23
Bethlehem Lutheran Church and School Schematic Design Options March 11, 2012

The Next Door Project Revised Options March 2012

Embed Size (px)

DESCRIPTION

Revised Options from March 2012 for The Next Door Project at Bethlehem Lutheran Church. This is a presentation presented at congregational meetings on March 11, 2012

Citation preview

Page 1: The Next Door Project Revised Options March 2012

Bethlehem Lutheran Church and School

Schematic Design Options

March 11, 2012

Page 2: The Next Door Project Revised Options March 2012

Existing Facilities

Vance St.

W. 20

th A

ve.

W. 22

nd A

ve.

Wadsworth Blvd.

W. 23

rd A

ve.

North

Page 3: The Next Door Project Revised Options March 2012

(Insert existing plan)

Existing

Floor Plan

Area A

Area C

Area B

North

Page 4: The Next Door Project Revised Options March 2012

Option 1

(Insert plan)

1st Floor

Page 5: The Next Door Project Revised Options March 2012

Option 1

(Insert plan)

1st Floor – School Administration

Page 6: The Next Door Project Revised Options March 2012

Option 1

(Insert plan)

1st Floor – Commons / Table

Page 7: The Next Door Project Revised Options March 2012

(Insert plan)

Option 1

2nd Floor

Page 8: The Next Door Project Revised Options March 2012

Option 1 – Pros and Cons

+ Basic Commons function

+ Improved security for School

+ Improved School Admin Location

+ Bathrooms at Church Entry

+ Gains 2 Classrooms

+ No additional debt

+ Windows remain in Kitchen

- Basic Commons, smaller, no theatrical light

- Removes Computer Lab, redistribute computers to classrooms

- Relocates Library to smaller room, less ideally located

- Lacks dedicated Cafeteria, limiting flexibility of Commons usage

- Separated Church/School Admin

- Poor access to Toilet Rooms for Gym patrons

- Lacks Life Group and other small group spaces

- Limits ELC Growth

- Limits ministry staff Office growth

- Separate Entrances

- Minimal Church reception, security

- No change at PAC for Chapel

- Music/Choir location challenges at PAC/Chapel

- Potential acoustic issues from PAC/Chapel to Sanctuary

- Access to Church Office

- (e) 2nd Floor mech. stays in Classroom

- Sanctuary mech. not included (Alt.)

- No Sacristy Access to Chapel

- No Improvement at Parlor for Coffee Shop

- Fire Sprinklers exposed, unpainted

- Add Alternate: Add ramps to improve HC/Accessibility to School

+ -

Page 9: The Next Door Project Revised Options March 2012

Option 2

1st Floor

Page 10: The Next Door Project Revised Options March 2012

Option 2

1st Floor – Chapel

Page 11: The Next Door Project Revised Options March 2012

Option 2

1st Floor – School Administration

Page 12: The Next Door Project Revised Options March 2012

Option 2

1st Floor – Commons / Table

Page 13: The Next Door Project Revised Options March 2012

(Insert plan)

Option 2

2nd Floor

Page 14: The Next Door Project Revised Options March 2012

Option 2 – Pros and Cons

+ Basic Commons Area

+ Some Commons theatrical lighting

+ Improved security for School, Church

+ Consolidated Main Entry

+ Bathrooms at Main Entry

+ Gains 3 Classrooms

+ Minimal upgrades at Parlor for Coffee Shop

+ Basic Sacristy access to Chapel

+ Some improvement at PAC for Chapel

+ Gains Cafeteria

+ Increases Commons availability

+ Better School Admin space and location

+ Better Toilet Room access for Gym and

Cafeteria

+ School Admin structured to accept future

Church Admin

+ Minor Church Admin renovation

+ Same cash flow

- Basic Commons, minimal theatrical lighting

- Additional Debt incurred (but same cash flow)

- Removes Computer Lab, redistributes computers

- Relocates Library to smaller room, less ideally

located

- Lacks Life Group and other small group spaces

- Limits ELC Growth

- Limits ministry staff Office growth

- Music/Choir location challenges at PAC/Chapel

- Potential acoustic issues from PAC/Chapel to

Sanctuary

- Access to Church Office

- (e) 2nd Floor mech. stays in Classroom

- Sanctuary mech. not included (Alt.)

- Sacristy passage impacts Nursery

- Sacristy passage impacts corner of Sanctuary seating

- Add Alternate: Add ramps to improve

HC/Accessibility to School

+ -

Page 15: The Next Door Project Revised Options March 2012

(Insert plan)

Option 3

1st Floor

Page 16: The Next Door Project Revised Options March 2012

(Insert plan)

Option 3

1st Floor - Chapel

Page 17: The Next Door Project Revised Options March 2012

(Insert plan)

Option 3

1st Floor – School Administration

Page 18: The Next Door Project Revised Options March 2012

(Insert plan)

Option 3

1st Floor – Commons / Table

Page 19: The Next Door Project Revised Options March 2012

(Insert plan)

Option 3

2nd Floor

Page 20: The Next Door Project Revised Options March 2012

(Insert plan)

Option 3

2nd Floor – Church Administration

Page 21: The Next Door Project Revised Options March 2012

Option 3 – Pros and Cons

+ Enhanced Commons with theatrical lighting

+ Renovated of Parlor for Coffee Shop / Warming

Kitchen

+ Enables enhanced security for School, Church

+ Bathrooms at Main Entry

+ Gains 3 Classrooms

+ Basic Sacristy access to Chapel

+ Gains Cafeteria

+ Increases Commons availability

+ Better School Admin space and location

+ Better Toilet Room access for Gym and Cafeteria

+ Enhanced Chapel

+ Enlarged Chapel* (requires new Sanctuary Mech.)

+ ELC Expansion

+ Bigger, Better Church Admin, closer to School Admin

+ Church Admin can expand

+ Adds Conference Room on 2nd Floor

+ Recapture ELC and Church Offices for Life Groups

+ Add Alternate: Elevator near Main Entry

- Additional Debt incurred, funding TBD

- (e) 2nd Flr Mech stays in Classroom

- Sacristy passage impacts Nursery

- Sacristy passage impacts corner of

Sanctuary seating

- Add Alternate: Sanctuary RTU required

in order to enlarge Chapel

- Add Alternate: Add ramps to improve

HC/Accessibility to School

+ -

Page 22: The Next Door Project Revised Options March 2012

Options Comparison

OPTION 3 OPTION 2 OPTION 1

+ No additional debt

- Small Commons

(220 at tables/340 in chairs)

- Lacks dedicated Cafeteria

- Limits ELC Growth

- Separate Entrances

- No change at PAC for Chapel

- No improvement at Parlor

+/- Same cash flow, added debt

Improvements over Option 1:

+ Basic, full-size Commons

(320 at tables/500 in chairs)

+ Consolidated Main Entry

+ Minimal upgrades at Parlor

+ Basic Sacristy access to Chapel

+ Min improvement at Chapel

+ Regains Cafeteria

+ Better School Admin space

+ Provides for ELC Growth

- Additional Debt, funding TBD

Improvements over Option 2:

+ Enhanced Commons

(320 at tables/500 in chairs)

+ Renovation of Parlor

+ Consolidates Church/School Admin

+ Enlarged Chapel (requires new RTU)

+ Provides Life Group spaces

+ +

Page 23: The Next Door Project Revised Options March 2012

Group Discussion