Vault 9 Project Update9th September 2009

Paul Pointon – Site Project Delivery Manager

LLW Repository Ltd

Page 2: Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

Date: 11/03/2009 2

Overview of Presentation

• Vault 9 Design• Current Status

Page 3: Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

Date: 11/03/2009 3

Vault 9Vault 9 Design

Page 4: Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

Date: 11/03/2009 4

Plan Overview Scheme

ANDY – Can you insert the base site plan that you are using to show the new material facility plan – Showing the Current infrastructure

Page 5: Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

Date: 11/03/2009 5

Proposed Development

Page 6: Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

Vault 9 Liner Details

Page 7: Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

Date: 11/03/2009 7

Vault 9Current Status

Page 8: Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

Date: 11/03/2009 8

Bulk Excavation – 100% Complete

Page 9: Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

Date: 11/03/2009 9

Rail Deliveries – Aggregate, Reinforcement & Ancillaries

Page 10: Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

Date: 11/03/2009 10

Rail Deliveries – Port of Workington

Page 11: Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

Date: 11/03/2009 11

Rail Deliveries – Millom Main Line Loading

Page 12: Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

Date: 11/03/2009 12

West Outer Wall Construction - 95% Complete

Page 13: Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

Date: 11/03/2009 13

Secant Pile Wall – 100% Complete

Page 14: Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

Date: 11/03/2009 14

BES Bottom Layer - 80% Complete

Page 15: Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

Date: 11/03/2009 15

Geomembrane, Geotextile & Drainage Layer – 45% Complete

Page 16: Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

Date: 11/03/2009 16

Vault 9 Floor Slab - 22% Complete

Page 17: Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

Date: 11/03/2009 17

West Inner Wall - 60% Complete

Page 18: Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

Date: 11/03/2009 18

Partial Handover – 21st July 2009

Page 19: Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

Date: 11/03/2009 19

Delivery Schedule

• Partial Turnover to Operations – July 2009

• Operational Safety Case Approved

• First HHISO –July 2009• Contract Completion –

January 2010

Page 20: Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

Date: 11/03/2009 20

Vault 9Questions