UNIT 5-Group Project-Lecture Note

Embed Size (px)

Citation preview

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    1/77

    Unit 5: Group Project

    Allocated Learning hours: 45

    CIVIL ENGINEERING BATCH - 02(FULL TIME) 3RD SEMESTER

    Dr. Lalith Rajapakse/Dr. Lesly Ekanayake

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    2/77

    1.0 Introduction

    1.1 What is a PROJECT ?

    Task vs. Project: A task is an activity that needs to be accomplished within a defined period

    of time. Usually a project consists of a series of tasks or activities which are summarized in its

    work breakdown structure (WBS).

    1.1.1 Definit ion of a Project ? (There could be many!) Sequence of tasks

    Planned from beginning to end

    Bounded by time, resources, & required results

    Defined outcome and "deliverables"

    Deadline Budget

    Limits number of people, supplies, and capital

    1.1.2 Main Features of a Project Defined beginning, end, schedule, and approach

    Use resources specifically allocated to the work

    End results have specific goals (time, cost, performance/quality)

    Follows planned, organized approach

    Usually involves a team of people (Humans are social animals!!!)

    1.1.3 Resources (and Constraints)

    Time

    People

    Money

    Equipment

    Facilities

    2

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    3/77

    1.1 What is a PROJECT ? Contd.

    1.1.4 What Makes a Project Successful

    Organized, well planned approach Project Team Commitment (comes from individual commitment)

    Balance among

    Time

    Resources

    Results

    Customer Satisfaction

    1.1.5 Phases of a Project in General Conceptualization

    Feasibility

    Preliminary planning

    Detailed planning

    Construction/Execution Monitoring/Testing

    Closing/Termination

    3

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    4/77

    1.2 What is a PROJECT ? Examples

    What kind of Projects we are talking about? Just an example

    4

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    5/77

    What kind of Projects we are talking about? Another example

    1.2 What is a PROJECT ? Examples

    5

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    6/77

    UNIT 5: Group Project - Introduction

    1.3 Study Outline

    One of the SIX core

    subjects offered

    6

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    7/77

    UNIT 5: Group Project - Introduction

    7

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    8/77

    UNIT 5: Group Project Summary of Learning Outcomes

    8

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    9/77

    UNIT 5: Group Project Expected outcome & Assessment criteria

    9

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    10/77

    UNIT 5: Group Project Extent of the study, specs & procedures

    10

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    11/77

    UNIT 5: Group Project Extent of the study, specs & procedures

    11

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    12/77

    UNIT 5: Group Project Extent of the study, specs & procedures

    12

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    13/77

    UNIT 5: Group Project Links with other modules

    13

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    14/77

    UNIT 5: Group Project Links with other modules

    14

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    15/77

    UNIT 5: Group Project Links with other modules

    15

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    16/77

    UNIT 5: Group Project Higher Level Skills

    16

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    17/77

    UNIT 5: Group Project Implementation

    1.4 Study Approach

    1.4.1 Implementation

    The class will be divided into two working groups (companies) and team leaderswill be appointed.

    The over all project scope will be defined in a TOR.

    The leaderof each group is responsible for the overall project management.

    The main project should be divided into several manageable sub-tasks in

    preparing the work breakdown structure (WBS). Each member (engineer)should be assigned one of the (6~10) sub tasks depending on the

    expertise/minor taken and the optional subjects taken. However, each engineer

    is expected to know the work performed by all the other members of the group.

    Suitable deadlines will be set for achieving the targets.

    Engineers are encouraged to have group discussions to facilitate knowledgedissemination.

    Group leader (or an appointee) should maintain a project log book. Each

    engineer should maintain a daily diary for project related activities. These two

    documentations indicating actual work progress should be updated regularly

    and available for inspection at any given time.

    17

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    18/77

    UNIT 5: Group Project Implementation

    1.4 Study Approach

    1.4.2 Assessment

    The assessment will be based on the following criteria: one assignment and twopresentations requiring submission of reports as well.

    Assignment 01 will carry 10 marks.

    Each company will be given marks out of 25 on the basis of interim report and final

    report. Interim report will be assigned 10 marks. Final report will be assigned further15

    marks.

    Together with the final report, each member should submit a neat handwritten report on

    the tasks performed including a self assessment on the contribution to achieving and

    completing the project targets. Therefore, each member will be able to obtain marks for

    the individual contribution. It will be assigned marks out of20.

    18

    There will be TWO presentations. Interim and final

    presentations will be assigned 10 and 15 marksrespectively.

    A viva will be conducted on individual basis. The

    questions will/could be from the tasks performed

    by the other members of the group. The marks will

    be assigned out of20 forindividual viva.

    Assignment 01 10 marks

    Interim report 10 marks

    Interim presentation 10 marks

    Final report 15 marks

    Final presentation 15 marks

    Individial contribution/report 20 marks

    Individual viva 20 marks

    100 marks

    Summary

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    19/77

    UNIT 5: Group Project Implementation

    1.4 Study Approach

    1.4.3 Assessment scheme (The following target dates should be noted)

    Assignment 01: Handover 04/05/2010; Due date 18/05/2010 (10 marks)Assignment 02: First presentation -27th June, 2011. Each project should have a

    fifty minute power point presentation backed by transparencies if necessary. Each

    presenter will be allocated 5 minutes to explain the contribution. Four marks will

    be allocated to the presentation skills and six for the contents. (10 marks)

    Completion and submission of interim group report (typed) on 27

    th

    June, 2011. (10marks; common to all members in the group)

    Assignment 03: Second presentation -10thAugust, 2011. Each presenter will be

    allocated 8 minutes of a single power point presentation on the overall project.

    Five marks will be allocated for the presentation skills and ten for the contents.

    (15 marks)

    Completion and submission of final group report (typed) on 24thAugust, 2011.(15 marks; common to all members in the group)

    Completion and submission ofhandwritten individual report on 24thAugust 2011.

    Five marks for the presentation and fifteen for the contents. (20 marks)

    Viva for students -xxth August, 2011. Five marks will be allocated to the

    presentation skills and fifteen for the demonstration of knowledge. (20 marks)19

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    20/77

    UNIT 5: Group Project More Information

    More information on Group Project

    Group project is a part of six core modules. The aim is to provide an opportunity for

    the students to participate in real life projects in a competitive atmosphere similar to

    that prevails in the industry. It also intends to provide experience in utilizing the

    theory; design and practice learned so far forreal engineering applications.

    Therefore, it is expected that each engineer will take GP seriously and make a

    noteworthy contribution to the successful completion of the project.

    In order to ensure that each engineer will get a good grasp of the whole project, the

    question times after the presentation can be from any task related to the whole

    project, but not necessarily from the actual task performed by the engineer. It is also

    expected that each engineer will try their best to improve the accuracy of the data,

    design information, computer modeling, etc., so that it will be possible to use the

    tender documents for the selection of probable contractors. Staff will also assist asmuch as possible in improving the accuracy of the information.

    1.5 More Information

    Finally, this is not a taught course; rather, it is a series of

    practical learning activities - usually simulated by team

    working exercises and self-learning activities. Some

    teaching may be offered to support your progress anddevelop your underpinning knowledge. 20

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    21/7721

    Tasks

    TOR - Your Group/Company is assigned with the task of design and construction of a

    Housing/Shopping Complex and its surrounding facilities, which includes various

    functional spaces of multipurpose nature with leisure/recreational/amusement activities

    and all related services, access roads, parking needs etc.

    Pay particular attention to the site location and your Company is expected to come up with

    creative designs maximizing the space utilization and use of building materials and

    methods that will assist in minimizing the carbon foot print (promoting eco-friendly and

    green design concepts).

    1.

    Conceptualization - Define the project scope and list out all main functional

    areas/facilities intended for the development envisaged. (P1.1, P1.2)

    2.

    Itemization - Prepare the main work/project breakdown structure with all main

    targets/tasks, identify main project constraints and examine for financial feasibility and

    constructability criteria. (P1.2, P1.3)

    3.

    Develop approach for EIA/IEE for the project and carry out a detailed study on LEED

    (USGBC) specification and guidelines and propose creative methods for greater degree

    of sustainability to address eco- environmental concerns. (P1.3)

    4. Explain your individual contribution to the ongoing project work and attach a copy of

    project log book and your daily diary of project-related activities. (P2.4)

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    22/77

    1.6 UNIT 5: Group Project - Session Plan (*tentative)

    Last years schedule; Need updating

    * Refer to 1.4.3 Assessment scheme for important dates

    22

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    23/77

    1.7 UNIT 5: Group Project Activity Breakdown (*tentative)

    * Refer to 1.4.3 Assessment scheme for important dates 23

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    24/77

    More about Learning outcomes

    24

    1.8 UNIT 5: Group Project Extras

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    25/77

    25

    More about Learning outcomes

    1.8 UNIT 5: Group Project Extras

    2 0 C t li ti O tli & S ti M t i l

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    26/77

    2.0 Conceptualization: Outline & Supporting Materials

    Summary

    2.0 Conceptualization: Outline & Supporting Materials

    2.1 Brief introduction to Project Life Cycle

    2.1.1 Project Life Cycle - Project Cycle Management

    2.1.2 Main Phases of PLC

    2.1.3 Detailed steps of Project Life Cycle

    2.1.4 Work Breakdown Structure (WBS)

    2.1.5 Detailed steps (more applicable to construction projects and Group Project)

    2.2 Stages or Phases of a Project

    2.2.1 Concept stage: Importance of proper conceptualization

    2.2.2 Concept stage: Funnel of innovation and Risk of failure

    2.3 Project Feasibi lity Study

    2.3.1 What is a Project feasibility study

    2.3.2 Analysis of Economic/Financial Feasibility

    2.3.3 How to evaluate Financial Feasibility: Profitability Indicators and Cash Flow Concept

    2.3.4 Environmental Feasibility (EIA/IEE)

    2.3.5 EIA/IEE Process in Sri Lanka

    2.3.6 Steps and Contents of an EIA/IEE

    2.3.7 Schedule Feasibility; Project Time Management & Planning2.3.8 Why Do Projects Fail ? 26

    2 1 B i f i t d t i t P j t Lif C l

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    27/77

    The Project Life Cycle refers to a logical

    sequence of activities to accomplish the

    projects goals or objectives. Regardless

    of scope or complexity, any project goes

    through a series of stages during its life.

    Source: MPMM

    www.mpmm.com/project-management-methodology.php 27

    2.1 Brief introduction to Project Life Cycle

    2.1.1 Project Li fe Cycle - Project Cycle Management

    There is first an Initiation or Birth phase,in which the outputs and critical success

    factors are defined, followed by a

    Planning phase, characterized by

    breaking down the project into smaller

    parts/tasks, an Execution phase, in

    which the project plan is executed, andlastly a Closure or Exit phase, that

    marks the completion of the project.

    2.1.2 Main Phases of PLC

    Project Life Cycle

    2 1 B i f i t d ti t P j t Lif C l

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    28/77

    28

    2.1 Brief introduction to Project Life Cycle Contd.

    2.1.3 Detailed steps of Project Life Cycle

    2 1 B i f i t d ti t P j t Lif C l

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    29/77

    29

    2.1 Brief introduction to Project Life Cycle Contd.

    2.1.3 Detailed steps of Project Life Cycle; another example

    2 1 Brief introd ction to Project Life C cle

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    30/77

    30

    2.1 Brief introduction to Project Life Cycle Contd.

    2.1.3 Detailed steps of Project Life Cycle; another example

    Source: Euro Leisure B.V. 2000-2010

    2 1 Brief introduction to Project Life Cycle

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    31/77

    PBS

    WBS

    Work

    Product

    ActivityPlanning Package

    Planning

    Package

    Description

    What

    How

    31

    2.1 Brief introduction to Project Life Cycle Contd.

    2.1.4 Work Breakdown Structure (WBS)

    2 1 Brief introduction to Project Life Cycle

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    32/77

    1. Concept stage: This stage involves the conceptualization or the preparing a concept for developing

    the project. How large the project would be (scale and scope), what kind of functional areas facilities

    will be provided, services and other surrounding facilities (access roads, parking needs etc.) etc. are allneed to be included in the evaluation. Present your concept with adequate number of preliminary

    drawings for the proposed buildings, other structures and the internal road net work.

    2. Feasibility s tudy: Determine the feasibility of implementing the concept developed for project. Use

    social, economic, traffic, etc. data available for your study.

    3. Environmental impact assessment: Conduct an EIA or lEE for the project and suggest

    improvements to make your design more acceptable to the community.

    4. Preliminary design stage: You have to consider the following alternatives: Types of building

    facilities, number of stories for the main buildings or the maximum number of guests or customers to be

    accommodated, etc. in consultation with the lecturers in charge of Group Project.

    5. Detailed design s tage: Perform this complying with various standards used in UK/Sri Lanka while

    ensuring the constructability.

    6. Preparation of drawings: Prepare drawings using standard method of detailing.

    7. Cost study and preparation tender documents: Conduct a cost study for the project

    (Housing/Shopping Complex) to prepare the engineer's estimate and complete the tender documents

    ready to issue to the prospective bidders using lCTAD guidelines.

    32

    2.1 Brief introduction to Project Life Cycle Contd.

    2.1.5 Detailed steps (more applicable to construction projects and Group Project)

    2 2 Stages or Phases of a Project

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    33/77

    2.2 Stages or Phases of a Project

    2.2.1 Concept stage: Importance of proper conceptualization

    You need to define the project properly in order to avoid any ambiguities and deliver most viable

    solutions. Ill-defining a problem (project) can often lead to incorrect project solutions, which may be

    costly, ineffective and unconstructable.

    The project conceptualization phase is intended to give sufficient definition to a proposed project enable

    preliminary design considerations and reliable initial cost estimates for budgeting.

    In this phase, the need for the project is identified by the proponent and the scope is defined by the

    proponent and the consultants. The possible issues which may affect the project should be evaluated

    and options for overcoming any difficulties need to be developed. A site is usually identified during this

    phase of the process, if the project involves the construction of a new facility. Utility extensions and site

    improvements are usually required for a new site and the costs of these are estimated. If the project

    involves a building addition or major remodeling, limitations of the existing facility and infrastructure are

    noted, and an estimate will be made of their affect on the proposed project.

    Outcome/Product :

    A project fact sheet results from the conceptualization process.

    Contained in this brief is:

    a clear statement of the need for the project

    the scope of the project

    a summary of the issues which may influence the implementation of the project

    a preliminary budget estimate

    and a delivery schedule.

    33

    2 2 Stages or Phases of a Project

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    34/77

    2.2 Stages or Phases of a Project

    2.2.1 Concept stage: Importance of proper conceptualization

    34

    Schematic designThe schematic design (conceptual design) is the first step in translating

    the criteria and site constraints into a workable design. At this stage of

    the process, the objective is primarily to select concepts and identify

    and solve major design problems. It is basically a verification that thereare no physical constraints which will prevent meeting the production

    goals and purposes of the project.

    The schematic design stage identifies, assesses, and recommends

    design alternatives for meeting production goals. These alternatives

    should reflect the use of local construction techniques and materials

    where applicable.

    The end products of the schematic design stage will be:

    i. a written report fully describing the facility design concept,ii. a site layout, showing location of all major components on the

    site, which reflects topography and operational relationships,

    iii. floor plans for all major support buildings,

    iv. a schematic diagram of the hydraulics of all the water /services

    requirements for each production unit and facility, with elevations,

    and

    v. a topographic survey.

    Sketches are often useful to include in the schematic design report toillustrate the recommended design concepts. The schematic design

    also requires a site topographical survey to ensure that locations and

    hydraulic systems are conceptually correct. The survey should be

    included with the report.

    Finally, it is important to undertake and include in the schematic design

    report an estimate of the preliminary construction and operating

    costs, and the project construction schedule. However, it is

    accepted at this time that the construction cost estimates are only an

    order of accuracy. Source: www.fao.org

    2 2 Stages or Phases of a Project C td

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    35/77

    2.2 Stages or Phases of a Project Contd.

    2.2.2 Concept stage: Funnel of innovation and Risk of failure

    35

    Many alternatives at the beginning, converging into one most v iable solution at the end.

    Failures at later stages are costlier, thus careful screening of alternatives at the beginning to

    select the best viable option is crucial.

    2 3 Project Feasibil ity Study

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    36/77

    Five common factors (TELOS)

    Technology and system feasibility

    Economic feasibility

    Legal feasibility

    Operational feasibility

    Schedule feasibility

    Other feasibility factors

    Market and real estate feasibility

    Resource feasibility

    Cultural feasibility

    Feasibility study is an evaluation or analysis of the potential impact of a proposed

    project. It is a critical component of Project Life Cycle and involves documenting

    each of the potential solutions to a particular business problem or opportunity.

    Source: MPMM

    www.mpmm.com/project-management-methodology.php

    Project Initiation: Defining project purpose and scope, thejustification for initiating it and the solution to be implemented.

    36

    Project Life Cycle

    2.3 Project Feasibil ity Study

    2.3.1 What is a Project feasibility study

    2 3 Project Feasibil ity Study Contd

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    37/77

    37

    2.3 Project Feasibil ity Study Contd.

    2.3.2 Analysis of Economic/Financial Feasibility

    The objective of a financial feasibility study is to determine if the proposed expansion/addition

    will be financially viable.

    It analyzes total facility costs, including construction and operating expenses, and potentialfacility revenue that could vary from rental fees, ticket sales, and/or other forms of

    customer/participant contributions.

    A business plan that measures the adequacy of potential revenues to meet operating, debt

    service, and replacement costs is developed. Options for capital financing are analyzed and

    recommended.

    Two basic questions need to be answered with the analysis:1) Is there sufficient demand for the product or service?

    2) Can the product or service be provided on a profitable basis?

    The whole purpose for this document is to assist you/proponent in assessing whether or not

    to move on with your business concept. If it fails, move on to other more feasible alternatives.

    Content of the report may include:

    A brief overview of what the business is about (1 page; tentatively).Overview of the market for the product or service and the results of the market analysis (1-2

    page/s).

    Competitive advantage of your product or service over the competitor, and the strengths and

    weaknesses of your competitors (1 page).

    Rough proformas, including the income statement, which should show the expected level of profit

    over the next five years (1-2 page/s).

    Please refer to Annex 1-Guide to Financial Feasibility Analysis for further information.

    2 3 Project Feasibil ity Study Contd

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    38/77

    38

    2.3.3 How to evaluate Financial Feasibi li ty

    Profitability Indicators: A single number that is calculated for characterisation

    of project profitability in a concise and understandable form.

    Examples:

    1. Simple Payback

    2. Return on Investment (ROI)

    3. Net Present Value (NPV)

    4. Internal Rate of Return (IRR)

    Cash Flow Concept:A common management planning tool.

    Distinguishes between:

    Costs: cash outflows

    Revenues/savings: cash inflows

    2.3 Project Feasibil ity Study Contd.

    2 3 Project Feasibil ity Study Contd

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    39/77

    39

    2.3.3 How to evaluate Financial Feasibi li ty

    2.3 Project Feasibil ity Study Contd.

    1. Simple Pay Back Definition: number of years it will take for the project to

    recover the initial investments Usually a rule of thumb for selecting projects, e.g.

    payback must be < 3 years

    2. Return on Investment Definition: the percentage of initial investment that is

    recovered each year

    3. Net Present Value Money loses its value and purchasing power over time

    as product/service prices rise, so a 1000 Rs. today can

    buy more than a 1000 Rs. next year (Inflation)

    A 1000 Rs. that you invest today will bring you more

    than a 1000 Rs. next year (Return on Investment)

    Time value of money depends on rate of inflation and

    Rate of Return on Investment

    In NPV approach, all project cash flows are converted

    to their present value now, at the very beginning of

    the project

    More reliable than Simple Payback or ROI as it

    considers time value of money and all future year cashflows

    2 3 Project Feasibil ity Study Contd

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    40/77

    40

    2.3.3 How to evaluate Financial Feasibi li ty

    2.3 Project Feasibil ity Study Contd.

    4. Internal Rate of Return (IRR) Definition: The discount rate for which NPV = 0, over

    the project lifetime Tells exactly what discount rate makes the project

    just barely profitable

    Similar to NPV; considers time value of money and all

    future year cash flows

    2.3.4 Profitability Indicators Summary

    *Use NPV and IRR methods to analyze financial feasibility of Group Project.

    Use a reasonable discount rate for the analysis.

    2 3 Project Feasibil ity Study Contd

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    41/77

    41

    2.3 Project Feasibil ity Study Contd.

    2.3.4 Environmental Feasibi lity (EIA/IEE) The environmental feasibility analysis weighs the advantages and disadvantages

    of each option with regard to the environment and related eco-systems (Sri Lanka

    is one of the 25 biodiversity hotspots in the world).

    Environmental Impact Assessment (EIA) legislation in Sri Lanka is intended to

    involve citizens directly in the planning process through consultation on specific

    plans or projects and their potential environmental impact, while critically

    evaluating other possible alternatives.

    This includes not only the influences of the environment on the project itself, but

    also positive and negative effects the project may have on the environment.

    MAIN FEATURES OF EIA IN SRI LANKA

    Provisions for EIA are included in the NationalEnvironmental Act. No. 47 of 1980

    EIA is mandated only for PRESCRIBEDPROJECTS (Published in a Gazette Notification)

    22 State Agencies have been designed as ProjectApproving Agencies (PAA) for the administration ofthe EIA process with the Central EnvironmentalAuthority (CEA) bearing the primary responsibility

    Public participation is a mandatory requirement ofthe EIA process and all EIA reports are open forpublic comments for a mandatory period of 30working days

    EIA reports are published in all three languagescurrently used in the country

    Public hearings may be held at the discretion of theProject Approving Agency

    HISTORY OF EIA IN SRI LANKA

    1981 Legal provisions for EIA included in Coast

    Conservation Act No. 57 of 1981 (Provisions

    Restricted to Coastal Zone Only).

    Identification of Projects for EIA at the

    discretion of the Director, Coast

    Conservation.

    1984

    EIA made mandatory for all major

    development projects through a cabinet

    decision.

    1988

    Amendments to the National Environment

    Act mandates EIA for Prescribed Projectsisland wide.

    2 3 Project Feasibil ity Study Contd

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    42/77

    42

    2.3 Project Feasibil ity Study Contd.

    2.3.5 EIA/IEE* Process in Sri Lanka

    List of Typical Projects Requiring IEE/EIASchedule Part I:

    1. All river basin development and irrigationprojects

    2. Reclamation of Land, Wetland area exceeding4 hectares

    3. Extraction of Timber covering land areaexceeding 5 hectares

    4. Conversion of forests covering an areaexceeding 1 hectare into non forest uses

    5. Clearing of land area exceeding 50 hectares

    6. Mining and Mineral Extraction

    7. Transportation Systems

    8. Port & Harbor Development

    9. Power Generation & Transmission

    10. Transmission Lines

    11. Housing & Building

    12. Resettlement

    13. Water Supply14. Pipelines

    15. Hotels (>99 rooms in general)

    16. Fisheries

    17. Tunneling Projects

    18. Disposal of Waste

    19. Industrial Estates & Parks

    20. Selected Large Scale Industry (Stand Alone)

    PRESCRIBED PROJECTS

    Published in Government Gazette

    PART I 31 Projects and Undertakings if located

    wholly or partly outside the coastal zone(Infrastructure + Large ScaleDevelopment Projects).

    PART II Projects if located partly or within an

    Environmentally Sensitive Area. (ie: 20Industries + All Part 1 projects).

    PART III Lists out Environmental Sensitive Areas.

    *If the proposed activity is less damaging an IEE

    (Initial Environmental Examination) report isrequested, instead of an EIA.

    See Annex 5A-The Environmental Impact

    Assessment Process in Sr i Lanka 2004-

    Kodituwakku.pdf for further information.

    Please access www.cea.lk for downloadingsample EIAs, Acts, Regulations & Ordinance

    2.3 Project Feasibil ity Study Contd

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    43/77

    43

    2.3 Project Feasibil ity Study Contd.

    2.3.6 Steps and Contents of an EIA/IEE EIA REPORT: CONTENT AND FORMAT Table of Contents

    Executive Summary

    Proposed Actions Purpose, Need and LegalRequirements

    - Purpose of the EIA, EIA preparationprocess, legal actions required bygovernment to approve action.

    Proposed Action and Reasonable Alternatives

    - Description of proposed action, no actionalternative, other reasonable alternativesincluding mitigation measures.

    Affected Environment

    Environmental Consequences of ProposedAction and Alternatives

    - Comparison of impacts, including direct,indirect and cumulative impacts,insignificant impacts, irreversible andirretrievable commitments of resources,environmental evaluation criteria,application of criteria to proposed projectand alternatives, environmentally

    preferred alternatives. Benefit Cost analysis

    - Included if one has been prepared by theProject Proponent.

    Proposed Monitoring Plan

    - Including institutional responsibilities andprocedures for reporting and analysis.

    Appendices

    - List of EIA preparers, references, backupdata and analysis.

    2.3 Project Feasibil ity Study Contd.

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    44/77

    44

    2.3 Project Feasibil ity Study Contd.

    2.3.7 Schedule Feasib ili ty; Project Time Management & Planning

    2.3 Project Feasibil ity Study Contd.

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    45/77

    45

    2.3 Project Feasibil ity Study Contd.

    2.3.8 Why do projects fail?

    Source: SYSEDV/ITPM SS 2005/www.sysedv.tu-berlin.de

    3.0 Preliminary Design: Outline & Supporting Materials

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    46/77

    y g pp g

    Summary

    3.0 Preliminary Design: Outline & Supporting Materials

    3.1 Design Phases

    3.1.1 Preliminary Design Phase

    3.1.2 Preliminary Design Phases

    3.1.3 Preliminary Design Outcomes

    3.2 Building Services Design

    3.2.1 Building services engineering

    3.3 Building Services: Electrici ty/Lighting3.3.1 Electricity/Lighting basics

    3.3.2 Electricity Distribution and Local Connections

    3.3.3 Electricity/Lighting Service Considerations

    3.3.4 Miniature Circuit Breaker components and functions

    3.3.5 Services Wiring Considerations

    3.3.6 Services Wiring Considerations in Domestic Buildings

    3.3.7 Further Considerations: Accessibility for Disabled & Surge/LV Protectors

    3.3.8 Domestic/Office Premises Lighting Design

    3.3.9 Domestic/Office Premises Lighting Design: SUMMARY

    3.4 Building Services: Vertical Transportation Lifts & Escalators

    3.4.1 Vertical Transportation Basics of Lifts & Escalators

    46

    3.1 Brief introduction Preliminary Design Stage

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    47/77

    47

    y g g

    3.1.1 Design Phases

    The second phase of project development is Design.

    Design itself can be sub-divided into as many steps as necessary to resolve all design problems

    and to Integrate the concepts into a functional facility plan. It is generally recommended that at

    least two stages are used. These are:

    1. - Preliminary design, and

    2. - Final design.

    Both stages adhere to all the concepts developed during the planning phase. The remaining

    elements in the design process are:

    3. - Cost re-evaluation or value engineering, (which is optional), and

    4. - Construction documents and bid specifications.

    The conclusions, or end products, of the design phase are:

    written reports

    architectural and engineering drawings more accurate construction costs

    projected operational costs, and

    schedules of construction.

    There are also engineering specifications for materials, machinery, and equipment for each step.

    The reports will record the evolution of the design process and all criteria and assumptions used.

    3.1 Brief introduction Preliminary Design Stage

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    48/77

    48

    y g g

    3.1.2 Preliminary Design Phase

    During the preliminary design stage, major

    emphasis is given upon all civil,

    mechanical, and architectural design. The

    design of all the mechanical processes(water & other services systems) will also

    be completed at this time to ensure that

    they are integrated properly into the

    structures.Architectural concepts (if

    required) are developed, and structural

    systems identified.

    All the required site investigations,

    including soil analyses and topography, are

    made before completing this step. Based

    upon these investigations, the criteria are

    developed by the engineers for soil

    compaction and other necessary remedialsteps.

    A sufficient number of drawings are then

    completed to communicate the design

    concepts, strictly depending upon the size

    and complexity of the project.

    3.1 Brief introduction Preliminary Design Stage

    http://www.prefabuloushomes.ca/Zooms/lanehomeCLG.jpghttp://www.prefabuloushomes.ca/Zooms/lanehomeFLG.jpghttp://www.prefabuloushomes.ca/Zooms/lanehomeELG.jpghttp://www.prefabuloushomes.ca/Zooms/lanehomeALG.jpg
  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    49/77

    49

    y g g

    3.1.2 Preliminary Design PhaseA preliminary design report is prepared with

    the drawings to describe all the structural

    components and mechanical processes of the

    facility, and the ways in which they interrelate.

    The report should include an outline of

    materials and equipment specifications which

    are then used as a basis for revising earlier

    construction cost estimates. These will now be

    reduced from the plus or minus 25% accuracy

    of the Schematic Design to about 15%

    accuracy. Operating cost estimates and theconstruction schedule are also revised at this

    time.

    Costs and scheduling revisions are again

    compared with the original financial objectives

    and constraints to ensure that the project

    remains financially feasible. If not, the facilitydesign concept has to be altered as

    necessary.

    The detailed architectural and engineering

    drawings (the blueprints) of all physical

    components of the project are produced only

    during the final design stage.

    3.1 Brief introduction Preliminary Design Stage

    http://www.prefabuloushomes.ca/Zooms/lanehomeGLG.jpg
  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    50/77

    50

    y g g

    3.1.3 Preliminary Design Outcomes

    3.2 Building Services Design

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    51/77

    Design, installation, operation and monitoring of the mechanical, electrical and public

    health systems required for the safe, comfortable and environmentally friendly operation

    of modern buildings.

    Involves the internal environment and environmental impact of a building & essentiallybrings buildings and structures to life.

    Common Services:

    Communication lines, telephones and IT networks (ICT)

    Energy supply - gas, electricity and renewable sources

    Escalators and lifts

    Fire detection and protection Heating/Ventilation and air conditioning (HVAC)

    Lightning protection

    Low voltage (LV) systems, distribution boards and switchgear

    Natural lighting and artificial lighting, and building facades

    Security and alarm systems

    Cooling/refrigeration

    Water, drainage and plumbing

    51

    g g

    3.2.1 Building services engineering

    The capital and installation costs of building services in modern buildings can take up 50%

    of the total construction budget. For highly serviced buildings such as sports centres, this

    figure can easily exceed 75%. Services can also take up 15% of a buildings volume.

    Therefore building services cannot be ignored.

    Building services are the dynamics in a static structure, providing movement,

    communications, facilities and comfort.

    3.3 Building Services: Electricity/Lighting

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    52/77

    52

    3.3.1 Electric ity/Light ing Basics

    In 1831 Michael Faraday succeeded in producing electricity by plunging a bar magnet into a

    coil of wire. This is credited as being the elementary process by which we produce electricity

    today, but the coils of wire are cut by a magnetic field as the magnet rotates.

    These coils of wire (or stator windings) have an angular spacing of 120and the voltages

    produced are out of phase by this angle for every revolution of the magnets. Thus generating

    a three-phase supply.

    A three-phase supply provides 73%

    more power than a single-phase supply

    for the addition of a wire. With a three-

    phase supply, the voltage between twoline or phase cables is 1.73 times that

    between the neutral and any one of the

    line cables, i.e. 230 volts * 1.73 = 400

    volts, where 1.73 is derived from the

    square root of the three phases.

    Related Codes:

    BS 7671: Requirements for Electrical

    Installations

    The IEE Wiring Regulations 16th

    edition.

    3.3 Building Services: Electricity/Lighting Contd.

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    53/77

    53

    3.3.2 Electric ity Distribution and Local Connections

    The mains electricity is produced at power generating

    stations at 25/33 kilovolt (kV) potential, in three-phase supply

    at 50/60 cycles per second or hertz (Hz).

    Thereafter it is processed by step-up transformers to 132,

    275 or 400 kV before connecting to the national grid.

    Power to large towns and cities is by overhead lines at 132

    kV or 33 kV where it is transformed to an 11 kV

    overhead/underground supply to sub-stations.

    From these sub-stations the supply is again transformed tothe lower potential of 400 volts, three-phase supply and 230

    volts, single-phase supply for general distribution.

    In AC current lines, the voltage of the live wire at the mains

    changes from + to alternatively while the voltage of neutral

    wire is always zero

    Depth of cover to underground cables should be at least 750mm below roads and 450 mm below open ground.

    The IEE Wiring Regulations recommend that the earth

    electrode (10 mm2 minimum) resistance should not exceed

    200 ohms. The ground contact is made at about 1.5 to 2.0 m

    below the surface.

    3.3 Building Services: Electricity/Lighting Contd.

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    54/77

    Required voltage (110/240/415/600 V); amperage (5 /15 A); frequency (50/60 Hz)

    Single phase vs. polyphase (2-phase/3-phase)

    Required connections/points/equipments/machineries/other services

    Specifications for level of lighting based on functional areas/usage

    Main specifications are normally provided by the client or to be designed by the

    services engineers, together with electrical/services drawings.

    Traditional fuses are rated at 5, 15, 20, 30 and 45 amps whilst the more modernMCB`s are rated in accordance with BS EN 60898: Circuit breakers for over current

    protection for household and similar installations.

    54

    3.3.3 Electricity/Lighting Service Considerations

    3.3 Building Services: Electricity/Lighting Contd.

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    55/77

    55

    3.3.4 Miniature Circuit Breaker components and functions

    MCB: Modern Miniature Circuit Breaker components and functions

    3.3 Building Services: Electricity/Lighting Contd.

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    56/77

    56

    3.3.5 Services Wiring Considerations

    A ring circuit is used for single-phase power supply to three-pin sockets.

    In a domestic building a ring circuit (5 Amp) may serve an unlimited number of

    sockets up to a maximum floor area of 100 m2

    .A separate circuit is also provided solely for the kitchen/baths, as these may contain

    relatively high rated appliances (13 /15 Amp).

    Appliances and installations with a load factor above 3 kW, e.g. immersion heater,

    cooker, extension to an outbuilding, etc. must not be connected to any part of a ring

    circuit. These are supplied from a separate radial circuit from the consumer unit.

    3.3 Building Services: Electricity/Lighting Contd.

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    57/77

    57

    3.3.6 Services Wiring Considerations in Domestic Build ings

    Power sockets should be positioned between 150 mm and 250 mm above floor levels and

    work surfaces.

    An exception is in buildings designed for the elderly or infirm, where socket heights should

    be between 750 and 900 mm above the floor.

    Disposition of sockets would limit the need for lead lengths to no more than 2 m.

    3.3 Building Services: Electricity/Lighting Contd.

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    58/77

    58

    3.3.6 Services Wiring Considerations in Domestic Build ings

    A radial circuit may be used as an alternative to a ring circuit to supply any number of power

    sockets, provided the following limitations are effected:

    Therefore radial circuits are more suited to the following:

    3.3 Building Services: Electricity/Lighting Contd.

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    59/77

    59

    3.3.6 Services Wiring Considerations in Domestic Build ings

    In a one-way switch circuit the single-pole switch must be connected to the live conductor.

    In principle, the two-way switch is a single-pole changeover switch interconnected in pairs.

    Two switches provide control of one or more lamps from two positions, such as that found in

    stair/landing, bedroom and corridor situations.

    In large buildings, every access point should have its own lighting control switch.

    3.3 Building Services: Electricity/Lighting Contd.

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    60/77

    60

    3.3.7 Further Considerations: Accessibil ity for Disabled & Surge/LV Protectors

    BS 8300: Design of buildings and their approaches to meet the needs of disabled

    people - Code of Practice.

    Surge/Low-voltage protection:BS 88-5 and 6: Cartridge fuses for voltages up to and including 1000 V a.c. and 1500 V d.c.

    BS 1361: Specification for cartridge fuses for a.c. circuits in domestic and similar premises.

    BS EN 60269: Low voltage fuses.

    BS EN 60898: Circuit breakers for overcurrent protection for household and similar

    installations.

    BS ENs 61008 and 61009: Residual current operated circuit breakers

    3.3 Building Services: Electricity/Lighting Contd.

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    61/77

    Types of lamps: Incandescent Lamps, Discharge Lamps, LED bulbs (power saving)

    Factors to be considered: Luminous Efficacy

    The ability of a lamp to convert electrical energy to light energy is measured by its efficacy which

    is given by the following formula.

    Efficacy = Light output (lumens) / Electrical energy input (Watts)

    UNIT: lumens/watt (lm/W). Note: ~15 for incandescent bulbs and ~50-100 for fluorescent bulbs

    Others: Life, Colour temperature, Colour rendering

    61

    3.3.8 Domestic/Office Premises Lighting Design

    3.3 Building Services: Electricity/Lighting Contd.

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    62/77

    Reference Code: BS EN 12464-1:2002 Light and lighting - Lighting of work places - Part 1:

    Indoor work places

    62

    3.3.8 Domestic/Office Premises Lighting Design

    3.3 Building Services: Electricity/Lighting Contd.

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    63/77

    Reference Code: Chartered Institute of Building Services Engineers (CIBSE) Code for Lighting

    Part 2 (2002)

    63

    3.3.8 Domestic/Office Premises Lighting Design

    3.3 Building Services: Electricity/Lighting Contd.

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    64/77

    Reference Code: BS ISO 8995: Lighting of indoor work places.

    BS 8206-2: Lighting for buildings. Code of practice for daylighting. 64

    3.3.8 Domestic/Office Premises Lighting Design: Considering Daylight Factor

    Overall considerations fall into three categories:

    A: Daylighting alone, in which the window area occupies about 80% of the facades

    B: Permanent supplementary artificial lighting of interiors, in which the window area isabout 20% of the facades

    C: Permanent artificial lighting of interiors in which there are no windows.

    3.3 Building Services: Electricity/Lighting Contd.

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    65/77

    65

    3.3.9 Domestic/Office Premises Lighting Design: SUMMARY

    Main Supply and Distinction

    Load assessment: locations and types of loads expected (voltage, frequency, phase)

    Load estimation based on floor area or consumer units

    Major load centres and electrical equipments (identify and focus on them) Allow for diversity or future expansion

    Electricity supply provided by establishing a substation at the building or by direct

    Cables from existing low voltage network

    Location of transformer room(s)

    Essential (Emergency) Power Supply

    Assessment of essential loads to be supplied to (e.g. fire services pumps, firemans lift,

    Emergency lighting)

    Design of standby emergency generator

    Location, capacity required, operation

    To comply with FSDs requirements (see FSDs COP)

    Lighting System

    Design criteria: lighting (illuminance) level in lux for each area of the building

    Selection of luminaries for different usage and applications Simple lighting calculations (Lumen method)

    Other Minor Systems

    Lightning protection system

    Design Considerations

    Relationships with and implications from other Building Services systems: Electrical design always come

    after others because it has to obtain ratings and demand of equipment from other services systems

    Coordination of electrical services with other trades and with architectural design

    3.4 Building Services: Vertical Transportation Lifts & Escalators

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    66/77

    66

    3.4.1 Vertical Transportation Basics of Lifts & Escalators

    The invention of the elevator fostered the development of

    the skyscraperin modern cities.

    Following the invention of a safety device by Otis in 1852,

    the first (steam-powered) passenger elevator was

    introduced in New York City in 1857.

    Later improvements have included increased speeds,

    noise reduction, safety features (such as lighting and

    alarm systems), the automatic operation of groups of

    elevators, viewing galleries, and two-deck cars (serving

    two levels simultaneously).

    3.4.2 Lifts & Escalators: Design Considerations

    Planning should commence early in the design program (lift core provides structural torsional

    resistance in high-rise buildings).

    Priority must be given to locating lifts centrally within a building to minimise horizontal travel

    distance. Consideration must also be given to position, relative to entrances and stairs. Where

    the building size justifies several passenger lifts, they should be grouped together.

    In large buildings it is usual to provide a group of lifts near the main entrance and single lifts at

    the ends of the building.

    The lift lobby must be wide enough to allow pedestrian traffic to circulate and pass through the

    lift area without causing congestion.

    For tall buildings in excess of 15 storeys, high speed express lifts may be used which by-pass

    the lower floors.

    3.4 Building Services: Vertical Transportation Lifts & Escalators

    3 4 3 Lif & E l D i R i

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    67/77

    67

    3.4.3 Lifts & Escalators: Design Requirements

    Necessary in all buildings over three stories high.

    Essential in all buildings over a single storey if they are accessed by the elderly or disabled.

    Minimum standard: one lift per four stories.

    Minimum walking distance to access a lift: 45 m.

    Floor space and lift car capacity can be estimated at 0.2 m2 per person.

    Reference Codes:

    BS 5655: Lifts and service lifts.

    BS EN 81: Safety rules for the construction and installation of lifts.

    BS 5656: Safety rules for the construction and installation of escalators and

    passenger conveyors. Specification and pro formas for test and examination of

    new installations

    3.4 Building Services: Vertical Transportation Lifts & Escalators

    3 4 4 Lift D i C id ti M l C t l M th d

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    68/77

    68

    3.4.4 Lift Design Consideration: Manual Control Methods

    Single automatic lift control responds to the first call and one operation at a time. Most

    suited to light traffic conditions in low rise buildings such as nursing homes, small hospitals

    and flats.

    Down collective - stores calls made by passengers in the car and those made from the

    landings. As the car descends, landing calls are answered in floor sequence to optimise car

    movement. Most suited to flats and small hotels, where the traffic is mainly between the

    entrance lobby and specific floors.

    Full or directional collective - a variation in which car and landing calls are immediately

    stored in any number. Greater flexibility than the down collective system and is appropriate

    for offices and departmental stores where there is more movement between intermediatefloors.

    Two cars may be co-ordinated by a central processor to optimise efficiency of the lifts. Each

    car operates individually on a full or down collective control system.

    Reference Codes:

    BS 5655-7: Lifts and service lifts. Specification for manual control devices, indicators and

    additional fittings; BS 5655: Lifts and service lifts; BS EN 81: Safety rules for the

    construction and installation of lifts.

    3.4.4 Lift Design Consideration: Safety Requirements

    Buffers (oil or spring loaded), Over-speed Governorand Safety Gear (linked to EmergencyBreaking System), Signage, Auxiliary Power, Emergency Call Button, Accessibility

    3.4 Building Services: Vertical Transportation Lifts & Escalators

    3 4 5 Lift D i C id ti P f d N f Lift R i d

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    69/77

    69

    3.4.5 Lift Design Consideration: Performance and No. of Lifts Required

    Lift performance depends on:

    acceleration

    retardation

    car speed speed of door operation and

    stability of speed and performance with variations of car load.

    The assessment of population density may be found by allowing between one person per

    9.5 m2 to 11.25 m2 of floor area.

    For unified starting and finishing times, 17% of the population per five minutes may be used.

    For staggered starting and finishing times 12% of the population may be used.

    The number of lifts will have an effect on the quality of service. Four 18-person lifts provide

    the same capacity as three 24-person lifts but the waiting time will be about twice as long

    with the three-car group.

    The quality of service may be found from the interval of the group. A 25-35 seconds interval

    is excellent, 35-45 seconds is acceptable for offices, 60 seconds for hotels and 90 seconds

    for flats.

    Reference Codes:

    BS 5655: Lifts and service lifts.

    BS EN 81: Safety rules for the construction and installation of lifts.

    3.4 Building Services: Vertical Transportation Lifts & Escalators

    3 4 5 Lift D i C id ti P f d N f Lift R i d

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    70/77

    70

    3.4.5 Lift Design Consideration: Performance and No. of Lifts Required

    Reference Codes:

    BS 5655: Lifts and service lifts.

    BS EN 81: Safety rules for the construction and installation of lifts.

    3.4 Building Services: Vertical Transportation Lifts & Escalators

    3 4 6 E l t D i C id ti P f d N f E l t R i d

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    71/77

    71

    3.4.6 Escalator Design Consideration: Performance and No. of Escalators Required

    Reference Codes:

    3.5 Eco-fr iendly & Green Design Concepts

    3 5 1 General Introduction

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    72/77

    Green Building Resources ?

    What is Green Design/Architecture? What is Sustainable Design/Architecture?

    => ideas and philosophies related to

    sustainable development and the

    relationship between engineering/

    architecture and ecology.

    72

    3.5.1 General Introduction

    Green Design Concepts

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    73/77

    "Thinking green"

    * Smaller is better: Optimize use of interior space through careful design so that the overall building size--and resource use in constructing

    and operating it--are kept to a minimum.

    * Design an energy-efficient building: Use high levels of insulation, high-performance windows, and tight construction. In southern

    climates, choose glazings with low solar heat gain.

    * Design buildings to use renewable energy: Passive solar heating, daylighting, and natural cooling can be incorporated cost-effectively

    into most buildings. Also consider solar water heating and photovoltaics--or design buildings for future solar installations.

    * Optimize material use: Minimize waste by designing for standard ceiling heights and building dimensions. Avoid waste from structural

    over-design (use optimum-value engineering/advanced framing). Simplify building geometry.

    * Design water-efficient, low-maintenance landscaping: Conventional lawns have a high impact because of water use, pesticide use, and

    pollution generated from mowing. Landscape with drought-resistant native plants and perennial groundcovers.

    * Make it easy for occupants to recycle waste: Make provisions for storage and processing of recyclables: recycling bins near the kitchen,

    undersink compost receptacles, and the like.

    * Look into the feasibility of graywater:Water from sinks, showers, or clothes washers (graywater) can be recycled for irrigation in some

    areas. If current codes prevent graywater recycling, consider designing the plumbing for easy future adaptation.

    * Design for durability: To spread the environmental impacts of building over as long a period as possible, the structure must be durable. A

    building with a durable style ("timeless architecture") will be more likely to realize a long life.

    * Design for future reuse and adaptability: Make the structure adaptable to other uses, and choose materials and components that can

    be reused or recycled.

    * Avoid potential health hazards: radon, mold, pesticides: Follow recommended practices to minimize radon entry into the building and

    provide for future mitigation if necessary. Provide detailing that will avoid moisture problems, which could cause mold and mildew growth.

    Design insect-resistant detailing that will require minimal use of pesticides.

    73

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    74/77

    74

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    75/77

    75

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    76/77

    76

    ENVIRONMENTALLY SUPPORTIVE DESIGNS

  • 7/21/2019 UNIT 5-Group Project-Lecture Note

    77/77

    Hydronic (water-based) heating system that does everything: instant domestic hot water, radiant and convection heat from radiators for

    living areas and bedrooms, heated towel rails in the bathrooms, and it can even heat the water for the Spa.

    This heating system is more than 95% efficient, meaning that very little energy will be required for all of the above distribution areas. In

    addition, this system is very flexible in that other energy sources, in this case integral Solar Water Heating, can be used to supplement thenatural gas or propane fuel.

    The Home at BC Place has an energy efficient lighting design. Only Energy Efficient Appliances and Windows are used. Maximuminsulation is used in the walls, ceilings and floors. The Japanese are renowned for their technology in toilet design and their Toto Toilet (1.6

    gal/flush) which has been tried and proven by us in other projects is featured in the EcoFabulous Home.

    These options and others are available to homeowners and developers who want to reduce the eco-footprint of their own PreFabulous Home.Summary of Features in the EcoFabulous Home:

    BC Hydro Power Smart GOLDSTAR RatingBuiltGreen in progress

    Energy Efficient lighting with fluorescent/LED luminaires

    Energy Efficient appliances and windows

    Over 95% heat/hot water efficiency, including SpaSprinkler System

    Radiant and Convection wall radiators for heat, with individual temperature sensors

    Continuous Fresh Air Ventilation System

    Solar Panel to supplement natural gas or propane

    High-Efficiency Condensing Boiler for all hot water requirementsSmall eco-footprint

    Minimal/Zero Volatile Organic Compounds (VOCs)

    Kitchen Cabinets are 100% recycled paper (zero VOC) with photo-imprinted teak veneer"Green" paint

    Reduced wastage in factory

    Sustainable wood and cork productsB th bl B ildi W d R i S

    http://www.prefabuloushomes.ca/Images/ecofabulousbath2B_LG.jpghttp://www.prefabuloushomes.ca/Images/ecofabulous240b_LG.jpghttp://www.prefabuloushomes.ca/Images/ecofabuloushallwayB_LG.jpg