    Test Automation Strategy

    Author:

  • 7/27/2019 Test Strategy Template Instructions_Automation

    2/24

    Master Test Plan Version 1.0- 10/14/2009

    Page 2

    Document Status: Final Template Version: 1.1

    Version History

    Changes to the Test Automation Strategy must follow the update process to ensure that the most

    current version(s) are being used by all project team members. This section outlines how theseupdates to the Test Automation Strategy will be published and approved. The project teams

    versioning standards should be adhered to for numbering convention.

    Circumstances requiring approvals for changes to the Test Automation Strategy could include

    any of the following:

    Changes in automation scope or requirements resulting in corresponding updates to theAutomation Test Strategy

    Risks, Constraints, Dependencies and Assumptions as and when identified as far asautomation is concerned.

    Following any significant revision, the Test Automation Strategy will be distributed by email forreview and sign off by individuals identified as approvers in section 1.2. Voting button options

    will include approve, approve with change(note in email response) orreject. Smaller or lesssignificant changes do not require project team approval.

    Review Log

    Version Date Section(s) Changed By Approval

    0.1 Original Release QA Lead

  • 7/27/2019 Test Strategy Template Instructions_Automation

    3/24

    Master Test Plan Version 1.0- 10/14/2009

    Page 3

    Document Status: Final Template Version: 1.1

    This Test Automation Strategy template reflects the standard processes and

    procedures for the test automation-planning phase. The format of this template is

    designed to facilitate the creation of a Test Automation Strategy by providing theessential sections that should be included in a comprehensive test automation plan,

    and by suggesting subject matter for each section. The author should be familiarwith the Principal Financial Group development processes and related automation

    testing procedures.

    Text displayed in blue italics (style=InfoBlue) is included to provide guidance to

    the author and should be deleted before publishing the document.

    To customize automatic fields in Microsoft Word (which display a gray

    background when selected), select File>Properties and replace the Title, Subject,

    Project, and Version fields with the appropriate information for this document.After closing the dialog, automatic fields may be updated throughout the document

    by selecting Edit>Select All (or Ctrl-A) and pressing F9, or simply click on the

    field and press F9. This must be done separately for Headers and Footers. Alt-F9will toggle between displaying the field names and the field contents. See Word

    help for more information on working with fields.

    All sections of this Test Automation Strategy document are to be preserved to

    maintain uniformity and indicate areas of deliberate omissions. The author shouldnot deliberately omitsections with the notation NA.

    Each section of this template provides guiding information for the author and or

    actual text that the author may use as examples of the content of each section.

    Action Item: Any text in blue serves as a placeholder and/or sample data.Substitute it with real information or delete it.

    Action Item: Please make sure to update all fields and tables in this document.(The key sequence is then )

  • 7/27/2019 Test Strategy Template Instructions_Automation

    4/24

    Master Test Plan Version 1.0- 10/14/2009

    Page 4

    Document Status: Final Template Version: 1.1

    Table of Contents

    1.0 INTRODUCTION ......................................................................................................................................... 6

    1.1 PURPOSE...................................................................................................................................................... 6

    1.2 TARGET AUDIENCE ..................................................................................................................................... 6

    2.0 ESTABLISHING THE ASSIGNMENT ...................................................................................................... 7

    2.1 IDENTIFY THE SCOPE ................................................................................................................................... 7

    2.1.1 In scope .................................................................................................................................................. 7

    2.1.2 Out of scope ........................................................................................................................................... 7

    2.2 IDENTIFY THE PRECONDITIONS.................................................................................................................... 82.2.1 Dependencies/Constraints/Considerations ............................................................................................. 8

    2.3 IDENTIFY THE ASSUMPTIONS....................................................................................................................... 9

    2.4 IDENTIFY THE RISKS .................................................................................................................................. 10

    3.0 DETERMINING THE STRATEGY ......................................................................................................... 13

    3.1 TEST LEVELS............................................................................................................................................. 13

    3.1.1 System Test .......................................................................................................................................... 13

    3.1.2 Regression Testing .......... .......... ........... .......... ........... .......... ........... .......... ........... .......... ........... .......... .. 13

    3.2 RISK TABLE ............................................................................................................................................... 13

    4.0 HIGH LEVEL MILESTONES .................................................................................................................. 14

    4.1 HIGH LEVEL MILESTONE ESTIMATED DATES ............................................................................................ 14

    5.0 ENTRANCE / EXIT CRITERIA ............................................................................................................... 15

    6.0 SUSPENSION CRITERIA ......................................................................................................................... 15

    7.0 DEFINE THE TEST PRODUCTS ............................................................................................................ 16

    7.1 TEST STRATEGY ........................................................................................................................................ 16

    7.2 TEST SCRIPTS ............................................................................................................................................ 16

    7.3 TEST DATA................................................................................................................................................ 167.4 PROGRESS REPORTS................................................................................................................................... 16

    7.5 TEST EVALUATION REPORTS..................................................................................................................... 16

    8.0 DEFINE THE ORGANIZATION ............................................................................................................. 17

    8.1 ROLES &RESPONSIBILITIES ...................................................................................................................... 17

    8.2 TRAINING NEEDS ....................................................................................................................................... 18

  • 7/27/2019 Test Strategy Template Instructions_Automation

    5/24

    Master Test Plan Version 1.0- 10/14/2009

    Page 5

    Document Status: Final Template Version: 1.1

    9.0 COMMUNICATION PLAN ...................................................................................................................... 19

    9.1 MEETINGS AND REPORTS ........................................................................................................................... 19

    9.2 TELECONFERENCE INFORMATION .............................................................................................................. 21

    9.3 WEB CONFERENCE INFORMATION............................................................................................................. 21

    9.4 PROJECT DISTRIBUTION LISTS .................................................................................................................... 21

    9.5 OUTLOOKPUBLIC FOLDERS ...................................................................................................................... 21

    9.6 DOCUMENT STORAGE ............................................................................................................................... 21

    9.7 QUERY LOG............................................................................................................................................... 21

    10.0 DEFINE THE INFRASTRUCTURE ........................................................................................................ 22

    10.1 APPLICATION SETUP IN SYSTEM TEST ENVIRONMENT .............................................................................. 22

    10.2 TEST USERS SETUP.................................................................................................................................... 22

    10.3 SYSTEM SETUP .......................................................................................................................................... 22

    11.0 ORGANIZE TEST MANAGEMENT ....................................................................................................... 23

    11.1 TEST PROCESS MANAGEMENT .................................................................................................................. 23

    11.2 TEST CASE COVERAGE RATIOS .................................................................................................................. 24

    11.3 INFRASTRUCTURE MANAGEMENT ............................................................................................................. 24

    11.3.1 Meetings .......................................................................................................................................... 24

    11.3.2 Environment, Tools and Workplaces .............................................................................................. 24

    11.4 DEFECT MANAGEMENT............................................................................................................................. 24

  • 7/27/2019 Test Strategy Template Instructions_Automation

    6/24

    Page 6

    Document Status: Final Template Version: 1.1

    1.0 INTRODUCTION

    This Test Automation Strategy communicates the approach to implementing the automation

    testing effort using a test automation tool.

    This document serves as both a communication tool for the automation team and a governingdocument for the test automation initiative. It will be maintained to reflect all significant

    changes to the scope, approach, test methods or entry/exit criteria defined in this strategy. In

    addition, the only authorized deviations from standard practice controls and deliverables are

    those noted in the approved plan. All activities and their deliverables will be conducted inaccordance with standard policy and procedures and are subject to a compliance audit.

    1.1 PURPOSE

    The purpose of this Test Automation Strategy is to communicate to the project

    stakeholders and to the testing team how the Strategy will be implemented and to

    establish authorization to proceed with the test initiative using the referenced approach,

    standards and controls. This is a governing document for the test activities therefore thedeliverables and key controls identified in this Strategy are subject to review for

    compliance with standard policies and procedures.

    1.2 TARGET AUDIENCE

    Indicate who will approve document. Sign-off is only required for approvers.

    The target audiences for this document are those that represent the following roles on thisproject:

    Role Name Approver /

    Reviewer

    Sign-off

    Date

    QA LeadTest Manager(As per

    the RUP template)

    Test Analyst -Automation

    Business Analyst

  • 7/27/2019 Test Strategy Template Instructions_Automation

    7/24

    Page 7

    Document Status: Final Template Version: 1.1

    2.0 ESTABLISHING THE ASSIGNMENT

    2.1 IDENTIFY THE SCOPE

    2.1.1 In scope

    This Test Strategy for the testing initiativeincludes the following areas of scope:

    In this section, identify the scope of automation testing activities planned. Includethe following topics:

    Explain about the need/goals of automation for the project and how it would help

    in overall testing.

    What types of testing are covered under this automation strategy, such as

    functional, regression, smoke or other tests?

    Why a particular test tool is selected.

    How the proof of concept was carried out, how much coverage is expected throughautomation, which types of test cases are to be automated.

    Define dependencies, such as, impact of changes in development plan, features,

    etc. Make recommendations on the time-line for automation.

    Provide a high level design that is scalable and allows future addition of testscripts.

    Provide a plan to manage and maintain the Automation scripts (post-delivery)

    What components of the overall application are to be tested?

    What is the relationship of the application to be automated to the overall system /

    environment?

    2.1.2 Out of scope

    The following functions, systems, processes are specifically out of scope for the testing initiative:

    In this section, identify specific items that are outside the scope of testing

    What functional business areas will not be automated?

    Mention that high complex functions will not be automated.

    Mention that tests requiring large calculation or more user interference will not beautomated. Files containing multiple records would not be tested.

    Mention if tests involving backend validations are not done

    Mention that non repetitive Test Cases (They may be automated but is not feasible)

    Mention that tests requiring longer time to automate but manual testing time would

    be too less, would not be automated.

  • 7/27/2019 Test Strategy Template Instructions_Automation

    8/24

    Page 8

    Document Status: Final Template Version: 1.1

    Mention that tests involving Graphics might not be automated.

    Mention that test cases involving testing of printing features can not be tested

    Mention that test cases involving the Mozilla browser can not be tested

    2.2 IDENTIFY THE PRECONDITIONS

    2.2.1 Dependencies/Constraints/Considerations

    List any dependencies/constraints/considerations that may impact the design,

    development or implementation of automation testing; e.g., dependencies on other

    organizations (such as DEV, Environment group, Users, and or SMEs) and orschedules, resource dependencies, etc. Some samples have been provided below.

    Indicate other projects that may affect this project.

    Description Type

    Dependency, Constraint, Offshore

    consideration, XBU consideration,

    Vendor consideration, other

    Impact/Consideration

    Manual test cases not ready Dependency Automation may not start as

    the framework maynot be

    created without knowing allthe test cases that needs to be

    automated.

    Contractors contract expires12/01/2010

    Constraint Resource availability

    There is a company freezebeginning 12/15/2009

    Constraint Time frame/ Schedule

    PFG will be assessed a fine if

    change does not occur by12/31/2009

    Constraint Regulatory

    SharePoint Access Offshore consideration Who will need access toSharePoint

    Timing Issues related to cycle Offshore consideration Time difference

    Communication across

    business units

    XBU consideration How will communication be

    handled?

    Determine which QualityCenter Domain & Project will

    be used

    XBU consideration Access/Security to QualityCenter Domain & Project

    Defect Resolution Vendor consideration How will defects becommunicated to vendor and

    how will vendor communicate

    when defect has been

  • 7/27/2019 Test Strategy Template Instructions_Automation

    9/24

    Page 9

    Document Status: Final Template Version: 1.1

    resolved?

    2.3 IDENTIFY THE ASSUMPTIONS

    Identify the significant assumptions made in developing this plan, which if false,

    may impact the design, development or implementation of testing

    The Business Analysts for this project will be available to answer questionswhen necessary.

    The environment will be available andstable.

    Manual testing will be completed before automation begins. The results willbe available to the project team.

    If there is a slippage in the project timeline or scope, automation test scriptcreation will also be impacted.

    Existing production issues will remain unless specifically addressed by the

    project. QA resources assigned to the project will have previous knowledge of

    creating test scripts using the test automation tool.

    All assigned QA resources must be given a background of the project andunderstand those aspects prior to the start of script creation.

    Test execution will not start until signoffs are received for all QA artifacts thatrequire signoff.

    All the security access needed will be given to the test automators prior to testscript creation.

    Test cases will be written based on business and functional requirements andtechnical designs. If any of these documents are not completed, test scripts

    will not be in accordance and there will be a risk of having gaps and rework.

  • 7/27/2019 Test Strategy Template Instructions_Automation

    10/24

    Page 10

    Document Status: Final Template Version: 1.1

    2.4 IDENTIFY THE RISKS

    The table below outlines project or process risks to testing. These types of risk generally

    affect the test teams ability to work efficiently or meet project milestones.

    The content of the table below are examples only -

    Estimates of project Impact and Probability of occurrence are listed in the table as

    L=Low, M=Medium, or H=High. The Risk Measure is a calculation of[Impact x Probability] with a scale of 1-9. Values are assigned as follows:

    L = 1

    M = 2

    H=3

    Description Impact Probability

    Risk

    Measure Mitigation

  • 7/27/2019 Test Strategy Template Instructions_Automation

    11/24

    Page 11

    Document Status: Final Template Version: 1.1

    Description Impact Probability

    Risk

    Measure Mitigation

    The completion of

    automation scripts woulddepend on the Manual

    Testing completion

    H H 9 As and when the manual test case

    creation and execution iscomplete, one can start

    automation, need not wait for theall the test cases to be complete.

    Certain test cases will not

    be automated due to high

    complexity. Henceautomation will be

    incomplete for those area

    H H 9 This might not be decided at the

    time of planning but as the work

    progresses in automation, one mayfind such a scenario which needs

    to be discussed and addressed.

    Requirements will changewhile the project is in

    development due to

    changing regulatoryrequirements, businesschanges, etc.

    H H 9 Project Management will reviewany changes, assess impact, risk,

    and cost and present these to the

    steering committee for review.This will include date changediscussions.

    Testers unfamiliar with newenvironments.

    H H 9 PM will provide point of contactfor environments to the QA Lead.

    If any environmental issues arise,

    QA will raise any issues orconcerns immediately to the PM.

    Security access and profile

    timelines.

    M L 2 PM has negotiated the dates for

    Security definition

    Testing resources assigned

    to project are unable to

    commit time for testing.

    M M 4 Work with testing resources to set

    up dedicated testing time. Work

    with Project Manager to resolveany resourcing issues.

    Delay in code delivery. H L 3 Additional QA effort will need tobe identified to overcome the

    timeline gap. This will happen if

    the timeline is not adjusted for the

    delay.

  • 7/27/2019 Test Strategy Template Instructions_Automation

    12/24

    Page 12

    Document Status: Final Template Version: 1.1

  • 7/27/2019 Test Strategy Template Instructions_Automation

    13/24

    Page 13

    Document Status: Final Template Version: 1.1

    3.0 DETERMINING THE STRATEGY

    The test strategy is based on the product risk analysis, and the decision on which

    quality characteristic must be tested per test level, and to what depth.

    3.1 TEST LEVELS

    The following test levels will be executed:

    3.1.1 System Test

    A system test is a test carried out by the test team, with the aim of

    demonstrating that the developed system, or parts of the system, meets with thefunctional specifications and the technical design. (This includes regression

    testing of existing functionality and interfaces with other systems.)

    The automation scripts would be created as per the test cases and would be

    executed end to end to complete the System Testing test cases.

    3.1.2 Regression Testing

    Regression Testing will be to demonstrate rerunning previously run scripts andchecking whether previously fixed faults have re-emerged.

    3.2 RISK TABLE

    Determine which test phase characteristics are tested in; System, Performance,

    Regression. Rate them by High. Medium, Low

    The manual test cases would cater to these characteristics but in case you want to

    emphasize on the part creation of test scripts, you can enter the product riskanalysis and the decision on which quality characteristic the test scripts must be

    created per test level, and to what depth. The decision totally depends on the

    feasibility of creation of automation scripts and support of the test tool.

    System Performance Regression

    Connectivity

    Continuity

    Data

    controllability

    EffectivelyEfficiency

    Flexibility

    Functionality

    Suitability of

    Infrastructure

    Maintainability

    Manageability

  • 7/27/2019 Test Strategy Template Instructions_Automation

    14/24

    Page 14

    Document Status: Final Template Version: 1.1

    Performance

    Portability

    Reusability

    Security

    Suitability

    TestabilityUser-

    Friendliness

    4.0 HIGH LEVEL MILESTONES

    4.1 HIGH LEVEL MILESTONE ESTIMATED DATES

    Below are high-level milestone as currently defined. For more detailed schedule

    and milestone information reference the project Strategy on the project share drive.

    Activity Estimated Start Date Estimated End Date

    Create Test Automation Strategy

    Create Automation Framework

    Identifying the reusablecomponents and preparation

    Creating the OR

    Test Data Preparation

    Script Creation

    Review

    Rework

    Individual Execution

    Batch Execution

    Report Analysis

    Downtime/Issue Log

    Documentation

  • 7/27/2019 Test Strategy Template Instructions_Automation

    15/24

    Page 15

    Document Status: Final Template Version: 1.1

    5.0 ENTRANCE /EXIT CRITERIA

    System Test (performed by automation Tester role)Criteria Description

    Entry Criteria Coding is complete and unit integration testing has been reviewed and

    accepted by the test organization

    No outstanding critical defects open

    The defined System Test environment is prepared and stable

    System Test scripts have been written and reviewed for coverage and

    completeness

    System Test data is available for test execution

    Change Request and Version Control process is in place

    Exit Criteria Agreed upon coverage ratios have been met and all scripts have been

    executed.

    Application has been sufficiently tested to meet requirements (by

    execution of scripts)

    No outstanding critical defects remain open

    Regression Test (performed by automation Tester roles)

    Criteria Description

    Entry Criteria Approval to deploy application has been received from business

    Application has been deployed to production

    Exit Criteria All test scripts have been executed

    No outstanding critical defects remain open

    6.0 SUSPENSION CRITERIA

    This section will identify and address any situation where the automation test script

    creation effort might have to be temporarily suspended.

    6.1 Test environment becomes unavailable.

    6.2 Test cases are blocked by a documented defect.

  • 7/27/2019 Test Strategy Template Instructions_Automation

    16/24

    Page 16

    Document Status: Final Template Version: 1.1

    7.0 DEFINE THE TEST PRODUCTSDefine the artifacts that will be produced for this project. Examples have been includedbelow.

    7.1 TEST STRATEGY

    System Test Plan

    Regression Test Plan

    7.2 TEST SCRIPTSTest scripts, test data and documentation and other xls, vbs files attached to the

    script are housed in Quality center:

    Domain=Project=

    7.3 TEST DATADocumentation of data to be used for execution of test scripts, both in QC and in

    the xls data sheet.

    7.4 PROGRESS REPORTS

    Test execution status reportsweekly reports of test execution status andapplication quality

    7.5 TEST EVALUATION REPORTS

    Issues after Release Advice

    Gives insight into the way the test script creation and execution process hasgone

    Provides results from the lessons learned session

  • 7/27/2019 Test Strategy Template Instructions_Automation

    17/24

    Page 17

    Document Status: Final Template Version: 1.1

    8.0 DEFINE THE ORGANIZATIONDefine the Roles & Responsibilities that will be utilized with this project. If you will notbe using a specific role, indicate Not Applicable.

    8.1 ROLES &RESPONSIBILITIES

    Role Assigned To Responsibilities

    QA Lead/

    AutomationAssignment Manager

    Prepare Test Automation Strategy

    Schedules and facilitates automation testrelated meetings

    Provides oversight of automation relatedDefect Management process

    Assists in mentoring and training of projecttesters when appropriate

    Provides testing status updates throughout theautomation testing phase

    Provides resource estimatesTesters/ Test

    Automationdeveloper(as per the RUPtemplate)

    Create test scripts

    Execute test scripts within the timeframeallowed

    Log defects and retest as necessary

    Communicate status of testing to QA Lead

    Assignment Manager

    Partner with QA Lead to ensure successfulexecution and completion of automationtesting related activities on business unit

    projects.

    Business Owner/SME Work with Business Analyst to clarify

    requirements. Collaborate with QA to get clarification while

    creating test scripts in order to ensure propercoverage of all business requirements andfunctional specs., that are already dealt with inthe test case.

    Help identify new areas for automationtesting, and define validation responsibilities.

    Project Manager Ensure the project scope is finalized prior tothe team beginning test script creation and

    execution.

    Ensure adequate project timelines support thetime needed for test preparation andautomation script execution.

    Assist the QA Lead, as a resource, inidentifying the reporting needs, specific to the

    project.

  • 7/27/2019 Test Strategy Template Instructions_Automation

    18/24

    Page 18

    Document Status: Final Template Version: 1.1

    Test Environment

    Support

    Migrate code

    Test environment issue resolution.

    Configuring test environment.

    Participate in Automation Testing StatusMeetings as needed.

    8.2 TRAINING NEEDS

    Describe what training, if any, is needed for the test team to come up to speed.

    Examples may include automation tool training, Quality Center training orapplication knowledge.

  • 7/27/2019 Test Strategy Template Instructions_Automation

    19/24

    Page 19

    Document Status: Final Template Version: 1.1

    9.0 COMMUNICATION PLAN

    9.1 MEETINGS AND REPORTS

    Describe how often and in which way the automation test team will report withinand outside the team. Make sure this is in accordance with the customers wishes.

    Describe how often and with whom a meeting shall take place

    This section should address all forms of communication; meetings, reporting, etc.,list exceptions to the standards.

    Event Objective Method

    (Report

    /Meeting)

    Chair Attendees /

    Audience

    Frequency

    Testing Kickoff Review timeline

    and introduce theTest Automation

    Strategy document

    to QA resources.

    QA Lead Project Manager

    QA LeadAutomation

    developer

    Technical Lead

    Project Sponsor

    Once

    Test Status

    Review

    Review general

    health of

    Automation Testing

    Initiative.

    Operational Issues

    QA Lead Test team

    QA Lead

    Weekly

    General

    Project

    Meeting(s)

    Describe any

    general project

    meetings known at

    the time of the Test

    Strategy that

    members of the test

    team will be

    attending.

    Project

    Manager

    Technical Lead

    Business AnalystProject Sponsor

    QA Lead

    Weekly

    Weekly Status Shows status of

    automation script

    creation and

    execution.

    Report QA Lead Project Manager

    QA Lead

    Project Sponsor

    Weekly

    Defect Review Review status of

    open defects.

    Identify any newissues. Release

    status.

    QA Lead QA Lead

    Project Manager

    Technical Lead

    Weekly or As

    needed

    Lessons

    Learned

    Discuss project

    results and ID

    lessons learned for

    future

    improvement.

    Project

    Manager

    QA Lead

    Project Manager

    Technical Lead

    Automation

    developer

    Once

  • 7/27/2019 Test Strategy Template Instructions_Automation

    20/24

    Page 20

    Document Status: Final Template Version: 1.1

    Business Analyst

  • 7/27/2019 Test Strategy Template Instructions_Automation

    21/24

    Page 21

    Document Status: Final Template Version: 1.1

    9.2 TELECONFERENCE INFORMATION

    Update items in red with your specific information.

    US & Canada: Dial-In Number: XXX-XXX-XXXXInternational: Dial-In Number: XXX-XXX-XXXX

    Enter conference Code: XXX-XXX-XXXX#

    Leader enter *; then PIN: XXXX#, then 1

    System will ask you to state your namemay do so, or leave blank bypressing #

    System will sound a tone then connect the call

    9.3 WEB CONFERENCE INFORMATION

    Update items in red with your specific information.Sign in by clicking on the URL keying all information below:

    Meeting URL:https://www.livemeeting.com/cc/principal/joinMeeting ID: XXXXXX

    Presenter Key: XXXXXX

    Attendee Key: XXXXXXXX

    9.4 PROJECT DISTRIBUTION LISTS

    Include email distribution lists built for this project.

    9.5 OUTLOOKPUBLIC FOLDERS

    The following public folders will be used by this project for testing:

    Add Outlook path here

    9.6 DOCUMENT STORAGE

    Indicate where your documentation is stored and provide the path or a link.

    SharePoint

    Project folder

    9.7 QUERY LOGIf your project is not utilizing PGS resources, the Query Log is Not Applicable.

    The Query Log within SharePoint will be utilized to communicate general

    questions and answers regarding terminology, resources and knowledge gaps

    encountered while creating automation test scripts.

    https://www.livemeeting.com/cc/principal/joinhttps://www.livemeeting.com/cc/principal/joinhttps://www.livemeeting.com/cc/principal/joinhttps://www.livemeeting.com/cc/principal/join
  • 7/27/2019 Test Strategy Template Instructions_Automation

    22/24

    Page 22

    Document Status: Final Template Version: 1.1

    10.0 DEFINE THE INFRASTRUCTURE

    10.1 APPLICATION SETUP IN SYSTEM TEST ENVIRONMENT

    The system test environment needs to mimic the production environment. The

    environment, including the software and data, must be a controlled environment.Development will be delivering new builds to the System environment on an agreed upon

    schedule. When each new build is delivered to QA, the following application setup needs

    to be completed:

    Provide additional information as needed for your project.

    10.2 TEST USERS SETUP

    Specify any special user setup. Consider the needs for test accounts with various

    access levels.

    10.3 SYSTEM SETUP

    The following applications must be controlled and available in the System environmentto support the System Testing effort.(This should include any hardware setup that needs

    to be done for the automation tool to run smoothly.)

    System Included in test? Notes

    Yes No Note special data requirements, etc.

    Yes No

    Yes No

    Yes No

    Yes No

    Yes No

    Yes No

    Yes No

    Yes No

  • 7/27/2019 Test Strategy Template Instructions_Automation

    23/24

    Page 23

    Document Status: Final Template Version: 1.1

    11.0 ORGANIZE TEST MANAGEMENT

    Describe the manner in which the management of the test process, infrastructure, test

    products and defects is organized

    11.1 TEST PROCESS MANAGEMENT

    This should be in line with the manual test process management. The defects detected bythe execution of the automation scripts should be assigned and tracked. Some in-process,

    production readiness metrics can be calculated from the data gathered in defect

    management tool and the test management tool. Some of these real-time metrics help

    predict whether the quality of the software will be acceptable by the scheduled release.Others provide status on the completeness of the testing phases, which can be compared

    to the project plan. Typically, these metrics are calculated and reviewed as part of project

    status.

    Note: In the metrics below defects include defects only. Defects do not include anyenhancements that may be logged. Each test level may report the metrics for that level in

    their weekly status.

    Metric: Indicates/Reflects on:

    # open defects by severity Status of the software towards production ready.

    List of open defects used to evaluate the current status,

    severity and priority of open defects.

    # new defects found by week Whether the software is approaching production ready.

    This is viewed graphically as a time series chart.

    If defect arrival rate does not quickly decrease, teamleaders and management should promptly assess the

    situation.

    # new defects found by week by

    severity

    Whether the software is approaching production ready.

    This is viewed graphically as a time series chart.

    Critical and major defects should decrease very quickly.

    # defects resolved by week Whether the software is approaching production ready.This is viewed graphically as a time series chart.

    If defect resolution rate is not greater than the # of newdefects found by week, team leaders and management

    should promptly assess the situation.

    # test cases by execution status

    pass/fail/no run

    % test cases executed

    Whether the software is converging on production

    ready.

    If the # test scripts passed per week does not quicklyincrease, team leaders and management should promptly

  • 7/27/2019 Test Strategy Template Instructions_Automation

    24/24

    Page 24

    Metric: Indicates/Reflects on:

    assess the situation.

    11.2 TEST CASE COVERAGE RATIOS

    80% is the recommended overall test case coverage ratio for test automation. Thismay be adjusted up or down based on project risks, priorities and impacts.

    The test coverage ratio is the comparison of the total number of test cases

    automated to the total number of test cases written.

    11.3 INFRASTRUCTURE MANAGEMENT

    11.3.1 Meetings

    The Automation Test Manager & QA Lead will meet on an agreedupon scheduled time to discuss what more needs to be automation and

    its feasibility.

    11.3.2 Environment, Tools and Workplaces

    Describe any additional items that are specific to your project. Examples havebeen provided.

    Test automation validation will occur in Text Pad and/or Excel asneeded

    Test Environment Location:

    Path/Logical location information needed to access Test Environment

    Security required for access to the Test Environment

    Script creation and execution will occur at automation testers desks

    11.4 DEFECT MANAGEMENT

    Defects will be tracked within the following Quality Center Domain & Project.

    < QC Project>

    Justify any deviations from this process.