Upload
loginxscribd
View
227
Download
0
Embed Size (px)
Citation preview
7/24/2019 toc_18R-97
1/6
CopyrightAACEInternational AACE
InternationalRecommendedPractices
AACEInternationalRecommendedPracticeNo.18R97
COSTESTIMATECLASSIFICATIONSYSTEM
ASAPPLIED
IN
ENGINEERING,
PROCUREMENT,
AND
CONSTRUCTION
FORTHEPROCESSINDUSTRIESTCMFramework:7.3CostEstimatingandBudgeting
Rev.November29,2011Note:AsAACEInternationalRecommendedPracticesevolveovertime,pleaserefertowww.aacei.orgforthelatestrevisions.
Contributors:
Disclaimer:Theopinionsexpressedbytheauthorsandcontributorstothisrecommendedpracticearetheirown
anddonotnecessarilyreflectthoseoftheiremployers,unlessotherwisestated.
PeterChristensen,
CCE
(Author)
LarryR.Dysert,CCCCEP(Author)
JenniferBates,CCE
JefferyJ.Borowicz,CCECEPPSP
PeterR.Bredehoeft,Jr.CEP
RobertB.Brown,PE
DorothyJ.Burton
RobertC.Creese,PECCE
JohnK.Hollmann,PECCECEP
KennethK.
Humphreys,
PE
CCE
DonaldF.McDonald,Jr.PECCEPSP
C.ArthurMiller
ToddW.Pickett,CCCCEP
BernardA.Pietlock,CCCCEP
WesleyR.Querns,CCE
DonL.Short,IICEP
H.LanceStephenson,CCC
JamesD.Whiteside,IIPE
7/24/2019 toc_18R-97
2/6
AACEInternationalRecommendedPracticeNo.18R97
COSTESTIMATECLASSIFICATIONSYSTEM AS
APPLIEDINENGINEERING,PROCUREMENT,AND
CONSTRUCTIONFORTHEPROCESSINDUSTRIESTCMFramework:7.3CostEstimatingandBudgeting
November29,2011
CopyrightAACEInternational AACE
InternationalRecommendedPractices
PURPOSE
AsarecommendedpracticeofAACEInternational,theCostEstimateClassificationSystemprovidesguidelinesfor
applyingthegeneralprinciplesofestimateclassificationtoprojectcostestimates(i.e.,costestimatesthatareused
toevaluate,approve,and/orfundprojects).TheCostEstimateClassificationSystemmapsthephasesandstagesof
projectcostestimatingtogetherwithagenericprojectscopedefinitionmaturityandqualitymatrix,whichcanbe
appliedacrossawidevarietyofprocessindustries.
Thisaddendumtothegenericrecommendedpractice(17R97)providesguidelines forapplyingtheprinciplesof
estimateclassificationspecificallytoprojectestimatesforengineering,procurement,andconstruction(EPC)work
fortheprocessindustries.Thisaddendumsupplementsthegenericrecommendedpracticebyproviding:
asectionthatfurtherdefinesclassificationconceptsastheyapplytotheprocessindustries;and
achart
that
maps
the
extent
and
maturity
of
estimate
input
information
(project
definition
deliverables)
againsttheclassofestimate.
Aswiththegenericrecommendedpractice,anintentofthisaddendumistoimprovecommunicationsamongallof
thestakeholdersinvolvedwithpreparing,evaluating,andusingprojectcostestimatesspecificallyfortheprocess
industries.
The overall purpose of this recommended practice is to provide the process industry definition deliverable
maturitymatrixwhichisnotprovidedin17R97.Italsoprovidesanapproximaterepresentationoftherelationship
ofspecificdesign inputdataanddesigndeliverablematuritytotheestimateaccuracyandmethodologyusedto
produce the cost estimate. The estimate accuracy range is driven by many other variables and risks, so the
maturityandqualityofthescopedefinitionavailableatthetimeoftheestimate isnotthesoledeterminateof
accuracy;riskanalysisisrequiredforthatpurpose.
Thisdocumentisintendedtoprovideaguideline,notastandard.Itisunderstoodthateachenterprisemayhave
its own project and estimating processes and terminology, and may classify estimates in particular ways. This
guidelineprovidesagenericandgenerallyacceptableclassificationsystemforprocessindustriesthatcanbeused
asabasistocompareagainst.Thisaddendumshouldalloweachusertobetterassess,define,andcommunicate
theirownprocessesandstandardsinthelightofgenerallyacceptedcostengineeringpractice.
INTRODUCTION
For the purposes of this addendum, the term process industries is assumed to include firms involved with the
manufacturing and production of chemicals, petrochemicals, and hydrocarbon processing. The common thread
amongthese
industries
(for
the
purpose
of
estimate
classification)
is
their
reliance
on
process
flow
diagrams
(PFDs)
and piping and instrument diagrams (P&IDs) as primary scope defining documents. These documents are key
deliverables indeterminingthedegreeofprojectdefinition,andthustheextentandmaturityofestimate input
information.
Estimates forprocess facilitiescenteronmechanicalandchemicalprocessequipment,andtheyhavesignificant
amountsofpiping,instrumentation,andprocesscontrolsinvolved.Assuch,thisaddendummayapplytoportions
of other industries, such as pharmaceutical, utility, metallurgical, converting, and similar industries. Specific
addendumsaddressingtheseindustriesmaybedevelopedovertime.
7/24/2019 toc_18R-97
3/6
18R97:CostEstimateClassificationSystem AsAppliedinEngineering,Procurement,and
ConstructionfortheProcessIndustries
2 of10
November 29,2011
CopyrightAACEInternational AACE
InternationalRecommendedPractices
This addendum specifically does not address cost estimate classification in nonprocess industries such as
commercial building construction, environmental remediation, transportation infrastructure, hydropower, dry
processessuchasassemblyandmanufacturing, softassetproductionsuchassoftwaredevelopment,andsimilar
industries.
It
also
does
not
specifically
address
estimates
for
the
exploration,
production,
or
transportation
of
mining or hydrocarbon materials, although it may apply to some of the intermediate processing steps in these
systems.
Thecostestimatescoveredbythisaddendumareforengineering,procurement,andconstruction(EPC)workonly.
It does not cover estimates for the products manufactured by the process facilities, or for research and
development work in support of the process industries. This guideline does not cover the significant building
constructionthatmaybeapartofprocessplants.
Thisguidelinereflectsgenerallyacceptedcostengineeringpractices.Thisaddendumwasbaseduponthepractices
ofawiderangeofcompaniesintheprocessindustriesfromaroundtheworld,aswellaspublishedreferencesand
standards. Company and public standards were solicited and reviewed, and the practices were found to have
significant commonalities. These classifications are also supported by empirical process industry research of
systemicrisksandtheircorrelationwithcostgrowthandscheduleslip[8]
.
COSTESTIMATECLASSIFICATIONMATRIXFORTHEPROCESSINDUSTRIES
PrimaryCharacteristic SecondaryCharacteristic
ESTIMATE
CLASS
MATURITYLEVELOF
PROJECTDEFINITION
DELIVERABLESExpressedas%ofcomplete
definition
ENDUSAGETypicalpurposeof
estimate
METHODOLOGYTypicalestimatingmethod
EXPECTEDACCURACY
RANGETypicalvariationinlowandhigh
ranges[a]
Class
5
0%to
2%
Concept
screening
Capacityfactored,
parametricmodels,
judgment,oranalogy
L:
20%to
50%
H: +30%to+100%
Class4 1%to15%Studyor
feasibility
Equipmentfactoredor
parametricmodels
L: 15%to30%
H: +20%to+50%
Class3 10%to40%
Budget
authorizationor
control
Semidetailedunitcosts
withassemblylevelline
items
L: 10%to20%
H: +10%to+30%
Class2 30%to75%Controlor
bid/tender
Detailedunitcostwith
forceddetailedtakeoff
L: 5%to15%
H: +5%to+20%
Class1 65%to100%Checkestimate
orbid/tender
Detailedunitcostwith
detailedtakeoff
L: 3%to10%
H: +3%to+15%
Notes:[a]
The
state
of
process
technology,
availability
of
applicable
reference
cost
data,
and
many
other
risks
affect
the
range
markedly.
The
+/ valuerepresentstypicalpercentagevariationofactualcostsfromthecostestimateafterapplicationofcontingency(typicallyat
a50%levelofconfidence)forgivenscope.
Table1CostEstimateClassificationMatrixforProcessIndustries
Table1providesasummaryofthecharacteristicsofthefiveestimateclasses.Thematuritylevelofdefinitionisthe
sole determining (i.e., primary) characteristic of Class. In Table 1, the maturity is roughly indicated by a % of
complete definition; however, it is the maturity of the defining deliverables that is the determinant, not the
percent.Thespecificdeliverables,andtheirmaturity,orstatus,areprovidedinTable3.Theothercharacteristics
7/24/2019 toc_18R-97
4/6
18R97:CostEstimateClassificationSystem AsAppliedinEngineering,Procurement,and
ConstructionfortheProcessIndustries
3 of10
November 29,2011
CopyrightAACEInternational AACE
InternationalRecommendedPractices
aresecondaryandaregenerallycorrelatedwiththematuritylevelofprojectdefinitiondeliverables,asdiscussed
in the generic RP[1]
. The characteristics are typical for the process industries but may vary from application to
application.
Thismatrix
and
guideline
outline
an
estimate
classification
system
that
is
specific
to
the
process
industries.
Refer
tothegenericestimateclassificationRP[1]
forageneralmatrixthatisnonindustryspecific,ortootheraddendums
for guidelines that will provide more detailed information for application in other specific industries. These will
provide additional information, particularly the project definition deliverable maturity matrix which determines
theclassinthoseparticularindustries.
Table1illustratestypicalrangesofaccuracyrangesthatareassociatedwiththeprocessindustries.Dependingon
thetechnicalandprojectdeliverables(andothervariables)andrisksassociatedwitheachestimate,theaccuracy
rangeforanyparticularestimateisexpectedtofallintotherangesidentified(althoughextremeriskscan leadto
widerranges).
Inadditiontothedegreeofprojectdefinition,estimateaccuracyisalsodrivenbyothersystemicriskssuchas:
Levelofnonfamiliartechnologyintheproject.
Complexityoftheproject.
Qualityofreferencecostestimatingdata.
Qualityofassumptionsusedinpreparingtheestimate.
Experienceandskillleveloftheestimator.
Estimatingtechniquesemployed.
Timeandlevelofeffortbudgetedtopreparetheestimate.
Systemic risks such as these are often the primary driver of accuracy; however, projectspecific risks (e.g. risk
events)alsodrivetheaccuracyrange[3]
.
Anotherwayto lookatthevariabilityassociatedwithestimateaccuracyranges isshown inFigure1.Depending
uponthetechnicalcomplexityoftheproject,theavailabilityofappropriatecostreferenceinformation,thedegree
ofproject
definition,
and
the
inclusion
of
appropriate
contingency
determination,
atypical
Class
5estimate
for
a
processindustryprojectmayhaveanaccuracyrangeasbroadas50%to+100%,orasnarrowas20%to+30%.
Figure1alsoillustratesthattheestimatingaccuracyrangesoverlaptheestimateclasses.Therearecaseswherea
Class 5 estimate for a particular project may be as accurate as a Class 3 estimate for a different project. For
example, similar accuracy ranges may occur for the Class 5 estimate of one project that is based on a repeat
projectwithgoodcosthistoryanddataandtheClass3estimateforanotherprojectinvolvingnewtechnology.Itis
forthisreasonthatTable1providesrangesofaccuracyrangevalues.Theaccuracyrange isdeterminedthrough
riskanalysisofthespecificproject.
7/24/2019 toc_18R-97
5/6
18R97:CostEstimateClassificationSystem AsAppliedinEngineering,Procurement,and
ConstructionfortheProcessIndustries
4 of10
November 29,2011
CopyrightAACEInternational AACE
InternationalRecommendedPractices
Figure1ExampleoftheVariabilityinAccuracyRangesforaProcessIndustryEstimate
DETERMINATIONOFTHECOSTESTIMATECLASS
The cost estimator makes the determination of the estimate class based upon the maturity level of project
definitionbasedonthestatusofspecifickeyplanninganddesigndeliverables.Thepercentdesigncompletionmay
be correlated with the status, but the percentage should not be used as the Class determinate. While the
determinationof
the
status
(and
hence
class)
is
somewhat
subjective,
having
standards
for
the
design
input
data,
completenessandqualityofthedesigndeliverableswillservetomakethedeterminationmoreobjective.
CHARACTERISTICSOFTHEESTIMATECLASSES
Thefollowingtables(2athrough2e)providedetaileddescriptionsofthefiveestimateclassificationsasappliedin
theprocessindustries.Theyarepresentedintheorderofleastdefinedestimatestothemostdefinedestimates.
Thesedescriptionsincludebriefdiscussionsofeachoftheestimatecharacteristicsthatdefineanestimateclass.
50
40
30
20
10
0
10
20
30
40
50
60
70
80
90
100
0 10 20 30 40 50 60 70 80 90 100
Growthfrom
EstimatedCostsIncludingContingency(%)
MaturityLevelofProjectDefinitionDeliverables(%)
Class
4
Class3
Class
2
Class1
Class5
7/24/2019 toc_18R-97
6/6
18R97:CostEstimateClassificationSystem AsAppliedinEngineering,Procurement,and
ConstructionfortheProcessIndustries
5 of10
November 29,2011
CopyrightAACEInternational AACE
InternationalRecommendedPractices
Foreachtable,thefollowinginformationisprovided:
Description:ashortdescriptionoftheclassofestimate,includingabrieflistingoftheexpectedestimate
inputs based on the maturity level of project definition deliverables. The minimum inputs reflect the
rangeofindustryexperience,butwouldnotgenerallyberecommended.
Maturity
Level
of
Project
Definition
Deliverables
(Primary
Characteristic):
Describes
a
particularly
key
deliverableandatypicaltargetstatusinstagegatedecisionprocesses,plusanindicationofapproximate
percentoffulldefinitionofprojectandtechnicaldeliverables.Fortheprocess industries,thiscorrelates
withthepercentofengineeringanddesigncomplete.
End Usage (Secondary Characteristic): a short discussion of the possible end usage of this class of
estimate.
EstimatingMethodology (Secondary Characteristic): a listing of the possible estimating methods that
maybeemployedtodevelopanestimateofthisclass.
ExpectedAccuracyRange (SecondaryCharacteristic): typical variation in low and high ranges after the
applicationofcontingency(determinedata50%levelofconfidence).Typically,thisrepresentsabout80%
confidence that the actual cost will fall within the bounds of the low and high ranges. The estimate
confidenceintervaloraccuracyrangeisdrivenbythereliabilityofthescopeinformationavailableatthe
time
of
the
estimate
in
addition
to
the
other
variables
and
risk
identified
above.
AlternateEstimateNames,Terms,Expressions,Synonyms: this sectionprovides other commonly used
namesthatanestimateofthisclassmightbeknownby.Thesealternatenamesarenotendorsedbythis
Recommended Practice. The user is cautioned that an alternative name may not always be correlated
withtheclassofestimateasidentifiedinTables2a2e.
CLASS
5
ESTIMATE
Description:
Class5estimatesaregenerallypreparedbasedonverylimited
information,andsubsequentlyhavewideaccuracyranges.As
such, some companies and organizations have elected to
determine that due to the inherent inaccuracies, such
estimates cannot be classified in a conventional and
systematicmanner.Class5estimates,duetotherequirements
ofenduse,maybepreparedwithinavery limitedamountof
timeandwithlittleeffortexpendedsometimesrequiringless
than an hour to prepare. Often, little more than proposed
plant type, location, and capacity are known at the time of
estimatepreparation.
MaturityLevelofProjectDefinitionDeliverables:
Key deliverable and target status: Block flow diagram agreed
bykeystakeholders.0%to2%offullprojectdefinition.
End
Usage:
Class 5 estimates are prepared for any number of strategic
business
planning
purposes,
such
as
but
not
limited
to
market
studies, assessment of initial viability, evaluation of alternate
schemes, project screening, project location studies,
evaluation of resource needs and budgeting, longrange
capitalplanning,etc.
Estimating
Methodology:
Class5estimatesgenerallyusestochasticestimatingmethods
such as cost/capacity curves and factors, scale of operations
factors, Lang factors, Hand factors, Chilton factors, Peters
Timmerhaus factors, Guthrie factors, and other parametric
andmodelingtechniques.
Expected
Accuracy
Range:
TypicalaccuracyrangesforClass5estimatesare
20%to50%onthelowside,and+30%to+100%onthehigh
side, depending on the technological complexity of the
project, appropriate reference information and other risks (
after inclusionofan appropriatecontingency determination).
Rangescouldexceedthoseshownifthereareunusualrisks.
Alternate
Estimate
Names,
Terms,
Expressions,
Synonyms:
Ratio, ballpark, blue sky, seatofpants, ROM, idea study,
prospect estimate, concession license estimate, guesstimate,
ruleofthumb.
Table2aClass5Estimate