Upload
amrit
View
11
Download
0
Tags:
Embed Size (px)
DESCRIPTION
itb wapcos
Citation preview
NO. WAP/EPC/CAM/2013
TENDER DOCUMENT
SUPPLY AND INSTALLATION OF HAND PUMPS FOR AUGMENTATION OF RURAL
WATER SUPPLY IN CAMBODIA
VOLUME II GENERAL TECHNICAL SPECIFICATIONS
WAPCOS LIMITED House No. 260, St. 2013, Group 14, Tangon Village,
Kakab Commune, Dangkor District, Phnom Penh, Cambodia
Tel: (855) 23866329 Email: [email protected]
December, 2013
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-1
WAPCOS Ltd. Bidder
BIDDING DOCUMENT
FOR
SUPPLY AND INSTALLATION OF HAND PUMPS
FOR AUGMENTATION OF RURAL WATER SUPPLY
IN CAMBODIA
VOLUME – II
GENERAL TECHNICAL SPECIFICATION
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-2
WAPCOS Ltd. Bidder
VOLUME II
GENERAL TECHNICAL SPECIFICATION
CONTENTS
Section No Title of Sections
SECTION – 1 Intent of General Technical Specifications
SECTION – 2 Working Facilities
SECTION – 3 Survey and Investigations
SECTION – 4 Installation of Hand Pumps
SECTION – 5 Drawings
SECTION – 6 Broad Village wise Locations for Installation of Hand Pumps
Annexure I Bore Well Schedule
Annexure II Pumping Data Schedule
Annexure III Well Pump Training & Receipt of Tools and Spare Parts
Record
Annexure IV Pumping Test Recording Sheet
BiddingDocumentforSupplyandInstallationofHandPumpsforAugmentationofRuralWaterSupplyinCambodia
========================================================================================
SECTION-1
INTENT OF GENERAL TECHNICAL
SPECIFICATIONS
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-3
WAPCOS Ltd. Bidder
SECTION-1
INTENT OF GENERAL TECHNICAL SPECIFICATIONS
1.1 Introduction
The General Technical Specifications (hereinafter called GTS) will give general information
about execution of various items of works under the Contract and cover the specified
stipulations for measurements and payments therefor included in the Bill of Quantities.
These specifications are part of the requirements for various items of works, which shall be
executed according to the stipulations of the Contract. Hence, the instructions given herein
form an integral part of the bidding document for the works. Addenda to these specifications
may be issued, as and when required during bidding and construction phases.
These specifications shall be read in conjunction with the Bill of Quantities (BoQ in the
Financial Bid), drawings and the Conditions of Contract. While quoting the price, the
Contractor shall comply with all provisions contained in the Bidding documents with the
objective to complete each item of work without any addition of cost thereof. In case
Specifications, BoQ and Condition of Contract do not corroborate each other towards
completion of any particular item of work, the same as well as the assumptions made in
quoting of price for such item(s) of Works shall be brought out clearly in the Technical
Proposal.
It is the intent of these specifications to establish acceptable standards of quality as specified
in the technical specifications. Minor deviations in details due to manufacturer’s standard
shop process will be considered for acceptance provided that, in the opinion of the Employer/
Project Executor, the proposed substitutions are equal in quality to those specified.
All works shall be executed in conformity with the approved construction drawings and
instructions issued by the Employer/ Project Executor for construction. Execution of works
contemplated under these specifications shall include, in complete, all the procurement and
supply of required Man power (skilled and un-skilled) and Materials (inclusive of royalties,
and all other taxes and charges as levied, if any), Equipment, Plant and Machineries, office,
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-4
WAPCOS Ltd. Bidder
stores and workshop etc., transportation, handling and placement of Materials and Equipment
to site in a professional and diligent manner. All works shall comply with the quality
requirements defined in the relevant sections of these specifications and other sections of the
bidding document to the satisfaction of the Employer/ Project Executor.
1.2 Scope of Work
The broad scope of work in general, shall be supply and Installation of 1500 Afridev Hand
Pumps for Augmentation of Rural Water Supply in Kampong Cham and Banteay Meanchey
Provinces of Cambodia, which shall include Engineering, Procurement, Supply and Drilling /
Installation, Commissioning, Testing, Operation and Maintenance for one year of Hand
Pumps, but not limited to the following works:
i. Engineering and Development of local Infra-Structures in each Province [The Contractor shall provide offices with all camp facilities / inspection vehicles for Employer/ Project Executor and / or his authorized representatives for site inspection and office works in addition to his own requirements for field works as described in Section : Camp Equipment / Facilities in GTS. Such camp facilities shall be provided in the central locations in each province to maneuver execution of works at different villages under the respective provinces].
ii. The Contractor shall clear the parts of the Site to be occupied by the Permanent Works of all vegetation and artificial obstructions including the occurrence of mines if any. The responsibility for clearance of mines if any in the selected locations for the hand pumps will be that of the Contractor who would take necessary steps for clearance in consultation and with the cooperation of MoRD.
iii. Preparation of sites
iv. Procurement, Supply and Installation of 1500 Afridev Hand Pumps (SKAT Revised Edition-4) with all accessories, spare parts and tools at the identified sites in different Districts/ Communes/ Villages of Kampong Cham and Banteay Meanchey Provinces in Cambodia.
v. Drilling of Boreholes, installation of Well Assembly and Installation of 1500 Hand pumps with construction of RCC platforms with drainage outlets at designated locations as per GTS.
vi. Commissioning, Testing and handing over after successful operations of Hand Pumps.
vii. Testing of water yield.
viii. Testing for water quality.
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-5
WAPCOS Ltd. Bidder
ix. Preparation of basic data report for each Hand Pump site.
x. Providing Training to the community members and others as approved by the Employer/
Project Executor or their representatives in coordination with MoRD.
xi. Providing set of tools and spare parts for operation, maintenance and upkeep of Hand Pumps
along with the standard “user manuals” for the installation, operation and maintenance
procedures produced by Manufacturer both in English and local Khmer language.
xii. Operation and maintenance of each Hand Pump after the successful installation till the Defect
Liability Period for one year.
xiii. Availability of good drinking water through these Hand Pumps and their operation and
maintenance at least up to the Defects Liability Period (DLP) for one year will be the
responsibility of the Bidder/ Contractor. In case, availability of water through any of these
1500 hand Pumps during DLP is interrupted for any reason, the Hand Pump will have to be re-
commissioned at the other location as approved by the Employer at the Bidder’s risk cost and
responsibility.
xiv. Ensuring sustained availability of spares.
xv. Placing the plaque at the site as approved by the Employer/ Project Executor.
BiddingDocumentforSupplyandInstallationofHandPumpsforAugmentationofRuralWaterSupplyinCambodia
========================================================================================
SECTION -2
WORKING FACILITIES
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-6
WAPCOS Ltd. Bidder
SECTION -2
WORKING FACILITIES
2.1 Scope of Work
The Scope of work for the Contractor under this section shall be to design, provide, erect/
commission, operate and maintain all the working facilities including shipment and
mobilization of material, equipment ,machinery ,personnel and labour, required for the
execution of the Works, such as but not necessarily limited to the following:
• Office and Camp Facilities
• Plant and Equipment
• Electric Power Supply System
• Water Supply System
• Communication Network
• Sewage and Waste Water Disposal System
• Transportation system
• Testing Laboratory for quality control
Materials for the working facilities shall be new and of first-class quality. The capacity and
number of equipment shall conform to the specific minimum requirements for the works they
are intended for and the climatic conditions prevailing at the site. The Contractor shall
maintain all his equipment and machineries with sufficient spare parts, special tools for repair
work and complete standby units of vital parts to guarantee a continuous operation without
any delays. The Contractor shall be fully responsible for any delays due to disregard of said
necessity.
Working Facilities shall be subject to the Employer/ Project Executor approval. The
Contractor shall, prior to dispatching any items of the Working Facilities, give written notice
to the Employer/ Project Executor with clear indications about the purpose of the items, the
kind, date and place of consignment for approval. Said notice must be given in due time to
allow for a possible cancellation in case the items do not comply with the requirements as
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-7
WAPCOS Ltd. Bidder
stipulated. The Employer/ Project Executor will issue the response within 15 days of receipt
of the notice.
Should the Employer/ Project Executor determine that the equipment furnished does not meet
all requirements, the deficiencies shall be corrected by the Contractor before further use, or
the deficient equipment shall be replaced with satisfactory equipment. Any cost incurred in
the correction or replacement shall be borne by the Contractor.
The Contractor shall comply with all laws, regulations, and ordinances relating to the
construction and operation of the working facilities applicable in Kingdom of Cambodia.
2.2 Submittals
The Contractor shall submit basic plans of Working Facilities together with his bid. He shall
attach to his bidding documents, drawings, pictures and operating descriptions for his
proposed working facilities and shall indicate weight, standards, capacity, manufacturing date
and country of origin.
At least 15 days prior to commencing the work, the Contractor shall submit to the Employer/
Project Executor for approval the drawings of layout and details of Working Facilities.
2.3 Working Facilities
2.3.1 General
The Camp Facilities shall include, but are not limited to:
Camp offices and Accommodation
Miscellaneous Working Facilities like
• Warehouses and Equipment yard/ Sheds for the Contractor
• Workshops / Garages
• Inspection Vehicles
All working facilities shall be equipped with proper light arrangement, water supply,
communication system, sewage and waste water disposal system. Contractor shall make his
own arrangement for all working facilities.
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-8
WAPCOS Ltd. Bidder
2.3.2 Office and Camp Facilities
The Contractor shall supply all facilities as mentioned in Clause 3.2.6.2 of Employer’s
Requirements.
He shall also ensure that an adequate supply of replacement items and spare parts covering all
the facilities is always available on site. In the case of work station computing facilities, the
Contractor shall ensure that adequate back-up is available in the event of a malfunction.
2.3.3 Plant and Equipment
The Contractor shall provide all construction plants and equipment like truck mounted
drilling rigs, concrete mixtures, etc. as would be necessary for the efficient execution of the
work simultaneously in three LOTS in accordance with the Specifications as well as the
details furnished by the Contractor in the constructional plant and equipment schedule. The
Contractor shall also deploy additional equipment, if needed, at his own cost for timely
completion of the Works.
2.3.4 Electric Power Supply System
The Contractor shall make his own arrangement for supply of power at all offices, stores /
garages, etc inclusive of all working places throughout the working period upto Defects
Liability Period. At the working places, the Contractor may have to provide his own
generating sets, depending upon site conditions.
2.3.5 Water Supply System
The Contractor shall make his own arrangement for the adequate supply of potable water to
the field offices and the working places.
2.3.6 Communication Network System
The Contractor shall supply, install, operate and maintain an appropriate Tele-communication
network, complete with standby power supply, to connect his offices with those of the
Employer/ Project Executor and all working places. He shall furnish a directory of the various
equipments installed at the Site and make it available to the Employer/ Project Executor.
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-9
WAPCOS Ltd. Bidder
2.3.7 Sewage and Waste Water Disposal System
The Contractor shall design, construct, equip, operate and maintain all the installation
necessary to properly collect and dispose of sewage from his camps, Employer/ Project
Executor site office and other construction facilities. The Contractor shall not, under any
circumstances, discharge sewage or contaminated water into natural streams or any open
areas. Collection and Disposal of sewage shall be performed in accordance with the current
related standards and laws in force in Cambodia and always subject to the Employer/ Project
Executor approval.
2.3.8 Transport System
In addition to his own requirements for transport of ‘Men & materials” from one place to
other, the Contractor shall provide two Inspection Vehicles- one at each office at the
provincial headquarters for use by the Employer/ Project Executor and/ or their authorized
representatives for site visit/ inspection works, etc. The vehicles shall be provided with drivers
and POL and other essentials as may be required time to time. The vehicles shall be in good
serviceable condition with proper provisions.
2.3.9 Chemical Laboratory
For ensuring proper and acceptable quality of ground water, it is essential to have fully
equipped chemical laboratory for determination of various radicals for ascertaining the
chemical and pathogenic characteristics of the ground water. The concentration of various
parameters like pH, Total Dissolved Solids (TDS)/ Electric Conductivity (EC), Hardness as
CaCO3, Chlorides (Cl), Sulphates (SO4), Fluoride (F), Nitrate (NO3), Calcium (Ca),
Magnesium (Mg), Manganese (Mn), Iron (Fe), Arsenic (As) and Pathogenic contamination
like Total Coliforms & Fecal Coliforms would need to be determined. The facility for
chemical analysis available in the existing laboratories namely; Ministry of Industry Mines
and Energy (MIME) Laboratory and Laboratory of Institute of Technology of Cambodia
(LITC) which are approved by the Ministry of Rural Development, Cambodia may be availed
for the purpose. However, in case the above laboratories are inadequately equipped the same
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-10
WAPCOS Ltd. Bidder
shall be upgraded or other appropriate arrangements shall be made by the Contractor at his
cost for conducting the desired chemical and pathogenic analysis of the ground water.
The Contractor shall also provide suitable Field Testing Kits in each of the 3 areas involving
LOT I (Memot District of Kampong Cham Province – 758 Hand Pumps), LOT II (Tboung
Khmum & Krouch Chhmar Districts of Kampong Cham Province – 542 Hand Pumps) and
LOT III (Banteay Meanchey Province – 200 Hand Pumps), for in situ spontaneous tests for
each Hand Pump site for determining the water quality. During the execution of the project
the Employer/ Project Executor will have the right to change the number of Hand Pumps in a
particular LOT and also the locations of the Hand Pump in a particular village for which the
Contractor will not be entitled for any extra cost. The Contractor shall ensure facility for
precise sounding of the bore holes down to the depth upto 100 m.
The laboratory shall be well equipped to conduct the following tests as per accepted
international standards but not limited to:-
1. Ground Water Samples
The Contractor shall collect the samples as specified or as directed by the Employer/Project
Executor, carryout the relevant test under the guidance of Employer/Project Executor or his
representative, prepare the complete report and submit them to the Employer/Project
Executor. All tests will be conducted according to the approved standards and therefore, the
equipment shall comply with the same standards. All relevant standards shall be made
available in the laboratory.
2.4 Misc. Working Facilities
2.4.1 Workshops and Sheds
The Contractor shall construct and maintain warehouses, storage yard, a workshop for repairs,
vehicle sheds / garages, fuel storages etc. for the efficient execution of the work at different
locations as per requirements.
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-11
WAPCOS Ltd. Bidder
2.4.2 Site Security
The Contractor shall employ adequate security guards at the worksite and also at the field
offices on 24-hours duty including all non-working days i.e. Sundays and holidays. Storage
areas shall be fenced, lighted and regularly patrolled by security guards. The Contractor shall
be entirely responsible for any loss occurring in his installations and those of the
Employer/Project Executor, resulting from carelessness on the Contractor’s part.
2.4.3 Medical Care Facilities
The Contractor shall comply with laws and health standards presently in force in Cambodia.
In the event of illness of an epidemic nature breaking out, the Contractor shall carry out and
comply with all orders, arrangements or regulations, which may be issued by the Government
or local authorities. Each site shall be provided with sufficient first aid facilities.
2.4.4 Environmental Obligations
The Contractor shall, during the whole period of the Works, comply fully with all applicable
laws and regulations relating to environmental protection, mitigating measures for reducing
environmental impacts and remedial works on completion of the Works. This obligation shall
extend to the construction sites including all site installations as approved by the Employer/
Project Executor.
2.4.5 Final Clean-Up
Upon the Completion of Works the Contractor shall dismantle and demolish all temporary
structures/ scaffolding, etc. and remove all refuse, debris, and objectionable material, and fill,
grade and dress all excavated areas in a clean and proper condition acceptable to the
Employer/Project Executor. All such areas, as far as possible, shall conform to the natural
appearance of the landscape.
2.5 Measurement and Payment
Measurement and Payment for the works will be made as per the provision of General
Conditions of Contract and Particular Conditions of Contract.
BiddingDocumentforSupplyandInstallationofHandPumpsforAugmentationofRuralWaterSupplyinCambodia
========================================================================================
SECTION-3
SURVEY AND INVESTIGATIONS
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-12
WAPCOS Ltd. Bidder
SECTION 3
SURVEY AND INVESTIGATIONS
3.1 General
Before submission of the Technical Proposal / Financial Bid, the Bidder are
encouraged to visit the sites and collect the required information about quality of
ground water in particular, etc. He can have interactions with the local people. Though
some results/ information about geological formation vs ground water quality at the
proposed sites have been furnished along with the Bidding Documents, but these are
indicative only and the Bidder should make his own assessment for availability of
materials, transport facilities, accommodation facilities, communication facilities, etc
at the sites.
3.2 Information for Location of Hand Pumps
The field investigations in the project area had been conducted earlier by a team of
Hydrogeologist, Geophysicist and Engineer in both the provinces. The results of these
field surveys have been documented in a report which will be made available for
guidance to the successful bidder. The broad village wise locations of sites for
installation of Hand Pumps are given in the GTS Section 6. The exact sites for each of
the 1500 locations for installation of the Hand Pumps will be intimated to the
successful Bidder along with the work order. Further, during the execution of the
project the Employer/ Project Executor will have the right to change the number of
Hand Pumps in a particular LOT and also the locations of the Hand Pump in a
particular village for which the Contractor will not be entitled for any extra cost. If any
information contradictory to expectations is collected by him, he should bring out the
facts for needful action by the Project Executor.
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-13
WAPCOS Ltd. Bidder
It may be mentioned that the Bidder should ensure that good quality drinking water
will be available through these hand Pumps. Successful installation of the Hand Pumps
will be the sole responsibility of the Bidder. In case, after installation, Arsenic
contaminated and /or acidic/ toxic radicals are identified through chemical tests, the
tube well shall have to be abandoned, resulting in withholding payment for drilling
and associated works for that particular work. In that case, the Bidder shall have to
install the Hand Pump at an alternate location as approved by the Site Engineer/
Project Executor/ MoRD representative, without any extra cost.
BiddingDocumentforSupplyandInstallationofHandPumpsforAugmentationofRuralWaterSupplyinCambodia
========================================================================================
SECTION-4
INSTALLATION OF HAND PUMPS
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-14
WAPCOS Ltd. Bidder
SECTION 4
INSTALLATION OF HAND PUMPS
4.1 General
4.1.1 This section covers installation of Hand Pumps at the designated locations in Kampong Cham
and Banteay Meanchey Provinces of Cambodia together with supply of all required materials,
labour, plant and equipment for the works as per specifications and approved drawings and /or
as directed by the Employer / Project Executor or their authorized Representative. The works
involved under this section are, but not limited to :
• Drilling of bore holes through all geological formations at the identified sites and
providing MS/PVC casings in underground soil strata to prevent collapse of bore well.
• Collection of underground soil / water samples for in-situ and Lab Tests
• Lowering of well assembly (vertical PVC Casing / Screening Pipes).
• Filling in annular gaps by pea gravel between borehole surface and PVC screen pipes and Bentonite and Cement Seal as per the specifications
• Development of the underground structure by deploying compressor/ centrifugal pump/ submersible pump to obtain totally sand free water.
• Carrying out Aquifer Performance Test (APT)
• Disinfection of bore well by Chlorination
• Installation of Afridev Hand Pumps • Construction of Base Platform including consolidation grouting and provision of
drainage outlet. • Operation and Maintenance of each Hand Pump during Defects Liability Period of one
year. • Training of Community regarding Operation and Maintenance along with provision of
a set of tools and spares.
4.1.2 Typical drawing for well structure as well as the drilling well with Afridev Hand Pump and also the drawing for Platform with the drainage outlet are given in Section 5. However the Bidder will submit all the relevant drawings with specifications along with the bid, which will form the basis for execution of the project.
4.1.3 All well data shall be recorded by the Contractor in the forms as given at Annexure I, II, III
and IV.
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-15
WAPCOS Ltd. Bidder
4.2 Submissions
(1) At least thirty (30) days prior to commencement of the drilling work, the Contractor
shall submit to the Employer / PE for approval, his complete schedule of works
including updated list of equipment and experienced working personnel to be assigned
for simultaneous operations at different locations. In preparing his program, the
Contractor shall duly consider the overall construction schedule and arrange suitably
to achieve overall work progress as per approved schedules. This program shall show
operation and time requirements related to a particular location or working sections,
type, number and other data of equipment used, materials to be furnished, details on
drilling and equipping bore well with appropriate PVC tubage assembly and
operational methods to be applied, etc. The schedule of works shall be furnished with
the approach and methodology along with a bar chart in respect of complete
installation of hand pumps in each province.
(2) The Contractor shall maintain Weekly and Monthly Progress Reports at site and
submit to the Site Engineer periodically (Weekly & Monthly) with all records and
summary of drillings & drill records, sampling & testing of soil and water testing,
problems encountered , if any etc for each location of work.
4.3 Standards and Codes
Installation of the Hand Pumps with allied works shall conform to the Indian Standards
(Table 4.1) or equivalent International Standards and / or as directed by the Engineer.
Table 4.1 : Reference Indian Standards and Codes
Sl.No. Code No. Title of code
1 IS: 6926 Diamond Core drilling for Site Investigation for River Valley Projects.
2 IS: 4078 Code of Practice for Indexing and Storage of Drill Cores
3 IS: 4464 Code of Practice for Presentation of Drilling Information and Core Description in Foundation Investigation
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-16
WAPCOS Ltd. Bidder
4 IS : 6935 Method for Determination of Water Level in a Borehole
5 IS : 4895:2000 U PVC casings and Screens [slotted pipes for bore well/ tube wells]
7 IS-383 – 1997 Specification for Coarse and Fine Aggregates from natural sources for concrete.
8 IS: 2386(P-I) Method of Tests for Aggregates for concrete : Particle size and shape
9 IS-269 – 1998 Specification for Ordinary Portland Cement (33 Grade).
10 IS-12584 – 2000 Specification for Bentonite for grouting in Civil Engineering works.
11 IS-14343 – 2001 Guidelines for choice of Grouting Materials for alluvial
grouting.
12 IS-2720 (P-V) Method of Tests for Liquid and Plastic Limits1
13 IS-4999 Recommendations for grouting of pervious soil.
4.4 Material, Plant and Equipment
4.4.1 General
All Construction / Installation materials like hand pumps, pipes, cement, aggregates and all
construction plant and equipment with all necessary attachments and tools, installations
,auxiliary services etc. shall be provided by the Contractor as required for an adequate
performance of the works within given time limits.
Type and number of the plant and equipment for drilling and sinking of PVC pipes vertically
inside the boreholes as well as all required materials for construction / installation of hand
pumps and consumables including in-situ and lab tests are subject to the approval of the
Employer/ Project Executor or their authorized representatives.
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-17
WAPCOS Ltd. Bidder
4.4.2 Construction/ Installation Materials
(a) Hand Pumps
AFRIDEV Hand Pumps (SKAT Revision 4) shall be installed at each identified location. The
bidder shall however provide the design and drawing of the Afridev Hand Pump (SKAT
Revision 4) with list of accessories, tools and spare parts along with his bid.
(b) PVC Casings
The Rising mains shall be PVC Casings of 101.6 mm (4”) dia (8.5 Bar), conforming to IS:
4895:2000. The pipes shall have all fittings and fixtures at the ends for jointing and shall be
straight, uniform in shape & free from any deformity or injury. The pipes shall be strong
enough to resist earth pressure upto 100 m depths, when the casings will run dry. Total length
of PVC pipe with screens shall not exceed 100 m at different sites, depending upon prevailing
water table and anticipated draw down.
(c) PVC Screens
The screens shall be slotted / perforated PVC pipes of 101.6 mm (4”) dia with slot size of
1.587mm or 1/16” duly cladded with vinyl sheets, and fitted with matching couplings /
sockets at the ends for jointing with casing pipes, and shall conform to IS: 4895:2000. Length
of the PVC Screens shall be 6m to 10m , depending upon the thickness of the aquifer which
shall be identified through Logging/ Litholog of the drilled bore wells.
All manufacturing details alongwith the samples of PVC Casings as well as PVC Screens
shall be submitted to the Employer/ Project Executor or the Site Engineer for approval, 30
days prior to the shipment of the pipes.
(d) Cement
Cement shall be in general, Ordinary Portland Cement (OPC) in conformity to the
requirements as specified in IS : 269. Cement shall be stored in adequate quantities and in an
appropriate manner so that the quality remains unchanged.
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-18
WAPCOS Ltd. Bidder
(e) Sand
Sand shall comply with the requirements as specified in IS : 383.
(f) Bentonite
Bentonite is clay having high content of montmorillonite (83% or more) and shall be naturally
powdered pure sodium cation base with high swelling characteristics. It shall be of high grade
quality conforming to IS: 12584-2000.
(g) Water
The water to be used in concrete / the grout and / or other purpose shall be fresh, clean and
free from harmful amounts of sewage, oil, acid, alkali, salts, or organic or any other
deleterious /undesirable matters. Necessary tests have to be performed by the Contractor to
ensure clean and non-contaminated fresh water without additional payment.
(h) Pea Gravel
Pea gravels shall be assorted and uniform in size of 2mm to 6mm size with tolerance of ±5%,
made from hard rocks. The gravels shall be free from flat particles, shale particles, anhydrite
and gypsum and shall be cleaned and washed properly before use.
(i) Drainage Outlet
The drainage outlet shall comprise of 203.2 mm x 150 mm and 5 m long as detailed in the
drawing. The sub-surface shall be well dressed with a uniform slope and compacted
satisfactorily before laying of drain. Broad specifications have been given in drawing. The
bidder will however submit the drawing along with his bid.
(j) Grouting Materials
In general, a grout is a homogenous colloidal mixture of cement and water. Where necessary,
Bentonite shall be mixed proportionately as to be readily pumpable. Admixtures like sodium
silicate ( Na2SO3) may also be added subject to the approval of the Site Engineer.
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-19
WAPCOS Ltd. Bidder
4.5 Execution
4.5.1 Contractor’s Equipment and Construction Material
The contractor shall submit an itemized list of equipment and materials to the Project
Executor for approval in advance. The Contractor shall ensure the availability and provide
minimum 3 sets of construction equipments one set for each LOT of Hand Pumps as
detailed in Table 4.2 but not limited to the following:
Table 4.2
Item Description Quantity Specification
1 Drilling rigs 3 No. Truck mounted drilling rig capable of
drilling 203.2 mm diameter borehole
down to a depth of 100 m
2 Drilling tools 3 Sets Drilling bit, rods, accessories, etc.
3 Compressor 3 No. Discharge air capacity 165 CFM.
4 Pick-up truck for transport 3 No. 2 tonne
5 Water Tank Truck 3 No. 2000 liter minimum
6 Pumping Test
Equipment’s
3 Sets Submersible/Centrifugal Pump with a
capacity of pumping volume 6 cu-m per
hour
7 Miscellaneous 3 Sets Portable water level indicator, GPS,
Daily well drilling log sheet for each
well, etc.
The drilling rigs shall be in good condition and of such capacity as to drill to a depth of 100
meter. No worn or obsolete equipment shall be used and in no case shall the maker’s rating of
capacity for any equipment be exceeded. The Contractor shall provide a detail description of
the drilling method and type and age of the equipment for approval by the Project Executor
before the equipment is brought to the site.
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-20
WAPCOS Ltd. Bidder
The Contractor shall provide appropriate tools, accessories, power, fuel, materials, supplies,
lighting, water, and other equipment’s; and experienced personnel necessary to conduct safe
and efficient drilling operations, on-site testing, and to restore the site as required. The Project
Executor or his representative will inspect all equipment’s before the start of the drilling
operations. If, in the opinion of the Project Executor the personnel and equipment are not
capable of satisfactorily performing the work specified, the Contractor shall immediately
substitute proper personnel and equipment’s.
Only fresh water shall be used in drilling fluids, whether employed alone or in combination
with drilling additives.
4.5.2 Drilling Bore Holes
(1) Borehole Details:
(i) Diameter of Borehole: 203.2mm (8″) for drilling in loose sedimentary formation
and 7″5/8 for drilling in rock formation.
(ii) Length of Borehole: Dependent upon site conditions, but not exceeding 100 m
(iii) Thickness of Overburden: 2m to 4m or more, depending upon site conditions
(2) Drilling Equipment
Drilling equipment shall be Rotary / DTH / Combination rigs and shall have capacity to drill
bore holes of 203.2 mm (8″) / 7″5/8 dia upto a depth of about 100 m. All equipment, plant,
and tools for carrying out drilling operations shall be in good working conditions.
4.5.3 Drilling Operation
Drilling of boreholes shall be carried out dry in 2-3m stages or less, depending upon thickness
of the overburden. After drilling through the overburden, all required observations /collection
of borehole data and samples/ testing, etc shall be conform as per specifications. MS casings
shall then be inserted upto the depth of loose formation/ overburden before proceeding for the
next stage of drilling. Diameter of the borehole in overburden shall preferably be slightly
more than 203.2mm so as to permit insertion of steel casings having internal dia of 203.2mm.
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-21
WAPCOS Ltd. Bidder
For drilling in bed rock, diamond core drilling shall be carried out in 3m stages. Core/ drilling
cuts shall be properly preserved for inspection. Drilling shall be extended upto 3m below the
bottom of the identified aquifer so as to insert blank pipe below the aquifer. However, drilling
operation in the location shall be discontinued if contamination of Arsenic is confirmed by
field testing kit during the Preliminary Yield Test (PYT).
The following sequential operations shall be carried out during and after drilling of boreholes:
i. Drilling and Collection of drill cuttings samples for every meter of drilling
ii. Checking of Alignment and Verticality of Borehole
iii. Identification of Aquifer/ Granular Zone
iv. Fabrication of Bore Well Assembly as per instruction of Site Engineer/ Geologist and
lowering of the same in the bore well and gravel shrouding, providing bentonite and
cement seal and other requirement as per GTS.
v. Development of Tube Well by air compressor initially followed by centrifugal/
submersible pump
vi. Pumping Test (APT) at constant discharge and/or Step Drawdown Test (SDT)
wherever necessary/ possible. SDT is optional and may require to be conducted
sparingly in exceptional circumstances.
vii. Collection and Testing of Tube well Water samples
viii. Disinfection through Chlorination
ix. Well Completion
4.5.4 Collection / Testing of underground soil / water of the Bore hole
During drilling operation, samples of drill cuttings and groundwater shall be collected and
tested in-situ and/or in the laboratory, as directed by the Site Engineer. The water samples
shall be collected in non-reactive translucent double corck polythene bottles of 1 liter
capacity.
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-22
WAPCOS Ltd. Bidder
4.5.5 Alignment Checking
Well should be vertical and straight. The alignment and verticality of well shall be checked by
plummet which shall be suspended with a thin wire from tripod with winch. The verticality
test shall be carried out in presence of site Engineer. To ensure verticality of tube well, the
guides may be used with assembly pipe at the time of lowering of well assembly.
4.5.6 Ascertaining the Quality of Aquifer Water
Preliminary Yield Test (PYT) shall be conducted in naked borehole where packers test is not
possible due to operational or other reasons. The PYT shall be limited to 10 minutes or less
depending upon the ejection of ground water from the zone of aquifer after the compressor
has been run for some time.
Alternately, Drill stem test shall be carried out at the selected bore wells limited to a period of
10 minutes or less. Drill stem test (packers test) is optional and may be required in Tboung
Khmum and Krouch Chhmar Districts only where Arsenic contamination of shallow ground
water has been reported.
4.5.7 Lowering of PVC Well Assembly
Where it has been established after DST/ PYT that there is no Arsenic hazard, then only
lowering of well assembly would be taken up. However if contamination of Arsenic is
confirmed, the bore hole shall be abandoned.
The site Hydrogeologist/ Engineer shall recommend fabrication of bore well assembly based
on study of drill cuttings. Bore well assembly shall have 3.0 m blank PVC pipe at the base of
the assembly to serve as Bail Plug at the bottom. Whereas slotted section is so fixed in the
well assembly that it rests against the granular zone. Every joint shall be firmly secured.
4.5.8 Filling of Annular spaces between Tube Well and Borehole
(a) Gravel Packing
After lowering of the PVC blank pipe (3m below the bottom of the identified aquifer) and the
PVC Screens thereupon, the annular space between well assembly and the bore hole surface
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-23
WAPCOS Ltd. Bidder
from bottom of the bore well shall be properly shrouded with approved quality pea-gravel of
2-6 mm size assorted, satisfying the filter criteria. The gravel packing shall be done in such a
manner that it wholly shrouds the slotted section of the well assembly and the level of the
gravel pack rests 6-8 m above the top of the slotted section. Shrouding of pea gravels shall be
carried out by adopting Reverse Fluid Circulation Method ensuring that no bridging takes
place. In case of thick mud available in borehole, it should be thinned by flowing fresh water
after lowering well assembly and before gravel shrouding. Filling and subsequent packing
shall be carried out in stages of one meter or so. It should be ensured that the Gravel pack
consists of well rounded, washed particles comprising at least 90% silicious material and
should not contain any clay, shale, silt and other fine material or crushed material.
(b) Bentonite Packing
The annular space between the casing pipe and the borehole from top of the gravel packing of
the screen pipe shall be shrouded with 2.0 metre thick bentonite seal by using approved
quality of bentonite pellets and well compacted with the purpose to protect infiltration of
water from the upper layer of overburden or otherwise. Pouring of bentonite pellets shall be
followed with water in stages of one meter or so to ensure proper setting and occupy the
spaces uniformly.
(c) Earth Filling
The annular space between the casing pipe and the borehole from top of the bentonite seal
extending upto 3.0 metre below ground level shall be backfilled with the excavated soil and
well compacted in stages as described above.
(d) Cement Seal
Three (3) meters of annular space from the top of the ground level shall be sealed with cement
slurry of 1.85 – 2.15 kg cement / litre grout to prevent dirty surface water and contaminants
from entering the bore hole and also to hold the well assembly tightly in place. The grout shall
be injected into the annulus in a single operation so that a complete and continuous seal is
achieved. However top 0.4 metre of annulus shall be left ungrouted (but temporarily
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-24
WAPCOS Ltd. Bidder
backfilled with inert drill cuttings), to facilitate installation of Hand pump pedestal which will
also be sealed subsequently.
4.5.9 Development of Tube Well
The Tube wells shall be developed by air lift through air compressor and over pumping unit to
ensure sand free discharge/ optimal yield as follows :
a) Development by Air Compressor (Air Lift and/or Surging)
During, development by air compressor, the operation shall be carried out as under:
1) Development by compressor with variable discharge shall be carried out using
compressor of suitable capacity 100 PSI/165 CFM or more air pressure as per site
requirement to achieve development upto the bottom of the tube well.
2) Suitable dia Eductor pipe shall be used as discharge pipe and 25 mm diameter air line
should be used for air supply/ observation and recording of water levels during
different stages of development if deem necessary.
3) The development shall be carried out from the top of aquifer to the bottom of the
aquifer and vice versa.
4) The development with Air compressor should be carried out for till the water becomes
mud/sand free and gravel is fully set in the annular space. Development should be
carried out atleast for 24 running hours.
b) Development by pumping Unit
Suitable low capacity submersible pump/centrifugal pump having a discharge range of 0.5 to
6 m3/hr and lift upto 40 m shall be lowered for development of bore wells to ensure sand free
discharge. Alternatively turbine pump of suitable capacity can also be used for development
by pumping unit.
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-25
WAPCOS Ltd. Bidder
c) Treatment of newly constructed tube well (Optional)
Where the water of the newly constructed structure is not getting clear /sand free, the tube
well shall be treated as follows:
1. Treatments by Hexametaphosphate for removal of Bentonite cake/scales if any[ in Kampong Cham Province].
Duration: 24 hrs.
2. Treatment by commercial hydrochloric acid in Limestone terrain to open up solution cavities/caverns [in Banteay Meanchey Province].
Duration: 24 hrs.
Note: Chemical treatment of the tube wells shall be resorted to only in cases where prolonged
development procedure (compressor and pump separately) fail to obtain clear sand free water.
Thus the chemical treatment of the tube well is optional which may or may not be required
at all.
d) After the completion of mechanical (or even chemical) development of the tube well, the
contractor shall accurately sound the well to determine the level of accumulated sediments
within the tubage assembly. The contractor shall record the level of accumulated sediments in
the driller’s daily log. The contractor shall ensure removal of such accumulated sediments
through air lift.
4.5.10 Pumping Test
Actual pumping test shall be preceded by short duration Preliminary Yield Test (PYT) for a
period not exceeding 2 hours during which water level data, before and after pumping and
recovery period shall be recorded. After development of a tube well, an Aquifer Performance
Test (A.P.T.) of 6 - 8 hours duration shall be carried out at constant discharge for evaluation
of aquifer yield characteristics, well efficiency and aquifer parameters. To carry out such tests,
the following equipment shall be required:
i) A suitable pump and prime mover (where electric power is not available at the well site).
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-26
WAPCOS Ltd. Bidder
ii) Measuring devices for time, discharge, water level recorder (engraved steel tape) and/or
acoustic water level recorder, Electric water level recorder, flow pipe of suitable dia and size.
iii) 25 mm dia airline needed to be lowered in the test well as well as observation well up to
required depth for measurement of water levels during the test.
iv) Discharged water from the bore well shall be removed through pipe system (without involving
spillage of water at the bore well site) to at least 200m away from the site.
Pumping test shall be conducted on the bore well to be fitted with Hand pump at constant
discharge varying between 0.5 to 6 lps. The duration of pumping test shall be 6-8 hrs. During
the pumping test, monitoring of water levels at the time of Pumping as also the recovery
period shall be recorded with their frequency as given in Table-4.3.
Table-4.3: Frequency of Pumping and Recovery for Pumping Test
S.No. Pumping Period Recovery Period
Minutes Frequency Minutes Frequency
1. 1-10 Every Minute 1-10 Every Minute 2. 10-30 Every 2 Minute 10-30 Every 2 Minute 3. 30-60 Every 5 minute 30-60 Every 5 minute 4. 60-120 Every 10 Minute 60-120 Every 10 Minute 5. 120-240 Every 20 Minute 120-240 Every 20 Minute 6. 240-360 Every 30 Minute 240-360 Every 30 Minute 7. 360-480 Every 60 Minute 360-480 Every 60 Minute
Depending upon the behavior of the bore well as reflected by the water level (WL) data the
pumping test may have to be continued upto maximum of 8 hours. In case where the
drawdown gets stabilized and the WL data does not show decline during pumping, the test
may be completed earlier than intended 6-8 hours. All such measurements shall be undertaken
using embossed steel tape and/ or Electric Sounder/ Acoustic sounder.
4.5.11 Collection of Water Samples/ Testing of Tube Well Water
Two samples of the ground water shall be collected in 1 litre capacity translucent non-
reactive double cork polythene bottle of good quality. The first sample shall be collected
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-27
WAPCOS Ltd. Bidder
any time during the initial 20-40 minutes of pumping and the second sample just before the
termination of pumping. At the time of collection of water samples, the Contractor shall
record the temperature, pH and Electric Conductivity (EC) of the ground water sample and
precisely label the container. The two ground water samples thus collected shall be analysed
in the field itself through the field testing kit for the parameters as given in Table 4.3:
Table 4.3 Parameters to be tested at site for each Hand Pump
Sr. No. Parameter Desirable Limit
1. pH 6.5 – 8.5
2. Total Dissolved Solids (TDS) 500-800 mg/l
3. Total Hardness (CaCO3) 300-600 mg/l
4. Turbidity 5-10 NTU
5. Chloride (Cl) 250-1000 mg/l
6. Fluoride (F) 1.0-1.5 mg/l
7. Nitrate (NO3) 45-50 mg/l
8. Iron (Fe) 0.3-1.0 mg/l
9. Arsenic (As) 0.01-0.05 mg/l
10. Fecal Coliform Totally Absent
Each Bore Well is required to be tested for presence of Fecal Coliform. Where it indicates
positive presence, the well would need to be adequately bleach chlorinated to make it totally
disinfected.
At least one representative ground water sample shall also be collected from cluster of Hand
Pumps constructed in the village for determination of concentration of various parameters as
cited below at Table 4.4 in the chemical laboratory for establishing chemical characteristics
of the ground water. The number of such samples shall not exceed 380.
Table 4.4 Parameters to be tested in Laboratory
Sr. No. Parameter Desirable Limit
1. pH 6.5 – 8.5
2. Total Dissolved Solids (TDS) 500-800 mg/l
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-28
WAPCOS Ltd. Bidder
3. Total Hardness (CaCO3) 300-600 mg/l
4. Turbidity 5-10 NTU
5. Chloride (Cl) 250-1000 mg/l
6. Sulphate (SO4) 200-400 mg/l
7. Fluoride (F) 1.0-1.5 mg/l
8. Nitrate (NO3) 45-50 mg/l
9. Calcium (Ca) 75-200 mg/l
10. Magnesium (Mg) 30-100 mg/l
11. Manganese (Mn) 0.1-0.3 mg/l
12. Iron (Fe) 0.3-1.0 mg/l
13. Arsenic (As) 0.01-0.05 mg/l
14. Total Coliform < 10 per 100 ml
15. Fecal Coliform Totally Absent
However, ground water samples collected from Tboung Khmum and Krouch Chhmar need
special attention regarding contamination of Arsenic. Selected samples from suspected
Arsenic infested area will have to be analysed for concentration of Arsenic in the ground
water. The total number of such samples shall not exceed 20.
4.5.12.1 Disinfection of Bore Well through Chlorination
Every well is required to receive a chlorine bleach treatment. The treatment shall be by
pouring one 1.5 litre bottle of chlorine bleach (6% solution) per well. The chlorination
treatment shall be done prior to installation of Hand Pump and kept for 24 hours for proper
disinfection of well. The Contractor shall then pump out this water until the residual
chlorine is less than 0.1 mg/l.
4.5.12.2 Completion of Installation of Hand Pumps & Platform
After satisfactory commissioning of the Hand Pumps, 4 holes of 50 mm dia shall be drilled
radially upto a depth of 3m from GL, within an area of 1.5 m radius from the base of the
hand Pumps. A mixture of cement, sand, bentonite and / or sodium silicate solution,
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-29
WAPCOS Ltd. Bidder
depending upon soil grains, shall then be poured through these holes with appropriate
pressure such that no upheaval occurs. After grouting, a RCC platform (M-15) with nominal
reinforcement and 125mm thickness shall be laid over the ground surface duly consolidated
and leveled, covering an area of 1.5m radius from the base of the Hand Pumps as per the
drawing in Section 5 of GTS. The platform shall be provided with a drainage outlet as per
the drawing over the consolidated ground formation with an uniform slope to facilitate
proper drainage of water. The inlet and outlet of the drain shall be smoothly finished. The
surface of the platform shall also be plastered with 20mm thick cement plaster
(1cement:4sand, finished with neat cement coating.
For all successful well the Contractor shall engrave on the Platform, well number, well
depth, SWL, DWL & date of installation.
The drawing attached with the bidding document is for reference only. The bidder shall
however provide the design and drawing of the Platform and drainage outlet and
specifications along with the bid.
5.0 Definition of Successful Well
Bore well is considered successful when 25 liters of water of an acceptable water quality are
produced per minute and the dynamic water level does not exceed 40 meters depth from the
ground surface in case of over 50 meters drilled borehole.
With regard to water quality, only the wells with quality not exceeding the following
parameters and value shall be considered successful as indicated in Table 4.5:
Table 4.5 Parameters of successful Hand Pump
Sr. No. Parameter Desirable Limit
1. Ph 6.5 – 8.5
2. Total Dissolved Solids (TDS) 500-800 mg/l
3. Total Hardness (CaCO3) 300-600 mg/l
4. Turbidity 5-10 NTU
5. Chloride (Cl) 250-1000 mg/l
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-30
WAPCOS Ltd. Bidder
6. Fluoride (F) 1.0-1.5 mg/l
7. Nitrate (NO3) 45-50 mg/l
8. Iron (Fe) 0.3-1.0 mg/l
9. Arsenic (As) 0.01-0.05 mg/l
10. Fecal Coliform Totally Absent
5.1 Unsuccessful Wells in Respect of Water Yield
When using the DTH hammering method, it is possible to judge whether the well is
successful or not during drilling. In rotary drilling success or failure can only be judged after
drilling is completed, such as installation of screen casings, gravel packing, well
development and pumping test. Therefore if well is determined to be unsuccessful in respect
of water volume (yield) the Contractor shall provide a written record of the actual quantities
of drilling, casing, screens and well development for the Project Executor and the payment
will be released accordingly for the item of works actually carried out.
5.2 Unsuccessful Wells in Respect of Water Quality
In case of unsuccessful wells in respect of water quality, success or failure can only be
judged through works after drilling is completed, such as installation of screen casings,
gravel filling, well development, pumping test and water quality analysis. Therefore if a well
is determined to be unsuccessful due to poor water quality, the Contractor shall provide a
written record of the actual quantities of drilling, casing, screens and well development for
the Project Executor for consideration of payments.
In case the presence of Fecal Coliform is observed in respect of any Hand Pump site, the
well would need to be adequately bleach chlorinated to make it totally disinfected and
successful.
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-31
WAPCOS Ltd. Bidder
5.3 Countermeasures for Unsuccessful Wells
It is dangerous to leave the drilled boreholes as they are, the holes shall be filled in the
drilled holes are to be filled up with clean sand and this shall be well compacted with water
for proper settling.
5.4 Alternative Drilling Sites
After a well is declared as unsuccessful the same shall be abandoned and an alternate site
will be taken up for drilling and installation of the Hand Pump after the approval from
Employer/ Project Executor or his authorized representative.
The payment for the unsuccessful well site so declared and abandoned will be paid as per the
provisions of the Contract.
6.0 Hand Pump Installation, Commissioning, Operation & Maintenance and Training on
Operation and Maintenance of Hand Pumps
6.1 The Contractor shall install and commission the Hand Pump according to the
Manufacturer’s instruction. After the installation, Hand Pumps shall be continuously
operated for 100 strokes to check for installation quality. Necessary performance and other
tests would be conducted as detailed in the GTS before handing over the completed Hand
Pump to the concerned authorities.
6.2 After successful installation and handing over of the Hand Pump to the Employer/ Project
Executor or his authorized representative, the Contractor will carry out the Operation and
Maintenance of each pump during the defects liability period for one year. During the
above period of one year, continuous availability of good drinking water through these
Hand Pumps will be the responsibility of the Bidder/ Contractor. In case, availability of
water through any of these 1500 hand Pumps during DLP is interrupted for any reason, the
Hand Pump will have to be re-commissioned at the other location as approved by the
Employer/ Project Executor at the Bidder/ Contractor’s risk cost and responsibility.
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-32
WAPCOS Ltd. Bidder
6.3 The representatives of Project Executor/ MoRD/ Village Community will also be
associated by the contractor right from the preparation of the site till the commissioning of
the hand pump for on work training. The Contractor shall provide extensive operational
training to the nominated community/ and Staff of MoRD after commissioning of the
Pumps in each area. The training shall be imparted by the Contractor for running, upkeep
and maintenance of various pump components at each location as approved by MoRD.
This Training has to be provided before handing over of the Hand Pump to the Employer/
Project Executor or their representative.
6.4 A set of essential tools and spares parts for one year shall also be provided free of cost to
the community members at each pump site for operation, maintenance and upkeep of Hand
Pumps along with the standard “User Manuals” for the installation, operation and
maintenance procedures produced by Manufacturer both in English and Khmer languages.
The list of the set of essential tools and spare parts which shall be supplied by the
Contractor at each location shall be provided along with the bid.
6.5 The Contractor shall install a plaque as per the drawing given in Section 5 at each location
of Hand Pump. The relevant matter to be printed on the plaque will be given to the
successful Bidder.
BiddingDocumentforSupplyandInstallationofHandPumpsforAugmentationofRuralWaterSupplyinCambodia
========================================================================================
SECTION-5
DRAWINGS
Bidding Document for Supply and Installation of Hand Pumps for Augmentation of Rural Water Supply in Cambodia
==================================================================================================
Vol-II-33
WAPCOS Ltd. Bidder
SECTION 5
DRAWINGS
5.1 Typical drawing for well structure as well as the drilling well with Afridev Hand
Pump.
5.2 Typical drawing for Platform with the drainage outlet.
5.3 AFRIDEV Hand Pumps (SKAT Revision 4) shall be installed at each identified
location. The bidder shall however provide the design and drawing of the Afridev
Hand Pump (SKAT Revision 4) with list of accessories, tools and spare parts along
with his bid.
5.4 Typical drawing of the Plaque to be installed at each location of Hand Pump. The
relevant matter to be printed on the plaque will be given to the successful Bidder
Note: The above drawings attached with the Bidding documents are for reference only. Based upon site visit and experience, the EPC Contractor shall prepare the Layout of the Project works as well as the Infra-structure development works with details and submit his Technical Bid along with all the relevant drawings and specifications along with the bid.
BiddingDocumentforSupplyandInstallationofHandPumpsforAugmentationofRuralWaterSupplyinCambodia
========================================================================================
SECTION-6
BROAD VILLAGE WISE LOCATION FOR
INSTALLATION OF HAND PUMPS
Sr. N
O.
DIS
TRIC
TC
OM
MU
NE
VILL
AGE
No.
of H
AND
PU
MP
REC
OM
MEN
DED
DR
ILLI
NG
DEP
TH (m
)R
EMAR
KS
1TH
MA
PE
CH
I2
40-5
02
THM
A P
EC
H II
I3
50.0
3K
OK
340
-50
4O
PIR
340
-50
5D
ON
G2
40-5
06
CH
HIE
S II
340
-50
7B
OE
NG
PR
UO
L LE
U6
50-6
08
TUO
L K
AM
PO
T TI
MU
OY
660
.09
TUO
L K
AM
PO
T TI
BE
I6
50-6
010
MA
SIN
SR
AU
V5
50-6
011
VIH
EA
R K
RA
OM
750
-60
12B
ATD
EI K
RA
OM
750
-60
13B
EU
NG
KA
MB
AO
450
-60
14TU
OL
DA
MB
AN
G4
50-6
015
SP
EA
N C
HH
EU
350
-60
16B
EU
NG
KO
R3
60.0
17B
EU
NG
PR
AH
350
-60
18C
HO
B M
UO
Y4
40-5
019
CH
OB
PIR
440
-50
20C
HO
B K
RA
O4
40-5
021
CH
RO
RK
CH
AM
BO
RK
440
-50
22S
LAB
KD
AO
NG
350
.023
AN
DA
UN
G L
VE
440
-50
24TU
OL
TRE
A T
BO
NG
440
-50
25TU
OL
TRE
A C
HH
EU
NG
440
-50
26TU
OL
SA
MB
O4
40-5
027
KA
ND
IEN
G2
40-5
028
TRA
PE
AN
G S
NA
O4
45.0
29C
HH
I PE
AN
G2
40-5
030
CH
HIN
KLA
340
-50
31TH
NO
NG
340
-50
32C
HH
RO
Y C
HA
NG
HA
R3
40-5
033
TRA
PE
AN
G K
RA
PE
U2
50.0
34P
AU
N2
40-5
035
RO
KA
R K
HN
UO
CH
CH
HE
UN
G2
40-5
036
STU
EN
G P
EN
H2
50.0
37K
HN
AC
H K
RA
SA
NG
240
-50
38S
AM
AK
I2
40-5
039
CH
HI K
O2
40-5
040
TUO
L K
AN
DA
L TB
ON
G2
50.0
KAM
PON
G C
HAM
PR
OVI
NC
ELI
ST O
F FA
VOU
RAB
LE V
ILLA
GES
FO
R D
RIL
LIN
G A
ND
INST
ALLA
TIO
N O
F H
AND
PU
MPS
CH
OB
THM
A P
EC
H
BO
EN
G P
RU
OL
TBO
UN
G K
HM
UM
CH
IKO
R
MO
UN
G R
IEV
Sr. N
O.
DIS
TRIC
TC
OM
MU
NE
VILL
AGE
No.
of H
AND
PU
MP
REC
OM
MEN
DED
D
RIL
LIN
G D
EPTH
(m)
REM
ARK
S
41C
HEU
TEAL
CH
HR
UM
245
.042
TRAP
EAN
G C
HR
OR
K2
40-5
043
KRAO
Y VA
T2
40-5
044
TA K
EB2
40-5
045
PAO
N3
40-5
046
POU
RO
UN
G3
50.0
47N
EI P
HSA
R3
40-5
048
TA T
RAV
340
-50
49D
AMN
AK C
HAR
240
-50
50PR
EK K
AMPE
NG
240
-50
51EI
SA M
EAN
CH
EY2
40-5
052
CH
HIE
CH
HO
UN
GR
OK
240
-50
53D
OU
NG
PR
EAH
245
.054
RO
UN
G3
40-5
055
TRAC
H2
40-5
056
ANC
HAE
UM
240
-50
57N
EAM
EUN
KH
EUN
G3
40-5
058
CH
AN T
OU
NG
440
-50
59TR
APEA
NG
TH
OM
440
-50
60BR
A YA
B2
40-5
061
SAN
GKO
M T
HM
EI4
40-5
062
ANG
KOR
CH
EA3
40-5
063
SRA
LOR
B3
40-5
064
DAN
G K
AMBE
T3
40-5
065
KHLA
ON
G4
50.0
66TR
APEA
NG
DO
M4
40-5
067
KHN
AR5
40-5
068
ANG
KOR
CH
EY8
45.0
69VE
AL K
HN
ACH
440
-50
70TR
A BO
KS3
40-5
071
NIK
OM
LEU
340
-50
72N
IKO
M K
RAO
M5
40-5
073
TRAP
EAN
G S
ANG
KE4
40-5
074
BRA
THEA
T2
40-5
075
TRAP
EAN
G K
OU
440
-50
76KI
EN R
OM
IET
740
.077
AND
AUN
G P
OK
440
-50
SRAL
AB
ANH
CH
AEU
M
TBO
UN
G K
HM
UM
Sr. N
O.
DIS
TRIC
TC
OM
MU
NE
VILL
AGE
No.
of H
AND
PU
MP
REC
OM
MEN
DED
DR
ILLI
NG
DEP
TH (m
)R
EMAR
KS
78LN
GIE
NG
350
.079
KO K
I5
40-5
080
CH
RAB
340
-50
81SM
AOG
N7
40-5
082
LVEA
TH
UM
250
.083
PHU
M B
UO
N D
ABBR
AMM
UO
Y3
40-5
084
THLO
K PO
NG
RO
440
-50
85PH
UM
PI D
ABR
AMPI
350
.086
KIEN
CH
OR
K4
40-5
087
LVEA
TO
CH
240
-50
88TE
P N
IMIT
H3
40-5
089
KBAL
BEU
NG
SES
S KE
UT
440
-50
90SA
MBU
OR
340
-50
91D
AMN
AK P
OPE
L2
40-5
092
KOR
240
-50
93VE
AL T
EUK
CH
EGN
240
-50
94TR
APEA
NG
BEI
340
-50
95SE
SS5
40-5
096
VEAL
KH
MU
M2
40-5
097
KBAL
O7
40-5
098
THN
ON
G10
40-5
099
TUO
L TH
MEI
540
-50
100
KAN
DAL
640
-50
101
SOKH
SAN
350
.010
2PH
UM
BR
AMM
UO
Y D
ABBR
AMM
UO
Y3
40-5
010
3PH
UM
BR
ABEI
DAB
BRAM
640
-50
104
TUO
L VI
HEA
R M
EAN
CH
EY4
40-5
010
5TU
MN
OB
TUEK
SEN
CH
EY11
50.0
106
KBAL
BEU
NG
SES
S6
40-5
010
7C
HO
NG
O3
40-5
010
8VE
AL V
ON
G5
40-5
010
9R
OKA
PO
PR
AM T
I MU
OY
1060
.011
0VI
HEA
R S
AMBO
UR
540
.011
1PH
UM
BR
ABEI
DAB
MU
OY
340
-50
112
PHU
M D
AB D
ABM
UO
Y3
40-5
011
3PH
NO
M L
OK
340
-50
114
SAM
RO
M3
40-5
011
5C
HH
EAM
MLO
U3
40-5
011
6TR
APEA
N P
RO
LET
340
-50
117
PRAH
AN
G5
40-5
011
8KO
L3
40-5
011
9C
HAN
NIM
ITH
440
-50
120
PRA
PHAT
940
-50
121
CH
HU
K SA
ND
AL5
40-5
012
2R
OKA
PO
PR
AM T
I PIR
540
-50
123
TRAP
EAN
G K
HLA
340
-50
124
PON
G T
UEK
745
.012
5TA
PAV
BPM
PEN
HTE
SS8
40-5
012
6TR
APEA
NG
RU
SSEI
1050
.0
LNG
IEN
GTB
OU
NG
KH
MU
M
TBO
UN
G K
HM
UM
KOR
RO
KA P
O P
RAM
Sr. N
O.
DIS
TRIC
TC
OM
MU
NE
VILL
AGE
No.
of H
AND
PU
MP
REC
OM
MEN
DED
DR
ILLI
NG
DEP
TH (m
)R
EMAR
KS
127
CH
RAV
EAK
DEK
650
.012
8C
HAM
KAR
DAU
NG
540
-50
129
KRAB
EI K
RIE
K3
40-5
013
0C
HH
UK
1040
-50
131
BAR
AY5
40-5
013
2SR
AH7
50.0
133
TUO
L SN
UO
L5
40-5
013
4SA
NG
KOM
MEA
NC
HEY
540
-50
135
TUO
L TA
KAO
340
-50
136
TUO
L R
OKA
R2
40-5
013
7BE
I MAE
TR5
50.0
138
CH
AMR
AEU
N5
45.0
139
TRAP
EAN
G R
EAN
G14
50.0
140
MO
UK
KRAS
540
-50
141
THN
GO
SAL
A4
40-5
014
2TH
NG
O K
EUT
440
-50
143
CH
HI P
ESS
440
-50
144
SAN
GKO
M M
EAN
CH
EY T
HM
EI5
50.0
145
CH
HEA
M M
A AO
540
-50
146
SAM
NO
RN
G K
RAP
EU4
40-5
014
7M
EMO
T KA
ND
AL5
40-5
014
8TB
ON
G V
AT5
40-5
014
9TR
A BE
K6
40-5
015
0M
EMO
T PH
SAR
540
-50
151
SAN
GKO
M M
EAN
CH
EY C
HAS
640
-50
152
MEM
OT
CH
AS8
40-5
015
3N
GIE
V2
60.0
154
LEAC
H K
RAO
M5
50.0
155
BEU
NG
CH
HR
AUN
G3
45-5
515
6LE
ACH
LEU
345
-55
157
CH
HEA
M A
MPI
L2
45-5
515
8C
HH
EAM
245
-55
159
CH
HEU
NG
245
-55
160
MO
NG
235
-45
161
PO P
HLE
ANG
340
-50
162
ANG
KAM
250
-60
163
SRAE
TA
NAU
NG
LEC
H3
40.0
164
SRAE
TA
NAU
NG
KEU
T2
50-6
016
5TH
LOK
350
-60
166
SAAM
350
-60
167
CH
AN M
OU
L4
50-6
016
8PE
AM2
60.0
169
KO3
50-6
017
0TA
LO
U2
60.0
171
KAN
TREU
Y2
50-6
017
2TA
KEO
255
-65
173
KHLO
NG
TBO
NG
250
-60
CH
HU
K
TUO
L SN
UO
L
MEM
OT
MEM
OT
CH
OAM
CH
AN M
UL
KR
OU
CH
C
HH
MAR
Sr. N
O.
DIS
TRIC
TC
OM
MU
NE
VILL
AGE
PRO
POSE
D H
AND
PU
MP
REC
OM
MEN
DED
DR
ILLI
NG
DEP
TH (m
)R
EMAR
KS
174
KO K
I CH
HEU
NG
850
-60
175
KO K
I TBO
NG
650
-60
176
TUO
L TH
MEI
450
-60
177
SRAE
PO
L4
50-6
017
8KN
GAO
K4
50-6
017
9C
HAM
KAR
TH
MEI
850
.018
0PR
EK P
UO
Y6
50-6
018
1SA
LO
RN
G B
EI4
50-6
018
2R
OU
NG
250
-60
183
TRAP
EAN
G R
USS
EI4
50-6
018
4BE
NG
250
-60
185
CH
HEA
M T
OU
K4
50-6
018
6TA
OG
N3
50-6
018
7AN
DAU
NG
TA
DO
UK
350
-60
188
MAS
IN2
50-6
018
9BO
SS4
50-6
019
0D
AUN
G2
50-6
019
1SO
TEI
550
-60
192
DO
UN
RAT
H T
I MU
OY
450
-60
193
CH
AM B
OR
K5
50-6
019
4D
OU
N R
ATH
TI P
IR4
70.0
195
LOU
R10
60.0
196
KAM
PEA
NN
750
-60
197
TUEK
TU
M5
60.0
198
SRAE
SAO
M T
HM
EI7
50-6
019
9TU
OL
TUM
POU
NG
750
-60
200
SRAE
SAO
M C
HAS
650
-60
201
SRAE
KAN
DAL
850
-60
202
CH
HLO
UN
G M
UO
Y6
60.0
203
CH
HLO
NG
TI P
I4
50-6
020
4C
HH
LON
G T
I BEI
350
-60
205
THG
NO
KAN
DAL
540
-50
206
DAR
LEC
H7
40-5
020
7BR
AM P
I MAK
ARA
440
-50
208
SPEA
N11
40.0
209
DAR
PH
SAR
540
-50
210
SRAE
CH
HEA
M4
40-5
021
1D
AR K
AND
AL12
45-5
521
2D
AR K
AND
AOL
745
-55
213
MEA
K PU
K6
40-5
021
4D
AR T
BON
G6
40-5
021
5TR
IEK
540
-50
216
THN
GO
CH
HEU
NG
840
-50
217
SAM
RO
NG
CH
HEU
NG
640
-50
218
DAR
CH
HEU
NG
635
-45
219
BEN
G5
50-6
022
0C
HAM
KAR
KO
650
-60
221
SALO
RN
G I
850
-60
222
SALO
RN
G II
1550
-60
223
KOR
NG
KEN
G3
40-5
0
KOKI
R
RU
NG
KAM
POAN
DAR
MEM
OT
Sr. N
O.
DIS
TRIC
TC
OM
MU
NE
VILL
AG
EN
o. o
f HA
ND
PU
MP
REC
OM
MEN
DED
DR
ILLI
NG
DEP
TH (m
)R
EMA
RK
S22
4M
EM
ON
G5
50-6
022
5S
AN
GK
AE
CH
AS
460
.022
6P
EU
K2
40-5
022
7M
E K
CH
AO
RN
G2
50-6
022
8TR
IEK
350
-60
229
KA
M B
AS
340
-50
230
SA
NG
KE
TH
ME
I2
50-6
023
1C
HH
EA
CH
240
-50
232
DO
RK
PO
1040
-50
233
PR
AH
PO
NLE
A6
40-5
023
4R
OM
EA
S C
HO
L2
40-5
023
5K
HLE
Y3
35-4
523
6S
AM
RO
NG
345
-55
237
PR
EI
430
-40
238
TRA
MA
EN
G L
EU
350
-60
239
O K
HLO
T2
45-5
524
0TR
AM
UN
G7
50-6
024
1C
HE
AM
TR
IEK
550
-60
242
AN
DO
NN
TH
MO
R L
EU
250
-60
243
AN
DO
NN
TH
MO
R K
RA
OM
350
-60
244
RO
NG
CH
AK
SK
OR
360
.024
5TR
A M
AE
NG
KR
AO
M2
45-5
524
6D
AU
NG
TI M
UO
Y2
50-6
024
7C
HE
AM
TR
AV
250
-60
248
CH
HO
UK
450
-60
249
NG
EU
TH
OM
545
-55
250
NG
EU
TH
ME
I3
40-5
025
1TR
A P
EA
NG
NG
EU
250
-60
252
CH
HR
EI
350
-60
253
KH
NO
RN
G K
RA
PE
U L
EC
H4
50-6
025
4K
HN
OR
NG
KR
AP
EU
KE
U4
50-6
025
5S
AM
BO
450
-60
256
KR
OC
H3
50-6
025
7D
AU
NG
II4
50-6
025
8C
HE
AM
TA
MA
O C
HH
EU
NG
545
-55
259
CH
HU
M N
UM
PO
L5
40-5
026
0TU
OL
KR
UO
S4
50-6
026
1TH
NA
L K
EN
G5
40-5
026
2A
NG
KA
M5
40-5
026
3S
AM
PA
O L
ON
N4
40-5
026
4K
AN
TU
OT
850
.026
5TH
MO
R T
OTE
UN
G T
BO
NG
340
-50
266
TAM
AO
KE
UT
540
-50
267
SR
AE
TA
PIC
H7
40-5
026
8K
OU
N K
RA
PE
U4
40.0
269
BO
SS
TA
EU
M5
40-5
027
0TO
TEU
NG
CH
HE
UN
G3
40-5
027
1LA
M K
AM
BA
O3
40-5
0
MEM
OT
ME
MO
NG
TRE
AK
TRA
MU
NG
CH
OA
M T
A M
AU
Sr. N
O.
DIS
TRIC
TC
OM
MU
NE
VILL
AGE
No.
of H
AND
PU
MP
REC
OM
MEN
DED
DR
ILLI
NG
DEP
TH (m
)R
EMAR
KS
272
KD
OL
KR
AO
M4
60.0
273
KD
OL
PH
SA
E8
40-5
027
4K
DO
L LE
U2
60.0
275
CH
AN
G K
OM
TI M
UO
Y5
45-5
527
6C
HA
NG
KO
M K
AN
DA
L6
45-5
527
7S
LA P
HN
OM
745
-55
278
KA
OH
TH
MA
940
-50
279
SP
EA
N C
HA
NG
KO
RM
845
-55
280
MK
AO
845
-55
281
BE
NG
KA
ON
G8
45-5
528
2P
ON
G T
UE
K8
60.0
283
LVE
A L
EU
755
-65
284
SLA
KIL
O7
45-5
528
5R
UM
CH
EK
940
-50
286
CH
HE
U K
HLE
UM
450
-60
287
THM
OR
DA
B3
40-5
028
8K
AM
PE
I3
50-6
028
9P
NO
V7
60.0
290
SR
AE
PO
NG
RO
445
.029
1K
HLI
EC
H2
40-5
029
2K
AN
TU
OT
150
-60
293
KR
A V
EA
N T
HO
M4
50-6
029
4K
RA
VE
AN
CH
HE
UN
G3
50-6
029
5D
AU
NG
440
-50
296
SA
TU
M3
40-5
029
7K
HM
UO
R1
40-5
029
8K
BA
L S
LEN
G3
40-5
029
9R
OB
AN
G C
HR
OH
440
-50
300
THM
A T
A D
AO
K1
40.0
EXP
LOR
ATO
RY
DR
ILLI
NG
301
CH
HR
EI L
EU
NG
240
-50
302
MR
AN
N2
40-5
030
3D
AN
GH
ET
140
-50
304
BA
NG
HE
UY
HU
OS
135
-45
305
PR
EI
245
-55
306
DE
I BLO
K1
40-5
030
7TH
MA
DA
250
-60
308
MK
HA
H2
35-4
530
9K
CH
EA
Y4
40-5
0
MEM
OT
TON
LUN
G
RU
MC
HE
K
CH
OA
M
KR
AV
EIN
Sr. N
O.
DIS
TRIC
TC
OM
MU
NE
VILL
AG
EN
o. o
f HA
ND
PU
MP
REC
OM
MEN
DED
D
RIL
LIN
G D
EPTH
(m)
REM
AR
KS
1TU
EK
TH
LA6
40-4
52
PH
NO
M B
AK
640
.03
KE
AB
635
-45
4O
U A
MB
IL4
35-4
55
SE
SE
N5
30-4
06
PR
O H
OU
T5
50.0
7K
AN
TUO
T7
50.0
8B
AN
G R
OS
750
.09
PR
EA
H P
ON
LEA
630
-40
10P
RE
AH
RU
SS
EI
630
-40
11K
AO
H P
ON
G S
ATR
530
-40
12A
NG
KE
A B
OS
550
.013
NA
KA
CH
HA
Y2
50.0
14S
O R
YA3
40-5
015
KO
B L
EC
H1
40-5
016
KO
N T
RE
I3
40-5
017
KO
UK
CH
OR
K2
30-4
0
18K
OU
K P
RIC
H2
30.0
19B
EU
NG
SE
LA2
30-4
020
PA
OY
VA
T2
30-4
021
TA C
HR
UE
NG
240
.022
TA P
HA
OK
230
-40
23C
HH
RE
Y2
30-4
024
TUM
NO
B D
AC
H2
65.0
25P
RE
Y C
HA
N3
60.0
26TH
NA
L B
AT
260
.027
YEA
NG
DA
NG
KO
M2
50-6
028
BA
NTE
AY
THM
EI
250
-60
29O
U B
EI C
HO
AN
250
-60
30C
HO
K C
HE
Y3
50-6
031
PR
OC
HE
A T
HA
M L
EC
H1
50-6
032
PR
OC
HE
A T
HA
M K
EU
T2
50-6
033
CH
AN
KIR
I1
50-6
034
TUO
L P
RA
SA
T1
50-6
035
TUM
NO
B K
OR
PR
AM
150
-60
36 K
ILO
LE
K B
UO
N2
50-6
037
PR
EY
KO
B3
50-6
038
TUO
L P
ON
GR
O2
50-6
039
OU
NE
AN
G2
65.0
PAO
Y PA
ET
BA
NTE
AY
MEA
NC
HEY
PR
OVI
NC
E
LIST
OF
FAVO
UR
AB
LE S
ITES
FO
R D
RIL
LIN
G A
ND
INST
ALL
ATI
ON
OF
HA
ND
PU
MPS
OU
CH
RO
V
OU
BE
I CH
OA
N
TUE
K T
HLA
SO
UP
HI
KO
UB
CH
AN
GH
A
SER
EI S
OPH
OAN
OU
AM
BE
L
PH
NIE
T
PR
EA
H P
ON
LEA
PA
OY
PA
ET
EXP
LOR
ATO
RY
DR
ILLI
NG
EXP
LOR
ATO
RY
DR
ILLI
NG
EXP
LOR
ATO
RY
DR
ILLI
NG
KA
OH
PO
NG
SA
TR
Sr. N
O.
DIS
TRIC
TC
OM
MU
NE
VILL
AGE
PRO
POSE
D
HAN
D P
UM
PR
ECO
MM
END
ED
DR
ILLI
NG
DEP
TH (m
)R
EMAR
KS
40TH
MO
R S
IN3
50-6
041
DO
NG
AR
AN
H2
60.0
42S
NA
G K
E1
30-3
543
PH
NO
UM
RO
UN
G1
30-3
544
CH
AM
BA
K1
30-3
545
CH
HR
EY
130
-35
46LV
EA
2
30-3
547
O A
MP
IL2
35-4
548
KA
OH
SN
UO
L2
40.0
49TU
OL
PO
NG
RO
235
-45
50S
AN
G T
EP
HE
AP
335
-45
51TR
O L
OU
K C
HE
UN
G2
40.0
52TR
A Y
EA
NG
140
.053
PH
NU
M L
IEB
KE
UT
240
.054
PH
NU
M L
IEB
LE
CH
140
.055
TA A
M2
30-4
056
THM
EI
230
-40
57TO
NLO
AB
230
-40
58TE
AN
KA
M T
BO
NG
240
-50
59TE
AN
KA
M L
EC
H2
40-5
060
CH
RO
AB
CH
AS
240
.061
CH
RO
AB
TH
ME
I2
35-4
562
KO
RK
235
-45
63S
ALA
CH
HE
S3
35-4
564
CH
AK
335
-45
65K
OU
K K
RA
OL
440
-50
66K
OU
K R
UM
CH
EK
440
-50
67K
OU
K T
AR
EA
CH
240
-50
68S
VA
Y S
AR
440
.0
69S
VA
Y K
HM
AU
340
.0
70TA
SO
K3
40.0
71SV
AY
CH
EKD
ISA
BLE
AN
D F
OR
ME
R M
ILIT
AR
Y D
EV
ELO
PM
EN
T C
EN
TER
1065
.0
EXP
LOR
ATO
RY
DR
ILLI
NG
CH
OB
VE
AR
I
RO
HA
L
PHN
UM
SR
OK
SR
AH
CH
IK
PO
NLE
YE
XPLO
RA
TOR
Y D
RIL
LIN
G
PAO
Y PA
ETN
IMIT
T
MA
LAI
BO
EN
G B
EN
G
TUO
L P
ON
GR
O
PREA
H N
ETR
PR
EAH
PH
NU
M L
IEB
PR
AS
AT
TEA
N K
AM
BiddingDocumentforSupplyandInstallationofHandPumpsforAugmentationofRuralWaterSupplyinCambodia
========================================================================================
ANNEXURES
BORE WELL SCHEDULE ANNEXURE I For Official use only Date Received: Entered by (name):
Date Entered: Signature
Standard Well Number: Other Number: 1. GENERAL INFORMATION Province: ……………………………………………………………….
Implementing Organization: …………………………………………...
District: ……………………………………….....................................
Supervisor: ………………………………………………………………
Commune: ……………………………………………………………..
Estimated Number of Beneficiaries: …………………………………...
Village: …………………………………………………………………
X-Coordinate of Well (UTM): ………………………………………….
Location Description: …………………………………………………
Y-Coordinate of Well (UTM): ………………………………………….
………………………………………………………………………….. Elevation by GPS (m above MSL): ………………………………….. Successful Well Dry Well 2. TECHNICAL DATA Type Drilled Well Purpose: Domestic Use DRILLING INFORMATION INFORMATION ON MATERIALS
Date Start: ……………………... End: ………………………………… Gravels (m3): …………………………………………………………….
Rig Type: ………………………………………………………………... Cement (Bags): …………………………………………………………..
Drilling Method: ………………………………………......................... Bentonite (Bags): ………………………………………………………..
Flushing Medium: ……………………………………………………… Sand: …………………………………………………………………….
Borehole Diameter (mm): …………………………………………….... Other (Specify): …………………………………………………………
Total Drilling Depth (m): ……………………………………………….
Inner Casing Diameter (mm): ………………………….......................
Total Length of Casing (m): …………………………………………....
Casing Material: ………………………………………………………...
ID Screen (mm): …………………. Slot Size (mm): ………………….
Screen Setting (m): From: ……………… To: ………………............. PUMP INFORMATION
Screen Material: ………………………………………………………... Pump Installed: Yes No
Static Water Level (m): ………………………………………………… Type of Pump: Hand Pump Motor Pump Other
Dynamic Water Level (m): …………………………………………….. Model: ………………………………………………………………….
Yield (m3/hour): ………………………………………………………... Date of Installation: ……………………………..…………………….
Well Development: Compressor …………………………..hr Turbine / Submersible ………………hr Chemical Treatment ……………….. hr
Depth Setting (m): …………………………………………………….
Method: ………………………………………………………………..... Yield (m3/hour): …………………………………………………………
Date Start: ………………… Total Duration (h): …………………….. Rising Main Material: ………………………………………………….
3. WATER QUALITY 6. LITHOLOGY AND WELL SPECIFICATION
Taste: Sweet Salty Bitter Tasteless Screen Casing Seals Depth (m) Log Lithology Description and
Remark Color: Clear Gray Yellow Brown
Odour: No Yes
10
pH: …………………………………………………………………..
Electrical Conductivity (μS): ……………………………………….
20
4. OTHER INFORMATION 5. SKETCH OF WELL LOCATION:
30 40 50 60
70
80 90 100
Log Legend:
Hard Rock Soft Rock Gravel Coarse Sand Fine Sand Clay
Static Water Level:
Province: ……………………………………………………………………………………
hour min hour min
(m) (l/min} (m3/h) (m)
0 0
1 1
2 2
3 3
4 4
5 5
6 6
7 7
8 8
9 9
10 10
12 12
14 14
16 16
18 18
22 22
24 24
26 26
28 28
30 30
35 35
40 40
45 45
50 50
1h 00 60 1h 00 60
70 70
80 80
90 90
100 100
110 110
2h 00 120 2h 00 120
140 140
160 160
3h 00 180 3h 00 180
200 200
220 220
4h 00 240 4h 00 240
270 270
5h 00 300 5h 00 300
330 330
6h 00 360 6h 00 360
7h 00 420 7h 00 420
8h 00 480 8h 00 480
Measure Discharge by 'V' notch (90)/ Orifice Plate & Discharge
Pipe/ Measured Container
Location: ……………………………………………………………………………………
Description: …………………………………………………………………………….. Name of Operator: ……………………………………………………………………………
Signature: ……………………………………………………………….
Date: ……………………………………………………………………….
Time: Time:
Elapsed time
Record Water Recovery Level
(Step Start)
Name of Technician: ……………………………………………….
(Step Start)
(Q) DischargeGround
Water Level
Elapsed time
2. Record Dynamic Water Level (Pumping Test) 3. Record Recovery Water Level (Recovery Test)
Village Code Number: ……………………………………………….Standard Well Number: ……………………………………………………………
District: ………………………………………………………………………………………
Commune: …………………………………………………………………………………
Village: ………………………………………………………………………………………
Implementing Company: …………………………………………………………………
Capacity of Pump: ………………… M3/h. Max Total head …………………
Pump Depth Installation: ……………………………………….m
Starting Date: …………………………………………………………………………………….
Finishing Date: …………………………………………………………………………………
1. General Information
PUMPING AND RECOVERY TEST RECORDING SHEET
PUMPING DATA SCHEDULE
ANNEXURE II
ANNEXURE III
WELL PUMP TRAINING & RECEIPT OF TOOLS AND SPARE PARTS RECORD
STANDRD WELL NUMBER:…………………………………. VILLAGE:…………………………………..
PROVINCE:…………………………………………. District:……………………………………………………… Commune:………………………………………….. Village:………………………………………………………..
CONTRACTOR:………………………………………………………………………………………………………………..
HEAD OF WSUG NAME:………………………………………………………………………………………………….
Member of WSUG (Trained Repairer):………………………………………………………………………….
Members of WSUG:……………………………………………………………………………………………………...
NAME OF TRAINEES:………………………………………………. and:……………………………………………..
SIGNATURE:…………………………………………………………… and:……………………………………………...
SIGNATURE:…………………………………………………………… and:……………………………………………...
DATE OF TRAINING:………………………………………………………………………………………………………
We acknowledge that we have receive the following…………………………………………………………………………………………………………………
Training on the operation and Maintenance of Afridev Hand Pump:…………………………………………………………………………………………………………………………
Tool kit:…………………………………………………………………………………………………………………………
Spare Parts for three years:……………………………………………………………………………………………
cc:
Trainees:…………………………………………………………………….
Contractor:…………………………………………………………………
Project Manager:………………………………………………………..
ANNEXURE IV
PUMPING TEST RECORDING SHEET
For office use only Date Received:………………………………………….. Date Entered:………………………………………. Entered by (Name):………………………………….. Signature:…………………………………………….
BOREHOLE WELL WITH HANPPUMP
Standard Well number: /MRD/ Village code Number: 1. GENERAL INFORMATION
Province:………………………………....... Implementing organization:…………………………… District:…………………………….............. Starting date:………………………………………..…………. Commune:………………………………… Finishing Date:……………………………………..…………. Village ::…………………………………….. Name of Operator:…………………………….…………….. Location Description:………………. Casing diameter (mm):……………………………………. .................…………………………………….. …………………………………………………..
2. PUMPING RESULT Static water level:……………………………. Dynamic Water level (mm):………………………… Pumping Rate (m3/h):……………………. Drawdown (m):…………………………………………….. Duration of pumping test (h):………… Well Depth (m):……………………………………………..
3. RECOMMENDATION FOR PUMP DEPTH INSTALLATION Type of Hand Pump Afridev Installation Depth (m):……………………………………………
Name of Technician: _______________________________ Date: ______________________________________
Signature: __________________________________________