1 Solway Firth Technical Feasibility Study Tidal Power; Technologies Review Solway; Stakeholder Presentation Presented by: Dr Malcolm Balls Date: 28 th October 2009

Tidal Power Technology Review

Embed Size (px)

DESCRIPTION

Tidal Power Technology Review

Citation preview

1 Solway Firth Technical Feasibility Study

Tidal Power; Technologies ReviewSolway; Stakeholder Presentation

Presented by: Dr Malcolm Balls

Date: 28th October 2009

04/24/232 Solway Firth Technical Feasibility Study2 Solway Firth Technical Feasibility Study

The Technologies

• Tidal Barrage:• Arrangement• Equipment• Mode of operation

• Tidal Lagoons:• Land connected• Isolated

• Tidal Reef• Tidal stream• Tidal Fence

04/24/233 Solway Firth Technical Feasibility Study3 Solway Firth Technical Feasibility Study

Tidal Energy Barrage

04/24/234 Solway Firth Technical Feasibility Study4 Solway Firth Technical Feasibility Study

La Rance tidal barrage, Brittany

04/24/235 Solway Firth Technical Feasibility Study5 Solway Firth Technical Feasibility Study

Arrangement

04/24/236 Solway Firth Technical Feasibility Study6 Solway Firth Technical Feasibility Study

•Equipment; TurbinesNote depth of water required for turbines.

04/24/237 Solway Firth Technical Feasibility Study7 Solway Firth Technical Feasibility Study

Equipment; Sluices

04/24/238 Solway Firth Technical Feasibility Study8 Solway Firth Technical Feasibility Study

Barrage modes of operation; Ebb-generation

04/24/239 Solway Firth Technical Feasibility Study9 Solway Firth Technical Feasibility Study

Barrage operation; Ebb-generation with pumping

04/24/2310 Solway Firth Technical Feasibility Study10 Solway Firth Technical Feasibility Study

Barrage operation; 2-way generation

04/24/2311 Solway Firth Technical Feasibility Study11 Solway Firth Technical Feasibility Study

Comparison of operating modes

04/24/2312 Solway Firth Technical Feasibility Study12 Solway Firth Technical Feasibility Study

Barrage operation; ebb-generation effect on basin water levels

04/24/2313 Solway Firth Technical Feasibility Study13 Solway Firth Technical Feasibility Study

Tidal Lagoons; Land Connected or Isolated

04/24/2314 Solway Firth Technical Feasibility Study14 Solway Firth Technical Feasibility Study

Tidal Reef – a low-head barrage arrangement.

04/24/2315 Solway Firth Technical Feasibility Study15 Solway Firth Technical Feasibility Study

Tidal Power Reefs:

• Technology unproven• Design solutions not evident for many features• Reliable estimates of energy yield not available• Large turbines required in large numbers• Operational effects appear more environmentally

acceptable (e.g. larger part of tidal range retained)

04/24/2316 Solway Firth Technical Feasibility Study16 Solway Firth Technical Feasibility Study

Tidal Stream

04/24/2317 Solway Firth Technical Feasibility Study17 Solway Firth Technical Feasibility Study

Requirements for tidal stream development

• Current velocity >circa 4m/s• Significant depth of water to submerge turbine at low water• Space to set up array of machines

Advantages:• Small scale & piecemeal development possible• Effect on tidal regime minimized

Challenges:• Turbine design and deployment as yet at prototype stage• Large numbers of machines required for substantial output

04/24/2318 Solway Firth Technical Feasibility Study18 Solway Firth Technical Feasibility Study

Tidal Fence

04/24/2319 Solway Firth Technical Feasibility Study19 Solway Firth Technical Feasibility Study

Tidal Fence

• Technology unproven• Design solutions not evident for many features• Reliable estimates for energy yield not available• Large turbines required in large numbers• Operational effects appear more environmentally

acceptable (e.g. larger part of tidal range retained)