35
Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 1 of 35 September 27, 2017 USQ #16-2002-D Ownership matrix Link to Native Word file TABLE OF CONTENTS 1.0 PURPOSE AND SCOPE ................................................................................................................ 3 2.0 ENGINEERING VISION ............................................................................................................... 3 3.0 ENGINEERING MISSION ............................................................................................................ 3 4.0 GUIDING TENETS ........................................................................................................................ 3 5.0 ENGINEERING POLICY .............................................................................................................. 3 6.0 ENGINEERING ACCOUNTABILITIES ...................................................................................... 4 6.1 Design Authority................................................................................................................. 4 6.2 Specialist Technical Support............................................................................................... 4 6.3 Engineering Standards and Procedures ............................................................................... 5 6.4 Engineering Assurance and Performance Measurement .................................................... 5 6.5 Design Engineering............................................................................................................. 5 6.6 Nuclear Safety..................................................................................................................... 6 6.7 Plant and System Engineering ............................................................................................ 6 6.8 Tank Farm Projects ............................................................................................................. 6 6.9 EPC Projects Engineering ................................................................................................... 6 7.0 ENGINEERING FUNCTION ORGANIZATION ......................................................................... 6 8.0 ENGINEERING GOVERNANCE AND OVERSIGHT ................................................................ 7 9.0 ENGINEERING ROLES AND RESPONSIBILITIES .................................................................. 8 9.1 Generic Engineering Roles ................................................................................................. 8 10.0 ENGINEERING QUALIFICATION.............................................................................................. 8 10.1 Engineering Qualification Cards......................................................................................... 8 10.2 Competency Review ......................................................................................................... 10 10.3 Contracted Staff requirements .......................................................................................... 10 10.4 Qualifications for Originating Engineering Documents ................................................... 11 10.5 Delegation ......................................................................................................................... 11 10.6 Requalification Cards ....................................................................................................... 11 11.0 ENGINEERING TRAINING AND REQUIRED READING ...................................................... 12 11.1 Engineering Training ........................................................................................................ 12 11.2 TOC General Employee Core Training ............................................................................ 12 11.3 Engineering Core Training ............................................................................................... 12 11.4 Qualification Training....................................................................................................... 12 11.5 Continuing Training .......................................................................................................... 13 11.6 License/Certification......................................................................................................... 13 11.7 Required Reading ............................................................................................................. 13 12.0 DESIGN AUTHORITY ................................................................................................................ 14 12.1 Design Agency .................................................................................................................. 15 12.2 DA Delegation .................................................................................................................. 15 13.0 ENGINEERING FUNCTIONAL SUPPORT AREAS................................................................. 16 13.1 Engineering Programs....................................................................................................... 16 13.2 Design Engineering........................................................................................................... 18 13.3 Nuclear Safety................................................................................................................... 19 13.4 Production Operations Engineering .................................................................................. 20 13.5 SST Retrieval Engineering ............................................................................................... 21

TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

  • Upload
    others

  • View
    6

  • Download
    1

Embed Size (px)

Citation preview

Page 1: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

1 of 35

September 27, 2017

USQ #16-2002-D

Ownership matrix

Link to Native Word file

TABLE OF CONTENTS

1.0 PURPOSE AND SCOPE ................................................................................................................ 3 2.0 ENGINEERING VISION ............................................................................................................... 3 3.0 ENGINEERING MISSION ............................................................................................................ 3 4.0 GUIDING TENETS ........................................................................................................................ 3 5.0 ENGINEERING POLICY .............................................................................................................. 3 6.0 ENGINEERING ACCOUNTABILITIES ...................................................................................... 4

6.1 Design Authority ................................................................................................................. 4 6.2 Specialist Technical Support............................................................................................... 4 6.3 Engineering Standards and Procedures ............................................................................... 5 6.4 Engineering Assurance and Performance Measurement .................................................... 5 6.5 Design Engineering ............................................................................................................. 5 6.6 Nuclear Safety ..................................................................................................................... 6 6.7 Plant and System Engineering ............................................................................................ 6 6.8 Tank Farm Projects ............................................................................................................. 6 6.9 EPC Projects Engineering ................................................................................................... 6

7.0 ENGINEERING FUNCTION ORGANIZATION ......................................................................... 6 8.0 ENGINEERING GOVERNANCE AND OVERSIGHT ................................................................ 7 9.0 ENGINEERING ROLES AND RESPONSIBILITIES .................................................................. 8

9.1 Generic Engineering Roles ................................................................................................. 8 10.0 ENGINEERING QUALIFICATION .............................................................................................. 8

10.1 Engineering Qualification Cards......................................................................................... 8 10.2 Competency Review ......................................................................................................... 10 10.3 Contracted Staff requirements .......................................................................................... 10 10.4 Qualifications for Originating Engineering Documents ................................................... 11 10.5 Delegation ......................................................................................................................... 11 10.6 Requalification Cards ....................................................................................................... 11

11.0 ENGINEERING TRAINING AND REQUIRED READING ...................................................... 12 11.1 Engineering Training ........................................................................................................ 12 11.2 TOC General Employee Core Training ............................................................................ 12 11.3 Engineering Core Training ............................................................................................... 12 11.4 Qualification Training ....................................................................................................... 12 11.5 Continuing Training .......................................................................................................... 13 11.6 License/Certification ......................................................................................................... 13 11.7 Required Reading ............................................................................................................. 13

12.0 DESIGN AUTHORITY ................................................................................................................ 14 12.1 Design Agency .................................................................................................................. 15 12.2 DA Delegation .................................................................................................................. 15

13.0 ENGINEERING FUNCTIONAL SUPPORT AREAS ................................................................. 16 13.1 Engineering Programs ....................................................................................................... 16 13.2 Design Engineering ........................................................................................................... 18 13.3 Nuclear Safety ................................................................................................................... 19 13.4 Production Operations Engineering .................................................................................. 20 13.5 SST Retrieval Engineering ............................................................................................... 21

Page 2: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

2 of 35

September 27, 2017

13.6 Process & Control System Engineering ............................................................................ 22 13.7 Process Engineering Analysis ........................................................................................... 23 13.8 Tank Farm Projects and Tank Integrity Engineering ........................................................ 25 13.9 EPC Project Engineering .................................................................................................. 27 13.10 One System ....................................................................................................................... 28 13.11 TOC Fire Protection Program ........................................................................................... 28

14.0 DEFINITIONS .............................................................................................................................. 28 15.0 SOURCES ..................................................................................................................................... 30

15.1 Requirements .................................................................................................................... 30 15.2 References ......................................................................................................................... 30

TABLE OF FIGURES

Figure 1. WRPS Engineering Function Organization. ................................................................................. 7

TABLE OF TABLES

Table 1. Engineering Governance Committees. .......................................................................................... 7 Table 2. Design Authority Program/Services. ........................................................................................... 14 Table 3. Engineering Programs Department Programs/Services. .............................................................. 17 Table 4. Design Engineering Programs/Services. ...................................................................................... 19 Table 5. Nuclear Safety Programs / Services ............................................................................................. 20 Table 6. Process & Control System Engineering Programs/Services. ....................................................... 22

TABLE OF ATTACHMENTS

ATTACHMENT A – ENGINEERING ROLES AND QUALIFICATIONS. ............................................ 34 ATTACHMENT B - GENERIC ENGINEERING ROLES AND QUALIFICATIONS. .......................... 35

Page 3: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

3 of 35

September 27, 2017

1.0 PURPOSE AND SCOPE

This Engineering Program Management Plan (herein after referred to as the Plan) describes

Washington River Protection Solutions’ (WRPS) Engineering Functional Area arrangements,

including policies, key accountabilities, organizational structure, qualification and training,

governance and key functional support programs and services put in place to support the Tank

Operations Contract (TOC) in the safe and compliant operation and maintenance of the Tank

Farms, 242-A Evaporator, 222-S Laboratory and the Effluent Treatment Facility (ETF) and

Engineer-Procure-Construct (EPC) project execution.

TFC-CHARTER-01 provides a high-level description of the TOC organization and plans for

executing the contract scope. This Plan provides specific detail regarding WRPS’ engineering

arrangements and how they support TOC mission. Additional detail is provided by reference to

other specific program plans/documents and procedures.

2.0 ENGINEERING VISION

WRPS Engineering will endeavor to fulfill the following Vision:

WRPS Engineering will be known in the DOE complex and by our parent companies as

the “best in class” for people, processes and technology and our ability to successfully

respond to an ever changing environment by continually improving.

3.0 ENGINEERING MISSION

WRPS Engineering is committed to the following Mission:

WRPS Engineering supports the safe and efficient management, retrieval, treatment and

storage of Hanford’s radioactive and hazardous tank waste and protecting the Columbia

River through the delivery of innovative ideas implemented by dedicated people, using

efficient processes and procedures that produce clear, concise, and error free products.

4.0 GUIDING TENETS

Engineering will strive to deliver its mission incorporating the following attributes into its day to

day working:

Integrity – Doing what’s right even when no one is looking

Inquisitiveness – Ask questions and question answers

Initiative – Own the issue and propose solutions

Ingenuity – Think out of the box. New ideas for old issues.

Improvement – Reduce engineering errors through use of human performance tools

5.0 ENGINEERING POLICY

TFC-POL-07 describes WRPS’ commitment to engineering excellence which is founded upon an

integrated, technically sound, efficient, safe, and effective engineering program. This document

also sets out the expectations of the Chief Engineer with respect to disciplined conduct of

engineering.

Page 4: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

4 of 35

September 27, 2017

6.0 ENGINEERING ACCOUNTABILITIES

The accountabilities of the engineering function comprise a wide range of topical areas with a

wide range of responsibilities and authorities under each that can be logically grouped under the

following primary headings:

Design Authority

Specialist Engineering/Technical support

Engineering Standards and Procedures

Engineering Assurance and Performance management

Design Engineering

Nuclear Safety

Plant and System Engineering

Tank Farm Infrastructure Projects and Tank Integrity Engineering

EPC Project Engineering.

Each of the above are described below with the associated Functional Support Area (FSA)

programs and service capabilities described in more detail in Section 13.

6.1 Design Authority

Engineering serves as the Design Authority (DA) for the TOC with the TOC Chief Engineer

serving as the ultimate DA. The DA is the organization responsible for establishing the design

intent of facilities and SSCs and ensures that design outputs and the physical plant and equipment

accurately reflect and satisfy the design intent. The DA is responsible for the technical adequacy

of the design, and providing function and requirements input to the Design Agency, including

applicable codes, standards, and quality requirements. The DA maintains ownership of SSCs

Technical Baseline.

WRPS Engineering will normally function in the role of the DA, overseeing the Design Agency

that is responsible for performing many of the detailed design activities, particularly those

associated with design analysis, calculations, reports, drawings and specifications. Note that the

Design Agency could be the WRPS Design Engineering organization or an outside contractor.

WRPS’ DA arrangements are discussed further in section 12.

6.2 Specialist Technical Support

Engineering is accountable for the provision of specialist technical support across a wide

spectrum of engineering disciplines and specialist topical areas. This accountability includes

responsibility for establishing and maintaining relationships with parent companies and the

supply chain (including national laboratories and universities) where it is impractical to maintain

the specialist capability in house.

Specialist technical support is embedded within a number of engineering FSAs as discussed in

Section 13.

WRPS engineering maintains a listing of specialist technical support resources, referred to as

Subject Matter Experts (SMEs), under the Toolbox section of the Engineering website. The

individuals on this list are nominated and confirmed by the relevant Level 2 Engineering

Page 5: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

5 of 35

September 27, 2017

Managers (primarily Design Engineering and Engineering Programs) and approved by the Chief

Engineer. This list is periodically updated.

6.3 Engineering Standards and Procedures

Engineering is accountable for establishing and maintaining fit-for-purpose charters, plans,

processes, procedures, standards, and associated guidance documents for the effective and

efficient execution of engineering and nuclear safety work that cover the entire spectrum of

engineering accountabilities. A listing of these documents, along with the respective document

owners is maintained on the WRPS Procedures website.

6.4 Engineering Assurance and Performance Measurement

Engineering is accountable for ensuring the effective delivery of its accountabilities through a

program of periodic assessments focused on the following:

Compliance with the requirements of the TOC contract

Compliance with consensus codes and standards

Effective implementation of engineering processes and procedures

Effective compliance with engineering and other functional processes, procedures, and

requirements.

Engineering inputs to the annual company-wide Integrated Assessment Schedule and is

responsible for performing the planned assessments. Engineering actively participates in the

Management Observation Program (MOP) including supporting assessments performed by other

organizations.

Engineering is also responsible for monitoring its performance in the delivery of its

accountabilities via the measurement of key performance indicators (KPIs) that are tracked,

reported, reviewed, and trended by the engineering management team. Company level and

Engineering level KPIs are periodically reviewed to inform the need for intervention and/or

improvement initiatives.

6.5 Design Engineering

Engineering is accountable for the provision of the design engineering services needed to support

ongoing operations and project delivery including plant modifications, minor tasks and small

projects. This accountability includes responsibility for establishing and maintaining

relationships with the supply chain to augment WRPS capabilities when it is impractical or

inefficient to maintain the required design capability in house. Aligned with this accountability is

the responsibility for establishing and maintaining oversight arrangements for procured design

services.

Key aspects of the programs that fall within the Design Engineering accountability are described

in Section 13.2.

Page 6: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

6 of 35

September 27, 2017

6.6 Nuclear Safety

Engineering is accountable for providing a nuclear safety engineering capability for effectively

implementing 10CFR830, Subpart B, Safety Basis Requirements and referenced DOE directives

and technical standards, and managing the full suite of safety basis documents, the USQ process,

and the Nuclear Criticality Safety Program for the TOC in compliance with DOE-STD-1186,

DOE STD-3009 and TFC-PLN-02. (15.1.1, 15.1.4)

Key aspects of the programs that fall within the Nuclear Safety accountability are described in

Section 13.3.

6.7 Plant and System Engineering

Engineering is accountable for providing ongoing effective and timely support to Operations and

Maintenance and waste tank retrievals including the management of engineering activities and

programs that ensure safe, reliable, predictable, and compliant operation and maintenance of plant

and equipment. WRPS program elements that fall within this accountability include:

Production Operations Engineering (See Section 13.4)

SST Retrieval Engineering (See Section 13.5)

Process and Control Systems Engineering (See Section 13.6)

Process Engineering Analysis (See Section 13.7)

TOC System Engineering Program. (See Section 13.4.1) (15.1.4)

6.8 Tank Farm Projects

Engineering is accountable for providing effective and timely engineering support to

infrastructure projects that fall within the scope of the Tank Farm Projects (TFP) Organization,

focusing on the safe and compliant execution of projects needed to support the short and long-

term TOC mission. TFP oversees design, construction, testing and turnover of field project

activities.

Key aspects of the programs that fall within this accountability are described in Section 13.8.

6.9 EPC Projects Engineering

Engineering is accountable for providing effective and efficient engineering support to projects

that fall within the scope of the EPC Project Execution organization. The mission of the EPC

organization is to execute Capital Line Item Projects for the TOC. EPC projects are involved in

the design, construction and commissioning of new facilities for the processing, storage and

disposition of nuclear waste. (15.1.3)

Key aspects that fall within this accountability are described in Section 13.9.

7.0 ENGINEERING FUNCTION ORGANIZATION

The organization of the Engineering Function is shown graphically in Figure 1 below. It has been

structured to support the effective implementation of the Engineering Policy, delivery of the

engineering accountabilities described above, and to align with other WRPS programs and

functions.

Page 7: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

7 of 35

September 27, 2017

Figure 1. WRPS Engineering Function Organization.

8.0 ENGINEERING GOVERNANCE AND OVERSIGHT

Engineering has established a number of governance and oversight committees to support the

discharge of its accountabilities and to enhance the efficient operation of the function. Table 1

below provides a list of these and the respective charters where detailed information can be

found. (15.1.1)

Table 1. Engineering Governance Committees.

Committee Reference Charter

Safety Basis Change Review Board TFC-CHARTER-33

Waste Transfer Confinement Review Board TFC-CHARTER-37

Plant Installed Change Control Board TFC-CHARTER-55

Field Modification Control Board TFC-CHARTER-56

Tank Integrity Expert Panel TFC-CHARTER-67

TOC Chief Engineer

SST

Retrievals

Engineering

Nuclear

Safety

Tank Farm

Projects and

Tank Integrity

Engineering

Production

Operations

Engineering

Design

Engineering

Engineering

Programs

Process

Engineering

Analysis

Process and

Control

System

Engineering

Low Activity

Waste

Pretreatment

(LAWPS)

Project

Engineering

TOC Deputy Chief

Engineer

222-S

Engineering

Manager

ETF

Engineering

Manager

242-A

Engineering

Manager

EPC

Engineering

Manager

FUTURE

PROJETCS

Page 8: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

8 of 35

September 27, 2017

9.0 ENGINEERING ROLES AND RESPONSIBILITIES

Primary roles within the engineering function have been determined and the associated role,

responsibility, accountability, and authority (R2A2) for these has been documented in a suite of

R2A2 documents. Attachment A of this Plan provides a list of the primary engineering roles with

reference to the respective R2A2 and associated Qualification Card (where applicable).

NOTE: Not all engineering function roles have an associated R2A2 and/or a Qualification Card.

9.1 Generic Engineering Roles

Attachment B of this plan lists a number of generic engineering roles that are referred to

throughout the WRPS procedure suite. The individuals associated with these roles may have any

number of job and/or working titles depending upon their assignment and facility. These roles do

not have their own Qualification Card or R2A2 as the scope of these roles and associated

responsibilities are procedure specific. The general responsibilities and required qualifications

are as shown in Attachment B.

10.0 ENGINEERING QUALIFICATION (15.1.5)

Engineering qualification is defined as the education, experience, training and any special

requirements an individual needs to satisfy to perform the assigned responsibilities for a given

role safely, effectively and efficiently. Level 2 and 3 engineering managers are responsible for

determining the level of training and qualification and ensuring their staff are assigned and

complete all requisite training and qualification activity for the assigned role.

Engineering qualification is established in one of two ways:

a. Via the completion of a Qualification Card as described in Section 10.1

or

b. Via a Competency Review as described in Section 10.2

10.1 Engineering Qualification Cards

Engineering is responsible for determining the need for and the technical content of engineering

related Qualification Cards. The cards themselves are issued and controlled by the WRPS

Training department in accordance with TFC-PLN-61. The management of the qualification card

process and general qualification card requirements are described in TFC-BSM-TQ_IMP-C-02.

Attachment A of this Plan lists key engineering roles that require a Qualification Card and

periodic requalification. A complete listing of current engineering Qualification and

Requalification Cards can be found on the WRPS Training website.

With the approval of the Chief Engineer, WRPS staff newly hired or newly appointed to a role

with an associated Qualification Card can perform the duties of the role without prior

qualification via the Qualification Card process providing they undergo a competency review,

work under the direction of a qualified person and do not exercise final approval authority during

the period they are completing the Qualification Card requirements. This period should not

Page 9: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

9 of 35

September 27, 2017

exceed 12 months. Individuals that fall in this category are typically listed on the Engineering

Signature Authority List with an asterisk (*) by their name.

10.1.1 Engineering Technical Staff Qualification Card

WRPS qualification requirements for personnel serving in “Technical Staff” roles as used in DOE

O 426.2, are described in TFC-BSM-TQ-STD-01.

Engineering Technical Staff Qualification, which is a requirement for most (but not all) technical

engineering roles, entitles individuals to perform most routine engineering duties including

reviewing, checking and approving engineering information within their area of expertise and as

prescribed within applicable procedures.

Many engineering roles require additional training and/or qualification beyond Engineering

Technical Staff qualification, in particular those associated with high-hazard facilities and

processes and/or technical specialties. As noted in Section 10.0 above, Level 2 and 3 engineering

managers are responsible for determining what, if any, additional special or facility-specific

training is required beyond that required for Engineering Technical Staff qualification.

At the discretion of the Level 2 Engineering Manager responsible for the specific facility/area of

scope, Engineering Technical Staff Qualification also allows individuals to serve as an

Engineering Manager as described in WRPS procedures and as indicated in Attachment B of this

Plan. Note that Engineering Manager in this context should not be confused with the Engineering

Technical Manager qualification discussed in section 10.1.3.

Engineering Technical Staff qualification and requalification requirements can be found in

Qualification Card #350850 and #357850 respectively.

10.1.2 Design Authority Qualification Card

DA qualification is a requirement for nomination and acceptance of DA delegation for TOC SSCs

as discussed in Section 12 of this Plan. Engineering Technical Staff qualification is a prerequisite

to the DA qualification.

NOTE: Once qualified, a DA does not have to repeat the DA Qualification Card process upon a

change in assignment or delegation of DA for a different SSC providing, where applicable, an

appropriate turnover has been made between the outgoing and incoming DA. In all cases, Level

2 Engineering Managers confirm an individual’s readiness and the delegation of DA for a given

SSC via the Design Authority Delegation Table approved by the Chief Engineer.

Design Authority qualification requirements can be found in Qualification Card #350832.

10.1.3 Engineering Technical Manager Qualification Card

WRPS has determined Engineering Technical Manager Qualification, as used in DOE O 426.2, is

a requirement for Level 2 and Level 3 Engineering Managers. Engineering Technical Manager

Qualification is available to other engineering managers but is not a requirement.

Engineering Technical Manager Qualification requirements can be found in Qualification Card

#350848.

Page 10: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

10 of 35

September 27, 2017

10.1.4 Other Engineering Qualification Cards

WRPS has determined the need for other qualifications associated with performing certain

specialized engineering roles and technical support activities. Examples of these qualifications

are listed on Attachment A of this Plan.

Refer to the WRPS Training website for a complete listing of TOC engineering-related

qualifications.

10.2 Competency Review

Individuals serving in roles which do not have a Qualification Card requirement can be qualified

via a Competency Review.

Where an R2A2 has been created, the Competency Review process comprises line manager

review of the individual’s education, training, and experience against the requirements articulated

in the R2A2. Formal documentation of this review is not required provided evidence can be

produced in the future if necessary. Note that this evidence is typically documented in staff

resumes, training records and in information held by Human Resources (e.g., employment

application, background checks, performance reviews, etc.) gathered as part of the hiring and

advancement process.

For engineering roles which do not have an associated Qualification Card or an R2A2, individual

competency is confirmed by line management using their knowledge of the education, training,

and experience required for the assigned role against the credentials of the individual. Formal

documentation of this review is not required. Note that evidence of competency is typically

documented in staff resumes, training records, and in information held by Human Resources (e.g.,

employment application, background checks, performance reviews, etc.) gathered as part of the

hiring and advancement process.

10.3 Contracted Staff requirements

Contracted staff refers to individuals engaged to support WRPS engineering for specific tasks

based on education, job experience, specific Hanford experience or other technical skills on a

staff augmentation (e.g., Blanket Master Agreement (BMA)) or parent company reachback (ROS)

basis.

Contracted staff engaged to support WRPS engineering are qualified in the same manner as

WRPS staff with the following exceptions:

Contracted staff engaged on a short term basis (nominally less than 12 months) in a role

that would normally require a Qualification Card can perform the associated duties

without qualification via the Qualification Card process providing they undergo a

competency review, work under the direction of a qualified person and do not exercise

final approval authority.

Formatted: Keep with next

Page 11: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

11 of 35

September 27, 2017

Contracted staff engaged to support WRPS on a short term basis are not required to

complete the TOC Engineering Core training Option (#3472) as discussed in section 11.3

below.

While the verification of required contracted staff credentials and experience is typically the

accountability of the individual’s employer in line with WRPS procurement requirements, the

WRPS hiring manager is responsible for satisfying themselves that contracted staff are competent

to perform assigned tasks. This could involve requesting the supplier to provide evidence of their

employee’s education and experience.

Contracted engineering and other technical staff working off-site for external suppliers on

managed task or other scoped work (i.e. not in a staff augmentation capacity) are not required to

maintain WRPS qualification.

10.4 Qualifications for Originating Engineering Documents

Engineering document Originators are not required to possess any specific qualification provided

the document is subject to review and approval by qualified personnel. Where engineering

documents are prepared by originators who are not Engineering Technical Staff qualified, the

reviewer and approver of the document retain full responsibility for the technical adequacy,

document quality and ensuring compliance with requirements.

See TFC-ENG-DESIGN-C-25 for additional requirements.

For Engineering Drawings prepared in accordance with TFC-ENG-DESIGN-C-09, the term

“Drafter” is used in place of Originator. There is no specific qualification required to originate or

modify a drawing as “Drafter.”

10.5 Delegation

The delegation of authority to perform a qualified engineering role can only be made to an

individual who is qualified to perform the delegated role and who is authorized for that area of

scope.

10.6 Requalification Cards

After initial qualification, some engineering roles require requalification via periodic completion

of a Requalification Card. Attachment A of this Plan indicates which engineering roles require

requalification.

Staff that maintain Qualifications Cards that do not require requalification but that have

Engineering Technical Staff qualification as a prerequisite will be required to requalify as

Engineering Technical Staff on a 2-year basis.

Page 12: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

12 of 35

September 27, 2017

11.0 ENGINEERING TRAINING AND REQUIRED READING

11.1 Engineering Training (15.1.5)

To ensure compliance with TOC requirements and to maintain a competent cadre of engineering

professionals, WRPS uses the Systematic Approach to Training (SAT), incorporating a graded

approach (as required by DOE O 426.2) to determine engineering staff training requirements.

The graded approach considers the hazards involved, the associated risks and the importance of

the role to achieving the mission to determine the knowledge and/or skills to be trained.

Specific training requirements for engineering roles have been determined and a suite of Training

Program Options have been developed that can be assigned to an individual’s Training Plan in the

Enterprise Learning Management (ELM) system. Each Training Program Option contains a

number of individual training courses, and, in the case of Qualification Card-related Option set,

the course number of the Qualification Card itself.

Line managers are responsible for creating Training Plans for their new employees and modifying

Training Plans for their assigned staff when requirements change using the Training Selection

Form process to ensure that employee training profiles are aligned with their job responsibilities.

11.2 TOC General Employee Core Training

General Employee Core (Training Option 3255) applies to all WRPS staff and covers the

prerequisites necessary to work on the TOC and to enter Hanford site boundaries (e.g., HGET

[Hanford General-Employee Training], etcetc.).

11.3 Engineering Core Training

TOC Engineering Core Training (Training Option 3472) applies to all WRPS engineering staff

and covers general knowledge of Tank Farms and associated key processes and programs.

Completion of this training ensures a high-level understanding of key TOC facilities and

operations, the WRPS organization, human performance improvement and conduct of operations

expectations. Engineering Core Training is a prerequisite to the Engineering Technical Staff

Qualification Card discussed in Section 10.1.1 of this Plan. (15.1.2)

NOTE: This training is not required for subcontracted staff engaged for short duration tasks as

discussed in Section 10.3.

11.4 Qualification Training

Training required in connection with a Qualification Card for an Engineering role is specified in

the respective Training Program Option(s) found in the ELM system.

Page 13: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

13 of 35

September 27, 2017

11.5 Continuing Training

WRPS encourages continuing training for all staff as a way of satisfying management

expectations that staff maintain proficiency within their discipline. Continuing training is

required for Engineering Technical Staff qualified personnel with the goal of ensuring these staff

maintain and improve their skills, and are cognizant of nuclear facility physical changes,

procedural modifications, changes to DOE and regulatory requirements, and lessons learned from

industry and facility-specific operating experience.

Engineering Technical Staff requalification (Requalification Card #357850) requires a total of 30

hours (nominally 15 hours per year) of documented Continuing Training be completed over the

24 months following initial qualification or requalification. Continuing Training may comprise a

combination of the following:

Documented Self-Study

Completion of Required Reading (see Section 11.7 below)

Staying up to date with procedure changes

Other study, research, reading, etc. that is relevant to the role, may include

technical, ethical, or managerial content.

Attending Seminars. (e.g., Engineering Brownbags, internal or external technical or

professional presentations made at meetings, conventions, or conferences)

Successful completion of in-house training (including CBT)

Successful completion of professional Continuing Education Units (CEUs)

Successful completion of College Credits

Authoring published papers or articles

Participation in DOE sponsored technical activities e.g., EFCOG

Membership and Participation in Technical or Professional Organizations.

Continuing Training is documented in the Engineering Training Database. Line Managers are

responsible for periodically reviewing the Database to confirm applicability, successful

completion and credit claimed.

11.6 License/Certification

WRPS engineering professionals are encouraged to obtain and maintain a Professional License

(e.g., Registered Professional Engineer, Architect, etc.) where applicable and available. WRPS

reimburses the costs of this activity in line with the guidelines found in TFC-BSM-AC-C-02.

11.7 Required Reading

The required reading process described in TFC-OPS-OPER-C-33 is the formal method WRPS

uses to designate documents that are required to be read, the personnel who are required to read

them, and the date by which they are required to be read. Engineering makes use of required

reading as an essential element of initial and continuing training and qualification to ensure staff

are made aware of changes to key processes and procedures and technical documents.

Page 14: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

14 of 35

September 27, 2017

12.0 DESIGN AUTHORITY

Engineering Function accountability for TOC DA is discussed in section 6.1. Some of the key

tenets of WRPS’ DA program are as follows:

SSCs in nuclear facilities shall be under the oversight and technical ownership of a DA at

all times

DA responsibility is delegated from the Chief Engineer to the lowest practical level in the

Engineering Organization

The DA is responsible for maintaining the design intent of assigned SSCs from project

initiation through decommissioning

A single DA is assigned for a defined scope (two individuals should not share DA

responsibility for the same scope)

DA approval is required for changes or modifications to the technical baseline within the

scope of the assigned system

Transfer of DA is accepted by the receiving DA and shall include a turnover briefing on

system status, open items, and issues.

Level 2 Engineering Managers confirm an individual’s readiness and the delegation of

DA for a given SSC via the Design Authority Delegation Table approved by the Chief

Engineer.

Listed in Table 2 are some of the key DA-related programs and activities managed or supported

by Engineering with the reference of the associated plan or implementing document.

Table 2. Design Authority Program/Services.

Program Reference Plan/Procedure

Configuration Management Program TFC-PLN-23

Requirements Management TFC-PLN-100

Technical Baseline Management HNF-1901

TFC-ENG-STD-46

System Design Descriptions TFC-ENG-DESIGN-P-07

Code of Record TFC-ENG-DESIGN-C-57

Page 15: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

15 of 35

September 27, 2017

12.1 Design Agency

The Design Agency is the organization responsible for performing the design activities,

particularly those associated with design analysis, calculations, reports, drawings and

specifications, with the oversight of the DA. The Design Agency implements the design aspects

of the project functional specification and other design inputs provided by the DA. The Design

Agency prepares and issues design output documents and maintains their alignment with the

Functional Specification and other design input requirements. The Design Agent is responsible

for delivering the required design outputs, ensuring the content, format, technical completeness

and quality meet the requirements specified by the DA.

12.2 DA Delegation

DA is delegated by the Chief Engineer to qualified personnel within the engineering organization,

including those deployed or matrixed to project groups. Engineers delegated DA responsibility

are accountable to the Chief Engineer for maintaining DA qualification and performing the DA

role within the scope of the delegation including providing appropriate coverage if needed in the

event of absence.

The Chief Engineer has authorized Level 2 Engineering Managers to delegate DA for SSCs

within the scope of their respective support areas.

DA delegation is documented in the Design Authority Delegation Table which is updated

periodically and published to the WRPS Engineering website.

12.2.1 DA Delegation for Operating Systems

DA for operating SSCs is delegated to an individual assigned to and directly supporting the

respective line organization (e.g., Production Operations Engineering or SST Retrieval

Engineering), normally the Cognizant System Engineer (CSE) where one is assigned. The scope

of the delegation is usually a single system, but can also be a part of a large system or a

combination of multiple SSCs.

12.2.2 DA Delegation for Projects/Modifications

DA delegation for facility modifications and associated projects is determined on a case-by-case

basis and confirmed by the respective Level 2 Engineering Manager. Generally the approach to

DA delegation is as follows:

For minor modifications to an existing system or facility, the assigned DA (e.g., CSE,

Support Engineer) for the affected systems typically continues in the role of DA through

modification completion.

For modifications to existing systems/facilities that require significant time to design or a

significant outage to install, DA responsibility can remain with the assigned operations

DA or be delegated to the DA-qualified Project Engineer responsible for the design

modification.

Page 16: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

16 of 35

September 27, 2017

For new facilities and new builds, where there are minimal interface points with existing

operating facilities, DA is delegated to a specific Project Engineer or Project Engineering

Manager who serves through the design phase and typically until commissioning is

completed and the project is turned over to Operations.

12.2.3 DA Delegation for EPC Projects

DA delegation for the EPC organization is discussed in Section 13.9.1.

13.0 ENGINEERING FUNCTIONAL SUPPORT AREAS

The sections below provide additional information on key engineering programs and services

supporting the delivery of the engineering accountabilities discussed in Section 6.

13.1 Engineering Programs

The Engineering Programs is responsible for a number of key cross-functional responsibilities

including:

Maintaining the Engineering Discipline Lead (EDL) capability

Leading the administration of engineering processes and procedures

Leading the administration of TOC equipment identification and associated databases

(see TFC-ENG-FACSUUP-C-23)

Leading the administration of the engineering performance assurance program, including

engineering KPIs and input to monthly award fee Special Emphasis Area (SEA) reporting

Leading the administration of the engineering assessment program

Leading the administration and development of the SmartPlant® Foundation® (SPF)

capability

Serving as the primary WRPS interface with the DNFSB.

Listed in Table 3 are some of the key programs managed or supported by Engineering Programs

and the reference of the associated plan and/or implementing procedure.

Page 17: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

17 of 35

September 27, 2017

Table 3. Engineering Programs Department Programs/Services.

Program/Services Reference Plan/Procedure

Welding

Hoisting and Rigging TFC-ENG-FACSUP-C-25

Structural integrity verification of lifting points TFC-ENG-DESIGN-D-37

Double-Shell Tank (DST) Dome Survey Program RPP-25782

Tank Dome Loading Control TFC-PLN-142

TFC-ENG-FACSUP-C-10

Engineering Processes and Procedures TFC-BSM-AD-D-01

Engineering Codes and Standards TFC-ENG-DESIGN-D-13.2

Engineering Assessments TFC-ENG-ADMIN-D-07

Engineering Performance Measurement See Section 13.1.3

Configuration Management Plan TFC-PLN-23

Engineering Equipment Identification and Data

Management

TFC-ENG-FACSUP-C-23

Post-Natural Phenomena Hazard Assessment (15.1.4) TFC-ENG-DESIGN-C-30

Flammable Gas Ignition Source Control TFC-ENG-FACSUP-P-17

TFC-ENG-STD-13

Defense Nuclear Facilities Safety Board Interface TFC-ENG-ADMIN-C-16

Design and Installations for Potentially Flammable

Atmospheres

TFC-ENG-STD-45

13.1.1 Engineering Discipline Leads

Engineering has established Engineering Discipline Leads (EDLs) to serve as the WRPS

authority for the identification and interpretation of discipline engineering related requirements

and resolution of associated technical issues in the following areas:

Mechanical

Ventilation

Electrical

Civil/Structural.

13.1.2 Engineering Processes and Procedures

Although responsibility for engineering processes and procedures lies with a number of

individuals in a number of Functional Support Areas, overall responsibility for the organization

and administration of Engineering standards and procedures is maintained within Engineering

Programs. These responsibilities include ensuring the development, maintenance and ongoing

improvement of a comprehensive suite of processes, procedures and standards that govern the

conduct of engineering.

Page 18: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

18 of 35

September 27, 2017

13.1.3 Performance Assurance

Engineering Programs has the lead for the Engineering Function’s performance assurance

arrangements including the following activities:

Develop, maintain, status and report on Key Performance Indicators (KPIs or PIs)

including monthly reviews.

Lead the development of annual Engineering SEA award fee objectives, statusing, and

reporting on Engineering SEA performance and organizing monthly reviews.

Track, trend, analyze, and report on corrective action management performance,

verifying timely completion of corrective actions using the PER and Electronic Suspense

Tracking and Routing System (E-STARS) systems.

13.2 Design Engineering

Design Engineering provides in-house design engineering support to Production Operations, SST

Retrievals and Tank Farm Projects. It is responsible for oversight of design execution and change

control and drawing configuration control for the TOC and owns the associated procedures.

Design Engineering is also responsible for Procurement Engineering and supporting

implementation of the Commercial Grade Dedication (CGD) process. Design Engineering also

provides the following:

Technical leadership in the areas of mechanical, electrical, civil/structural design

engineering services

Technical leadership in computer-aided design (CAD) and drawing/CAD file access

control

Design reviews of externally generated designs

Review of all Safety Significant items, materials, and services procurements

Human Factors in design safety management program

Listed below in Table 4 are some of the key Design Engineering program elements and the

reference of the associated plan and/or implementing procedure.

Page 19: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

19 of 35

September 27, 2017

Table 4. Design Engineering Programs/Services.

Program/Services Reference Plan/Procedure

Engineering Design Program TFC-PLN-136

TFC-ENG-DESIGN-D-50

Technical Reviews TFC-ENG-DESIGN-C-52

TFC-ENG-DESIGN-P-53

Design Checking and Verification TFC-ENG-DESIGN-P-17

TFC-ENG-DESIGN-P-54

Engineering Change Control TFC-ENG-DESIGN-C-06

TFC-ENG-DESIGN-C-61

TFC-ENG-DESIGN-C-67

Design Subcontract Deliverable Review TFC-ENG-DESIGN-C-55

Commercial Grade Dedication TFC-ENG-DESIGN-C-15

TFC-ENG-DESIGN-C-48

TFC-ENG-DESIGN-C-65

Human Factors in Design TFC-PLN-09

TFC-ENG-DESIGN-D-29

TFC-ENG-STD-01

13.3 Nuclear Safety (15.1.1, 15.1.2, 15.1.4)

Nuclear Safety provides nuclear safety support for the tank farms, the 242-A Evaporator, and the

222-S Laboratory, and has the responsibility to:

Develop and maintain nuclear safety policies, procedures, and standards

Administer the USQ process and the USQ qualification requirements

Communicate with DOE on the project safety basis approval needs and priorities

Manage the interface with ORP on safety basis and USQ matters

Develop and maintain safety analysis methods and procedures, including consequence

analysis and frequency determination

Administer the control selection process and prepare safety basis change packages

Maintain the Nuclear Safety-related Qualifications program

Provide safety basis user services to line management, including overall day-to-day

nuclear safety support and USQ reviews. This support includes developing safety basis

amendments, justifications for continuing operations, and DSA Annual Updates, , and

managing the Tank Farms Operations Administrative Control Manual (HNF-IP-1266)

Page 20: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

20 of 35

September 27, 2017

Manage the PrHA process, including facilitating the workshops and issuing the Process

hazard Analysis (PrHA) reports for new or modified equipment/operations

Provide nuclear criticality analyses and oversight of TOC activities and processes.

Listed below in Table 5 are the key elements of the nuclear safety program and the reference of

the associated plan and/or implementing procedure.

Table 5. Nuclear Safety Programs / Services

Program/Services Reference Plan/Procedure

Maintenance of the Documented Safety Analysis

(DSA) and Technical Safety Requirements (TSR)

for TOC facilities

TFC-ENG-SB-C-01

Development of safety basis documents for new

(or major modifications to existing) Hazard

Category 2 and 3 facilities

TFC-ENG-SB-C-06

Management of the Process Hazard Analysis

(PrHA) process1

TFC-ENG-DESIGN-C-47

Management of the USQ process TFC-ENG-SB-C-03

Management of the Criticality Safety Program TFC-PLN-49

1 Note that the PrHA process develops the hazard analysis that supports the DSAs and also

defines the control selection process for safety-significant SSCs and TSRs.

13.4 Production Operations Engineering

Production Operations Engineering provides a variety of engineering services in support of the

operation and maintenance of TOC facilities and ensuring proper implementation of engineering

requirements. These include:

Developing inputs, assumptions, design criteria, Engineering Change Notices, work

package reviews, and technical support for procurement associated with tank farm facility

modifications

Administrating the System Engineering program and providing Cognizant System

Engineering (CSE) and Shift Technical Engineer (STE) support to facilities for vital

safety systems or other systems.

Providing resident waste transfer and characterization technical expertise and facility

knowledge, support of operability determinations, performance monitoring program,

centralized resolution of Structures, Systems, and Components (SSC) performance

problems, and providing system-specific technical support

Providing Maintenance engineering support

Supporting work package preparation for Production Operations tasks

Developing safe waste management strategies for DSTs that balances the needs of the

retrieval projects and the future Waste Treatment Plant

Page 21: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

21 of 35

September 27, 2017

Identifying SSC improvements and recommending enhancements to operations and

engineering management.

13.4.1 System Engineer Program (15.1.4)

Production Operations Engineering oversees the implementation of the TOC’s System

Engineering (SE) Program in accordance with the requirements of DOE-O-420.1C The TOC SE

Program applies to active safety significant SSCs as defined in the facility’s DOE-approved

safety basis, and applies to other active systems that perform important defense-in-depth

functions, as determined by facility line management.

NOTE: The TOC has no Hazard Category 1 facilities or Safety Class SSCs.

The WRPS SE Program is described in TFC-ENG-FACSUP-P-01 where the process for the

identification of systems to be covered by the SE Program and the assignments of the identified

systems is described. A listing of the TOC systems covered by the SE Program can be found in

TFC-ENG-STD-43.

Cognizant System Engineers (CSEs) are deployed within the Production Operations and SST

Retrievals organizations.

13.5 SST Retrieval Engineering

SST Retrieval Engineering provides a variety of engineering services in support of SST and DST

retrievals and ensures proper implementation of engineering requirements from the TOC

Engineering organization. These include:

Providing the resources needed to support the Integrated Project Teams (IPTs) involved

in the designing, building, testing, and operation of SST and DST waste retrieval systems

for delivery of waste to Production Operations (and other appropriate waste treatment and

disposal options).

Supporting the retrieval of waste in accordance with environmental, waste management

regulations, and compliance agreements.

Implementing required Cognizant System Engineering and Design Authority

arrangements within SST Retrieval projects for safety systems or other systems including

routine walk-downs and system health reports. Note that the administration of the

System Engineering program including associated processes and procedures falls within

the scope of Production Operations Engineering (See Section 13.4.1).

Developing project design criteria, verifying that projects meet the criteria, and being

accountable for the technical quality of engineering work

Page 22: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

22 of 35

September 27, 2017

Providing resident waste transfer and characterization technical expertise and facility

knowledge, support of operability determinations, performance monitoring program,

centralized resolution of SSC performance problems, and system-specific technical

support

Overseeing the Temporary Waste Transfer Line Life-Cycle Management Program for

monitoring and managing the life cycle of Hose-In-Hose Transfer Lines (HIHTL)

consistent with direction from the Washington State Department of Ecology

(TFC-PLN-68).

13.6 Process & Control System Engineering

Process & Control System (P&CS) Engineering is responsible for establishing the vision,

direction and the strategic plan for Operational Technology (OT) in support of Industrial Control

Systems (ICS) in the TOC. P&CS Engineering is also responsible for design, development and

day-to-day oversight of process control computer systems, process network infrastructure and

process software automation and applications used to support the TOC mission.

Listed below in Table 6 are the key elements of the P&CS program and the reference of the

associated plan and/or implementing procedure.

Table 6. Process & Control System Engineering Programs/Services.

Program/Services Reference Plan/Procedure

Strategic Plan for Process Automation

and Information Management

TFC-PLN-118

Process and Control System Standards TFC-ENG-STD-23

TFC-ENG-STD-36

TFC-ENG-STD-40

Plant Installed Change Control Board TFC-CHARTER-55

Plant Installed Software Engineering and

Software Configuration Management

TFC-ENG-DESIGN-P-12

TFC-ENG-DESIGN-P-59

TFC-ENG-DESIGN-D-12.1

Safety Instrumented Systems TFC-PLN-138

TFC-ENG-DESIGN-P-43

TFC-ENG-DESIGN-P-44

P&CS Engineering provides the following key engineering services and ensures proper

implementation of engineering requirements:

Provides primary software, controls, and instrumentation engineering support for

operation and maintenance field work activities associated with ICS, plant installed

software, and instrumentation, including related systems and support functions such as

operator interface stations, field instrumentation, and other process computing systems.

Provides primary engineering support for design and development to tank farm projects

and field work activities associated with ICS control, plant installed software, and

instrumentation, including process computing systems, ICS networks, and wireless

infrastructure.

Page 23: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

23 of 35

September 27, 2017

Maintains compliance with TOC ICS cyber security procedures as applicable to

production systems in Tank Farms, ETF, Portable Exhausters, 222-S HVAC and 242-A

Evaporator control systems.

Ensures Software Quality Assurance process implementation and maintenance is in

compliance with TOC procedures.

Provides Engineering Change Notices, work package reviews, and technical support for

Production Operations, Tank Farm Projects, and Retrieval Operations

Responsible for ownership of software configuration management ICS for plant installed

software system

Serves as Design Authority and responsible for ownership of assigned TOC process and

control systems, including DSA, TSR, and environmental compliance.

Performs Cognizant System Engineering duties for assigned TOC process and control

systems including monitoring, trending, system health.

Provides primary engineering support for automation systems obsolescence planning and

upgrade strategy.

Identifies SSC improvements and recommending enhancements to operations and

engineering management.

13.7 Process Engineering Analysis

Process Engineering Analysis (PEA) supports safe and compliant TOC operations through:

Providing technical integration among Process Engineering, Tank Waste

Characterization, and Mission Analysis Engineering with One System and Technology

Development managers and WRPS Operations managers.

Evaluating Production Operations and Retrieval activities to ensure consistency with the

River Protection Project (RPP) System Plan and comply with Safety Basis,

Environmental and Operational requirements.

Providing process leadership to Production Operations to plan waste transfers, retrievals

and evaporator campaigns.

Providing process leadership to other areas of the company and special task teams in

support of mission objectives.

PEA capabilities are organized under four focus areas, each of which is discussed in the

paragraphs below.

Page 24: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

24 of 35

September 27, 2017

13.7.1 Waste Tank Chemistry Control

Waste tank chemistry control is required to ensure that Double Shell Tank (DST) waste chemistry

is maintained within the limits specified in OSD-T-151-00007 to minimize corrosion in the

DST’s to ensure these assets are operational for the life of the RPP mission (RPP 7795).

Key activities performed in support of this service are:

Compilation (annually) of an approved database of measured and process knowledge-

based waste compositions related to the chemistry control limits, including waste layering

Evaluation of future waste compositions from predictive empirical equations or

mechanistic models to determine the likelihood for waste to become out-of-specification

Identification of preventive measures (e.g., caustic additions) to ensure waste remains

within Operational Specification Document (OSD) limits, including definition of the

waste sample types needed

Maintenance and improvement of the technical basis for waste characteristic related

safety basis controls (e.g., Buoyant Displacement Gas Release Event (BDGRE)

evaluation criteria).

13.7.2 Tank Waste Inventory and Characterization

Tank waste inventory and characterization is required to support safety basis compliance per TSR

Key Element 5.9.4, regulatory compliance including but not limited to the Tri-Party Agreement

and Resource Conservation and Recovery Act requirements, contractual obligations, operations

and maintenance needs, and waste disposal.

Key activities performed in support of this responsibility include:

Preparing data quality objectives (DQO) that establish performance or acceptance criteria

and that serve as the basis for designing a plan for data collection leading to efficient and

effective expenditure of resources.

Sampling and analysis plans (SAPs) implement requirements of the DQOs to identify

sample collection, laboratory analysis, quality assurance, quality control and reporting

objectives.

Preparation of best-basis inventories (BBI) integrating characterization data, process

knowledge, and surveillance data to estimate double-shell and single-shell tank waste

composition by phase.

Evaluation of unit-liter-dose and sum-of-fractions to ensure concentrations are within

DSA hazard and accident analyses.

Updates to toxicological source term methodology through DOE published Protective

Action Criteria.

Maintenance of the Tank Waste Inventory Network System (TWINS) database including

characterization reports, tank waste inventory, and sample data.

Page 25: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

25 of 35

September 27, 2017

Monthly revisions to the Waste Tank Summary Report (HNF-EP-0182) for the official

inventory stored in Underground Storage Tanks in the 200 Areas.

13.7.3 Tank Farms Waste Transfer Compatibility Program

The Tank Farms Waste Transfer Compatibility Program provides a formal process for evaluating

waste transfers and chemical additions through the preparation of documented Waste

Compatibility Assessments. The primary purpose of the program is to ensure that sufficient

controls are in place to prevent the formation of incompatible mixtures as the result of waste

transfer operations. The program defines a consistent means of evaluating compliance with

certain administrative controls, safety, operational, regulatory, and programmatic criteria, and

specifies considerations necessary to assess waste transfers and chemical additions (HNF-SD-

WM-OCD-015).

13.7.4 Waste Feed Delivery Technical Baseline

Mission Analysis Engineering has the responsibility to define and maintain the Waste Feed

Delivery (WFD) technical baseline.

Key activities performed in support of this responsibility include:

Technical studies and evaluations in support of WFD projects and other TOC initiatives,

“what if” studies to evaluate proposed options to enhance waste feed efficiency, and

mission analysis/project definition (Front End Engineering) activities

Operations baseline activities including development of Operations Research (OR)

models to support on-going TOC activities, project designs, and planned mission critical

activities. Defining and assisting in the development of operations/maintenance program

enhancements needed by the increased operations tempo required by WFD

Requirements baseline activities focusing on implementation of systems engineering

through the analysis of TOC mission requirements as defined by contract, development

of associated functions and requirements as well as project specifications, and

maintaining a consistent set of DST system and subsystem specifications. Providing

leadership in the definition of the TOC technical baseline.

13.8 Tank Farm Projects and Tank Integrity Engineering

13.8.1 Tank Farm Projects Engineering

Tank Farm Projects (TFP) Engineering provides a variety of engineering services in support of

Tank Farm infrastructure projects and ensures proper implementation of engineering

requirements from the TOC functional Engineering organization. TFP Engineering:

Manages the resources and delivers the scope of the engineering aspects of TF Projects

efficiently and effectively, to the agreed functional specification and within the approved

cost and schedule baseline.

Provides operations and maintenance support for the safe field execution of projects

Page 26: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

26 of 35

September 27, 2017

Provides support to waste sampling services

Provides support to commissioning for successful testing and operational readiness

Establishes the engineering project delivery strategies including engagement of the

supply chain.

Leads the development and maintains control of the engineering elements of the project

baseline including scope, schedule and budget.

Leads the development and documentation of the project functional specification, design

basis and design criteria.

Ensures the engineering solutions deliver the business case, meet the project functional

specification, preserve the design intent and meet agreed performance and quality

requirements.

Establishes design review strategies and the level of verification and validation necessary

to underpin engineering solutions that meet the safety, engineering and operational needs

of projects.

13.8.2 Tank and Pipeline Integrity

The Tank and Pipeline Integrity (TAPI) Engineering team provides review, integration and

execution of the technical aspects for the Tank Farm associated with integrity and fitness-for-

service programs covering the DST, SST, Waste Transfer, 242-A, ETF and ancillary facilities or

systems. It provides a central engineering overview of the conditions and operations pertaining to

the corrosion control program and maintaining the long term health of systems necessary to

support the Tank Farm mission.

TAPI Engineering scope includes:

Provide documented analyses and assessments for tank leak determinations

Provide oversight and direction to waste chemistry corrosion optimization studies

Facilitate and interface with Expert Panel groups for SST and DST Integrity initiatives

Overview and provide direction for DST and SST Integrity programs (e.g., DST/SST

underground tank and visual inspection programs)

Maintain Operating Specification Documents (OSDs) and their technical bases for single-

shell and double-shell tanks.

The Tank Monitoring Engineering team provides continuous review and analysis of tank waste

surveillance data, and maintenance of baseline limits included in Round Sheets and computerized

monitoring systems. Through effective monitoring, adverse or unexpected trends are identified

and investigated which may include TAPI Engineering to assist with identifying potential causes.

Tank Monitoring Engineering scope includes:

Page 27: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

27 of 35

September 27, 2017

Perform analyses of tank waste surveillance data to determine appropriate baselines that

predict future measurements.

Prepare Baseline Change Authorizations, including technical justification for baseline

changes.

Interface with WRPS Environmental, ORP and Ecology on tank monitoring questions

and issues.

13.8.3 Fitness for Service

The Fitness for Service (FFS) program, as described in RPP-PLAN-52788, provides a means to

determine waste transfer system (WTS) component projected life and allow for management of

aging WTS components. Through implementation of the FFS program, WRPS is provided with a

means to prevent leaks and failures in the tank farms WTS. The data collected to understand,

analyze, and trend damage mechanisms, or to evaluate transient overloads, is then used to make

run-or-replace decisions, and if necessary, modify system design, maintenance, or operating

procedures. Data collection and the periodic projection of remaining component useful life are

ongoing activities that are not included in this plan.

The outcome of a fully developed and successfully implemented WTS FFS plan includes (1)

improved waste transfer route integrity and reliability, and (2) reduced maintenance costs. The

intent is to attain maximum safe operation, economic benefit, and service life from existing

equipment without sacrificing WTS integrity.

13.9 EPC Project Engineering

The execution of DOE’s strategy to meet the mission objective to disposition Hanford tank farm

waste has evolved over time, due to the progression of the overall integrated clean up and

remediation programs, as well as emergent technical issues and challenges. In response, WRPS

has formed the Engineer-Procure-Construct (EPC) Projects Execution organization to execute

large new build Capital Asset and Capital Line Item projects.

An enhanced engineering infrastructure may be required in the event this organization has more

than one EPC project going at the same time. At the current time there is only one capital line

item project (LAWPS) being executed by the EPC organization, thus the EPC Engineering

Manager also serves as the LAWPS Project Engineering Manager with the engineering resources

matrixed from the TOC Engineering Function. The EPC Engineering Manager reports

administratively to the TOC Chief Engineer but takes day-to-day direction from the EPC Project

Execution Manager.

13.9.1 EPC Design Authority

DA for the EPC Projects organization is delegated by the TOC Chief Engineer to the EPC

Engineering Manager. This delegation includes the authority to further delegate DA to qualified

engineering resources within the EPC Projects Execution organization.

Page 28: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

28 of 35

September 27, 2017

13.9.2 EPC Processes and Procedures

EPC capital asset projects must be performed in compliance with DOE O 413.3B, Program and

Project Management for the Acquisition of Capital Assets, associated standards, orders, guides,

and TFC-PLN-84, Tank Operations Contract Project Execution Plan. Given the significant

difference between EPC and TOC’s traditional high-hazard operations projects, a suite of EPC

procedures have been developed based on industry best practice and parent company procedures.

The EPC Engineering procedures are owned by the EPC Project Execution organization and do

not fall within the scope of Engineering Programs. (15.1.3)

13.9.3 EPC Training and Qualification

Engineering staff assigned to the EPC Project Execution organization are qualified in the same

manner as other TOC engineering staff. EPC staff participate in WRPS training programs to the

extent applicable to their needs and scope.

13.10 One System

The One System organization supports the integration of TOC operations and the new Waste

Treatment Plant (WTP). Key activities include such things as long term system planning,

flowsheet integration, and technology development. A significant number of engineering

resources are assigned to the OneSystem organization but they are not matrixed from the TOC

Engineering Function and report administratively and otherwise to One System management.

Because the technical work and associated deliverables produced by One System engineering

staff do not directly impact operating TOC nuclear facilities or, in rare instances where they may,

are implemented by qualified engineering staff reporting to the TOC Chief Engineer, they are not

required to be qualified in the same manner as other TOC engineering staff (described in Section

10.0 of this Plan). The TOC Engineering Function facilitates the qualification of One System

engineering staff when needed or recommended by One System management.

13.11 TOC Fire Protection Program

While the engineering organization provides significant technical support, the TOC Fire

Protection Program itself falls within the remit of the WRPS Environmental Safety Health and

Quality (ESH&Q) organization. Refer to TFC-PLN-13, “Fire Protection Program’, for details.

14.0 DEFINITIONS

Capital Line Item Project. A distinct design, construction, betterment or fabrication activity,

effort or project for which Congress will be requested to authorize and appropriate specific funds

(capital and/or operating), and where the resulting asset (structure, equipment, facility, product,

system or plant) has an estimated useful life of two years or more.

Code of Record. A COR contains, or references, requirements that directly affect the public,

facility worker, environment or nuclear safety; engineering disciplines, including civil, structural,

mechanical, electrical, instrumentation and control, piping, and fire protection; and management

systems including safety, security, and quality assurance. The COR includes Federal and state

laws and regulations, DOE requirements, and specific design criteria defined by national codes

and standards. This includes national codes and standards invoked through 10 CFR 830, “Nuclear

Safety Management;” 10 CFR 851, “Worker Safety and Health Program;” the design criteria in

DOE O 420.1C, “Facility Safety;” and applicable state and local building codes. While the

Page 29: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

29 of 35

September 27, 2017

standards listed in subsections of 10 CFR 851 must be met, more recent editions of the standards

may be used as long as the more recent standards are at least as protective as the edition specified

in 10 CFR 851.

Configuration Management. Configuration management is a disciplined process that involves

both management and technical direction to establish and document the design requirements and

the physical configuration of the nuclear facility, and to ensure that they remain consistent with

each other and the documentation.

Design Basis. Design basis consists of the design inputs, the design constraints, and the design

analysis and calculations. The design basis explains why a design requirement has been specified

in a particular manner or as a particular value.

Documented Safety Analysis (DSA). Within the scope of 10 CFR 830, the documented safety

analysis provides a documented analysis of the extent to which a category 1, 2, or 3 nuclear

facility can be operated safely with respect to workers, the public, and the environment, including

a description of the conditions, safe boundaries, and hazard controls that provide the basis for

ensuring safety.

Safety Basis. The safety basis is the documented safety analysis and hazard controls that provide

reasonable assurance that a DOE nuclear facility can be operated safely in a manner that

adequately protects workers, the public, and the environment. The tank farm safety basis

includes the DSA, Technical Safety Requirements, Safety Evaluation Reports, and other

documents identified by ORP in Safety Evaluation Reports as relied upon to approve changes.

These documents are listed on the WRPS safety basis website as “Contractor Prepared” and

“DOE Prepared.” (15.1.1)

Technical Baseline. The complete set of documents/data, identified by the Design Authority,

used to identify, justify, and demonstrate the physical, functional, or operational requirements of

configuration controlled SSCs.

Technical Safety Requirements (TSR). The limits, controls, and related actions that establish the

specific parameters and requisite actions for the safe operation of a nuclear facility and include, as

appropriate for the work and the hazards identified in the documented safety analysis for the

facility: Safety limits, operation limits, surveillance requirements, administrative and

management controls, use and application provisions, and design features, as well as abases

appendix. The DSA identifies the need for TSRs, but the actual limits are identified in the TSRs.

Unreviewed Safety Question (USQ) Process. The Unreviewed Safety Question process is the

method used to determine appropriate approval authority for a given activity or change and to

keep a safety basis current by: Reviewing proposed changes and tests to determine if a potential

USQ exists, reporting USQs to DOE, and obtaining approval from DOE prior to taking any action

that involves an USQ. The USQ process is approved by DOE and required to meet the provisions

of 10 CFR 830. (15.1.1)

Page 30: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

30 of 35

September 27, 2017

15.0 SOURCES

15.1 Requirements

1. 10 CFR 830, “Nuclear Safety Management.”

2. 10 CFR 851, “Worker Safety and Health Program.”

3. DOE O 413.3B, “Program and Project Management for the Acquisition of Capital

Assets.”

4. DOE O 420.1C, “Facility Safety.”

5. DOE O 426.2, “Personnel Selection, Training, Qualification, and Certification

Requirements for DOE Nuclear Facilities.”

15.2 References

1. ASME/NQA-1, “Quality Assurance Requirements for Nuclear Facility Applications.”

2. 10 CFR 830, “Nuclear Safety Management.”

3. DOE-STD-1073, “Configuration Management.”

4. DOE-STD-1186, “Specific Administrative Controls.”

5. DOE-STD-3009, “Preparation Guide for U.S. Department of Energy Nonreactor Nuclear

Facility Documented Safety Analyses.”

6. HNF-1901, “Technical Baseline Summary Description for the Tank Operations

Contractor.”

7. HNF-IP-1266, “Tank Farms Operations Administrative Controls.”

8. HNF-SD-WM-OCD-015, “Tank Farms Waste Transfer Compatibility Program.”

9. OSD-T-151-00007, “Operating Specification for the Double Shell Storage Tanks.”

10. RPP-7795, “Technical Basis for the Chemistry Control Program”

11. RPP-PLAN-39432, “As Built Program Description.”

12. TFC-BSM-AD-STD-05, “Administrative Document Format and Preparation Standard.”

13. TFC-CHARTER-01, “Tank Operations Contractor Charter.”

14. TFC-CHARTER-33, “Safety Basis Change Review Board.”

15. TFC-CHARTER-37, “Waste Transfer Confinement Review Board.”

16. TFC-CHARTER-55, “Plant Installed Change Control Board.”

Page 31: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

31 of 35

September 27, 2017

17. TFC-CHARTER-56, “Facility Modification Control Board.”

18. TFC-CHARTER-67, “Tank Integrity Expert Panel.”

19. TFC-ENG-ADMIN-C-16, “Defense Nuclear Facilities Safety Board Interface.”

20. TFC-ENG-ADMIN-D-07, “Engineering Assessments.”

21. TFC-ENG-DESIGN-C-15, “Commercial Grade Dedication.”

22. TFC-ENG-DESIGN-C-30, “Post-Natural Phenomena Hazard Assessment.”

23. TFC-ENG-DESIGN-C-47, “Process Hazard Analysis.”

24. TFC-ENG-DESIGN-C-48, “Commercial Grade Dedication for Other Hanford Site

Contractors.”

25. TFC-ENG-DESIGN-C-52, “Technical Reviews.”

26. TFC-ENG-DESIGN-C-55, “Design Subcontract Deliverable Review.”

27. TFC-ENG-DESIGN-C-57, “Development and Maintenance of Code of Record.”

28. TFC-ENG-DESIGN-C-61, “Fabrication Change Control.”

29. TFC-ENG-DESIGN-C-65, “Commercial Grade Dedication of Software.”

30. TFC-ENG-DESIGN-C-67, “Facilities Change Package Process.”

31. TFC-ENG-DESIGN-D-12.1, “Plant Installed Software Configuration Management.”

32. TFC-ENG-DESIGN-D-13.2, “Guidance for Applying Engineering Codes and Standards

to Design.”

33. TFC-ENG-DESIGN-D-29, “Guidance for Inclusion of Human Factors in Design.”

34. TFC-ENG-DESIGN-D-37, “Structural Integrity Verification of Lifting Points.”

35. TFC-ENG-DESIGN-D-50, “Design Process Guidance.”

36. TFC-ENG-DESIGN-P-07, “System Design Descriptions.”

37. TFC-ENG-DESIGN-P-12, “Plant Installed Software.”

38. TFC-ENG-DESIGN-P-43, “Control Development Process for Safety-Significant Safety

Instrumented Systems.”

39. TFC-ENG-DESIGN-P-44, “Safety Instrumented Systems Functional Safety Assessment

Process.”

40. TFC-ENG-DESIGN-P-54, “Checking of Engineering Documents.”

Page 32: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

32 of 35

September 27, 2017

41. TFC-ENG-DESIGN-P-59, “Plant Installed Software Quality Assurance.”

42. TFC-ENG-FACSUP-C-10, “Control of Dome Loading and SSC Load Control.”

43. TFC-ENG-FACSUP-C-23, “Equipment Identification and Data Management.”

44. TFC-ENG-FACSUP-C-25, “Hoisting and Rigging.”

45. TFC-ENG-FACSUP-P-01, “TOC System Engineer Program.”

46. TFC-ENG-FACSUP-P-17, “Flammable Gas Activities Ignition Source Control.”

47. TFC-ENG-SB-C-01, “Safety Basis Issuance and Maintenance.”

48. TFC-ENG-SB-C-03, “Unreviewed Safety Question Process.”

49. TFC-ENG-SB-C-06, “Safety Basis Development.”

50. TFC-ENG-STD-01, “Human Factors in Design.”

51. TFC-ENG-STD-13, “Ignition Source Controls for Work Controls in Potentially

Flammable Atmospheres.”

52. TFC-ENG-STD-23, “Human-Machine Interface for Process Control Systems.”

53. TFC-ENG-STD-36, “Hardware for ABB Process Control Systems.”

54. TFC-ENG-STD-40, “Alarm Management and Annunciator Panel for Process Control

Systems.”

55. TFC-ENG-STD-43, “Engineering TOC Systems, Structures, and Components

Boundaries; Selection Basis; Description; and Implementation.”

56. TFC-ENG-STD-45, “Design and Installations for Potentially Flammable Atmospheres.”

57. TFC-ENG-STD-46, “Technical Baseline Management.”

58. TFC-OPS-OPER-C-33, “Required Reading.”

59. TFC-PLN-02, “Quality Assurance Program Description.”

60. TFC-PLN-09, “Human Factors Program.”

61. TFC-PLN-13, “Fire Protection Program.”

62. TFC-PLN-23, “Configuration Management Plan.”

63. TFC-PLN-49, “Criticality Safety Program.”

64. TFC-PLN-61, “Tank Operations Contractor Training and Qualification Plan.”

65. TFC-PLN-68, “Temporary Waste Transfer Line Life-Cycle Management.”

Page 33: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

33 of 35

September 27, 2017

66. TFC-PLN-100, “Tank Operations Contractor Requirements Basis Document.”

67. TFC-PLN-118, “Strategic Plan for Hanford Waste Feed Delivery and Treatment Process

Control Systems.”

68. TFC-PLN-136, “Engineering Design Program.”

69. TFC-PLN-138, “Implementation Plan for ISA 84 Safety Instrumented System (SIS).”

70. TFC-PLN-142, “Dome Loading Management Plan.”

71. TFC-POL-07, “Engineering Policy and Chief Engineer’s Expectations.”

Page 34: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

34 of 35

September 27, 2017

ATTACHMENT A – ENGINEERING ROLES AND QUALIFICATIONS.

Role R2A2 Reference

Qualification

Card No.

Requalification

Card No.

EPC Engineering Manager R2A2-ENG-022 350848 Note 1

Engineering Programs Manager R2A2-ENG-002 350848 Note 1

Design Engineering Manager R2A2-ENG-003 350848 Note 1

Process Engineering Analysis Manager R2A2-ENG-004 350848 Note 1

Process and Control System Manager R2A2-ENG-005 350848 Note 1

Production Operations Engineering Manager R2A2-ENG-023 350848 Note 1

SST Retrieval Engineering Manager R2A2-ENG-024 350848 Note 1

Tank Farms Projects and Tank Integrity

Engineering Manager

R2A2-ENG-025 350848 Note 1

LAWPS Project Engineering Manager R2A2-ENG-006 350848 Note 1

ETF, 222-S and 242-A Engineering Manager R2A2-ENG-026 350848 Note 1

Engineering Technical Staff N/A 350850 357850

Design Authority N/A 350832 Note 1

Engineering Discipline Lead R2A2-ENG-009 351860 Note 1

Cognizant System Engineer R2A2-ENG-010 350976 350977

Shift Technical Engineer R2A2-ENG-012 350505 350518

Project Engineer R2A2-ENG-016 350886 Note 1

Process Engineer N/A 350255 357255Note 1

Nuclear Safety Manager R2A2-ENG-007 350848 Note 1

Nuclear Safety Engineer R2A2-ENG-014 350007 Note 1

Criticality Safety Representative R2A2-ENG-015 350004 357004

Criticality Safety Engineer R2A2-ENG-017 351004 351005

Hoisting and Rigging Engineer N/A 350847 Note 1

Process Hazard Analysis Leader N/A 350857 357857

Post NPH Inspector N/A 351731 N/A

Procurement Engineering Specialist R2A2-ENG-018 350257 N/A

USQ Evaluator N/A 350950 350950

NOTE 1: Requires requalification as Engineering Technical Staff (357850)

Page 35: TFC-PLN-03, Engineering Program Management Plan Library/011819... · Engineering Program Management Plan Manual Document Page Issue Date Management Plan TFC-PLN-03, REV H-2 4 of 35

Engineering Program Management

Plan

Manual

Document

Page

Issue Date

Management Plan

TFC-PLN-03, REV H-2

35 of 35

September 27, 2017

ATTACHMENT B - GENERIC ENGINEERING ROLES AND QUALIFICATIONS.

Role General Responsibilities Qualifications

Engineering Manager (or

Responsible Engineering Manager)

The individual assigned by the Level 2

Engineering Manager to provide

managerial oversight to engineering

personnel, other than System

Engineers. This role is considered

technical staff only when managing

other technical staff roles.

Provides technical engineering leadership

and support as described in engineering

procedures to engineering programs and

projects.

Manages assigned scope and subordinates

by ensuring that adequate resources are

available, assigning and tracking tasks,

evaluating personnel performance, ensuring

proper training and qualification.

Ensures integration of environmental,

safety, health, and quality requirements and

standards into engineering processes and

products.

Engineering Technical Staff

(#350850)

– Plus–

Any additional experience and/or

training specified by the Level 2

Engineering Manager responsible

for the specific facility/area of

scope.

Responsible Engineer

The individual assigned by the

Engineering Manager to lead the

execution of a specific scope of

engineering work.

Provides engineering technical support as

described in engineering procedures to

engineering programs and projects.

Engineering Technical Staff

(#350850)

Support Engineer

The individual assigned by the

Engineering Manager to perform

engineering work and/or provide

support to key engineering activities.

Provides engineering technical support as

described in engineering procedures to

engineering programs and projects

including, but not limited to, the Cognizant

System Engineering program.

May be delegated Design Authority if DA

qualified.

Engineering Technical Staff

(#350850)

Area Engineer

The individual assigned by the

Production Operations Engineering

Manage to an Operations Area Team

for direct support to Operations and

Maintenance.

Provides engineering technical support as

described in engineering procedures to key

engineering programs and projects within

the Production Operations Engineering

Functional Support Area.

Provides a direct and consistent

communications link between

Operations/Maintenance and Engineering.

Engineering Technical Staff

(#350850)

Technical Authority

When used in an Engineering context,

the individual assigned by the

Engineering Manager to lead a specific

task and/or serve in an SME role.

Provides engineering technical support as

described in company procedures to

engineering programs, other functional

organizations or projects.

Engineering Technical Staff

(#350850)