2
Vapor Lock Project Synopsis Project: Casey’s Pizza & Bar, Vapor Lock enhanced concrete Project Location: Port Huron, Michigan A/E/GC: East Lake Builders, Port Huron, Michigan Concrete Contractor: Nutech Services, Michigan Batch Plant: Port Huron Building Supply, Port Huron, Michigan Project Description: Three separate pours, two at 2,000 sqft colored concrete, one pour was 300 sqft colored in-laid bar top Project Date: June 2013 Product’s used: Vapor Lock 20/20 WVRA Notes: First pour 2,000 sqft colored in-laid concrete, second pour 2,000 sqft colored stamped concrete, third pour 300 sqft colored in-laid bar top. First pour “washout” cost was cut in half because how quickly truck cleaned-up. Both the Batch Plant and the flatwork contractor have been certified by Specialty Products Group. Concrete was epoxy coated in 14 days !

Vapor Lock Project Synopsis - SPG Go Green · 2019-09-18 · Vapor Lock Project Synopsis Project: Casey’s Pizza & Bar, Vapor Lock enhanced concrete Project Location: Port Huron,

  • Upload
    others

  • View
    11

  • Download
    0

Embed Size (px)

Citation preview

Vapor Lock Project Synopsis

Project: Casey’s Pizza & Bar, Vapor Lock enhanced concrete

Project Location: Port Huron, Michigan

A/E/GC: East Lake Builders, Port Huron, Michigan

Concrete Contractor: Nutech Services, Michigan

Batch Plant: Port Huron Building Supply, Port Huron, Michigan

Project Description: Three separate pours, two at 2,000 sqft colored concrete, one pour

was 300 sqft colored in-laid bar top

Project Date: June 2013

Product’s used: Vapor Lock 20/20 WVRA

Notes: First pour 2,000 sqft colored in-laid concrete, second pour 2,000 sqft colored

stamped concrete, third pour 300 sqft colored in-laid bar top. First pour “washout” cost

was cut in half because how quickly truck cleaned-up.

Both the Batch Plant and the flatwork contractor have been certified by Specialty

Products Group. Concrete was epoxy coated in 14 days !

4,000 sqft slab on grade, stamped and colored Vapor Lock 20/20 enhanced concrete