Upload
doanthuan
View
221
Download
1
Embed Size (px)
Citation preview
South Worcestershire Development Plan –
Transport Background Paper
Technical Update
Worcestershire County Council
November 2014
CH2M HILL
Burderop Park
Swindon
Wiltshire
SN4 0QD
tel 01793 812479 fax 01793 812089
ch2m.com
CH2M HILL has prepared this report in accordance with
the instructions of client Worcestershire County Council for the client’s sole and specific
use.
Any other persons who use any information contained herein do so at their own risk.
South Worcestershire Development Plan
Transport Background Paper Technical Update
3
Contents
1 Executive Summary 5
2 Introduction 12 2.1 Background 12
2.2 Purpose of this report 13
2.3 Structure of this report 14
3 Methodology 15 3.1 Introduction 15
3.2 Need for assessment 15
3.3 Development of assessment tool 16
3.4 Overview of assessment results 17
3.5 Overview: existing highway Issues 17
3.6 Overview of passenger transport (rail) issues 19
3.7 Overview: existing local passenger transport (bus) issues 21
3.8 Overview of existing pedestrian network 22
3.9 Overview of existing cycle network 23
4 Review of previous SWDP work 24 4.1 Introduction 24
4.2 Worcester Transport Strategy 24
4.3 Worcester Transport Model and Worcester Transport Model
Assessment of South Worcestershire Development Plan (2011) 28
4.4 Worcester Transport Model – South Worcestershire Development
Plan 2 (June 2014) 28
4.5 Accessibility assessment of South Worcestershire Development
Plan (2011) 29
4.6 Spreadsheet model assessment of South Worcestershire
Development Plan (2011) 29
5 Baseline and Do-Minimum Network Problems/Issues 31
5.1 Introduction 31
5.2 Worcester – analysis of the 2008 Base SATURN Model 31
5.3 Worcester – analysis of the 2026 forecast SATURN Model 32
5.4 Worcester Transport Model – South Worcestershire Development
Plan 2 (June 2014) 34
5.5 Droitwich, Great Malvern, Pershore, Evesham 35
5.6 Passenger transport and sustainable modes of transport 39
4
6 Scheme Identification 42
6.1 Introduction 42
6.2 Scheme identification methodology 42
6.3 Overview of schemes 45
6.4 Scheme tables 45
7 Conclusions and Next Steps 47 7.1 Conclusions 47
7.2 Potential future activities 47
Appendices
Appendix 1: SWDP2: (2014) Transport Schemes Summary Tables
Appendix 2: Worcester Transport Model Technical Note SWDP
2
Appendix 3: Transport Schemes Summary Table
5
1 Executive Summary
Introduction
Malvern Hills, Worcester City and Wychavon Councils are collaborating to prepare a
joint Development Plan with the aim of ensuring that future development within
South Worcestershire is well planned and managed effectively, whilst having a
positive impact on the economy and the environment.
The joint Development Plan is called the South Worcestershire Development Plan
(SWDP). It considers the long term vision and objectives for South Worcestershire up
to the year 2031 and includes the policies for delivering these objectives in a planned
and cohesive manner.
In October 2013 the proposed Draft SWDP housing and employment allocations were
considered at an Examination in Public (EiP). The Inspector’s consideration of the
contributions made resulting in the three Districts being required to identify
additional allocations for residential development above that included in the Draft
SWDP. In response to the EiP Inspector’s report, revised SWDP housing allocation
figures were released in May 2014. For the purposes of this document the
development allocations released in May 2014 are termed SWDP2. It should be noted
that the proposed employment land allocations remain unchanged from the earlier
proposed Draft SWDP employment allocations.
CH2M HILL has been commissioned to support Worcestershire County Council
(WCC) with identifying the necessary transport related infrastructure and public
transport services to mitigate the impact of the proposed allocations, and giving
advice on and preparing the transport evidence to fulfil the requirements of the
Infrastructure Delivery Plan (IDP). The transport infrastructure (highway, public
transport, cycle and pedestrian) and public transport services identified are based on
the housing and development assumptions set out in the SWDP2.
The IDP will give details of the infrastructure that is required to support the growth
set out in SWDP2. It is envisaged that the information set out in the IDP will be used
to develop a Community Infrastructure Levy (CIL), and to inform and support
negotiations with developers about site specific s106 (and other relevant) agreements
to contribute towards their impact on the local and strategic transport network.
The IDP will also inform the further development of the LTP3 and associated
transport packages (infrastructure and service schemes), including the inter‐urban
links between the key urban areas, the Worcester Transport Strategy, the packages for
Droitwich, Evesham, Malvern, Pershore and the wider rural hinterland. This will
help to ensure that the transport improvements are integrated with and take full
account of cumulative impact on the transport network of the planned land use
changes contained within SWDP2. This package approach will help to avoid a
piecemeal and potentially poorly targeted approach to investment in transport which
will do little to support economic growth or encourage sustainable development.
Approach
A key premise of this project is to recognise that the quantum of development
proposed in South Worcestershire will not only have a local transport impact
6
immediately adjacent to the site but also on the local and strategic transport network
further afield (including the Highways Agency and Network Rail managed
networks).
The local impacts of any development can be directly identified, assessed and local
access and other minor mitigation measures implemented, however, for the strategic
transport network and locations further away from the proposed development sites,
whilst the transport problems which arise as a result of cumulative growth in travel
demand are all too readily obvious, the cause may not be clear to all. The cumulative
impact is a key issue for Worcestershire County Council (and its key stakeholders) as
it has to manage the network such that it supports the key policy aim of supporting
economic growth. This aim would be undermined in the event of increased costs
being imposed on businesses, other network users and transport operators arising
from traffic congestion, inadequate levels of service on and performance of the rail
and bus networks, and increased and variable journey times and costs. It is critical,
therefore, that the cumulative effects of increased travel demand are properly
understood and mitigating measures identified.
The identification of the source of issues away from the immediate environs of
development sites can demonstrate that a relatively small development site (or the
summation of a number of small development sites) can cause a significant issue on
the transport network as a result of both local and long distance trips. In identifying
the cumulative effects of growth it is possible to both develop adequate (network
wide) mitigation and to provide the evidence which underpins the requirement that
the identified sources of additional traffic (vehicular and all person trips) should
contribute appropriately toward the costs of delivering the necessary improvements
to the wider transport infrastructure.
In order to undertake a network wide assessment of the transport network in South
Worcestershire and specifically to assess the cumulative transport impact on
transport networks resulting from development sites proposed through the SWDP2, a
Vehicle/Trip Generation modelling tool has been developed. The modelling tool
enables:
The calculation of the numbers of trips that each proposed development site will
generate;
An assessment of the way in which those trips will route on the network; and
The summation of trips to establish an overall (cumulative) impact.
The modelling tool, in the form of a strategic gravity model, draws upon existing
evidence and previous related SWDP studies, namely:
Worcester Multi‐Modal Transport Model;
Evesham, Pershore, Malvern and Droitwich Town Development Models;
Accessibility Assessments; and
WCC Officer Workshops.
Where appropriate the Vehicle/Trip Generation Model was validated for consistency
against the previous studies and the Worcester Multi‐Modal Model.
7
Development Assumptions
The revised land use assumptions underpinning this work have been provided by the
SWDP Planning Authorities in response the EiP Inspectors Report.
For clarity, the transport infrastructure (highway, passenger transport, cycle and
pedestrian) and passenger transport services identified are based on the SWDP2 land
use assumptions provided to CH2M HILL by Worcestershire County Council in May
2014. These land use assumptions supersede those set out in the Draft SWDP
Significant Changes (provided to CH2M HILL in September 2012) and the Draft
SWDP Preferred Options (provided to Halcrow in November 2011).
Table 1 shows the overall quantum of residential and employment development
figures modelled for the SWDP2 and the resulting forecast number of 24 hour
development trip demand for Vehicles, Pedestrians, Cyclists and Bus.
Table 1: SWDP2 Development Site – Development Assumptions and Total Trip
Generation (24 hour period – Vehicles, Pedestrians, Cyclists, Bus)
Development Assumptions
2019 Forecast Model 2031 Forecast Model
Residential (Dwellings) 9151 19434
Employment (Hectares) 118 170
Commitments
(Residential Dwellings)
Commitments
(Employment Hectares)
Windfalls
(Residential Dwellings)
414 1406
38 101
797 2013
Completions 6989 6989
Demolition / Non Delivery of Commitments
Total Trips
Total 24 hrs Development Trips
(Vehicles, Walk, Cycle, Bus)
‐110 ‐110
341775 587561
8
Evidence
In proposing future year transport infrastructure and service schemes, the work has,
where appropriate and the evidence demonstrates a need, drawn on existing LTP3
Transport Packages. For example, scheme proposals identified through the Worcester
Transport Strategy have been taken as the core schemes for Worcester and locations
and/or schemes identified through the ‘Development Traffic Impact Assessment’ work
have been used as a basis for the towns (Droitwich, Evesham, Malvern and
Pershore). This previous work provides a reasonable starting point as it included, as
input, previous SWDP (and in some cases SWJCS) land use assumptions.
Where additional issues have been identified in both Worcester and the four main
towns, and for areas not previously covered, this project has identified further locations
where mitigation is required to overcome or reduce the impact of proposed
development. That is, there are locations outside Worcester that do not currently have the
benefit of an existing package of measures identified through the LTP3 strategy.
Furthermore, there are some development sites that were not considered at the time the
LTP3 strategy was developed. For these sites, an additional task has been undertaken to
identify schemes and other mitigation measures. These proposed schemes have been
identified with the assistance of the Vehicle/Trip Generation Model.
Schemes
The transport schemes proposed have been identified to mitigate the transport
impact and hence support the growth proposed for South Worcestershire. The
proposed highway infrastructure schemes aim to improve capacity at key junctions
which are anticipated to incur additional delays in future years as a result of the
housing and employment growth proposed for the SWDP area.
The proposed sustainable transport infrastructure schemes aim to connect the
SWDP2 development sites to the existing transport network and where appropriate
improve the existing transport network to encourage greater use of more sustainable
transport modes and maximise the performance of the transport network to meet
economic and environmental policy aims.
In developing the IDP transport scheme proposals, relevant policy/strategy,
feasibility/deliverability and the appropriate design standards and guidelines have
been considered to ensure that schemes are appropriate and practicable (subject to
funding). A fundamental requirement of the infrastructure delivery plan is that the
schemes can be implemented to the same programme as the proposed development.
Hence, possible solutions which would have potentially longer planning and/or land
ownership issues have not been included in the infrastructure list.
It should be noted, however, that in view of the early stage of development of a
number of the transport schemes, there may well remain planning and/or land
acquisition issues that will need to be overcome and more detailed designs are
prepared. This has, necessarily led to a cautious approach has been taken in the costing
of schemes.
9
Scheme Costs
Each of the proposed transport schemes is accompanied with a cost for
implementation. Costs include construction costs, relevant percentage uplifts to
account for scheme preparation and development costs over and above the basic
construction and materials and ʺoptimism biasʺ (reflective of the stage of
development of scheme designs). An estimate is also made of the maintenance costs
of the schemes over a 30 year period.
A breakdown of the costs for the proposed transport schemes on a mode‐by‐mode
and town‐by‐town basis is provided below. Where schemes fall outside the towns the
cumulative costs are shown in the interurban/rural table.
Please note that these costs exclude those associated with the Highways Agency
Trunk Road network. Whilst Worcestershire County Council and the Highways
Agency have been working closely together on transport issues and have shared data
where appropriate, the Highways Agency will be reporting separately on the
measures needed to mitigate adverse impacts on the performance of their network
and the associated costs.
Table 2: Worcester Schemes – Highway and Walk, Cycle and Passenger Transport
Worcester Costs (£/millions)
Worcester Transport
Strategy &
Total (Incl. Constru ction, Contingency,
Risk and Optimism Bias) (1) (2) (3) Ongoing Maintenance and/or
Operating Costs (4)
Additional IDP
Highway Measures
(5) (6)
Additional
Worcester IDP
Sustainable
Measures
£163,490,000 £40,870,000
£21,710,000 £5,427,500
Table 3: Highway Schemes
Droitwich Spa
Costs (£/millions)
Total (Incl. Construction, Contingency,
Risk and Optimism Bias) (1) (2) (3
£3,620,000
Ongoing Maintenance and/or
Operating Costs (4)
£905,000
Evesham (8) £1,200,000 £300,000
Malvern £5,640,000 £1,410,000
Pershore £1,050,000 £262,500
Inter‐Urban (7) £4,070,000 £1,017,500
10
Table 4: Walk, Cycle & Passenger Transport Infrastructure
Costs (£/millions)
Total (Incl. Construction,
Contingency, Risk and Optimism Bias)
Ongoing Maintenance and/or
Operating Costs (4)
(1) (2) (3) Droitwich Spa £8,748,000 £2,187,000
Evesham £7,600,000 £1,900,000
Malvern £710,000 £177,500
Pershore £3,360,000 £840,000
Rural Malvern Hills £220,000 £55,000
Rural Wychavon £2,290,000 £572,500
Notes:
(1) This accounts for Supervision, Evaluation, Drainage, Preliminary Design, Site Supervision,
Design Services and Utilities, Landscape, Traffic Management TM, Groundworks/Earthworks,
Maintenance, Consultation, Ecology
(2) Optimism Bias represents a contingency allowance reflecting the early stage in the development
of schemes. It is a standard approach developed by the DfT to avoid over‐optimistic estimates of
transport infrastructure costs
(3) Costs EXCLUDE any land acquisition and CPO costs in the event that these are required
(4) Maintenance costs are for 30 years from completion of works and are the expressed as % of total
construction costs at this stage in scheme development
(5) EXCLUDES allowance for: M5 Junctions 6 and 7 works (BUT these to be assessed by HA).
INCLUDES allowance for: A4440/SLR capacity enhancements, Key corridors enhancements,
traffic signal enhancements (SCOOT/MOVA etc.), amended TRO’s, improvements to Worcester
Foregate Street & Shrub Hill rail stations a new Worcestershire Parkway, improved bus stop
infrastructure, Real Time Information Systems, new/improved walk and cycle routes and
additional bridge
(6) Excludes City and Town Centre Public Realm Improvements
(7) Includes improvements to A44, A38 and A449
(8) Excludes allowances for works to A46 junctions (BUT these to be assessed by HA).
The total costs across South Worcestershire for infrastructure and maintenance
(not including the exclusions below) are as follows:
Infrastructure: £223.708 million
30 year Maintenance: £55.924 million
Additional costs not included on summary tables (tables 2‐4)
Please note that the above tables and costs exclude some elements of transport
infrastructure and passenger transport service improvements. Specifically they do
not include:
Passenger Transport Operation Enhancements: 2019 Annual Cost;
£37.21 million; 2031 Annual Cost; £57.55 million. The transport evidence
presented shows that enhancements to local and regional passenger transport
11
services will be required to address accessibility issues, reduce traffic
generation, manage traffic congestion and support the delivery of sustainable
development. Potential enhancements have been identified along with an
estimate of operating costs (before revenue), however, further work will be
required to identify the net increase in operating costs after allowance
has been made of development generated demand and revenues. The
figures associated with these cost estimates are contained in Appendix 3.
Inter‐Urban Walk and Cycle Infrastructure: £18.95 million. Schemes have been
developed which provide improved walk and cycle links between the main
urban areas in South Worcestershire (e.g. Malvern – Worcester). These links
would also serve a number of the proposed developments within the Draft
SWDP and would serve a dual function of providing increased choice of
transport modes for journeys generated by the new development and also
support increased leisure use which will benefit both existing and new
developments and the tourist/leisure industry. Further work is underway to
identify the capital and ongoing maintenance costs of such measures and the
extent to which the Draft SWDP is dependent upon their delivery. The figures
associated with these cost estimates are contained in Appendix 3
PT Corridor Improvement Schemes: £172.17 million. Cost estimates for South
Worcestershire Bus Priority Route Corridors. The figures associated with these
cost estimates are contained in Appendix 3.
12
2 Introduction
2.1 Background
Malvern Hills, Worcester City and Wychavon Councils are collaborating to prepare a
joint Development Plan with the aim of ensuring that future development within
South Worcestershire is well planned and managed effectively, whilst having a
positive impact on the environment.
The joint Development Plan is called the South Worcestershire Development Plan
(SWDP). It considers the long term vision and objectives for South Worcestershire up
to the year 2031, and includes the policies for delivering these objectives in a planned
and cohesive manner, through:
providing policies to ensure that all development is sustainable;
allocating larger ‘strategic’ sites across South Worcestershire;
identifying infrastructure requirements to support the delivery of the
development plan, including transport, education, health, water and energy.
This will be the Infrastructure Delivery Plan; and
assessing all other potential development sites whether it is for housing,
employment, retail, education, health, community use or indeed an open space
use.
The SWDP will replace the existing Local Plans of the three councils when it is
adopted. It will also supersede elements of Worcestershire County Council’s County
Structure Plan.
The extents of the three districts comprising South Worcestershire; Worcester,
Malvern Hills and Wychavon are shown in Figure 2.1
13
Figure 2.1 – Location Plan
Based upon the Ordnance Survey Map with the permission of the Controller of Her Majesty’s Stationary Office. Crown
Copyright Licence No. LA09073L Worcestershire County Council.
2.2 Purpose of this report
CH2M HILL has been commissioned to support Worcestershire County Council
(WCC) with identifying the necessary transport related infrastructure and public
transport services, and giving advice on and preparing the transport evidence to fulfil
the requirements of the Infrastructure Delivery Plan (IDP). The transport
infrastructure (highway, public transport, cycle and pedestrian) and public transport
services identified will be based on the assumptions set out in the Draft SWDP.
The Infrastructure Delivery Plan (IDP) will give details of the infrastructure that is
required to support the growth set out in the SWDP. It is envisaged that the
information set out in the IDP will be used to develop a Community Infrastructure
Levy (CIL), and to inform and support negotiations with developers about site
specific s106 and s278 (and other relevant) agreements to contribute towards their
impact on the local and strategic transport network. The IDP will also inform the
further development of the LTP3 and associated transport packages (infrastructure
and service schemes), including the inter‐urban links between the key urban areas,
the Worcester Transport Strategy, the packages for Droitwich, Evesham, Malvern,
14
Pershore and the wider rural hinterland. This will help to ensure that the
transport improvements are integrated with and take full account of cumulative
impact on the transport network of, the planned land use changes contained
within the Draft SWDP. This package approach will help to avoid a piecemeal
and potentially poorly targeted approach to investment in transport which will
do little to support economic growth or encourage sustainable development.
The methodology adopted through this study has been agreed between CH2M
HILL and WCC through the Scoping Note and Officer Meetings and
Workshops. The methodology has created a means of providing an evidence
base to justify the provision of transport infrastructure (highway, public
transport, cycle and pedestrian) and public transport services. These are
necessary to mitigate the transport impacts (vehicle access and movements,
multi‐modal trip generation) of the potential development sites identified in the
draft SWDP.
This report identifies the transport schemes required to mitigate the transport
impact and hence support the growth proposed for South Worcestershire
contained in the SWDP and provides supporting evidence to demonstrate the
way in which the transport schemes contribute towards the wider aims of the
SWDP. The report contains a description of the adopted methodology used to
derive the list of proposed transport schemes and sets the work in the context of
other transport evidence work recently undertaken in the South Worcestershire
area.
For clarity, the transport infrastructure (highway, passenger transport, cycle and
pedestrian) and passenger transport services identified are based on the SWDP2
land use assumptions provided to CH2M HILL by Worcestershire County
Council in May 2014. These land use assumptions supersede those set out in the
Draft SWDP Significant Changes (provided to CH2M HILL in September 2012)
and the Draft SWDP Preferred Options (provided to Halcrow in November
2011).
2.3 Structure of this report
Following this introductory chapter:
Chapter 3 sets out the methodology followed to identify schemes. This
includes an introduction to the spreadsheet based transport model used to
assess future trip generation by all modes of transport
Chapter 4 considers previous transport evidence work undertaken in the
South Worcestershire area and how this comprehensive review has drawn
upon and complemented the previous work undertaken.
Chapter 5 describes the baseline performance of the transport network
Chapter 6 introduces and contains the scheme tables
The report contains four appendices:
Appendix 1: Phase 1 Impacts on Network Performance (2014)
Appendix 2 SWDP2: South Worcestershire Development Plan – Planning
Data;
Appendix3 SWDP2: Transport Schemes Summary
15
3 Methodology
3.1 Introduction
The methodology used to complete this project was agreed jointly between CH2M
HILL and Worcestershire County Council. The technical scope of work was set out in
a Scoping Note dated 16th December 2011. Through discussions at various meetings
and workshops attended by CH2M HILL and Worcestershire County Council, some
minor amendments to that original scope have been agreed in order to focus the
project on the requirements of the SWDP South Worcestershire Planning Authorities.
The methodology adopted has:
Understood, from previous work, relevant policy guidance, development
quantum’s, types and locations and agreed parameters for the project;
Established the transport network and infrastructure baseline conditions for
South Worcestershire thereby understanding the general network performance
for all modes of transport and identifying potential future issues relating to
transport infrastructure and service provision across South Worcestershire;
Developed a Vehicle/Trip Generation model to act as an assessment tool to
assist with the identification of schemes to support proposed development
contained in the draft SWDP; and
Identified infrastructure schemes and services to mitigate against the impacts
of proposed development.
The methodology adopted has ensured that the best use was made of existing data
and tools available. It has set a clear foundation for the identification of schemes and
has provided a means by which complex cumulative ‘knock on’ effects can be
identified and assessed.
The process by which infrastructure schemes have been identified has recognised
both environmental and deliverability factors as well as requirements to address
network capacity issues and create opportunities for more sustainable travel choices.
The overall approach has been based on delivering achievable interventions across
the network and thus does not rely on an approach focussing on a single or limited
number of schemes that could not be implemented in the required timescale.
3.2 Need for assessment
A key premise of this project is to recognise that the quantum of development
proposed in South Worcestershire will not only have a local transport impact
immediately adjacent to individual sites but also a wider network impact across the
SWDP area. That is, whilst the local impacts of any one development can be directly
identified, assessed and mitigation measures implemented, for the wider transport
network. Whilst the wider transport network issues to address are all too readily
obvious, without a means of undertaking a wider network assessment the cause and
identification of which site(s) should be attributed may not be.
16
Hence, as the methodology considers the wider network, the identification of the
source of issues away from the immediate environs of development sites can show
that a relatively small development site (or the summation of a number of small
development sites) can cause a significant issue on the wider transport network as a
result of long distances trips. By identifying the cumulative effects of growth it is
possible to develop adequate mitigation to address wider network issues. In doing so,
the methodology provides the evidence that justifies the assessment that has
identified generators of additional traffic (vehicular and all person trips). Hence, the
process identifies which sites should contribute appropriately toward the costs of
delivering the necessary improvements to the wider transport infrastructure.
Thus a tool that allows the:
calculation of the numbers of trips that each proposed development site will
generate;
the assessment of the way in which those trips will route on the network; and
has the ability to sum the trips to establish an overall impact assessment
….will enable a network wide assessment to be conducted. Such an assessment tool
has been prepared for South Worcestershire. Whilst the tool is necessarily strategic in
nature, it does include all the key routes and, most importantly, key junctions.
Without such a tool it is difficult to assess the combined impact of development sites
over a large area.
Existing data, and recently undertaken transport network assessments in South
Worcestershire also provide the means to identify the need for transport
infrastructure and services resulting from the proposals in the Draft SWDP, the
source of this data includes the Worcester Multi‐Modal Transport Model, accessibility
assessments, South Worcestershire Town development models (Malvern, Pershore,
Evesham and Droitwich). A review of previous studies informing the IDP and the
associated transport scheme proposals is provided in Section 3 of this report.
3.3 Development of assessment tool
The assessment tool is a spreadsheet model that combines a number of functions:
Multi‐modal trip generation model;
Trip routeing model;
Gravity model; and
Presentation and analysis of results.
In summary, the model provides a means of assessing the cumulative assessment of
the impact of the SWDP development on the highway network across South
Worcestershire for the AM and PM peak periods. The development allocations
assumed, provided by the SWDP planners,. The model covers the AM and PM peak
periods and provides trip generation data for walk, cycle, passenger transport (bus)
and highway for both the AM and PM peak periods and a full 24 hour period.
The model concentrates on the SWDP area, but recognises key destinations for travel
beyond south Worcestershire. The assignment of highway trips is based on the
17
strategic road network serving the south Worcestershire area. That is, the main ʹA‐
roads’ and key ‘B’ class roads in the area and the Highways Agency managed
Motorway and Trunk Road network.
In terms of non car trips (sustainable modes), the model contains a ‘multi‐modal trip
generation’ calculation. The model indicates the likely number of trips by walk, cycle,
and passenger transport (bus and rail) modes from each of the planned
developments. The model takes account of relevant local mode share data and
applies appropriate trip rates to indicate the number of additional trips on the
transport network resulting from the proposed SWDP development sites. dix A.
3.4 Overview of assessment results
The Vehicle/Trip Generation Model has been used to assist the identification of the
schemes to be included within the SWLP IDP. Appendices E and F of the SWDP2:
Impacts on Transport Network Performance Technical Note (Appendix 1) contains a
listing of trip generations from each planned development cluster/site. The results
have been used to identify the locations where schemes should be considered to
overcome the pressure points in the network shown to be an issue in the forecast year
scenario. It is noted that the model has not been the sole source of scheme
identification, other sources of evidence include:
Worcester Multi‐Modal Transport Model;
Evesham, Pershore, Malvern and Droitwich Town Development Models;
Accessibility Analysis of Walk, Cycle and Passenger Transport (bus and rail); and
WCC Officer Workshops.
These sources have all combined to provide a comprehensive assessment of network
requirements to accommodate forecast development proposals. The inputs from this
assessment are set out in Section 3 of this report.
3.5 Overview: existing highway Issues
A review of the existing highway network across the South Worcestershire area
shows the strategic A‐road network to form a ‘spoke’ like effect spreading from
Worcester (as the main residential and employment centre in the area) to the
surrounding towns and rural areas. A‐roads provide links to Worcester from the
following towns, Stourport/Kidderminster (A449 north), Droitwich (A38), Pershore
and Evesham (A44), Great Malvern (A449 south and A4103) and the A38 south to
Upton and Tewkesbury/Gloucester.
In addition to this network of main roads, the M5 Motorway travelling north to
south, lies immediately east of Worcester, providing a high quality link to the West
Midlands conurbation, the South West and via the M50 South Wales. Worcester is
linked to the M5 via Junction 6 (Worcester North) and Junction 7 (Worcester South).
The main east to west route through the area is the A44, linking to Oxford and the
Cotswolds to the east and to Leominster and Mid‐Wales to the west.
Worcester has a network of by‐passes (A4440 in south and east Worcester and A449
in north Worcester) which is formed by sections of single and dual carriageways. The
southern bypass (A4440) provides one of two road links over the River Severn
18
through Worcester, the other being in the City Centre (A44). All of the major A‐Road
routes to Worcester from the surrounding towns join with junctions on the partial
ring road around Worcester (A449 and A4440).
Due to the strategic pattern of the A‐Road highway network in South Worcestershire
and its links to the M5, trips routeing between the main population and employment
centres in the area generally route via Worcester, using sections of the A449 and
A4440 around Worcester and key junctions on these links. These traffic volumes
mean that the A449 northern bypass and the A4440 southern and eastern bypass are
key corridors for through trips as well as distributing local trips to Worcester.
It is noted that the cumulative impact of SWDP proposals is greatest at these
locations.
This pressure on the highway network in and around Worcester is shown by
evidence from the Worcester Transport Model and the associated Road Side
Interview data collected as part of the model development. This data shows that there
are a large proportion of ‘through trips’ routeing through the Worcester area.
Although a high percentage of these trips travel through the area to access the M5, a
significant proportion are trips which, at some point, pass through junctions located
along the Worcester Bypass (A4440 and A449). As a result there is a conflict between
key junctions that allow trips into Worcester City Centre and through trips routeing
around Worcester on the A449 and the A4440.
The major development sites, proposed through the SWDP, will contribute to
additional local and longer distance traffic routeing through these key corridors due
to their proposed locations, the layout of the existing strategic road network and
likely trip origin and destination patterns. This has an impact on the location and
scale of transport schemes resulting from this SWDP IDP assessment and other
transport network performance reviews associated with the development of the
Worcester Transport Strategy and the Worcestershire LTP3. In particular there is a
need to address capacity constraints to the south of the city and to ensure that the
planned major urban extensions are designed from the outset to maximise use of
walk, cycle and passenger transport modes, particularly for journeys to/from/within
Worcester City.
For the other towns, the assessment has found that there are issues to address as a
direct result of development proposals, with some identified cumulative impacts on
the wider transport network. That is, issues are predominantly associated with
individual sites or clusters of development local to the town. Hence the mitigation
schemes identified tend not to be of such a significant nature, but there are a number
of locations that will need mitigation as a result of development.
The South Worcestershire Strategic Road Network is shown on Figure 3.1
19
Figure 3.1 – South Worcestershire Strategic Road Network
Based upon the Ordnance Survey Map with the permission of the Controller of Her Majesty’s Stationary Office. Crown
Copyright Licence No. LA09073L Worcestershire County Council.
3.6 Overview of passenger transport (rail) issues
The local rail network provides a valuable contribution towards local and longer
distance travel. Indeed, the main towns in the area all have the benefit of being
connected to Worcester and regional/national destinations by the rail network.
However, as noted in WCC’s contribution to the Greater Western rail franchise
process, there are limited services to/from some key locations during peak times and
evening and weekend services are poor in terms of timetabling and frequencies.
Specifically, to improve service provision, WCC is seeking:
Worcester – London journey times to be 2 hours or less, fully utilising the
recent investment in Cotswold Line infrastructure and planned investment in
infrastructure between Oxford and London or by raising line speeds between
Evesham and Moreton‐in‐Marsh.
To have, by the end of the franchise period, two trains per hour between Great
Malvern, Worcester and London Paddington, with one train per hour running
fast or semi – fast between Worcester and Oxford.
20
Further Cotswold Line redoubling to improve reliability and journey times
including new signalling and track layout in Worcester city centre.
An improved rail service between Worcester, Cheltenham and Gloucester that
is fit for purpose and meets the demand for travel between Worcestershire and
Gloucestershire. This will involve a regular service throughout the day,
reduced journey times and improved quality rolling stock in use.
There is, therefore, an opportunity to improve the provision of rail services on the
existing network that could result in a mode shift to rail for local and longer distance
journeys, and consequently help meet LTP3 objectives to provide greater accessibility,
reduce carbon emissions and protect the environment. Access to railway stations by
all modes is also key to meeting economic and environmental objectives.
In addition to improvements to the existing rail service pattern, WCC is actively
promoting the introduction of a new ʺWorcestershire Parkwayʺ station at the
intersection between the Cotswold Line and Bristol – Birmingham line at Norton, east
of Worcester, to be served by all Worcester – London services (and a proportion of
Bristol/Cardiff – Birmingham services).
The Worcestershire Parkway business case was updated during 2012 (in line with
Department for Transport appraisal guidelines). The findings of that work is that
operationally both Worcester – Oxford/London and Cross‐Country services could be
accommodated at a new station and that the proposed station has a strong economic
case with a benefit: cost ratio of 3:1, and approximately 0.3 million passengers per
annum forecast to use the station. The financial case for the scheme is also strong with
a net operating surplus for train operating companies of approximately
£0.75m/annum (excluding car parking revenues).
The Railway Lines on which passenger services operate are shown on Figure 3.2
21
Figure 3.2 – South Worcestershire Rail Network
Based upon the Ordnance Survey Map with the permission of the Controller of Her Majesty’s Stationary Office. Crown
Copyright Licence No. LA09073L Worcestershire County Council.
3.7 Overview: existing local passenger transport (bus) issues
In terms of passenger numbers, the local bus network is the most important
passenger transport mode in South Worcestershire, recognising that rail is the
dominant mode for regional and inter‐city journeys. For many of the planned new
developments, the local bus network will provide the only passenger transport choice
for journeys to/from/within urban areas. It is critical, therefore that new
developments are planned from the outset to accommodate and support efficient and
ideally commercial (i.e. not reliant on public subsidy) local passenger transport
services. Failure to do so will make it difficult for commercial operators to deliver the
services needed to manage travel demand and support sustainable development.
The existing bus network operating in South Worcestershire, in terms of its proximity
to proposed SWDP development sites is described below.
The bus network in operation across South Worcestershire is concentrated on and
within Worcester. Service patterns connect the outlying residential and employment
22
districts on the edge of the city with the city centre. The main 4 towns surrounding
Worcester, namely; Droitwich, Great Malvern, Pershore and Evesham are served by
inter‐urban routes connecting to Worcester and other towns surrounding the study
area. The network is key to providing access to employment, training and social
opportunities whilst providing benefits to maximising the performance of the
transport network and meeting economic and environmental objectives.
In order to accommodate the growth contained within the Draft SWDP a set of bus
operation standards have been developed by WCC, consistent with the policies set
out in the Worcestershire LTP3. An assessment of total cost to provide services to
these standards to each SWDP2 development cluster has been calculated. It is
recognised that these services may be already provided on a commercial or
subsidised basis, either wholly or in part. Hence the role of the IDP is to ensure that
this level of service is maintained in order to retain the attractiveness of services as an
alternative to the car and to provide the necessary capacity to accommodate the
forecast bus passenger demand. If this level of service is not met, whilst some
individuals may have the ability to transfer mode to use a car (resulting in increased
pressure on the highway network), for others potential travel opportunities by bus to
access employment, education and health opportunities will be lost.
These local bus service operations requirements would need to be accompanied by
infrastructure to deliver a reliable and attractive local passenger transport network.
These include stop and station infrastructure and access arrangements to these from
the development sites, as well as measures to protect service reliability and journey
times at the most congested locations. Stop and station provision is proposed to fit
with WCC’s ‘Gold’, ‘Silver’ and ‘Bronze’ standards for passenger transport service
corridors, these are based upon the service frequency. For those corridors in
Worcester the WTS has already undertaken detailed study work and established a
cost to provide the necessary infrastructure to address reliability issues.
For those locations beyond Worcester, where a detailed review and consultation with
stakeholders along the routes would be required, a means of assessing the funding
requirement to create a reliable passenger transport service corridor has been
developed. From the Worcester Transport Strategy schemes it is possible to develop a
‘cost rate’ for ‘corridor infrastructure measures’. From the three WTS corridors that
have been costed in detail a cost rate of £170,000 per 100m for ‘general measure to
improve service reliability and quality’ has been calculated.
Applying the WTS derived cost to other urban/inter‐urban corridors has provided a
methodology to estimate a cost to implement the suite of measures needed to deliver
the desired bus service and infrastructure standards.
3.8 Overview of existing pedestrian network
Maximising pedestrian movements at key trip attractors and generators, including
railway stations, is key to improving the efficiency of the transport network
(particularly in congested urban areas) and meeting national and local economic and
environmental objectives. It is important, therefore that planned new developments
take full account of policies and best practice design standards that relate to
maximising walk accessibility within developments and also linking to destinations
that are within a reasonable walk distance.
23
To identify pedestrian infrastructure requirements to support the development
assumptions put forward through the SWDP, each development site has been
considered in turn. The number of anticipated pedestrians travelling to and from
each site over a 24 hour period has informed the process.
The analysis focussed on identifying links from the proposed development sites to
the existing pedestrian network in terms of footways and pedestrian crossing
facilities where required. The infrastructure requirements include linkages from the
proposed development sites to existing links surrounding the sites, but not
pedestrian infrastructure within the development sites.
3.9 Overview of existing cycle network
Encouraging cycling as a mode of transport has benefits in terms of improving the
efficiency of the transport network (in particular in urban areas) as well as bringing
health benefits. It is important, therefore, that planned new developments take full
account of policies and best practice design standards that relate to maximising cycle
accessibility within developments and also linking to destinations that are within a
reasonable walk distance.
The cycle network in South Worcestershire comprises of a combination of
recommended on‐road routes (that have been assessed for suitability) and a series of
dedicated off road routes, some of which form part of the National Cycle Network.
The cycle route maps for South Worcestershire (taken from the WCC website) have
been used to assess linkages from proposed development sites to existing cycle
infrastructure.
In order to identify cycle infrastructure requirements to support the development
assumptions put forward through the SWDP, each development site has been
considered in turn. The number of anticipated cyclists travelling to and from each site
over a 24 hour period has informed the process. Analysis has focussed on identifying
links from the proposed development sites to existing cycle infrastructure, it has been
assumed cycle infrastructure within the development sites will be considered by
developers and will meet relevant LTP3 and other policy & design standards, this
includes all cycle paths and the appropriate amount of cycle storage facilities. The
cycle infrastructure included on the proposed list of schemes includes all aspects of
cycle infrastructure including signage, on‐road cycle marking and where appropriate
dedicated off road cycle links.
24
4 Review of previous SWDP work
4.1 Introduction
In order to ensure alignment between all transport studies highlighting requirements
for future year transport infrastructure within South Worcestershire, the following
information and studies have informed this project;
Worcester Transport Strategy;
Worcester Transport Strategy – Phase 1 – Major Scheme Bid and BAFFB (2009‐
2011);
Worcester Transport Model and Worcester Transport Model Assessment of
South Worcestershire Development Plan (2011);
Worcester Transport Model – South Worcestershire Development Plan 2 (June
2014);
Accessibility Assessment of South Worcestershire Development Plan (2011);
and
Spreadsheet Model Assessment of South Worcestershire Development Plan
(2011).
A brief discussion of how each of the studies was used follows.
4.2 Worcester Transport Strategy
The Worcester Transport Strategy (WTS) has been developed to identify a
programme of investment in transport infrastructure, to deal with existing and future
year transport challenges for the City of Worcester and across South Worcestershire.
The complete programme of investment would cost an estimated £200 million. The
proposed improvements to the existing network will include the following measures
and are shown on Figure 4.1:
Strategic Highway Improvements including the dualling of the Southern Link
Road;
Key corridor improvements to enhance the main routes into and out of the city
for all users, improving traffic flow and reducing congestion this includes all
main radial routes and the orbital route linking the Southern Link Road/M5
Junction 7 with the employment, health, education and leisure facilities located
to the east/north east/north of Worcester ;
Local Highway Improvements including junction, signals and pavement
enhancements;
Rail station enhancements;
The construction of a new Railway Station (Worcestershire Parkway);
Improvements to infrastructure and services for walking and cycling;
25
Implementation of Intelligent Transport Systems to improve efficiency and
choice;
Enhancement of the City Centreʹs public realm, transport infrastructure and
services and;
Smarter Choices measures ‐ incentivise greater use and improvement to the
perception of sustainable modes (walking, cycling, passenger transport). .
In developing the list of schemes for the South Worcestershire Infrastructure Delivery
Plan, CH2M HILL has been mindful of the considerable work undertaken to develop
the Worcester Transport Strategy and associated Major Scheme Bid (see below) and
has thus not sought to duplicate this work. In developing the Worcester Transport
Strategy the planned development/land use assumptions were consistent with the
emerging SWDP. Similarly, the Major Scheme Business case submitted to the
Department for Transport used the latest land use assumptions available at the time
of submission.
Not unsurprisingly the pressure points on the network identified through the WTS
process have been found to be consistent with those identified through this project.
Hence, the list of highway, passenger transport, cycle and walk schemes included in
the Worcester Transport Strategy has all been included in the Infrastructure Delivery
Plan.
With specific regard to the highway impact assessment work completed to inform the
IDP, the highway junctions proposed to be upgraded through the SWDP work are
consistent with the issues identified through the modelling work completed to inform
the WTS. That is, the junctions identified as requiring investment through the WTS
are all shown to require upgrading as result of the additional pressure on the
highway network associated with the additional housing and employment
development proposed through the South Worcestershire Development Plan.
26
Figure 4.1 – Worcester Transport Strategy
Worcester
(BAFFB)
Transport Strategy Phase 1 – Major Scheme Bid September 2012
In December 2011 Worcestershire County Council was successful in securing £14.2
million from the Department for Transportʹs Major Scheme Fund, the total cost of
Phase 1 being £19.6 million. The proposals contained within the funding bid include:
Strategic Highways Improvements: Enhancements to the key junctions on the
Worcester Southern Link Road, to improve traffic flow, particularly at peak
times and reduce transport costs to businesses and road users;
Rail Station Enhancements: This will involve investment and improvement in
passenger and interchange facilities at Worcester Foregate Street and Malvern
Link stations, helping to improve the quality of rail travel and encourage
increased use of these under‐utilised transport assets. The improvements to
passenger facilities to Worcesterʹs Foregate Street will include upgrading of
signage, the ground level waiting area, information and ticketing facilities,
lighting, security and improved sheltered walk links to Foregate Street and its
taxi ranks and bus stops.
Key Corridor Improvements: This will involve investment in key corridors to
improve the quality of transport infrastructure and public realm along these
routes. This will help to smooth traffic flows and improve conditions for all
road users;
27
Transport Information Systems: Measures to provide users with better, more
accurate information on the transport network, with the aim of increasing
network efficiency. For example, variable message signs will direct car drivers
to city centre car parks which have available capacity, while public transport
users will be provided with real time information on services via mobile
phones and at stop/station signs.
Improved infrastructure for walking and cycling: This would involve
enhancements designed to encourage more local trips on foot and by bike. The
improvements to passenger facilities to Worcesterʹs Foregate Street will be on
the ground level and include upgrading of the waiting area, signage,
information, shelters, lighting and security.
Figure 4.2 illustrates the location of the Phase 1 schemes.
Subject to Full Approval by the Department for Transport, these improvements will
be delivered over the period 2012/13 – April 2015.
28
Figure 4.2 – Worcester Transport Strategy Phase 1
4.3 Worcester Transport Model and Worcester Transport Model Assessment
of South Worcestershire Development Plan (2011)
In order to satisfy DfT requirements to assess scheme for DfT funding, a detailed
multi‐modal variable demand model was required to inform the scheme assessment
process. This model is known as the Worcester Transport Model (WTM). Where
possible the same assumptions used through the development of the WTM have been
used to develop the spreadsheet gravity model for the IDP project. For example,
vehicle trip rates for development sites in Worcester are consistent between the
Worcester Transport Model and the gravity model built for the purposes of the
Infrastructure Development Plan.
As noted under the WTS commentary above, the work undertaken for SWDP and the
work undertaken for WTS is revealing the same patterns of movement and hence the
same issues to be mitigated against.
4.4 Worcester Transport Model – South Worcestershire Development Plan 2
(June 2014)
The results of transport modelling work undertaken using the Worcester Transport
Model to assess the proposed SWDP2 development assumptions as provided in May
2014 have been considered.
29
4.5 Accessibility assessment of South Worcestershire Development Plan
(2011)
A meeting was held with WCC officers’ to gain an understanding of local issues and
to draft a list of possible infrastructure requirements. This resulted in a list of
sustainable transport schemes to support the SWDP development proposals. The
draft list of schemes was considered against the findings of the Accessibility
Assessment of South Worcestershire Development Plan completed in 2011 in order to
finalise the list of sustainable infrastructure proposed through the Infrastructure
Development Plan.
The assessment analysed accessibility by walk, cycle and passenger transport to key
employment, health, education, retail and leisure destinations. The assessment
concluded that accessibility by walk, cycle and passenger transport is poor for a
number of sites, with accessibility in more rural areas in general being poorer.
It concluded that investment in transport infrastructure and services across all modes
of transport, and broadband networks, will be required if network performance is not
to deteriorate and lead to a decline in economic and environmental performance. This
investment is likely to be significant in some cases.
The sites in rural areas are likely to require a combination of investment in broadband
networks, passenger transport services (including in some cases Community
Transport) and strengthening of local service provision (i.e. within walk & cycle
distance) if residents are not to be dependent upon the car to access key services and
facilities.
The ongoing financial costs of sustaining accessibility in rural areas will be an
important consideration as the ability of the County Council to increase its
maintenance and subsidy budgets is constrained. The role of the private sector in
contributing toward both the costs of both infrastructure provision and associated
increased and ongoing maintenance/subsidy is critical in this respect.
4.6 Spreadsheet model assessment of South Worcestershire Development
Plan (2011)
During 2011 WCC commissioned CH2M HILL to produce a series of spreadsheet
gravity models to assess the highway impact of potential new development strategies
for the following towns within South Worcestershire;
Droitwich;
Great Malvern;
Pershore; and
Evesham
The purpose of these models was to establish the potential cumulative impact of
locating new development within and around the towns. They also helped inform
discussion on the potential for mitigation measures.
It should be noted that these spreadsheet gravity models were built for different
purposes to the model developed for the purposes of the SWDP IDP (SWDP
Vehicle/Trip Generation Model) and hence there is some difference in the
30
methodology and input data used. However, a sense check between the models has
been undertaken to ensure consistency between the proposed recommendations. The
results indicate that no matter what methodology is chosen, a similar set of
conclusions drawn to which highway junctions require investment in order to
support the development proposed through the South Worcestershire Development
Plan.
31
5 Baseline and Do-Minimum Network Problems/Issues
5.1 Introduction
This section of the report provides an overview of the current situation as found in
South Worcestershire in transport terms. The previous research undertaken into the
identification of current and forecasting of future transport network performance has
provided a comprehensive database of problems and issues. This section of the report
draws on that work.
5.2 Worcester – analysis of the 2008 Base SATURN Model
Analysis of the performance of the highway network across Worcester, using the 2008
base year Worcester Transport Model, indicates a number of key radial and orbital
corridors which are performing at levels approaching, at or over capacity. These
corridors include the following and are shown on Figure 5.1;
A4440 Southern Bypass;
A449 Northern Bypass;
A449 Bromwich Road;
A44 London Road;
A443 Henwick Road;
A38 Barbourne Road;
B4205 Tolladine Road and
Inner section of Newtown Road (including Lowesmoor/Pheasant Street/St
Martins Gate).
In addition to these key links and junctions on the core city centre network is also
performing at levels approaching, at or over capacity. These include:
Foregate Street/The Tything/Castle Street
St Nicholas Street
The Butts/Shaw Street
Sidebury/College Street/City Walls Road
North Quay/Dolday/Deansway
32
Figure 5.1 – 2008 Worcester Route Corridors operating at a level at, approaching or
over capacity – as indicated by Worcester Transport Model
Based upon the Ordnance Survey Map with the permission of the Controller of Her Majesty’s Stationary Office. Crown
Copyright Licence No. LA09073L Worcestershire County Council.
5.3 Worcester – analysis of the 2026 forecast SATURN Model
The Worcester Transport Model 2026 forecast year do‐minimum scenario indicates
the highway corridors in Worcester that are shown to be performing, at or over
capacity in the 2008 base year, perform worse in terms of volume over capacity ratios
the future year compared to the base year. This can be attributed to growth in
demand for travel in and around Worcester as a result of both housing and
employment growth. The additional traffic on the highway network is a result of both
local developments in Worcester and growth in travel demand from origins further a
field. The future year growth included in the 2026 SATURN Modelling work is not
site specific to the sites proposed through this stage of the SWDP work.
It should be noted that the future year development assumptions included in the 2026
SATURN Models (carried out by Halcrow in July 2011) are not exactly the same as
those modelled through the SWDP Vehicle/Trip Generation Model as provided to
Halcrow by WCC in January 2012. The work does however remain relevant and a
comparison of the model outputs indicates a similar trend in the results, that being,
the same key highway corridors are shown to be operating at capacity in each of the
models.
33
The 2026 do‐minimum SATURN Model indicates the following additional corridors
to the 2008 SATURN Model will perform at levels approaching, at or over capacity in
the 2026 future year do minimum scenario (as shown on Figure 5.2):
A4440 Eastern Bypass; and
A38 Bath Road.
A4440 Southern Bypass;
A449 Northern Bypass;
A449 Bromwich Road;
A44 London Road;
A443 Henwick Road;
A38 Barbourne Road; and
B4205 Tolladine Road.
34
Figure 5.2 – 2026 Worcester Route Corridors operating at a level at, approaching or
over capacity – as indicated by Worcester Transport Model
Based upon the Ordnance Survey Map with the permission of the Controller of Her Majesty’s Stationary Office. Crown
Copyright Licence No. LA09073L Worcestershire County Council.
Unsurprisingly, conditions on the city centre network are forecast to deteriorate
further as a result of increased traffic. This will lead to additional delays, transport
related costs and deteriorating environmental conditions (there are already
designated Air Quality Management Areas in the city and additional ʺborderlineʺ
areas). This is of particular concern given the importance of the city centre to the local
and South Worcestershire economy.
5.4 Worcester Transport Model – South Worcestershire Development Plan 2
(June 2014)
The analysis of the transport modelling work undertaken using the Worcester
Transport Model to assess the SWDP2 development assumptions demonstrates
similar trends to those shown under the 2026 modelled scenario.
The assessment of predicted volume compared to junction capacity results extracted
from the SWDP2 Worcester Transport Model scenarios show the corridors forecast to
perform with a high volume over capacity ratio are consistent with those shown
under the 2026 model scenario. These route corridors include the following:
A443 (Hallow Road);
35
A449 (Barbourne Road);
A449 (Northern Bypass);
A4440 (Eastern Bypass);
A44 (London Road);
A4440 (Southern Bypass);
A38 (Bath Road); and
A449 (Bromwich Road).
5.5 Droitwich, Great Malvern, Pershore, Evesham
The analysis undertaken using the spreadsheet models for Droitwich, Great Malvern,
Pershore and Evesham indicates a number of key junctions within these towns that
are performing at levels approaching, at or over capacity in the base year (2011) and
the future year (2030) scenarios. These junctions occur at key intersections on the
main routes through and around the towns. These junctions and routes were
considered in the development of the highway network used through the
development of the Vehicle/Trip Generation Model used for the purposes of
identifying mitigation schemes for the Infrastructure Delivery Plan.
The Great Malvern assessment has identified key route corridors and junctions as
requiring further consideration as a result of forecast future year traffic growth.
Figure 5.3 shows the locations identified.
36
Figure 5.3 – Great Malvern Route Corridors and Junctions requiring further
assessment as a result of forecast year traffic growth – as indicated by Great Malvern
Spreadsheet Model
Based upon the Ordnance Survey Map with the permission of the Controller of Her Majesty’s Stationary Office. Crown
Copyright Licence No. LA09073L Worcestershire County Council.
37
The Pershore assessment has identified key route corridors and junctions as requiring
further consideration as a result of future year traffic predictions. Figure 5.4 shows
the locations identified.
Figure 5.4 – Pershore Route Corridors and Junctions requiring further assessment as a
result of forecast year traffic growth – as indicated by Pershore Spreadsheet Model
Based upon the Ordnance Survey Map with the permission of the Controller of Her Majesty’s Stationary Office. Crown
Copyright Licence No. LA09073L Worcestershire County Council.
38
The Evesham assessment has identified key route corridors and junctions as
requiring further consideration as a result of future year traffic predictions. Figure 5.5
shows the locations identified.
Figure 5.5 – Evesham Route Corridors and Junctions requiring further assessment as
a result of forecast year traffic growth – as indicated by Evesham Spreadsheet Model
Based upon the Ordnance Survey Map with the permission of the Controller of Her Majesty’s Stationary Office. Crown
Copyright Licence No. LA09073L Worcestershire County Council.
39
The Droitwich assessment has identified key route corridors and junctions as
requiring further consideration as a result of future year traffic predictions. Figure 5.6
shows the locations identified.
Figure 5.6 – Droitwich Route Corridors and Junctions requiring further assessment as
a result of forecast year traffic growth – as indicated by Droitwich Spreadsheet Model
Based upon the Ordnance Survey Map with the permission of the Controller of Her Majesty’s Stationary Office. Crown
Copyright Licence No. LA09073L Worcestershire County Council.
5.6 Passenger transport and sustainable modes of transport
The Accessibility Assessment of South Worcestershire Development Plan (2011) work
completed by Halcrow and Worcestershire County Council considered a number of
the proposed SWDP development sites. It identified where there are gaps in the
existing network of public transport and sustainable transport provision to access
proposed residential and employment sites.
Pedestrian infrastructure
The report identified where proposed sites for new residential development had poor
provision of pedestrian facilities and the links to key services. The sites identified
were:
Droitwich (particularly Copcut Lane);
Evesham (all sites and in particular, for access to employment and health);
40
Malvern (in particular access to to/from Newlands);
Pershore (in particular access to health);
Malvern Hills Rural (all sites); and
Wychavon Rural (all sites).
Cycle infrastructure
The report also identified where proposed sites for new residential development had
poor provision of cycle facilities and the links to key services. The sites identified
were:
Droitwich Spa (in particular access to employment and health);
Evesham (in particular access to education and employment);
Pershore (in particular access to education, employment and health);
Malvern (in particular access to employment);
Malvern Hills Rural (in particular access to all destinations from proposed sites
to the south of Worcester); and
Wychavon Rural (in particular Worcester Road, Hartlebury.)
Passenger transport infrastructure and services
The report also identified where proposed sites for new residential development had
poor provision of public transport facilities and the links to key services. The sites
identified were:
Droitwich Spa sites in terms of access to health;
Evesham sites in terms of access to education and health, with the Pershore
Road, Hampton site performing particularly poorly in terms of access to
education, health and retail;
Pershore sites in terms of access to education;
Malvern, in particular the Newlands site;
Malvern Hills Rural (all sites in terms of access to education and health); and
Wychavon Rural, in particular the Worcester Road, Hartlebury site.
Access to proposed employment sites
The report undertook a separate analysis of the SWDP proposed employment sites.
The following conclusions were noted:
The employment sites located within, or in proximity of, major settlements can
be accessed by a greater number of people by walk, cycle and passenger
transport.
The employment site with the highest catchment area population for those
accessing by walk, cycle and passenger transport is Droitwich, Copcut Lane,
although measures to improve access will be required to maximise use of these
41
modes and mitigate adverse impact on the performance of the strategic (A38)
and local highway network.
The Malvern Hills Newlands and QinetiQ employment sites are both
reasonably accessible, although investment will be required across all modes to
mitigate adverse impacts on the strategic (A449 & A4440) and local highway
network.
The Wychavon Evesham Vale Park and Pershore Station Road/Wyre Road are
less accessible and are likely to require more significant investment in walk,
cycle and passenger transport sustainable modes infrastructure and services to
mitigate the adverse impacts on the strategic (A46 and A44) and local highway
network.
The Malvern Hills Blackmore Park employment site will also require more
significant investment in walk, cycle and passenger transport infrastructure
and services.
Overall conclusion
In conclusion, the Accessibility Assessment of South Worcestershire Development
Plan (2011) work concluded that there are accessibility issues to address at all the
proposed SWDP development sites.
42
6 Scheme Identification
6.1 Introduction
This section of the Technical Note sets out the mitigation measures identified. They
have been presented in tabular form, with a description of location, issue, the
mitigation proposed and cost.
The following sections set out the assumptions that have formed the basis of the
scheme assessment and costs.
6.2 Scheme identification methodology
Where appropriate identification of mitigation measures has drawn on existing
Transport Packages. For example, scheme proposals identified through the WTS have
been taken as the core schemes for Worcester and schemes identified through the
‘Development Traffic Impact Assessment’ work has been used as a basis for the
towns.
Where additional issues have been identified in both Worcester and the four main
towns, and for other areas not previously covered, the assessment undertaken for this
project, through the application of the Vehicle/Trip Generation Model, has identified
further locations where mitigation is required to overcome or reduce the impact of
proposed development. That is, there are locations outside Worcester that do not
currently have the benefit of an existing package of measures identified through the
LTP3 strategy. Furthermore, there are some development sites that were not
considered at the time the LTP3 strategy was developed. For these sites, an additional
task has been undertaken to identify schemes and other mitigation measures. These
proposed schemes have been identified through the use of the Vehicle/Trips
Generation Model.
Proposed transport schemes have been identified to mitigate against predicted future
year transport issues. That being, the proposed highway infrastructure schemes aim
to improve capacity at key junctions which are anticipated in incur additional delays
in future years as a result of the housing and employment growth proposed for the
SWDP area. These junctions have been identified through the use of the Vehicle/Trip
Generation Model.
The proposed sustainable transport infrastructure schemes aim to connect the
proposed SWDP development sites to the existing transport network and where
appropriate improve the existing transport network to encourage greater use of more
sustainable transport modes. These schemes have been identified through
consideration of the results of the Vehicle/Trip Generation Model to determine where
additional infrastructure is required to complete the sustainable transport network to
support trips by sustainable modes to and from these development sites.
The proposed transport schemes are shown on Figure 6.1 and Figure 6.2. These plans
show the locations of the schemes identified as a result of the Vehicle/Trip Generation
Model (outside Worcester) and the WTM within Worcester. Outside Worcester in all
locations where a problem has been identified in the Vehicle/Trips Generation Model
a scheme has been proposed. Within Worcester, with greater ability to encourage
43
mode change and greater use of sustainable modes, a more network wide approach
has been adopted. This has resulted in not all junctions being the subject of individual
schemes, but the overall approach of encouraging more sustainable travel is forecast
to result in mode change which, in turn, has reduced the use of private transport
(particularly for local journeys to/from/within Worcester) thus relieving congestion
on the highway network. These plans can also be related to the plans shown in
Chapter 4 where the main issues were identified (individual junctions and corridors).
Figure 6.1. – Draft SWDP IDP proposals – excluding Worcester
44
Figure 6.2. – Draft SWDP IDP proposals – Worcester Transport Strategy
Each of the proposed transport infrastructure schemes have also been considered
against the following design considerations;
Policy/Strategy – proposals have recognised the policies and strategies put
forward through WCC’s Local Transport Plan and to be consistent with the
general approach to transport schemes in the area;
Feasibility/Deliverability – consideration has been given to the deliverability of
the proposed transport schemes. That is, the proposed schemes have
considered potential land constraints, proximity to existing obstructions (e.g.
Railway Lines), topography and overground services and utilities; and
Design Standards and Guidelines – good practice design guidelines have been
considered against all of the proposed transport schemes. Only schemes that
could meet appropriate design guidelines have been proposed, subject to
detailed design.
All of the proposed transport schemes have been priced using Worcestershire County
Council rates.
45
6.3 Overview of schemes
The different characteristics of locations within the SWDP area have been taken into
consideration when identifying schemes. That is, though there is always an emphasis
on the provision of sustainable alternatives, there is also an acknowledgement that
the measure identified need to be appropriate for the journey being made and
location of the start point.
Thus, in Worcester there has been an emphasis on dealing with the capacity problems
on the A4440 Southern and Eastern Bypasses, improving conditions along the key
radial corridors and in the city centre supported by the provision of sustainable
transport alternatives. In combination the assessment indicates that these measures
will make a significant contribution towards addressing the forecast increases in
traffic and congestion as a result of increased demand for travel.
In the South Worcestershire towns a similarly balanced approach has been adopted,
identifying both highway and more sustainable measures. In the rural areas, whilst
the use of sustainable modes is to be encouraged, it is acknowledged that highway
capacity issues must be addressed to enable both car and local passenger transport
trips to use the network efficiently.
6.4 Scheme tables
The Summary scheme tables is presented in Appendix 3
Cost estimates for each scheme were prepared primarily using construction rates
used through the costing of schemes associated with the WTS. It should be noted that
where some items fell outside the scope of the WTS, assumptions were made using
costs incurred from other similar schemes carried out for other local authorities. Costs
can vary considerably from site to site and supplier to supplier. More detailed cost
estimates will be determined when the precise details of each scheme are known
during further design stages. These uplifts are summarised in Table 6.1 (Highways)
and Table 6.2 (Sustainable Modes)
Table 6.1: Uplifts to Highway Scheme base construction costs
Highway
Preparation 12%
Supervision 5%
Evaluation 0%
Drainage 10%
Preliminary 5%
Site Supervision 5%
Design 10%
Services and Utiities 30%
Landscape 10%
Normal Road TM 10%
Strategic Road TM 20%
Groundworks/Earthworks 2%
Maintenance 25%
Consultation 10%
Ecology 10%
46
The uplifts included in Table 6.1 are based upon values used for Worcester Transport
Strategy and associated Major Scheme Bid costing purposes and previous work for
other local authorities.
These uplifts are calculated based on the construction cost and prior to the optimism
bias being added. The uplifts cover the additional costs associated with scheme
delivery above and beyond the actual cost of construction. That is, items including
site preparation, site supervision and evaluation. A generic drainage cost is included
along with design, landscaping and ecology. Different uplifts are applied for traffic
management dependent on the local road network, i.e. a greater allowance is
provided for on the strategic highway network.
Table 6.2: Uplifts to Sustainable Mode base construction costs
Sustainable
Preparation 0%
Supervision 2%
Evaluation 0%
Drainage 3%
Preliminary 5%
Site Supervision 3%
Design 10%
Services and Utiities 3%
Landscape 3%
Normal Road TM 2%
Groundworks/Earthworks 2%
Maintenance 5%
Consultation 5%
Ecology 2%
The uplifts for sustainable mode schemes are generally less than those applied for the
highway schemes. This is because the proposed schemes are generally smaller
schemes which are less intrusive and have fewer associated risks. Allowances for
Ecology and Drainage are often less as the proposed schemes pose less risk to local
environments and SUDs and surface drainage can often be applied. The design uplift
costs remain the same for both the highway and sustainable schemes.
The Optimism Bias is calculated by referring to ‘The British Department for Transport
Procedures for Dealing with Optimism Bias in Transport Planning Guidance
Document – June 2004’. It is noted that all the uplift items have been added to the cost
of construction prior to the 44% Optimism Bias Uplift. The Optimism Bias uplift is
based upon the maximum applied rate for standard civil engineering works at this
preliminary stage. This percentage, when applied, suggests an 80% probability of
staying within the budget.
The cost estimates do not include Land Costs or Part 1 claims (if required).
47
7 Conclusions and Next Steps
7.1 Conclusions
The report has set out the context, methodology and tabulated results of a strategic
assessment of the impact of development proposals in the SWDP. The mitigation
schemes identified have been chosen based on the degree to which additional
demand to travel impacts on the surrounding road network and the policy and
design requirements of central and local government.
The list is comprehensive, but contains no very major proposals to accommodate the
increase in demand because of the criteria set to ensure deliverability. Hence, there is
an expectation that some change in mode share will occur as a result of increased
attractiveness of more sustainable modes, as well as increased congestion on the
highway network. Accommodating the forecast increases in traffic and congestion as
a result of increased demand for travel would only be achieved as a result of a
combination of the consideration of larger new highway schemes and sustainable
modes measures.
It is noted that the scale of infrastructure proposed is significantly less than that
which has been introduced to the network in the past 20/30 years. With the exception
of the significant improvements to the capacity of the A4440 Southern Link Road,
improvements to the highway network are targeted at dealing with specific pinch
points (usually junctions) on the urban and in particular inter‐urban, networks. There
are no new major river crossings.
The schedule of schemes presented, and the associated costs, have taken into account
the additional costs associated with scheme design and an allowance made for
scheme maintenance over a 30 year period. These added allowances mean that if the
scheme costs are simply compared to construction costs they appear high, but the
additional costs have been derived through experience and represent the total cost to
deliver the individual schemes.
Overall, the inputs provide a comprehensive schedule of infrastructure interventions
to mitigate the transport impacts of the proposed SWDP development.
7.2 Potential future activities
This report has set out a comprehensive listing of infrastructure and public transport
service requirements in order to mitigate against the impact of the new development
proposals contained in the SWDP. These requirements have been identified through
reference to policy statements and work to assess the impact of additional journeys
on the highway network.
The work undertaken to date is based on proposed SWDP developments as identified
in the SWDP2 in 2014. It is recognised that this document will be submitted to the
SWDP EIP to be accepted and as a result of this, and the potential for further changes
to the proposed development assumptions, there is the possibility of further changes
going forward.
48
How will we deal with changes to development assumptions?
Under guidance from Planning Officers at Worcester, Malvern Hills and Wychavon
District Councils, changes to the development assumptions for the SWDP area may
be necessary. Assuming any changes to these assumptions fit the ‘development
clusters’, as used in the Vehicle Trip Generation Model, any changes to these
assumptions can be relatively easily incorporated into the model and the associated
impact on the transport network assessed. CH2M HILL proposes no action to update
the model is undertaken until guidance is received from all of the three district
councils.
49
Appendix 1: SWDP2: (2014) Transport Scheme Summary Table
50
51
TABLE 1: DRAFT TRANSPORT SCHEMES & INFRASTRUCTURE COSTS (for inclusion in SWIDP APPENDIX Y)
Category Project SWDP Policy Delivery Partners Estimated Construction
Cost (£millions) Potential Sources of Funding Estimated Timescale
Costs/Funding/Delivery
Notes Further Details
PHYSICAL INFRASTRUCTURE
A. Movement (costs exclude any land acquisition and CPO costs (in the event that these are required), passenger transport operating costs and local s278 highways works)
Worcester (Worcester Transport Strategy)
HIGHWAY SCHEMES
A4440/Southern Link Road capacity enhancements (phases 3 & 4, Whittington - Ketch - Powick), Key Corridors Infrastructure
and operational enhancements, traffic signals enhancements (SCOOT/MOVA etc.), VMS signing. NOTES: EXCLUDES costs for
M5 junctions 5, 6 and 7 which are within the jurisdiction of the Highways Agency. EXCLUDES costs for highway schemes
needed to mitigate proposed new development in and around Worcester Shrub Hill/Sherriff Gate area
SWDP 4 & SWDP 7
Worcestershire CC (ITBlock),
Development Industry, WLEP/SEP,
WLTB, New Homes Bonus, Central
Govt
£121.21
Worcs CC (IT Block), Local Transport Board
(Devolved Major Scheme Funding),
Developers (s106 & s278), New Homes
Bonus, +other funding sources as available
2012-2020:
(1) Dualling A4440 (Whittington-Ketch)
(2) Key Corridors linking urban extensions with City Centre (3)
Shrub Hill Opportunity Zone transport infrastructure works
2020-2030:
(1) Further Enhancements to A4440 and remaining key corridors
RAIL SCHEMES
Worecstershire Parkway & Shrub Hill Station improvements (limited to improved access arrangements for users, EXCLUDES
development-specific infrastructure improvments associated with major new developments such as Sherriff Gate
SWDP 4 & SWDP 7
Rail Industry (NR/TOC's/DfT),
Worcestershire CC (ITBlock),
Development Industry, WLEP/SEP,
WLTB, New Homes Bonus, Central
Govt
£18.97
Worcs CC (IT Block), Local Transport Board
(Devolved Major Scheme Funding),
Developers (s106 & s278), Network Rail,
Train operating Companies, DfT +other
funding sources as available
2012-2020:
(1) Worcestershire Parkway
(2) Shrub Hill Station (if Opportunity Zone development proposals advanced for delivery in this period)
2020 - 2030:
(1) Shrub Hill (if delivery of Opportunity Zone development delayed)
LOCAL PASSENGER TRANSPORT
SCHEMES
Including:
Upgraded bus stop infrastructure, extension of Real Time Information systems (incl. SVD & links to signals operations) to
corridors linking SWDP2 developments with Worcester City Centre and key trip attractors such as Shires Business Park and
which were not covered by Phase 1 of the WTS.
SWDP 4 & SWDP 7
Bus Industry, Worcestershire CC
(ITBlock), Development Industry,
WLEP/SEP, WLTB, New Homes
Bonus, LSTF, Central Govt
£19.57
Worcs CC (IT Block), Local Transport Board
(Devolved Major Scheme Funding),
Developers (s106 & s278), New Homes
Bonus, +other funding sources as available
Across both phases (2012 - 2020 and 2020 - 2030) aligned with key Corridor improvments and delivery of
SWDP planned growth (in particular the urban extensions of SWUE, WoWUE, Gwillims Farm, Kilbury
Drive and Swinesherd Way)
WALK & CYCLE SCHEMES
New and improved walk and cycle routes, additional walk and cycle bridge to north of city (and associated access links) and
walk & cycle elements of key Corridor schemes
SWDP 4 & SWDP 7
Sustrans, Worcestershire CC (IT
Block), Development Industry,
WLEP/SEP, WLTB, New Homes
Bonus, LSTF, Central Govt
£11.04
Worcs CC (IT Block), Local Transport Board
(Devolved Major Scheme Funding),
Developers (s106 & s278), New Homes
Bonus, +other funding sources as available
Across both phases (2012 - 2020 and 2020 - 2030) aligned with key Corridor improvments and delivery of
SWDP planned growth (in particular the urban extensions)
TOTAL £170.8
Droitwich
HIGHWAY SCHEMES
Local highway network improvements and elements of A38 highway enhancements in vicinity of Droitwich, including: A38
Roman Way / B4065 Bromsgrove Road, A38 Roman Way / A442 Kidderminster Road, A38 Roman Way / B4090 Worcester Road
and Hanbury Street / Queen Street / Saltway / Bromsgrove Road
SWDP 4 & SWDP 7
Worcestershire CC (ITBlock),
Development Industry, WLEP/SEP,
WLTB, New Homes Bonus, Central
Govt
£3.62
Worcs CC (IT Block), Local Transport Board
(Devolved Major Scheme Funding),
Developers (s106 & s278), New Homes
Bonus, +other funding sources as available
Across both phases (2012-2020 & 2020 – 2030)
RAIL, LOCAL PASSENGER
TRANSPORT AND WALK & CYCLE
LINK SCHEMES
Including:
(1) Improvements to Droitwich rail station and associated interchange facilities (including parking, information, access
routes etc.).
(2) Provision of Infrastructure to enable local PT services to access & serve SWDP development sites (particularly Copcut &
Yew Tree Village).
(3) Provision of walk & cycle footbridge over A38 linking proposed development sites to town centre & railway station.
(4) Improvements to walk & cycle routes, crossing facilities, signage and other associated facilities
SWDP 4 & SWDP 7
Sustrans, Bus Industry, Rail Industry
(NR/TOC's/DfT), Worcestershire CC
(ITBlock), Development Industry,
WLEP/SEP, WLTB, New Homes
Bonus, LSTF, Central Govt
£5.32
Worcs CC (IT Block), Local Transport Board
(Devolved Major Scheme Funding),
Developers (s106 & s278), New Homes
Bonus, +other funding sources as available
Across both phases (2012-2020 & 2020 – 2030)
TOTAL £8.9
Evesham
HIGHWAY SCHEMES
Including town centre junction enhancements, including: (A4184 / B4624) Greenhill / High Street / Worcester Road, Vine
Street / High Street / Bridge Street, Bridge Street / Port Street / Waterside and A4184 (Cheltenham Road) / Davies Road.
NOTE: EXCLUDES A46 schemes which are within the jurisdiction of the Highway Agency.
SWDP 4 & SWDP 7
Worcestershire CC (ITBlock),
Development Industry, WLEP/SEP,
WLTB, New Homes Bonus, Central
Govt
£1.20
Worcs CC (IT Block), Local Transport Board
(Devolved Major Scheme Funding),
Developers (s106 & s278), New Homes
Bonus, +other funding sources as available
Across both phases (2012-2020 & 2020 – 2030)
RAIL, LOCAL PASSENGER
TRANSPORT AND WALK & CYCLE
LINK SCHEMES
Including:
(1) Provision of walk & cycle footbridges over A46 and River Avon linking proposed development sites to town centre, railway
station, retail parks and employment centres. (2)
Improvements to Evesham rail station and associated interchange facilities (including cycle parking, information, access routes
etc.). (3)
Provision of Infrastructure to enable local PT services to access & serve SWDP development sites.
(4) Improvements to walking and cycling connectivity
SWDP 4 & SWDP 7
Sustrans, Bus Industry, Rail Industry
(NR/TOC's/DfT), Worcestershire CC
(ITBlock), Development Industry,
WLEP/SEP, WLTB, New Homes
Bonus, LSTF, Central Govt
£7.600
Worcs CC (IT Block), Local Transport Board
(Devolved Major Scheme Funding),
Developers (s106 & s278), New Homes
Bonus, +other funding sources as available
Across both phases (2012-2020 & 2020 – 2030)
TOTAL £8.8
Malvern
HIGHWAY SCHEMES
Local highway network improvments, including: A4103 / B4503 Leigh Sinton Road, A449 Worcester Road / Richmond Road /
Pickersleigh Avenue, A449 Worcester Road / Howsell Road / Pickersleigh Road, A449 Worcester Road / B4505 (Newtown Road)
/ Hornyold Road, B4208 Pickersleigh Road / North End Lane / Hayslan Road, B4208 Pickersleigh Road / North End Lane
/ Hayslan Road, B4211 Barnards Green Rd / B4208 Pickersleigh Rd / Upper Chase Rd / Court Rd / Avenue Rd, A449 Belle Vue
Terrace / Wells Road / B4211 Church Street, B4208 Barnards Green Rd / B4211/ Poolbrook Road and B4208 Blackmore Park
Rd / B4209 Hanley Rd. NOTE: EXCLUDES improvements to Townsend Way/A449 Junction associated with proposed Newlands
development.
SWDP 4 & SWDP 7
Worcestershire CC (ITBlock),
Development Industry, WLEP/SEP,
WLTB, New Homes Bonus, Central
Govt
£5.6
Worcs CC (IT Block), Local Transport Board
(Devolved Major Scheme Funding),
Developers (s106 & s278), New Homes
Bonus, +other funding sources as available
Across both phases (2012-2020 & 2020 – 2030)
RAIL, LOCAL PASSENGER
TRANSPORT AND WALK & CYCLE
LINK SCHEMES
Including:
(1) Provision of Infrastructure to enable local PT services to access & serve SWDP development sites.
(2) Improvements to walking and cycling connectivity, including to/from proposed development sites
(3) Improvements to town centre walking and cycling facilities
SWDP 4 & SWDP 7
Sustrans, Bus Industry, Rail Industry
(NR/TOC's/DfT), Worcestershire CC
(ITBlock), Development Industry,
WLEP/SEP, WLTB, New Homes
Bonus, LSTF, Central Govt
£0.7
Worcs CC (IT Block), Local Transport Board
(Devolved Major Scheme Funding),
Developers (s106 & s278), New Homes
Bonus, +other funding sources as available
Across both phases (2012-2020 & 2020 – 2030)
TOTAL £6.4
Pershore
HIGHWAY SCHEMES
Local highway network improvements, including:(A4104 / B4084) Worcester Road / Three Springs Road, (A4104 / B4084)
Station Road / Worcester Road / High Street and A4104 Station Road / B4083 Wyre Road NOTE: See
Inter-Urban Highway section (below) for A44 highway enhancements.
SWDP 4 & SWDP 7
£1.050
Worcs CC (IT Block), Local Transport Board
(Devolved Major Scheme Funding),
Developers (s106 & s278), New Homes
Bonus, +other funding sources as available
Across both phases (2012-2020 & 2020 – 2030)
RAIL, LOCAL PASSENGER
TRANSPORT AND WALK & CYCLE
LINK SCHEMES
Including:
(1) Improvements to Pershore rail station and associated interchange facilities (including parking, information, access routes
etc.). (2)
Provision of Infrastructure to enable local PT services to access & serve SWDP development sites.
(3) Improvements to walking and cycling connectivity
(4) Improvements to town centre walking and cycling facilities
SWDP 4 & SWDP 7
£3.360
Worcs CC (IT Block), Local Transport Board
(Devolved Major Scheme Funding),
Developers (s106 & s278), New Homes
Bonus, +other funding sources as available
Across both phases (2012-2020 & 2020 – 2030)
TOTAL £4.4
Rural Malvern Hills
LOCAL PASSENGER TRANSPORT
AND WALK & CYCLE LINK SCHEMES
Including:
(1) Provision of Infrastructure to enable local PT services to access & serve SWDP development sites.
(2) Improvements to walking and cycling connectivity to the existing network (3)
Improvements to walking and cycling facilities and infrastructure
SWDP 4 & SWDP 7
£0.2
Worcs CC (IT Block), Local Transport Board
(Devolved Major Scheme Funding),
Developers (s106 & s278), New Homes
Bonus, +other funding sources as available
Across both phases (2012-2020 & 2020 – 2030)
TOTAL £0.2
Rural Wychavon
RAIL, LOCAL PASSENGER
TRANSPORT AND WALK & CYCLE
LINK SCHEMES
Including:
(1) Provision of Infrastructure to enable local PT services to access & serve SWDP development sites.
(2) Improvements to rail stations (Hartlebury) and associated interchange facilities (including parking, information, access
routes etc.).
SWDP 4 & SWDP 7
£2.3
Worcs CC (IT Block), Local Transport Board
(Devolved Major scheme Funding),
Developers (s106 & s278), New Homes
Bonus, +other funding sources as available
Across both phases (2012-2020 & 2020 – 2030)
TOTAL £2.3
Inter-Urban Highways
HIGHWAY SCHEMES
Including improvements to the A44 mainline (Evesham-Worcester - Bromyard) at Pinvin Crossroads, Crown East, A38 Fernhill
Heath (Hurst Lane) & Martin Hussingtree, A449 roundabout at Claines NOTE:
EXCLUDES A449/Townsend Way Junction, subject to s278 discussions with the developer of Newlands site
SWDP 4 & SWDP 7
£4.1
Worcs CC (IT Block), Local Transport Board
(Devolved Major Scheme Funding),
Developers (s106 & s278), New Homes
Bonus, +other funding sources as available
Across both phases (2012-2020 & 2020 – 2030)
TOTAL £4.1
App Y TOTAL
£205.9
52
53
Wo rces te r T ranspo r t Mode l
South Worcestershire Development Plan 2
Prepared for
Worcestershire County Council
2014
Red Hill House
227 London Road
Worcester, WR5 2JG
+44 (0) 1905 361 361
+44 (0) 1905 361 362
54
55
Contents
Section Page
Introduction ............................................................................................................................... 56
1.1 Introduction............................................................................................................................ 56
Assessment Methodology ........................................................................................................... 57
2.1 Introduction............................................................................................................................ 57
2.2 Model Specification ................................................................................................................ 57
2.3 Model Scenarios ..................................................................................................................... 57
2.4 Model Information ................................................................................................................. 58
SWDP2 Assumptions................................................................................................................... 59
3.1 Assumptions ........................................................................................................................... 59
3.2 Model Assessment ................................................................................................................. 59
SWDP2 Network Impacts ............................................................................................................ 60
4.1 Introduction............................................................................................................................ 60
4.2 Forecast Demand ................................................................................................................... 60
4.3 Mode Split .............................................................................................................................. 60
4.4 Passenger Transport ............................................................................................................... 60
4.5 Highway Statistics................................................................................................................... 62
4.6 Link flow and travel time changes .......................................................................................... 63
4.7 Link Volume‐Capacity Ratios .................................................................................................. 65
Conclusion .................................................................................................................................. 67
5.1 Conclusion .............................................................................................................................. 67
5.2 Next steps ............................................................................................................................... 67
Appendices
i SWDP 2021‐2031 Core Development Assumptions
ii Nunnery Way Site Layout Plan iii Junction Turning Movements
Tables
4.1 Matrix Totals
4.2 Mode Split
4.3 SWDP1 PT network Statistics
4.4 PT network statistics ‐ SWDP2 and change against SWDP1
4.5 SWDP1 highway network statistics
4.6 SWDP2 Highway network model statistics and % change
Figures
4.1 SWDP2 vs SWDP1 ‐ Link Flow difference 2031 AM
4.2 SWDP2 vs SWDP1 ‐ Link Flow difference 2031 PM
4.3 SWDP2 vs SWDP1 – Travel time difference 2031 AM
4.4 SWDP2 vs SWDP1 ‐ Travel time difference 2031 PM
4.5 SWDP2 – Link VCR 2031 AM
4.6 SWDP2 – Link VCR 2031 PM
SWDP2- TRANSPORT MODELLING REPORT_FINAL/[INSERT DOCUMENT LOCATOR]
56
SECTION 1 INTRODUCTION
SECTION 1
Introduction
1.1 Introduction
Malvern Hills, Worcester City and Wychavon councils have joined together and prepared a development
plan for South Worcestershire. This plan is called the South Worcestershire Development Plan (SWDP1) that
considers the long term vision and objectives for South Worcestershire up to 2030. Following the Stage 1
examination of the plan by the Inspector, the councils have undertaken further work related to the increased
objective assessment of housing need recommended by the inspector. The increased housing allocation to
the SWDP is referred to as SWDP2 in this document.
This report sets out the Phase 1 transport modelling undertaken to appraise the proposed SWDP2. The
results of this Phase 1 modelling will help inform the various measures required to mitigate transport impact
that will subsequently be assessed under Phase 2. It has been produced by CH2M Hill following a request
from Worcestershire County Council (WCC).
This report is structured as follows:
chapter 2 details the assessment methodology;
chapter 3 details the SWDP2 assumptions assessed;
chapter 4 details the SWDP2 impacts; and
chapter 5 details conclusions and next steps.
SWDP2- TRANSPORT MODELLING REPORT_FINAL/[INSERT DOCUMENT LOCATOR]
57
SECTION 2
Assessment Methodology
2.1 Introduction
The assessment of SWDP2 described in this report has been undertaken using the Worcester Multi‐Modal
Transport Model (WTM). This is a 4‐stage WebTAG‐compliant variable demand model. This includes use of
the EMME software platform for demand model calculations and passenger transport (PT) assignment and
the SATURN software platform for highway assignment.
The assessment methodology is as specified in the Model Use Protocol document and is summarised here to
confirm the approach taken for this particular assessment. However, the model has now been updated to
account for the latest WebTAG (May 2014) value changes factored and applied to 2008 base year values,
NTEM v6.2 and WTS Phase 1 network assumptions.
2.2 Model Specification
The WTM encompasses a highway and public transport model validated to a 2008 base year and covers the
AM peak (0800 – 0900), an average inter peak (1000 – 1500) and a PM peak (1700‐1800). It incorporates
census, employment and planning data and by using local household trip rates develops the quantum of
trips generated by each zone in the model. These trips are then distributed across available modes and
subsequently distributed to destination zones. Whilst assessment previously were undertaken for 2021 and
2031, for SWDP2, the forecast year requested are 2019 and 2031. Therefore the forecast matrices are
available for 2019 and 2031 with inclusions of planning data for population and employment growth being
constrained to NTEM (v6.2) growth at County level.
The trip rates used in the WTM are 24hr ‘all mode’ production‐attraction (PA) person trip rates split by
journey purpose and by car availability based on local household survey data. Trip rates for employment and
other non‐residential developments are not directly input into the demand model. Rather, they are partially
generated as a consequence of residential population trips distributed, for example, to employment zones,
weighted by the number of jobs in any given zone.
The main mode choice is calculated using a logit choice model to split the input trip generations into the
three main modes of travel: car, PT and active (cycling and walking). The generalised cost of travel for each
of these modes is required as an input to the mode choice model. For each zone, the generalised costs of
travel will be the composite (log sum) of the costs of travel to each potential destination. A logit choice
model is also used to allocate the modal trip generations to alternative attraction zones.
Following mode choice and trip distribution to generate 24hr PA matrices by mode, origin‐destination (OD)
matrices are estimated by time period using factors derived from survey data. The model applies an absolute‐
incremental formulation to produce future year trip matrices for assignment.
The demand model is run iteratively using WebTAG convergence criteria.
2.3 Model Scenarios
Models were developed for 2019 and 2031 to determine the level of trips with SWDP2 developments and
infrastructure schemes as per WTS Phase 1 strategy. The infrastructure assumptions include the MSBC FA
(Full Approval) north and north‐east transport corridors and junction improvements at the Ketch
roundabout. The improvements at the Whittington roundabout are also included.
SWDP2- TRANSPORT MODELLING REPORT_FINAL/[INSERT DOCUMENT LOCATOR]
58
SECTION 2 ASSESSMENT METHODOLOGY
The model outputs were compared with SWDP1 results to assess the implications of the increased housing
allocations on the transport infrastructure.
2.4 Model Information
A wide range of network and operational information is available from the model. To inform the assessment
of the plan, the information provided is limited to the most relevant items being highway network summary
statistics, public transport statistics and flow differences along key links and corridors.
SWDP2- TRANSPORT MODELLING REPORT_FINAL/[INSERT DOCUMENT LOCATOR]
59
SECTION 3
SWDP2 Assumptions
3.1 Assumptions
The development plan assumptions were provided by WCC and included in the model. They are summarised
as follows:
2019 and 2031 forecast years assessed;
AM and PM peaks were assessed for highway and public transport impacts;
WTS Phase 1 strategy schemes
The housing allocations provided were for the period between 2006 and 2030. However as the base model
was developed for 2008 conditions, the allocations (completions) were factored down on a pro‐rata basis.
No changes are envisaged in the employment allocations between SWDP 1 and SWDP 2. The SWDP2 core
development assumptions are given in Appendix i.
Table 3‐1 SWDP 2 Residential Allocations modelled
SWDP 2 Allocations Units
Developments Allocations 2014 ‐ 2019 9,146
Completions 2008‐2014 5,158
Commitments ‐1st April 2014 1,406
Windfall 2014 ‐ 2019 917
Total Development 2008 ‐ 2019 16,626
Developments Allocations 2019 ‐ 2031 10,268
Windfall 2019 ‐ 2031 1,560
Total Development 2008 ‐ 2031 28,454
3.2 Model Assessment
A full demand model run has been undertaken for the increased allocations under SWDP2 for each forecast
year. The increased allocations were distributed to the various model zones, with zone connectors
permitting access to the wider network.
Since the base year model has been calibrated to 2008 household travel survey data, which was undertaken
following the implementation of the Sustainable Travel Towns project, the model base year mode shares
reflect the implementation of successful sustainable travel initiatives within Worcester. Use of the model for
the SWDP2 allocations therefore assumes sustainable initiatives (such as Choose How You Move (CHYM)
quality Travel Plans) are in place, without any specific further model adjustments. This is equivalent to
assuming an 8 to 10% decrease in car travel due to travel plan measures. It is implicit within this assumption
that any travel plans of CHYM quality adopted would be actively implemented on an ongoing basis.
SWDP2- TRANSPORT MODELLING REPORT_FINAL/[INSERT DOCUMENT LOCATOR]
60
SECTION 4
SWDP2 Network Impacts
4.1 Introduction
This section of the report outlines the highway network performance and discusses the highway impacts of
the increased allocations under SWDP2 and compares them with impacts of SWDP1 allocations.
4.2 Forecast Demand
Table 4.1 shows the all mode (car, bus, rail and HGV) matrix totals for the 2008 base year and the forecast
year, together with the percentage growth from 2008.
TABLE 4.1
Matrix Totals
Year
Total Trips % Growth
AM PM AM PM
2008 Base 44376 42711
2021 SWDP1 48870 47218 10.1% 10.6%
2031 SWDP1 51767 49861 16.7% 16.7%
2019 SWDP2 49341 47626 11.2% 11.5%
2031 SWDP2 52759 50862 18.9% 19.1%
4.3 Mode Split
The model indicates percentage mode split as shown in Table 4.5. It shows that the mode split remains very
much the same with the increased allocation under SWDP2.
TABLE 4.2
Mode Split
Mode
SWDP1_2021 SWDP2_2019 SWDP1_2031 SWDP2_2031
AM PM AM PM AM PM AM PM
PT 6.4% 5.9% 6.4% 5.9% 6.8% 5.9% 6.9% 6.0%
Car 56.6% 58.1% 56.6% 58.1% 57.2% 59.2% 57.4% 59.3%
HGV 3.0% 2.0% 3.0% 1.9% 3.2% 2.1% 3.2% 2.1%
Active 34.0% 34.0% 34.0% 34.0% 32.8% 32.8% 32.5% 32.5%
4.4 Passenger Transport
Table 4.3 shows the PT network results for the SWDP1 scenario, compared to the 2008 base.
SWDP2- TRANSPORT MODELLING REPORT_FINAL/[INSERT DOCUMENT LOCATOR]
61
SECTION 4 SWDP2 NETWORK IMPACTS
TABLE 4.3
SWDP 1 PT network statistics
Metric
Base 2008 SWDP1 2021 SWDP1 2031
AM PM AM PM AM PM
Across Network ‐ Total Number of Buses 107 108 127 123 131 127
Across Network ‐ Total Number of Passengers 2057 1731 2713 2061 3540 2383
Across Network ‐ Average Journey Time per
Passenger (hours)
0.26
0.31
0.24
0.32
0.27
0.41
Across Network ‐ Total Passenger kilometres 10264 9112 12931 9836 18382 11568
Across Network ‐ Total Bus Revenue (£) £ 3,188 £ 1,627 £ 3,655 £ 2,535 £ 5,487 £ 2,240
Across Network ‐ Annualised Bus Revneue (£) £ 6,486,253 £ 8,537,975 £ 10,316,957
Total Peak Vehicle Requirement 94 90 118 114 128 117
The model results indicate that the 2021 and 2031 networks under SWDP1 allocation will experience
relatively stable average journey times in the AM peak compared to the 2008 base year, although there will
be increased congestion, some improvements can be expected through the WTS MSBC FA package
measures. The PM peak is forecast to experience increased average journey times, especially in 2031.
There is a significant increase in the peak vehicle requirement between 2008 and the future years in both
the AM and PM peaks due to congestion on the network and bus network changes incorporated into the
models. The service changes have been provided by WCC, which reflect changes to existing services since
2008 and future services proposed to cater for new developments.
Table 4.6 provides Passenger Transport results from the WTM for SWDP2 and compares it to the SWDP 1
results. The SWDP2 2019 results have been compared against the SWDP1 2021 results. The comparison for
2031 between SWDP2 and SWDP1 are also included.
TABLE 4.4
PT network statistics ‐ SWDP2 and change against SWDP1
Metric
SWDP2 2019
SWDP2 2019 vs
SWDP1 2021
SWDP2 2031
SWDP2 2031 vs
SWDP1 2031
AM PM AM PM AM PM AM PM
Across Network ‐ Total Number of Buses 127 123 0 0 131 127 0 0
Across Network ‐ Total Number of Bus Passengers 2805 2111 +92 +50 3671 2492 +131 +110
Across Network ‐ Average Journey Time per
Passenger (hours)
0.25
0.33
0
+0.01
0.28
0.41
+0.01
0
Across Network ‐ Total Passenger kilometres 13282 10125 +351 +290 18918 12055 +537 +487
Across Network ‐ Total Bus Revenue (£) £3,782 £2,597 +£127 +£62 £5,690 £2,343 +£203 +£103
Across Network ‐ Annualised Bus Revenue (£) £8,537,975 +£252540 £10,725,950 +£408992
Total Peak Vehicle Requirement 118 116 0 +2 129 118 +1 +1
Notes: 1. WCC supplied vehicle operating cost of £110k per annum 2. Results provided are based on the modelled assumptions as documented and actual outturn passenger levels cannot be guaranteed
The PT results indicate that:
Bus passenger numbers increase under SWDP2 in both forecast years;
The average journey time per passenger is similar to SWDP1;
The revenue generated increases marginally; and
The peak vehicle requirement also increases slightly due to increase in passengers and potentially
worsening network congestion.
SWDP2- TRANSPORT MODELLING REPORT_FINAL/[INSERT DOCUMENT LOCATOR]
62
4.5 Highway Statistics
SECTION 4 SWDP2 NETWORK IMPACTS
Table 4.5 provides highway network model statistics for the SWDP1 scenario compared to the 2008 base
year. The model results indicate that the 2021 and 2031 network under SWDP1 allocations will experience
lower speeds than the 2008 base year and therefore increased journey times, with reductions of around 9‐
16%, as a result of the growth in the total number of trips of 10‐17% in the AM and PM Peak periods. The
associated increases in total travel time and distance are 20‐36% and 9‐15% respectively.
These results show that over time the level of congestion increases in the AM and PM peak periods. The
transient and over capacity queues increase significantly in the forecast years compared to the 2008 base
year model, where over capacity queues increase by 300% in the AM 2031 and 520% in the PM 2031.
TABLE 4.5
SWDP1 highway network statistics Description
Units
Base 2008
SWDP1 2021
SWDP1 2021 vs
Base 2008 %
SWDP1 2031
SWDP1 2031 vs
Base 2008 %
AM PM AM PM AM PM AM PM AM PM
Transient Queues pcu. hrs./hr. 908 729 1124 944 24% 29% 1266 1045 39% 43%
Over‐capacity Queues pcu. hrs./hr. 379 187 963 765 154% 309% 1537 1161 305% 520%
Total Travel Time pcu. hrs./hr. 7472 6966 8950 8377 20% 20% 10183 9356 36% 34%
Travel Distance pcu. kms./hr. 380608 371716 415034 405421 9% 9% 437292 426083 15% 15%
Overall Average Speed kph 51 53 46 48 ‐9% ‐9% 43 46 ‐16% ‐15%
Total Trips Loaded pcu/hr 42276 40137 46119 44133 9% 10% 48693 46780 15% 17%
Average Travel Time pcu/mins 10.6 10.4 11.6 11.4 10% 9% 12.5 12.0 18% 15%
Table 4.7 provides forecast year highway network model results under SWDP2 and provides percentage
changes against SWDP1 results.
TABLE 4.6
SWDP2 Highway network model statistics and % change
Description
Units
SWDP2 2019 SWDP2 2019 vs
SWDP1 2021 %
SWDP2 2031 SWDP2 2031 vs
SWDP1 2021 %
AM PM AM PM AM PM AM PM
Transient Queues pcu. hrs./hr. 1152 968 2.5% 2.6% 1310 1089 3.5% 4.2%
Over‐capacity Queues pcu. hrs./hr. 989 872 2.7% 13.9% 1789 1428 16.4% 23.0%
Total Travel Time pcu. hrs./hr. 9003 8479 0.6% 1.2% 10596 9765 4.1% 4.4%
Travel Distance pcu. kms./hr. 414981 404136 0.0% ‐0.3% 442116 430264 1.1% 1.0%
Overall Average Speed kph 46.1 47.7 ‐0.6% ‐1.4% 41.7 44.1 ‐2.8% ‐3.1%
Total Trips Loaded pcu/hr 46477 44471 0.8% 0.8% 49778 47979 2.2% 2.6%
Average Travel Time pcu/mins 11.62 11.44 ‐0.2% 0.4% 12.77 12.21 1.8% 1.8%
Under SWDP2, vehicle trips on the highway network slightly decrease in 2019 AM compared to SWDP1 2021
AM, whereas in the PM, it slightly increases. In 2031 however, the vehicle trips under SWDP2 increase by
2.2‐2.6% as compared to SWDP1 as a result of the increased allocations. Changes in highway network
performance indicators due to the increased allocations under SWDP2 show the following:
An increase in travel time of between 0.6‐4.4% and increase in over capacity queuing of between 2.7‐
23.0%;
An increase in transient queuing of between 2.5‐4.2%; and
A reduction in overall speed of between 0.6‐3.1% within the Worcester network.
SWDP2- TRANSPORT MODELLING REPORT_FINAL/[INSERT DOCUMENT LOCATOR]
63
4.6
Link
flow and travel time
changes
SECTION 4 SWDP2 NETWORK IMPACTS
Model parameters such as flow and travel time were compared between SWDP2 and SWDP1 for the two
forecast horizons to understand links and corridors that are impacted by the increased allocations. Link flow
difference plots for 2031 AM and PM are illustrated in Figures 4‐1 and 4‐2 below.
Figure 4‐1: SWDP2 vs SWDP1 ‐ Link Flow difference 2031 AM
The figures show that traffic flows increase is generally spread wide across the model network in both AM
and PM peak hours. The A4440 is expected to experience more demand on it especially along the eastern
and western sections. The A38, north of A449 is forecast to experience a reduction in flow in both AM and
PM peak hours. The radials routes from/to the city centre are forecast to experience increasing demand.
Link travel time difference plots for 2031 AM and PM are illustrated in Figures 4‐3 and 4‐4 below. The plots
show that travel time on various links increase due to the increased demand under SWDP2 compared to
SWDP1, with most links around the city centre experiencing an increase. There are few links however that
would experience a decrease in travel time presumably due to effects of re‐routeing. The SLR and arms
leading to M5 j6 are expected to experience further congestion. The model also shows one particular zone in
Redhill where the DEFRA offices are situated to experience significant increase in congestion (over 900s) in
2031 PM to gain access to the road network (on the link from the zone connector).
SWDP2- TRANSPORT MODELLING REPORT_FINAL/[INSERT DOCUMENT LOCATOR]
64
SECTION 4 SWDP2 NETWORK IMPACTS
Figure 4‐2: SWDP2 vs SWDP1 ‐ Link Flow difference 2031 PM
Figure 4‐3: SWDP2 vs SWDP1 – Travel time difference 2031 AM
SWDP2- TRANSPORT MODELLING REPORT_FINAL/[INSERT DOCUMENT LOCATOR]
65
SECTION 4 SWDP2 NETWORK IMPACTS
Figure 4‐4: SWDP2 vs SWDP1 – Travel time difference 2031 PM
4.7 Link Volume-Capacity Ratios
Link Volume–Capacity Ratios (VCR) for 2031 AM and PM under SWDP2 are illustrated in Figure 4‐5 and 4‐6.
The figures highlight those links where the VCR is expected to be 85% or above. They show that in the AM
peak hour many links on the radials leading to the city centre are expected to be heavily congested. The VCR
on links along the SLR and motorway junctions are also forecast to be high with most exceeding the link
capacity.
In the PM peak hour, there are fewer links with high VCRs compared to the AM. The most prominent links
are the M5 motorway between J7 and J6, the SLR between Ketch and Powick, Whittington roundabout and
the links approaching M5 J6. The links in the city centre too are expected to experience significant
congestion.
Plots showing the equivalent link parameters as above for 2019 under SWDP2 and their comparisons with
SWDP1 for 2021 are given in Appendix ii
SWDP2- TRANSPORT MODELLING REPORT_FINAL/[INSERT DOCUMENT LOCATOR]
66
SECTION 4 SWDP2 NETWORK IMPACTS
Figure 4‐5: SWDP2 – Link VCR 2031 AM
Figure 4‐6: SWDP2 – Link VCR 2031 PM
SWDP2- TRANSPORT MODELLING REPORT_FINAL/[INSERT DOCUMENT LOCATOR]
67
SCETION 5
Conclusion
5.1 Conclusion
The increased residential allocations under SWDP2, have been modelled using the WTM as part of Phase 1
assessments. The networks considered for the modelling process are the WTS Phase1 improvements.
Assessments were undertaken for the 2019 and 2031, AM and PM peaks and compared with results under
SWDP1.
The results presented indicate:
Additional highway trips will be generated that will impact on the Worcester network;
The model indicates peak mode shares, in 2031, to remain similar to those predicted under SWDP1;
Public transport passenger numbers are forecast to increase under SWDP2 by over 110 trips in 2031;
The highway network will experience more congestion with travel times increasing by over 4% and
network speeds dropping by 3% in 2031; and
The routes leading to the city centre, A4440 and motorway junctions are expected to experience
worsening congestion.
5.2 Next steps
It is anticipated that results from this report will help WCC and other local authorities develop potential
mitigation strategies and measures to address the increased network congestion to be experienced under
SWDP2.
SWDP2- TRANSPORT MODELLING REPORT_FINAL/[INSERT DOCUMENT LOCATOR]
68
69
Appendix i SWDP2 2019-2031 Core Development
Assumptions
70
Appendix ii 2019 Link Plots – Flow, Travel time and VCR
71
SWDP2 vs SWDP1 ‐ Link Flow difference 2019‐2021 AM
SWDP2 vs SWDP1 – Travel time difference 2019‐2021 AM
72
SWDP2 – VCR 2019 AM
SWDP2 vs SWDP1 ‐ Link Flow difference 2019‐2021 PM
73
SWDP2 vs SWDP1 – Travel time difference 2019‐2021 PM
SWDP2 – VCR 2019 PM
74
75
T E C H N I C A L M E M O R A N D U M
SWDP2 - Phase 1 - Impacts on Network Performance
PREPARED FOR:
COPY TO:
Worcestershire County
Council
PREPARED BY: CH2M HILL
DATE: 30 June 2014
PROJECT NUMBER: 473946.MA.01.30
Background
CH2M Hill has supported Worcestershire County Council (WCC) with identifying the necessary transport
related infrastructure (highway, cycle and walk) and bus services required to mitigate against the
additional residential and employment development arising from the proposed allocations identified in
the Draft South Worcestershire District Plan (SWDP).
In October 2013 the proposed Draft SWDP housing and employment allocations were assessed at an
Examination in Public (EiP). The findings of the EiP required the three Districts comprising South
Worcestershire, namely Worcester City, Malvern Hills and Wychavon, to identify additional allocations
for residential development above the quantity included in the Draft SWDP. In response to the EiP
Inspector’s report, revised SWDP residential allocation figures were released in May 2014. It should be
noted that the proposed employment land allocations remain unchanged.
CH2M Hill has been commissioned by WCC to undertake a review of the impact on the transport
network arising from the revised SWDP allocations to ensure the previously identified transport
infrastructure and services included in the South Worcestershire Infrastructure Delivery Plan remain
appropriate to the level of growth proposed.
This Technical Note, forming Phase 1 of a 2 phase process, provides an initial commentary of the change
in impact on the Transport Network resulting from the proposed additional SWDP housing allocations
compared to the allocations assessed in the initial round of SWDP transport modelling. The findings of
this Technical Note will inform the Phase 2 work to review and identify the appropriate transport
infrastructure schemes and services required to support the revised SWDP allocations. Workshops to
discuss proposed transport schemes with WCC Officers from the Highway Network and Sustainable
Travel teams are scheduled for 4th July 2014. The information set out in this Technical Note will form a
key part of those discussions.
Process / Methodology
The impact of the revised residential allocations on the transport network has been assessed using the
South Worcestershire Vehicle / Trip Generation Model. The updated residential allocations have been
supplied to CH2M Hill by Worcester City, Malvern Hills and Wychavon District Councils to undertake
forecast year scenarios using the Vehicle / Trip Generation Model for 2019 and 2031. The 2019 and 2031
forecast year scenarios are in line with those assessed through the previous SWDP transport network
review and scheme identification.
Once the assessment of the revised SWDP residential allocations is complete, the South Worcestershire
Transport Infrastructure Delivery Plan document will be updated to include additional / revised schemes.
As part of the update to this document, Appendix A (Gravity Modelling Technical Note) will be updated to set out any changes required to allow Vehicle / Trip Generation model to most accurately take
account of the changes to the development assumptions. The amendment to Vehicle / Trip Generation
DRAFT - SWDP 2 - PHASE 1 - TRANSPORT NETWORK IMPACT TN - AB/[INSERT DOCUMENT LOCATOR]
76
model involves the addition of Development Clusters to enable the most accurate reflection of the
updated residential allocations.
For the purposes of this Technical Note the results of the initial residential and employment allocation
scenarios for 2019 and 2030 are referred to as SWDP 1. The revised residential and employment
allocation scenarios for 2019 and 2031 are referred to as SWDP 2.
Development Assumptions
Tables 2.1 and 2.2 show the overall quantum of residential and employment development figures
modelled for SWDP 1 and SWDP 2 and the resulting forecast number of 24 hour development trip
demand for Vehicles, Pedestrians, Cyclists and Bus.
Table 2.1 – SWDP 1 - 2019 and 2030 Development Assumptions and 24 hour Total Trips
2019 Forecast Model 2030 Forecast Model
Development Assumptions
Residential (Dwellings) 7478 12893
Employment (Hectares) 118 170
Commitments
(Residential Dwellings)
2262 2900
Commitments
(Employment Hectares)
38 101
Windfalls
(Residential Dwellings)
710 2859
Empty Homes
(C3 Residential Dwellings)
190 551
Total Trips
Total 24 hrs Development Trips
(Vehicles, Walk, Cycle, Bus)
280453 491659
Table 2.2 – SWDP 2 - 2019 and 2030 Development Assumptions and 24 hour Total Trips
2019 Forecast Model 2031 Forecast Model
Development Assumptions
Residential (Dwellings) 9151 19434
Employment (Hectares) 118 170
Commitments
(Residential Dwellings)
414 1406
Commitments
(Employment Hectares)
38 101
Windfalls
(Residential Dwellings)
797 2013
Completions 6989 6989
DRAFT - SWDP 2 - PHASE 1 - TRANSPORT NETWORK IMPACT TN - AB/[INSERT DOCUMENT LOCATOR]
77
SWDP2 - PHASE 1 - IMPACTS ON NETWORK PERFORMANCE
Demolition / Non Delivery of
Commitments
-110 -110
Total Trips
Total 24 hrs Development Trips
(Vehicles, Walk, Cycle, Bus)
341775 587561
Tables 2.1 and 2.2 show the increase in the allocation of dwellings between SWDP 1 and SWDP 2. The
increase in the number of dwellings results in an increase in the total number of forecast 24 hour
development trips (vehicles, pedestrians, cyclists and bus) from the proposed development sites across
South Worcestershire.
Highway Network Impacts
Data has been extracted from the Vehicle / Trip Generation model to provide an initial commentary of
the change in development traffic flows on the South Worcestershire highway network resulting from
the revised residential growth data.
Appendices A-D set out the development traffic flows on selected links in and around Worcester, Great
Malvern, Evesham, Pershore and Droitwich Spa. Where base year traffic flow data is available a
comparison in terms of forecast year traffic flows against the highway network capacity in that location
is provided. Also included as part of the analysis is a comparison of the forecast year traffic flow against
the highway capacity provided through the SWDP 1 proposed scheme.
In the following analysis, the assessment of highway capacity has been taken from SATURN based
link/junction capacity calculations based on road and junction type, and the measure used to assess the
performance of the link/junction is ‘volume over capacity’ which effectively considered whether the
road has sufficient space (capacity) to allow the amount for traffic (volume) to pass through. Where the
amount of traffic is greater than the space available, the result of the calculation is more than 100%,
indicating that the link/junction is ‘over capacity’. This indication is a good measure of the potential for
congestion.
A brief commentary summarising the data contained in Appendices A-D is provided below for Worcester,
Great Malvern, Evesham, Pershore and Droitwich Spa for 2019 and 2031 (AM and PM peak periods).
Reference is made to where the results indicate that congestion is likely, where the proposed scheme has
a beneficial impact and where, despite assuming a mitigation scheme, the link/junction is still shown to
have congestion. It is noted that the mitigation schemes proposed were identified within a set of criteria
which limited their size.
2019 – AM Peak - Highway Network Impacts
Worcester
The 2019 AM SWDP 2 development trip traffic data shows an increase in the number of trips compared
to the 2019 AM SWDP 1 scenario on most of the selected routes in and around Worcester.
Notable percentage increases in development vehicle trips are shown on the:
• Eastbound approach to the A44 / A4440 (Whittington Road / Swinesherd Way) Roundabout;
• Northbound approach to the A38 / A4536 (Droitwich Road / Hurst Lane) priority junction; and
• North east bound approach to the A38 / A453 (Droitwich Road / Pershore Lane) signalised
junction.
The highway junction improvement schemes identified through SWDP 1 show an improvement in terms
of volume over capacity compared to the existing situation on all of the selected links. Despite the
inclusion of the proposed SWDP 1 schemes, some junction approaches with a volume over capacity
result of over 100% remain, notably: DRAFT - SWDP 2 - PHASE 1 - TRANSPORT NETWORK IMPACT TN - AB /[INSERT DOCUMENT LOCATOR]
COPYRIGHT 2014 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
78
• Northwest bound approach to the A44 / A4440 (Whittington Road / Swinesherd Way)
roundabout junction;
• Southbound approach to the A38 / A4538 (Droitwich Road / Pershore Lane) signalised junction;
and
• A44 / A422 / Pershore Lane roundabout junction.
The Vehicle / Trip Generation model shows all the junction approaches with the proposed SWDP 1
scheme in place with a volume over capacity ratio of under 100% in the 2019 AM peak under the SWDP 1 scenario, continue to operate with a volume over capacity ratio under 100% in the SWDP 2 scenario.
Great Malvern
The 2019 AM SWDP 2 development trip traffic data shows a variation in development traffic flows to
those shown under the SWDP 1 scenario.
Notable percentage increases in development vehicle trips are shown on the:
• Northbound and southbound approaches to the A4103 / B4503 Leigh Sinton Road Priority
Junction;
• North east bound approach to the A449 Worcester Road / Howsell Road / Pickersleigh Road Junction;
• Eastbound approach to the B4211 Barnards Green Rd / B4208 Pickersleigh Rd / Upper Chase Rd
/ Court Rd / Avenue Rd Gyratory; and
• Westbound and Southbound approaches to the A449 Belle Vue Terrace / Wells Road / B4211
Church Street Priority Junction. Percentage
decreases in trips are shown on the:
• Northbound approach to the A449 Worcester Road / Townsend Way Roundabout;
• Northbound and westbound approach to the B4208 Pickersleigh Road / North End Lane /
Hayslan Road signalised junction;
• Southbound approach to the B4211 Barnards Green Rd / B4208 Pickersleigh Rd / Upper Chase
Rd / Court Rd / Avenue Rd Gyratory;
• Northbound approach to the B4208 Barnards Green Rd / Guarlford Road / Poolbrook Road
priority junction; and
• Southbound approach to the B4208 Blackmore Park Rd / B4209 Hanley Rd signal junction.
The highway junction improvement schemes identified through SWDP 1 show an improvement in terms
of volume over capacity compared to the existing situation at all of the selected junctions. Despite the
inclusion of the proposed SWDP 1 schemes, some junction approaches with volume over capacity result
of over 100% remain, notably the southbound approach to the A449 Worcester Road / Townsend Way
roundabout and the northbound approach to the A449 Belle Vue Terrace / Wells Road / B4211 Church
Street priority junction.
Under the SWDP 2 development scenario the volume over capacity result on the links identified above is
further exacerbated. Additionally, the following links also operate with a volume over capacity of above
100%:
• North East bound approach to the A449 Worcester Road / Townsend Way Roundabout;
• Westbound approach to the B4211 Barnards Green Rd / B4208 Pickersleigh Rd / Upper Chase Rd
/ Court Rd / Avenue Rd Gyratory; and
• Westbound and southbound approaches to the A449 Belle Vue Terrace / Wells Road / B4211
Church Street priority junction.
DRAFT - SWDP 2 - PHASE 1 - TRANSPORT NETWORK IMPACT TN - AB/[INSERT DOCUMENT LOCATOR]
79
SWDP2 - PHASE 1 - IMPACTS ON NETWORK PERFORMANCE
Evesham
The 2019 AM SWDP 2 development trip traffic data shows an increase in the number of trips compared
to the 2019 AM SWDP 1 scenario on all of the selected routes in and around Evesham.
Notable percentage increases are shown on the:
• Northbound approach to the A44 / A4184 / B4088 Evesham Road Roundabout;
• Northbound approach to the A44 / A46 Roundabout; and
• Southbound approach to the A46 / A4184 Cheltenham Road roundabout.
The highway junction improvement schemes identified through SWDP 1 show an improvement in terms
of volume over capacity compared to the existing situation on all of the selected links. Despite the
inclusion of the proposed SWDP 1 schemes, some junction approaches with volume over capacity result
of over 100% remain, notably:
• Westbound approach to the A46 / A4184 Cheltenham Road roundabout;
• Westbound approach to the A46 / The Link / Millennium Way roundabout; and
• Southbound approach to the A46 / B4035 Badsey Road roundabout.
The Vehicle / Trip Generation model shows the volume over capacity ratio on these junction approaches
to be further exacerbated under the SWDP 2 scenario.
Pershore
The 2019 AM SWDP 2 development trip traffic data shows an increase in the number of trips compared
to the 2019 AM SWDP 1 scenario on all of the selected routes in and around Pershore.
Notable percentage increases are shown on the northbound and eastbound approaches to the A4104 /
B4084 (Worcester Road / Three Springs Road) priority junction.
The highway junction improvement schemes identified through SWDP 1 show an improvement in terms
of volume over capacity compared to the existing situation on all of the selected links.
At most of the junctions the volume over capacity ratio is at approximately 100% or below with the
SWDP 1 proposed schemes in place under the SWDP 1 development scenario.
Under the SWDP 2 development scenario the eastbound approach to the A44 / A4104 / B4082 (Allens
Hill / Terrace Road / Main Street) signalised junctions and northbound approach to the A4104 / B4084
(Worcester Road / Three Springs Road) are operating at a volume over capacity ratio of over 100%.
Droitwich Spa
The 2019 AM SWDP 2 development trip traffic data shows an increase in the number of trips compared
to the 2019 AM SWDP 1 scenario on most of the selected routes in and around Droitwich Spa. A slight
reduction in the number of development related trips is shown on the westbound approach to the A38
Roman Way / A442 Kidderminster Road Roundabout.
Notable percentage increases are shown on the:
• Northbound approach to the A38 Roman Way / A442 Kidderminster Road Roundabout;
• Northbound approach to the A38 Roman Way / A4133 roundabout; and
• Northbound approach to the A38 Roman Way / B4090 Worcester Road roundabout.
The highway junction improvement schemes identified through SWDP 1 show an improvement in terms
of volume over capacity compared to the existing situation on all of the selected links. The inclusion of
the proposed schemes at the A38 Roman Way / B4090 Worcester Road and M5 Junction 5 does not
improve the volume over capacity result on the junctions to below 100% under the SWDP 1 scenario. The Vehicle / Trip Generation model shows the volume over capacity ratio on these junction approaches
to be further exacerbated under the SWDP 2 scenario.
DRAFT - SWDP 2 - PHASE 1 - TRANSPORT NETWORK IMPACT TN - AB /[INSERT DOCUMENT LOCATOR]
COPYRIGHT 2014 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
80
The Vehicle / Trip Generation model shows all the junction approaches with the proposed SWDP 1
scheme in place with a volume over capacity ratio of under 100% in the 2019 AM peak under the SWDP
1 scenario, continue to operate with a volume over capacity ratio under 100% in the SWDP 2 scenario. 2031 – AM Peak - Highway Network Impacts Worcester
The 2031 AM SWDP 2 development trip traffic data shows an increase in the number of trips compared
to the 2031 AM SWDP 1 scenario on all of the selected routes in and around Worcester.
Notable percentage increases in development vehicle trips are shown on the:
• Eastbound approach to the A44 / A4440 (Whittington Road / Swinesherd Way) Roundabout;
• Eastbound approach to the London Road / Whittington Road / Spetchley Road Gyratory;
• Westbound approach to the A44 / A4440 / A4103 Bromyard Road Roundabout;
• Northbound approach to the A38 / A4536 (Droitwich Road / Hurst Lane) priority junction; and
• North east bound approach to the A38 / A453 (Droitwich Road / Pershore Lane) signalised
junction.
The highway junction improvement schemes identified through SWDP 1 show an improvement in terms
of volume over capacity compared to the existing situation on all of the selected links. Despite the
inclusion of the proposed SWDP 1 schemes, some junction approaches with a volume over capacity ratio
of over 100% remain, notably:
• Northwest bound and southbound approach to the A44 / A4440 (Whittington Road /
Swinesherd Way) roundabout junction;
• Westbound approach to the A4536 Blackpole Road / Cotswold Way signalised junction;
• Northwest bound and Southbound approach to the A38 / A4538 (Droitwich Road / Pershore
Lane) signalised junction;
• Northbound approach to the M5 Junction 7 Roundabout; and
• A44 / A422 / Pershore Lane roundabout junction.
Additional junction approaches operate with a volume over capacity ratio greater than 100% under the
SWDP 2 development scenario. These include the following:
• Eastbound approach to the A44 / A4440 (Whittington Road / Swinesherd Way) roundabout;
• Eastbound approach to the London Road / Whittington Road / Spetchley Road Gyratory;
• Westbound approach to the A44 / A4440 / A4103 Bromyard Road roundabout;
• Northeast bound approach to the (A38 / A4538) Droitwich Road / Pershore Lane signal junction;
and
• Eastbound approach to M5 Junction 7. Great Malvern
The 2031 AM SWDP 2 development trip traffic data shows a variation in development traffic flows to
those shown under the SWDP 1 scenario.
Notable percentage increases in development vehicle trips are shown on the:
• Northbound and southbound approaches to the A4103 / B4503 Leigh Sinton Road Priority
Junction; DRAFT - SWDP 2 - PHASE 1 - TRANSPORT NETWORK IMPACT TN - AB/[INSERT DOCUMENT LOCATOR]
81
SWDP2 - PHASE 1 - IMPACTS ON NETWORK PERFORMANCE
• North east bound approach to the A449 Worcester Road / Howsell Road / Pickersleigh Road
Junction;
• Westbound, Southbound and Northbound approaches to the A449 Belle Vue Terrace / Wells Road / B4211 Church Street Priority Junction.
Percentage decreases in trips are shown on the:
• Northbound approach to the A449 Worcester Road / Townsend Way Roundabout;
• Northbound and westbound approaches to the B4208 Pickersleigh Road / North End Lane /
Hayslan Road signalised junction;
• Southbound approach to the B4211 Barnards Green Rd / B4208 Pickersleigh Rd / Upper Chase Rd / Court Rd / Avenue Rd Gyratory;
• Northbound approach to the B4208 Barnards Green Rd / Guarlford Road / Poolbrook Road
priority junction; and
• Southbound approach to the B4208 Blackmore Park Rd / B4209 Hanley Rd signal junction.
The highway junction improvement schemes identified through SWDP 1 show an improvement in terms
of volume over capacity compared to the existing situation at all of the selected junctions. Despite the
inclusion of the proposed SWDP 1 schemes, some junction approaches with volume over capacity result
of over 100% remain, notably:
• Southbound approach to the A449 Worcester Road / Townsend Way roundabout;
• North east bound and southbound approaches to the A449 Worcester Road / Howsell Road /
Pickersleigh Road priority junction;
• Westbound approach to the B4211 Barnards Green Rd / B4208 Pickersleigh Rd / Upper Chase Rd
/ Court Rd / Avenue Rd Gyratory; and
• Northbound, southbound and westbound approaches to the A449 Belle Vue Terrace / Wells
Road / B4211 Church Street priority junction.
Under the SWDP 2 development scenario the volume over capacity results on the links identified above
is further exacerbated and the following links also operate with a volume over capacity of above 100%:
• Southbound approach to A4103 / B4503 Leigh Sinton Road priority junction; and
• North east bound approach to the A449 Worcester Road / Townsend Way roundabout.
Evesham
The 2031 AM SWDP 2 development trip traffic data shows an increase in the number of trips compared
to the 2031 AM SWDP 1 scenario on all of the selected routes in and around Evesham.
Notable percentage increases are shown on the:
• Northbound approach to the A44 / A4184 / B4088 Evesham Road Roundabout;
• Northbound approach to the A44 / A46 Roundabout;
• Westbound approach to the A46 / A4184 Cheltenham Road roundabout; and
• Westbound approach to the A46 / The Link / Millennium Way roundabout.
The highway junction improvement schemes identified through SWDP 1 show an improvement in terms
of volume over capacity compared to the existing situation on all of the selected links. Despite the
inclusion of the proposed SWDP 1 schemes, some junction approaches with volume over capacity result
of over 100% remain, notably:
• Northbound approach to the A44 / A46 roundabout;
DRAFT - SWDP 2 - PHASE 1 - TRANSPORT NETWORK IMPACT TN - AB /[INSERT DOCUMENT LOCATOR] COPYRIGHT 2014 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
82
• Southbound approach to the (A4184 / B4624) Greenhill / High Street / Worcester Road signal
junction;
• Southbound approach to the Abbey Road / Pershore Road / Waterside / Cheltenham Road signal
junction;
• Southbound approach to the Vine Street / High Street / Bridge Street priority junction;
• Westbound approach to the A46 / A4184 Cheltenham Road roundabout;
• Eastbound and westbound approaches to the A46 / The Link / Millennium Way roundabout;
• Northbound approach to the A46 / Broadway Road roundabout; and
• Southbound approach to the A46 / B4035 Badsey Road roundabout.
The volume over capacity calculation on the links identified above is further exacerbated under the
SWDP 2 growth scenario.
Additional links performing with a volume over capacity result above 100% under the SWDP 2 scenario
include the following:
• Northbound and eastbound approaches to the A44 / A4184 / B4088 Evesham Road roundabout;
and
• Southbound approach to the A46 / A4184 Cheltenham Road roundabout.
Pershore
The 2031 AM SWDP 2 development trip traffic data shows an increase in the number of trips compared to the 2031 AM SWDP 1 scenario on all selected routes in and around Pershore.
Notable percentage increases are shown on the:
• Northbound and eastbound approaches to the A4104 / B4084 (Worcester Road / Three Springs
Road) priority junction;
• Northbound approach to the A44 / A4104 / B4082 (Allens Hill / Terrace Road / Main Street)
signal junction; and
• Westbound approach to the A44 Evesham Road roundabout.
Despite the highway junction improvement schemes identified through SWDP 1 a number of the
selected links show a volume over capacity ratio greater than 100% under SWDP 1 development
scenario, notably:
• Eastbound approach to the A44 / A4104 / B4082 (Allens Hill / Terrace Road / Main Street) signal
junction;
• Northbound approach to the (A4104 / B4084) Worcester Road / Three Springs Road; and
• Southbound approach to the (A4104 / B4084) Station Road / Worcester Road / High Street signal
junction.
Under the SWDP 2 development scenario the volume over capacity ratio increases on the links identified
above. The westbound approach to the A44 Evesham Road roundabout also operates with a volume
over capacity ratio greater than 100%. Droitwich Spa
The 2031 AM SWDP 2 development trip traffic data shows an increase in the number of trips compared
to the 2031 AM SWDP 1 scenario on most of the selected routes in and around Droitwich Spa. A slight
reduction in the number of development related trips is shown on the westbound approach to the A38
DRAFT - SWDP 2 - PHASE 1 - TRANSPORT NETWORK IMPACT TN - AB/[INSERT DOCUMENT LOCATOR]
83
SWDP2 - PHASE 1 - IMPACTS ON NETWORK PERFORMANCE
Roman Way / A442 Kidderminster Road Roundabout and the eastbound approach to the A38 Roman
Way / A4133 roundabout.
Notable percentage increases are shown on the:
• Northbound approach to the A38 Roman Way / A442 Kidderminster Road Roundabout;
• Northbound approach to the A38 Roman Way / A4133 roundabout; and
• Northbound approach to the A38 Roman Way / B4090 Worcester Road roundabout.
The highway junction improvement schemes identified through SWDP 1 show an improvement in terms
of volume over capacity compared to the existing situation on all of the selected links. The inclusion of
the proposed schemes at the A38 Roman Way / A442 Kidderminster Road, A38 Roman Way / B4090
Worcester Road and M5 Junction 5 does not improve the volume over capacity result of the junctions to
below 100% under the SWDP 1 scenario. Under the SWDP 2 scenario the volume over capacity result of
these junction approaches is further exacerbated.
2019 – PM Peak - Highway Network Impacts
Worcester
The 2019 PM SWDP 2 development trip traffic data shows an increase in the number of trips compared
to the 2019 PM SWDP 1 scenario on all of the selected routes in and around Worcester.
Notable percentage increases in development vehicle trips are shown on the:
• North west bound approach to the A44 / A4440 (Whittington Road / Swinesherd Way)
Roundabout;
• Westbound approach to the London Road / Whittington Road / Spetchley Road Gyratory;
• Southbound approach to the A38 / A4536 (Droitwich Road / Hurst Lane) priority junction; and
• Eastbound approach to the A38 / A453 (Droitwich Road / Pershore Lane) signalised junction.
The highway junction improvement schemes identified through SWDP 1 show an improvement in terms
of volume over capacity compared to the existing situation on all of the selected links. Despite the
inclusion of the proposed SWDP 1 schemes, some junction approaches with volume over capacity result
of over 100% remain, notably:
• Northwest bound and southbound approaches to the A44 / A4440 (Whittington Road /
Swinesherd Way) roundabout junction;
• North west bound and southbound approaches to the A38 / A4538 (Droitwich Road / Pershore Lane) signalised junction; and
• Northbound approach to the M5 junction 7.
The Vehicle / Trip Generation model shows all the junction approaches with the proposed SWDP 1
scheme in place with a volume over capacity ratio of under 100% in the 2019 AM peak under the SWDP
1 scenario, continue to operate with a volume over capacity ratio under 100% in the SWDP 2 scenario.
The junction volume over capacity increases to above 100% on the westbound approach to the A44 /
A4440 / A4103 Bromyard Road roundabout and westbound approach to the A4536 Blackpole Road /
Cotswold Way under the SWDP 2019 PM scenario.
Great Malvern
The 2019 PM SWDP 2 development trip traffic data shows a variation in development traffic flows to
those shown under the SWDP 1 scenario.
Notable percentage increases in development vehicle trips are shown on the:
• Northbound and southbound approaches to the A4103 / B4503 Leigh Sinton Road Priority
Junction;
DRAFT - SWDP 2 - PHASE 1 - TRANSPORT NETWORK IMPACT TN - AB /[INSERT DOCUMENT LOCATOR] COPYRIGHT 2014 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
84
• North east bound approach to the A449 Worcester Road / Howsell Road / Pickersleigh Road
Junction;
• Eastbound approach to the B4211 Barnards Green Rd / B4208 Pickersleigh Rd / Upper Chase Rd
/ Court Rd / Avenue Rd Gyratory;
• Westbound, Northbound and Southbound approaches to the A449 Belle Vue Terrace / Wells
Road / B4211 Church Street Priority Junction; and
• Eastbound approach to theB4208 Blackmore Park Rd / B4209 Hanley Rd signal junction.
Percentage decreases in trips are shown on the:
• Northbound approach to the A449 Worcester Road / Townsend Way Roundabout;
• Northbound and westbound approach to the B4208 Pickersleigh Road / North End Lane /
Hayslan Road signalised junction;
• Southbound approach to the B4211 Barnards Green Rd / B4208 Pickersleigh Rd / Upper Chase
Rd / Court Rd / Avenue Rd Gyratory;
• Northbound approach to the B4208 Barnards Green Rd / Guarlford Road / Poolbrook Road
priority junction; and
• Southbound approach to the B4208 Blackmore Park Rd / B4209 Hanley Rd signal junction.
The highway junction improvement schemes identified through SWDP 1 show an improvement in terms
of volume over capacity compared to the existing situation at all of the selected junctions. Despite the
inclusion of the proposed SWDP 1 schemes, some junction approaches with volume over capacity ratio
of over 100% remain, notably:
• North east bound and southbound approaches to A449 Worcester Road / Howsell Road /
Pickersleigh Road priority junction; and
• Southbound approach to the A449 Belle Vue Terrace / Wells Road / B4211 Church Street priority
junction.
Under the SWDP 2 development scenario the volume over capacity result on the links identified above is
further exacerbated and the following links also operate with a volume over capacity of above 100%:
• Southbound approach to the A4103 / B4503 Leigh Sinton Road priority junction; and
• Southbound approach to the A449 Worcester Road / Townsend Way roundabout.
Evesham
The 2019 PM SWDP 2 development trip traffic data shows an increase in the number of trips compared
to the 2019 PM SWDP 1 scenario on all of the selected routes in and around Evesham.
Notable percentage increases are shown on the:
• Northbound and eastbound approaches to the A44 / A4184 / B4088 Evesham Road Roundabout;
• Southbound approach to the A44 / A46 Roundabout;
• Southbound approach to the A46 / A4184 Cheltenham Road roundabout;
• Eastbound approach to the A46 / The Link / Millennium Way roundabout;
• Northbound approach to the A46 / Broadway Road roundabout; and
• Southbound approach to the A46 / B4035 Badsey Road Roundabout.
The highway junction improvement schemes identified through SWDP 1 show an improvement in terms
of volume over capacity compared to the existing situation on all of the selected links. Despite the
DRAFT - SWDP 2 - PHASE 1 - TRANSPORT NETWORK IMPACT TN - AB/[INSERT DOCUMENT LOCATOR]
85
SWDP2 - PHASE 1 - IMPACTS ON NETWORK PERFORMANCE
inclusion of the proposed SWDP 1 schemes, some junction approaches with a volume over capacity
result of over 100% remain, notably:
• Northbound approach to the A44 / A46 roundabout;
• Westbound approach to the A46 / A4184 Cheltenham Road roundabout; and
• Westbound approach to the A46 / The Link / Millennium Way roundabout.
The volume over capacity ratio result is further exacerbated under the SWDP 2 growth scenario with a
number of junction approaches showing volume over capacity ratios close to 100%.
Pershore
The 2019 PM SWDP 2 development trip traffic data shows an increase in the number of trips compared
to the 2019 PM SWDP 1 scenario on all of the selected routes in and around Pershore.
Notable percentage increases are shown on the northbound and eastbound approaches to the A4104 /
B4084 (Worcester Road / Three Springs Road) priority junction.
The highway junction improvement schemes identified through SWDP 1 show an improvement in terms
of volume over capacity compared to the existing situation on all of the selected links.
At most of the junctions the volume over capacity ratio is at approximately 100% or below with the
SWDP 1 proposed schemes in place under the SWDP 1 development scenario.
Under the SWDP 2 development scenario the eastbound approach to the A44 / A4104 / B4082 (Allens
Hill / Terrace Road / Main Street) signalised junctions and southbound approach to the A4104 / B4084
(Worcester Road / Three Springs Road) are operating at a volume over capacity ratio of over 100%.
Droitwich Spa
The 2019 PM SWDP 2 development trip traffic data shows an increase in the number of trips compared
to the 2019 PM SWDP 1 scenario on most of the selected routes in and around Droitwich Spa. A slight
reduction in the number of development related trips is shown on the eastbound approach to the A38 Roman Way / A4133 Roundabout.
Notable percentage increases are shown on the:
• Southbound approach to the A38 Roman Way / A442 Kidderminster Road Roundabout; and
• Southbound approach to the A38 Roman Way / A4133 roundabout.
The highway junction improvement schemes identified through SWDP 1 show an improvement in terms
of volume over capacity compared to the existing situation on all of the selected links. The inclusion of
the proposed schemes at the A38 Roman Way / B4090 Worcester Road, A38 Roman Way / B4090
Worcester Road and M5 Junction 5 does not improve the volume over capacity result of the junctions to
below 100% under the SWDP 1 scenario. Under the SWDP 2 scenario the volume over capacity result of
these junction approaches is further exacerbated.
The Vehicle / Trip Generation model shows all the junction approaches with the proposed SWDP 1
scheme in place with a volume over capacity ratio of under 100% in the 2019 AM peak under the SWDP
1 scenario, continue to operate with a volume over capacity ratio under 100% in the SWDP 2 scenario.
2031 – PM Peak - Highway Network Impacts
Worcester
The 2031 PM SWDP 2 development trip traffic data shows an increase in the number of trips compared
to the 2031 PM SWDP 1 scenario on all of the selected routes in and around Worcester.
Notable percentage increases in development vehicle trips are shown on the:
DRAFT - SWDP 2 - PHASE 1 - TRANSPORT NETWORK IMPACT TN - AB /[INSERT DOCUMENT LOCATOR] COPYRIGHT 2014 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
86
• North west bound approach to the A44 / A4440 (Whittington Road / Swinesherd Way)
Roundabout;
• Westbound approach to the London Road / Whittington Road / Spetchley Road Gyratory;
• Westbound approach to the (A44 / A4440 / A4103 ) Bromyard Road roundabout;
• Southbound and north west bound approaches to the A38 / A4536 (Droitwich Road / Hurst
Lane) priority junction;
• Southbound approach to the (A38 / A4538) Droitwich Road / Pershore Lane signal junction; and
• Southbound approach to the M5 Junction 7.
The highway junction improvement schemes identified through SWDP 1 show an improvement in terms
of volume over capacity compared to the existing situation on all of the selected links. Despite the
inclusion of the proposed SWDP 1 schemes, some junction approaches with volume over capacity
performance of over 100% remain, notably:
• Northwest bound and southbound approaches to the A44 / A4440 (Whittington Road /
Swinesherd Way) roundabout junction;
• Westbound approach to the (A44 / A4440 / A4103) Bromyard Road roundabout;
• Westbound approach to the A4536 Blackpole Road / Cotswold Way signal junction;
• North west bound and southbound approaches to the A38 / A4538 (Droitwich Road / Pershore
Lane) signalised junction;
• Northbound approach to the M5 junction 7; and
• Northbound and southbound approaches to the A44 / A422 / Pershore Lane roundabout.
The Vehicle / Trip Generation model shows all the junction approaches with the proposed SWDP 1 scheme in place with a volume over capacity ratio of under 100% in the 2019 AM peak under the SWDP
1 scenario, continue to operate with a volume over capacity ratio under 100% in the SWDP 2 scenario.
Great Malvern
The 2031 PM SWDP 2 development trip traffic data shows a variation in development traffic flows to
those shown under the SWDP 1 scenario.
Notable percentage increases in development vehicle trips are shown on the:
• Northbound and southbound approaches to the A4103 / B4503 Leigh Sinton Road Priority
Junction;
• North east bound approach to the A449 Worcester Road / Howsell Road / Pickersleigh Road
Junction;
• Eastbound approach to the B4211 Barnards Green Rd / B4208 Pickersleigh Rd / Upper Chase Rd
/ Court Rd / Avenue Rd Gyratory;
• Westbound and Northbound approaches to the A449 Belle Vue Terrace / Wells Road / B4211
Church Street Priority Junction; and
• Eastbound approach to the B4208 Blackmore Park Rd / B4209 Hanley Rd signal junction.
Percentage decreases in trips are shown on the:
• Northbound approach to the A449 Worcester Road / Townsend Way Roundabout;
• Northbound and westbound approach to the B4208 Pickersleigh Road / North End Lane /
Hayslan Road signalised junction;
DRAFT - SWDP 2 - PHASE 1 - TRANSPORT NETWORK IMPACT TN - AB/[INSERT DOCUMENT LOCATOR]
87
SWDP2 - PHASE 1 - IMPACTS ON NETWORK PERFORMANCE
• Southbound approach to the B4211 Barnards Green Rd / B4208 Pickersleigh Rd / Upper Chase
Rd / Court Rd / Avenue Rd Gyratory;
• Northbound approach to the B4208 Barnards Green Rd / Guarlford Road / Poolbrook Road priority junction; and
• Southbound approach to the B4208 Blackmore Park Rd / B4209 Hanley Rd signal junction.
The highway junction improvement schemes identified through SWDP 1 show an improvement in terms
of volume over capacity compared to the existing situation at all of the selected junctions. Despite the
inclusion of the proposed SWDP 1 schemes, some junction approaches with volume over capacity ratio
of over 100% remain, notably:
• Southbound and northeast bound approaches to the A449 Worcester Road / Townsend Way;
• North east bound and southbound approaches to A449 Worcester Road / Howsell Road /
Pickersleigh Road priority junction; and
• Southbound approach to the A449 Belle Vue Terrace / Wells Road / B4211 Church Street priority
junction.
Under the SWDP 2 development scenario the volume over capacity performance on the links identified
above is further exacerbated and the following links also operate with a volume over capacity of above
100%:
• Southbound approach to the A4103 / B4503 Leigh Sinton Road priority junction; and
• Westbound approach to the A449 Belle Vue Terrace / Wells Road / B4211 Church Street.
Evesham
The 2031 PM SWDP 2 development trip traffic data shows an increase in the number of trips compared
to the 2031 PM SWDP 1 scenario on all of the selected routes in and around Evesham.
Notable percentage increases are shown on the:
• Northbound and eastbound approaches to the A44 / A4184 / B4088 Evesham Road Roundabout;
• Southbound approach to the A44 / A46 Roundabout;
• Southbound approach to the (A4184 / B4624) Greenhill / High Street / Worcester Road signal
junction;
• Southbound approach to the Abbey Road / Pershore Road / Waterside / Cheltenham Road signal
junction;
• Southbound approach to the Vine Street / High Street / Bridge Street priority junction;
• Southbound approach to the A46 / A4184 Cheltenham Road roundabout;
• Eastbound approach to the A46 / The Link / Millennium Way roundabout;
• Northbound approach to the A46 / Broadway Road roundabout; and
• Southbound approach to theA46 / B4035 Badsey Road Roundabout.
The highway junction improvement schemes identified through SWDP 1 show an improvement in terms
of volume over capacity compared to the existing situation on all of the selected links. Despite the
inclusion of the proposed SWDP 1 schemes, some junction approaches with volume over capacity ratio
of over 100% remain, notably:
• Northbound approach to the A44 / A46 roundabout;
• Westbound approach to the A46 / A4184 Cheltenham Road roundabout; and
• Westbound approach to the A46 / The Link / Millennium Way roundabout.
DRAFT - SWDP 2 - PHASE 1 - TRANSPORT NETWORK IMPACT TN - AB /[INSERT DOCUMENT LOCATOR] COPYRIGHT 2014 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
88
The volume over capacity ratio results are further exacerbated under the SWDP 2 growth scenario. The
following additional junctions are forecast to operate at a volume over capacity ratio in excess of 100%
under the SWDP 2 growth scenario with the SWDP 1 schemes in place:
• Eastbound approach to the A44 / A4184 / B4088 Evesham Road roundabout;
• Southbound approach to the A44 / A46 roundabout;
• Southbound approach to the (A4184 / B4624) Greenhill / High Street / Worcester Road signal
junction;
• Southbound approach to the Abbey Road / Pershore Road / Waterside / Cheltenham Road signal
junction;
• Southbound approach to the Vine Street / High Street / Bridge Street priority junction;
• Northbound approach to the A46 / Broadway Road roundabout; and
• Southbound approach to the A46 / B4035 Badsey Road roundabout.
Pershore
The 2031 PM SWDP 2 development trip traffic data shows an increase in the number of trips compared
to the 2031 PM SWDP 1 scenario on all of the selected routes in and around Pershore.
Notable percentage increases are shown on the northbound and eastbound approaches to the A4104 /
B4084 (Worcester Road / Three Springs Road) priority junction.
The highway junction improvement schemes identified through SWDP 1 show an improvement in terms
of volume over capacity compared to the existing situation on all of the selected links.
At most of the junctions the volume over capacity ratio is at approximately 100% or below with the SWDP
1 proposed schemes in place under the SWDP 1 development scenario. The eastbound approach to the
A44 / A4104 / B4082 (Allens Hill / Terrace Road / Main Street) signal junction and the southbound
approach to the (A4104 / B4084) Station Road / Worcester Road / High Street signal junction are
operating at a volume over capacity ratio in excess of 100%. The volume over capacity ratio on these links
is further exacerbated which the addition of the SWDP 2 growth. Droitwich Spa
The 2031 PM SWDP 2 development trip traffic data shows an increase in the number of trips compared
to the 2031 PM SWDP 1 scenario on most of the selected routes in and around Droitwich Spa. A slight
reduction in the number of development related trips is shown on the eastbound approach to the A38 Roman Way / A4133 Roundabout.
Notable percentage increases are shown on the:
• Southbound approach to the A38 Roman Way / A442 Kidderminster Road Roundabout; and
• Southbound approach to the A38 Roman Way / A4133 roundabout.
The highway junction improvement schemes identified through SWDP 1 show an improvement in terms
of volume over capacity compared to the existing situation on all of the selected links. The inclusion of
the proposed schemes at the A38 Roman Way / B4090 Worcester Road, A38 Roman Way / A442
Kidderminster Road, A38 Roman Way / B4090 Worcester Road and M5 Junction 5 does not improve the
volume over capacity ratio of the junctions to below 100% under the SWDP 1 scenario. Under the SWDP
2 scenario the volume over capacity ratio of these junction approaches is further exacerbated. Under the
SWDP 2 scenario the southbound approach to the A38 Roman Way / A4133 roundabout is also shows a
volume over capacity ratio greater than 100%.
DRAFT - SWDP 2 - PHASE 1 - TRANSPORT NETWORK IMPACT TN - AB/[INSERT DOCUMENT LOCATOR]
89
Sustainable Transport SWDP2 - PHASE 1 - IMPACTS ON NETWORK PERFORMANCE
Data has been extracted from the Vehicle / Trip Generation Model to provide an initial commentary of
the sustainable travel trips (pedestrians, cyclists, bus) from the SWDP 2 development sites compared to
the SWDP 1 development sites.
Appendices E and F set out the forecast 24 hour sustainable travel trips from the Development Clusters
in the Vehicle / Trip Generation Model. The forecast number of sustainable travel trips from each
Development Cluster over a 24 hour period will be used as an indicator to the requirement for a
sustainable travel infrastructure scheme or service to link proposed development sites to the existing
sustainable travel network. The information set out in Appendices E and F will be used to inform
discussions at the Sustainable Travel Workshop to be held with WCC Officers on 4th July 2014.
The locations of the Development Clusters as modelled using the Vehicle / Trip Generation Model are
shown in Appendix G.
In order to most accurately model the SWDP 2 development assumptions there was a requirement to
add an additional four Development Clusters to the Vehicle / Trip Generation Model. The additional
Development Clusters are as follows:
• Worcester – Cluster 13 – Sites located along the A449 Corridor (Bromwich Road) south of
Worcester Town Centre;
• Worcester – Cluster 14 – Sites located along the A38 Corridor (Bath Road) south of Worcester
Town Centre;
• Wychavon – Cluster 23 – Yew Tree Development Site located off Pulley Lane, Droitwich Spa; and
• Wychavon – Cluster 24 – Harvington.
All of the above development sites show the requirement for sustainable travel infrastructure in the
2019 and 2031 with the SWDP 2 development proposals.
A brief commentary summarising the data contained in Appendices E and F is provided below to set out
the change in sustainable travel demand between SWDP 1 and SWDP 2 for 2019 and 2031.
2019
Appendix E shows the 2019 forecast demand for sustainable travel trips (pedestrian, cyclist, bus) from
the proposed development sites over a 24 hour period for SWDP 1 and SWDP 2.
The data extracted from the Vehicle / Trip Generation model shows additional demand under the SWDP
2 scenario for sustainable travel (Pedestrian, Cyclist and Bus) compared to the SWDP 1 scenario from the
following Worcester Development Clusters:
• Worcester – Cluster 1;
• Worcester – Cluster 2;
• Worcester – Cluster 3;
• Worcester – Cluster 7;
• Worcester – Cluster 10; and
• Worcester – Cluster 12.
Demand for sustainable travel shows notable reductions at Worcester Cluster 4 and Worcester Cluster
11.
The data extracted from the Vehicle / Trip Generation model shows additional demand under the SWDP
2 scenario for sustainable travel (Pedestrian, Cyclist and Bus) compared to the SWDP 1 scenario from the
following Malvern Hills Development Clusters:
• Malvern – Cluster 1; DRAFT - SWDP 2 - PHASE 1 - TRANSPORT NETWORK IMPACT TN - AB /[INSERT DOCUMENT LOCATOR]
COPYRIGHT 2014 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
90
• Malvern – Cluster 4;
• Malvern – Cluster 5;
• Malvern – Cluster 6;
• Malvern – Cluster 7;
• Malvern – Cluster 8;
• Malvern – Cluster 9;
• Malvern – Cluster 10;
• Malvern – Cluster 11;
• Malvern – Cluster 12;
• Malvern – Cluster 14; and
• Malvern – Cluster 17.
Demand for sustainable travel shows notable reductions at Malvern Clusters 2, 3, 13 and 15.
The data extracted from the Vehicle / Trip Generation model shows additional demand under the SWDP
2 scenario for sustainable travel (Pedestrian, Cyclist and Bus) compared to the SWDP 1 scenario from the
following Wychavon Development Clusters:
• Wychavon – Cluster 2;
• Wychavon – Cluster 4;
• Wychavon – Cluster 5;
• Wychavon – Cluster 6;
• Wychavon – Cluster 7;
• Wychavon – Cluster 8;
• Wychavon – Cluster 9;
• Wychavon – Cluster 11;
• Wychavon – Cluster 12;
• Wychavon – Cluster 13;
• Wychavon – Cluster 14;
• Wychavon – Cluster 15;
• Wychavon – Cluster 16; and
• Wychavon – Cluster 22.
Demand for sustainable travel shows notable reductions at Wychavon Clusters 17 and 19.
2031
Appendix F shows the 2031 forecast demand for sustainable travel trips (pedestrian, cyclist, bus) from
the proposed development sites over a 24 hour period for SWDP 1 and SWDP 2.
The data extracted from the Vehicle / Trip Generation model shows additional demand under the SWDP
2 scenario for sustainable travel (Pedestrian, Cyclist and Bus) compared to the SWDP 1 scenario from the
following Worcester Development Clusters:
• Worcester – Cluster 1;
DRAFT - SWDP 2 - PHASE 1 - TRANSPORT NETWORK IMPACT TN - AB/[INSERT DOCUMENT LOCATOR]
91
SWDP2 - PHASE 1 - IMPACTS ON NETWORK PERFORMANCE
• Worcester – Cluster 2;
• Worcester – Cluster 3;
• Worcester – Cluster 7;
• Worcester – Cluster 9;
• Worcester – Cluster 10; and
• Worcester – Cluster 12.
Demand for sustainable travel shows notable reductions at Worcester Clusters 4, 6 and 11.
The data extracted from the Vehicle / Trip Generation model shows additional demand under the SWDP
2 scenario for sustainable travel (Pedestrian, Cyclist and Bus) compared to the SWDP 1 scenario from the
following Malvern Hills Development Clusters:
• Malvern – Cluster 1;
• Malvern – Cluster 3;
• Malvern – Cluster 5;
• Malvern – Cluster 6;
• Malvern – Cluster 7;
• Malvern – Cluster 8;
• Malvern – Cluster 9;
• Malvern – Cluster 10;
• Malvern – Cluster 12;
• Malvern – Cluster 14;
• Malvern – Cluster 16; and
• Malvern – Cluster 17.
Demand for sustainable travel shows notable reductions at Malvern Clusters 2, 4, 11, 13 and 15.
The data extracted from the Vehicle / Trip Generation model shows additional demand under the SWDP
2 scenario for sustainable travel (Pedestrian, Cyclist and Bus) compared to the SWDP 1 scenario from the
following Wychavon Development Clusters:
• Wychavon – Cluster 2;
• Wychavon – Cluster 4;
• Wychavon – Cluster 5;
• Wychavon – Cluster 7;
• Wychavon – Cluster 8;
• Wychavon – Cluster 9;
• Wychavon – Cluster 11;
• Wychavon – Cluster 12;
• Wychavon – Cluster 13;
• Wychavon – Cluster 14; and
• Wychavon – Cluster 22. Demand for sustainable travel shows notable reductions at Wychavon Clusters 3, 17, 18, 19 and 20.
DRAFT - SWDP 2 - PHASE 1 - TRANSPORT NETWORK IMPACT TN - AB /[INSERT DOCUMENT LOCATOR] COPYRIGHT 2014 BY CH2M HILL, INC. • COMPANY CONFIDENTIAL
92
Concluding Remarks
The initial review of the data extracted from the Vehicle / Trip Generation Model shows additional trips
on the South Worcestershire transport network resulting from the additional residential allocations
proposed over the forecast period up to 2031.
In summary, the additional development trips on the highway network, under the SWDP 2 scenario,
leads to a general worsening of the highway network performance in terms of volume over capacity. The
impact of this change is particularly pronounced in the immediate vicinity of the development sites,
dependant location and scale of proposed development. That is, the Vehicle / Trip Generation model
forecasts some junctions to show worsening volume over capacity ratio performance due to an increase
in development quantum or a change in development location. Conversely, where a proposed
development site is removed or scaled down in terms of overall number of proposed dwellings, the
volume over capacity result at some junctions is improved. The impact of these changes and the
requirement for amended highway improvement schemes to support the increase in residential
development is to be discussed at a Highway Workshop with WCC Officers on Friday 4th July.
The increase in residential development shows a general increase in the demand for sustainable travel
across South Worcestershire. As shown with the highway network analysis, the impact is localised
dependant on the location and scale of proposed development. That is, some Development Clusters
show an overall increase in the demand for sustainable trips and others show a reduced demand.
However, it should be noted that all of the Development Clusters show a demand for sustainable travel,
albeit either increased or decreased. The scale of the demand for sustainable travel and the
infrastructure required to link each of the Development Clusters to the existing sustainable transport
network will be discussed at a Sustainable Travel Workshop with WCC Officers on Friday 4th July.
DRAFT - SWDP 2 - PHASE 1 - TRANSPORT NETWORK IMPACT TN - AB/[INSERT DOCUMENT LOCATOR]
93
Appendix A – 2019 AM SWDP 1 / SWDP 2 Highway Network
Performance
94
95
2019 - Worcester - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Junction
Existing Junction Type
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2019 AM Development
Trip Forecast Flow
SWDP 2 2019 AM Development
Trip Forecast Flow
Change in Development
Forecast Flow (+/-)
SWDP 1 2019 AM V/C Ratio
SWDP 2 2019 AM V/C Ratio
A4440/B4636
Roundabout
Northbound left slip, widening to eastbound entry of 40m,
southbound entry and exit widening as required to achieve
additional capacity
Northbound
838
1001
19%
-
-
(A44 / A4440) Nunnery W ay / Swinesherd
W ay / W ildwood Drive Roundabout
W estbound arm - W iden on entry for a distance of 100
metres. Land constraints will require CPO
W estbound
312
420
35%
71%
80%
(A44 / A4440) W hittington Road /
Swinesherd W ay
3 arm Roundabout
Convert to a 3 arm signal junction with 2 right turn and 2
ahead lanes from the motorway
North W est bound 811 970 20% 188% 201%
Southbound 806 928 15% 171% 181%
Eastbound 253 445 76% 114% 130%
London Road / W hittington Road /
Spetchley Road
Gyratory
East west movement predominant. Convert to 3 arm signals to
favour east west movement. Civils works extensive.
Eastbound
253
445
76%
114%
130%
W estbound 287 273 -5% 133% 131%
(A44 / A4440 / A4103)Bromyard Road Roundabout W iden west bound lane to 2 lanes for a distance of 100 metres W estbound
641
883
38%
78%
94%
(A38 / A4536) Droitwich Road / Hurst Lane
Priority Junction
Create a 3 arm signal junction on MOVA ; Constrained by road
space on southbound approach and northbound (railway bridge)
cannot gain extra lanes.
Southbound
149
156
5%
91%
91%
Northbound 130 206 58% - -
North westbound 85 85 0% 61% 61%
A4536 Blackpole Road / Cotswold W ay 3 arm Traffic Signal junction Refurbishment of junction and add MOVA. Extend existing 2
lane westbound approach
W estbound
359
409
14%
140%
146%
(A38 / A4538) Droitwich Road / Pershore
Lane
3 arm Traffic Signal junction
Put junction on to MOVA; Extra 50m lane to be added on
Pershore Lane and 100m on South bound and northbound
A38 on entrance and 100m from exit from junction.
North W est Bound
379
457
21%
226%
245%
Southbound 692 703 2% 223% 224%
North East Bound 204 290 42% 151% 165%
M5 Junction 7
Roundabout
Signalise North, South and Eastbound node (Any works would
come under the jurisdiction of the Highways Agency)
Southbound
358
375
5%
80%
82%
Eastbound 639 785 23% 109% 119%
Northbound 570 707 24% 123% 135%
A44 / A422 / Pershore Lane
Roundabout
W idening to north, south and west entry and exit of 80m in
each case
Eastbound 341 426 25% 83% 90%
Southbound 736 793 8% 149% 154%
Northbound 613 834 36% 106% 124%
2019 - Droitwich Spa - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Junction
Existing Junction Type
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2019 AM Development
Trip Forecast Flow
SWDP 2 2019 AM Development
Trip Forecast Flow
% Change in Development
Forecast Flow
SWDP 1 2019 AM V/C Ratio
SWDP 2 2019 AM V/C Ratio
A38 Roman W ay / B4090 Bromsgrove
Road
Traffic Signals
To increase capacity and through put add additional left turn
lane by widening for 80m – 2 straight ahead and one left turn Southbound
284
283
0%
129%
129%
A38 Roman W ay / A442 Kidderminster
Road
4 arm Roundabout
Partially signalise A38 slips and A442 Kidderminster road, all
other arms to remain give way - 3 nodes
Southbound 181 184 2% 34% 34%
Northbound 460 564 23% 101% 109%
W estbound 237 233 -2% 43% 43%
A38 Roman W ay / A4133
4 arm Roundabout
Signalise A38 approaches and Ombersley W ay approach – 3
nodes
Eastbound 195 202 4% 79% 79%
Southbound 303 311 3% 62% 63%
Northbound 389 484 24% 76% 84%
A38 Roman W ay / B4090 W orcester Road
5 arm Roundabout
Create a bypass lane of 250m continuing the A38 to a give
way on north bound away from roundabout arm. Land
ownership issues and tree clearance necessary
Northbound
752
886
18%
164%
175%
M5 Junction 5 Roundabout Signalise the southern roundabout using a 2 node approach. Northbound
247
254
3%
133%
134%
2019 - Pershore - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Junction
Existing Junction Type
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2019 AM Development
Trip Forecast Flow
SWDP 2 2019 AM Development
Trip Forecast Flow
% Change in Development
Forecast Flow
SWDP 1 2019 AM V/C Ratio
SWDP 2 2019 AM V/C Ratio
(A44 / A4104 / B4082) Allens Hill / Terrace
Road / Main Street
4 arm staggered Traffic Signal junction
Realign B4082 to create inline crossroads and widen Terrace
road to create to two lane approach allowing signal to run in
fewer stages. Stage two would involve widening on East bound
and W est bound approaches and exits to create to a additional
ahead lane
Northbound
199
285
43%
67%
81%
Eastbound 652 789 21% 142% 155%
(A4104 / B4084) W orcester Road / Three
Springs Road
Priority Junction
Convert existing priority junction to a 3 arm signalised junction Eastbound 24 37 54% 16% 16%
Northbound 123 221 80% 146% 166%
(A4104 / B4084) Station Road / W orcester
Road / High Street
3 arm Traffic Signal junction
Minor re-modelling of junction due to land constraints Southbound 177 217 23% 113% 119%
W estbound 149 172 15% 103% 107%
96
A4104 Station Road / B4083 W yre Road
Priority Junction
Convert existing priority junction to signalised 3 arm junction
Northbound 259 356 37% 31% 35%
W estbound 296 299 1% 111% 112%
Southbound 178 241 35% 53% 58%
A44 Evesham Road Roundabout Creat a bypass lane, shift roundabout north, hamburger
roundabout and signalise
W estbound
432
592
37%
132%
152%
2019 - Evesham - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Junction
Existing Junction Type
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2019 AM Development
Trip Forecast Flow
SWDP 2 2019 AM Development
Trip Forecast Flow
% Change in Development
Forecast Flow
SWDP 1 2019 AM V/C Ratio
SWDP 2 2019 AM V/C Ratio
(A44 / A4184 / B4088 Evesham Road) 4 arm Roundabout Proposing left turn slips off north bound over a distance of
60m and widen east bound over 70m Northbound 483 696 44% 95% 112%
Eastbound 395 497 26% 99% 107%
(A44 / A46)
Roundabout
Hamburger from north west bound to north bound or slip road
between northwest and west bound. Signals on 3 arms. Dual
between Junction 60 and 61 – distance of 150m; two lane
existing (Any works would come under the jurisdiction of the
Highways Agency)
Northbound
251
409
63%
128%
141%
Southbound 285 338 19% 89% 93%
(A4184 / B4624) Greenhill / High Street /
W orcester Road 3 arm Traffic Signals Limited junction works due to site constraints
Southbound
314
399
27%
96%
105%
Abbey Road / Pershore Road / W aterside /
Cheltenham Road Traffic Signals
Scheme for this junction included in Secured Major Scheme
Bid
Southbound
314
399
27%
96%
105%
Vine Street / High Street / Bridge Street Priority Junction Limited junction works due to site constraints Southbound 314 399 27% 96% 105%
A46 / A4184 Cheltenham Road
3 arm Roundabout
Extend two lane approaches southbound by 100m and
westbound by 100m. (Any works would come under the
jurisdiction of the Highways Agency)
Southbound
447
594
33%
97%
109%
W estbound 493 629 28% 127% 138%
A46 / The Link / Millennium W ay
4 arm Roundabout
Convert to 4 arm signal junction dual on approach; widen east
approach to two lanes additional 40m required. W iden on exit
of north and south bound by 50m to create merge on exit. (Any
works would come under the jurisdiction of the Highways
Agency)
Eastbound
454
558
23%
123%
132%
W estbound 493 629 28% 127% 138%
A46 / Broadway Road
4 arm Roundabout
Extend 2 lane entry north & south by 100m. W idening on exit
of 50m. (Any works would come under the jurisdiction of the
Highways Agency)
Northbound
454
558
23%
123%
132%
A46 / B4035 Badsey road
4 arm Roundabout
Extend 2 lane entry N & S by 100m and widen on exit of 100m.
(Any works would come under the jurisdiction of the Highways
Agency)
Southbound
395
454
15%
129%
134%
2019 - Great Malvern - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Junction
Existing Junction Type
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2019 AM Development
Trip Forecast Flow
SWDP 2 2019 AM Development
Trip Forecast Flow
% Change in Development
Forecast Flow
SWDP 1 2019 AM V/C Ratio
SWDP 2 2019 AM V/C Ratio
A4103 / B4503 Leigh Sinton Road
Priority Junction
Convert existing priority junction to signalised junction
North East bound 84 98 17% 49% 51%
Northbound 78 334 328% 105% 190%
Southbound 147 295 101% 66% 78%
A449 W orcester Road / Townsend W ay
4 arm Roundabout
W idening on exit from the south east, north west and north
bound arms
Southbound 645 738 14% 152% 159%
North East bound 494 554 12% 125% 130%
Northbound 126 106 -16% 39% 37%
A449 W orcester Road / Howsell Road /
Pickersleigh Road
Priority Junction (staggered)
Realign junction to create 4 arm signal crossroads using land
to the south - This land is park land. Existing road would
become access road to houses but no access to W orcester
Road
Northbound
110
106
-4%
104%
103%
North East bound 446 655 47% 98% 119%
Southbound 571 662 16% 152% 161%
B4208 Pickersleigh Road / North End Lane
/ Hayslan Road
Traffic Signals
Extend two lanes west bound back a further 60m to give more
efficient use of green time. Provide right turn facility for
southbound approaching vehicles
Northbound
194
179
-8%
70%
69%
W estbound 163 150 -8% 95% 93%
B4211 Barnards Green Rd / B4208
Pickersleigh Rd / Upper Chase Rd / Court
Rd / Avenue Rd
Gyratory
Covert existing gyratory junction to signalised junction
Eastbound
122
174
43%
240%
257%
Southbound 179 166 -7% 248% 243%
W estbound 314 318 1% 42% 42%
A449 Belle Vue Terrace / W ells Road /
B4211 Church Street
Priority Junction
Change in junction priority and signalised A449
W estbound 103 196 90% 205% 236%
Southbound 252 388 54% 42% 53%
Northbound 149 198 33% 69% 73%
B4208 Barnards Green Rd / Guarlford Road
/ Poolbrook Road
Priority Junction
Convert existing priority junction to signalised junction with
revised northbound approach
Northbound 261 243 -7% 213% 207%
W estbound 75 91 21% 26% 28%
Eastbound 383 412 8% 62% 64%
B4208 Blackmore Park Rd / B4209 Hanley
Rd
Traffic Signals
Additional lanes approaching junction
Eastbound
18
21
17%
37%
38%
Southbound 254 240 -6% 113% 111%
W estbound 86 102 19% 88% 90%
Northbound 10 13 30% 32% 33%
97
Appendix B – 2031 AM SWDP 1 / SWDP 2 Highway Network
Performance
98
99
2031 - Worcester - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Location
Existing Situation
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2031 AM Development
Trip Forecast Flow
SWDP 2 2031 AM Development
Trip Forecast Flow
Change in Development
Forecast Flow (+/-)
SWDP 1 2031 AM V/C Ratio -
Existing Junction Set-up
SWDP 2 2031 AM V/C Ratio -
Existing Junction Set-up
A4440/B4636
Roundabout
Northbound left slip, widening to eastbound entry of 40m,
southbound entry and exit widening as required to achieve
additional capacity
Northbound
1738
2082
20%
-
-
(A44 / A4440) Nunnery W ay / Swinesherd
W ay / W ildwood Drive Roundabout
W estbound arm - W iden on entry for a distance of 100
metres. Land constraints will require CPO
W estbound
594
718
21%
95%
105%
(A44 / A4440) W hittington Road /
Swinesherd W ay
3 arm Roundabout
Convert to a 3 arm signal junction with 2 right turn and 2
ahead lanes from the motorway
North W est bound 1791 2127 19% 269% 297%
Southbound 1469 1682 14% 226% 244%
Eastbound 517 687 33% 136% 150%
London Road / W hittington Road /
Spetchley Road
Gyratory
East west movement predominant. Convert to 3 arm signals to
favour east west movement. Civils works extensive.
Eastbound
517
687
33%
136%
150%
W estbound 582 585 1% 162% 163%
(A44 / A4440 / A4103)Bromyard Road Roundabout W iden west bound lane to 2 lanes for a distance of 100 metres W estbound
1132
1767
56%
111%
153%
(A38 / A4536) Droitwich Road / Hurst Lane
Priority Junction
Create a 3 arm signal junction on MOVA ; Constrained by road
space on southbound approach and northbound (railway bridge)
cannot gain extra lanes.
Southbound
253
316
25%
99%
105%
Northbound 225 323 44% - -
North westbound 130 144 11% 65% 66%
A4536 Blackpole Road / Cotswold W ay 3 arm Traffic Signal junction Refurbishment of junction and add MOVA. Extend existing 2
lane westbound approach
W estbound
660
748
13%
177%
188%
(A38 / A4538) Droitwich Road / Pershore
Lane
3 arm Traffic Signal junction
Put junction on to MOVA; Extra 50m lane to be added on
Pershore Lane and 100m on South bound and northbound
A38 on entrance and 100m from exit from junction.
North W est Bound
646
827
28%
293%
338%
Southbound 1171 1400 20% 271% 294%
North East Bound 343 457 33% 174% 193%
M5 Junction 7
Roundabout
Signalise North, South and Eastbound node (Any works would
come under the jurisdiction of the Highways Agency)
Southbound
649
747
15%
105%
113%
Eastbound 1255 1451 16% 151% 164%
Northbound 1110 1276 15% 168% 182%
A44 / A422 / Pershore Lane
Roundabout
W idening to north, south and west entry and exit of 80m in
each case
Eastbound 751 872 16% 117% 127%
Southbound 1654 1723 4% 226% 231%
Northbound 1146 1466 28% 150% 177%
2031 - Droitwich Spa - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Location
Existing Situation
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2031 AM Development
Trip Forecast Flow
SWDP 2 2031 AM Development
Trip Forecast Flow
% Change in Development
Forecast Flow
SWDP 1 2031 AM V/C Ratio
SWDP 2 2031 AM V/C Ratio
A38 Roman W ay / B4090 Bromsgrove
Road
Traffic Signals
To increase capacity and through put add additional left turn
lane by widening for 80m – 2 straight ahead and one left turn Southbound
495
508
3%
150%
151%
A38 Roman W ay / A442 Kidderminster
Road
4 arm Roundabout
Partially signalise A38 slips and A442 Kidderminster road, all
other arms to remain give way - 3 nodes
Southbound 331 348 5% 46% 48%
Northbound 807 1065 32% 130% 151%
W estbound 442 438 -1% 60% 60%
A38 Roman W ay / A4133
4 arm Roundabout
Signalise A38 approaches and Ombersley W ay approach – 3
nodes
Eastbound 340 303 -11% 91% 88%
Southbound 590 632 7% 86% 89%
Northbound 676 992 47% 100% 126%
A38 Roman W ay / B4090 W orcester Road
5 arm Roundabout
Create a bypass lane of 250m continuing the A38 to a give
way on north bound away from roundabout arm. Land
ownership issues and tree clearance necessary
Northbound
1220
1678
38%
203%
241%
M5 Junction 5 Roundabout Signalise the southern roundabout using a 2 node approach. Northbound
413
449
9%
147%
150%
2031 - Pershore - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Location
Existing Situation
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2031 AM Development
Trip Forecast Flow
SWDP 2 2031 AM Development
Trip Forecast Flow
% Change in Development
Forecast Flow
SWDP 1 2031 AM V/C Ratio
SWDP 2 2031 AM V/C Ratio
(A44 / A4104 / B4082) Allens Hill / Terrace
Road / Main Street
4 arm staggered Traffic Signal junction
Realign B4082 to create inline crossroads and widen Terrace
road to create to two lane approach allowing signal to run in
fewer stages. Stage two would involve widening on East bound
and W est bound approaches and exits to create to a additional
ahead lane
Northbound
452
551
22%
109%
126%
Eastbound 1502 1719 14% 227% 248%
(A4104 / B4084) W orcester Road / Three
Springs Road
Priority Junction
Convert existing priority junction to a 3 arm signalised junction Eastbound 50 77 54% 17% 18%
Northbound 351 455 30% 192% 213%
(A4104 / B4084) Station Road / W orcester
Road / High Street
3 arm Traffic Signal junction
Minor re-modelling of junction due to land constraints Southbound 478 529 11% 163% 171%
W estbound 292 316 8% 127% 131%
100
A4104 Station Road / B4083 W yre Road
Priority Junction
Convert existing priority junction to signalised 3 arm junction
Northbound 540 654 21% 42% 47%
W estbound 561 564 1% 164% 165%
Southbound 441 533 21% 75% 83%
A44 Evesham Road Roundabout Creat a bypass lane, shift roundabout north, hamburger
roundabout and signalise
W estbound
815
1057
30%
180%
210%
2031 - Evesham - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Location
Existing Situation
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2031 AM Development
Trip Forecast Flow
SWDP 2 2031 AM Development
Trip Forecast Flow
% Change in Development
Forecast Flow
SWDP 1 2031 AM V/C Ratio
SWDP 2 2031 AM V/C Ratio
(A44 / A4184 / B4088 Evesham Road) 4 arm Roundabout Proposing left turn slips off north bound over a distance of
60m and widen east bound over 70m Northbound 719 1030 43% 114% 140%
Eastbound 733 889 21% 127% 140%
(A44 / A46)
Roundabout
Hamburger from north west bound to north bound or slip road
between northwest and west bound. Signals on 3 arms. Dual
between Junction 60 and 61 – distance of 150m; two lane
existing (Any works would come under the jurisdiction of the
Highways Agency)
Northbound
517
754
46%
150%
170%
Southbound 547 642 17% 111% 119%
(A4184 / B4624) Greenhill / High Street /
W orcester Road 3 arm Traffic Signals Limited junction works due to site constraints
Southbound
525
655
25%
118%
131%
Abbey Road / Pershore Road / W aterside /
Cheltenham Road Traffic Signals
Scheme for this junction included in Secured Major Scheme
Bid
Southbound
525
655
25%
118%
131%
Vine Street / High Street / Bridge Street Priority Junction Limited junction works due to site constraints Southbound 525 655 25% 118% 131%
A46 / A4184 Cheltenham Road
3 arm Roundabout
Extend two lane approaches southbound by 100m and
westbound by 100m. (Any works would come under the
jurisdiction of the Highways Agency)
Southbound
788
948
20%
125%
139%
W estbound 687 882 28% 143% 159%
A46 / The Link / Millennium W ay
4 arm Roundabout
Convert to 4 arm signal junction dual on approach; widen east
approach to two lanes additional 40m required. W iden on exit
of north and south bound by 50m to create merge on exit. (Any
works would come under the jurisdiction of the Highways
Agency)
Eastbound
772
904
17%
149%
160%
W estbound 687 882 28% 143% 159%
A46 / Broadway Road
4 arm Roundabout
Extend 2 lane entry north & south by 100m. W idening on exit
of 50m. (Any works would come under the jurisdiction of the
Highways Agency)
Northbound
772
904
17%
149%
160%
A46 / B4035 Badsey road
4 arm Roundabout
Extend 2 lane entry N & S by 100m and widen on exit of 100m.
(Any works would come under the jurisdiction of the Highways
Agency)
Southbound
751
848
13%
159%
167%
2031 - Great Malvern - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Location
Existing Situation
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2031 AM Development
Trip Forecast Flow
SWDP 2 2031 AM Development
Trip Forecast Flow
% Change in Development
Forecast Flow
SWDP 1 2031 AM V/C Ratio
SWDP 2 2031 AM V/C Ratio
A4103 / B4503 Leigh Sinton Road
Priority Junction
Convert existing priority junction to signalised junction
North East bound 166 186 12% 56% 58%
Northbound 129 427 231% 122% 221%
Southbound 287 547 91% 77% 99%
A449 W orcester Road / Townsend W ay
4 arm Roundabout
W idening on exit from the south east, north west and north
bound arms
Southbound 988 1143 16% 180% 193%
North East bound 788 926 18% 150% 161%
Northbound 203 153 -25% 45% 41%
A449 W orcester Road / Howsell Road /
Pickersleigh Road
Priority Junction (staggered)
Realign junction to create 4 arm signal crossroads using land
to the south - This land is park land. Existing road would
become access road to houses but no access to W orcester
Road
Northbound
148
136
-8%
117%
113%
North East bound 696 953 37% 123% 148%
Southbound 860 1042 21% 181% 199%
B4208 Pickersleigh Road / North End Lane
/ Hayslan Road
Traffic Signals
Extend two lanes west bound back a further 60m to give more
efficient use of green time. Provide right turn facility for
southbound approaching vehicles
Northbound
281
253
-10%
79%
76%
W estbound 268 227 -15% 108% 103%
B4211 Barnards Green Rd / B4208
Pickersleigh Rd / Upper Chase Rd / Court
Rd / Avenue Rd
Gyratory
Covert existing gyratory junction to signalised junction
Eastbound
226
274
21%
274%
290%
Southbound 291 272 -7% 285% 279%
W estbound 483 474 -2% 49% 48%
A449 Belle Vue Terrace / W ells Road /
B4211 Church Street
Priority Junction
Change in junction priority and signalised A449
W estbound 174 259 49% 229% 257%
Southbound 447 673 51% 58% 77%
Northbound 203 283 39% 73% 80%
B4208 Barnards Green Rd / Guarlford Road
/ Poolbrook Road
Priority Junction
Convert existing priority junction to signalised junction with
revised northbound approach
Northbound 408 371 -9% 262% 250%
W estbound 101 123 22% 28% 30%
Eastbound 616 631 2% 81% 83%
B4208 Blackmore Park Rd / B4209 Hanley
Rd
Traffic Signals
Additional lanes approaching junction
Eastbound
42
44
5%
41%
41%
Southbound 408 383 -6% 139% 135%
W estbound 162 161 -1% 100% 100%
Northbound 19 20 5% 34% 34%
101
Appendix C – 2019 PM SWDP 1 / SWDP 2 Highway Network
Performance
102
103
2019 - Worcester - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Location
Existing Situation
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2019 PM Development
Trip Forecast Flow
SWDP 2 2019 PM Development
Trip Forecast Flow
Change in Development
Forecast Flow (+/-)
SWDP 1 2019 PM V/C Ratio
SWDP 2 2019 PM V/C Ratio
A4440/B4636
Roundabout
Northbound left slip, widening to eastbound entry of 40m,
southbound entry and exit widening as required to achieve
additional capacity
Northbound
934
1078
15%
-
-
(A44 / A4440) Nunnery W ay / Swinesherd
W ay / W ildwood Drive Roundabout
W estbound arm - W iden on entry for a distance of 100
metres. Land constraints will require CPO
W estbound
377
471
25%
79%
87%
(A44 / A4440) W hittington Road /
Swinesherd W ay
3 arm Roundabout
Convert to a 3 arm signal junction with 2 right turn and 2
ahead lanes from the motorway
North W est bound 968 1241 28% 166% 188%
Southbound 905 1070 18% 172% 186%
Eastbound 279 292 5% 103% 105%
London Road / W hittington Road /
Spetchley Road
Gyratory
East west movement predominant. Convert to 3 arm signals to
favour east west movement. Civils works extensive.
Eastbound
279
292
5%
103%
105%
W estbound 260 418 61% 122% 138%
(A44 / A4440 / A4103)Bromyard Road Roundabout W iden west bound lane to 2 lanes for a distance of 100 metres W estbound
1003
1212
21%
124%
138%
(A38 / A4536) Droitwich Road / Hurst Lane
Priority Junction
Create a 3 arm signal junction on MOVA ; Constrained by road
space on southbound approach and northbound (railway bridge)
cannot gain extra lanes.
Southbound
202
275
36%
71%
77%
Northbound 111 138 24% - -
North westbound 66 70 6% 61% 61%
A4536 Blackpole Road / Cotswold W ay 3 arm Traffic Signal junction Refurbishment of junction and add MOVA. Extend existing 2
lane westbound approach
W estbound
504
619
23%
155%
169%
(A38 / A4538) Droitwich Road / Pershore
Lane
3 arm Traffic Signal junction
Put junction on to MOVA; Extra 50m lane to be added on
Pershore Lane and 100m on South bound and northbound
A38 on entrance and 100m from exit from junction.
North W est Bound
409
438
7%
251%
258%
Southbound 766 879 15% 174% 185%
North East Bound 164 180 10% 133% 136%
M5 Junction 7
Roundabout
Signalise North, South and Eastbound node (Any works would
come under the jurisdiction of the Highways Agency)
Southbound
409
477
17%
62%
68%
Eastbound 513 616 20% 118% 125%
Northbound 716 800 12% 137% 144%
A44 / A422 / Pershore Lane
Roundabout
W idening to north, south and west entry and exit of 80m in
each case
Eastbound 332 439 32% 73% 82%
Southbound 525 650 24% 115% 125%
Northbound 668 833 25% 114% 128%
2019 - Droitwich Spa - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Location
Existing Situation
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2019 PM Development
Trip Forecast Flow
SWDP 2 2019 PM Development
Trip Forecast Flow
% Change in Development
Forecast Flow
SWDP 1 2019 PM V/C Ratio
SWDP 2 2019 PM V/C Ratio
A38 Roman W ay / B4090 Bromsgrove
Road
Traffic Signals
To increase capacity and through put add additional left turn
lane by widening for 80m – 2 straight ahead and one left turn Southbound
227
233
3%
165%
165%
A38 Roman W ay / A442 Kidderminster
Road
4 arm Roundabout
Partially signalise A38 slips and A442 Kidderminster road, all
other arms to remain give way - 3 nodes
Southbound 330 412 25% 118% 125%
Northbound 338 355 5% 63% 64%
W estbound 222 224 1% 45% 45%
A38 Roman W ay / A4133
4 arm Roundabout
Signalise A38 approaches and Ombersley W ay approach – 3
nodes
Eastbound 148 147 -1% 47% 47%
Southbound 448 539 20% 88% 96%
Northbound 285 298 5% 80% 81%
A38 Roman W ay / B4090 W orcester Road
5 arm Roundabout
Create a bypass lane of 250m continuing the A38 to a give
way on north bound away from roundabout arm. Land
ownership issues and tree clearance necessary
Northbound
761
791
4%
165%
167%
M5 Junction 5 Roundabout Signalise the southern roundabout using a 2 node approach. Northbound
279
278
0%
124%
124%
2019 - Pershore - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Location
Existing Situation
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2019 PM Development
Trip Forecast Flow
SWDP 2 2019 PM Development
Trip Forecast Flow
% Change in Development
Forecast Flow
SWDP 1 2019 PM V/C Ratio
SWDP 2 2019 PM V/C Ratio
(A44 / A4104 / B4082) Allens Hill / Terrace
Road / Main Street
4 arm staggered Traffic Signal junction
Realign B4082 to create inline crossroads and widen Terrace
road to create to two lane approach allowing signal to run in
fewer stages. Stage two would involve widening on East bound
and W est bound approaches and exits to create to a additional
ahead lane
Northbound
191
263
38%
87%
99%
Eastbound 623 833 34% 122% 143%
(A4104 / B4084) W orcester Road / Three
Springs Road
Priority Junction
Convert existing priority junction to a 3 arm signalised junction Eastbound 43 56 30% 25% 26%
Northbound 114 203 78% 111% 129%
(A4104 / B4084) Station Road / W orcester
Road / High Street
3 arm Traffic Signal junction
Minor re-modelling of junction due to land constraints Southbound 241 331 37% 143% 158%
W estbound 165 198 20% 111% 116%
104
A4104 Station Road / B4083 W yre Road
Priority Junction
Convert existing priority junction to signalised 3 arm junction
Northbound 176 232 32% 24% 26%
W estbound 217 228 5% 79% 81%
Southbound 211 296 40% 40% 47%
A44 EveshPM Road Roundabout Creat a bypass lane, shift roundabout north, hPMburger
roundabout and signalise
W estbound
410
531
30%
129%
145%
2019 - Evesham - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Location
Existing Situation
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2019 PM Development
Trip Forecast Flow
SWDP 2 2019 PM Development
Trip Forecast Flow
% Change in Development
Forecast Flow
SWDP 1 2019 PM V/C Ratio
SWDP 2 2019 PM V/C Ratio
(A44 / A4184 / B4088 Evesham Road) 4 arm Roundabout Proposing left turn slips off north bound over a distance of
60m and widen east bound over 70m Northbound 355 475 34% 96% 106%
Eastbound 436 589 35% 84% 97%
(A44 / A46)
Roundabout
Hamburger from north west bound to north bound or slip road
between northwest and west bound. Signals on 3 arms. Dual
between Junction 60 and 61 – distance of 150m; two lane
existing (Any works would come under the jurisdiction of the
Highways Agency)
Northbound
366
447
22%
130%
137%
Southbound 289 464 61% 108% 123%
(A4184 / B4624) Greenhill / High Street /
W orcester Road 3 arm Traffic Signals Limited junction works due to site constraints
Southbound
440
631
43%
92%
111%
Abbey Road / Pershore Road / W aterside /
Cheltenham Road Traffic Signals
Scheme for this junction included in Secured Major Scheme
Bid
Southbound
440
631
43%
92%
111%
Vine Street / High Street / Bridge Street Priority Junction Limited junction works due to site constraints Southbound 440 631 43% 92% 111%
A46 / A4184 Cheltenham Road
3 arm Roundabout
Extend two lane approaches southbound by 100m and
westbound by 100m. (Any works would come under the
jurisdiction of the Highways Agency)
Southbound
234
409
75%
91%
105%
W estbound 403 521 29% 129% 139%
A46 / The Link / Millennium W ay
4 arm Roundabout
Convert to 4 arm signal junction dual on approach; widen east
approach to two lanes additional 40m required. W iden on exit
of north and south bound by 50m to create merge on exit. (Any
works would come under the jurisdiction of the Highways
Agency)
Eastbound
423
557
32%
119%
130%
W estbound 403 521 29% 129% 139%
A46 / Broadway Road
4 arm Roundabout
Extend 2 lane entry north & south by 100m. W idening on exit
of 50m. (Any works would come under the jurisdiction of the
Highways Agency)
Northbound
423
557
32%
119%
130%
A46 / B4035 Badsey road
4 arm Roundabout
Extend 2 lane entry N & S by 100m and widen on exit of 100m.
(Any works would come under the jurisdiction of the Highways
Agency)
Southbound
246
391
59%
146%
158%
2019 - Great Malvern - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Location
Existing Situation
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2019 PM Development
Trip Forecast Flow
SWDP 2 2019 PM Development
Trip Forecast Flow
% Change in Development
Forecast Flow
SWDP 1 2019 PM V/C Ratio
SWDP 2 2019 PM V/C Ratio
A4103 / B4503 Leigh Sinton Road
Priority Junction
Convert existing priority junction to signalised junction
North East bound 105 163 55% 35% 40%
Northbound 102 364 257% 111% 198%
Southbound 208 406 95% 70% 86%
A449 W orcester Road / Townsend W ay
4 arm Roundabout
W idening on exit from the south east, north west and north
bound arms
Southbound 481 533 11% 123% 127%
North East bound 547 637 16% 105% 113%
Northbound 153 138 -10% 106% 104%
A449 W orcester Road / Howsell Road /
Pickersleigh Road
Priority Junction (staggered)
Realign junction to create 4 arm signal crossroads using land
to the south - This land is park land. Existing road would
become access road to houses but no access to W orcester
Road
Northbound
49
43
-12%
64%
62%
North East bound 385 505 31% 111% 123%
Southbound 509 572 12% 118% 124%
B4208 Pickersleigh Road / North End Lane
/ Hayslan Road
Traffic Signals
Extend two lanes west bound back a further 60m to give more
efficient use of green time. Provide right turn facility for
southbound approaching vehicles
Northbound
167
153
-8%
77%
76%
W estbound 122 103 -16% 116% 114%
B4211 Barnards Green Rd / B4208
Pickersleigh Rd / Upper Chase Rd / Court
Rd / Avenue Rd
Gyratory
Covert existing gyratory junction to signalised junction
Eastbound
95
184
94%
173%
202%
Southbound 181 166 -8% 261% 256%
W estbound 360 386 7% 35% 36%
A449 Belle Vue Terrace / W ells Road /
B4211 Church Street
Priority Junction
Change in junction priority and signalised A449
W estbound 120 188 57% 161% 184%
Southbound 467 637 36% 54% 68%
Northbound 93 137 47% 48% 51%
B4208 Barnards Green Rd / Guarlford Road
/ Poolbrook Road
Priority Junction
Convert existing priority junction to signalised junction with
revised northbound approach
Northbound 237 221 -7% 187% 182%
W estbound 50 67 34% 29% 30%
Eastbound 311 320 3% 47% 48%
B4208 Blackmore Park Rd / B4209 Hanley
Rd
Traffic Signals
Additional lanes approaching junction
Eastbound
11
17
55%
26%
27%
Southbound 241 222 -8% 98% 95%
W estbound 112 125 12% 71% 73%
Northbound 9 12 33% 23% 24%
105
Appendix D – 2031 PM SWDP 1 / SWDP 2 Highway Network
Performance
106
107
2031 - Worcester - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Location
Existing Situation
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2031 PM Development
Trip Forecast Flow
SWDP 2 2031 PM Development
Trip Forecast Flow
Change in Development
Forecast Flow (+/-)
SWDP 1 2031 PM V/C Ratio
SWDP 2 2031 PM V/C Ratio
A4440/B4636
Roundabout
Northbound left slip, widening to eastbound entry of 40m,
southbound entry and exit widening as required to achieve
additional capacity
Northbound
1612
1859
15%
-
-
(A44 / A4440) Nunnery W ay / Swinesherd
W ay / W ildwood Drive Roundabout
W estbound arm - W iden on entry for a distance of 100
metres. Land constraints will require CPO
W estbound
748
874
17%
110%
120%
(A44 / A4440) W hittington Road /
Swinesherd W ay
3 arm Roundabout
Convert to a 3 arm signal junction with 2 right turn and 2
ahead lanes from the motorway
North W est bound 1534 1891 23% 213% 242%
Southbound 1717 2050 19% 240% 267%
Eastbound 560 580 4% 127% 129%
London Road / W hittington Road /
Spetchley Road
Gyratory
East west movement predominant. Convert to 3 arm signals to
favour east west movement. Civils works extensive.
Eastbound
560
580
4%
127%
129%
W estbound 524 664 27% 149% 163%
(A44 / A4440 / A4103)Bromyard Road Roundabout W iden west bound lane to 2 lanes for a distance of 100 metres W estbound
1520
2032
34%
159%
193%
(A38 / A4536) Droitwich Road / Hurst Lane
Priority Junction
Create a 3 arm signal junction on MOVA ; Constrained by road
space on southbound approach and northbound (railway bridge)
cannot gain extra lanes.
Southbound
332
443
33%
82%
91%
Northbound 210 245 17% - -
North westbound 110 145 32% 65% 68%
A4536 Blackpole Road / Cotswold W ay 3 arm Traffic Signal junction Refurbishment of junction and add MOVA. Extend existing 2
lane westbound approach
W estbound
896
1080
21%
204%
227%
(A38 / A4538) Droitwich Road / Pershore
Lane
3 arm Traffic Signal junction
Put junction on to MOVA; Extra 50m lane to be added on
Pershore Lane and 100m on South bound and northbound
A38 on entrance and 100m from exit from junction.
North W est Bound
691
808
17%
321%
351%
Southbound 1186 1620 37% 216% 259%
North East Bound 281 349 24% 153% 164%
M5 Junction 7
Roundabout
Signalise North, South and Eastbound node (Any works would
come under the jurisdiction of the Highways Agency)
Southbound
639
812
27%
82%
96%
Eastbound 907 1038 14% 144% 153%
Northbound 1569 1669 6% 208% 217%
A44 / A422 / Pershore Lane
Roundabout
W idening to north, south and west entry and exit of 80m in
each case
Eastbound 606 730 20% 95% 106%
Southbound 1048 1197 14% 158% 171%
Northbound 1413 1666 18% 176% 197%
2031 - Droitwich Spa - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Location
Existing Situation
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2031 PM Development
Trip Forecast Flow
SWDP 2 2031 PM Development
Trip Forecast Flow
% Change in Development
Forecast Flow
SWDP 1 2031 PM V/C Ratio
SWDP 2 2031 PM V/C Ratio
A38 Roman W ay / B4090 Bromsgrove
Road
Traffic Signals
To increase capacity and through put add additional left turn
lane by widening for 80m – 2 straight ahead and one left turn Southbound
384
418
9%
181%
184%
A38 Roman W ay / A442 Kidderminster
Road
4 arm Roundabout
Partially signalise A38 slips and A442 Kidderminster road, all
other arms to remain give way - 3 nodes
Southbound 557 714 28% 137% 150%
Northbound 622 689 11% 87% 92%
W estbound 377 418 11% 58% 62%
A38 Roman W ay / A4133
4 arm Roundabout
Signalise A38 approaches and Ombersley W ay approach – 3
nodes
Eastbound 316 305 -3% 61% 60%
Southbound 760 989 30% 114% 133%
Northbound 470 570 21% 95% 104%
A38 Roman W ay / B4090 W orcester Road
5 arm Roundabout
Create a bypass lane of 250m continuing the A38 to a give
way on north bound away from roundabout arm. Land
ownership issues and tree clearance necessary
Northbound
1242
1523
23%
205%
228%
M5 Junction 5 Roundabout Signalise the southern roundabout using a 2 node approach. Northbound
482
499
4%
141%
142%
2031 - Pershore - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Location
Existing Situation
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2031 PM Development
Trip Forecast Flow
SWDP 2 2031 PM Development
Trip Forecast Flow
% Change in Development
Forecast Flow
SWDP 1 2031 PM V/C Ratio
SWDP 2 2031 PM V/C Ratio
(A44 / A4104 / B4082) Allens Hill / Terrace
Road / Main Street
4 arm staggered Traffic Signal junction
Realign B4082 to create inline crossroads and widen Terrace
road to create to two lane approach allowing signal to run in
fewer stages. Stage two would involve widening on East bound
and W est bound approaches and exits to create to a additional
ahead lane
Northbound
419
519
24%
125%
142%
Eastbound 1162 1468 26% 175% 206%
(A4104 / B4084) W orcester Road / Three
Springs Road
Priority Junction
Convert existing priority junction to a 3 arm signalised junction Eastbound 73 99 36% 26% 27%
Northbound 280 376 34% 144% 164%
(A4104 / B4084) Station Road / W orcester
Road / High Street
3 arm Traffic Signal junction
Minor re-modelling of junction due to land constraints Southbound 494 601 22% 185% 203%
W estbound 305 342 12% 134% 140%
108
A4104 Station Road / B4083 W yre Road
Priority Junction
Convert existing priority junction to signalised 3 arm junction
Northbound 446 514 15% 35% 37%
W estbound 455 471 4% 127% 130%
Southbound 440 540 23% 59% 68%
A44 EveshPM Road Roundabout Creat a bypass lane, shift roundabout north, hPMburger
roundabout and signalise
W estbound
734
918
25%
170%
193%
2031 - Evesham - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Location
Existing Situation
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2031 PM Development
Trip Forecast Flow
SWDP 2 2031 PM Development
Trip Forecast Flow
% Change in Development
Forecast Flow
SWDP 1 2031 PM V/C Ratio
SWDP 2 2031 PM V/C Ratio
(A44 / A4184 / B4088 Evesham Road) 4 arm Roundabout Proposing left turn slips off north bound over a distance of
60m and widen east bound over 70m Northbound 573 752 31% 114% 129%
Eastbound 816 1046 28% 116% 135%
(A44 / A46)
Roundabout
Hamburger from north west bound to north bound or slip road
between northwest and west bound. Signals on 3 arms. Dual
between Junction 60 and 61 – distance of 150m; two lane
existing (Any works would come under the jurisdiction of the
Highways Agency)
Northbound
725
853
18%
160%
171%
Southbound 518 789 52% 127% 150%
(A4184 / B4624) Greenhill / High Street /
W orcester Road 3 arm Traffic Signals Limited junction works due to site constraints
Southbound
660
940
42%
114%
142%
Abbey Road / Pershore Road / W aterside /
Cheltenham Road Traffic Signals
Scheme for this junction included in Secured Major Scheme
Bid
Southbound
660
940
42%
114%
142%
Vine Street / High Street / Bridge Street Priority Junction Limited junction works due to site constraints Southbound 660 940 42% 114% 142%
A46 / A4184 Cheltenham Road
3 arm Roundabout
Extend two lane approaches southbound by 100m and
westbound by 100m. (Any works would come under the
jurisdiction of the Highways Agency)
Southbound
535
679
27%
116%
128%
W estbound 724 878 21% 156% 168%
A46 / The Link / Millennium W ay
4 arm Roundabout
Convert to 4 arm signal junction dual on approach; widen east
approach to two lanes additional 40m required. W iden on exit
of north and south bound by 50m to create merge on exit. (Any
works would come under the jurisdiction of the Highways
Agency)
Eastbound
638
827
30%
136%
152%
W estbound 724 878 21% 156% 168%
A46 / Broadway Road
4 arm Roundabout
Extend 2 lane entry north & south by 100m. W idening on exit
of 50m. (Any works would come under the jurisdiction of the
Highways Agency)
Northbound
638
827
30%
136%
152%
A46 / B4035 Badsey road
4 arm Roundabout
Extend 2 lane entry N & S by 100m and widen on exit of 100m.
(Any works would come under the jurisdiction of the Highways
Agency)
Southbound
553
772
40%
172%
190%
2031 - Great Malvern - Selected Route Analysis - Comparison of SWDP 1 and SWDP 2
Location
Existing Situation
Optimum Scheme Proposed Through SWDP Stage 1
Junction Approach
SWDP 1 2031 PM Development
Trip Forecast Flow
SWDP 2 2031 PM Development
Trip Forecast Flow
% Change in Development
Forecast Flow
SWDP 1 2031 PM V/C Ratio
SWDP 2 2031 PM V/C Ratio
A4103 / B4503 Leigh Sinton Road
Priority Junction
Convert existing priority junction to signalised junction
North East bound 166 263 58% 40% 48%
Northbound 175 521 198% 135% 251%
Southbound 331 576 74% 80% 100%
A449 W orcester Road / Townsend W ay
4 arm Roundabout
W idening on exit from the south east, north west and north
bound arms
Southbound 805 904 12% 150% 158%
North East bound 807 990 23% 127% 142%
Northbound 253 206 -19% 114% 110%
A449 W orcester Road / Howsell Road /
Pickersleigh Road
Priority Junction (staggered)
Realign junction to create 4 arm signal crossroads using land
to the south - This land is park land. Existing road would
become access road to houses but no access to W orcester
Road
Northbound
81
82
1%
75%
75%
North East bound 634 817 29% 136% 154%
Southbound 810 953 18% 148% 163%
B4208 Pickersleigh Road / North End Lane
/ Hayslan Road
Traffic Signals
Extend two lanes west bound back a further 60m to give more
efficient use of green time. Provide right turn facility for
southbound approaching vehicles
Northbound
270
250
-7%
87%
85%
W estbound 194 143 -26% 125% 119%
B4211 Barnards Green Rd / B4208
Pickersleigh Rd / Upper Chase Rd / Court
Rd / Avenue Rd
Gyratory
Covert existing gyratory junction to signalised junction
Eastbound
162
243
50%
195%
222%
Southbound 264 235 -11% 288% 279%
W estbound 574 584 2% 44% 44%
A449 Belle Vue Terrace / W ells Road /
B4211 Church Street
Priority Junction
Change in junction priority and signalised A449
W estbound 219 280 28% 194% 214%
Southbound 712 934 31% 74% 93%
Northbound 134 201 50% 51% 57%
B4208 Barnards Green Rd / Guarlford Road
/ Poolbrook Road
Priority Junction
Convert existing priority junction to signalised junction with
revised northbound approach
Northbound 376 347 -8% 234% 224%
W estbound 90 115 28% 32% 34%
Eastbound 473 466 -1% 61% 60%
B4208 Blackmore Park Rd / B4209 Hanley
Rd
Traffic Signals
Additional lanes approaching junction
Eastbound
22
25
14%
28%
28%
Southbound 373 335 -10% 120% 114%
W estbound 204 187 -8% 86% 83%
Northbound 18 19 6% 25% 25%
109
Appendix E – 2019 Sustainable Travel Demand
110
111
Arrivals
Departures
Total
Two-Way
24 Hr 24 Hr 24 Hour
Worcester - Cluster 1 564 627 1190
Worcester - Cluster 2 151 161 312
Worcester - Cluster 3 101 111 212
Worcester - Cluster 4 125 136 261
Worcester - Cluster 5 722 778 1501
Worcester - Cluster 6 203 240 443
Worcester - Cluster 7 159 175 333
Worcester - Cluster 8 628 678 1306
Worcester - Cluster 9 81 91 171
Worcester - Cluster 10 51 60 111
Worcester - Cluster 11 68 77 145
Worcester - Cluster 12 51 60 111
Malvern - Cluster 1 29 29 59
Malvern - Cluster 2 33 32 65
Malvern - Cluster 3 22 21 43
Malvern - Cluster 4 62 60 122
Malvern - Cluster 5 4 4 8
Malvern - Cluster 6 10 10 20
Malvern - Cluster 7 5 5 10
Malvern - Cluster 8 3 3 5
Malvern - Cluster 9 19 19 38
Malvern - Cluster 10 2 2 4
Malvern - Cluster 11 17 17 34
Malvern - Cluster 12 31 30 61
Malvern - Cluster 13 29 28 57
Malvern - Cluster 14 37 36 73
Malvern - Cluster 15 43 42 84
Malvern - Cluster 16 336 316 652
Malvern - Cluster 17 29 28 57
Malvern - Cluster 18 183 174 358
Wychavon - Cluster 1 56 54 110
Wychavon - Cluster 2 96 91 187
Wychavon - Cluster 3 74 74 148
Wychavon - Cluster 4 244 254 498
Wychavon - Cluster 5 286 274 560
Wychavon - Cluster 6 36 34 69
Wychavon - Cluster 7 14 15 30
Wychavon - Cluster 8 27 25 52
Wychavon - Cluster 9 56 55 111
Wychavon - Cluster 10 147 142 289
Wychavon - Cluster 11 8 8 17
Wychavon - Cluster 12 8 8 15
Wychavon - Cluster 13 9 9 18
Wychavon - Cluster 14 8 8 16
Wychavon - Cluster 15 25 23 48
Wychavon - Cluster 16 44 43 87
Wychavon - Cluster 17 240 235 475
Wychavon - Cluster 18 232 227 459
Wychavon - Cluster 19 42 40 82
Wychavon - Cluster 20 79 76 155
Wychavon - Cluster 21 8 8 17
Wychavon - Cluster 22 15 15 31
Arrivals
Departures
Total
Two-Way
24 Hr 24 Hr 24 Hour
Worcester - Cluster 1 939 1044 1983
Worcester - Cluster 2 252 269 521
Worcester - Cluster 3 168 186 353
Worcester - Cluster 4 208 227 435
Worcester - Cluster 5 1203 1297 2501
Worcester - Cluster 6 338 400 738
Worcester - Cluster 7 264 291 556
Worcester - Cluster 8 1047 1130 2177
Worcester - Cluster 9 135 151 286
Worcester - Cluster 10 85 99 184
Worcester - Cluster 11 113 128 241
Worcester - Cluster 12 85 99 184
Malvern - Cluster 1 26 26 52
Malvern - Cluster 2 29 28 57
Malvern - Cluster 3 19 19 38
Malvern - Cluster 4 54 53 107
Malvern - Cluster 5 3 3 7
Malvern - Cluster 6 9 9 17
Malvern - Cluster 7 4 4 9
Malvern - Cluster 8 2 2 4
Malvern - Cluster 9 17 16 33
Malvern - Cluster 10 2 2 4
Malvern - Cluster 11 15 15 30
Malvern - Cluster 12 41 40 82
Malvern - Cluster 13 38 37 76
Malvern - Cluster 14 49 48 97
Malvern - Cluster 15 57 56 113
Malvern - Cluster 16 448 422 870
Malvern - Cluster 17 39 38 76
Malvern - Cluster 18 245 232 477
Wychavon - Cluster 1 49 48 97
Wychavon - Cluster 2 85 80 165
Wychavon - Cluster 3 98 99 197
Wychavon - Cluster 4 325 339 664
Wychavon - Cluster 5 382 365 747
Wychavon - Cluster 6 47 45 92
Wychavon - Cluster 7 19 20 40
Wychavon - Cluster 8 24 22 46
Wychavon - Cluster 9 112 110 221
Wychavon - Cluster 10 294 285 579
Wychavon - Cluster 11 7 7 15
Wychavon - Cluster 12 7 7 13
Wychavon - Cluster 13 8 8 16
Wychavon - Cluster 14 7 7 14
Wychavon - Cluster 15 22 21 43
Wychavon - Cluster 16 39 38 76
Wychavon - Cluster 17 320 314 634
Wychavon - Cluster 18 310 302 612
Wychavon - Cluster 19 37 35 72
Wychavon - Cluster 20 70 66 136
Wychavon - Cluster 21 7 7 15
Wychavon - Cluster 22 14 13 27
SWDP 1 - 2019
Pedestrian Trips Cycle Trips Bus Trips
Arrivals
Departures
Total
Two-Way
24 Hr 24 Hr 24 Hour
Worcester - Cluster 1 4321 4803 9124
Worcester - Cluster 2 1159 1237 2395
Worcester - Cluster 3 772 854 1626
Worcester - Cluster 4 955 1044 1999
Worcester - Cluster 5 5536 5968 11504
Worcester - Cluster 6 1555 1839 3394
Worcester - Cluster 7 1216 1340 2556
Worcester - Cluster 8 4817 5198 10016
Worcester - Cluster 9 619 695 1314
Worcester - Cluster 10 391 457 848
Worcester - Cluster 11 519 589 1109
Worcester - Cluster 12 391 457 848
Malvern - Cluster 1 136 135 271
Malvern - Cluster 2 152 148 299
Malvern - Cluster 3 101 98 199
Malvern - Cluster 4 286 279 565
Malvern - Cluster 5 18 18 36
Malvern - Cluster 6 45 45 90
Malvern - Cluster 7 23 23 47
Malvern - Cluster 8 12 12 23
Malvern - Cluster 9 88 86 174
Malvern - Cluster 10 9 9 19
Malvern - Cluster 11 80 78 158
Malvern - Cluster 12 267 263 530
Malvern - Cluster 13 249 243 493
Malvern - Cluster 14 318 312 630
Malvern - Cluster 15 369 363 732
Malvern - Cluster 16 2912 2741 5652
Malvern - Cluster 17 252 246 497
Malvern - Cluster 18 1590 1510 3100
Wychavon - Cluster 1 259 251 509
Wychavon - Cluster 2 445 422 867
Wychavon - Cluster 3 638 642 1280
Wychavon - Cluster 4 2116 2202 4318
Wychavon - Cluster 5 2482 2372 4854
Wychavon - Cluster 6 308 293 601
Wychavon - Cluster 7 125 133 258
Wychavon - Cluster 8 124 117 241
Wychavon - Cluster 9 642 630 1272
Wychavon - Cluster 10 1691 1637 3328
Wychavon - Cluster 11 39 39 78
Wychavon - Cluster 12 35 35 70
Wychavon - Cluster 13 41 41 83
Wychavon - Cluster 14 36 36 72
Wychavon - Cluster 15 116 108 224
Wychavon - Cluster 16 204 197 401
Wychavon - Cluster 17 2078 2041 4119
Wychavon - Cluster 18 2014 1965 3979
Wychavon - Cluster 19 193 185 378
Wychavon - Cluster 20 367 350 717
Wychavon - Cluster 21 39 39 78
Wychavon - Cluster 22 71 71 142
112
Arrivals
Departures
Total
Two-Way
Percentage
Change to
SWDP 1
24 Hour 24 Hour 24 Hour (+/-)
Worcester - Cluster 1 652 718 1370 15%
Worcester - Cluster 2 213 226 439 41%
Worcester - Cluster 3 137 149 287 35%
Worcester - Cluster 4 98 108 206 -21%
Worcester - Cluster 5 718 774 1491 -1%
Worcester - Cluster 6 185 221 406 -8%
Worcester - Cluster 7 193 211 404 21%
Worcester - Cluster 8 591 639 1231 -6%
Worcester - Cluster 9 74 83 157 -8%
Worcester - Cluster 10 55 63 118 7%
Worcester - Cluster 11 46 54 99 -31%
Worcester - Cluster 12 247 264 511 362%
Malvern - Cluster 1 63 63 126 114%
Malvern - Cluster 2 26 25 52 -20%
Malvern - Cluster 3 19 19 38 -11%
Malvern - Cluster 4 68 67 135 11%
Malvern - Cluster 5 4 4 8 4%
Malvern - Cluster 6 44 44 88 351%
Malvern - Cluster 7 23 23 46 355%
Malvern - Cluster 8 3 3 7 33%
Malvern - Cluster 9 36 35 71 90%
Malvern - Cluster 10 32 32 64 1492%
Malvern - Cluster 11 25 25 50 47%
Malvern - Cluster 12 52 52 104 71%
Malvern - Cluster 13 14 13 27 -52%
Malvern - Cluster 14 127 126 253 248%
Malvern - Cluster 15 34 33 67 -21%
Malvern - Cluster 16 307 287 594 -9%
Malvern - Cluster 17 221 220 441 669%
Malvern - Cluster 18 179 170 350 -2%
Wychavon - Cluster 1 54 52 106 -4%
Wychavon - Cluster 2 182 177 358 91%
Wychavon - Cluster 3 69 69 139 -6%
Wychavon - Cluster 4 316 330 646 30%
Wychavon - Cluster 5 319 308 628 12%
Wychavon - Cluster 6 94 95 189 173%
Wychavon - Cluster 7 30 32 62 107%
Wychavon - Cluster 8 72 70 142 172%
Wychavon - Cluster 9 68 67 134 21%
Wychavon - Cluster 10 146 142 288 0%
Wychavon - Cluster 11 16 16 32 93%
Wychavon - Cluster 12 26 26 52 244%
Wychavon - Cluster 13 70 70 139 679%
Wychavon - Cluster 14 25 25 49 217%
Wychavon - Cluster 15 52 50 102 110%
Wychavon - Cluster 16 60 59 119 37%
Wychavon - Cluster 17 162 156 317 -33%
Wychavon - Cluster 18 235 229 464 1%
Wychavon - Cluster 19 36 35 71 -13%
Wychavon - Cluster 20 76 72 148 -4%
Wychavon - Cluster 21 0 0 0 0%
Wychavon - Cluster 22 58 58 116 280%
Worcester - Cluster 13 44 46 90 N/A
Worcester - Cluster 14 61 64 125 N/A
Wychavon - Cluster 23 59 60 119 N/A
Wychavon - Cluster 24 0 0 0 N/A
Arrivals
Departures
Total
Two-Way
Percentage
Change to
SWDP 1
24 Hour 24 Hour 24 Hour (+/-)
Worcester - Cluster 1 1086 1197 2283 15%
Worcester - Cluster 2 355 377 732 41%
Worcester - Cluster 3 229 249 478 35%
Worcester - Cluster 4 163 180 343 -21%
Worcester - Cluster 5 1196 1290 2486 -1%
Worcester - Cluster 6 308 368 676 -8%
Worcester - Cluster 7 322 351 673 21%
Worcester - Cluster 8 985 1066 2051 -6%
Worcester - Cluster 9 123 139 262 -8%
Worcester - Cluster 10 91 106 197 7%
Worcester - Cluster 11 76 90 166 -31%
Worcester - Cluster 12 412 440 852 362%
Malvern - Cluster 1 55 55 110 114%
Malvern - Cluster 2 23 22 45 -20%
Malvern - Cluster 3 17 17 34 -11%
Malvern - Cluster 4 60 59 119 11%
Malvern - Cluster 5 4 4 7 4%
Malvern - Cluster 6 39 39 78 351%
Malvern - Cluster 7 20 20 40 355%
Malvern - Cluster 8 3 3 6 33%
Malvern - Cluster 9 32 31 63 90%
Malvern - Cluster 10 28 28 57 1492%
Malvern - Cluster 11 22 22 44 47%
Malvern - Cluster 12 70 69 139 71%
Malvern - Cluster 13 19 18 36 -52%
Malvern - Cluster 14 169 168 337 248%
Malvern - Cluster 15 45 44 89 -21%
Malvern - Cluster 16 409 383 791 -9%
Malvern - Cluster 17 294 294 588 669%
Malvern - Cluster 18 239 227 466 -2%
Wychavon - Cluster 1 47 46 93 -4%
Wychavon - Cluster 2 160 155 315 91%
Wychavon - Cluster 3 92 93 185 -6%
Wychavon - Cluster 4 421 440 861 30%
Wychavon - Cluster 5 426 411 837 12%
Wychavon - Cluster 6 125 127 252 173%
Wychavon - Cluster 7 40 42 82 107%
Wychavon - Cluster 8 63 62 125 172%
Wychavon - Cluster 9 135 133 269 21%
Wychavon - Cluster 10 293 283 576 0%
Wychavon - Cluster 11 14 14 29 93%
Wychavon - Cluster 12 23 23 46 244%
Wychavon - Cluster 13 61 61 122 679%
Wychavon - Cluster 14 22 22 43 217%
Wychavon - Cluster 15 45 44 90 110%
Wychavon - Cluster 16 53 51 104 37%
Wychavon - Cluster 17 216 207 423 -33%
Wychavon - Cluster 18 313 305 618 1%
Wychavon - Cluster 19 32 31 62 -13%
Wychavon - Cluster 20 67 63 130 -4%
Wychavon - Cluster 21 0 0 0 0%
Wychavon - Cluster 22 51 51 102 280%
Worcester - Cluster 13 74 77 151 N/A
Worcester - Cluster 14 102 106 208 N/A
Wychavon - Cluster 23 79 80 159 N/A
Wychavon - Cluster 24 0 0 0 N/A
SWDP 2 - 2019
Pedestrian Trips Cycle Trips Bus Trips
Arrivals
Departures
Total
Two-Way
Percentage
Change to
SWDP 1
24 Hour 24 Hour 24 Hour (+/-)
Worcester - Cluster 1 4995 5506 10501 15%
Worcester - Cluster 2 1635 1733 3368 41%
Worcester - Cluster 3 1051 1145 2197 35%
Worcester - Cluster 4 748 829 1578 -21%
Worcester - Cluster 5 5501 5933 11434 -1%
Worcester - Cluster 6 1416 1694 3110 -8%
Worcester - Cluster 7 1481 1616 3097 21%
Worcester - Cluster 8 4533 4902 9435 -6%
Worcester - Cluster 9 565 639 1204 -8%
Worcester - Cluster 10 419 486 906 7%
Worcester - Cluster 11 349 412 762 -31%
Worcester - Cluster 12 1894 2023 3918 362%
Malvern - Cluster 1 291 290 581 114%
Malvern - Cluster 2 122 117 239 -20%
Malvern - Cluster 3 90 87 177 -11%
Malvern - Cluster 4 316 310 626 11%
Malvern - Cluster 5 19 19 37 4%
Malvern - Cluster 6 204 204 408 351%
Malvern - Cluster 7 107 106 213 355%
Malvern - Cluster 8 16 16 31 33%
Malvern - Cluster 9 166 164 330 90%
Malvern - Cluster 10 149 149 298 1492%
Malvern - Cluster 11 117 115 233 47%
Malvern - Cluster 12 454 450 905 71%
Malvern - Cluster 13 121 115 236 -52%
Malvern - Cluster 14 1099 1094 2193 248%
Malvern - Cluster 15 293 288 581 -21%
Malvern - Cluster 16 2658 2487 5145 -9%
Malvern - Cluster 17 1913 1909 3822 669%
Malvern - Cluster 18 1555 1475 3029 -2%
Wychavon - Cluster 1 248 240 488 -4%
Wychavon - Cluster 2 840 817 1657 91%
Wychavon - Cluster 3 600 602 1202 -6%
Wychavon - Cluster 4 2739 2861 5600 30%
Wychavon - Cluster 5 2767 2672 5439 12%
Wychavon - Cluster 6 814 827 1640 173%
Wychavon - Cluster 7 260 274 534 107%
Wychavon - Cluster 8 332 324 656 172%
Wychavon - Cluster 9 778 767 1545 21%
Wychavon - Cluster 10 1684 1629 3313 0%
Wychavon - Cluster 11 75 75 150 93%
Wychavon - Cluster 12 121 120 241 244%
Wychavon - Cluster 13 322 321 644 679%
Wychavon - Cluster 14 114 113 227 217%
Wychavon - Cluster 15 239 232 471 110%
Wychavon - Cluster 16 278 271 549 37%
Wychavon - Cluster 17 1402 1348 2750 -33%
Wychavon - Cluster 18 2033 1985 4018 1%
Wychavon - Cluster 19 168 160 328 -13%
Wychavon - Cluster 20 352 334 686 -4%
Wychavon - Cluster 21 0 0 0 0%
Wychavon - Cluster 22 270 269 539 280%
Worcester - Cluster 13 340 354 693 N/A
Worcester - Cluster 14 468 487 955 N/A
Wychavon - Cluster 23 510 523 1033 N/A
Wychavon - Cluster 24 0 0 0 N/A
113
Appendix F – 2031 Sustainable Travel Demand
114
115
Arrivals
Departures
Total
Two-Way
24hr 24hr 24 Hour
Worcester - Cluster 1 788 872 1660
Worcester - Cluster 2 160 180 340
Worcester - Cluster 3 172 192 364
Worcester - Cluster 4 289 337 626
Worcester - Cluster 5 1049 1181 2230
Worcester - Cluster 6 414 488 902
Worcester - Cluster 7 271 296 567
Worcester - Cluster 8 1271 1365 2636
Worcester - Cluster 9 189 211 400
Worcester - Cluster 10 118 136 254
Worcester - Cluster 11 127 146 273
Worcester - Cluster 12 134 153 286
Malvern - Cluster 1 32 32 64
Malvern - Cluster 2 77 74 151
Malvern - Cluster 3 8 8 16
Malvern - Cluster 4 128 124 252
Malvern - Cluster 5 4 4 8
Malvern - Cluster 6 10 10 20
Malvern - Cluster 7 12 12 25
Malvern - Cluster 8 3 3 5
Malvern - Cluster 9 58 57 116
Malvern - Cluster 10 7 7 14
Malvern - Cluster 11 42 41 82
Malvern - Cluster 12 11 12 23
Malvern - Cluster 13 116 112 228
Malvern - Cluster 14 72 71 143
Malvern - Cluster 15 74 72 146
Malvern - Cluster 16 441 420 861
Malvern - Cluster 17 57 55 113
Malvern - Cluster 18 219 209 428
Wychavon - Cluster 1 109 103 212
Wychavon - Cluster 2 401 383 784
Wychavon - Cluster 3 147 147 295
Wychavon - Cluster 4 272 280 552
Wychavon - Cluster 5 322 307 629
Wychavon - Cluster 6 154 155 309
Wychavon - Cluster 7 18 19 37
Wychavon - Cluster 8 89 83 172
Wychavon - Cluster 9 136 130 267
Wychavon - Cluster 10 285 275 560
Wychavon - Cluster 11 12 12 24
Wychavon - Cluster 12 189 172 362
Wychavon - Cluster 13 15 15 31
Wychavon - Cluster 14 13 13 27
Wychavon - Cluster 15 100 94 195
Wychavon - Cluster 16 107 104 211
Wychavon - Cluster 17 344 336 680
Wychavon - Cluster 18 344 334 678
Wychavon - Cluster 19 100 94 195
Wychavon - Cluster 20 223 210 432
Wychavon - Cluster 21 0 0 0
Wychavon - Cluster 22 15 15 31
Arrivals
Departures
Total
Two-Way
24hr 24hr 24 Hour
Worcester - Cluster 1 1313 1454 2766
Worcester - Cluster 2 267 300 567
Worcester - Cluster 3 286 320 606
Worcester - Cluster 4 481 562 1043
Worcester - Cluster 5 1749 1968 3717
Worcester - Cluster 6 689 814 1503
Worcester - Cluster 7 451 493 945
Worcester - Cluster 8 2118 2276 4394
Worcester - Cluster 9 315 351 666
Worcester - Cluster 10 196 227 423
Worcester - Cluster 11 212 243 455
Worcester - Cluster 12 223 254 477
Malvern - Cluster 1 28 28 57
Malvern - Cluster 2 68 65 133
Malvern - Cluster 3 7 7 14
Malvern - Cluster 4 113 109 221
Malvern - Cluster 5 3 3 7
Malvern - Cluster 6 9 9 17
Malvern - Cluster 7 11 11 22
Malvern - Cluster 8 2 2 4
Malvern - Cluster 9 51 50 102
Malvern - Cluster 10 6 6 13
Malvern - Cluster 11 37 36 73
Malvern - Cluster 12 15 15 31
Malvern - Cluster 13 154 149 303
Malvern - Cluster 14 97 94 191
Malvern - Cluster 15 98 96 194
Malvern - Cluster 16 588 560 1148
Malvern - Cluster 17 76 74 150
Malvern - Cluster 18 292 279 571
Wychavon - Cluster 1 96 91 186
Wychavon - Cluster 2 353 337 689
Wychavon - Cluster 3 196 197 393
Wychavon - Cluster 4 363 373 736
Wychavon - Cluster 5 429 409 838
Wychavon - Cluster 6 205 206 412
Wychavon - Cluster 7 24 25 49
Wychavon - Cluster 8 78 73 151
Wychavon - Cluster 9 273 261 533
Wychavon - Cluster 10 570 550 1120
Wychavon - Cluster 11 11 11 21
Wychavon - Cluster 12 166 152 318
Wychavon - Cluster 13 14 13 27
Wychavon - Cluster 14 12 12 23
Wychavon - Cluster 15 88 83 171
Wychavon - Cluster 16 94 91 185
Wychavon - Cluster 17 459 448 907
Wychavon - Cluster 18 458 446 904
Wychavon - Cluster 19 88 83 171
Wychavon - Cluster 20 196 184 380
Wychavon - Cluster 21 0 0 0
Wychavon - Cluster 22 14 13 27
SWDP 1 - 2031
Pedestrian Trips Cycle Trips Bus Trips
Arrivals
Departures
Total
Two-Way
24hr 24hr 24 Hour
Worcester - Cluster 1 6038 6687 12725
Worcester - Cluster 2 1227 1381 2608
Worcester - Cluster 3 1315 1473 2788
Worcester - Cluster 4 2214 2584 4798
Worcester - Cluster 5 8046 9053 17099
Worcester - Cluster 6 3170 3743 6913
Worcester - Cluster 7 2076 2270 4346
Worcester - Cluster 8 9743 10469 20212
Worcester - Cluster 9 1451 1614 3065
Worcester - Cluster 10 902 1043 1945
Worcester - Cluster 11 976 1118 2094
Worcester - Cluster 12 1024 1170 2194
Malvern - Cluster 1 149 149 298
Malvern - Cluster 2 356 343 699
Malvern - Cluster 3 36 36 72
Malvern - Cluster 4 592 573 1165
Malvern - Cluster 5 18 18 36
Malvern - Cluster 6 45 45 90
Malvern - Cluster 7 57 57 114
Malvern - Cluster 8 12 12 23
Malvern - Cluster 9 271 264 534
Malvern - Cluster 10 34 33 67
Malvern - Cluster 11 194 188 382
Malvern - Cluster 12 100 100 199
Malvern - Cluster 13 1004 968 1972
Malvern - Cluster 14 628 613 1241
Malvern - Cluster 15 639 624 1263
Malvern - Cluster 16 3819 3640 7459
Malvern - Cluster 17 495 480 976
Malvern - Cluster 18 1900 1811 3712
Wychavon - Cluster 1 504 477 980
Wychavon - Cluster 2 1855 1771 3626
Wychavon - Cluster 3 1274 1278 2553
Wychavon - Cluster 4 2359 2424 4783
Wychavon - Cluster 5 2788 2659 5448
Wychavon - Cluster 6 1334 1341 2675
Wychavon - Cluster 7 155 164 319
Wychavon - Cluster 8 410 383 793
Wychavon - Cluster 9 1568 1498 3067
Wychavon - Cluster 10 3278 3164 6442
Wychavon - Cluster 11 56 56 112
Wychavon - Cluster 12 875 797 1673
Wychavon - Cluster 13 71 71 142
Wychavon - Cluster 14 62 61 123
Wychavon - Cluster 15 464 437 901
Wychavon - Cluster 16 494 480 974
Wychavon - Cluster 17 2983 2913 5896
Wychavon - Cluster 18 2977 2897 5874
Wychavon - Cluster 19 464 437 901
Wychavon - Cluster 20 1031 970 2000
Wychavon - Cluster 21 0 0 0
Wychavon - Cluster 22 71 71 142
116
Arrivals
Departures
Total
Two-Way
Percentage
Change to
SWDP 1
24 Hour 24 Hour 24 Hour (+/-)
Worcester - Cluster 1 1111 1210 2321 40%
Worcester - Cluster 2 215 238 452 33%
Worcester - Cluster 3 200 222 422 16%
Worcester - Cluster 4 257 305 562 -10%
Worcester - Cluster 5 1044 1176 2220 0%
Worcester - Cluster 6 381 455 836 -7%
Worcester - Cluster 7 309 337 646 14%
Worcester - Cluster 8 1291 1387 2679 2%
Worcester - Cluster 9 234 258 493 23%
Worcester - Cluster 10 135 154 289 14%
Worcester - Cluster 11 94 111 205 -25%
Worcester - Cluster 12 315 342 657 130%
Malvern - Cluster 1 75 75 151 134%
Malvern - Cluster 2 48 45 92 -39%
Malvern - Cluster 3 18 18 36 129%
Malvern - Cluster 4 114 110 224 -11%
Malvern - Cluster 5 4 4 8 4%
Malvern - Cluster 6 62 62 124 532%
Malvern - Cluster 7 25 25 50 103%
Malvern - Cluster 8 3 3 7 33%
Malvern - Cluster 9 69 67 136 18%
Malvern - Cluster 10 52 52 105 623%
Malvern - Cluster 11 35 33 68 -17%
Malvern - Cluster 12 58 58 116 404%
Malvern - Cluster 13 100 96 196 -14%
Malvern - Cluster 14 162 161 323 126%
Malvern - Cluster 15 45 43 88 -40%
Malvern - Cluster 16 474 453 926 8%
Malvern - Cluster 17 277 275 552 390%
Malvern - Cluster 18 203 193 396 -8%
Wychavon - Cluster 1 110 104 215 1%
Wychavon - Cluster 2 529 510 1039 33%
Wychavon - Cluster 3 136 136 272 -8%
Wychavon - Cluster 4 446 464 910 65%
Wychavon - Cluster 5 358 346 704 12%
Wychavon - Cluster 6 151 152 303 -2%
Wychavon - Cluster 7 42 44 86 135%
Wychavon - Cluster 8 132 126 259 51%
Wychavon - Cluster 9 152 146 298 12%
Wychavon - Cluster 10 284 275 559 0%
Wychavon - Cluster 11 36 35 71 193%
Wychavon - Cluster 12 214 197 412 14%
Wychavon - Cluster 13 128 128 257 736%
Wychavon - Cluster 14 29 29 58 118%
Wychavon - Cluster 15 106 100 206 6%
Wychavon - Cluster 16 110 107 216 3%
Wychavon - Cluster 17 306 297 602 -11%
Wychavon - Cluster 18 315 306 621 -8%
Wychavon - Cluster 19 83 77 160 -18%
Wychavon - Cluster 20 191 178 370 -15%
Wychavon - Cluster 21 0 0 0 0%
Wychavon - Cluster 22 91 91 182 493%
Worcester - Cluster 13 63 66 129 N/A
Worcester - Cluster 14 96 100 196 N/A
Wychavon - Cluster 23 177 181 358 N/A
Wychavon - Cluster 24 11 11 22 N/A
Arrivals
Departures
Total
Two-Way
Percentage
Change to
SWDP 1
24 Hour 24 Hour 24 Hour (+/-)
Worcester - Cluster 1 1852 2016 3868 40%
Worcester - Cluster 2 358 396 754 33%
Worcester - Cluster 3 333 370 703 16%
Worcester - Cluster 4 429 508 937 -10%
Worcester - Cluster 5 1740 1960 3700 0%
Worcester - Cluster 6 635 758 1393 -7%
Worcester - Cluster 7 516 561 1077 14%
Worcester - Cluster 8 2152 2312 4464 2%
Worcester - Cluster 9 391 430 821 23%
Worcester - Cluster 10 225 257 482 14%
Worcester - Cluster 11 156 186 342 -25%
Worcester - Cluster 12 525 570 1096 130%
Malvern - Cluster 1 66 66 132 134%
Malvern - Cluster 2 42 39 81 -39%
Malvern - Cluster 3 16 16 31 129%
Malvern - Cluster 4 100 97 197 -11%
Malvern - Cluster 5 4 4 7 4%
Malvern - Cluster 6 54 54 109 532%
Malvern - Cluster 7 22 22 44 103%
Malvern - Cluster 8 3 3 6 33%
Malvern - Cluster 9 60 59 119 18%
Malvern - Cluster 10 46 46 92 623%
Malvern - Cluster 11 31 29 60 -17%
Malvern - Cluster 12 77 77 155 404%
Malvern - Cluster 13 134 128 262 -14%
Malvern - Cluster 14 217 214 431 126%
Malvern - Cluster 15 60 57 117 -40%
Malvern - Cluster 16 631 604 1235 8%
Malvern - Cluster 17 369 367 735 390%
Malvern - Cluster 18 271 257 528 -8%
Wychavon - Cluster 1 97 92 189 1%
Wychavon - Cluster 2 465 449 914 33%
Wychavon - Cluster 3 181 181 362 -8%
Wychavon - Cluster 4 595 619 1214 65%
Wychavon - Cluster 5 478 461 939 12%
Wychavon - Cluster 6 202 203 404 -2%
Wychavon - Cluster 7 56 59 115 135%
Wychavon - Cluster 8 116 111 227 51%
Wychavon - Cluster 9 304 292 596 12%
Wychavon - Cluster 10 569 549 1118 0%
Wychavon - Cluster 11 31 31 62 193%
Wychavon - Cluster 12 189 174 362 14%
Wychavon - Cluster 13 113 113 226 736%
Wychavon - Cluster 14 26 26 51 118%
Wychavon - Cluster 15 93 88 181 6%
Wychavon - Cluster 16 96 94 190 3%
Wychavon - Cluster 17 407 395 803 -11%
Wychavon - Cluster 18 421 407 828 -8%
Wychavon - Cluster 19 73 68 141 -18%
Wychavon - Cluster 20 168 157 325 -15%
Wychavon - Cluster 21 0 0 0 0%
Wychavon - Cluster 22 80 80 160 493%
Worcester - Cluster 13 105 110 215 N/A
Worcester - Cluster 14 160 167 327 N/A
Wychavon - Cluster 23 236 241 477 N/A
Wychavon - Cluster 24 10 10 20 N/A
SWDP 2 - 2031
Pedestrian Trips Cycle Trips Bus Trips
Arrivals
Departures
Total
Two-Way
Percentage
Change to
SWDP 1
24 Hour 24 Hour 24 Hour (+/-)
Worcester - Cluster 1 8518 9275 17793 40%
Worcester - Cluster 2 1645 1821 3466 33%
Worcester - Cluster 3 1531 1702 3233 16%
Worcester - Cluster 4 1973 2337 4309 -10%
Worcester - Cluster 5 8004 9014 17018 0%
Worcester - Cluster 6 2920 3486 6406 -7%
Worcester - Cluster 7 2371 2581 4952 14%
Worcester - Cluster 8 9899 10636 20535 2%
Worcester - Cluster 9 1798 1980 3777 23%
Worcester - Cluster 10 1033 1183 2215 14%
Worcester - Cluster 11 719 855 1574 -25%
Worcester - Cluster 12 2417 2624 5041 130%
Malvern - Cluster 1 349 348 696 134%
Malvern - Cluster 2 220 208 427 -39%
Malvern - Cluster 3 82 82 164 129%
Malvern - Cluster 4 527 508 1035 -11%
Malvern - Cluster 5 19 19 37 4%
Malvern - Cluster 6 286 286 572 532%
Malvern - Cluster 7 116 115 231 103%
Malvern - Cluster 8 16 16 31 33%
Malvern - Cluster 9 317 311 628 18%
Malvern - Cluster 10 243 242 485 623%
Malvern - Cluster 11 161 155 316 -17%
Malvern - Cluster 12 502 503 1005 404%
Malvern - Cluster 13 869 833 1703 -14%
Malvern - Cluster 14 1407 1394 2801 126%
Malvern - Cluster 15 387 372 760 -40%
Malvern - Cluster 16 4104 3926 8030 8%
Malvern - Cluster 17 2396 2384 4781 390%
Malvern - Cluster 18 1759 1670 3429 -8%
Wychavon - Cluster 1 510 483 994 1%
Wychavon - Cluster 2 2447 2361 4807 33%
Wychavon - Cluster 3 1178 1177 2355 -8%
Wychavon - Cluster 4 3869 4021 7890 65%
Wychavon - Cluster 5 3107 2997 6104 12%
Wychavon - Cluster 6 1311 1318 2629 -2%
Wychavon - Cluster 7 364 385 749 135%
Wychavon - Cluster 8 612 584 1196 51%
Wychavon - Cluster 9 1748 1678 3426 12%
Wychavon - Cluster 10 3270 3157 6427 0%
Wychavon - Cluster 11 165 164 329 193%
Wychavon - Cluster 12 992 913 1905 14%
Wychavon - Cluster 13 594 592 1187 736%
Wychavon - Cluster 14 135 134 269 118%
Wychavon - Cluster 15 490 463 952 6%
Wychavon - Cluster 16 507 493 1000 3%
Wychavon - Cluster 17 2649 2571 5219 -11%
Wychavon - Cluster 18 2734 2648 5382 -8%
Wychavon - Cluster 19 384 357 741 -18%
Wychavon - Cluster 20 885 825 1709 -15%
Wychavon - Cluster 21 0 0 0 0%
Wychavon - Cluster 22 421 420 841 493%
Worcester - Cluster 13 484 504 988 N/A
Worcester - Cluster 14 737 768 1504 N/A
Wychavon - Cluster 23 1531 1569 3100 N/A
Wychavon - Cluster 24 52 51 103 N/A
117
Appendix G – Vehicle / Trip Generation Development Site
Clusters
118
119
Malvern Hills North
Development Sites
by Cluster
Malvern Hills South
Development Sites
by Cluster
120
Worcester Development
Sites by Cluster
121