toc_18R-97

Embed Size (px)

Citation preview

  • 7/24/2019 toc_18R-97

    1/6

    CopyrightAACEInternational AACE

    InternationalRecommendedPractices

    AACEInternationalRecommendedPracticeNo.18R97

    COSTESTIMATECLASSIFICATIONSYSTEM

    ASAPPLIED

    IN

    ENGINEERING,

    PROCUREMENT,

    AND

    CONSTRUCTION

    FORTHEPROCESSINDUSTRIESTCMFramework:7.3CostEstimatingandBudgeting

    Rev.November29,2011Note:AsAACEInternationalRecommendedPracticesevolveovertime,pleaserefertowww.aacei.orgforthelatestrevisions.

    Contributors:

    Disclaimer:Theopinionsexpressedbytheauthorsandcontributorstothisrecommendedpracticearetheirown

    anddonotnecessarilyreflectthoseoftheiremployers,unlessotherwisestated.

    PeterChristensen,

    CCE

    (Author)

    LarryR.Dysert,CCCCEP(Author)

    JenniferBates,CCE

    JefferyJ.Borowicz,CCECEPPSP

    PeterR.Bredehoeft,Jr.CEP

    RobertB.Brown,PE

    DorothyJ.Burton

    RobertC.Creese,PECCE

    JohnK.Hollmann,PECCECEP

    KennethK.

    Humphreys,

    PE

    CCE

    DonaldF.McDonald,Jr.PECCEPSP

    C.ArthurMiller

    ToddW.Pickett,CCCCEP

    BernardA.Pietlock,CCCCEP

    WesleyR.Querns,CCE

    DonL.Short,IICEP

    H.LanceStephenson,CCC

    JamesD.Whiteside,IIPE

  • 7/24/2019 toc_18R-97

    2/6

    AACEInternationalRecommendedPracticeNo.18R97

    COSTESTIMATECLASSIFICATIONSYSTEM AS

    APPLIEDINENGINEERING,PROCUREMENT,AND

    CONSTRUCTIONFORTHEPROCESSINDUSTRIESTCMFramework:7.3CostEstimatingandBudgeting

    November29,2011

    CopyrightAACEInternational AACE

    InternationalRecommendedPractices

    PURPOSE

    AsarecommendedpracticeofAACEInternational,theCostEstimateClassificationSystemprovidesguidelinesfor

    applyingthegeneralprinciplesofestimateclassificationtoprojectcostestimates(i.e.,costestimatesthatareused

    toevaluate,approve,and/orfundprojects).TheCostEstimateClassificationSystemmapsthephasesandstagesof

    projectcostestimatingtogetherwithagenericprojectscopedefinitionmaturityandqualitymatrix,whichcanbe

    appliedacrossawidevarietyofprocessindustries.

    Thisaddendumtothegenericrecommendedpractice(17R97)providesguidelines forapplyingtheprinciplesof

    estimateclassificationspecificallytoprojectestimatesforengineering,procurement,andconstruction(EPC)work

    fortheprocessindustries.Thisaddendumsupplementsthegenericrecommendedpracticebyproviding:

    asectionthatfurtherdefinesclassificationconceptsastheyapplytotheprocessindustries;and

    achart

    that

    maps

    the

    extent

    and

    maturity

    of

    estimate

    input

    information

    (project

    definition

    deliverables)

    againsttheclassofestimate.

    Aswiththegenericrecommendedpractice,anintentofthisaddendumistoimprovecommunicationsamongallof

    thestakeholdersinvolvedwithpreparing,evaluating,andusingprojectcostestimatesspecificallyfortheprocess

    industries.

    The overall purpose of this recommended practice is to provide the process industry definition deliverable

    maturitymatrixwhichisnotprovidedin17R97.Italsoprovidesanapproximaterepresentationoftherelationship

    ofspecificdesign inputdataanddesigndeliverablematuritytotheestimateaccuracyandmethodologyusedto

    produce the cost estimate. The estimate accuracy range is driven by many other variables and risks, so the

    maturityandqualityofthescopedefinitionavailableatthetimeoftheestimate isnotthesoledeterminateof

    accuracy;riskanalysisisrequiredforthatpurpose.

    Thisdocumentisintendedtoprovideaguideline,notastandard.Itisunderstoodthateachenterprisemayhave

    its own project and estimating processes and terminology, and may classify estimates in particular ways. This

    guidelineprovidesagenericandgenerallyacceptableclassificationsystemforprocessindustriesthatcanbeused

    asabasistocompareagainst.Thisaddendumshouldalloweachusertobetterassess,define,andcommunicate

    theirownprocessesandstandardsinthelightofgenerallyacceptedcostengineeringpractice.

    INTRODUCTION

    For the purposes of this addendum, the term process industries is assumed to include firms involved with the

    manufacturing and production of chemicals, petrochemicals, and hydrocarbon processing. The common thread

    amongthese

    industries

    (for

    the

    purpose

    of

    estimate

    classification)

    is

    their

    reliance

    on

    process

    flow

    diagrams

    (PFDs)

    and piping and instrument diagrams (P&IDs) as primary scope defining documents. These documents are key

    deliverables indeterminingthedegreeofprojectdefinition,andthustheextentandmaturityofestimate input

    information.

    Estimates forprocess facilitiescenteronmechanicalandchemicalprocessequipment,andtheyhavesignificant

    amountsofpiping,instrumentation,andprocesscontrolsinvolved.Assuch,thisaddendummayapplytoportions

    of other industries, such as pharmaceutical, utility, metallurgical, converting, and similar industries. Specific

    addendumsaddressingtheseindustriesmaybedevelopedovertime.

  • 7/24/2019 toc_18R-97

    3/6

    18R97:CostEstimateClassificationSystem AsAppliedinEngineering,Procurement,and

    ConstructionfortheProcessIndustries

    2 of10

    November 29,2011

    CopyrightAACEInternational AACE

    InternationalRecommendedPractices

    This addendum specifically does not address cost estimate classification in nonprocess industries such as

    commercial building construction, environmental remediation, transportation infrastructure, hydropower, dry

    processessuchasassemblyandmanufacturing, softassetproductionsuchassoftwaredevelopment,andsimilar

    industries.

    It

    also

    does

    not

    specifically

    address

    estimates

    for

    the

    exploration,

    production,

    or

    transportation

    of

    mining or hydrocarbon materials, although it may apply to some of the intermediate processing steps in these

    systems.

    Thecostestimatescoveredbythisaddendumareforengineering,procurement,andconstruction(EPC)workonly.

    It does not cover estimates for the products manufactured by the process facilities, or for research and

    development work in support of the process industries. This guideline does not cover the significant building

    constructionthatmaybeapartofprocessplants.

    Thisguidelinereflectsgenerallyacceptedcostengineeringpractices.Thisaddendumwasbaseduponthepractices

    ofawiderangeofcompaniesintheprocessindustriesfromaroundtheworld,aswellaspublishedreferencesand

    standards. Company and public standards were solicited and reviewed, and the practices were found to have

    significant commonalities. These classifications are also supported by empirical process industry research of

    systemicrisksandtheircorrelationwithcostgrowthandscheduleslip[8]

    .

    COSTESTIMATECLASSIFICATIONMATRIXFORTHEPROCESSINDUSTRIES

    PrimaryCharacteristic SecondaryCharacteristic

    ESTIMATE

    CLASS

    MATURITYLEVELOF

    PROJECTDEFINITION

    DELIVERABLESExpressedas%ofcomplete

    definition

    ENDUSAGETypicalpurposeof

    estimate

    METHODOLOGYTypicalestimatingmethod

    EXPECTEDACCURACY

    RANGETypicalvariationinlowandhigh

    ranges[a]

    Class

    5

    0%to

    2%

    Concept

    screening

    Capacityfactored,

    parametricmodels,

    judgment,oranalogy

    L:

    20%to

    50%

    H: +30%to+100%

    Class4 1%to15%Studyor

    feasibility

    Equipmentfactoredor

    parametricmodels

    L: 15%to30%

    H: +20%to+50%

    Class3 10%to40%

    Budget

    authorizationor

    control

    Semidetailedunitcosts

    withassemblylevelline

    items

    L: 10%to20%

    H: +10%to+30%

    Class2 30%to75%Controlor

    bid/tender

    Detailedunitcostwith

    forceddetailedtakeoff

    L: 5%to15%

    H: +5%to+20%

    Class1 65%to100%Checkestimate

    orbid/tender

    Detailedunitcostwith

    detailedtakeoff

    L: 3%to10%

    H: +3%to+15%

    Notes:[a]

    The

    state

    of

    process

    technology,

    availability

    of

    applicable

    reference

    cost

    data,

    and

    many

    other

    risks

    affect

    the

    range

    markedly.

    The

    +/ valuerepresentstypicalpercentagevariationofactualcostsfromthecostestimateafterapplicationofcontingency(typicallyat

    a50%levelofconfidence)forgivenscope.

    Table1CostEstimateClassificationMatrixforProcessIndustries

    Table1providesasummaryofthecharacteristicsofthefiveestimateclasses.Thematuritylevelofdefinitionisthe

    sole determining (i.e., primary) characteristic of Class. In Table 1, the maturity is roughly indicated by a % of

    complete definition; however, it is the maturity of the defining deliverables that is the determinant, not the

    percent.Thespecificdeliverables,andtheirmaturity,orstatus,areprovidedinTable3.Theothercharacteristics

  • 7/24/2019 toc_18R-97

    4/6

    18R97:CostEstimateClassificationSystem AsAppliedinEngineering,Procurement,and

    ConstructionfortheProcessIndustries

    3 of10

    November 29,2011

    CopyrightAACEInternational AACE

    InternationalRecommendedPractices

    aresecondaryandaregenerallycorrelatedwiththematuritylevelofprojectdefinitiondeliverables,asdiscussed

    in the generic RP[1]

    . The characteristics are typical for the process industries but may vary from application to

    application.

    Thismatrix

    and

    guideline

    outline

    an

    estimate

    classification

    system

    that

    is

    specific

    to

    the

    process

    industries.

    Refer

    tothegenericestimateclassificationRP[1]

    forageneralmatrixthatisnonindustryspecific,ortootheraddendums

    for guidelines that will provide more detailed information for application in other specific industries. These will

    provide additional information, particularly the project definition deliverable maturity matrix which determines

    theclassinthoseparticularindustries.

    Table1illustratestypicalrangesofaccuracyrangesthatareassociatedwiththeprocessindustries.Dependingon

    thetechnicalandprojectdeliverables(andothervariables)andrisksassociatedwitheachestimate,theaccuracy

    rangeforanyparticularestimateisexpectedtofallintotherangesidentified(althoughextremeriskscan leadto

    widerranges).

    Inadditiontothedegreeofprojectdefinition,estimateaccuracyisalsodrivenbyothersystemicriskssuchas:

    Levelofnonfamiliartechnologyintheproject.

    Complexityoftheproject.

    Qualityofreferencecostestimatingdata.

    Qualityofassumptionsusedinpreparingtheestimate.

    Experienceandskillleveloftheestimator.

    Estimatingtechniquesemployed.

    Timeandlevelofeffortbudgetedtopreparetheestimate.

    Systemic risks such as these are often the primary driver of accuracy; however, projectspecific risks (e.g. risk

    events)alsodrivetheaccuracyrange[3]

    .

    Anotherwayto lookatthevariabilityassociatedwithestimateaccuracyranges isshown inFigure1.Depending

    uponthetechnicalcomplexityoftheproject,theavailabilityofappropriatecostreferenceinformation,thedegree

    ofproject

    definition,

    and

    the

    inclusion

    of

    appropriate

    contingency

    determination,

    atypical

    Class

    5estimate

    for

    a

    processindustryprojectmayhaveanaccuracyrangeasbroadas50%to+100%,orasnarrowas20%to+30%.

    Figure1alsoillustratesthattheestimatingaccuracyrangesoverlaptheestimateclasses.Therearecaseswherea

    Class 5 estimate for a particular project may be as accurate as a Class 3 estimate for a different project. For

    example, similar accuracy ranges may occur for the Class 5 estimate of one project that is based on a repeat

    projectwithgoodcosthistoryanddataandtheClass3estimateforanotherprojectinvolvingnewtechnology.Itis

    forthisreasonthatTable1providesrangesofaccuracyrangevalues.Theaccuracyrange isdeterminedthrough

    riskanalysisofthespecificproject.

  • 7/24/2019 toc_18R-97

    5/6

    18R97:CostEstimateClassificationSystem AsAppliedinEngineering,Procurement,and

    ConstructionfortheProcessIndustries

    4 of10

    November 29,2011

    CopyrightAACEInternational AACE

    InternationalRecommendedPractices

    Figure1ExampleoftheVariabilityinAccuracyRangesforaProcessIndustryEstimate

    DETERMINATIONOFTHECOSTESTIMATECLASS

    The cost estimator makes the determination of the estimate class based upon the maturity level of project

    definitionbasedonthestatusofspecifickeyplanninganddesigndeliverables.Thepercentdesigncompletionmay

    be correlated with the status, but the percentage should not be used as the Class determinate. While the

    determinationof

    the

    status

    (and

    hence

    class)

    is

    somewhat

    subjective,

    having

    standards

    for

    the

    design

    input

    data,

    completenessandqualityofthedesigndeliverableswillservetomakethedeterminationmoreobjective.

    CHARACTERISTICSOFTHEESTIMATECLASSES

    Thefollowingtables(2athrough2e)providedetaileddescriptionsofthefiveestimateclassificationsasappliedin

    theprocessindustries.Theyarepresentedintheorderofleastdefinedestimatestothemostdefinedestimates.

    Thesedescriptionsincludebriefdiscussionsofeachoftheestimatecharacteristicsthatdefineanestimateclass.

    50

    40

    30

    20

    10

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    0 10 20 30 40 50 60 70 80 90 100

    Growthfrom

    EstimatedCostsIncludingContingency(%)

    MaturityLevelofProjectDefinitionDeliverables(%)

    Class

    4

    Class3

    Class

    2

    Class1

    Class5

  • 7/24/2019 toc_18R-97

    6/6

    18R97:CostEstimateClassificationSystem AsAppliedinEngineering,Procurement,and

    ConstructionfortheProcessIndustries

    5 of10

    November 29,2011

    CopyrightAACEInternational AACE

    InternationalRecommendedPractices

    Foreachtable,thefollowinginformationisprovided:

    Description:ashortdescriptionoftheclassofestimate,includingabrieflistingoftheexpectedestimate

    inputs based on the maturity level of project definition deliverables. The minimum inputs reflect the

    rangeofindustryexperience,butwouldnotgenerallyberecommended.

    Maturity

    Level

    of

    Project

    Definition

    Deliverables

    (Primary

    Characteristic):

    Describes

    a

    particularly

    key

    deliverableandatypicaltargetstatusinstagegatedecisionprocesses,plusanindicationofapproximate

    percentoffulldefinitionofprojectandtechnicaldeliverables.Fortheprocess industries,thiscorrelates

    withthepercentofengineeringanddesigncomplete.

    End Usage (Secondary Characteristic): a short discussion of the possible end usage of this class of

    estimate.

    EstimatingMethodology (Secondary Characteristic): a listing of the possible estimating methods that

    maybeemployedtodevelopanestimateofthisclass.

    ExpectedAccuracyRange (SecondaryCharacteristic): typical variation in low and high ranges after the

    applicationofcontingency(determinedata50%levelofconfidence).Typically,thisrepresentsabout80%

    confidence that the actual cost will fall within the bounds of the low and high ranges. The estimate

    confidenceintervaloraccuracyrangeisdrivenbythereliabilityofthescopeinformationavailableatthe

    time

    of

    the

    estimate

    in

    addition

    to

    the

    other

    variables

    and

    risk

    identified

    above.

    AlternateEstimateNames,Terms,Expressions,Synonyms: this sectionprovides other commonly used

    namesthatanestimateofthisclassmightbeknownby.Thesealternatenamesarenotendorsedbythis

    Recommended Practice. The user is cautioned that an alternative name may not always be correlated

    withtheclassofestimateasidentifiedinTables2a2e.

    CLASS

    5

    ESTIMATE

    Description:

    Class5estimatesaregenerallypreparedbasedonverylimited

    information,andsubsequentlyhavewideaccuracyranges.As

    such, some companies and organizations have elected to

    determine that due to the inherent inaccuracies, such

    estimates cannot be classified in a conventional and

    systematicmanner.Class5estimates,duetotherequirements

    ofenduse,maybepreparedwithinavery limitedamountof

    timeandwithlittleeffortexpendedsometimesrequiringless

    than an hour to prepare. Often, little more than proposed

    plant type, location, and capacity are known at the time of

    estimatepreparation.

    MaturityLevelofProjectDefinitionDeliverables:

    Key deliverable and target status: Block flow diagram agreed

    bykeystakeholders.0%to2%offullprojectdefinition.

    End

    Usage:

    Class 5 estimates are prepared for any number of strategic

    business

    planning

    purposes,

    such

    as

    but

    not

    limited

    to

    market

    studies, assessment of initial viability, evaluation of alternate

    schemes, project screening, project location studies,

    evaluation of resource needs and budgeting, longrange

    capitalplanning,etc.

    Estimating

    Methodology:

    Class5estimatesgenerallyusestochasticestimatingmethods

    such as cost/capacity curves and factors, scale of operations

    factors, Lang factors, Hand factors, Chilton factors, Peters

    Timmerhaus factors, Guthrie factors, and other parametric

    andmodelingtechniques.

    Expected

    Accuracy

    Range:

    TypicalaccuracyrangesforClass5estimatesare

    20%to50%onthelowside,and+30%to+100%onthehigh

    side, depending on the technological complexity of the

    project, appropriate reference information and other risks (

    after inclusionofan appropriatecontingency determination).

    Rangescouldexceedthoseshownifthereareunusualrisks.

    Alternate

    Estimate

    Names,

    Terms,

    Expressions,

    Synonyms:

    Ratio, ballpark, blue sky, seatofpants, ROM, idea study,

    prospect estimate, concession license estimate, guesstimate,

    ruleofthumb.

    Table2aClass5Estimate