U.S. Army Corps of Engineers Omaha District October 2011

US Army Corps of Engineers BUILDING STRONG®

BUILDING STRONG® 2

MILCON FY12($463 M) 18 Active Installations 3 Readiness Centers

> 400 Projects

Military boundary Civil Works boundary

• 700,000 square miles • Nearly 60 locations • 27 Dams (including 6 hydropower main stems) • 247 miles River Navigation • 284 Recreation Areas • 99 miles Missouri National Recreation River • 6,627 miles of Shoreline • 4,910 Regulatory Permit Applications • 53 Federally-recognized Tribal Nations • Protected Cultural Sites • > 1,200 projects

• Protective Design MCX • Transportation MCX • USACE Rapid Response

• Interior Design CX • Hydrant Fuels CX • MMRP Design Center • Religious Facilities Center of Standardization (CoS) • Access Control Points CoS • Regulatory Program in 6 states • Real Estate Services in 10 states

ER FY12 ($179 M) > 550 Projects

Special Projects FY12($282 M)

CIVIL WORKS FY12 ($227 M) Flood Protection, Navigation, Hydropower,

Recreation, Regulatory, Ecosystem Restoration, Flood Control and Coastal

Emergencies (FCCE)

BUILDING STRONG® 3

Omaha District Missions MILITARY BRANCH

• Design & Construction Management • 10 Active Air Force Installations • 2 Air Force Reserve Installations • 1 Army Installation & 1 Reserve • 3 Army Ammunition Plants • 2 Major Reserve Commands

ENVIRONMENTAL BRANCH • Environmental Remediation Work • EPA, FUDS, MMRP • More than 550 Projects Nationwide

SPECIAL PROJECTS BRANCH • DLA Fuels Program & SRM

CONUS/OCONUS • MILCON SRM • Rapid Response Nationwide

CIVIL WORKS BRANCH • Flood Protection, Navigation, Hydropower,

Water Supply, Water Quality, Recreation, Irrigation, Fish & Wildlife, Regulatory, Ecosystem Restoration, Flood Control and Coastal Emergencies (FCCE)

BUILDING STRONG®

COLORADO

WISCONSIN

IOWA

MINNESOTA

NORTH DAKOTA

SOUTH DAKOTA

MONTANA

NEBRASKA

WYOMING

Fitzsimons Medical Facility

Fort Carson

Pueblo DA

Cornhusker AAP Iowa AAP

Fort McCoy Badger

AAP

Twin Cities AAP

Military Works Boundary US Army Facilities US Air Force Facilities

Peterson AFB NORAD

USAF Academy Lowry AFB

F.E. Warren AFB

Minot AFB Grand Forks

AFB

Ellsworth AFB

Offutt AFB

Gen. Mitchell Field

Minn.-St Paul IAP

Schriever AFB

Buckley ANG

Civil Works Boundary

Regulatory Offices Operations Projects

Omaha

Missouri River

Niobrara River

Platte River

Helena

Bismarck

Cheyenne

Denver

Kearney

Pierre

Omaha

Black Hills

Rocky Mountain

Fort Crook

Area Offices

Regulatory Boundary

District Mission Areas

BUILDING STRONG® 5

Omaha District Workload

FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15

CW 244 197 243 240 304 227 189 191 192 MIL 640 661 591 576 254 463 299 535 215 ER 193 186 296 230 235 179 170 170 184 SP NA NA 143 220 370 282 279 288 282 $M 1077 1044 1273 1266 1163 1151 937 1184 873

BUILDING STRONG® 6

Civil Works Branch

Perry Creek

Western Sarpy

Boyer Bend

Antelope Creek

BUILDING STRONG® 7

CW – Program

BUILDING STRONG® 8

Project Location/Type of Project Cost Range Adv Date

Western Sarpy, NE

- Segment #5 Clear Creek Levee $1M - $5M 03/2012

- West Bank Chute $1M - $5M 03/2012

Missouri River Recovery

- SWH – Desoto Bend/Boyer Chute $1M - $5M 06/2012

- SWH – River Structure Modifications $1M - $5M 07/2012

- SWH – Deer Island/Little Sioux (Phase 2) $1M - $5M 08/2012

- SWH – Backwater Construction $1M - $5M 08/2012 - ESH – Modifications (North Dakota) $100K - $500K 04/2012

- ESH – Modifications (NE & SD) $100K - $500K 04/2012

Big Sioux River, Sioux Falls, SD

- Closure Structures $1M - $5M 01/2012

Civil Works Opportunities

BUILDING STRONG® 9

Project Location/Type of Project Cost Range Adv Date

Jamestown SE Project, ND

- Riprap Bank Stabilization $100K - $500K 11/2011

Yellowstone Corridor Study, MT and ND

- Socioeconomic Study $100K - $500K 07/2012

Big Bend Project

- Rehab Powerhouse Crane $100K - $500K 07/2012

- Thrust Bearing Cooler $500K - $1M 01/2012

Fort Peck Project

- Upgrade Campground Electric $100K - $500K 07/2012

- Rehab Unit 2 $5M - $10M 09/2012

Civil Works Opportunities

BUILDING STRONG® 10

Project Location/Type of Project Cost Range Adv Date

Fort Randall Project

- Rehab Tailrace Crane $100K - $500K 08/2012

- Sequencing Study $100K - $500K 11/2011

- 115KV Switchyard Upgrade $5M - $10M 02/2013

Gavin’s Point Project

- Power Plant Generator Step-Up Transformers $1M - $5M 10/2012

- Trash Racks $500K - $1M 05/2012

Oahe Project

- Replace Transformer Accessories $100K - $500K 09/2012

- Switchyard Upgrade $5M - $10M 02/2013

Civil Works Opportunities

BUILDING STRONG®

CW – NWO Successes Antelope Creek in Lincoln, NE

► Great example of Collaboration

Use of ARRA $

► Met our commitments and then some ► Improved infrastructure Within Missouri River basin.

11

BUILDING STRONG®

Military Programs Branch Wilderness Road Brigade Battalion HQ

4th ID HQ

Brigade Battalion HQ

Soldier Family Activity Center

BUILDING STRONG®

BUILDING STRONG®

FY12 Military Construction Army (MCA)

Location Description Advertise Bid Open Cur/ActAward QTR CCL

($000) Remarks

Ft CarsonBrigade Headquarters PN 65602 P2:

3365432-Nov-10 2-Dec-10 31-Dec-10 1 $12,973 In House Design Development ongoing.100% -

DESIGN BID BUILD IFB - SB

Ft Carson Barracks PN 77264 P2:336548 25-Oct-10 30-Nov-10 14-Dec-10 1 $60,360Design Build - RFP - Directive Code 7 - SWF Preparing RFP - in house site work design. SWF will Procure using COS MATOC

Ft Carson Barracks PN 77265 P2:336545 25-Oct-10 30-Nov-10 14-Dec-10 1 $41,441Design Build - RFP - Directive Code 7 - SWF Preparing RFP - in house site work design. SWF will Procure using COS MATOC

Ft CarsonASB Maintenance Hangar PN 77306

P2: 3365586-Nov-10 8-Dec-10 31-Dec-10 1 $54,955

Design Build - RFP -Directive Code 7 - Mobile preparing RFP - in house sitework. CENWO will execute contract action - UNRESTRICTED SITE SPECIFIC RFP

Ft Carson Control Tower PN 77302 P2:336560 2-Nov-10 2-Dec-10 31-Dec-10 1 $12,252

Design Build - RFP -Directive Code 7 - Mobile preparing RFP - in house sitework. CENWO will execute contract action. UNRESTRICTED SITE SPECIFIC RFP

Ft CarsonAircraft Loading Apron - Infrastructure

PN 77319 P2:33656129-Oct-10 30-Nov-10 14-Dec-10 1 $30,631

Design Bid Build - Directive Code 6 - In House 100% Design. Executing Surveys and Borings for entire CAB Complex Facilties and Sitework - 100% DESIGN BID BUILD IFB -SB

BUILDING STRONG® 15

FY12 Military Construction Air Force (MCAF)

Location Description Advertise Bid Open Cur/ActAward QTR CCL

($000) Remarks

Minot Dormitory (168 Room) QJVF092001 P2:334786

18-Oct-11 15-Nov-11 15-Dec-11 1 $19,820 Unrestricted - 100% Design Bid Build

Minot

B-52 3-BAY CONVENTIONAL MUNITIONS - QJVF092010 P2: 334785

18-Oct-11 15-Nov-11 22-Dec-11 1 $10,450 TBD - Design Build RFP

Minot

B-52 TWO-BAY PHASE MAINTENANCE DOCK - QJVF092012 P2: 334784

7-Oct-11 15-Nov-11 22-Dec-11 1 $30,631 Unrestricted - Design Build RFP

AF Academy

Large Vehicle Inpspection XQPZ044003

18-Oct-11 15-Nov-11 22-Dec-11 1 $12,072 TBD - Design Build RFP

BUILDING STRONG®

Environmental Remediation Branch

MacDill AFB, FL Soil Remediation Seymour Johnson AFB, NC

Well drilling at FE Warren AFB, WY, former Atlas Missile Site

BUILDING STRONG® 17

Environmental Remediation Mission

Value-added environmental services to Federal agencies including: Investigations Studies Remedial Design Remedial Actions, including rapid response Long-Term Operation/Long-Term

Maintenance (LTO/LTM) Military Munitions Response Program

(MMRP) Emphasis is on remedy in place (RIP),

response complete (RC) and site closeouts.

BUILDING STRONG® 18

Omaha District Major Installations

Langley AFB (ACC)

Seymour Johnson AFB (ACC)

Andrews AFB (AFD-W)

Legend Omaha District Military Boundaries

Northwestern Division Boundaries

Travis AFB (AMC)

Minot AFB (ACC)

Grand Forks AFB (AMC)

Ellsworth AFB (ACC)

Offutt AFB (ACC) F.E. Warren AFB

(AFSPC)

Buckley AFB (AFSPC) Shriever AFB (AFSPC)

USAF Academy Peterson AFB (AFSPC)

Ft Carson NORAD

Pueblo Depot

Ft McCoy

Badger AAP

Iowa AAP

Twin Cities AAP

Cornhusker AAP

Pope AFB (AMC)

Myrtle Beach AFB (BRAC)

McConnell AFB (AMC)

MacDill AFB (AMC)

Shaw AFB (ACC)

Moody AFB (AFSPC)

Holloman AFB (ACC)

Cannon AFB (ACC)

Eglin AFB (AFMC)

Kirtland AFB (AFMC)

Davis-Monthan AFB (ACC)

Nellis AFB (ACC)

Dover AFB (AMC)

Dyess AFB (ACC)

Goodfellow AFB (AETC)

KI Sawyer AFB (BRAC)

Mountain Home AFB (ACC)

Maxwell AFB (AETC)

Scott AFB (AMC)

Vandenberg AFB (AFSPC)

Charleston AFB (AMC)

Beale AFB (ACC)

Barksdale AFB (ACC)

Whiteman AFB (ACC)

BUILDING STRONG® 19

Environmental Remediation Current Workload

INSTALLATIONS STATES

ER 44 26 MMRP 106 38 ER/MMRP 122 41 RAPID RESPONSE (RR) 22 18

TOTAL ER/MMRP/RR 135 41

BUILDING STRONG® 20

BUILDING STRONG® 21

~95% of environmental work is contracted out.

Primarily utilize Environmental Remediation Services (ERS) Indefinite Delivery Indefinite Quantity (IDIQ)

Emphasis on developing and utilizing small business (SB) firms.

Project Acquisition Strategy Board determines appropriate method of execution.

Regional sharing of ERS contracts within NWD.

Environmental Remediation Execution Methods

BUILDING STRONG® 22

• Multi Environmental Government Acquisition (MEGA):

• MEGA is a combined acquisition strategy with multiple USACE Districts. • The acquisition strategy includes combinations of Unrestricted and Small

Business ERS; A-E; Pre-Placed Remedial Action (PRAC); and Environmental Consultation Services contracts that are national and/or regional.

• Current Status:

• Acquisition Strategy and Plan has been approved. • MEGA Management Plan has been approved • Statement of Work developed collaboratively by all eight Districts. • Kansas City District submitted first solicitation and made first award – AE.

Environmental Remediation Opportunities

BUILDING STRONG®

MEGA Participants The 3 USACE Divisions involved in the MEGA are:

► Northwestern Division (NWD) • Omaha • Kansas City • Seattle

► Southwestern Division (SWD) • Tulsa • Fort Worth

► South Pacific Division (SPD) • Sacramento • Albuquerque • Los Angeles

23

BUILDING STRONG®

MEGA Specifications

Total $7.07B 5 Year strategy – Based on approval of

MEGA Acquisition Plan Acquisition Strategy approved by OSD on

March 27, 2011 Acquisition Plan approved by PARC on

May 23, 2011

24

BUILDING STRONG®

MEGA Specifications

Total MEGA approved capacity - $7.07B 95 MATOC pools (Total of 447 contracts) 27 Brooks Act A-E pools Most MATOC pools will have 5 Contractors Contracts 3 year base plus 2 year option A Total of 474 Contracts may be Awarded!

25

BUILDING STRONG®

Approved MEGA Strategy ► Environmental Remediation Services – 562910

• Nationwide $2B • NWD, SPD, SWD Regional $2B

► Military Munitions Response Program • NWD Regional $750M

► Pre-Placed Remedial Action Contracts • NWD Regional $1.5B

► A-E Services – NAICS 541330 • NWD Regional $320M

► Environmental Consulting Services - 541620 • NWD, SPD, SWD Regional $500M

26

BUILDING STRONG®

Unprecedented Support of Small Business

SDVOSB $423.5 Million = 6% 68 Contracts

HUBZone $311 Million = 4% 63 Contracts

Small Business (no subcategory) $2.587 Billion = 37% 133 Contracts

Unrestricted $2.77 Billion = 39% 104 Contracts

Section 8 (a) $978.5 Million = 14% 106 Contracts

61 % Small

Business

MEGA $7.07 Billion

27

BUILDING STRONG®

Multiple Environmental Government Acquisition - $7.07B Plan

MEGA Progress

28

Advertized Total * A-E Brooks Act contracts

13

22

10 12

4

10*

20

6 4 4

BUILDING STRONG®

MEGA Points of Contact

Linda White, PE, PMP (technical) ►[email protected] ►402-995-2743

Loreen Blume (contractual) ►[email protected] ►402-995-2092

BUILDING STRONG®

MEGA Contacts Albuquerque – (C) Erica.M.Talley@ Fort Worth – (P) Mark.E.Simmons@; (C) Elizabeth.A.Crawford@ Kansas City – (C) Shelley.Thomas@ Los Angeles – (C) Patricia.B.Bonilla@ Omaha - (C) Loreen.K.Blume@; (P) Linda.J.White@ Sacramento – (P) Christopher.E.Prescott@

(C) Colette.C.Nalley@ Seattle – (P) Robert.l.Frazier@; (C) Bonnie.I.Kirmse@ Tulsa – (C) Brenda.K.Anderson@ @USACE.Army.mil (C) Contracting (P) Project Management

30

BUILDING STRONG® 31

Cost Proposed Proposed Project Location/Type of Project Range Adv Date Awd Date (Mo/Yr) (Mo/Yr) •MEGA - Small Business ERS w/MMRP IDIQ $250M 5/11 12/11 Multi Award Task Order Contract (MATOC) Nationwide , 5 contract pool •MEGA - Small Business Environmental $60M 10/11 4/12 Consulting IDIQ Multi Award Task Order Contract (MATOC) NWD Boundaries and existing USACE customers, 3 contract pool

Environmental Remediation FY12 Omaha Opportunities

BUILDING STRONG® 32

Cost Proposed Proposed Project Location/Type of Project Range Adv Date Awd Date (Mo/Yr) (Mo/Yr) •MEGA – 8a Environmental $60M 2/12 6/12 Consulting IDIQ Multi Award Task Order Contract (MATOC) NWD Boundaries and existing USACE customers, 3 contract pool •MEGA - Small Business Military Munitions $112.5M 2/12 6/12 Response Program (MMRP) IDIQ MATOC NWD Boundaries and existing USACE customers, 5 contract pool

Environmental Remediation FY12 Omaha Opportunities

BUILDING STRONG® 33

Environmental Remediation Opportunities – FY12

Cost Proposed Proposed Project Location/Type of Project Range Adv Date Awd Date (Mo/Yr) (Mo/Yr)

•MMRP SATOCs (NWD boundaries and existing USACE customers)

•Small Business $9.9M TBD TBD •Small Business $9.9M TBD TBD

•Pueblo Chemical Depot , CO $ 9M 10/12 12/12 Remediation Services, Site Specific (BRAC)

BUILDING STRONG®

Special Projects Branch

Indiana Dunes National Lakeshore, IN – DOI NPS

Temporary Pumping Stations USACE HPO

Detroit Powerhouse Fire, OR Portland District

BUILDING STRONG® 35

Special Projects Mission & Function

Special Projects Branch mission: Execution of programs and projects formally known as “Support for Others”, “Environmental Support for Others”, and “Interagency and International Services (IIS)”

Branch is responsible for assembling project delivery teams to manage reimbursable funded customers such as:

EPA, DOI, DOE, DoD-FSRM (Facility Sustainment, Restoration & Modernization)

DHS, DLA/ DESC and VA

BUILDING STRONG® 36

Special Projects Mission & Function

Provide national and international time-sensitive as well as non time-sensitive support of homeland security/defense, disaster, and infrastructure work

Utilize Internal District & External USACE staff resources to manage project execution

Execution tools include discretionary/flexible cost reimbursement contract mechanisms to accomplish the mission to, serving the nation and all Federal Agencies

BUILDING STRONG® 37

BUILDING STRONG® 38

Cost Proposed Proposed Contract / Project Range Adv Date Awd Date (Mo/Yr) (Mo/Yr) Rapid Response 5 IDIQ (four contracts) $245M Total Environmental Response Contract (SATOC)

• Unrestricted $80M 4/22/11* 8/11 • Small Business $95M 4/22/11* 10/11 • Service Disabled Vet $35M 10/11 5/12 • 8a $35M 10/11 5/12

Note * Actual Advertised

Special Projects Opportunities

BUILDING STRONG® 39

Omaha District Points of Contact

Deputy District Engineer Ted Streckfuss 402-995-2003

Chief, Civil Works Branch Bradley Thompson 402-995-2718 Chief, Environmental Remediation Randy Petersen Branch 402-995-2736 Chief, Military Branch Vincent Turner 402-995-2781 Chief, Planning Branch Kayla Eckert-Uptmor 402-995-2693 Chief, Special Projects Branch Greg Herring 402-995-2644

BUILDING STRONG® 40

Questions?