11
Testing at Fermilab April 14 th 2011 Visit by: Osamu (5 days) Koji and Makoto (3 weeks) KEK KIT KATs (permanent transfer) Goal for this week: - Power up Module 72 (warm) - Get IV curves - Interface to KEK ADC system - Try to see a signal at Room T 1

Testing at Fermilab April 14 th 2011

  • Upload
    patch

  • View
    41

  • Download
    0

Embed Size (px)

DESCRIPTION

Testing at Fermilab April 14 th 2011. Goal for this week: - Power up Module 72 (warm) - Get IV curves - Interface to KEK ADC system - Try to see a signal at Room T. Visit by: Osamu (5 days) Koji and Makoto (3 weeks) KEK KIT KATs (permanent transfer). - PowerPoint PPT Presentation

Citation preview

Page 1: Testing at  Fermilab April 14 th  2011

1

Testing at Fermilab

April 14th 2011

Visit by: Osamu (5 days) Koji and Makoto (3 weeks) KEK KIT KATs (permanent transfer)

Goal for this week:

- Power up Module 72 (warm)

- Get IV curves

- Interface to KEK ADC system

- Try to see a signal at Room T

Page 2: Testing at  Fermilab April 14 th  2011

2

Quiet 1 Module 72

All LNA’s have individual Gate Control

Summary

All Active Devices on Module 72 appear to be alive at room T

Success: We see the internal noise signal We see signal from Gunn Oscillator

Goal for Next Week:

- Move system to Cryostat

- Do cool down

Page 3: Testing at  Fermilab April 14 th  2011

3

KEK 64-channel ADC system

KEK Preamp

Bias Board and MAB and Gunn Diode

Page 4: Testing at  Fermilab April 14 th  2011

4

Leg A Drain Current versus Gate Voltage

Drain Voltage for all LNA’s = 250 mV

We did NOT do I-V curve for V-drain = 750 mV(afraid of pushing too much drain current)

LNA1

LNA2

LNA3

Page 5: Testing at  Fermilab April 14 th  2011

5

Leg B Drain Current versus Gate Voltage

Drain Voltage for all LNA’s = 250 mV

We did NOT do I-V curve for V-drain = 750 mV(afraid of pushing too much drain current)

LNA1

LNA2

LNA3

Page 6: Testing at  Fermilab April 14 th  2011

6

Warm IV curve ofU2 Detector Diode

We found thatthe Detector Diode Polarity in module 72 is OPPOSITE ofwhat we expect.

We adapted by reversingour low voltage lines.

Result shown AFTERreversing voltage lines

Page 7: Testing at  Fermilab April 14 th  2011

7

Module is ALIVE: Receiver Noise is seen by KEK ADC system

Phase switch Diode PA1 is turned ON and OFF

Total Power signal x 100seen by KEKADC system

Page 8: Testing at  Fermilab April 14 th  2011

8

Toggling Phase Switch Power

All Phase SwitchDiodesare alive

Note: Plotted istotal power seen by KEK ADC x 100

Page 9: Testing at  Fermilab April 14 th  2011

9

Inject W-band power (from Gunn oscillator) into module, modulated at 1 Hz

Page 10: Testing at  Fermilab April 14 th  2011

10

Inject W-band power (from Gunn oscillator) into module, modulated at 1 Hz

Zoomed in time

Page 11: Testing at  Fermilab April 14 th  2011

11