2 U.S. Army Corps of Engineers Temporary Power Update

U.S. Army Corps of Engineers Temporary Power Update

Embed Size (px)

DESCRIPTION

U.S. Army Corps of Engineers Temporary Power Update. FEDERAL EVACUEE RE-ENTRY PLAN. Friday, September 05, 2008. AMERICAN RED CROSS 5 SEP 2008. GUSTAV Shelters open Population Florida 2 25 Alabama 37 8,743 - PowerPoint PPT Presentation

Citation preview

2

U.S. Army Corps of EngineersTemporary Power Update

3

FEDERAL EVACUEE RE-ENTRY PLAN

NUMBER DEPARTURE CITY MODE DESTINATION ETA

1000 FORT SMITH AIR NOLA MSY 9/6 – 9/8

1393/1486* LOUISVILLE AIR NOLA MSY 9/6 – 9/8

1843 LOUISVILLE AIR NOLA MSY 9/6 – 9/8

Total Air 4329

710 KNOXVILLE BUS NOLA UPT 9/5 PM

48 MEMPHIS BUS NOLA UPT 9/5 0700

193 MEMPHIS BUS NOLA UPT 9/6

Total Bus 951

832 MEMPHIS TRAIN NOLA UPT 9/5 0900

950 MEMPHIS TRAINNOLA UPT

9/6 0900

Total Train 1782

Total Return

7062*Requirement for an additional 93 mode TBD

Friday, September 05, 2008

4

GUSTAV Shelters open Population Florida 2 25 Alabama 37 8,743Texas 2 32Georgia 4 221Oklahoma 1 5Louisiana 28 5,542Arkansas 4 193Kentucky 1 1,432Tennessee 32 5,086Mississippi 23 1,419TOTAL 134 22,698

AMERICAN RED CROSS5 SEP 2008

FAY Shelters open Population Florida 1 425

HANNA Shelters open Population South Carolina 2 9

Total American Red Cross Managed and Partner shelters: 137Total Population of American Red Cross Managed and Partner shelters: 23,132The American Red Cross has the overall capacity to shelter 142,443 people.

5

Medical Sheltering

6

Medical Concerns

HHS:-Ambulance Contract-Monitor Public Health Concerns-Mental Health / Behavioral Health

EPA:-Assessment as Requested by the States-Local Debris Management Planning-Debris Clearance

7

CI/KRIP PRIORITIES AND CONCERNS: GUSTAV RECOVERY, ELECTRICAL POWER

• Electrical Power Restoration is the prime domino for IP recovery

• Damage assessments could take days, with up to weeks for full recovery

• Cascading impacts across multiple sectors

– Oil & Gas production, processing, and transportation

• Refineries shut down; unable to run processes, safeties, controls, comms

• Henry Hub gas terminal on generator power; nominal compression capability

• LOOP dependent upon restoration of pipeline systems before able to move product/crude through port

– Drinking & Waste Water processes

– Transportation: Signal and control devices out of service

– Communications, IT & SCADA systems

– Dams: unable to operate control systems

– Health and Human Services, incl hospitals and public safety operations

– Critical manufacturing and commercial operations

• PSAs facilitating coordination between private sector, jurisdictions, and response organization to streamline access to area for assessment and restoration, provision of critical support and resources, and prioritize focus of effort

8

Recovery– DR 1786: 34 Parishes declared for IA and PA– Governor’s Request for Declaration for FL and MS– Total registrations: 139,775

• Approx. 1,300 employees will be available to take roughly 28,100 registrations today

• Registration assistants have started to deploy to the shelters to take registrations

– Transitional Shelter Codes Authorized: 42,569 – Total Inspections Issued/Returned: 64,629/759– Housing Mission Planning Teams deployed to Region IV and VI– PA Preliminary Damage Assessments (PDAs) began conducting PDAs in MS and AL

9/4– Loading list of HUD multifamily rental property vacancies into FEMA Housing Portal – Updated Regions and States on eligibility guidance for Hotel/Motel program – Coordinating with Regions IV and VI and Louisiana JFO on sheltering and feeding

requirements for de-evacuation – Working with Public Affairs and Field to message process for shelter registration

and available assistance