22
Released under FOI

under FOI - Bureau of Meteorology

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Releas

ed un

der F

OI

Releas

ed un

der F

OI

Releas

ed un

der F

OI

Released: Error! Reference source not found.

Error! Reference source not found.5 Supercomputer Programme Management Plan

Page 4 of 22

Contents 1. Programme Background ................................................................................................................. 6

2. Programme Objective ..................................................................................................................... 6

3. Product Descriptions .................................................................................................................... 7

4. Programme Scope ................................................................................................................... ..... 7

4.1. In Scope ................................................................................................................. ........ .. 7

4.2. Out of Scope ...................................................................................................... .... .......... 7

5. Key Assumptions ................................................................................................................ ......... 7

6. Dependencies ................................................................................................. ............................ 7

7. Constraints ........................................................................................... ...... ..... ..................... 8

8. Programme Approach ................................................................. ..... ....... ............................ 8

9. Projects within the Programme .............................................. ......... ........................................ 9

10. Programme Roles and Management Structure ............. ..... ........................................ 10

11. Key Stakeholders .......................................................... .......... ................................................ 14

12. Project Tolerances ..................................................... ...... ....................................................... 15

12.1. Escalation Process ................ .................. ..... ............................................................... 15

13. Project Definition Documentation .. ... ................................................................................... 16

14. Monitoring and Control.................. ......... . ............................................................................... 16

14.1. Schedule ................ ..... ... ............................................................................................ 16

14.2. Costs and Budget ........ ................................................................................................ 16

14.3. Financial Management ......................................................... Error! Bookmark not defined.

14.4. Quality A surance Plan...................................................................................................... 16

1 5. Chang Management Plan ................................................................................................ 17

14 6. Risk and Issue Management ............................................................................................. 17

14.7. Procurement Plan ............................................................................................................. 17

14.8. Resources .......................................................................................................................... 17

14.9. Information and Documentation Management ............................................................... 17

14.10. Lessons Learnt ................................................................................................................... 17

15. Product Acceptance Plan .............................................................................................................. 17

15.1. Product Acceptance Criteria ............................................................................................. 18

Releas

ed un

der F

OI

Released: Error! Reference source not found.

Error! Reference source not found.5 Supercomputer Programme Management Plan

Page 5 of 22

15.2. Product Gateway Planning ................................................................................................ 18

15.3. Product Accountability Matrix .......................................................................................... 18

15.4. Testing ............................................................................................................................... 20

16. Project Interdependencies ............................................................... Error! Bookmark not defined.

17. Commissioning Plan ................................................................................................................. .. 21

18. Communication Plan ........................................................................................................ ....... .. 21

18.1. Project Reporting .......................................................................................... .......... ...... 2

18.2. Programme Reporting ....................................................................................... ............ 22

Releas

ed un

der F

OI

Error! Reference source not found. Released: Error! Reference source not found.

Error! Reference source not found. Programme Management Plan Page 6 of 22

1. Programme Background

Numerical Weather Prediction (NWP) is a core capability of the National Meteorological and Hydrological Services of most developed countries, and increasingly of developing nations. It is essential for the provision of fast response, high impact, and high value weather services. All nations recognise that timely, specific and accurate warnings and forecasts for their region offer distinct national security, economic and social benefits. NWP necessitates the use of a high performance supercomputer to run complex models of the highly dynamical atmosphere/land/ocean system. These models produce weather forecasts over various timescales and at different levels of spatial resolution which are then used to issu warnings and general advice to end users.

2. Programme Objective

The objective of the Supercomputer Programme is to replace the existing supercomputer which will

reach end of life in 2016, and enable the Bureau to meet demand for enhanced NWP forecast

services and products into the future.

Material redacted in black is removed under s 34(3)

Releas

ed un

der F

OI

Releas

ed un

der F

OI

Error! Reference source not found. Released: Error! Reference source not found.

Error! Reference source not found. Programme Management Plan Page 8 of 22

There are some projects in the Bureau that need to have planning integrated with HPC to

assure alignment and benefits.

7. Constraints

The procurement of Supercomputers is highly specialist and quir s some additional steps

and approaches that are not inconsistent with Commonwealth P ocurement Rules but add

complexity to the process;

and

Applicable Bureau policies need t be adhered to by the projects and programme.

8. Programme Approach

Under the leadership of the Prog mme SRO, Dr. Lesley Seebeck, the approach of the programme is

to direct, support and govern th delivery of the projects within the programme, but not to directly

run the projects within the programme as this is the accountability of the individual project

executives, projec teams and project boards. This includes:

Ensuring the Supercomputer funds are spent in line with the funding allocations.

Ensu ing an appropriate level of project documentation is produced and approved by the

r levant Project Executive;

Providing a shared resource pool to realise efficiencies across the programme, functions to

be provided include project management, business analysis, programme administration and

change acceptance management;

Quality assurance of project documentation; and

Advice on options and approaches to achieve the best outcomes in regards to risks and

issues.

Coordination of communication regarding the programme, including production and

distribution of the Programme Report and management of the programme intranet site.

Material redacted in black is removed under s 34(3)Material redacted in grey is removed under s 47E(d)

Releas

ed un

der F

OI

Releas

ed un

der F

OI

Releas

ed un

der F

OI

Releas

ed un

der F

OI

Releas

ed un

der F

OI

Releas

ed un

der F

OI

Releas

ed un

der F

OI

Releas

ed un

der F

OI

Releas

ed un

der F

OI

Error! Reference source not found. Released: Error! Reference source not found.

Error! Reference source not found. Programme Management Plan Page 17 of 22

14.4. Change Management Plan

Refer to the file

14.5. Risk and Issue Management

Risk Management Process:

Issue Management Process:

HPC and Data Centre Risk and Issue Plan and Register:

Refer to the files:

14.6. Procurement Plan

Refer to the file:

14.7. Resources

The resources for the Programme consist of the pr gramm team, support staff and executive

programme board members. Full resour e planning fo the projects will occur when the

procurement outcomes are known.

14.8. Information and Documentation Management

Information and document managemen will be controlled through the Enterprise Portfolio

Management Office.

14.9. Lessons Learnt

Many lessons learned have been gathered from the first Supercomputer implementation that has

been onsid ed d ring this procurement. The Programme Manager and Director will manage new

lessons le rned for the HPC and data centre projects.

15. Product Acceptance Plan

The acceptance plan for each product will be undertaken in a staged approach. Each product will

have clearly defined planning, execution and commissioning stages with gateways requesting

authority to proceed. This process will ensure business and technical requirements are well defined,

implemented, tested and signed off.

Filepaths redacted in grey are removed by consentFile names redacted in grey are removed under s 47E(d)

Releas

ed un

der F

OI

Error! Reference source not found. Released: Error! Reference source not found.

Error! Reference source not found. Programme Management Plan Page 18 of 22

15.1. Product Acceptance Criteria

Each specialist product will have clearly defined acceptance criteria, established during the planning

stage and will form part of the documentation and highlighted in the product descriptions.

15.2. Product Gateway Planning

Each specialist product will have clearly defined gateways to pass before moving to the next stage.

Business products will vary in content to technical products however the following illustrates a igh

level generalised representation of the product gateways

15.3. Product Accountabil ity Matrix (further development)

As each product is developed, various stakeholders will be accountable for aspe s of specific items

and activities. The following matrix indicates how each stakeholder group is likely t be accountable.

Material redacted in black is removed under s 34(3)

Releas

ed un

der F

OI

Error! Reference source not found. Released: Error! Reference source not found.

Error! Reference source not found. Programme Management Plan Page 19 of 22

Material redacted in black is removed under s 34(3)

Releas

ed un

der F

OI

Error! Reference source not found. Released: Error! Reference source not found.

Error! Reference source not found. Programme Management Plan Page 20 of 22

15.4. Testing

Areas considered for the Testing comprises of the following components, not all forms of testing

may be required:

Unit Testing

Functional Testing

Usability Testing

Accessibility Testing

User Acceptance Testing

Unit Testing

The developer wil ensure he code/scripts are working as expected before the product is deployed

into the test vironment for functional testing. This will ensure the code deployed into the test

environment is quality tested by the developer.

Function l Testing

he unc onal testing is done by a test analyst to ensure that the product deployed into the test

en iro ment reflects the business requirements. The test analyst should raise defects if there is any

discrepancy in the product.

Usability Testing

The Usability Testing is a phase of functional testing and this is where the Tester ensures all usability

issues have been resolved before the product is deployed into the UAT Environment.

Accessibility Testing

Material redacted in black is removed under s 34(3)

Releas

ed un

der F

OI

Error! Reference source not found. Released: Error! Reference source not found.

Error! Reference source not found. Programme Management Plan Page 21 of 22

Accessibility Testing is where the product is tested to ensure compliance with WCAG 2.0. The Digital

Data Delivery team will be required to test for accessibility and work with the team to ensure all

accessibility issues have been resolved before the product is deployed into the UAT Environment.

User Acceptance Testing (UAT)

User Acceptance Testing is the phase where Business users get to review the product in the UAT

environment. The Users review the product against the agreed acceptance criteria, raising JIRA

entries for items that do not meet the criteria. This is a critical step prior to any product being

released in to Production.

If the Business has worked with the Developer during the development phases as plan ed here will

be a reduced likelihood of product failure during UAT. At a minimum, two iterations of UAT should

be planned for each product.

16. Commissioning Plan

The HPC and Data Centre projects will follow the approved Transition t Ope tions plan as defined

by ISS when commissioning products in to the Production environment. A many products will be

planned, executed and commissioned in parallel, the defined T ansit n o Operations plan will be

applied for each major product as it is due for release to t e Produ tion environment.

The Readiness Gateway planned for the end of the Execu ion Stage is the major point at which

approval to deploy the product is obtained. Approval stakeholders will vary depending upon the

product in question and is documented in he Product Descriptions.

This leads in to the Commissioning Stag where he product/s will be deployed in to the Production

environment once it has passed th Read ess Gateway; BAU Acceptance and training/support

documentation is handed over t BAU. Business Engagement during the Commissioning Stage will

involve user training and su ort uring the parallel run period, whereby a product Acceptance

Certificate will be sought confi m ng Business acceptance of the product.

17. Commun cation Plan

The HPC a d D ta Centre - Stakeholder Engagement and Communication Strategy involves

proacti ely d termining the information needs of stakeholders, what information needs to be

coll ted and when, who needs the information, when and in what form.

The strategy and plan cover:

methods used to gather and store information,

Limits, if any, on who may give direction and to whom,

reporting relationships,

list of contact information of all stakeholders,

schedule for distribution of information, and

Material redacted in grey is re removed under s 47E(d)

Releas

ed un

der F

OI

Error! Reference source not found. Released: Error! Reference source not found.

Error! Reference source not found. Programme Management Plan Page 22 of 22

provides a method to update the communications management plan as the projectprogresses.

Refer to the files:

17.1. Project Reporting

TBD – subject of Executive Meeting outcomes.

17.2. Programme Reporting

TBD – subject of Executive Meeting outcomes.

Filepaths redacted in grey are removed by consentFile names redacted in grey are removed under s 47E(d)

Releas

ed un

der F

OI