Site Reference Client Name 

Traffic Management Plan (part of Construction Method Statement)

Houghton Main TRRC

Peel Environmental Ltd

CRM.066.006.PL.R.002.

Octavia House Schools  

Contact Details: 

Enzygo Ltd. Samuel House 5 Fox Valley Stocksbridge Sheffield S36 2AA 

tel: 0114 3215151 email: [email protected] 

www: enzygo.com 

Traffic Management Plan (part of Construction Method Statement) at 

Houghton Main TRRC, Great Houghton 

Project:  Traffic Management Plan (part of Construction Method Statement) at Houghton 

Main TRRC, Great Houghton 

For:  Peel Environmental Ltd 

Status:  Final  

Date:  March 2018  

Author:  Sarah Strauther – Senior Transport Planner 

Reviewer:  Barry Roberts BSc (Hons) IEng MICE MIHT – Director of Traffic & Transportation 

Approver:  Barry Roberts BSc (Hons) IEng MICE MIHT – Director of Traffic & Transportation 

Disclaimer: 

This report has been produced by Enzygo Limited within the terms of the contract with the client and taking account of the resources devoted to it by agreement with the client. 

We disclaim any responsibility to the client and others in respect of any matters outside the scope of the above. 

This report is confidential to the client and we accept no responsibility of whatsoever nature to third parties to whom this report, or any part thereof, is made known.  Any such party relies on the report at their own risk. 

Enzygo Limited Registered in England No. 6525159 Registered Office Stag House Chipping Wotton‐Under‐Edge Gloucestershire GL12 7AD

SHF.1268.001.R.TR.001 i March 2016 

Contents 

Contents ........................................................................................................................................ i 1.0  Introduction ........................................................................................................................ 1 

1.1  Background ....................................................................................................................... 1 

2.0  Overview of Construction Activity ....................................................................................... 2 2.1  General .............................................................................................................................. 2 

2.2  Site Clearance .................................................................................................................... 2 

2.3  Remediation Works .......................................................................................................... 3 

2.4  Highway Access ................................................................................................................. 3 

2.5  Preparation Works ............................................................................................................ 4 

2.5  Construction Works .......................................................................................................... 4 

2.6  Soft Landscaping ............................................................................................................... 6 

2.7  Construction Programme .................................................................................................. 6 

3.0  Specific Measures................................................................................................................ 7 3.1  General .............................................................................................................................. 7 

3.2  Health and Safety Requirements ...................................................................................... 7 

3.3  Site Security and Fencing .................................................................................................. 8 

3.4  Site Logistics ...................................................................................................................... 9 

3.5  Traffic Management ........................................................................................................ 10 

4.0  Construction Traffic and Deliveries .................................................................................... 12 4.1  Construction Period and Contractor Liaison ................................................................... 12 

4.2  Vehicle Types and frequencies ....................................................................................... 13 

4.3  Abnormal Loads .............................................................................................................. 13 

4.4  Heavy Goods Vehicles (HGVs) ......................................................................................... 13 

4.5  Light Goods Vehicles ....................................................................................................... 14 

4.6  Loading/Unloading and Parking ...................................................................................... 14 

4.7  Parking ............................................................................................................................ 16 

4.8  Route to and from Site .................................................................................................... 16 

5.0  Pedestrian and Vehicle Controls ........................................................................................ 18 5.1  Pedestrian Measures ...................................................................................................... 18 

5.2  Vehicle Controls .............................................................................................................. 18 

6.0  Signage and Lighting .......................................................................................................... 19 6.1  Signage and Lighting ....................................................................................................... 19 

 

Houghton Main TRRC TMP          March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

 

1.0 Introduction 

1.1 Background 

1.1.1 Enzygo has been  instructed by Peel Environmental  Ltd  to prepare a Construction Method 

Statement,  that  includes  issues  that  relating  to Traffic Management,  to discharge Planning 

Condition 9 as part of the existing planning consent (2015/0137).   This Traffic Management 

Plan should be read in conjunction with the Construction Method Statement.  

1.1.2 In terms of the Traffic Management requirements that Barnsley Metropolitan Borough Council 

(BMBC)  has  requested  these  are  outlined  in  the  BMBC  document  reference 

HDC/DC/2017/1726. 

1.1.3 Following  our  discussing  with  Peel  Environmental  Ltd  and  using  Enzygo’s  experience  of 

Renewable Energy Park developments  this document will aim  to address  the above  issues 

raised by BMBC; 

1.1.4 Enzygo’s  traffic  and  transportation  team  will  introduce  similar  traffic  management 

procedures, methods of management, communication techniques and monitoring methods 

experienced on similar renewable energy sites that we have worked on; 

1.1.5 Currently  the  Principal  Contractor  is  yet  to  be  appointed  and  additional  information  and 

refinement to this plan is expected from the Contractor.  Any amendments will be provided to 

the  Local  Planning Authority  for  approval  prior  to  commencement  of  construction  of  the 

facility. 

1.1.6 In accordance with good practice this statement is being prepared at an early stage in the site 

development to allow it to be used to influence the detailed design and construction process. 

1.1.7 This Traffic Management Plan should be read  in conjunction with the Construction Method 

Statement. 

 

 

 

 

 

 

Houghton Main TRRC TMP          March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

 

2.0 Overview of Construction Activity 

2.1 General 

2.1.1 The site currently comprises overgrown derelict land with shrub bushes and rough grassland. 

Access  is from Houghton Main Colliery Roundabout to the south east of the site. An access 

spur is present on Houghton Main Colliery Roundabout, which will provide future access onto 

the site for construction traffic and subsequently for future site users. 

2.1.2 Proposed development works will involve the following: 

1 Clearance of existing vegetation, including trees and bushes; 

2 Construction of internal road system 

3 Reduced level excavation to sub‐formation level; 

4 Placement of piling mat; 

5 Substructure works to the buildings and plant; 

6 Construction of site drainage and services; 

7 Construction of the structures 

8 Construction of pavement and hardstanding areas; 

9 Landscaping; 

2.1.3 The proposed development  is shown on Drawing CRM.066.006.GE.D.001 a copy of which  is 

included in the Drawing Section of this document.   

2.1.4 More specific information is given for the three main stages of work are outlined below: 

  

2.2 Site Clearance 

2.2.1 Prior to any site clearance works being undertaken fencing it to be erected around retained 

trees to protect them in accordance with Planning Condition 7.  The fencing will be undertaken 

in accordance with approved plans. 

2.2.2 Prior  to  commencement  of  works  a  condition  survey  of  the  highways  to  be  used  by 

construction traffic will be undertaken in Accordance with Planning Condition 10. 

2.2.3 Site clearance will involve the felling of trees, which are not to be retained and grubbing out 

of shrubs and root balls. 

2.2.4 Areas of low vegetation such as grass and scrub will be subject to a soft strip using an excavator 

or dozer. 

2.2.5 Soils containing roots will be stockpiled on site awaiting suitable disposal off site. 

 

Houghton Main TRRC TMP          March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

 

2.2.6 Vegetation and timber will be temporarily stored on site awaiting removal for appropriate re‐

use or disposal. 

2.2.7 No demolition of structures is proposed. 

2.3 Remediation Works 

2.3.1 Ground investigations and risk assessments have been undertaken by Enzygo Ltd (Reference 

CRM.066.005.GE.R.001.A) in accordance with the requirements of Planning Conditions. 

2.3.2 The ground investigation identified no evidence of significant contamination on the site, with 

no specific requirements for remediation. 

2.3.3 A discovery strategy is included within the Contamination Assessment Report.   If unforeseen 

contamination is encountered during construction works such as localised spillage outside the 

areas  investigated  an  Environmental  consultant  will  be  available  on  a  ‘call  out’  basis  to 

undertake an assessment of risk.  If ‘unforeseen contamination’ is encountered the discovery 

strategy will be to remove the source as it is likely to be very limited in extent and the Local 

Planning Authority advised 

2.3.4 It is proposed that should contaminated soils be encountered requiring remediation that these 

are discarded directly off site to avoid the potential risk of cross contamination.  Where this is 

not feasible soils will be stockpiled on areas of hardstanding or on suitable membrane awaiting 

disposal. 

2.3.5 It is anticipated that this operation will require the use of a single tracked excavator and road 

vehicles  for  disposal.    The  excavation  of  contaminated  soils  will  be  monitored  by  an 

environmental consultant to minimise the volume of waste generated. 

2.3.6 Should  remediation  of  unforeseen  contamination  be  required  a  validation  report will  be 

prepared  in  accordance  appropriate  guidance  and  in  liaison with  regulators  and with  the 

requirements of the Planning Conditions. 

2.4 Highway  Access 

2.4.1 A highway access is to be constructed on to the site from the existing spur off the Houghton 

Main Colliery Roundabout  in a north westerly direction.   The civil engineering access works 

comprise an extension  to  the existing  roundabout  spur  that  includes  the provision of new 

Houghton Main TRRC TMP    March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

pavement construction up to the extent of the ASOS car park access and the access to the 

west.  It also extends south to the threshold point of the compound. 

2.4.2 The access works includes additional footpath construction, on both sides, along with kerbing 

proposals, new linear drainage, an uncontrolled crossing point, new speed limit signs on the 

approach and new thermoplastic lining.  The proposed access works have been submitted to 

BMBC to address conditions 5 and 7 referenced in HDC/DC/2017/1726. 

2.5 Preparation Works 

2.5.1  The site preparation works will comprise: 

Bulk excavation down to sub‐formation level across the site.  This will be designed and

implemented in accordance with regulatory requirements. of Planning Condition 3.

Existing redundant service runs and old  foundations will be excavated  in accordance

with Series 200 of the Specification for Highway Works.  Where possible underground

obstructions will be crushed and processed on site for re‐use.

Resultant voids will be backfilled with suitable granular fill, placed and compacted  in

accordance with Series 600 of the Specification for Highway Works.

The reduced  level excavation will be raised to formation level using selected granular

materials.  Where possible secondary aggregate will be used, including processed site

won arisings.  The selected granular fill will comprise a piling mat below the proposed

building footprint and within the working area.  Areas of proposed hard standing outside

of  the working  area will be made up using  capping material.    This will  then  form  a

running layer for plant and equipment.

2.5 Construction Works 

2.5.1 Sub structure works to the proposed buildings will comprise the following: 

Piling;

Construction of pile caps; and,

Construction of the ground floor slabs.

Houghton Main TRRC TMP    March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

2.5.2 Based on the findings of the ground investigation it is proposed that piled foundations are to 

be used.  Details of the piling works will be determined by the specialist contractor. The piling 

works will  require  the  use  of  piling  rigs with  support  crane  and  ancillary  plant,  including 

excavators and dumpers. 

2.5.3 Piles will be advanced from the top of the piling mat to the embedment depth.  When seated, 

the soils around the piles will be excavated to allow construction of the pile caps.  The concrete 

at  the  top  of  the  pile will  be  broken  out  to  reveal  the  reinforcement.  This will  then  be 

connected in to the reinforcement cage of the pile cap, temporary formwork installed and the 

concrete cast. 

2.5.4 Once the piles and pile caps are in place the floor slab will be constructed. 

2.5.5 Infrastructure  comprising  surface  and  foul water,  gas  and  electricity will  be  installed  and 

connected to service entry points within the ground floor slab.  

2.5.6 Appropriate attenuation will be constructed to the surface water drainage system to meet the 

requirements of Conditions 3 and 12. 

2.5.7 Foul  drainage  shall  be  designed  and  constructed  in  accordance with  the  requirements  of 

Planning Condition 12. 

2.5.8 Areas of hardstanding will be constructed up to road base, together with temporary setting of 

manholes. 

2.5.9 The structures will be erected. The buildings are to comprise steel portal frame structures, 

which will be erected using a crane.  The crane will also be used place the roof, internal floors, 

staircases, ‘stack’ and hoist equipment to height, for placement within the buildings. 

2.5.10 Cladding to the structures will also be placed using a mobile crane. 

2.5.11 Following completion of the main structures, the wearing course can then be constructed on 

areas of hardstanding. The screed (power‐floated) will then be constructed to complete the 

ground floor slabs. 

 

Houghton Main TRRC TMP          March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

 

2.6 Soft Landscaping 

2.6.1 Areas of proposed  landscaping will be constructed  in accordance with  landscape plan and 

management plan required under Planning Condition 15.  

2.6.2 Landscape works will be undertaken following the main construction phases. 

 

2.7 Construction Programme 

2.7.1 A Construction Programme will be prepared by  the Principal Contractor,  taking account of 

their method and  schedules of working.     The  construction programme will  incorporate a 

critical path which  can  accommodate  incorporated design,  co‐ordinated  trade  contractors 

design  and  design  reviews,  procurement,  equipment/materials  orders,  deliveries  and  site 

installation period as necessary. 

2.7.2 The construction programme will be monitored, tracked and updated on a regular basis and 

any corrective action applied as necessary. 

2.7.3 The construction programme will be used to identify times and periods of works, which may 

have  adverse  impact  on  neighbours.  Typically,  this  may  include  periods  of  more  noisy 

operations, such as piling.  By identifying these periods, the impact on neighbours can be more 

easily managed. 

 

 

 

 

Houghton Main TRRC TMP          March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

 

3.0 Specific Measures 

3.1 General 

3.1.1 This section provides details of the measures proposed to address the specific items. 

3.1.2 As  part  of  the  site management  process  it  is  proposed  that  the  Principal  Contractor,  in 

conjunction with the Client, will liaise on a regular basis with ASOS and its operator Expo, and 

the local residents/businesses regarding the progress of the construction works. In particular, 

it is proposed that the Construction Programme is used to identify critical stages of the works 

which, could cause potential nuisance to neighbours.  These typically include: 

 

1 Noisy operations such as piling; 

2 Periods of increased traffic such as major deliveries; 

3 Periods where  there  is a  greater  risk of mud on  the  roads, as  a  result of earthworks 

excavation. 

4 On  the  basis  of  the  terms  agreed  in  the  sale  contracts  by  both  Peel  and  ASOS,  the 

construction of the access road will be undertake by ASOS in order to ensure there is no 

disruption to the Fulfilment Centre arising during the peak months of business (November 

to January). 

 

3.1.3 The method of stakeholder engagement is yet to be finalised, though is likely to include: letter‐

drops to neighbours and a pre‐start meeting with local stakeholders. 

3.1.4 Contact details for the Site Agent will be included on the site hoarding, should members of the 

public need  to  raise concerns of complain over activities being undertaken.   Details of  the 

client and Resident Engineer will also be included. Any complaints received will be relayed to 

the  Local  Planning  authority,  together  with  any  investigation  undertaken  and mitigation 

measures proposed or implemented. 

3.2 Health and Safety Requirements 

3.2.1  Prior to the commencement of the works a Designers Risk Assessment and Pre‐Tender Health 

and  Safety  Plan will  be  prepared  outlining  the Health  and  Safety  issues  by  the  CDM  Co‐

ordinator (CDMc). 

Houghton Main TRRC TMP    March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

3.2.2 The  appointed Contractor  for  the works will be  required  to provide  a Construction  Stage 

Health and Safety Plan and comprehensive supporting Method Statement for the works. 

3.2.3 As a general measure all working areas at the site will require fencing and appropriate signs 

to prevent access by unauthorised persons during the progression of deeper excavations or 

demolition works. 

3.2.4 All personnel will be inducted prior to gaining access to the site by the Principal Contractor.  

They will be informed of the specific site rules which apply.  In addition, all site staff operating 

without supervision by the Principal Contractor and all plant operators will be required to hold 

valid and appropriate CSCS cards. 

3.2.5 All trade contractors are obliged to provide safety policies, plans and method statements and 

will be interviewed, where appropriate, prior to placement of orders, on relevant aspects of 

health and safety.   

3.2.6 A ‘tool box talk’ will be provided to the Contractors and site staff by the Principal Contractor. 

3.2.7 Banksmen and Traffic Marshalls will be used where appropriate. 

3.3 Site Security and Fencing  

3.3.1 Due  to  the nature of  the  construction works  it  is proposed  that plywood hoarding will be 

constructed around the site boundary.  This will reduce potential risks associated with material 

migrating out of the site and reduce noise impact. 

3.3.2 The  existing  site  access  off  Houghton  Main  Colliery  Roundabout  will  be  retained  for 

construction traffic. Access and egress routes are shown on Drawing CRM.066.006.GE.D.001. 

3.3.3 The site access and internal haul road system will be linked to the existing access spur. 

3.3.4 Temporary site accommodation will be constructed adjacent to the site access and will provide 

security to the site.  This will be used to prevent members of the public accessing the site and 

to check vehicles entering and leaving the site. 

3.3.5 The site hoarding will include the names and contact details of the Principal Contractor, Client 

and  Engineer.    Details  of  any  decorative  displays will  be  provided  to  the  Local  Planning 

Authority for approval in advance. 

Houghton Main TRRC TMP    March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

3.3.6 Details  of  any  specific  health  and  safety  requirements  such  as  the  use  of  PPE  and  site 

requirements, will also be included on the hoarding. 

3.4 Site Logistics  

3.4.1 A plan showing the proposed locations of site offices and compound is presented as Drawing 

CRM.066.006.GE.D.001. The key features are discussed below: 

Temporary  site  accommodation  will  be  provided  by  the  Principal  Contractor,

comprising:  office  accommodation,  mess  facilities  and  welfare  facilities.  The

temporary accommodation is located adjacent to the site access so that it can also be

used for security;

Car parking for site workers and visitors will be provided adjacent to the temporary

accommodation.

Any  vehicles  showing  substantial  amounts of mud  and dirt will be  required  to be

cleaned using the Jet Wash facility and road sweepers will also be employed;

The  proposed  sequence  of  construction  discussed  in  Section  2  should  limit  the

generation of mud and dirt.

The Contractors Compound will be  constructed on hardstanding  comprising either

tarmac or granular capping.  Vehicles using the Contractors Compound will not enter

the site and will not be required to use the wheel wash.

The adjacent highway will be regularly inspected and if mud/debris is identified then

a road sweeper will be used to remove the material.

3.4.2 Areas of proposed storage for materials are shown on Drawing CRM.066.006.GE.D.001. This 

area will be used for  loading and unloading of plant and materials. Materials will be stored 

within the building ready for the finishing trades once construction of the building has been 

completed. Where possible a ‘just  in time’ delivery system will be used to minimise on‐site 

storage. This will be further developed by the appointed Principal Contractor. 

3.4.3 More vulnerable materials and equipment will be stored within the Contractor’s Compound.  

3.4.4 A  single  point  of  access  and  egress  is  proposed.    There  will  be  separation  on‐site  of 

construction plant and pedestrian access from the Contractor’s Compound to the construction 

site.  

 

Houghton Main TRRC TMP          March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

10 

 

3.4.5 A circular route is proposed, where possible, for delivery vehicles to prevent vehicle crossing 

and to ensure that the wheel wash facilities are used. These will be kept separate from the 

working  area  of  the  plant.  The  internal  traffic  route  is  shown  on  Drawing 

CRM.066.006.GE.D.001. A specific plan will be developed  in accordance with  the proposed 

Traffic Management procedures discussed later in this document. 

3.4.6 The working areas for plant and machinery on site will vary depending on the stage of the 

construction works. Suitable phasing plans will be determined by the Principal Contractor and 

the route for delivery vehicles will be amended as necessary. 

3.5 Traffic Management 

3.5.1 The works will comply with Regulation 36 (Traffic Routes) and Regulation 27 (Vehicles) of CDM 

2007 by providing a traffic management plan which will be displayed in the site office.  The 

objectives of the plan will ensure: 

The safe and efficient working environment for all staff, visitors and contractors when 

on site; 

To ensure visiting  traffic and deliveries arriving and  leaving site can operate within 

definitive areas; 

Abnormal loads to be pre‐booked; 

To  ensure  that  any  contractors  on  site  can  operate  their  workforce,  plant  and 

equipment in a safe and manageable environment.   

Houghton Main TRRC TMP    March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

11 

3.5.2 The  plan will  be  developed  by  the  Principal  Contractor  and will  detail  specific measures, including those outlined in the Site Locations Section and will include: 

Speed restrictions;

Traffic flow directions;

Road crossing points;

Turning circles;

Wheel wash facilities; Pedestrian access and egress points;

Site offices and compounds;

Materials storage;

Emergency assembly points.

3.5.3 The site entrance will be clearly signed to raise driver’s awareness to the site entrance.  The 

site will have adequate signage in accordance with Chapter 8 of the Traffic Signs Manual. 

3.5.4 A speed limit of 5mph will be applied on site vehicles when operating within the works.  All 

drivers will be notified of the limit with speed signs clearly displayed. 

3.5.5 To mitigate risks associated with plant and vehicles the following will also be used: 

Pedestrian barriers at site entrance;

Temporary crossings to direct pedestrians across road way away from conflict areas;

Banksmen and Traffic Marshalls;

 

Houghton Main TRRC TMP          March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

12 

 

4.0 Construction Traffic and Deliveries 

4.1 Construction Period and Contractor Liaison 

4.1.1 The predicted construction period for the construction of the new Renewable Energy Park, that 

will  comprise of a Timber Resource Recovery Centre  (TRRC) and associated  infrastructure,  is 

between approximately 30  months.  However, it should be noted that this contract period may 

fluctuate as the construction work progresses on site. 

4.1.2 It  should  be  noted  that  construction  works  will  be  limited  to  the  following  hours  unless 

otherwise agreed with the Local Planning Authority; 

07:00 hours to 19:00 hours Monday to Friday; 

07:00 hours to 13:00 hours on Saturday; 

No working on Sundays or Bank Holidays 

There may be exceptional circumstances where work will be necessary outside of the hours 

set out above.  Any abnormal working hour requirements outside the proposed construction 

working hours will be notified in writing to the Local Planning Authority. 

4.1.3 The main construction phases of the TRRC will include the following, although timescales are 

currently unavailable for the main construction activities.    Indicative construction durations 

have been included below and will be firmed up once the contractor has been appointed.   

4.1.4 As the temporary ASOS car park is currently in use and has been temporarily ‘stoned up’ to 

approximate  levels  it has not yet been confirmed when the permanent car park works will 

commence.  

4.1.5 The  details  of  the  personnel  who  will  be  responsible  for  supervising,  controlling  and 

monitoring vehicle movements to and from the site will be provide once the contractor has 

been confirmed.  The contractor will nominate an individual who will operate as a site security 

who will be responsible for ensuring all drivers sign in and out once they have visited the site.  

The site security staff will work alongside the site project manager who will ensure that the 

vehicle movements are supervised with site operatives assigned specific roles. 

 

 

 

Houghton Main TRRC TMP          March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

13 

 

4.2 Vehicle Types and frequencies  

4.2.1 Peel Environmental Limited’s design team has experience in the delivery of similar Renewable 

Energy schemes and therefore an appreciation of the construction Information provided by 

design team has been used to inform this section. 

4.3 Abnormal Loads 

4.3.1 During the construction process, it may be necessary for the occasional abnormal load vehicles 

to transport components to the site. In advance of any such movements, the routing, timing 

and any specific traffic management requirements for such deliveries will be agreed in advance 

with the police and local highway authority. 

4.4 Heavy Goods Vehicles (HGVs) 

4.4.1 The construction period  is anticipated to take approximately two and a half years. During 

this period  there will be  trips associated with  the arrivals and departures of construction 

staff, and with  the delivery of parts and construction materials. Staff  trips will mainly be 

made by cars, vans or minibuses, whilst deliveries of construction materials and equipment 

will mainly be made by HGVs. 

4.4.2 The construction phase includes the preparation of the site, including the installation of any 

required internal roads, erection of fencing, construction of the building and grid connection. 

4.4.3 The  Contractor will  seek  to  limit  traffic  flows  during  the  road  network  peak  hours  and 

consideration will be given to any need for concrete pours requiring an intensification of HGV 

movements. 

4.4.4 A maximum of up  to 200  construction workers  are  anticipated  to be on  site during  key 

milestones of the construction phase over a 24 – 30 month period.  A temporary construction 

compound will be provided to accommodate storage, parking for contractors and turning 

provision for HGVs. 

4.4.5 The  location  from which staff will  travel  is not yet known, however  it  is envisaged  that a 

number of the non‐local workforce will stay in local accommodation and be transported to 

the site by minibuses to minimise the impact on the road network. 

 

Houghton Main TRRC TMP          March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

14 

 

4.4.6 The construction period will include the use of HGVs to bring equipment onto the site and 

these operations will be strictly managed to ensure that vehicle movements are controlled 

and minimised. 

4.4.7 Construction  of  the  Renewable  Energy  Centre  is  unlikely  to  require  any 

equipment/components to be delivered by abnormal load vehicles. 

4.4.8 The majority of construction traffic movements will be generated from site operatives’ cars 

and  light vans. Most construction machinery will be delivered to the site during the early 

stages of the build programme and will remain on‐site for most of its duration. 

4.4.9 The  materials  required  during  the  construction  of  the  facility  will  be  transported  by 

articulated vehicles with a maximum length of 16.5 metres.   

4.4.10 Generally, the flow of construction traffic would be spread evenly over the working day, with 

occasional peaks resulting from operational requirements for materials and stock‐piling on 

site.  At the peak of construction approximately 60 vehicles are predicted. 

4.5 Light Goods Vehicles 

4.5.1 In  addition  to  the  HGV movements  there  will  also  be  a  small  number  of  construction 

movements associated with smaller vehicles, such as the collection of skips and the transport 

of construction workers. 

4.5.2 The number of construction staff on site will vary over the construction period depending on 

the activity that is taking place. The majority of staff will travel in crew buses, which will park 

on site during the day. 

4.5.3 In addition, there are expected to be a small number of managerial cars / vans. There will be 

sufficient parking space provided during construction to accommodate these vehicles and 

the unloading of delivery vehicles. 

4.6 Loading/Unloading and Parking 

4.6.1 GSDA drawing reference 1313 PL003 Revision A, that is in the drawing appendix to this report, 

shows the route of circulatory route of the site vehicles including the unloading and loading 

 

Houghton Main TRRC TMP          March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

15 

 

points within the site.  To confirm the vehicles will enter and exit via the western spur off the 

roundabout and will load up via the 2 No. loading access points on the west facing side of the 

reception hall.   To exit  the vehicles will drive around  the west, north and east  side of  the 

process building and exit via the western roundabout spur onto the main network.  This route 

has been tracked on the drawing for a 16.5m legal length articulated HGV.  The construction 

vehicles will follow a similar route, particularly as the site work progresses. 

 

4.6.2 To ensure that any unloading or loading activities do not result in HGV’s reversing into the live 

carriageway  a  suitable  designed  part  of  the  site  will  assigned  to  accommodate  vehicles 

entering, turning and exiting in a forward gear.  The site is of a sufficient size to accommodate 

such movements  along with  the  aid of banksmen who will be  readily  available under  the 

supervision of the project manager. 

 

4.6.3 Any unloading or  loading times associated with construction activities and deliveries will be 

deliberately planned to avoid the staff changeover times of the shifts.  At present ASOS employ 

approximately 4,000 staff across 3 shifts and each shift employs 3 rota’s of which at any one 

time there are only 2 rota’s on shift due to rest days.   As a result the maximum number of 

people onsite are as follows and any loading, unloading or construction activities will avoid the 

changeover periods of the following shifts; 

 

AM Shift (07:00 – 15:00 hours) 

PM Shift (15:00 – 23:00 hours) 

Nights (23:00 – 07:00 hours) 

4.6.4 The  routes  shown on drawing 1313 PL003 Revision A  show  that  the majority of  the main 

pedestrian desire lines and walking routes are internal.  Any external walking routes, including 

the  internal parking areas, are clearly separate from the HGV routes to avoid and potential 

vehicle/pedestrian conflict. 

4.6.5 To ensure delivery vehicles do not queue back onto the live carriageway, via the roundabout 

spur,  a  sufficient  length  of  internal  road  alongside  the  western  site  boundary  has  been 

designated  for  queuing  vehicles.    The  weighbridge  has  been  positioned  at  least  4  No. 

articulated vehicle  lengths into the site (approximately 65 metres) that provides a sufficient 

internal queuing length and avoids vehicles queuing into the roundabout. 

 

Houghton Main TRRC TMP          March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

16 

 

4.6.6 In terms of the construction vehicles they will follow a similar on site route to the operational 

traffic and as the construction activity ramps up the building  lines and areas of  ‘stoned up’ 

internal roads along with signage and banksmen will assist the drivers. 

4.7 Parking 

4.7.1 A parking area for construction vehicles will be signposted and clearly  identifiable once the 

construction vehicles have entered the site.  The area that is designated as staff parking (see 

extract below)  seems  to be a practical place  for  construction vehicles  to park up  that will 

encroach too much on the construction activity.  This area is large enough to accommodate a 

number  of  large  HGV’s  and  providing  they  are  parked  in  an  organised manner,  via  the 

contractors banksmen. 

4.7.2 Internal parking arrangement will also be arranged with the contactor to ensure the staff also 

have a safe parking area that is segregated from the construction parking and vehicular routes.  

Although this area has yet to be confirmed there is a number of areas within the site that can 

accommodate the parking. 

4.8 Route to and from Site 

4.8.1 Although the route that the construction vehicles will take to the site has yet to be confirmed 

we have used our local knowledge of the area and the freight journey planner to predict what 

routes  the HGV’s  and  abnormal  route  vehicles will  take  to  reach  the  site.    To  avoid  any 

congested routes and potential torturous routes the HGV’s and abnormal  loads will seek to 

avoid these area during the AM and PM peak periods. 

4.8.2 The diagram below shows how the vehicles are predicted to reach the site from the north and 

south.  The A1(M) is the main route that can be used for HGV’s and abnormal vehicles and the 

A635 Barnsley Road can then be used to access the site.  This involves passing through villages 

including Marr, Hickleton and along Goldthorpe bypass, although the roads in general are of a 

good vertical and horizontal alignment and suitable for HGV’s.  Any abnormal vehicles using 

this route should also be able to pass safely although it is still recommended that they inform 

the  local police  authority  and highway  authority.    There  are  a  number of  laybys  that  are 

between the A1(M) and the site should the vehicles experience any difficulties, although this 

is unlikely.   

 

Houghton Main TRRC TMP          March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

17 

 

 

[www.freightjourneyplanner.co.uk] 

4.8.3 The above route is considered to the safest for HGV’s and abnormal sized vehicles to reach 

the site.  

4.8.4 The above route plan, including a list of directions, will be issued to all contractors prior to 

any site activity commencing.   The site staff will have been briefed on the highway  issues 

associated with the site and will be suitably trained to ensure that the vehicles are able to 

access and egress from the site in a safe manner. 

4.8.5 In terms of the internal haul road system and the predicted route that the vehicles will take 

this is shown in the extract in section 3.6 above.  Although the route may be subject to slight 

deviation the main buildings do dictate the route to an extent. 

 

Houghton Main TRRC Site 

 

Houghton Main TRRC TMP          March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

18 

 

5.0 Pedestrian and Vehicle Controls 

5.1 Pedestrian Measures 

5.1.1 The following measures will be put in place in order to protect pedestrians from construction vehicles; 

The  provision  of  suitable  pedestrian  safety  barriers  along with  clear  signage  and 

lighting to direct pedestrians away from the site activity; 

Banksmen who will  be  positioned  at  the  site  entrance/exit  at  all  times  to  direct 

pedestrians away from the site and ensure safer entry for construction vehicles; 

Temporary  footpaths  will  be  formed  and  signed  at  the  site  entrance  to  deter 

pedestrians  from  entering  the  site  or  encroaching  on  areas  that  are  subject  to 

construction activity; 

The site will have tight security with CCTV camera’s, site security guards and suitable 

fencing to prevent pedestrians from entering the site that will ensure they are do not 

conflict with any vehicles. 

5.1.2  The above measures will protect pedestrians during times of deliveries and ensure that any 

potential risk of any conflict is minimised. 

5.2 Vehicle Controls 

5.2.1 To ensure that the deliveries are carried out in a safe manner the following controls will be enforced at the proposed development site; 

The loading bay has been positioned and orientated to ensure the rear of the delivery 

vehicle opposes the main vehicle/pedestrian access; 

Peel Environmental Ltd has a strict protocol that is followed by all delivery drivers and 

staff to ensure the risk of any conflict is minimised; 

The delivery and construction vehicles will be briefed prior  to arrival at  the site  to 

ensure they follow the correct route once they are approaching the site entrance 

The contractor will time the deliveries and construction traffic activity during off peak 

periods to minimise any conflict with pedestrians, etc; 

Double yellow lines and warning signs will be erected to prevent ill‐disciplined parking 

local to the site entrance; 

 

Houghton Main TRRC TMP          March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

19 

 

6.0 Signage and Lighting 

6.1 Signage and Lighting 

6.1.1 Lighting at the entrance to the TRRC and within the site will be provided to assist the delivery drivers  to  unload  in  a  safe manner.    The  lighting will  provide  clear  visibility  at  all  times, particularly during the dark winter periods, to ensure the vehicles can be loaded and unloaded in a safe manner.  

 

 

   

 

Houghton Main TRRC TMP          March 2018 

CRM.066.006.R.TR.002 Houghton Main TRRC TMP  March 2018 

20 

 

APPENDIX 

 

 

Dismantled Railway

PA

RK S

PRIN

G R

OA

D

COLLIERY

MAIN

HOUGHTON

Generating

Electricity

ROUNDABOUT

Def

Hall

Reception

Condensers

Apron

Manoeuvring

Workshop

Offices/

12 bays inc. 2x disabled

Car park

Building

Process

maintained

Access

access

Loading

access

Loading

access

Service

access

Service

Turbine

1

1

-3%

0%Max Legal Articulated Vehicle (16.5m)

+ bypass lane

In weighbridge

Out weighbridge

4

4

0%

0%

Max Legal Articulated Vehicle (16.5m)

Queuing - 2 x HGVs

First Floor

Ctrl. Rm

Cycle shelter

ACCs

pumps enclosure

Fire water

and bund (double skin)

Fuel oil storage tank

silos

Ash storage

Fire water tank

Stack

Standby generator

Recovery Centre

Timber Resource

2 no. roller shutters

this elevation via

HGV access to

Switchgear Room

13

13

13

13

-3%

0%Max Legal Articulated Vehicle (16.5m)

Sub-Station

2

2

2

2-2%

0%

Max Legal Articulated Vehicle (16.5m)

Max Legal A

rticulated V

ehicle (16.5

m)

5

5

5

-1%

0%

22

2

2

2

0%

4%

Max Legal A

rticulated V

ehicle (16.5

m)

8

8

-2%

0%Large Car (2006)

9

-14%

0%

Large

Car (2006)

DWG. NO. REVISION

SCALE DATE

DRAWING

PROJECT

CHECKED

FOR INFORMATION

1.

2.

3.

4.

NOTE

HOUGHTON MAIN REC

GSDAGARRY STEWART DESIGN ASSOCIATES

LATTER TAKE PREFERENCE.DETAIL DRAWINGS, THEASSEMBLY DRAWINGS &BETWEEN REFERENCE ORWHERE DISCREPANCIES EXIST RESOLUTION.ARCHITECTS FORATTENTION OF THEBE BROUGHT TO THEDIMENSIONS THESE MUSTARE FOUND BETWEENWHERE ANY DISCREPANCIES DIMENSION STRINGS.TO BE TAKEN FROMDRAWING ALL DIMENSIONSNOT SCALE FROM THETHE CONTRACTOR MUST GSDA LTD. THIS DRAWING IS COPYRIGHT

T. 020 8544 8085 Broadway, Wimbledon, London, SW19 1NEHighlands House, Office 101A, 165 The

0 50 100 150m

-

Proposed Site Layout

1313_PL003 A GS

KEY

NORTH

1:1000@A31:500@A1

Issued for planning

Site boundary

tree line perimeter2.5m wide hedge/

Adjacent site

please refer to PL036-37landscaping and plantingFor details of proposed

150123

150130

A Issued for planning150130