Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
4/19/2012
1
THERMAL ENERGY STORAGE
SECTION S
WHY IS THERE INTEREST INTHERMAL ENERGY STORAGE?
Reduced peak demand costspSome utilities offer rebates and rate
incentivesReduced equipment size and cost (new)May be improved reliability due to
production and storageproduction and storageSmaller fans and pumps (colder water with
ice storage)
Section S - 2
4/19/2012
2
ECONOMIC PAYBACK TIME
Typical simple payback of 5 to 7 years (maybe 3 to 5 in some cases) for existing (maybe 3 to 5 in some cases) for existing buildings and chillers.
Recent examples from ASHRAE and others are showing the payback may be immediate to 1 – 2 years for good design in new constructionconstruction.
Section S - 3
CONVENTIONAL AIRCONDITIONING OPERATION
CAC system peaks at peak cooling timeCAC system is sized to meet peak cooling
loadCAC system may have its lowest efficiency
at the time it is needed the most
Section S - 4
4/19/2012
3
CAC OPERATION
Building Cooling Load ProfileConventional Air Conditioning (CAC)
1000
Building Load Chiller Load
250
500
750
1000
Load
(kW
)
Peak chiller load 1000 kW
0
Midnigh
t 1 2 3 4 5 6 7 8 9 10 11Noo
n 1 2 3 4 5 6 7 8 9 10 11
Time of Day
Section S - 5
OFF-PEAK AIRCONDITIONING OPERATION
CAC together with storage is used to meet peak cooling loadspeak cooling loads
Chilled water or ice is used for storage medium
Daytime peak load is reduced or eliminated
OPAC system operates at night when efficiencies are usually higher due to lower outside temperatures
Section S - 6
4/19/2012
4
OFF-PEAK AIR CONDITIONING OPERATION
The Total Daily Cooling Load (plus system losses) must be met
The Instantaneous Cooling Loads must also be met when they occur, just not directly from the chillers.
We are simply decoupling the Load (demand) from the Chiller (supply)
If we take advantage of optimal chiller If we take advantage of optimal chiller loading (sweet spot) and cooler condenser temperatures, we may gain significant efficiencies.
Section S - 7
Building Cooling Load Profile
750
1000
Building Load
Load x hours = 14,000 kWh
250
500
750
Lo
ad (
kW)
250 kW x 8hrs = 2000 kWh
750kW x 4hrs = 4000 3000 2000
0
Midn
ight 1 2 3 4 5 6 7 8 9 10 11
Noon 1 2 3 4 5 6 7 8 9 10 11
Time of Day
250 kW x 8hrs = 2000 kWh3000 kWh
4000 kWh
3000 kWh
2000 kWh
Section S - 8
4/19/2012
5
OPAC OPERATING STRATEGIES
• Load leveling– Partial shifting of AC load to off-peak hours
Chill l d l d – Chiller runs at constant load or near constant load for 24 hours per day
– Very cost effective for new construction– Less costly to purchase– Less space needed– But ~ less savings
Section S - 9
LOAD LEVELING CHILLER LOAD
CALCULATIONS
Where would we need to operate the chiller(s) in order to satisfy the building load? Peak period between 12:00 p.m. to 8 p.m.
Total kWh / Hours available to operate chillers
For the Load Leveling Strategy, the chiller will operate 24 hours per day at a load of:will operate 24 hours per day, at a load of: 14,000 kWh / 24 hours = 583.3 kW
Section S - 10
4/19/2012
6
Building Cooling Load ProfileLoad Levelling TES
1000
Building Load Load Levelling TES
Peak Chiller Load= 583.3 kWWith TES
250
500
750
Lo
ad (
kW)
Peak SavingsWith TES
P k P i d0
Midn
ight 1 2 3 4 5 6 7 8 9 10 11
Noon 1 2 3 4 5 6 7 8 9 10 11
Time of Day
Peak Period
Section S - 11
Load shifting Complete shifting of peak hour AC load to off-peak hours OPAC system must be sized to meet peak cooling load in
kWh Usually more cost effective for retrofit situations because
of large existing chiller load that can be moved mostly off peak
More costly to purchase and install Requires more space for storage tanks But ~ more savings
Section S - 12
4/19/2012
7
OPAC LOAD CALCULATIONS
Total kWh Hours / Hours available to operate chillers A peak period from noon to 8 p.m. would leave 16 hours to
generate cooling capacitygenerate cooling capacity.
For the Load Shifting Strategy, the chiller will operate at a load of:
14,000 kWh / 16 hours = 875 kW
Section S - 13
Building Cooling Load Profile
1000
Building Load Load Shifting TES
250
500
750
Lo
ad (
kW)
PeakSavings
0
Midn
ight 1 2 3 4 5 6 7 8 9 10 11
Noon 1 2 3 4 5 6 7 8 9 10 11
Time of Day
Section S - 14
4/19/2012
8
TES STORAGE MEDIA
Chilled water storage Simple ~ but large tanks needed; lots of space.
Requires 4 to 5 times the space of ice storageq p g Typical water temperatures of 4C Practical considerations for water storage tanks
Need to minimize mixing of warm returnwater with the cold water in storage
May need two tanks ~ if full capacity ofa tank is needed. If temperature stratification of tank is used the tank stratification of tank is used, the tank may need to be up to 20% bigger
Section S - 15
Ice Storage More complex tanks and auxiliary equipment needed;
more complex to maintain Ice/water requires around 20 to 30% of the space needed
for chilled water tanksfor chilled water tanks Solid ice requires around 10% of the space needed for
chilled water tanks Very low temperature water can be used ~ around 1C Can use ice harvester, ice on coil, or ice/water (slush)
Section S - 16
4/19/2012
9
PROPERTIES OF STORAGE MEDIA
Chilled water systems are typically operated in a manner to use only sensible p yheat storage and thus stores 4.2 kJ per kg of water for each C of temperature difference between the stored water and the returned water.
Ice systems are typically operated in a Ice systems are typically operated in a manner to use only latent heat associated with freezing and melting, and one kg of ice at 0C absorbs 335 kJ to become 0C water.
Section S - 17
SIZING CHILLED WATER STORAGE TANKS
Assume that chilled water is stored at 4C and is returned at the standard temperature f 12Cof 12C.
• This is an 8 ∆T for the AC system• Thus, one kg of water stores 33.6 kJ• One kWh of AC is 3600 kJ
So, to store 1 kWh you need:k f t • kg of water; or,
• litres of water; or,• cubic metres of water.
Section S - 18
4/19/2012
10
EFFICIENCY AND CAPACITY CONSIDERATION
OPAC system is less efficient at lower water temperatures ~ but night time operation is temperatures ~ but night time operation is more efficient ~ these might cancel each other
We might suffer a 10 to 15% capacity reduction because the OPAC system has less capacity at lower water temperatures
We might lose 5 to 10% of capacity because of lstorage losses
Section S - 19
HOW BIG WOULD A CHILLED WATER TANK
BE?(THEORETICALLY)
Section S - 20
4/19/2012
11
HOW BIG WOULD ANICE TANK BE?
ABOUT 10% AS BIG
Section S - 21
CONDITIONS THAT FAVOR TES
High peak demand charges
Low cost of energy used at nightLow cost of energy used at night
High on-peak loads
Low AC loads at night
Need for increased cooling system capacity
Section S - 22
4/19/2012
12
CEM REVIEW PROBLEMS1. TES systems yield large energy savings.
A) True B) False
2. Use of full storage allows use of smaller chillers than partial storage systems.
A) True B) False3. Why are utilities encouraging TES?
Section S - 23
4. Temperature stratification can occur in(A) Chilled water storage(B) Hot water storage(C) A & B(D) None of the above
5. TES for heating uses some of the following storages: 1) building mass; 2) hot water; 3) ground couple; 4) compressed air tanks; 5) rocks; and 6) propane containers. Select the right combination:right combination:
(A) 1,2,3,4 (B) 3,4,5,6(C) 1,2,3,5 (D) 2,4,5,6
Section S - 24
4/19/2012
13
6. With a load leveling TES strategy, a building manager will
(A) Not operate the chiller during peak hours(B) Essentially base load the chiller (i.e., operate
at high load most of the time)at high load most of the time)(C) Operate only during the peak times(D) Operate in the “off” season
7. A large commercial building will be retrofitted with a closed loop water to air heat pump system. Individual department meters will meter costs to
h d D d billi i ll f each department. Demand billing is a small part of the total electrical cost. Would you recommend a TES?
(A) Yes (B) No
Section S - 25
TES APPENDIX
Section S - 26
4/19/2012
14
TES CHILLED WATER TANK DFW
DFW TES DATA The DFW Airport TES tank:
• Tank fabricated and installed by CBI
• Physical dimensions: 56 ft. in height with a diameter of 138 ft.
• Storage volume: 6,000,000 gallons
• Storage capacity: 90,000 ton-hours
• Shifts over 15 MW off-peak
• Simple payback on the incremental investment was 4 years
One other interesting fact, the DFW CHW system was originally designed for a 24 degree F delta T with a leaving CHW temperature of 36 degrees F. The buoyancy of water inverts at 38 degrees F so 36 degree entering water would compromise the stratification in the TES. So, a buoyancy depressant called So Cool is used to depress the minimum buoyancy below 36 F. It has worked perfectly.
4/19/2012
15
ANOTHER STORAGE MEDIUM
There is one more storage medium that is available but it is almost never used It is available, but it is almost never used. It is Eutectic Salt.
Eutectic salt was used some in the 1970s and early 1980s for storage of heat, but its use for air conditioning is not common gtoday. But, it could be used.
Section S - 30
4/19/2012
16
Eutectic Salt Storage Expensive, high tech solution Allows use of existing 6 C chillers Typical melt range is 5 to 8 C Requires only 30 to 50% of the space needed for chilled
water tanks Requires secondary heat exchanger May be considered hazardous The salt has a useful life of about five years, and must
then be sent back and replaced
Section S - 31
STORAGE CAPABILITY OF EUTECTIC
SALTS
Eutectic salts use latent heat associated with freezing and melting but one kg of with freezing and melting, but one kg of solid eutectic salt absorbs only about 115 kJ to become liquid.
Section S - 32
4/19/2012
17
SUMMARY OF STORAGE TANK SIZINGTHESE ARE REAL WORLD, PRACTICAL NUMBERS – NOT FOR USE ON
CEM TEST
Chilled water.12 to .15 cubic metres per kWh
Eutectic salt.03 to .05 cubic metres per kWh
Ice.025 to .035 cubic metres per kWh.025 to .035 cubic metres per kWh
Section S - 33
END OF SECTION S
Section S - 34