U.S. 93, 200 South Intersection
Project Update No. 1 / March 2016Project Number: A018(737) / Key Number: 18737
Project BackgroundThe Idaho Transportation Department (ITD) is planning to reconstruct and widen U.S. 93 through the 200 South Road intersection in Jerome County (milepost 56.727). The project is one of several improvement projects in various stages of planning and design that were identified in the 2008 Environmental Assessment for U.S. 93 between I-84 and Idaho 25 east of Jerome. The 200 South Road intersection has been identified as a high-accident location and the project will improve safety for traffic at that location. The project is funded for construction in FY 2019.
Project Description
U.S. 93 Improvements - The project entails improvements on U.S. 93 from M.P. 56.227 to M.P. 57.231 (½ mile north and south of the 200 South intersection). Project improvements are planned so they will coordinate with other planned improvement projects in the corridor as described in the Environmental Assessment. Design elements on U.S. 93 include:
• Two lanes each direction • Left and right turn lanes at 200 South • U turns at mile and ½ mile locations • Widened shoulders • Divided median between intersections • Reconstruction of affected irrigation structures • Access control measures • Plans for future development of a bike/pedestrian
pathway
200 South Improvements - The project extends several hundred feet east and west along 200 South Road. Design elements on 200 South include:
• One through lane each direction • Left turn lanes • Widened shoulders
Public Involvement The process includes public involvement opportunities to inform and engage all corridor stakeholders and the general public. Public involvement activities include stakeholder interviews to identify concerns, property owner visits to explain the project and identify right of way issues, local government presentations to explain the project, public open houses, media coordination, and a project web page. Watch local media and the project web page at http://itd.idaho.gov/projects/D4/US93/index.html for announcements of upcoming public open house events and updated project information.
General Project Schedule Preliminary Design • Survey and mapping • Preliminary roadway and drainage design • Right of way identification • Initial stakeholder interviews • Local government coordination and
presentations • Property owner / business owner
communications and visits • Initial agency coordination • Identification of utility relocations • Public Open House #1 – March 16, 2016
Winter / Spring 2016
Final Design • Continued individual property / business
owner coordination • Continued agency coordination • Final determination of utility relocations • Confirmation of roadway alignment and
right of way needs • Public Open House #2 – Fall 2016
Summer / Late Fall
2016
Right of Way Acquisition • Coordination with affected property
owners • Parcel appraisals • Property acquisitions
2017
Advertisement and Contracting • Completion of bid documents and
advertisement • Selection of contractor
Spring / Summer
2018
Construction • Construction staging information
provided through public announcements * Construction schedule subject to change
Begin Fall 2018*
Preliminary Design Public Open House
Wednesday, March 16, 2016 5:30 p.m. to 7:30 p.m.
(drop in anytime during the session)
Idaho Department of Fish and Game Office 316 South U.S. 93
“Attention - If you would like information regarding this project in Spanish, please call (208) 334-4444 / Ana Gonzalez (208) 886-7837” “Atención - Si usted quiere la información acerca de este proyecto en Español, llame por favor al (208) 334-4444 / Ana Gonzalez (208) 886-7837”
U.S. 93, 200 South Intersection Preliminary Design
(As outlined in the Final Environmental Assessment / Note that the final design may vary)
Idaho Transportation Department 216 South Date Shoshone, ID 83352
For more information on the U.S. 93, 200 South Intersection Project:
Mike Scott, Project Manager, ITD Mike Pepper, Public Involvement, KMP Planning 208-886-7806 / [email protected] 208-316-5817 / [email protected] Project Web Page: http://itd.idaho.gov/projects/D4/US93/index.html