24
Unit Commitment and Dispatch 12/06/2016 PJM©2016

Unit Commitment and Dispatch - PJM

  • Upload
    others

  • View
    34

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Unit Commitment and Dispatch - PJM

Unit Commitment and Dispatch

12/06/2016 PJM©2016

Page 2: Unit Commitment and Dispatch - PJM

Objectives

• Describe security constrained unit commitment

• Describe security constrained economic dispatch

12/06/2016 PJM©2016 2

Page 3: Unit Commitment and Dispatch - PJM

“The operation of generation facilities to produce energy at the lowest cost to reliably serve consumers,

recognizing any operational limits of generation and transmission facilities”

Source: September 30, 2005 order, p14

SCUC and SCED - FERC Definition

Sounds like an optimization problem!

12/06/2016 PJM©2016 3

Page 4: Unit Commitment and Dispatch - PJM

• Unit Commitment is the process of turning on (committing) resources to meet load and other market requirements

• Security-Constrained Unit Commitment (SCUC) commits units while respecting limitations of the transmission system and unit operating characteristics

Security Constrained Unit Commitment

12/06/2016 PJM©2016 4

Page 5: Unit Commitment and Dispatch - PJM

Offers Received from Generators

25MW @ $15

40MW @$5

15MW @$25

10MW @$30

20MW @$10

12/06/2016 PJM©2016 5

Page 6: Unit Commitment and Dispatch - PJM

Supply Dispatched to Meet Demand RTO Load (MW)

70000

80000

90000

100000

110000

120000

130000

140000

150000Ti

me

(EP

T)

0:39

1:19

1:59

2:39

3:19

3:59

4:39

5:19

5:59

6:39

7:19

7:59

8:39

9:19

9:59

10:3

9

11:1

9

11:5

9

12:3

9

13:1

9

13:5

9

14:3

9

15:1

9

15:5

9

16:3

9

17:1

9

17:5

9

18:3

9

19:1

9

19:5

9

20:3

9

21:1

9

21:5

9

22:3

9

23:1

9

$5

$10 $15

$20

$25 $30

$35 $40

$45

$10 $5

$50

Load (MW)

Offers Sorted in Increasing Order

12/06/2016 PJM©2016 6

Page 7: Unit Commitment and Dispatch - PJM

Gen1: 200MW @ $50

Gen2: 300MW @ $30

Gen3: 400MW @ $80

Gen4: 200MW @ $10

Gen5: 100MW @ $40

Unit Commitment Example

In an unconstrained system, units are committed in simple economic order:

Gen4 – Gen2 – Gen5 – Gen1 – Gen3

12/06/2016 PJM©2016 7

Page 8: Unit Commitment and Dispatch - PJM

SCUC - Example

Limit = 400MW

Gen1: 200MW @ $50 Gen2: 300MW @ $30 Gen3: 400MW @ $80 Gen4: 200MW @ $10 Gen5: 100MW @ $40

Load = 200MW Load = 600MW

G3 G1

G2

G4

G5

200 MW

300 MW

200 MW

100 MW

600 MW FLOW

Area 1 Area 2

12/06/2016 PJM©2016 8

Page 9: Unit Commitment and Dispatch - PJM

SCUC - Example

Area 1 Area 2

Limit = 400MW

Load = 200MW Load = 600MW

G3 G1

G2

G4

G5

300 MW

200 MW

100 MW

200 MW

Gen1: 200MW @ $50 Gen2: 300MW @ $30 Gen3: 400MW @ $80 Gen4: 200MW @ $10 Gen5: 100MW @ $40

400 MW FLOW

12/06/2016 PJM©2016 9

Page 10: Unit Commitment and Dispatch - PJM

• SCED follows unit commitment and determines the level at which each committed resource should be operated

‒ Hourly solution interval in DA

‒ 5 minute solution interval in RT

Security Constrained Economic Dispatch (SCED)

12/06/2016 PJM©2016 10

Page 11: Unit Commitment and Dispatch - PJM

• SCED, like SCUC, enforces the “security” aspects of the transmission grid

• SCED must also consider operational limitations of generating plants, which may be different than limitations in SCUC

‒ Ramp limitations are important

‒ Start-up costs no longer a factor

Security Constrained Economic Dispatch (SCED)

12/06/2016 PJM©2016 11

Page 12: Unit Commitment and Dispatch - PJM

Generation Dispatch

Generation is economically dispatched to meet the

demand across the entire RTO at the lowest cost

12/06/2016 PJM©2016 12

Page 13: Unit Commitment and Dispatch - PJM

Which function is performed respecting limitations of the transmission system and unit operating characteristics?

1. Unit Commitment

2. Security Constrained Unit Commitment

3. Economic Dispatch

4. Weather forecasting

12/06/2016 PJM©2016 13

Page 14: Unit Commitment and Dispatch - PJM

Which function follows unit commitment and determines the level at which each committed resource should be operated?

1. FTR Market

2. RPM Auction

3. Lunch Break

4. Security Constrained Economic Dispatch

12/06/2016 PJM©2016 14

Page 15: Unit Commitment and Dispatch - PJM

SCUC and SCED with Operating Parameters

12/06/2016 PJM©2016 15

• SCUC and SCED become extremely complex with the addition of operating parameters

• Resources that may, on the surface, appear to be attractive to the optimization may contribute significantly to total bid production cost

• Optimization software may need to test several different scenarios to determine the least cost solution and still reliably meet demand

Page 16: Unit Commitment and Dispatch - PJM

SCUC - Advanced Example

Area 1 Area 2

Limit = 400MW

Gen1: 200MW @ $50, SU=$1,000 Gen2: 300MW @ $30, SU=$1,000 Gen3: 400MW @ $80, SU=$6,000 Gen4: 200MW @ $10, SU=$10,000 Gen5: 100MW @ $40, SU=$1,000

Load = 200MW Load = 600MW

G3 G1

G2

G4

G5

12/06/2016 PJM©2016 16

Page 17: Unit Commitment and Dispatch - PJM

• We know from the earlier example that Gen3 must be on-line to serve load in the congested area

• The question becomes which Area 1 units to commit to serve up to 600MW demand (200 local + 400 transfer)

‒ Will now need to consider start-up costs as part of the total production cost

SCUC - Advanced Example

12/06/2016 PJM©2016 17

Page 18: Unit Commitment and Dispatch - PJM

SCUC - Advanced Example

Total Production Cost = $48,000 Area 1 Area 2

Limit = 400MW

Gen1: 200MW @ $50, SU=$1,000 Gen2: 300MW @ $30, SU=$1,000 Gen3: 400MW @ $80, SU=$6,000 Gen4: 200MW @ $10, SU=$10,000 Gen5: 100MW @ $40, SU=$1,000

Load = 200MW Load = 600MW

G3 G1

G2

G4

G5

12/06/2016 PJM©2016 18

Page 19: Unit Commitment and Dispatch - PJM

• Note that you will only end up dispatching Gen3 for 200MW of its 400MW available

• Would it be cheaper to use all 400MW from Gen3 and only transfer 200MW instead of 400MW?

SCUC/SCED - Advanced Example

Resource MW $/MWh Startup BPC

Gen5 100 40 1,000$ $5,000

Gen2 300 30 1,000$ $10,000

Gen1 200 50 1,000$ $11,000

Gen4 0 10 -$ $0

Gen3 200 80 6,000$ $22,000

$48,000

As it stands now….. Gen1 ($11,000) + Gen2 ($10,000) + Gen5 ($5,000) + Gen3 for 200MW ($22,000) = $48,000

Alt Option 1: All energy from Gen2/Gen5/Gen3 = $53,000 Alt Option 2: Gen1/Gen5/partial Gen2/full Gen3 = $58,000

12/06/2016 PJM©2016 19

Page 20: Unit Commitment and Dispatch - PJM

Limit = 300MW

Gen1: 400MW @ $40, SU=$10,000 Gen2: 500MW @ $50, SU=$7,000 Gen3: 300MW @ $100, SU=$2,000 Gen4: 200MW @ $20, SU=$5,000 Gen5: 200MW @ $60, SU=$3,000 Gen6: 200MW @ $90, SU=$6,000

Load = 500MW Load = 500MW

G3 G1

G2

G4

G5 G6

Area 1 Area 2

SCUC/SCED - Class Exercise Determine the units that will serve the demand, minimizing production cost and considering the constraint (assume all gens are dispatchable)

12/06/2016 PJM©2016 20

Page 21: Unit Commitment and Dispatch - PJM

SCED - Advanced Exercise

12/06/2016 PJM©2016 21

• Problem: There is an increase in demand of 100MW from one hour to the next

• The generators on the next slide have to serve that additional load, but some have restrictions

• What units can fully serve the additional 100MW?

• What units will the optimization select?

Page 22: Unit Commitment and Dispatch - PJM

Generator Status Available MW Cost Ramp Rate

Gen1 On 100 $50 5 MW/Min

Gen2 On 100 $30 1 MW/Min

Gen3 Unavailable 300 $25 3 MW/Min

Gen4 On 100 $40 3 MW/Min

SCED - Advanced Exercise

12/06/2016 PJM©2016 22

Page 23: Unit Commitment and Dispatch - PJM

SCUC/SCED Exercise Comments

12/06/2016 PJM©2016 23

• This was a difficult exercise that shows the complexity of SCUC and SCED and the reason why software calculations may be time consuming

• This exercise may also help demonstrate why some generators may or may not have been committed

• Complexity increases with additional parameters, transmission limits, generators, etc.

Page 24: Unit Commitment and Dispatch - PJM

Questions?

12/06/2016 PJM©2016 24