Upload
batty-adi
View
224
Download
0
Embed Size (px)
Citation preview
8/7/2019 TEO12 Final Report Template
1/20
[Pick the date]
[Type the document subtitle]
H
| Paschal
[TYPE THE
COMPANY
NAME]
PROJECT PLAN ON INSTALLATION CABLE CAR
NEAR JOG FALLS Prepared by:
Guru
Stephane
Sundas
Bharath
Paschal
8/7/2019 TEO12 Final Report Template
2/20
2
T
l of Contents.
1.Executive Summary .
2.Background.
2.1. roject Background/Introduction
2.2. roject Objectives.
2.3. roject goals
2.4. i itations .
3.Requirement specifications
3.1. roduct requirements..
3.2. roject requirements.
3.3. rerequisites
4.Handover and implementations.
5.Situational analysis and stakeholders
5.1. WOT-anal sis..
5.2. takeholders mapping.
6.Milestones,activities and schedule
6.1.
ilestone plan .6.2. ctivity list
6.3.Barchart/Gantt chart .
7.Organization and Staffing ..
7.1. Roles,resiponsibilies and authorities..
7.2. Staffing plan ..
8.Project budget .
9.Communication and quality assurance.
9.1.Reports and documents ..
9.2. Communication plan .
9.3.Quality assurance .9.4.Change management .
10.Risk analysis and response
planning
11.Work break down structure
12 References
13.Appendices..
13.1. ppendix 1
Milestone flow chart.
13.2. Appendix 2..
Activity list.
13.3.Appendiix3
Gantt Chart.
13.4. Appendix4
Organizational structure.
13.5.Appendix 5
Tabulation of budget plan
13.6.Appendix 6
Work break down structure.
8/7/2019 TEO12 Final Report Template
3/20
3
1.ExecutiveSummary
The project,installation ofcable car at Jog fall,is aimed at making tourists have a clearview
ofJog fall. It is expected to be completed in.months at an estimated budget of In the
project, priority isgiven to quality and completion time of the project ,thuscost overrun of
25% may be accepted for the sake of quality and early completion.The scope of the project
includes preparation of the worksite,installation ofcable car, training of operators,
implementation and handover of the completed work. The cable car will be consisting of
two fixed cables and 3 passenger cabins each holding a capacity of 10 persons (max of 700kgper cabin).The fixed cables provide support for the cabins while the cables, by means of a
grip, is solidly connected to the wheel set that rolls on the track cables. An electric motor
drives the cable which provides propulsion.Jog falls is the highest plunge of water fall in
India. It falls from a height of 253 meters and attract potential tourists around the world.
2. Background.
2.1. Project Background/Introduction.
Jog fall has been known to be a very big tourist attraction in India for many past years.
Thousands of people from all over the world visit the place for sightseeing or tourism.
Record shows that the number of tourist visiting the Jog fall has been decreasing for the past
two years. Investigation on the reason for the continuous drop showed that tourists are not
satisfied with the level ofview they have on Jog fall, thus making them to patronize other
tourist sites.
Following the result of the investigation, the management of..has approved the
installation ofcable car at Jog fall.The project is expected to be completed inmonths,
that is before the commencement of next holiday season.
2.2. Project Objectives.
-Increase the number of tourists that visit Jog fall.
-To ensure that tourists have adequate view of the tourism site, thus have value for their
money.
-To increase revenue from the tourism site.
-To restore Jog fall to its formerstatus as one of the most visited tourist centre in the world.
2.3. Project goal.
-Installation of a high quality cable car within stipulated time of 7 months.
8/7/2019 TEO12 Final Report Template
4/20
4
-To train local resources for efficient operation of the cable car.
2.4. Limitations.
-Cable cars are built by another company
-Both downstream and upstream stations are built by another company
3. Requirement specifications.
At the completion of the project, it is expected to give the following results and have thespecifications stated below
3.1.Product requirements.
-Completed project should enable tourists to have scenic view of Jog waterfall.
-The cable car should consist of two fixed cables and one moving cable for propulsion.
-Three passenger cabins with a capacity of 10 persons each will be required.
-The maximum weight per cabin is 7000kg.
-The project will deliver a dual cable car.
Exploitation: 10 hours /day, 365 days/year
Travel duration: 20 minutesDownstream altitude: 810m
Upstream altitude: 810m
Distance:1.6
materials and component specifications.
Supporting cables: 2 x 56 mm per way
Width: 4 x 200 mm per way
Tractorcable: 48 mm per way.
Tractorcables tension: dynamic, 1 counterweight 40 t per way
Main engines: 2 electrical engines 500 kW.
Rescue engine:1 electrical engine 75 kW per way engaging a ring gear on the drive pulley
Recovery engine:1 electrical engine 55 kW per way engaging a ring gear on the pulley
recovery
Rescue engine: 4 generators of 560 kW
Numberof cars: 2*3 (group of 3 cars per way)
Carcapacity: 10 persons or 800 kg.
3.2.Project requirements.
The three major issues to be considered in the execution of the project are
1.Cost 2.Quality 3.Time
Time: The project has to be completed in four months and put into service by May
2011.Thus, the project must commence in June, 2011.
Quality: The project is expected to be of very high quality, thus the execution processes are
required to pass through thorough quality inspection and assurance. Materials and skills of
very high standard will be preferred irrespective of the cost.
Cost: The execution of the project is estimated to cost 1000000 SEK. However, cost over run
of 25% will be accepted for the sake of achieving high quality and early delivery of the
8/7/2019 TEO12 Final Report Template
5/20
5
project. Thus, during the project execution, the quality issue ranks 50% followed by the
delivery time,40% and cost 10%,in the priority of the project execution.
All contracts should be awarded only to first class companies.
Supplied materials should be subjected to adequate test and inspection for quality before they
can be used for project work.
3.3. Prerequisites.
In order to achieve expected result and have smooth execution of the project, the project
sponsor local government needs to meet up the following demand.
-Adequate funding of the project.
-Give the experts free hand to make decision on the technical issues.
-Sponsors decision on choice of suppliers and sub contractors should not be sentimental, but
must base on competency.
-Timely release of funds for project execution.
-Provision of adequate security for equipments and inventories at the project site.
4.Handover and implementations.
4.1. Implementations:
-Train operators and maintenance engineers: At the completion of the project, operators and
maintenance engineers will be trained on how to operate and maintain the cable car .
-.In collaboration with sponsors choice of external experts, acceptance test will be carried out
on the performance and functionalities of the completed project work with reference to the set
requirement specifications. The cable car will be test run under stressed condition for two
weeks, if the completed project did not show any sign of defect during the two weeks of
rigorous test, it will be confirmed alright for handover.
-Maximum exploitation speed: 4meters/second.
-The cable car is designed only for group of 3 cars per way.
-The car capacity must not exceed 800kg.
-Every operation should be performed only by trained personnel
-Strict adherence to the operation instructions and safety is required.
-There is need for monthly routine check maintenance and biannual overhaul maintenance.
4.2. Handover
-Major stake holders agreed on the handover date.
-The completed project will be totally handed over to the client (the local government). Thus,
the client will be responsible for the daily administration of the project result including
engineering maintenance and repairs. Thus, on the handover day, the sponsor receives a 3
8/7/2019 TEO12 Final Report Template
6/20
6
passenger cabins, dual way cable car, upstream and downstream stations equipped with
control equipments and power source.
-Preparation of project delivery document which should be signed by the project manager and
sponsor.
-The sponsor takes over the completed project.
5. Situational analysis and stakeholders.
5.1.SWOT analysis
In order to identify the external and internal factors that might effect the execution of the
project, we have made a SWOT analysis which is presented in the table below.
The external factors are opportunities and threats and they are positioned outside the project
and the executing organization. On the contrary, internal factors, strengths and weaknesses,
are inside and can be influenced.
After analyzing the SWOT we can see that there are two main weaknesses. The first one is
hard to influence and some time will be lose because of the inconvenient field. For the second
one, the project manager can for example propose some vacations in the middle of the project
to let some managers go back in their countries to see their families.
Table 1: SWOT analysis
Helpful Harmful
InternalOrigin
- The company is highly experimented for
this kind of cable-cars installation. Some
installations have already been done in
harder environment.
- The company has agreements with local
workers and companies with whom she has
already worked with.
- The installation site is difficult to access:
problems for materials transportations and
for building.
- Some project managers are not from India
and will have to stay close to the project site
for the whole project duration.
ExternalOrigin
- Train local resources to operate the project
efficiently.
- Some help from local government can be
provided because the project will attract
tourists from around the world and will
increase the gross income to local
government.
-Climatic conditions: strong wind, rain.
- Disagreement of people for the
environmental protection.
8/7/2019 TEO12 Final Report Template
7/20
7
5.2. Stakeholders mapping.
The company CEO: He decides if the company accept the project and in which price.
Project managers: They build the project proposal (they study the project offer, estimate the
overall cost and the expected benefice, study the feasibility, etc.) and lead the project.
Workers: They work on the installation and will determine if the projects durations will be
respected.
Local resources: They can be trained to work on the installation.
Local government: He asks for the project, which will create local employment and an
increase of the gross income.
Local trade: Once the project over, there will be more tourists who will boost the economy.
Organizations for environmental protection: They can slow down the project.
6.Milestones, activities and schedule.
6.1.
ilestone plan.
The milestone flow chart, in appendix 1, shows which are the different deadlines of the
project. It would help us to check if the project progress correctly and on time.
6.2.Activity list.
We have written all the activities used in the Gantt chart in a table, in appendix 2, with some
other information as the duration of each activities, the dependencies, the responsible and the
resources needed, and the cost.
6.3.Barchart/Gantt chart
Using the previous table, we have made a Gantt chart, in appendix 3, which shows the
repartition and dependencies of activities in time. We have considered 5 working days per
week and we have set the duration of each activity by considering 8 working hours per day.
7.Organization and Staffing.
7.1. Roles,responsibilities and authorities.
The organizational structure of the company follows a project organization. Indeed, the
company deals only with big projects so the project managers must have the strongest
authority. For the project we are interesting for, the organizational structural diagram is given
in appendix 4.
8/7/2019 TEO12 Final Report Template
8/20
8/7/2019 TEO12 Final Report Template
9/20
9
includes environmentalcostssuch ascutting of trees for building upstream and downstream stations,
costs due to disturbing animals and nature in the range due to invasion of people. Rough estimation of
the project budget is mentioned in below table and detailed list ofcosts for the project is mentioned in
13.2 Appendix (2).
External costs (Sek/year) Total Internal costs for complete project (Sek)
Disposalcosts 8800 800000
Maintenance costs 12000
Overhaulingcosts 4000*
Othercosts 12000
Total External Costs/year 36800
*overhaulingchargesincludes one day inspection charge 1600Sek + costs for 1 engineer and 2 workers
9. Communication and quality assurance.
9.1. Reports and documents.
Reports and documents are very much important for smooth working of a project. OurProject
managers always communicate with the project team to know the development of project. It isalso necessary for the manager to communicate with the local government to create awareness
about the development of project because they are always cautious about smooth and quality
works as the end users are people directly. So the only way to communicate is through reports
and documents. Creating reports for each and every activity is time consuming process, so
mostly reports are created for a complete process. Often reports are created separately
depending on whether communication is between team mates with the project manager or
project manager with the sponsor.
Reports from team mates with the project manager includes the following
Reports from Project manager to the sponsor includes the following
9.2. Communication plan.
In order for a successful project, communication is most important. Communication involves
an interface between government and the project manager and team mates with the manager.
The following model represents a communication model.
Time consumed and
Time estimated
Actual and
Expected Result
List of Activities
Overall
development
Actual and
Expected result
Time consumed and
Time estimated
Actual Cost and
Estimated cost
8/7/2019 TEO12 Final Report Template
10/20
10
Communication is successful only when the purpose of the message is served.
Communication can be anything such as just informing or passing message to someone within
the group or outside, to necessary action that should be taken after receiving the message.
Message that is sent should always be clear so that the receiver should easily act according to
it and make necessary changes where ever is required. Another important factor for
communication is the language, both sender and receiver should contact each other in a
common language or else there are bright chances of someone interpreting the message
wrong. In our project we dont have any language problem as most of us speak the same
language.
9.3.Quality assurance.
-Our quality engineers work with quality assurance manager in order to ensure acceptable
level of quality. They establish standard for all materials and works. The established qualitystandard is according to internationally accepted standard for quality.
-All materials for the project work are subjected to thorough inspection and test being used in
the project work. Thus, they are checked against the established acceptable quality.
-Every activity in the project work is checked against the established quality standard, right
from the beginning to the end.
-Any activity that does not meet the set minimum quality standard is corrected. Also,
materials that do not meet up the set minimum quality requirement are not used.
9.4. Change management.
Change in project can be a requirement or just a wish. In our case change was forced and was
within the project team. The forced change was inclusion of a new member in the project
team, a logistic manager. As the change was within the team ourProject manager alone
handled it but if the change was more complicated then it required the involvement of
customer (government) as well as the stake holders if there were any.
This was one of the high profile projects to the local government, so extra attention was given
to every activity in the project. Meanwhile, some of the risk which could hinder project
progress has been tabulated below. Occurrence of risk has been identified with in the project
and also from outside. The probability of identified risk and its impact on the progress of the
project has been scaled to 1 to 5, which represent low to very high respectively. Risk value
greater than 5 will be sorted and discussed before the start of the project.
10.Risk analysis and response planning .
Project Risk Management
Who is the
sender?
What message is
to be sent?
How can it
be sent?
Who is the
receiver?
8/7/2019 TEO12 Final Report Template
11/20
11
Brief description of the table below is needed
especially on the rating values
Risk Proba
bility
Imp
act
Risk
value
Risk Response
Delay of contract signing
with government due to
political issue
3 4 12 Explain clearly the advantages of
the project
Delay of material
transportation to project site
3 2 6 Make use of safety stock
inventory
Protestation from local
environmentalist
3 1 3 Peaceful discussion and guarding
the project site
Illness of foreign project
managers
2 2 4 Transfer the responsibility to
lower subordinates
Worker undergoing strikes 3 4 12 Compromise the workers and
compensate through extra work
Harsh weather like heavy
rain or storms
2 3 6 Put off work and compensate
through extra work
broke down of installed
setups
1 4 4 Discuss within the organization
and find solution before installing
predecessor
Broke down of heavy duty
cranes
2 4 8 Add penalty to contractor
Severe quality issue with
incoming material
3 4 12 Switch to next competitive
supplier
11.Work break down structure.Brief written description of the WBS needed
here. Reference should be made to the
appendix number and page while making the
8/7/2019 TEO12 Final Report Template
12/20
12
description
12References.
13. ppendices.
13.1.Appendi ! 1: Milestone flow cha " t
10/03 Cont act Signing with subcont acto
17/03 P oject P oposal and Ag eement
23/03 Choice ofsoftwa e fo in ento y management.
19/05 All pylons installed enti ely
25/08 Installation ofengines completed
8/7/2019 TEO12 Final Report Template
13/20
13
13.2. Appendi # 2: Acti $ ity list
01/09 Both stations completed
10/10 hole installation completed
8/7/2019 TEO12 Final Report Template
14/20
Activites
I e titiesec icalActivities D ratio
De e
e cieses o si le
1%
re st&
'
y oflocatio(
5'
ays Site E(
gi(
eer)
0
ara
2 Eval&
atio(
of)
&
'
get 3'
ays 1%
roject2
a(
ager G&
r
3 Eval&
atio(
ofTime 3'
ays 1%
roject2
a(
ager G&
r
4%
roject%
ro1
osal a(
'
Agreeme(
t 0'
ays 3
53
ecr&
itme(
t ofworkers 5'
ays 4
4
&
ma(
3
eso&
rce a(
'
5
evelo1
me(
tA
)
C
6 Tem1
orary S0
elter forworker 5'
ays 5%
roject2
a(
ager)
&
il'
7 Trai(
i(
g a(
'
K(
owle'
ge Tra(
sferActivities 2'
ays
4
&
ma(
3
eso&
rce a(
'
5
evelo1
me(
t G&
r
8 A'
vertise ofTe(
'
erNotice 1'
ay 6%
roject2
a(
ager G&
r
9 C0
oosi(
gs& 1 1
liers a(
'
co(
tract sig(
i(
g 3'
ays%
roject2
a(
ager G&
r
10 Co(
tract Sig(
i(
gwit0
s&
6
co(
tractor 0'
ays 9
11 Set mi(
im&
m7 &
ality re7 &
ireme(
t 2'
ays Q&
ality E(
gi(
eerG
&
r
12C
0
eck t0
e re7 &
ireme(
t s1
ecificatio(
s forsta(
'
ar'
1
ractice. 5
'
ays 11 Q&
ality E(
gi(
eerG
&
r
13 I(
s1
ectio(
ofmaterialsreceive'
forms& 1 1
liers 5'
ays 11 Q&
ality E(
gi(
eerG
&
r
8/7/2019 TEO12 Final Report Template
15/20
14@
iriA
gofware9
oB
se 4moA
t9
s 4 LogisticEA
giA
eer
C
eta
15
E
esearc9
of aA
aF F
roF
riate iA
veA
tory maA
agemeA
t
software4
D
ays 4 LogisticEA
giA
eer
16 C9
oice ofsoftware foriA
veA
tory maA
agemeA
t. 0D
ays 15
17 C9
oice ofsB
itaG
le traA
sactioA
moD
e 2D
ays 16 LogisticEA
giA
eer V
18H
ecisioA
ofTraA
sF
ortatioA
G
atc9
2D
ays 16 LogisticEA
giA
eer
19H
etermiA
atioA
oforD
erI B
aA
tity for eac9
material. 2D
ays 16 LogisticEA
giA
eer
20 Estimatio
A
ofi
A
ve
A
tory
9
ol
D
i
A
gcost. 2
D
ays 16 LogisticE
A
gi
A
eer
21 EstimatioA
oforD
eriA
gcost. 2D
ays 16 LogisticEA
giA
eer
22 IA
terA
al aA
D
ExterA
alE
isk ID
eA
tificatioA
10D
ays 48
rojectP
aA
ager
23H
etermiA
atioA
ofriskF
roG
aG
ility aA
D
ImF
act 10D
ays 228
rojectP
aA
ager
24H
rawiA
gB F
riskresF
oA
seF
laA
10D
ays 238
rojectP
aA
ager
25
C
B
ilD
iA
gofD
owA
streamstatioA
(G
y aA
ot9
ercomF
aA
y)
(IA
clB
D
es9
osF
ital aA
D
ticket coB A
ter)3mo
A
t9
s 6 Sigma company, Bharath Sigm
26I
A
stallatioA
ofgearsG
B
llw9
eel aA
D
rest of t9
e coA
trol
systemiA
D
owA
streamstatioA
2 mo
A
t9
s 25 X company and Bharath X
27 IA
sF
ectioA
ofD
owA
stream 10D
ays 26 QB
ality EA
giA
eerG
B
r
8/7/2019 TEO12 Final Report Template
16/20
28
S
T
ilU
iV
gofT W
streamstatioV
(X
y aV
otR
ercomW
aV
y)
(IV
clT
U
es ticket coT V
ter)2 mo
V
tR
s 6 Sigma company, Bharath Sigm
29I
V
stallatioV
ofgearsX
T
llwR
eel aV
U
rest of tR
e coV
trol
systemiV
T W
streamstatioV
2 mo
V
tR
s 28 X company and Bharath X
30 IV
sW
ectioV
ofT W
streamstream 10U
ays 29 QT
ality EV
giV
eer,Q
ascR
alG
T
r
31S
otR
statioV
scomW
leteU
0U
ays 27
32Q
reW
aratioV
of tR
e fielU
forW
yloV
s 10U
ays 6 Bharath, Civil engineer
Sit
3 o
33 IV
stallatioV
ofW
yloV
s 10U
ays 32 Bharath, Civil engineerCivil
orker
34 IV
stallatioV
ofW
yloV
sR
eaU
s 15U
ays 33 Bharath, Civil engineer engine
2 e
35 AllW
yloV
siV
stalleU
eV
tirely 0U
ays 34
36 IV
stallatioV
ofmaiV
eV
giV
es 15U
ays 34 Bharath, Civil engineeren
o
37 IV
stallatioV
ofrescT
e eV
giV
e 15U
ays 36 Stphane, Civil engineer1 m
8/7/2019 TEO12 Final Report Template
17/20
engine
38 IY
stallatioY
ofrecovery eY
giY
e 15`
ays 37 Stphane, Civil engineer1 m
engine
39 IY
stallatioY
ofa
ackb c
c
ower 15`
ays 38 Stphane, Civil engineer1 elec
+
40 IY
sc
ectioY
of all eY
giY
es aY
`
c
owerstatioY
s 10`
ays 39 Qb
ality EY
giY
eerG
b
r
41 IY
stallatioY
of eY
giY
escomc
lete`
0`
ays 40
42 IY
stallatioY
of te
e tractorcaa
les 3`
ays 27 Stphane, Civil engineer
1 civi
orke
43 IY
stallatioY
of te
e sb c c
ortiY
gcaa
les 3`
ays 42 Stphane, Civil engineer1 civi
44 IY
stallatioY
ofcaa
le cars 1`
ay 43 Stphane, Civil engineer8 ork
45 IY
sc
ectioY
of allcomc
lete`
iY
stallatioY
20`
ays 44 Qb
ality EY
giY
eerG
b
r
46 We
ole iY
stallatioY
comc
lete`
0`
ays 45
47 IY
stallatioY
testiY
g 5
`
ays 45 Stphane, Civil engineer2 en
8/7/2019 TEO12 Final Report Template
18/20
13.3. f ppend g g h 3: i antt cha p t
13.4.f ppend g h 4: Op q an g r at g s na t stp uctu p e
13.5. f ppend g h 5Tabulati
u v
ofbudgetplan
13.6. f ppend g h 6
Worw
break down structurex
Py
ject Mana er
S
te n
nner
ua
ty n
nner
Mechan
ca
n
nner
ElectricalEn
inner
ivilEn
ineer
gistic Enginner
EO
Hu
an Res
urcesManage
ent
Pr
ject
rdinat
r
8/7/2019 TEO12 Final Report Template
19/20
19
8/7/2019 TEO12 Final Report Template
20/20