Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
A 765 KV substations
1 Ariyalur 2x15002131.45/
1696
91/
07.11.1324 months
31.03.19/
2020-211082.5 396.15 217.35 945.23 576.89 173.88
For transferring
power either way
which have been
pooled at North
Chennai Pooling
station and for
transfer of
interstate Power
RECWorks are under
progress
765 KV DC line from Ariyalur
to Thiruvalam
2X400 KV DC line by making
LILO of 400 KV Pugalur -
Kalivanthapattu feeder at
Ariyalur 765/400 KV SS
2 nos. 765 KV, 240 MVAR Line
Reactors and one no. Spare
reactor with panels and
accessories for Ariyalur -
Thiruvalam line
60.8228/
07.10.1748.64 12.16 38.912 21.89
TENTATIVE CAPITAL EXPENDITURE AND CAPITALISATION OF TRANSMISSION SCHEMES FOR THE FY 2019-20 to 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
2North Chennai Pooling
Station (GIS)3X1500
1483.81 /
909.00
64/
25.07.1524 months
20.03.20/
2020-21545.40 272.70 90.90 163.62 463.59 218.16
Evacuating the
power from
various thermal
power projects in
north chennai
area and meet
the future load
growth of
chennai region.
PFCWorks are under
progress
765 KV DC line from North
Chennai - Pooling Station to
Ariyalur
2427.88/
2133.42
239/
17.10.171000 906.74 226.68 981.348 970.728 181.344 PFC
Works are under
progress
3 Coimbatore 765/400 2455.9874/
03.11.1624 months 2022-23 20.00 243.60 730.79 68.72 341.038
To export the
power from
North Chennai
Pooling station to
Coimbatore
region
REC
Land
registration is in
final stage.
Working
estimate is
under
preparation.
765 KV DC line with Hexa
Zebra conductor from
Coimbatore to Ariyalur 765 KV
SS
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
400 KV DC line with Twin
Moose conductor from
Coimbatore to Edayarpalayam
400 KV SS
2 runs of 400 KV DC line with
Quad Moose conductor for
making LILO of 400 KV DC
Rasipalayam - Palavady line at
Coimbatore 765 KV SS
4 Virudhunagar 765/400-2303713.33/
2129.49
18/
03.03.1824 months 2021-22 245.07 942.21 942.21 49.01 384.498 942.21
For evacuation of
power from
Uppur Thermal
Power Project
and for wind and
solar power
evacuation from
Kayathar,
Kamudhi and
Thappagundu
ADB
Tender opened
on 20.05.19 and
evaluation is
under process
765 KV DC line with Hexa
Zebra conductor from
Virudhunagar 765 KV SS to
Coimbatore SS
Out of 3
reaches, Work
awarded for
Reach-I & II
and tender
under Process
for Reach-III.
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
400 KV DC line with Quad
Moose conductor from
Virudhunagar 765 KV SS to
Kayathar 400 KV SS
Tender under
Process.
400 KV DC line from the
common point of 400 KV DC
Kamudhi - Thappagundu line.
230 KV SC line on DC towers
with Zebra conductor from the
proposed Virudhunagar 765
KV SS to Srivilliputhur 230 KV
SS
230 KV SC line on DC towers
with Zebra conductor from the
proposed Virudhunagar 765
KV SS to Thummakundu 230
KV SS
230 KV SC line on DC towers
with Zebra conductor from the
proposed Virudhunagar 765
KV SS to Savasapuram 230 KV
SS
Balance works 316.77 316.77
Total for 765 KV
(Excluding ADB)2082.5 1916.93 1289.26 1138.46 2129.11 2101.82 914.42
(B) 400 KV Substations
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
1 Thervaikandigai2X315+
1X200576.19
7/
10.02.1218
03.03.14/
31.03.205.00 172.857 172.857
To connect all
the private power
plants which can
be used as an
evacuation hub
with connectivity
to major 400 kV
substations for
power
evacuation, to
meet out the
rapidly increaing
load demand of
Chennai city and
for effective load
management.,
REC
SS Charged on
15.04.16 at 230
kV level.
400 kV line
works are under
progress.
2 Thennampatty2x315+
2x200418.88
190/
08.10.1418 Months
24.07.17/
30.05.19
For evacuation of
wind powerKfW
SS charged on
05.11.19.
Privision given in
kfw Schemes.
3 Vellalavidudhi (Pudukkottai)2x315+
2x200
909.19
/637.67
80/
11.12.1515 2020-21 20 118.10 362.61 136.96 43.62 167.002 317.48
For system
strengtheningPFC
Work under
Progress.
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
4 Pulianthope 3x315558/
495.13
83/
06.11.1318
02.02.20/
20-21 -- 176.22 269.39 49.51 35.244 194.854 225.414
To provide
System stability
in North and
Central EDCs.
REC
Works are under
progress for
Substations and
Liness.
5 Edayarpalayam2x315 +
3x200433.02
189/
10.08.1718 2021-22 40.00 117.91 157.21 8 55.58 125.77
For System
strengthening for
disposal of power
received from
Chattisgarh
REC
Board note for
award of
Contract
approved on
22.11.19.
6 Taramani (UG)2x500 +
2x200+ 2X50707.88
215/
15.12.1618 2021-22 35.39 212.36 283.15 77.866 226.518
To export the
power from
North Chennai
Generating
Stations to
Chennai South
Region.
REC
Work awarded
on 30.11.19. SS
Cost : Rs.413.56
Cr.
7 Ottapidaram2x500+
2x200
1038.9/
755.86
5/
03.02.1818 2021-22 37.79 302.34 302.34 98.2618 302.344
For evacuation of
power from
Udangudi
Thermal Power
Project and
renewable
power.
ADB
Work awarded
to M/s.L&T on
09.11.19
including 2 nos.
400 KV Lines
from
Ottapidaram to
Kamudhi and
Udagudi.
Awarded Value
Rs.715.86 Cr.
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
8 Samugarengapuram2x500+
2x200599.65
17/
03.03.1818 2022-23 59.97 239.86 107.942
To avoid
congestion in 110
KV and 230 KV
lines in
evacuation of
about 1800 MW
of wind power
in Aralvoimozhi
Pass.
MNRE
Tender will be
floated on
approval from
MNRE.
9 Parali
2 sets of
3x166.66
and one
spare unit
429.7821/
05.03.1918 2022-23 42.98 171.91 77.3604
For evacuation of
power from
Kundha Pumped
Storage Hydro
Electric Project
REC
Working
estimate is
under
preparation to
float Tender.
10 Manalmedu
11 Koyambedu GIS SS REC
12 Cuddalore
13 Arani
Sanction awaited schemes
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
14 Mangalapuram
15 Vadamadurai
16 Viswanathapuram
17 Sholinghur
18 Alagarkoil
19 S.P.Koil
20 Mathur
400 KV UG cable for Guindy
and Manali1200.00 2021-22 360.00 480.00 360.00
Associated lines
of Guindy and
Manali
Tender opened
on 30.03.19 and
under
evalauation
For sanction awaited schemes 50.00 100.00
Total for 400 KV SS -
Excluding Schemes under ADB20.00 369.72 1480.22 1618.61 106.86 668.16 1613.34
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
1 Korattur (JICA)2x500+
2x200511.30
55/
25.10.1218 2021-22 25.57 153.39 204.52 5.113 51.13 163.616
To strengthern
the Chennai
Network.
JICATender under
process
2 Guindy (JICA) 2x315
756.52/
(231.00+10
8.40)
55/
25.10.1218
25.06.20/
2020-2184.00 167.10 88.30 117.42 151.34 70.64
To strengthern
the Chennai
Network.
JICAWork under
progress.
400 kV Total 84.00 192.67 241.69 204.52 122.53 202.47 234.26
400 KV SS -JICA SCHEMES
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
( c )
1 Udanapally 2X100 168.06109/
28.10.142019-20 77.50 90.56 95.612 72.448
To meet the
future load
growth of
Krishnagiri
District due to
formation of SEZ
and Hokennakkal
Combined water
scheme.
PFCTest Charged
on 23.06.19
2 Thuvakudi 2x100 117.0050/
21.05.1512 2019-20 5.85 40.95 46.80 23.40 14.04 42.12 42.12
In order to give
load relief to
Trichy, Thanjavur
and Alundur 230
kV substations,
to extend supply
to the intending
HT consumers
and to meet the
future load
growth in and
around
Thuvakudy.
TNIPP-IIWorks are under
progress
3 Samayanallur 2x100 83.8959/
23.07.1512 2019-20 14.17 52.94 16.78 24.7584 45.7092 13.4224
In order to give
load relief to the
existing 230 kV
substations at
Alagarkoil and
Pasumalai and to
meet the future
load growth in
and around
Madurai
area.
RECWorks are under
progress.
230 KV SUB STATIONS WITH ASSOCIATED LINES- NON JICA SCHEMES
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
4 Narimanam 2x100 90.3167/
27.07.1515 2021-22 1.00 36.12 36.12 8.2248 36.124
To give load
relief to
Tiruvarur,
Kadalangudi and
Kumbakkonam
230 KV
Substations and
to facilitate
operation
flexiblities and
alternate feeding
arrangements for
the existing
substations and
to meet the
future load
growth.
PFC
Tender to be
Lodged. Re
tender to be
floated.
5 Sankarapuram 2x100 177.9410/
04.02.1615 months 06.08.19 50.00 88.90 25.40 12.70 67.78 76.2 22.86
To avoid
overloading to
give load relief to
110 KV
Vilupuram -
Deviakurichi
feeder for
operational
flexibilities to
strengthern the
infrastructure
facilities for
power evacuation
and to have N-1
Criteria as per
CEA Norms.
RECWorks are under
progress
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
6 Tiruppathur 2x100 148.1612/
04.02.1615
18.06.19/
31.03.2045 73.53 29.63 59.7056 64.7488 23.7056
To give load
relief to
Singarapet and
Vinnamangalam
230 KV
Substations and
to meet the
future load
growth in and
around
Tiruppathur area.
PFCWork under
progress
7 Thiruvanmiyur GIS (UG) 2x100 179.89137/
16.08.1612
24.05.19/
31.03.2035.98 71.96 71.96 7.1956 43.1736 71.96
In order to
accommodate
the future load
growth in and
around
Thiruvanmiyur
area and to give
load relief to
Thiruvanmiyur
33/11 kV SS and
near by
substations.
TNIPP-IIWork under
progress
8 Mambalam GIS 2x160 92.8236/
06.03.1412 2020-21 1.50 27.40 36.53 27.40 6.9792 29.2224 34.70
To provide load
relief to
Nandanam,
Kodambakkam
and
Valluvarkottam
110 KV
substations
RECWork under
progress
9 Karuppur 2x100 72.5152/
30.08.1712 2020-21 10.00 26.26 29.00 7.25 15.25 26.80 24.65
To provide load
relief to Salem
230 KV SS and
K.R.Thoppur 400
KV SS
RECWork under
progress
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
10Singarapet
(Replacement for existing SS)2X160 63.52
115/
15.07.1512 31.03.20 3.00 25.41 25.41 9.70 8.08 25.41 22.27
System
strengtheningREC
Work under
progress
11 Selvapuram (Puttuvikki) 2x100 64.3555/
06.09.1612 23.10.19 5 27.18 19.31 12.87 10.435 25.60 18.018
In order to give
load relief to
near by
substations and
to meet the
future load
growth.
RECWork under
Progress
12 Erode GIS 2x100 80.265/
11.01.1712 30.09.20 24.08 32.10 24.08 4.8156 25.6832 30.50
To provide load
relief to Ingur,
Gobi, Thingalur
and
Pallakkapalayam
230 KV
substations and
to meet future
load growth.
REC
Work awarded
on 08.03.19 and
under Progress.
13 Ganesh Nagar GIS - 230/33 2x100 93.86 50/
30.08.17 12 2020-21 28.16 56.32 2.8158 36.61
To provide load
relief to nearby
substations and
to meet future
loads.
PFCTender under
Process.
14 Avadi 2x100 102.83 54/
30.08.17 2020-21 5.14 30.85 30.85 6.1698 30.849
To provide
flexibility in
operation and to
meet future load
growth.
TNIPP-II
SS -Tender
under process.
230 KV Line
works are in
progress.
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
15 Maraimalai Nagar 2x100 110.35 2/
19.01.18 2020-21 5.52 33.11 33.11 6.621 33.105
To provide load
relief to existing
230 KV
substations and
to meet future
load growth
PFC
Tender under
process. 230 KV
Line works are
in Progress.
16 Sathumadurai 2x160 255.2350/
03.08.182021-22 2.55 76.57 102.09 15.3138 81.6736
To provide load
relief to
Thiruvalam,
Singarapet and
Vinnamangalam
230 KV
substations and
to meet future
load growth
PFC
Tender under
Process for Civil
works. Tender
to be opened on
18.12.19 for SSE
Works.
17 Kalivelampatty 2x100 117.7261/
04.10.182020-21 5.89 35.32 47.09 12.9492 37.6704
To provide load
relief to Arasur
and Palladam
230 KV
Substations and
to meet future
load growth in
and around
areas.
REC
Civil work
awarded. For
SSE works
Tender is being
finalised.
18 Nanguneri 2x100 135.7063/
04.10.182021-22 40.71 54.28 8.142 43.424
To avoid
overloading of
Kayathar 230 KV
SS and 110 KV
Melakallur -
Sankaneri feeder.
PFC
Tender opened
on 31.10.19 and
evaluation is in
Process.
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
19 Vembakkam 3x100 84.2060/
04.10.182021-22 25.26 33.68 5.052 26.944
To provide load
relief to Arani
230 KV SS and to
meet future load
growth
PFC
NIT Issued and
tender to be
opened on
21.12.19
20 Mambakkam 2x100 137.3759/
04.10.182021-22 41.21 54.95 8.2422 43.9584
Tprovide load
relief to S.P.Koil
230 KV
substation and to
avoid overloading
of 110 KV
S.P.Koil - Siruseri
and 110 KV
Veerapuram -
Thiruporur
feeders and to
meet future load
growth.
PFC
Tender opened
on 15.10.19 and
under process.
21 Nallur 155.0303/
10.01.19
2020-21/
2021-221.55 46.51 62.01 10.8521 49.6096 PFC
NIT Issued and
tender to be
opened on
19.12.19
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
22 K.Pudur (GIS) 2x100 320.49 36/
17.06.17 12 2021-22 32.05 160.25 6.4098 57.6882
To provide load
relief to 110 KV
feeders feeding
Madurai area and
to provide
reliable supply to
33 KV
substations
feeding Madurai
city.
PFC
Working
estimate is
under Scrutiny
for floating
tender.
23 K.K.Nagar (GIS) 3x100 333.13 87/
04.06.18 12 2021-22 66.63 133.25 13.3252 79.9512
To provide load
relief to Guindy
and Koyambedu
230 KV
substations, to
provide flexibility
of operation and
to to provide
alternate feeding
arrangements to
the existing
substations for
providing
uninterrupted
supply.
REC
NIT issued with
due date of
opening on
30.12.19.
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
24 Poolavady 2x100 107.3249/
06.09.162021-22 10.73 42.93 2.1464 17.1712
In order to give
load relief to
near by
substations and
to meet the
future load
growth.
MNRE
Proposed under
GEC Phase-II.
MNRE approval
awaited.
25 Ennore GIS2x100+
2x50+2x16116.42
181/
01.08.172021-22 11.64 46.57 2.3284 18.6272
To shift the
existing 230 KV
ETPS SS to a
new location in
the vacant space
availble at
Ennore 110 KV
SS to provide
start up power to
the proposed
power plants and
to extend supply
to Railway
Traction SS.
PFCNIT to be
issued.
26 Durainallur 2x100 60.35 51/
30.08.17 2021-22 6.04 18.11 1.207 8.449
To provide load
relief to Alamathy
and Manali 400
KV substations
TNIPP-II
Due to issues
involved in
existing land,
revised proposal
at Panjetty is
under process
27Rajagopalapuram GIS -
230/332x100 123.02
24/
07.05.18 2021-22 12.30 36.91 2.4604 17.2228
To avoid
overloading of
Kayathr 230 KV
SS and to
improve voltage
profile
PFC
Estimate is
under
preparation.
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
28 Muppandal 3x100 66.30 38/
30.06.18 2021-22 6.63 19.89 1.326 9.282
To have separate
corridor for wind
generators and
to avoid grid
congestion due
to wind power
evacuation
MNRE
Proposed under
GEC-II. Tender
will be floated
on approval
from MNRE.
29 Pallavaram GIS 3x100 184.5351/
03.08.182021-22 18.45 55.36 3.6906 25.8342
To provide load
relief to
Kadapperi 230
KV SS, to avoid
overloading of
110 KV
Kadapperi -
Pallavaram
feeder and to
meet future load
growth.
PFCNIT is to be
issued.
30 Thuckalay GIS SS 2x160 366.6362/
04.10.182021-22 36.66 109.99 7.3326 51.3282
In order to
enable wind
power evacuation
to avoid over
loading, to
provide
uninterrupted
supply and to
meet the load
growth
PFC
Estimate is
under
preparation.
31 Saravanampatty 3x100 188.3338/
09.08.192021-22 18.83 56.50 3.7666 26.3662
To provide Load
relief to NEAR BY
230 kv
Substations such
as,
Arasur,Karamadai
,Thudiayalur
,Karuvalur and
Coimbatore.
To be
tied up
Estimate is
under
preparation.
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
32 Kongalnagaram MNRE
Proposed under
GEC-II.
Load flow study
completed.
33 Edapady
34 Kondhagai
35 Srivilliputhur
36 Mathur
37 Thummakundu
38 Palani
39 Vedasandur
Sanction awaited schemes
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
40 Thindivanam
41 Virudhachalam
42 Ranipet
43 Vadakathipatty/ Pernampet
44 Mariputtur
45 Palayamkottai
46 Thiruppalai
47 Kalavai
48 Vadapathimangalam,
49 Velliyanai (Sankaramalaipatty)
50 Chinnasalem
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
51 Chidambaram (Thunisiramadu)
52 Polur/Mangalam
53 Aavanam
54 Uthayapatty
55 Nandhimangalam
56 Kalugoundapalayam
57 Sandinallah
58 Aavin
59 Augustinpatty
60 Kanagavallipuram
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
61 Chengapally
62 Chinnayampalayam
63 Irugur
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
Total amount for Sanction
awaited schemes25.00 50.00
Total for 230 KV -Non JICA 534.82 971.69 1429.59 314.65 605.49 1036.09
1 Thiruppur 2x10039/
25.10.1112 2019-20 9.50
To accommodate
future load
growth in
Tiruppur area
2 Shenbagapudur 2x10021/
14.06.1112 2019-20 9.50
In order to avoid
overloading of
110 KV Feeders
and to
accomodate
future load
growth in Gobi
area.
3 TNEB HQtrs 2x100 71.3968/
11.04.072019-20 35.70 21.42 7.139 32.8394 17.1336
To augment the
power needs of
Chennai city and
to strengthen the
230 KV and 110
KV network
JICAWork under
progress
230 kV JICA - Total 19.00 63.00 33.12 0.00 31.60 57.02 26.49
9.36 JICA
230 KV - JICA Schemes
(75.54+
77.66)/
58
27.30 11.70 24.46 24.18
SS Works are
under progress.
230 kV line
works are under
progress.
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
110 KV SUB STATIONS
110 KV Substations
- 40 nos.
Various
approvals19-20 62.00 200.00 102 160 REC/PFC
110 KV Substations
- 40 nos.
Various
approvals20-21 350.00 70 280 REC/PFC
110 KV Substations
- 40 nos.
Various
approvals21-22 350.00 70
110 kV Total 200.00 350.00 350.00 102.00 230.00 350.00
1765 KV DC line from Uppur to
Virudhunagar.810.00 2022-33 8.10 162.00 40.5
For evacuation of
power from
Uppur Thhermal
Power Project.
Administrative
approval
awaited
2
765 KV SC line from NCTPS
Stage -III to North Chennai
Pooling Station
8 99.87 2020-21 49.94 39.95 9.99 9.987 47.9376 33.9558Work in
Progress
To improve the
voltage
regulation,
reduce the line
loss, provide load
relief to the
existing
substations, to
meet the future
load growth in
and around the
area , to provide
33 KV source to
new 33KV
Substations and
to extened
EHT/HT Supply.
Power Evacuation lines
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
3
765 KV SC line from Ennore
Replacement to North
Chennai Pooling Station
2023-24
4
765 KV SC line from Ennore
Replacement to NCTPS Stage-
III
2023-24
5
Erection of 400 KV DC
transmission Line with Quad
Moose conductor from
Udangudi Pooling Station to
Virudhunagar 765/400 KV SS.
150 630.00 2021-22 31.50 189.00 69.3
For evacuation of
power from
UDANGUDI
Thermal Power
Project.
REC
To avoid
overloading of
Kayathar 400 KV
SS, 400 KV DC
line is proposed
from Udangudi
to Kayathar.
Proposal being
sent to Standing
Committee for
approval.
6400 KV DC line from Kamudhi
to Thappagundu370 660.97
262/
09.11.172020-21 66.10 198.29 13.2194 92.5358
For renewable
power EvacuationMNRE
Tender will be
floated on
approval from
MNRE
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
7
400 KV DC/MC line with Quad
Moose conductor from
(i)Ennore SEZ 400/230 KV
switchyard to North Chennai
765 KV Pooling station (ii)
Ennore SEZ 400/230 KV
switchyard to ETPS Expansion
400/230 KV switchyard (iii)
ETPS Expansion to North
Chennai Pooling station (iv)
Interconnecting line from
Common point AP 23 of SEZ -
Expansion line to NCTPS Stage
-II
Work under
progress
8
400 KV DC line with Quad
Moose conductor for making
LILO of 400 KV NCTPS -
Sunguvarchatram line at the
proposed SEZ 400/230 KV
switchyard for start up power
9
400 KV DC line from Kadaladi
Solar Park to Kamudhi 400 KV
SS
35 140.00 2021-22 7.00 28.00 12.6
For power
evacuation from
Kadaladi Solar
Park
Sanction
awaited
10230 KV DC line from Kundha
PH-VIII - Geddai - PH III
Included in
Parali SS B.P
11230 KV and 110 KV power
evacuation lines50.00 50.00 50.00 60.00 50.00
234.94 371.54 637.28 52.99 262.94 434.00
16.00 135.00 141.778168.89 43 135.112
for evacuation of
power from the
propsed Thermal
Projects in North
Chennai area.
PFC72.894 319.89 2019-20
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
B
230 KV and 110 KV
Improvement and link lines
Various
approvals100.00 150 100
230 KV and 110 KV
Improvement and link lines150.00 30 120
230 KV and 110 KV
Improvement and link lines150.00 30
230 KV and 110 KV
Improvement and link
lines - Total
100.00 150.00 150.00 150.00 130.00 150.00
IMPROVEMENT AND LINK LINES
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
SCHEMES UNDER KfW
FUNDING
1555/
1733.828
190/
08.10.14
Pack
age-I
400KV SS at Thennampatti
(Pavoorchatram)
Commissioned
on 05.11.19
Pack
age-II
Establishment of 400 kV DC
Line from Kayathar to
Thenampatti for a length of 24
km and 4 Nos. Bay extensions
at Kayathar 400 kV SS
Line energised
Pack
age-III
400 KV DC Line connecting
Rasipalayam & Singarapet and
2 Nos 400 KV bays
866.914 693.5312Works are under
progress.
Pack
age-IV
230 KV transmission lines
connecting various sub-
stations in Tirunelveli,
Madurai, Coimbatore region &
13 Nos 230 KV bays
Works are under
progress.
Pack
age-V
Augmentation of
transformation capacity at 6
sub-stations
Works are under
progress.
1041 400.00 293.00 0.00 912.8 378.6 234.4
1041 400.00 293.00
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
Schemes under ADB
Funding
Package
Cost Rs. In
Crs.
Pack
age-I
Ottapidaram 400 KV SS with 2
nos. DC Lines715.86
Work awarded
on 09.11.19.
Pack
age-VII
Associated 230 KV and 110 KV
Lines of Ottapidaram 400 KV
SS
40.00
Technical bid
opened on
27.11.19 and
under process.
Pack
age-IIVirudhunagar 765 KV SS 534.00
Pack
age-III
400 KV DC line from Kayathar -
Virudhunagar 765 KV SS - 72
Kms.
235.10
Pack
age-IV
765 KV DC Line from
Virudhunagar to Coimbatore
765 KV SS - Reach-I - 85
Kms
422.79
Work awarded
to M/s.Kalpataru
Power
Transmision Ltd.
Pack
age-V
765 KV DC Line from
Virudhunagar to Coimbatore
765 KV SS - Reach-II - 85
Kms
422.62
Work awarded
to M/s.KEC
International
Ltd.
Pack
age-VI
765 KV DC Line from
Virudhunagar to Coimbatore
765 KV SS - Reach-III - 72
Kms
514.81
Price bid opened
and evaluations
results sent to
ADB for their
concurrence.
Total for ADB Schemes 2885.18 282.86 1244.55 1244.55 49.01 482.76 1244.55
37.79 302.34 302.34 98.2618 302.344
Price bid opened
and evaluations
results sent to
ADB for their
concurrence.
245.07 942.21 942.21 49.01 384.498 942.21
Item No. Location
Capacity for
SubStation/
Length for EHT
Lines in Ckm
Construction
Schedule in
months
Date of
Completion
(Actual/
Anticipated)
Justification Funding Present status
Scheme
/Awarded
cost
Rs in Crs
B.P.No. 2019-20 2020-21 2021-22 2019-20 2020-21 2021-22
Initial Approved capital
Cost (Rs.Crs.)
with B.P. No.Expenditure
already incurred
- Rs. In Crs.
CAPEX Rs. In Crs CAPITALISATION Rs.in Crs
OTHERS
1Additional/ Enhancement of
Transformers
600
(approx)
Various
approvals150.00 150.00 150.00 150.00 150.00 150.00
2 TRANSCO Building 56.92 26.00 24.74 6.18 30.95 25.97
3 Capacitor Bank 17.55 1.50 12.54 3.51 4.01 10.73 2.808Work in
Progress
4 Reactors 62.82 3.14 50.26 9.42 12.56 42.09 PSDFWork awarded
on 11.10.19
5Quarters at Guindy and
Korattur10 & 7 2.00 8.70 6.30 3.74 8.22
Work awarded
for Qtrs at
Guindy and
tender to be
floated for Qtrs
at Korattur.
6SE/GCCs Office
(Trichy and Coimbatore)4.45 & 5.2 6.73 1.346 5.38
7Construction of Tr. Repair Bay
at Arasur5.24 2.00 3.24 2.00 3.24
Balance works of
commissioned/on going
Substations of 110 KV and
above and Emergency work in
nature
400
(approx)100.00 100.00 100.00 20.00 100.00 100.00
Total of Substations and
Lines4597.30 6743.72 7038.73 4179.86 5430.89 6540.67