilvray [email protected] 757-925-3664
HAMPTON ROADS DISTRICTMAINTENANCE TEAM
52
HAMPTON ROADS DISTRICTMAINTENANCE
Asphalt Pavements Ongoing 2016 Paving Contracts (Award Amount ~ $20.5 Million)
• 13 Plant Mix Contracts (137 lane miles)• 1 Latex Modified Contract (10 lane miles)• 4 Surface Treatment Contracts (301 lane miles)
Upcoming 2017 Paving Contracts (Budget Amount ~ $29.5 Million)• 13 Plant Mix Contracts (195 lane miles)
• 1 Plant Mix to resurface Virginia Capital Trail (3 miles)• 2 Latex Modified Contracts (28 lane miles)• 3 Surface Treatment Contracts (339 lane miles)
+ Bonus Project - Concrete Repair/ Plant Mix Overlay• $14.3M/29 lane miles
HAMPTON ROADS DISTRICTMAINTENANCE
Concrete Pavements
Upcoming 2017 Repair Contracts
• Route 164, Western Freeway ($3.5 Million)• Concrete repairs with 2” asphalt overlay (10.8 lane miles)• PM-5K-17 Advertised July 2016• PM-5L-17 To Be Advertised January 2017
• I-664, Southside ($14.3 Million)• Concrete repairs – 2,730 SY• 3.5” asphalt overlay (84,538 Tons/29 lane miles)
53
2014 2015 2016 2017
Quantity Lane Miles Quantity Lane
Miles Quantity Lane Miles Quantity
Lane Miles
Asphalt(Tons)
(4.75 mm)
196,809
(3,054)
277
(5)
108,037
(3,723)
144
(5)
139,409
(2,450)
137
(7)
255,396
(549)
227
(1)Latex Slurry(Tons) 2,849 47 3,489 50 1,558 10 2,690 28
Slurry Seal (SY) 490,666 73 127,321 24 0 0 0 0
Surface Treatment (SY)
2,022,911 308 818,217 157 1,442,759 301 1,916,201 339
Totals 705 375 448 594
Plan
t Mix Interstate 55 50 34,663 25 108,687 50
Primary 147 109 67,129 77 86,074 108
Secondary 503 216 37,617 35 60,635 69
Estimate* $33.6 million $13.4 million $22.5 million $43.8 million* Includes contract, CEI, contingencies, requirements
HAMPTON ROADS DISTRICT MAINTENANCE
192,453
4,356
83,832
24,205
113,836
25,573
170,828
84,568
-
50,000
100,000
150,000
200,000
250,000
2014Schedules
2014 BonusOA
2015Schedules
2015 ExtraSchedules
2016Schedules
2016 Bonus 2017Schedules
2017 Bonus
Tons
of A
spha
lt
55
Asphalt Tonnage, 2014 – 2017
(2014)196,809
(2015)108,037
(2016)139,409
(2017)255,396
56
District Paving Performance Measures
IS/PR Target =82%
Secondary Target =65%
57
HAMPTON ROADS DISTRICT MAINTENANCE – Structure & Bridge Contracts
Projects Under Construction: 6 Bridge Maintenance
• 2 Deck Waterproofing (~$7.1M CN value)• 2 On-Call Structural Repair (~$7M per year)• 1 Bridge Washing (~$200K per year)• 1 Steel Repair and Deck Waterproofing (~$3.6M CN value)
8 Bridge Replacements• 1 Bridge Rte. 301 over CSX (~$4.8M) • 2 Bridges I-95 over Meherrin (~$22.2M CN value)• 1 Bridge Rte. 58 over CSX (~$6.7M CN value)• 2 Bridges Rte. 621 & Rte. 680 (~$1.8M CN value)• 1 Bridge Rte. 35 over Tarrara Ck. (~$1.8M CN value)• 1 Bridge Rte. 301over Nottoway River (~$3.6M CN value)
58
HAMPTON ROADS DISTRICT MAINTENANCE – Structure & Bridge Contracts
Projects within 6 months of Advertisement: 4 Bridge Maintenance
• 1 Movable Bridge Repair (~$3.6 CN value)• 1 Bridge Painting (~$2.2M CN value)• 1 Bridge Repair (~$800K CN value)• 1 On-Call Structural Repair (~$3M per year)
2 Bridge Replacements• 1 Bridge Rte. 635 over NS R&R (~$2.4M CN value)• 1 Bridge Rte. 662 over Ragged Island Ck. (~$1.0M CN value)
59
HAMPTON ROADS DISTRICT MAINTENANCE – Structure & Bridge Contracts
Projects Under Design:
9 Bridge Maintenance• 7 On-Call (~$18M CN value)• 2 In-House (~$5M CN value)
12 Bridge Replacements• 9 On-Call (~$40M CN value)• 1 Project Specific (~$29 CN value)• 2 In-House (~$2M CN value)
Future Design Projects: 7 Bridge Maintenance
• 5 On-Call (~$50M CN value)• 2 In-House (~$3M CN value)
4 Bridge Replacements• 4 On-Call (~$7M CN value)
60
HAMPTON ROADS DISTRICT MAINTENANCE Bridge Condition Trends
62
Name Email Phone #
Dwayne Cook [email protected] (757) 925-2405
Ken Coody [email protected] (757) 361-3055
Rob Weber, P.E. [email protected] (757) 925-3610
Chuck Dixon [email protected] (757) 925-1679
Laurie Cordrey [email protected] (757) 925-2350
Alton Yates [email protected] (757) 727-4813
HAMPTON ROADS DISTRICTOPERATIONS TEAM
63
VDOT relies heavily on technology to manage transportation challenges and support critical programmatic initiatives that include
Key components of VDOT’soperations program include
– Transportation Operations Centers– Roadside devices and
communications infrastructure– Safety Service Patrols– Traveler Information Systems
• Congestion Management• Incident Management• Emergency Response• Traveler Information• Signal Systems
Quick Clearance
HAMPTON ROADS DISTRICTOPERATIONS
64
Staff Augmentation Contracts Professional Engineering Services Project Management Skilled Trades, Technicians,
Operators Commercial Services (i.e. wrecker
service)
Industrial Systems Maintenance &Replacement Mechanical Electrical Power Distribution Electronic SCADA
HAMPTON ROADS DISTRICTOPERATIONS
Asset Installation & Maintenance ServicesPavement MarkingsRoadway SignsGuardrailRoadway Lights
Traffic Signal Design& Installation Services
Marine Vessel ServicesMaintenanceRepairsDesign
65
Ongoing ‘On-Call’ Contracting Needs
• Pavement Markers/Markings/Messages• Traffic Engineering Services• ITS Construction Engineering & Inspection (CE&I) Services • ITS General Consulting Services• ITS Deployment Services• Traffic Signal Design & Installation • Guardrail Repair and Installation Services
HAMPTON ROADS DISTRICTOPERATIONS
66
HAMPTON ROADS DISTRICTOPERATIONS
Jamestown-Scotland Ferry Projects
Asset Installation & Maintenance Projects
Project Est Ad
Pocahontas – Engine & Propulsion Drive Replacements $5 M Summer 2017
Surry – Shipyard Overhaul $2.7 M Jan 2017Jamestown Slips – Repair Piles & Steel Framework $1.7 M Winter 2018
Project Est AdI-664 High Mast Light Pole $3 M Nov 2017
67
HAMPTON ROADS DISTRICTOPERATIONS
I-564 Projects
Monitor Merrimac Memorial Bridge Tunnel Projects
Project Est AdOpen Cut Seepage Repairs $40 K Dec 2016Newport News Inspection Station Barrier Offset $200 K Mar 2017Mid River Pump Room Repairs $500 K Summer 2017Cross Passage Egress & Signage $786 K Sep 2017
Replace Roadway Drainage Pumps (5 submersible) $714 K Sep 2018
Project Est AdTunnel - Roadway Lighting Replacement $2 M Jun 2017Emergency Generator Replacement $550 K Sep 2017
68
HAMPTON ROADS DISTRICTOPERATIONS
Hampton Roads Bridge Tunnel Projects
Project Est Ad
Ceiling Panel Repairs – Phase II Cut and Cover Section $554 K Jan 2017
Tide Gate Pin Pocket Repair $200 K Jan 2017
15th View Inspection Station Improvements $100K Jan 2017
Mechanical Over Height Measuring Station $50 K May 2017
Lightning Protection $ 500K Jun 2017
Electrical Mechanical Upgrades, Installation of COOP $3 M Oct 2017
Armor Stone Replacement $1.5 M May 2018
Roadway Plate Repair $715 K Jul 2018
Submersible Pumps $750 K Jun 2018
Ceiling Panel – Phase III Exhaust Duct Epoxy Injection $2 M Sept 2018
6868
69
HAMPTON ROADS DISTRICTOPERATIONS
Hampton Roads TOC Service ContractsProject Est Ad
Operations Program Management Support(3 yr w/ 2 – 1yr renewals) * Advertised
ITS Maintenance(3 yr w/ 2 – 1yr renewals) * Dec 2016
TOC Floor / Safety Service Patrol * Jan 2017
Tunnel Service ContractsProject Est Ad
HRBT Ventilation Fan Maintenance (5 yr, w/ 2 – 2yr renewals) * Dec 2016
MMMBT Ventilation Fan Maintenance(3 yr, w/ 2 – 1yr renewals) * Mar 2017
HRBT, MMMBT & James River Bridge Wrecker Service(3 yr w/ 2 – 1yr renewals) * Mar 2017
* Combined total annual estimated value ~$20M
Allowable Lane Closure Hours Document Purpose – provide standard allowable hours for:
Work beyond the shoulder Shoulder and Lane Closure Hours Full directional closures Ramp Closures Managed lane closures Process to manage work when it cannot be completed within allowable
hours
Adherence does not constitute approval
Additional considerations Scheduled water crossing closures expected to change traffic patterns Expected traffic impacts (if working outside allowable hours) Adjacent and/or nearby active work zones Special events/holidays Importance and/or urgency of work
HAMPTON ROADS DISTRICTOPERATIONS
70
Sample page from ALCH document
• VDOT Website search – Hampton Roads District Lane Closures
HAMPTON ROADS DISTRICTOPERATIONS
71
72
Thank You BE SAFE every minute of every day!
73
QUESTIONS?Follow us on Facebook, Twitter and YouTube.