37
University Hospital Operating Room Turnover Time Final Report Submitted to: Ms. Renee Prince, Nursing Services Director, University Hospital Operating Room Mr. Austin Chrzanowski, Continuous Improvement Specialist, Continuous Improvement Mr. Ian Perry, Continuous Improvement Specialist, Continuous Improvement Dr. Mark Van Oyen, IOE 481 Professor, Industrial and Operations Engineering Ms. Mary Duck, IOE 481 Liaison, Michigan Medicine Submitted by: IOE 481 Project Team 9 Danielle Kessler Hyunji Choi Vidisha Hemani Arda Koyunsev Date Submitted: December 10, 2019

University Hospital Operating Room Turnover Time Final Report

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

University Hospital Operating Room Turnover Time

Final Report

Submitted to:

Ms. Renee Prince, Nursing Services Director, University Hospital Operating Room

Mr. Austin Chrzanowski, Continuous Improvement Specialist, Continuous Improvement

Mr. Ian Perry, Continuous Improvement Specialist, Continuous Improvement

Dr. Mark Van Oyen, IOE 481 Professor, Industrial and Operations Engineering

Ms. Mary Duck, IOE 481 Liaison, Michigan Medicine

Submitted by:

IOE 481 Project Team 9

Danielle Kessler

Hyunji Choi

Vidisha Hemani

Arda Koyunsev

Date Submitted: December 10, 2019

2

Table of Contents

Executive Summary………………………………………………………………………… 5-7

Background …………………………………………………………………….……… 5

Methodology and Findings ……………………..……………………………………… 6

Recommendations……………………………………...……………………………… 7

Introduction …………………………………...………………………………………………... 8

Background and Key Issues ……………………………………………………………… 8-10

Goals and Objectives……………………………………………………….………………... 10

Project Scope ………………………………………………………………………………. 10-11

Deliverables and Design Tasks…………………………………………………………… 11-13

Construct current-state process…………………………………...…………………... 11

Perform benchmarking analysis…………………………………...…………………… 11

Construct future state turnover standards and procedures ……………………………..11

Perform Literature Search …………...……………………..…………...………… 11-13

Past IOE 481 Project…………...……………………..…………...…………… 11

Genji Genbutsu …………...……………………..…………...………………… 12

Operating Room Start Times and Turnover Times in a University Hospital.. 12-13

Improving Operating Room Turnover Time in a New York City Academic

Hospital via

Lean…………...……………………..…………...……………………..……… 13

Design Requirements, Constraints, and Engineering Standards …………...…………. 14-15

Design Requirements (Soft Constraints) in detail…………...………………………….14

Hard Constraints in detail…………...……………………..…………...……………… 14

Engineering standards…………...……………………..…………...…………………. 15

Data Collection and Analysis Methods…………...……………………..…………...…… 15-18

Data Collection Methods…………...……………………..…………...…………… 15-16

Interviews…………...……………………..…………...……………………….. 15

Historical Data…………...……………………..…………...…………………. 15

Observations…………...……………………..…………...…………………… 15

Time Studies…………...……………………..…………...…………………… 16

Data Analysis Methods…………...……………………..…………...……………… 16-18

Swim Lane Analysis……..…………...……………………..…………...…… 16-18

Findings and Conclusions…………...……………………..…………...…………………..18-25

Interviews…………...……………………..…………...……………………………. 18-19

Historical Data Analysis …………...……………………..…………...………….. 19-23

Calculating Turnover…………...……………………..…………...……………19

ASA Score …………...……………………..…………...………………….. 19-20

Time of Day …………...……………………..…………...………………. 20-21

Case to Follow Procedure Level…………...…………………..………….. 21-22

3

Observations …………...……………………..…………...………………………. 23-24

Time Studies …………...……………………..…………...………………………….. 24

Current State Flow Chart……………………..…………...……………………… 24-25

Alternatives Considered …………...……………………..…………...………………… 25-26

Criteria for Evaluation …………...……………………..…………...………………… 26

Decision matrix …………...……………………..…………...………………………… 26

Recommendations …………...……………………..…………...………………………... 26-27

Standard turnover time …………...……………………..…………...………………… 26

Standard “room ready” time .……………………..…………...…………………… 26-27

Clear communication of expectations …………...……………………..……………….27

Expected Impact…...………………..…………...………………………........................... 27-28

Impact of standardizing turnover time…...……………………..………...………..... 27

Impact of standardizing “room ready” time…...…………………….....………......... 27

Impact of clearly communicating expectations…...……………………..……..... 27-28

Recommendations for Future Work………………...………………………........................ 28

References …………...……………………..…………...………………………..................... 29

Appendix …………...……………………..…………...……………………….................. 30-37

Appendix A: Road to 30 - Room Turnover Operating Room Efficiency Poster………. 30

Appendix B: Requirements, Constraints, and Standards Matrix …………………… 31-32

Appendix C: OR Observation Form ………...……………………..…………………. 33

Appendix D: Swim Lane………...……………………..………………….……………. 34

Appendix E: Significant and Insignificant Factors …………………………………… 35

Appendix F: Current State Map …………………………………………………………36

Appendix G: Pugh Decision Matrix………...……………………..……………….....…37

4

List of Figures and Tables

Figure 1: Turnover times are too high and vary greatly by departments ……………………… 9

Figure 2: High level current turnover process from the Nursing Services Director’s perspective.9

Figure 3: Observation Form…………………………………………………………………… 16

Figure 4: Swim Lane Analysis ……………………………………………………………….. 17

Figure 5: ASA Score Box Plot ………………………………………………………………… 20

Figure 6: Time of Day Box Plot ……………………………………………………………… 21

Figure 7: Procedure Level Service Turnover Data Error Band Line Graph …………………. 22

Figure 8: Procedure Level Surgeon Turnover Data Error Band Line Graph ………………….. 23

Figure 9: UHOR Turnover Process Current State Map ……………………………………… 25

Table 1: Swim Lane Calculations ……………………………………………………………... 18

Table 2: Turnover Calculation Table ………………………………………………………… 19

Table 3: ASA Score Turnover Data …………………………………………………………. 20

Table 4: Time of Day Turnover Data………………………………………………………… 21

Table 5: Procedure Level Turnover Data for Same Service ………………………………… 22

Table 6: Procedure Level Turnover Data for Same Surgeon ………………………………… 23

Table 7: Time Studies Data ……………………………………………………………………. 24

5

Executive Summary

The University Hospital Operating Rooms (UHOR) at the University of Michigan perform

surgical operations in a variety of services such as plastics, orthopedics, and urology. Patient

turnover time is defined as the time from when a patient leaves the OR to when the following

patient enters. Currently, the perception is that process of turning over a room in the OR takes

too long. However, there is also not a standard for how long turnover should take. To address

this concern, the Nursing Services Director requested that the student team at the University of

Michigan develop a standard for turnover time and recommend improvements to the operating

room.

To accomplish this task, the student team conducted interviews, analyzed historical data,

performed on-site observations and time studies in the operating room, and conducted a literature

search to compare the process at the UHOR to other similar institutions. Based on the results of

this data collection, the team developed recommendations for the standard amount of time a

turnover should take as well as the changes the OR staff can make to their process to improve

turnover times. The team expects that the recommendations included in this report will result in

clarity about the turnover expectations in the OR.

Background

Although the hospital handles a variety of services and case types, the student team chose to

focus on neurosurgery, urology, and orthopedic services. This decision was made because these

services represent each of the three pods of the OR and due to their high volume and variety of

cases. Additionally, urology generally has lower turnover times while neurosurgery has higher

turnover times. Comparing the cause of the differences in turnover time is useful during the

observations. The Case Time Reporting Tableau Dashboard shows that urology has an average

turnover time of 40 minutes, neurosurgery has an average of 58 minutes, and orthopedics has an

average of 53 minutes. There are currently no set standards for how long the process should take,

but concerns among surgeons, hospital staff, and patients show that improvements can be made

to standardize the turnover process.

The current process of turning over a room goes as follows. When a patient exits the room, the

perioperative technician, or PT, comes in to clean the room and the scrub takes away the

instruments from the previous patient to decontaminate them. While the room is being cleaned,

the circulator brings the patient’s paperwork to the front desk and checks on the next patient. The

anesthesiologists get a page when the patient leaves and they clean their equipment and prepare

their lines for the upcoming patient. After the room is cleaned by the PT’s, the scrub opens and

counts the instruments for the next case. Anesthesia leaves to bring the patient into the OR after

room ready is called. Once the circulator, anesthesiologist, and scrub have completed their jobs,

the next patient may enter the operating room. While this is the expected process flow, it is not

6

standardized, resulting in highly variable turnover times. As a result of this issue, the goals and

objectives of this project were to develop a standard for turnover time and turnover process

based on the data collection and analysis that the team conducts.

Methodology and Findings

The team performed the following five tasks and arrived at their respective findings in order to

evaluate and improve the current turnover process.

● Conducted interviews with various stakeholders. The student team interviewed the pod

supervisors for each of the three pods as well as the perioperative technician supervisor in

order to understand the role of each person in the turnover process as well as gain insight

to perceived current problems in the process. Through these interviews, the team defined

clear roles of the circulator, scrub, and PT.

● Analyzed historical data. The student team analyzed historical data from July 2015 to

October 2019 regarding turnover times at the UHOR. Filters such as day of the week and

emergent or urgent cases were added. The data was used to calculate turnover time and

evaluate significant or insignificant factors to turnover time such as time of day, ASA

score, and procedure level. The time of day data analysis highlighted that range of

turnover decreases from 34 min - 48min to 32 min - 46 min. The ASA data analysis

showed that there was no correlation and that the median was 40 minutes across all

levels.

● Observed turnovers in the OR. The team observed a total of 13 turnovers at various times

of day in urology, neurosurgery, and orthopedics services. Through the observations the

team concluded that PT’s generally arrived quickly, the lack of cleanup prior to case

ending increased turnover significantly and most delays were due to external factors.

● Conducted time studies. The team conducted time studies during the 13 observations in

order to evaluate the length of turnover sub-processes such as cleaning the room, opening

up the next case, and getting the next patient. The general time it took PT’s to enter was

1:33 with orthopedics have the lowest average of 0:55. The PT’s took approximately 10

minutes, anesthesia and circulators didn’t have a large impact on turnover and scrubs

took the longest with an average of 25 minutes.

● Performed literature searches. The team found 5 pieces of literature that supported the

recommended turnover time and methods to increase turnover time. The articles helped

the team come to the recommendation that turnover time should be 37 minutes and that it

would be helpful to have a surgeon in the room during turnover time.

Recommendations

After reviewing the findings from the data collection and analysis, the team developed three

recommendations: (1) establish a set standard for turnover time for each department, (2) establish

a standard for “room ready” time and (3) clearly communicate expectations for all staff members

(nurses, PT’s, scrubs, etc).

7

Standard turnover time

● Average turnover time across the departments: 40 minutes

● Average turnover time for urology: 30 minutes

● Average turnover time for orthopedics: 40 minutes

● Average turnover time for neurosurgery: 45 minutes

This is due to the varying number of trays and different complexities of the surgeries that affect

turnover time.

Standard “room ready” time

Room ready is currently defined as the time that everything in the room is set up and ready for

the patient to arrive. Throughout the course of interviews and observations, it became clear that

many of the circulators had different ideas of when to call room ready. Calling room ready in the

system triggers a pager for anesthesia to bring the patient to the room. However, bringing the

patient to the room takes an average of around 10 minutes, as calculated in the time studies. If

room ready is called when everything is completely set up, the staff in the room was waiting

until the patient was brought back into the room. Therefore, the team recommends that the room

ready is redefined to be 10 minutes prior to the room being set up. Standardizing this expectation

across all of UHORs will allow the setup process to be finished concurrently with the patient

transportation to the OR.

Clear communication of expectations

During the interviews and observations, it became clear that different members of the staff had

different expectations of what the turnover time should be and how clearly the roles were

defined. The team came up with the following expectations for all staff members to be aware of:

● Circulators should have all of the trash ready and scrubs should have all their trays

packed up while the patient is getting ready to leave. This allows for the PT’s to be paged

immediately after the patient leaves the room, thus reducing turnover time.

● If possible, three PT’s should be used in neurosurgery and orthopedic cases in order to

further reduce the turnover time

● Nurses in Pre-Op should ensure all patient consent is obtained, all the tests are done, and

all the drugs are administered in a timely manner prior to their surgery. This will prevent

delays in calling for room ready due to patient unpreparedness.

● Newer CRNAs and anesthesia technicians should start in urology rooms because the

lower likelihood of raising turnover times

8

Introduction

The University Hospital Operating Room (UHOR) at the University of Michigan performs

surgical operations in a variety of services such as plastics, orthopedics, and urology. Patient

turnover time is the time between the point one patient leaves the operating room to the next

patient enters. The hospital is currently experiencing patient turnover times that vary widely and

take too long. Due to a lack of a standardized process, there are often concerns expressed by

surgeons, patients, and nurses regarding the amount of time it takes to turn over a room. The

Nursing Services Director has requested the IOE 481 student team from the University of

Michigan to develop a standard turnover time and process that will ensure patient safety and

satisfaction, as well as satisfaction among various employees at UHOR such as surgeons, nurses,

and perioperative technicians. The student team has conducted interviews, analyzed historical

data, and conducted on-site observations and time studies in order to map out the current state of

the turnover process. The primary goal of this project is to leverage the analysis of the current

state of the turnover process to develop a standard expectation for turnover time and recommend

improvements to the UHOR’s turnover process. This final report presents an analysis of the

historical data and observations, findings and conclusions from all data collection methods, and

recommendations for standardizing the turnover process at the UHOR.

Background and Key Issues

The hospital has a wide variety of services. Among them are general surgeries, transplants,

orthopedics, urology, plastics, and neurosurgery. These services are organized into three

different pods (Pod 1, Pod 2, and Pod 3) that are responsible for their own set of case types and

have its own supervisor. The services with the highest volumes of cases over the last year were

urology (Pod 3) with 4,297 case types, orthopedics with 3,566 (Pod 2), and neurosurgery with

2,284 (Pod 1).

Currently, the perception is that process of turning over a room in the OR takes too long. The

UHOR Case Time Reporting Tableau Dashboard shows that urology has an average turnover

time of 40 minutes, neurosurgery is 58 minutes, and orthopedics is 53 minutes. This data is based

on 1791 cases for urology, 647 cases for neurosurgery, and 1602 cases for orthopedics that took

place over the last 365 days. This data can be seen in Figure 1.

9

Figure 1: Turnover times are too high and vary greatly by departments

Source: UHOR Case Time Reporting Tableau Dashboard Collection Period: 365 days

Sample size: 1791urology cases, 647 cases neurosurgery, and 1602 orthopedic cases

Preliminary meetings and interviews with the Nursing Services Director suggest that turnover

time varies based on a variety of factors such as case type, time of day, surgeon, etc. There are

currently no set standards for how long the process should take, but there are concerns among

surgeons, hospital staff, and patients that show that improvements can be made to expedite the

turnover process.

The current turnover process is illustrated in Figure 2.

Figure 2: High level current turnover process from the Nursing Services Director’s perspective

When a patient exits the room, the perioperative technician, or PT, comes in to clean the room

and the scrub takes away the instruments from the previous patient to decontaminate them.

While the room is being cleaned, the circulator brings the patient’s paperwork to the front desk

10

and checks on the next patient. The anesthesiologists get a page when the patient leaves and they

clean their equipment and prepare their lines for the upcoming patient. After the room is cleaned

by the PT’s, the scrub opens and counts the instruments for the next case. Anesthesia leaves to

bring the patient into the OR after room ready is called. Once the circulator, anesthesia, and

scrub have completed their jobs, the next patient may enter the operating room. Once the

circulator, anesthesiologist and scrub have completed their jobs, the next patient may enter the

operating room.

The perceived main issue with turnover time in the OR is that the hospital staff is physically

taking too long to turn over rooms, which can delay other services such as feeding the patients on

time and staying on schedule for the remainder of the day. However, a likely contributor to the

problem is that there is currently no set standard for how long this process should take.

Goals and Objectives

The primary goal of this project is to evaluate the current state and provide recommendations to

decrease the turnover time at the UHOR. The student team will achieve this goal by addressing

the following objectives:

● Establish baseline standards for the expected time turnover takes for specific case type by

evaluating the current state and comparing the hospital to similar institutions

● Develop a process that will allow the UHOR to achieve those standards

Having a standard for turnover time will create a goal turnover time for scrubs, circulators,

anesthesiologists, and preoperative technicians to reach. Once turnover time is standardized with

the implementation of the team’s recommendations, surgeons will be able to adhere to their daily

schedule better. This, in turn, may have a positive impact for patients because it could prevent

delays in the OR procedures and in other services, such as feeding.

Project Scope

This project took place in the OR of the hospital at the University of Michigan. There are three

pods of the OR which are for different service types. The team examined one service per pod,

specifically neurosurgery, orthopedics, and urology. The scope of this project covers all of the

processes that take place that impact turnover time and all tasks inside the OR room between

patients, such as cleaning the room, setting up the room for the next patient, and setting up the

anesthetics for the upcoming patient. The process starts when one patient exits the room to when

the next patient enters.

11

This project did not include any services outside of neurosurgery, orthopedics, and urology. It

also did not include any activities that occur in the operating room during a surgery or when the

patient is present in the room.

Deliverables and Design Tasks

The team documented the current state of the turnover process and performed a benchmarking

analysis. Using that insight, the team constructed a future state turnover standards and

procedures. The sections below provide an overview of each task and the deliverables.

Construct current-state process

The team constructed a current-state process flow chart through observational data. Observations

in the OR’s and interviews with pod supervisors, perioperative technician supervisor, and other

employees from neurosurgery, orthopedics and urology departments were conducted to gain an

understanding of the current process.

Perform benchmarking analysis

The team investigated turnover times at other large teaching institutions which is detailed in

literature search section. The team specifically looked at how the services and the roles that are

included in the turnover process differ from Michigan Medicine.

Construct future state turnover standards and procedures

Using the data from historical data, observations, time studies, interviews, and literature search

the team developed a recommendation for standard turnover time and the procedure to achieve

that turnover goal for each department in scope.

Perform Literature Search

The team used different sources of literature as a resource. A past IOE 481 project, a review of

the concept Genji Genbutsu, and similar projects done at comparable hospitals were used to

provide the student team with ideas for observation techniques and potential recommendations.

Past IOE 481 Project

The team reviewed the past IOE 481 project called “Utilizing Garbology to Analyze

Discrepancies between Planned, Documented, and Trashed Surgical Supplies in Hospital

Operating Rooms” conducted in Winter 2017. This analyzes the relevant observation methods

that a past team in 2017 used. The goal of the project was to study the discrepancies between

planned, documented, and trashed surgical supplies in the operating rooms. The team analyzed

the past team’s project by going through their observation methods and made conclusions about

potential observation methods to implement in the OR and be used for turnover time

calculations.

12

Genji Genbutsu

In the past IOE 481 project, the team stated that they observed in the OR to have a better

understanding of the process from the visual context. In the report, it is also argued that

witnessing the environment that a circulator nurse worked in helped the team understand the

roles of the key people working in the system. “The team saw the collection of wrappers and

witnessed the environment that a circulating nurse works in, taking note of points in the process

that could affect the accuracy of documentation. The team gained a greater understanding of the

process from the visual context of planned, documented, and trashed items in the hospital” [1]. In

LEAN manufacturing, this is called “Genji Genbutsu” which translates to “real location, real

thing” and is one of the key principles in the Toyota Production System. By observing the

system themselves with their own eyes, the observers are able to draw conclusions about the

system and potential problems without being affected by any bias or other opinion.

The team will adapt this approach for the OR observations because the literature search analysis

gave evidence that this approach indeed is very useful when optimizing a system. What makes

this approach especially relevant to the project is that so far during the preliminary observations

that the team has conducted and interviews with the PT team and nurses, the team has been

receiving different information. Circulators and scrubs have stated that the turnover process steps

are conducted simultaneously whereas the surgeons tend to think that the steps are performed

sequentially. These differences in opinion create a bias for the team. The main point of Genji

Genbutsu is that by asking people to explain a process, the observer starts focusing on looking

for those inputs that have been previously explained, thus creating a bias. This can make the

observer miss a lot of valuable insights about the process and the only way to overcome that is to

see the system independently; therefore, the team would benefit a lot from observing the

turnover process themselves to get a better insight.

Operating Room Start Times and Turnover Times in a University Hospital

The team found and analyzed an additional article titled “Operating Room Start Times and

Turnover Times in a University Hospital” by William J. Mazzei, MD. The paper discusses the

approach that was taken at the University of California, San Diego, Medical Center to decrease

the turnover times. The turnover time definition for both the conducted study and this project

align, thus the study was analyzed to draw useful conclusions to implement when trying to

decrease the turnover rate at the UHOR.

The study used p-value analysis stating that any p-value for “room ready” less than 0.05 would

be considered statistically significant. “Because each OR at University Hospital was dedicated to

an individual surgical service, data were grouped according to service for analysis, ... The

average times for each surgical service were compared with the average of all the services using

analysis of variance. A p-value less than 0.05 was considered statistically significant” [2].

The analyzed study used the results obtained from the p-value statistical analysis to create a

13

baseline for the turnover rate between 7 a.m and 5 p.m in the hospital OR. “At this institution,

the results obtained in this study were used as a baseline for launching a Total Quality

Management approach” [2]. Having the same goal in mind, the team may use statistical p-value

analysis in the future. The main conclusion from the paper was the ability to compare UHOR

with the other hospital’s turnover rates to create a baseline for the turnover rates.

Improving Operating Room Turnover Time in a New York City Academic Hospital via Lean

The team found and analyzed an article titled “ Improving Operating Room Turnover Time in a

New York City Academic Hospital via Lean” by Robert J. Cerfolio, MD, MBA, Dana Ferrari-

Light, DO, MPH, Christine Ren-Fielding, MD, George Fielding, MD, Nissa Perry, MA, Annette

Rabinovich, MHA, Mark Saraceni, MBA, Maureen Fitzpatrick, MSN, Sudheer Jain, MD, and H.

Leon Pachter, MD, FACS. The article discusses the use of lean and value stream mapping

increasing the turnover rates by 37 minutes on 3 operating rooms at an academic health center in

New York City. The turnover time definition for both the conducted study and the project that

the team worked on align, thus the study was analyzed to draw useful conclusions to implement

when trying to decrease the turnover rate at the UHOR.

The study made use of value stream mapping to better understand their process and to be able to

value what amount of time was considered value added or non-value added. They proceeded by

seeking improvements to be able to eliminate the non-value added time. “Each step of each

process was determined as “valued” or “and ''nonvalued “nonvalued” steps were eliminated.”[3].

The study also argues that there is even an opportunity to improve in value added steps and

explored streamlining the value added steps. “Importantly, the valued steps were further

reviewed and streamlined by removing unnecessary or duplicate movements” [3].

One of the ways that the study argues that contributed to the reduction of turnover time was

decreasing the tasks of the circulating nurse. The study argues that the circulating nurse is a key

character during the turnover and also has the most amount of ground to cover within the OR.

“Another change we made was to the circulating nurse task list. It was observed that many of the

tasks performed by the circulating nurse during turnover time required travel to other areas of the

operating room…” [3].

Road to 30 - Room Turnover Operating Room Efficiency

The team analyzed a project titled “Road to 30 - Room Turnover Operating Room Efficiency” at

the Henry Ford Hospital, that was provided by the coordinators. The article argues that the

primary keys to success “selected motivated and engaged staff across all functions to serve as

change agents” and “developed a clear and attainable room turnover goal = 30 mintues.” The

project poster fortified the teams aimed turnover rate as somewhere around 30+/- 5 minutes

range. See Appendix A for more information on the study.

14

Design Requirements, Constraints, and Engineering Standards

The primary design task of this project is to set a standard for turnover time and develop

recommendations to improve turnover times. The following sections describe the design

requirements, constraints and engineering standards in regards to the development of the

deliverables. The outlined design requirements are guidelines that outline the qualities that are

wanted in the final design of a system. The hard constraints are metrics that must be met in order

in the construction of the design. Standards are the procedures and guidelines set by regulatory

bodies. The description of the requirements, constraints, and standards can also be found in a

constraints and standards matrix in Appendix B.

Design Requirements (Soft Constraints) in detail:

When developing a standard turnover time, the student team considered the following four

design requirements. These design requirements are soft constraints that are used in evaluating

the alternatives and recommendations presented.

● (R-E-1) Benchmark against other large teaching institutions with a similar model as

Michigan Medicine. This ensures that the model can be implemented.

● (R-E-2) Teams and processes that are involved in turnover process must be defined so

that alternate, unavailable resources are not factored in.

● (R-F-1) Clear roles and tasks for each staff member involved in turnover process that are

approved by the staff members. This ensures everyone is understands who performs what

processes.

● (R-H-1) Minimum non-value-added-time so that the staff’s time is used more efficiently.

Hard Constraints in detail:

The hard constraints provided concrete guidelines for the team had to follow when considering a

design to standardize the turnover time. The team considered two different categories of

constraints: the limitations on data collection methods and the limitations surrounding the design.

Data Collection Constraints

● (C-E-1) Only two team members can observe at any given time due to OR space

constraints, which affects the number of factors and variables that can be recorded.

● (C-H-1) Data can be collected only for 5 cases in services for each department due to

time constraints, as the project must be completed by the end of the semester.

Design Constraints

● (C-D-1) The team must develop turnover standards and procedures using the current

number of staff for the nursing, anesthesia and perioperative technician departments.

15

Engineering standards:

The engineering standards set out by regulatory bodies that all hospitals and all projects within

hospitals must comply with.

● (S-1-1) The team must take into consideration HIPAA when conducting observations and

collecting data in order to not expose PHI.

Data Collection and Analysis Methods

The team used various methods such as historical data, surveys, time studies and current state

mapping in order to collect and analyze data. The following sections describe the team’s data

collection and analysis.

Data Collection Methods

In order to create a future state of the standardized turnover process, the team obtained relevant

historical data from July 2015 to October 2019. In the span of 3 weeks, observations in different

OR services were conducted simultaneously with time studies.

Interviews

The leaders of the key roles within the OR such as pod supervisors and PT supervisors were

interviewed. During the interviews, the team asked detailed questions aiming at understanding

each individual’s role from circulators to PT’s and investigated how these leaders perceived the

current turnover system. The team additionally inquired about ways to increase efficiency and

provide insight through these people’s perspective. This led the team to have an understanding of

the role of each individual in the OR.

Historical Data

The team analyzed the historical data starting from July 2015 until October 2019, that was

provided by the client. The provided data composed of key elements such as start and end times,

procedure types, procedure complexities, surgeon scheduling, etc.

The team gained insights and conclusions from the historical data provided in order to develop a

new observation form (Figure 3). This form breaks down each step of the current turnover

process in order to gain additional insight into any potential bottlenecks or inefficiencies in the

process.

Observations

The team started preliminary observations on October 24 and conducted observations until

November 22 to get an unbiased, holistic perspective of the current state. The team used the

observation form (Figure 3, Appendix C) to record and understand the processes each staff

member in nursing, anesthesia and PT department goes through. Between these dates, a total of

16

13 observations were conducted. These observations consisted of two neurosurgery cases, seven

orthopedics cases, three urology cases within nine ORs and performed by 10 different surgeons.

The team conducted observations in different times of the day to better investigate the effect of

time of day on the turnover. Additional interviews were conducted during the time frames that

the team members went in the UHOR. These interviews mostly aimed at getting more insight on

aspects of the turnover that the staff believes cause extended turnover periods. They also asked

questions to determine what can be improved and what is already being done well.

Figure 3: Observation Form

Time Studies

The team has created an observation form (Figure 3) to record the time of the sub processes that

occur during turnover. The team used a stopwatch and recorded the timestamps stated on the

observation form. A total of 13 times studies were conducted concurrently with the observations.

The time studies provided the team with data to evaluate what is value added and non value

added time for the completion of turnovers as well as the time data about each step to use in the

value stream maps for creating sub-processes.

Data Analysis Methods

In order to analyze the data collected in the time studies, the student team developed a swim lane

analysis.

17

Swim Lane Analysis

The team classified the following processes in the turnover process as “Simultaneous Process”:

● PT cleaning

● Circulating nurse leaving for the front desk and coming back

● Anesthesia coming in and preparing the lines

● Scrub setting up for the next case and counting

In order to account for these processes, the team used a swim lane analysis (Figure 4, Appendix

D).

Figure 4: Swim Lane Analysis

The first lane, titled “OR Timeline,” explains the timeline of all the events explained taking

places from t = 0 until all the above listed processes end. The following lanes explain one by one

what each individual role does as well as the average start and end time of all of their

corresponding steps. The average start and end times for these processes are calculated from the

time studies that the team conducted. After calculating the average start and average end times

for each role in the OR, all of the role lanes were incorporated in the timeline of the overall

simultaneous process. To calculate the average amount of time that the simultaneous process, the

team used the difference of the earliest average start time and latest average end time among all

the individual roles. The earliest average start time was that of PT, which started at t = 1:34 and

the lates average end time was that of scrub, which ended at t = 36:38. The difference between

these values assigns the simultaneous process an average time of 2104 seconds in total, which

18

translates to 35 minutes and 6 seconds. The following table (Table 1) presents the average start

and average end time for all roles as well as the amount of time each takes.

Table 1: Swim Lane Calculations

One thing to note here is that, the data suggests that the time anesthesia takes is more that the

time the scrub takes, which contradicts our observations. The reason for this contradiction is that

the team’s timestamps don’t account for the time that anesthesiologist leaves the room to grab

certain items. In other words, the data doesn’t account for the travel time or idle time for the

anesthesiologist.

Findings and Conclusions

The findings from the team’s data collection methods, interviews, historical data, observations,

and time studies, led the student team to come up with the following conclusions. These

conclusions in turn shaped the team’s final recommendations. This section describes the

conclusions that the team determined and used from each data collection method. A summary of

the significant and insignificant factors found through the data collection and analysis can be

found in Appendix E.

Interviews

Through the interviews conducted with pod supervisors and the PT supervisor, the team was able

to gain a better understanding of the roles of the circulators and the PT’s. The role of the

circulator was defined to be the person in charge of the care of the patient. The circulator will

page for the PT’s to start cleaning the room right after the patient leaves the room. The circulator

will then take the papers regarding the patient up to the front desk and check on the next patient

in pre-op to ensure they are ready for surgery. The nurse will then come back into the room and

help the scrub tech open and count instruments. When the setup is complete, the circulator will

call room ready for the next patient to be brought into the room. The PT’s are responsible for the

clean up of the room. They mop the floors, wipe down the surfaces, and make the beds during

turnover time. Outside of turnover time, they also have multiple tasks such as picking for cases,

running for blood, and other various tasks needed to be done. The circulating nurses gave their

perspective on what caused a longer turnover time such as patient unreadiness and PT’s not

arriving when they are paged. The PT supervisor also input their perspective of all the tasks and

19

roles that the PT have to balance in addition to cleaning rooms during turnover which gave a

more holistic view of the job role.

Historical Data Analysis

Historical data from July 2015 until October 2019 was thoroughly analyzed and provided the

team with insight on what turnover times generally were, which factors affected turnover, and

the current state of turnover.

Calculating Turnover

The data was filtered for the past year, October 2018 - October 2019, based on day of week,

scheduled vs non scheduled surgery which excludes any emergency or last minute cases that may

affect turnover.

Using the filtered data turnover was calculated based on if the next case is in the same OR, is on

the same date, is in the service area. The team also calculated an additional turnover based on if

it was the same surgeon. After calculating the turnover team team calculated additional time

stamps to create a baseline comparison to the data collected in OR’s. This includes Room Ready

to Patient In, Prep Time, Start Hour and Level of Procedure to follow and is displayed in table 2

below.

Table 2: Turnover Calculation Table

ASA Score

American Society of Anesthesiologists (ASA) is a Patient Score Grading system for preoperative

health of the surgical patients. The team analysed the correlation between ASA and turnover to

check if there was any link between how sick the patient is to turnover as it might affect how

complicated the setup for the case would be. Using the turnover calculated the data was filtered

for each ASA score and various data points outlined in the table below (Table 3) was calculated.

20

Table 3: ASA Score Turnover Data

Figure 5: ASA Score Box Plot

Source: UHOR Mychart and Tableau Dashboard

Collection Period: 365 days

Sample size: 6,458 cases

As per the box plot in figure 5 the team concluded that the ASA score was not significant to

turnover hence when creating the OR observation form it was not recorded.

Time of Day

The team analyzed data on various time of the day, as seen in table 4 below, since anecdotally a

concern that was conveyed during interviews was that turnover increases around shift change

time and process becomes slower. This was brought up by several Pod Supervisors from all pods

and from the PT supervisor too. The shift change time is around 14:00-15:00.

21

Table 4: Time of Day Turnover Data

Figure 6: Time of Day Box Plot

Source: UHOR Mychart and Tableau Dashboard

Collection Period: 365 days

Sample size: 6,382 cases

The data from table 4 suggests that turnover is lowest during the first case of the day since a lot

of the preparation can be done before hand, however during shift change unlike the anecdotal

hypothesis turnover actually decreases. Figure 6 can be used by the Nursing Services Director to

disprove this claim. The source of the data is the historical OR data file provided by the

coordinators and the sample size was 6,382 cases.

Procedure level of Case to Follow

The procedure level is a linear scale from 1 to 7 that is allocated to each case depending on the

number of trays and the complexity of the case. In order to look at the correlation between

turnover and this procedure level, the team first extracted what the procedure level of the case to

follow is as the turnover is dependent on the setup of the next case. In order to conduct further

analysis the team also looked into the difference between the turnovers with same service and

turnover with the same surgeon.

22

Table 5: Procedure Level Turnover Data For Same Service

Figure 7: Procedure Level Service Turnover Data Error Band Line Graph

Source: UHOR MiChart and Tableau Dashboard

Collection Period: 365 days

Sample size: 3,077 cases

The shaded band region shows the bounds of the first quartile and third quartile. The data shows

that there is no significant correlation between the level of the procedure and turnover and the

dip in the turnover in level 4 in Figure 7 is due to the larger sample size which allows more

instances to be taken into account and cause variability.

Table 6: Procedure Level Turnover Data For Same Surgeon

23

Figure 8: Procedure Level Surgeon Turnover Data Error Band Line Graph

Source: UHOR MiChart and Tableau Dashboard

Collection Period: 365 days

Sample size: 2,674 cases

Similarly Figure 8 shows a similar analysis on the data set of turnover with the same surgeon.

The team looked into this to see if there were any significant differences between the two

correlations, however the correlations were similar to the turnover times in Figure 7.

Observations

During observations, there were several qualitative aspects of the turnover process that were

observed. Many of the subprocesses happened simultaneously such as the PT cleaning,

circulators bringing paperwork from the previous patient to the front desk and checking on the

next patient, and anaesthesia preparing their lines. These simultaneous processes happened

during the same time frame without much room for improvement. The team also observed that

the amount of clean up that was done prior to the PT’s arriving also varied which impacted the

turnover time. If the instruments were not all packed away and the trash was not prepared, there

was a delay in paging for the PT, thus delaying the entire process. Once the PT’s were paged

they arrived relatively quickly. When the PT’s arrived, there was little variation in the amount of

time it took to clean up the room. The more PT’s that arrived, the faster the room was turned

over. However, it was observed that with the limited number of tasks to clean the room, wiping

down surfaces, mopping the floor, and making the bed, three PT’s performed the most efficiently

in turning over the room. The scrubs took the longest amount of time in the turnover process in

opening and counting the instruments. Circulators helped the scrubs open and count, expediting

the process. Circulators had varying ideas about when to page for “room ready.” It was also

24

observed that sometimes the turnover time was inevitably delayed due to various reasons such as

surgeon unavailability, patient unpreparedness, pre-op miscommunications, and PT shortages.

Time Studies

Table 7: Time Studies Data

Through the time studies, the team was able to calculate the

average time it took to complete each subprocess within the

turnover process. The PT’s arrive to the rooms quickly

after being paged, 1 minute 33 seconds after patient leaves

on average. The PT arrival times for each of the

departments that were observed were as follows: 55

seconds for orthopedics, 1 minute 46 seconds for urology,

and 2 minute 20 seconds for neurosurgery. The PT’s took

an average of 10 minutes 17 seconds to clean each room.

Anaesthesia did not have a large influence on turnover

time. The circulator only impacted the turnover time when

they were not back in the room prior to the scrubbing

process beginning to help count instruments. The scrubbing

process was the most time consuming, on average it took

20 minutes 51 seconds to open and count all the trays.

Once room ready was called, it took an average of 8

minutes 31 seconds for anaesthesia to bring the patient into

the room. Table 7 outlines the average time and variance

for all the time studies data points the team recorded. The

source of the data in Table 7 is the observations that the

team conducted. The sample size is 13 cases, with a

breakdown of 7 orthopedics cases, 3 urology cases and 3

neurosurgery cases.

Current State Flow Chart

After conducting observations and time studies, the team used the data to develop a detailed

current state map showing each step of the turnover process (Figure 9, Appendix F) . The overall

value added time of 35 minutes and 6 seconds and non value added time of 6 minutes were

clearly indicated on the current state map. The ratio signifies the percentage of value added time

over the entire turnover time. Through this, the team found out that almost 85.4% of the turnover

process is value added and there is room for improvement for the 14.6% of non value added

time. This non-value added time consists of the 93 seconds wasted between the patient exiting

the OR and the PT entering as well 267 seconds of wasted time between the simultaneous

25

process and the next patient entering. One of the reasons for the waste of 267 second is that there

is not a standard time set within the OR. When conducting the time studies, the team found out

that calling room ready is very subjective and depends a lot on how experienced the nurse is.

Since there is not a standard to call room ready, the data had a lot of variation within which

resulted in such a big waste. Another major factor that plays into 267 seconds is that there is a

travel time for the patient from pre-op to the OR.

Figure 9: UHOR Turnover Process Current State Map

Alternatives Considered

After evaluating the results from the conclusions, the team came up with several different

recommendations that could be implemented to standardize turnover time. These alternatives

fulfilled the recommendations, constraints, and standards that were listed earlier in the paper.

Criteria for Evaluation

The criteria for evaluation follow the objectives of the project. The design should be able to

compare against other similar institutions, define team roles and responsibilities, get the roles

and tasks approved by the staff, and minimize non value added time.

26

Decision matrix

The team used a Pugh decision matrix as seen in Appendix G to evaluate the design alternatives

the team came up with. The alternatives are compared by being scored against the design criteria

that is assigned a weight based on importance. As seen in the Pugh matrix, the clear

communication of roles and expectations performed significantly better than the other

alternatives. This is primarily due to the fact that the criteria of minimizing non value added time

was weighed the most. The clear communication of expectations would enable the circulators,

PT’s, surgeons, and anaesthesia to complete their tasks in a timely manner and cooperate in order

to achieve the expected time.

Recommendations

After reviewing the findings and conclusions from historical data, interviews, observations, time

studies, the team developed three recommendations: (1) establish a set standard for turnover

time, (2) establishing a standard for “room ready” time and (3) clearly communicate expectations

for all parties (nurses, PT’s, scrubs, etc)

Standard turnover time

From analysis of the literature search, historical data, and time studies it is recommended to set

an average turnover time across the departments to be 40 minutes. More specifically, it would be

recommended to have a different turnover times for each department. The turnover time should

be 30 minutes for urology, 40 minutes for orthopedics, and 45 minutes for neurosurgery. This is

due to the varying tray counts and complexities of the surgeries that affect turnover time.

Standard “room ready” time

Room ready is currently defined as the time that everything in the room is set up and ready for

the patient to arrive. Throughout the course of interviews and observations, it became clear that

many of the circulators had different ideas of when to call room ready. Calling room ready in the

system triggers a pager for anesthesia to bring the patient to the room. However, bringing the

patient to the room takes 8 - 10 minutes as found in the time studies. If room ready is called

when everything is completely set up, the staff in the room were standing and waiting until the

patient was brought back into the room. Therefore, the team recommends that the room ready is

redefined to be 10 minutes prior to the room being set up. Standardizing this expectation across

all of ORs will allow the setup process to be finished concurrently with the patient transportation

to the OR.

Clear communication of expectations

During the interviews and observations, it became clear that different members of the staff had

different expectations of what the turnover time should be and how clearly the roles were

27

defined. The team decided to establish a set turnover time as seen above and clearly

communicate all duty expectations to all members of the staff. The team recommends for the

circulators to have all of the trash ready to leave the room and for the scrubs should have all their

trays packed up while the patient is getting ready to leave or in the process of waking up in the

OR. This allows for the PT’s to be paged immediately after the patient leaves the room, thus

reducing turnover time. If possible, three PT’s should be used in neurosurgery and orthopedic

cases in order to further reduce the turnover time. The nurses in pre-op should ensure all patient

consent is obtained, all the tests are done, and all the drugs are administered in a timely manner

prior to their surgery. This will prevent delays in calling for room ready due to patient

unpreparedness. Newer CRNAs and anesthesia technicians should start in urology rooms

because the lower likelihood of raising turnover times.

Expected Impact

The recommendations about standardizing turnover time, room ready time, and expectations of

the staff are expected to create clarity in the OR about what a successful turnover looks like. This

clarity about how long a turnover should take, when room ready should be pressed, and what

each person’s role is will help reduce turnover time by providing clear expectations of the

process.

Impact of standardizing turnover time

There is currently no clear expectation that communicates to employees in the OR about what an

acceptable turnover time is. By setting a standard for how long a turnover should take for each

service, the hospital employees involved in the turnover process now have a goal to meet. The

impact of this recommendation is expected to be large, as scrubs, circulators, and PT’s can work

together to reach a clearly defined and attainable goal.

Impact of standardizing “room ready” time

Setting a standard for when the circulator should press room ready during the turnover process is

also expected to have a large impact on turnover time. There is currently varying practices as to

when the nurse presses room ready, which can create a delay in the daily schedule. If it is pressed

too early, the room will not be completely ready when the patient arrives. If it is pressed too late,

then time is wasted because the following patient could have been in the room earlier. Setting the

standard that room ready should be pressed 10 minutes before the room is completely set up for

the following patient will reduce wait time as well as premature entry of patients.

Impact of clearly communicating expectations

The team expects that clearly communicating to each member of the staff about their duties in

the turnover process will improve turnover time. Setting up a clear standard would allow the staff

28

to help each other and work together to achieve their goals rather than waiting in the room after

their roles and tasks are finished.

Recommendations for Future Work

Because the student team was limited in time and scope, there are several recommendations for

future work done on OR turnover times. It is recommended that a future team look deeper into

the simultaneous processes that were outlined in this project. Within the simultaneous process,

there are several opportunities to look into reducing non-value added time within the different

jobs roles: anesthesia, circulators, PT’s, and scrubs. Another recommendation is to look more

into each of the roles present inside and outside the OR. It would be useful to determine what

other responsibilities anesthesia, circulators, and PT’s have outside of the OR in order to gain a

more wholistic view of their work. In addition, it would be helpful to gather more insight into the

roles and processes within pre-op and post-anesthesia care unit (PACU) which sometimes cause

delays in turnover. Another area look into is regarding the recommendation that the team made

to prepare for turnover by having all of the trash ready to leave the room and all the trays packed

up while the previous patient is getting ready to leave the room. It would be helpful to look into

the feasibility of standardizing this process.

29

References

[1] Fountain, Andrew, Kellman, Kimberly, Pitawanakwat, Colin, Zebus, Kathryn, “Utilizing

Garbology to Analyze Discrepancies between Planned, Documented, and Trashed Surgical

Supplies in Hospital Operating Rooms”, IOE 481, pp. 5-6, 2017.

[2] Mazzei, William J, “Operating room start times and turnover times in a university hospital,”

Journal of Clinical Anesthesia, vol. 6, no. 5, pp. 405–408, 1994.

[3] Cerfolio, Robert J., et al. "Improving operating room turnover time in a New York City

Academic Hospital via Lean." The Annals of thoracic surgery 107.4 (2019): 1011-1016.

30

Appendix A: Road to 30 - Room Turnover Operating Room Efficiency Poster

31

Appendix B: Requirements, Constraints, and Standards Matrix

Entry # 1 2 3 4

Requirements R-A.

Organizational

Policy

N.A.

R-B. Ethical N.A.

R-C. Health &

Safety

N.A.

R-D. Economic N.A.

R-E.

Implementability

(R-E-1) (R-E-2)

R-F. User

Acceptance

(R-F-1)

R-G. Patient

Acceptance

N.A.

R-H. Task

Duration

(R-H-1)

Entry # 1 2 3 4

Constraints C-A.

Organizational

Policy

N.A.

C-B. Ethical N.A.

C-C. Health &

Safety

N.A.

32

C-D. Economic (C-D-1)

C-E.

Implementability

(C-E-1)

C-F. User

Acceptance

N.A.

C-G. Patient

Acceptance

N.A.

C-H. Task

Duration

(C-H-1)

Entry # 1 2 3 4

Standards S-1. HIPAA (S-1-1)

S-2.

Organization's

Std.

N.A.

S-3. Best Practice N.A.

S-4. ASTM N.A.

S-5. Code N.A.

Standards that are

not applicable

ANSI NIOSH OSHA ASE

33

Appendix C: OR Observation Form

34

Appendix D: Swim Lane

35

Appendix E: Significant and Insignificant Factors

Significant Factors Insignificant Factors

Surgeon presence ASA score

Preparation before the patient exits Time of day

Number of PTs Procedure level

Scrub opening for next case Anesthesia

When room ready is called PT arrival time

Pre-Op activities

Service type

36

Appendix F: Current State Map

37

Appendix G: Pugh Decision Matrix

Criteria Weight Current State

of UHOR

Establish a

set standard

for “room

ready” time

Schedule in

additional

time for more

complex

cases

Clearly

communicate

expectations

for all parties

Benchmark

against other

similar

institutions

1.0 0 0 -1 0

Define team

roles and

responsibilities

2.0 0 +1 +1 +1

Clear roles and

tasks approved

by staff

2.0 0 +1 +1 +1

Minimize non

value added

time

3.0 0 -1 -1 +1

Total 0 +1 0 +7