Upload
barry-wilcox
View
222
Download
0
Tags:
Embed Size (px)
Citation preview
Transport & SustainabilityUpdate
April 2008
Paul Horan
Transport• Public transport
– Progress
• Cycling - 17% increase since 5 axel ban!
• Car parking – Limited: DTO ->DCC ->An Bord Pleanala– All basement - €20,00-25,000/space
• On-site student accommodation– 2x2000 journeys/day reduction!
Zone 1/city centre parking standards
DCC Dev PlanTransport
Well connected
Transport 21:‘The two Luas lines to be joined. .. Cross-
city link .. extended to serve Broadstone and the new Dublin Institute of Technology Campus at Grangegorman… connect with the Maynooth rail line… Liffey Junction’
Heuston
Connolly
DIT Grangegorman
LUAS A
QBC
Metro N
LUAS B
Metro NDrumcondra
Mater
Parnell Sq
500m
500m
1km1km
Metro North• Delivery of Metro North
– Railway Order application Metro North Autumn 2008 - via Strategic Infrastructure mechanism
– Enabling works start Winter 2009– Main PPP contract start 2010– Completion 2014
• Metro North stop at Parnell Square – Bus lane along Western Way currently used for
buses between Broadstone and Parnell Square
• Metro N stop Mater Hospital
Luas to Broadstone• Minister Dempsey has written to the transport bodies and
confirmed the Luas line to Broadstone
• BX route chosen: up O’Connell, down Marlborough– (stop at Cathal Brugh St)
• RPA now plan to combine Line BX (city centre) and Line D (Broadstone) into one project
• Can expect public consultation on Line D in Summer 2008 - Preferred route by Autumn 2008
• Publication of Luas Railway Order Autumn/Winter 2009 - Via Strategic Infrastructure mechanism
• RPA is also considering ways of streamlining and combining works on the cross-city Luas Line and the construction of Metro North in order to minimise disruption to the City Centre
Navan Line
• An Bord Pleanala approved the railway order for the first phase of the Navan line last week. This involves 7.5km of line between Clonsilla and Pace and the provision of a park-and-ride at Pace. Work will get underway as soon as the Order becomes enforceable.
Bus Network
• On-going consultation with Dublin Bus
• Plan for on-site 6 bay bus terminus accessed from Constitution Hill
• Lay-bys on Prussia St and NCR
SustainabilityThe basics• Southerly orientated courtyards• Narrow plan buildings <16m
– Natural lighting– Natural ventilation
• Good passive design• Water use reduction/mangement & reuse
• +5% of capital costs being allowed for sustainable features across all buildings
Projected Energy Demand
Heating 55% Hot water 10% Electricity 35%
Lighting ICT and other equipment
Central/District Heating
• Single large central heating plant v distributed local heating in individual buildings
• High capital costs – unit +distribution network• Possibly CHP (Combined Heat & Power)
– Generate electricity - at least emergency supply
• Simple solution – gas fired• Long term renewable – biomass/woodchip fired• Potential long term savings
– Single efficient boiler– Reduced operation and maintenance– ~10 year payback
• Savings accrue to recurrent budget• Potential to outsource – ESCO (Energy Supply Company)
atrium
SUSTAINABILITY CONCEPTS
A long term approach –> carbon neutral
• Reduce demand – Good passive design– Energy efficient lighting & appliances, thin
client technology,.…• Renewable sources
– On-site renewables• Biomass – heat, electricity• Miscellaneous small solar water, PV,….
– Purchase renewable power
ESB Strategic Framework
• €22 bn investment programme• Halving of carbon emissions within 12 years, • €4bn directly in renewable energy projects • €6.5bn will be spent facilitating renewables
including smart metering and smart networks.• By 2020, 1/3 from renewable generation.
– 1,400 megawatts of wind generation– Wave, tidal and biomass.
• Carbon net-zero by 2035.
CONCERTO
• CONCERTO is a major EU programme supporting sustainable developments
• €25,000 grant from Enterprise Ireland to develop application.
• Potential €4M to project
• Highly competitive, but initial reaction from commission officials positive
• Aidan Duffy, engineering + …
Up-front capital cost
v
Long term recurrent savings
Have we got a choice?
but