37
Development & Implementation of a SCADA System for Load Control of the Power System Simulator (PSS) Ahmed Fayez 199905252 Mohammed Adnan 199901444 Khalid Yousif 199900237 Salman Al katheeri 199900317

Ultimate Final SCADA Presentation

Embed Size (px)

Citation preview

Page 1: Ultimate Final SCADA Presentation

Development & Implementation of a SCADA

System for Load Control of the Power System Simulator (PSS)

Ahmed Fayez 199905252Mohammed Adnan 199901444Khalid Yousif 199900237Salman Al katheeri 199900317

Page 2: Ultimate Final SCADA Presentation

Presentation Layout SCADA Introduction SCADA Hardware

RTU PSS Wiring

SCADA Software ISaGraF Citect DNP

Future Work Demonstration

Page 3: Ultimate Final SCADA Presentation

Introduction

Page 4: Ultimate Final SCADA Presentation

Introduction (What Is SCADA?)

Stands for supervisory control And data acquisition.

SCADA systems are used in industrial processes: steel making, power generation (conventional and nuclear) and distribution.

There Are 4 Components In the SCADA System.

Page 5: Ultimate Final SCADA Presentation

SCADA Components

Field Instrumentation. Sensors, devices to control.

Remote Terminal Units. RTU Vs. PLC

Communications Network. Equipment needed to transfer data to and from different sites

Central Monitoring Station Collecting information gathered by the remote stations to

generate the necessary action

Page 6: Ultimate Final SCADA Presentation

Disadvantages Of Relay Systems Relays used only for on/off control.

Complicated control systems Expensive System. System takes up much floor and space. Control relays are power- hungry, heat

generation. Any change in control program requires the

rewiring of relays. For complicated control systems, it is difficult to

troubleshoot and locate the faults.

Page 7: Ultimate Final SCADA Presentation

Advantages Of SCADA systems Easily programmed or reprogrammed Easy maintained (self diagnostic). Capability to do arithmetic function. The ability to communicate with other

controller or a master host computer. PLCs. were able to move past simple on/off

control to more complex schemes as PID control.

Page 8: Ultimate Final SCADA Presentation

Applications Of SCADA

Almost every business in the manufacturing sector and many in the service sector

Aerospace Bottling and Canning Chemicals Plants Petroleum, Petrochemical

Page 9: Ultimate Final SCADA Presentation

Remote Terminal Unit (RTU)

Page 10: Ultimate Final SCADA Presentation

PDS eNET OVERVIEWDIGITAL / ANALOG INPUTS

32 x Digital Inputs 9-28V DC Operation range LED Indication (Disable Option) Optically Isolated (1500V peak)

12 x Analog Inputs0-5V,1-5V,0-10V,0-20mA, 4-

20mA(selectable per channel)

Surge Protection

Page 11: Ultimate Final SCADA Presentation

4 x Analog Outputs Internal / External power supply Source

0-20mA, 4-20mA (Voltage output with external resistor)

Short circuit protected

RTU PDS eNET OVERVIEWDIGITAL / ANALOG OUTPUTS

Page 12: Ultimate Final SCADA Presentation

RTU Scan Time

Page 13: Ultimate Final SCADA Presentation

Power System Simulator

Page 14: Ultimate Final SCADA Presentation

Power System Simulator ( PSS):

The objective of the PSS is to simulate a real power system.

Power system should be divide in to three sections , the generator station, transmission line and load ( distribution section ).

Page 15: Ultimate Final SCADA Presentation

PSS Parts

1- Generator Stations: The generator station contains two internal generators and a

third external generator. Separately excited synchronous generator is the type of the

machine which used in PSS. The DC motor in PSS is used as prime mover. The DC motor in PSS is Shunt DC motor type.

Page 16: Ultimate Final SCADA Presentation

2- Transmission lines: It is represented by wires that are different in shape and

size. The size and shape is depended on the level voltages and

the load.

Page 17: Ultimate Final SCADA Presentation

3- The loads: As in the real power system, the PSS has three type of load:

Residential. Commercial . Industrial.

The difference between these come from values of : - Load. - Power consumption.

- Power factor for each type. Also the difference rises in the peak load timing for each type.

Page 18: Ultimate Final SCADA Presentation

Sensors

In the industry field is now using computers to control and motions and sequences of machines.

PLC cannot see, hear, feel or tester processes by themselves but use industrial sensors to give industrial controllers these capabilities.

In our project the Sensors are used as feedback to PLC from PSS to enhance the system performance.

Page 19: Ultimate Final SCADA Presentation

Sensors

There were different types of sensor that will be used like Voltage sensor, current sensor, frequency sensor and power sensor.

Current sensor have rating of 0 – 5 A. Voltage sensor has a rating of 0 - 150 V. Frequency sensor, it has a rating of 0 -100Hz. Power sensor, it has rating of 0- 5 A and 0 – 150 v. The outputs from all sensors which going to RTU were 4 – 20 mA. It is

used this rating to sense any problem in system .

Page 20: Ultimate Final SCADA Presentation

Wiring

Page 21: Ultimate Final SCADA Presentation

Wiring

Auxiliary Switch

RTU

Output Port Input Port

Relay1(External)

Common

12V

0V

Internal Relay

0V

Common

Transistor Switch

12V

R1

220V Start

Page 22: Ultimate Final SCADA Presentation

0 V From RTU Power Supply

12 V+

0

0

+

COM 1 2 3 4 5 Com 1 2 3 4

220 V

T.B Control Circuit

A

BC

Coil 1

Ax 1

ABC

Coil 2

Ax 2

ON

NOff

3 – Phase Motor

M

COM IN 1 IN 2 IN 3 IN 4 IN 5

RTU 12 V

Page 23: Ultimate Final SCADA Presentation

ISaGRAF

Page 24: Ultimate Final SCADA Presentation

ISaGRAF

Page 25: Ultimate Final SCADA Presentation

The Citect Interface

Page 26: Ultimate Final SCADA Presentation

The DNP

Page 27: Ultimate Final SCADA Presentation

The DNP

Page 28: Ultimate Final SCADA Presentation

Future Plans

Page 29: Ultimate Final SCADA Presentation

Future Plans

Stand by generator.Adding generator 2 to the system.Power factor correction.Load scheduling.Improving the previous SCADA program.

Page 30: Ultimate Final SCADA Presentation

Stand by generator The whole system will be supplied by the main

supplying unit. A simulated fault will be applied on the system. During that generator 1 will be on a stand by mode. When the fault occur the main supplying unit will be

disconnected from the loads by using circuit breakers and generator 1 will be supplying the whole system instead.

All of this process will be done Automatically by the program.

Page 31: Ultimate Final SCADA Presentation

Adding generator 2

Generator 2 will be connected to the system using frequency and current sensors.

Generator 2 will be also controlled by the program which will be installed on the RTU.

Generator 2 will be as a back up if generator 1 didn’t work properly.

Page 32: Ultimate Final SCADA Presentation

Back Up generator

Page 33: Ultimate Final SCADA Presentation

Power factor correction

Capacitor banks are used to correct the power factor..

The value of the capacitance will depend on the value

of the load.

Capacitor banks will inject reactive power into the

system.

The reactive power will decrease the current in the

circuit reduce the losses in the transmission lines.

Page 34: Ultimate Final SCADA Presentation

Load Scheduling

There are two types of loads: Resistive load and active load.

1. The resistive load are two types: Critical: supplying vital instruments &machines . Non-critical: Ex: lighting gardens.

2. The active load: Simulated By a resistor and inductance in series.

Page 35: Ultimate Final SCADA Presentation

Load Scheduling

When the system suffers from overload on the generator the program disconnect the non-critical loads immediately.

Thus in the program all of the loads will be identified so that the program can do this process Automatically.

Page 36: Ultimate Final SCADA Presentation

Improving the SCADA program

Some blocks will be added to increase the speed of analyses process. This process will be applied on the LADDER program.

The Graphical Interface will be enhanced. This process will be applied on Citect.

Page 37: Ultimate Final SCADA Presentation

Thanks for ListeningNow, we’ll make a demo for our

work ..