Upload
patch
View
41
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Testing at Fermilab April 14 th 2011. Goal for this week: - Power up Module 72 (warm) - Get IV curves - Interface to KEK ADC system - Try to see a signal at Room T. Visit by: Osamu (5 days) Koji and Makoto (3 weeks) KEK KIT KATs (permanent transfer). - PowerPoint PPT Presentation
Citation preview
1
Testing at Fermilab
April 14th 2011
Visit by: Osamu (5 days) Koji and Makoto (3 weeks) KEK KIT KATs (permanent transfer)
Goal for this week:
- Power up Module 72 (warm)
- Get IV curves
- Interface to KEK ADC system
- Try to see a signal at Room T
2
Quiet 1 Module 72
All LNA’s have individual Gate Control
Summary
All Active Devices on Module 72 appear to be alive at room T
Success: We see the internal noise signal We see signal from Gunn Oscillator
Goal for Next Week:
- Move system to Cryostat
- Do cool down
3
KEK 64-channel ADC system
KEK Preamp
Bias Board and MAB and Gunn Diode
4
Leg A Drain Current versus Gate Voltage
Drain Voltage for all LNA’s = 250 mV
We did NOT do I-V curve for V-drain = 750 mV(afraid of pushing too much drain current)
LNA1
LNA2
LNA3
5
Leg B Drain Current versus Gate Voltage
Drain Voltage for all LNA’s = 250 mV
We did NOT do I-V curve for V-drain = 750 mV(afraid of pushing too much drain current)
LNA1
LNA2
LNA3
6
Warm IV curve ofU2 Detector Diode
We found thatthe Detector Diode Polarity in module 72 is OPPOSITE ofwhat we expect.
We adapted by reversingour low voltage lines.
Result shown AFTERreversing voltage lines
7
Module is ALIVE: Receiver Noise is seen by KEK ADC system
Phase switch Diode PA1 is turned ON and OFF
Total Power signal x 100seen by KEKADC system
8
Toggling Phase Switch Power
All Phase SwitchDiodesare alive
Note: Plotted istotal power seen by KEK ADC x 100
9
Inject W-band power (from Gunn oscillator) into module, modulated at 1 Hz
10
Inject W-band power (from Gunn oscillator) into module, modulated at 1 Hz
Zoomed in time
11