98
1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS OF INDIA. Architects: M/s. SHASHI DESHMUKH & ASSOCIATES Architects, Regd. Valuer & Int. Designers. 102, Konark Towers, Opp. Saibaba Temple, Ghantali Road, Thane(W)-400602. Ph. 25333191, 25334420, 25369467. Fax: 25332025 Structural Consultants: M/s. EPICONS CONSULTANTS Pvt. Ltd. 216/A, Margin Complex, Opp. S.T. Workshop, L.B.S. MARG, Khopat, Thane (W) - 400 601 Phone- 022-25475334, 25471144

TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

  • Upload
    others

  • View
    16

  • Download
    0

Embed Size (px)

Citation preview

Page 1: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

1

TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND

WALL OF INSTITUTIONAL BUILDING

At Navi Mumbai

FOR

THE INSTITUTE OF COST ACCOUNTANTS OF INDIA.

• Architects:

M/s. SHASHI DESHMUKH & ASSOCIATES

Architects, Regd. Valuer & Int. Designers.

102, Konark Towers, Opp. Saibaba Temple,

Ghantali Road, Thane(W)-400602.

Ph. 25333191, 25334420, 25369467.

Fax: 25332025

• Structural Consultants:

M/s. EPICONS CONSULTANTS Pvt. Ltd.

216/A, Margin Complex, Opp. S.T. Workshop,

L.B.S. MARG, Khopat,

Thane (W) - 400 601

Phone- 022-25475334, 25471144

Page 2: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

2

I N D E X

SECTION PAGE

NOS.

INDEX 2-2

PREFACE

3-3

SECTION 1 : INVITATION TO TENDERER

4-5

SECTION 2 : INSTRUCTIONS FOR FILLING IN TENDER

6-7

SECTION 3 : LETTER OF SUBMISSION

8-9

: APPENDIX TO TENDER 10

SECTION 4 : ARTICLES OF AGREEMENT

11-12

SECTION 5 : GENERAL CONDITIONS OF CONTRACT

13-34

SECTION 6 : SPECIAL CONDITIONS OF CONTRACT &

ANNXEURE A,B&C

35-50

SECTION 7 : STANDARD SPECIFICATION

51-69

SECTION 8 : SAFETY SPECIFICATION

70-71

SECTION 9 : SAFETY INSTRUCTION

72-77

SECTION 10 : ANTI – TERMITE TREATMENT

78-79

SECTION 11 : SPECIFICATION – PILING 80-85

SECTION 12 : ANNEXURES 86-92

SECTION 13 : BASIC RATES 93

SECTION 14 : BILL OF QUANTITIES - FOR PILING 94-95

SECTION – 15 : SOIL TEST REPORT

SECTION – 16 : DRAWING

Page 3: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

3

P R E F A C E

1. THE INSTITUTE OF COST ACCOUNTANTS OF INDIA (CMA Bhavan,12,

Sudder Street, Kolkata -700016) intends to construct institute building, At Navi

Mumbai. The recent tender is for construction of the piling work of underground tank

& compound wall of Institute building enumerated in the scope of work.

2. ‘SHASHI DESHMUKH & ASSOCIATES are the Architects for the work. Architects

shall provide drawings details and specifications including all service drawings

necessary for the project execution and also provide acceptance oriented inspection of

the work.

3. The Institute of Cost Accountants of India shall finance the project, and is the ultimate

owner. The Owner / Architect provide overall supervision and inspection and check the

measurement of the work done by the contractor, as per contract conditions.

4. M/s. Epicons Consultants pvt. Ltd. are the structural Consultants. They shall interpret

the document; provide acceptance oriented inspection of the work along with architect.

5. All right regarding ownership and use of drawings, specifications, reports, etc. prepared

by the Architects and Consulting Engineers are reserved by them. Such drawings,

specifications, reports etc. issued to the contractors shall be used only for the work

specified herein and are liable to be recalled.

Owner Contractors

Page 4: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

4

SECTION - 1:

INVITATION TO TENDERER

Sealed item rate un-conditional tenders are invited from contractors of repute, having adequate

resources, well established in the line and experienced in the execution of similar General works

of comparable magnitude for the following work :

1. a Name & Nature of Work : Piling of underground tank & compound wall

of Proposed Institute Building

The Institute Of Cost Accountants Of India ,

CMA Bhavan,12, Sudder Street, Kolkata -

700016.

b Location : Navi, Mumbai – 400 708

c Time of Completion : Two Calendar months including

Monsoon.To be counted from date

Of issue of Letter of Intent

2 Tender document will be available in the website of the Institute www.icmai.in from

10th June 2015 to 17th June 2015 as well as from the office of the Architects at the

address given below on payment of Rs.5,000/- in way of Demand Draft in favour of

The Institute of Cost Accountants of India” payable at Kolkata

ARCHITECTS: SHASHI DESHMUKH & ASSOCIATES

102, Konark Towers, Opp. Saibaba Temple,

Ghantali Road, Thane(W)-400602.

Ph. 25333191, 25334420, 25369467.

Fax.: 25332025

3 Pre-bid meeting will be held in Architect’s office on 12th June 2015 at 11.00 a.m. The

contractors compulsorily need to attend the pre-bid meeting or otherwise they will be

dis-qualified.

4 Sealed Tenders shall be received at the office of the Architect on the above mentioned

address not later than 4.00 p.m. on 17th June 2015.

5 The contractor shall also enclose Earnest Money Deposit in the form of DD/Pay Order/

from Nationalized Bank in favour of ‘The Institute of Cost Accountants of India’

payable at Kolkata amounting to Rs. 35,000.00. This deposit shall be refunded after

Page 5: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

5

the owners have awarded the work to one successful contractor, whose deposit shall be

adjusted against security deposit.

6 Tenders shall be valid for acceptance for full period of completion of the project from

the last date of submission.

7 The owner, The Institute of Cost Accountants of India, reserves the right to reject any

or all the tenders and accept the lowest or any other tender without assigning any

reasons therefore.

Owner Contractor

Page 6: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

6

SECTION - 2:

INSTRUCTIONS FOR FILLING IN TENDER

1. The tender shall be submitted in accordance with these instructions and any Tender not

conforming thereto is liable to be rejected. These instructions shall form part of the

Tender and the Contract. Bidder should submit Two Sealed Envelopes separately

(Financial & Technical)

2. Bid Criteria, Volume I will be opened first & regular tender will be opened of those who

are eligible in the first bid

3. The Tender documents which will be issued to each tenderer comprise these

instructions, Tender with Appendices, Conditions of Contract, Form of Agreement,

Specifications, Bill of Quantities and Drawings, Each Tenderer shall be furnished one

complete set of above tender documents.

4. The tender shall be filled in, signed with all particulars complete and submitted by one

duly authorized to do so. The Tenderer shall satisfy the Owner that he is competent and

authorized to submit the tender and/or to enter into a legally binding contract with the

Owner by furnishing documentary evidence to that effect.

5. The Tender shall be complete with all the documents set out in para 2 above and other

documents set out in these instructions and elsewhere in the Tender documents. In

particular, the Tenderer shall complete and submit the following for his tender to be

considered as bonfire :

Form of Tender with Appendix.

a. Bill of Quantities and its Abstract, each page duly signed.

b. List of Plant/Equipment and Personnel to be employed on the works.

c. Details of other works tendered for and on hand on the date of Submission of tender.

6. The Owner reserves the right to adjust arithmetical or other errors in the tender in

accordance with the following general rules. In the event of discrepancy between words

and figures quoted, the description in words shall prevail. Similarly in the event of an

error in the amount column arising as a result of wrong extension, the unit or item rates

shall be regarded as firm and extension amended accordingly.

7. This is an item rate measurement contract based on priced Bill of Quantities. The item

rates shall be valid for the entire duration of the contract and / or extension thereof.

Tenderers shall note that the prices and rates inserted in the Bill of Quantities, are to be

the full inclusive value of works described under each item including all costs and

expenses including Govt. levies, royalties, taxes, duties & octroi etc., which may be

required in, and for the construction of the works described whether specifically

Page 7: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

7

mentioned or not. However liabilities against all such levies shall be shown separately in

Tender. The tender rates shall also include all general risks liabilities and obligations set

forth or implied in the documents on which the tender is based. The Owner will not be

responsible for or pay for expenses or losses which may be incurred by any Tenderer in

the preparation and submission of the Tender, or in any activity connected therewith. As

soon as the successful tenderer is advised of the award of the contract to him all future

expenses and all taxes etc. to be incurred by him shall be deemed to be covered by the

prices quoted in his tender.

8. The tender shall remain valid for full period of completion of the project from the last

date of submission unless otherwise stipulated in the Tender Notice. Any tenderer

withdrawing or amending his tender within this period shall forfeit his earnest money to

the Owner.

9. Before tendering, the Tenderer shall visit the site of works and in any case shall be

deemed to have done so in order to acquaint himself with the nature of the site and the

conditions in which the works are to be executed.

10. The tender documents duly completed in all respects along with Tender drawings (if any)

and all other accompanying documents shall be submitted and delivered as required in

the Tender Notice in a plain sealed envelope superscribed "Tender For Educational

Building For M/s.“The Institute Of Cost Accountants of India”

11. Owner have a right to increase or decrease the quantity than mentioned in the tender for

which no compensation will be paid to the tenderer.

12. The Bill of Quantities is inclusive of Piling Work. Bill of Quantities for Piling &

Specification is the part of the agreement.

Page 8: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

8

SECTION - 3:

LETTER OF SUBMISSION

Note : All blanks to be filled in by the Tenderer.

To,

The Institute of Cost Accountants of India

CMA Bhavan, 12, Sudder Street, Kolkata -700016.

Gentlemen,

TENDER FOR PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF

PROPOSED INSTITUTIONAL BUILDING, NAVI MUMBAI –

1. Having inspected the site and having examined the Drawings, Conditions of Contract,

Specifications, Bill of Quantities for the above named work and having obtained required

clarifications, we the undersigned offer to carry out the entire work for the sum of Rs.

________________ ( Rupees __________________________Only.) or such other sum as

may be ascertained in accordance with the said conditions, all in conformity with the said

Drawings, Conditions of Contract, Specifications, Bill of Quantities hereto.

2. We undertake, if our Tender is accepted, to commence the works and complete and deliver

the same within the time stipulated in the tender.

3. We agree to abide by this tender for full period of completion of the project from the date

fixed for receiving the same and it shall remain binding on us and may be accepted at any

time before the expiry of that period and or before the expiry of any further period extended

by mutual consent in writing.

4. Until and Unless a formal Agreement is prepared and executed, this tender, together with

your written acceptance thereof, shall constitute a binding contract between us together with

all the conditions of contract, specifications, bill of quantities and price, drawings and

instructions to tenderers.

Page 9: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

9

We understand that you are not bound to accept the lowest or any other tender you may

receive without giving any reason.

5. We enclose herewith a DD/ Pay Order/Bank Guarantee from Nationalized Bank

amounting to Rs.35,000.00 of tender value in favour of The Institute of Cost Accountants of

India’ payable at Kolkata towards Earnest Money Deposit.

Signature of Contractor

Date :

(Authorized Signatory)

Address :

Page 10: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

10

APPENDIX TO TENDER

1 Security Deposit : 5% of the contract value. Balance Security

Deposit after adjustment of EMD i.e. Rs.35,000/-

for the successful bidder to be paid to the Owner

within 14 days from the date of the date of

issuance of the formal Work Order by way of .

D.D. / Pay Order/Bank Guarantee from

Nationalized Bank.

Note 1: 100% of the initial security deposit i.e. 5% of the contract value shall be refunded

within 14 days of the issue of the defects liability certificate. .

Note 2: Retention money will be refunded on issue of no defects certificate to be made after

Liability Period.

2 Defect Liability Period : 12 Months

3 Retention Money 5% amount will be deducted from

Each running bill duly certified by Architect,

which will be distinct from initial security

deposit.

4 Refund of Retention Money : Retention money will be refunded after expiry of

Defect Liability Period i.e. six months from

virtual completion of the work.

4 Time of Completion : 2 Calendar Months including monsoon

5 Period of Mobilization : Seven Days from date of Letter of Intent

6 Amount of Damages : The time is the essence of this contract and if the

contractor fails to complete the work in period

as mentioned in column ‘4’ above ___ (2)

months time from the date of issuing Letter of

Intent, the owner will be entitled to recover

Penalty from the contractor for the delay @

0.5% of the total value of the contract per week

subject to a maximum of 5% of the total value of

the contract.

The above is with prejudice to the owner's right

to recover damages from the contract for breach

of any of the conditions of the contract elsewhere

provided.

7 Interim Payment : Adhoc payment of 70% of the bill submitted by

the Contractor on the basis of joint measurements

of work done within a 14 days after date of

receipt of bill & balance 30% within a month

thereafter.

Page 11: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

11

8 Period of Submission of Final

Measurements & Valuation

: 15 Days

9 Period of Final Payment : 1 Months thereafter

SECTION - 4

ARTICLES OF AGREEMENT

made the ________ day of ______________ between The Institute Of Cost

Accountants Of India. CMA Bhavan, 12, Sudder Street, Kolkata -700016. (hereinafter called

"the Owner") of the one part and M/s. ___________________ (Hereinafter called "the

Contractor") of the other part.

Whereas the Owner is desirous of Awarding the Construction of Building (Hereinafter called

"the Work") at _________________________, NAVI MUMBAI -

And has caused Drawings and Bills of Quantities showing and describing the work to be done to

be prepared by or under the direction of ARCHITECTS.

And whereas the Contractor has supplied the Owner with a fully priced copy of the said Bills of

Quantities(which copy is hereinafter referred to as "the Contract Bills") and whereas the said

Drawings (hereinafter referred to as "the Contract Drawings") and the Contract Bills and

Contract Drawings have been signed by /and on behalf of the parties hereto and whereas the

Contractor has deposited the sum of Rs. _________________ (Rupees

______________________ Only.) with the Owner towards the Security Deposit for the due

performance of this Agreement.

Page 12: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

12

NOW IT IS HEREBY AGREED AS FOLLOWS :-

1. For the consideration hereinafter mentioned the Contractor will subject to the Conditions

annexed carry out and complete the Work shown upon the Contract Drawings and

described by or referred to in the Contract Bills and in the said Conditions.

2. The Owner will pay the Contractor the sum of Rs. ___________________ (Rupees

__________________________ Only.) (hereinafter referred to as "the Contract Sum") or

such other sum as shall become payable hereunder at the time and in the manner

specified in the Conditions annexed.

3. The term "the Architect" in the said Conditions shall mean the said M/s. SHASHI

DESHMUKH & ASSOCIATES. or in the event of his ceasing to be the Architect for

the purpose of this Contract, such other persons as the Owner shall nominate for that

purpose, and it is hereby declared that the owner shall be entitled at its discretion to

terminate the appointment of the Architect for the time being and to nominate another

one in his place instead, with notice to the contractor.

4 The Conditions annexed and Appendix thereto shall be read and construed as forming

part of this contract Agreement, and the parties hereto shall respectively abide by, submit

themselves to the conditions and perform the agreements on their parts respectively in

such Conditions contained.

AS WITNESS our hands this day of 2015

Signed by the Owner

in the presence of

Witness

Name:

Address:

Signed by the Contractor

in the presence of

Witness

Name:

Address:

Page 13: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

13

--------------------------------- ---------------------------- (Signature of the Contractor) (Signature of the Contractor)

SECTION: 5

GENERAL CONDITIONS OF CONTRACT

Definitions

1.(1) The contract document consists of the Agreement the General Conditions of the Contract

Specifications and drawings including all modifications thereof incorporated in the

document before the execution and the Contract Drawings prepared by the Architect from

time to time. These form the contract.

1.(2) Written notices shall be deemed to have been duly served if delivered in person to the

individual or to a member of the firm or to an office of the corporation for whom it is

intended, or if delivered at or sent by registered mail to the last business address known to

him who gives the notice.

1.(3) The term “Work” of the Contractor or Sub-Contractor includes labour, material,

equipments, transport or all of them.

1.(4) All Time Limits stated in the Contract Document are of the essence of the contract.

1.(5) The law of the place of work shall govern the construction under this contract.

1.(6) The date of virtual completion of a project or specified area of a project is the date when

construction is sufficiently completed, in accordance with the Contractor Documents as

modified by any change or variation orders agreed to by the parties, so that the Owner can

occupy the project for use it was intended.

2. Contract Document

The Contract Document is complementary. What is called for in any one shall be as binding as

if called for by all.

Page 14: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

14

So soon as is possible after the execution of this contract, copies of the Specifications,

descriptive schedule or other like document necessary for use in carrying the work shall without

charge be supplied by the Architect to the Contractor.

After the award of the Contract the Contractor shall without charge be supplied with all such

further drawings and details as may be prepared by the Architect and his Consultant, from time

to time as the work proceeds as are reasonably necessary either or amplify the Contract

Drawings or to enable the Contactor to carry out and complete the work in accordance with

these Conditions provided all such drawings shall be a reasonable development of the work

described in the Contract Document.

The Contractor shall keep at site one copy of the Specifications, Description schedule or other

like document referred to in this clause and one copy of the Contract Drawing and such other

drawings and details supplied to him from time to time and referred to in clause and sub-clause

upon the site so as to be available to the Architect or his representative at all reasonable times.

3. Type of Contract

The Contract shall be an item-rate contract. The Contractor shall be paid for the actual

quantity of work done, as measured at site, at the rates quoted by him in the Contract Bills

and agreed to by the Owner.

3A. Schedule of Quantities

The Schedule of Quantities given in the Contract Agreement is provisional and is meant to

indicate the intent of the work and to provide a uniform basis for tendering. The Owner

reserves the right to increase or decrease any of the quantities or to totally omit any item of

work and the Contractor shall not claim any extras or damages on these grounds.

3B. We agree that, the quantities are for piling work of underground tank & compound wall for

proposed institute building at Navi Mumbai

Any error in description or in quantity or omission of items from the Contract Agreement shall

not vitiate this Contract Agreement but shall be treated as a variation.

4. Contract Drawings

4(1) In general the Drawings shall indicate dimensions, position and type of construction, the

Specifications shall indicate the quantities and the methods. Any work indicated on the

Drawings and not mentioned in the Specification or vice versa shall be furnished as

through fully set forth in both. Work not specifically detailed. Called for, marked or

specified shall be the same as similar parts that are details marked or specified.

4(2) The Contractor’s work shall not deviate from the Drawings and the Specifications. The

Architects interpretation of these documents shall be final and without appeal.

Page 15: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

15

4(3) Errors or inconsistence discovered in the Drawings and Specifications shall be promptly

brought to the attention of the Architect through Engineer -in-charge, for interpretation or

correction. Local conditions which may affect the work shall likewise be brought to the

Architect attention. if at any time, it is discovered that work is being done which is not in

accordance with the Contract Drawings and specifications the Contractor shall correct the

work immediately. Corrections of defective work shall not be a basis for any claim for

extension of time. The Contractor shall not carry on work except with the approval of the

Engineer-in-charge.

4(4) Figured dimensions on the Scale Drawings and large size details shall govern. Large size

details shall take precedence over small scale drawings. Any work done before receipt of

such details if not in accordance with the same, shall be removed and replaced or adjusted,

as directed by the Engineer-in-charge without expense to the owner.

4(5) All drawings, Bill of quantities and specifications and copies thereof furnished by the

Architect are his property. They shall not be used on any other work and shall be returned

to the Architect at his request on completion or termination of the Contract.

5. Scope of Intent

5(1) Scope: The general character and the scope of the work is illustrated and defined by the

Specifications herewith attached and by the signed Drawings. If the Contractor shall find

any discrepancy in or divergence between the Contract Drawings and or the specifications

he shall immediately give to the Architect a written intimation specifying the discrepancy

or divergence and the Architect shall issue instructions in regard thereto.

5(2) Extent: The Contractor shall carry out and complete the work in every respect in

accordance with this Contract and with the directions of and to the reasonable satisfaction

of the Architect / Engineer -in-charge. The Architect may in his absolute discretion and

from time to time issue further drawings, details and /or written directions and written

explanations all of which are collectively referred to as Architect instructions. All such

Drawings and instructions shall be consistent with Contract Document, true developments

thereof and reasonably inferable there from.

5(3) Intent: The intention of the Document is to include all labour and materials, equipment and

transportation necessary for the proper execution of the work. All such drawings and

instructions shall be consistent with the Contract Document, true developments thereof and

reasonably inferable there from. Material of work described in words which so applied

have a well known technical or trade meaning shall be held to refer to such recognized

standard.

Page 16: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

16

6. Facilities and Co-operation

6(1) In the case of work indicated on the Drawings but not indicated in the contract the

Contractor shall provide necessary facilities and co-operation for any Sub-contractor or

supplier who may be approved by the Owner. The Contractor shall do all cutting, filling or

patching of his work that may be required to make it’s several parts come together properly

and fit it to receive or be received by work of other Contractors shown upon or reasonably

implied by the Drawings and Specifications for the completed structure, and he shall make

good after them, as the Architect / Engineer-in-charge may direct. Any cost caused by the

defective or ill-timed work shall be borne by the party responsible therefore.

6(2) The Contractor shall not endanger any work by cutting, excavating or otherwise altering

the work and shall not cut or alter the work of any other Contractor except with the consent

of the Engineer-in-charge.

6. Site Visit: Before tendering, the Contractor shall have visited and examined the site and Satisfied himself

as to the nature of the existing roads or other means of communication and the character of the

soil and of the excavations, the correct dimensions of the work and the facilities for obtaining

any special articles called for in the Contract Document and shall have obtained generally his

own information on all matters affecting the continuation and progress of the works.

No extra charge made in consequence of any misunderstanding or incorrect information on any

of these points, or on the grounds of insufficient description, will be allowed. Should the

Contractor after visiting the site, find any discrepancies, omissions, ambiguities or conflicts in or

among the Contract Documents, or to be in doubt as to their meaning, he shall bring the

questions to the Architect / Owners attention, not later than ten days before the last date for

submission of the tender.

Site is affected by buffer zone from the mangroves. The land under the buffer zone is marked

on site. The originality of the land under the buffer zone is not to be disturbed even it is not to

be leveled. If any concreting or storing of the material is to be done in the buffer zone it has to

be ‘Tadpatri’. Otherwise, the contractor will be liable for the consequences under CRZ

provisions.

LICENSE TO ENTER ON SITE FOR THE WORKS ONLY IS GIVEN TO THE

SUCCESSFUL CONTRACTOR. :

The main contractor should allow the other contractor who has been awarded the other work &

co-ordinate for dumping the material, execution, allowing to use the water & electricity etc. for

successful completion of work by both the contractors.

The Contractor shall be allowed admittance to the site or given a license to enter on site on the

‘Date of Commencement’ stated in the appendix and he shall thereupon and forthwith begin the

Page 17: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

17

work and shall regularly proceed with and complete the same on or before the ‘Date of

Completion’ stated in the appendix subject nevertheless to the extension of time hereinafter

contained.

8. Progress Chart or Bar Chart

The Contractor shall prepare progress charts and submit the same for approval of the Architect /

Engineer-in-charge and for his record within Fifteen days of the Award of the Contract. The

charts shall indicate the expected date of commencement and completion of each of the items of

the work and shall be in a form approved by the Engineer-in-charge. The Chart shall also

indicate the scheduling of samples, Shop Drawings and approvals.

9. Access for Architect to the Works

The Architect and his representative shall at all reasonable times have access to the Works and

to the Workshops or other places of the Contractor where work is being prepared for the

Contract and when work is to be so prepared in workshops or other place of a Sub-Contractor (

whether or not a nominated Sub-contractor of these Conditions) the Contractor shall have a term

in the Sub-Contract so as to secure a similar right of access to those workshops or places for the

Architect and his representative and shall do all things reasonably necessary to make such right

effective.

10. Architect Status and Decision

10(1) The Architect shall be the Owner’s representative during the Construction period. The

Architect shall periodically visit the site to familiarize himself generally with the

progress and the quality of the work and to determine in general if the work is proceeding

in accordance with the Contract Document. He shall not be required to make exhaustive

or continuous on site inspections to check the quality of the work and he shall not be

responsible for the Contractor failure to carry out the construction work in accordance

with the working drawings, specifications & Contract Document. During such

inspections and on the basis of his observations while at the site he shall keep the Owner

informed of the progress of the work, shall endeavor to guard the Owner against defects

and deficiencies in the work of the Contractor and he shall condemn to the Contract

Document. He shall have authority to act on behalf of the Owner only to the extent

expressly provided in the Contract Document or otherwise in writing which shall be

shown to the Contractor. He shall have authority to stop the work whenever such

stoppage may be necessary in his reasonable opinion to ensure the proper execution of

the Contract.

10(2) Decision: The Architect shall within a reasonable time make decisions on all claims of

the Owner or the Contractor and all other matters relating to the execution and progress

of the work or the interpretation of the Contract Document.

Page 18: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

18

The Architect may in his absolute discretion and from time to time issue further

Drawings. Details and /or written instructions, written directions and written explanations

in regard to:

A. Variation or modifications of the design.

B. The quality or quantity of works or the additions or omission or substitution of any

work.

C. Any discrepancy in or divergence between the Drawings and/or specifications.

D. The removal and /or re-execution of any works executed by the Contractor.

E. The dismissal from the works of any persons employed thereon.

F. The opening up for inspection of any work covered up.

G. The amending and making good of any defects under Defects Liability Period.

H. The removal from the site of any materials brought thereon by the Contractor and the

substitution of any other material therefore.

J. Assignment and sub-letting.

K. Delay and extension time.

L. The postponement of any work to be executed under the provision of this contract.

10(3) Dismissal:

The Contractor shall on the request of the Owner / Architect / Engineer -in-charge immediately

dismiss from the works any person employed thereon by him who may in the opinion of the

Architect be incompetent or misconduct’s himself and such person shall not be again employed

on the work without the permission of Owner / Architect / Engineer-in-charge.

11. Engineer -in-charge

The term “Engineer-in-charge” shall mean the person appointed and paid by the Owner and

acting under the orders of the Owner / Architect to inspect the works in the absence of the

Architect; the Contractor shall afford the Engineer-in-charge every facility and assistance for

inspecting the works and materials and for checking and measuring time and materials. Neither

the Engineer -in-charge nor any representative of the Architect shall have power to set out works

or to revoke, alter, enlarge or relax any requirements of the Contractor or to sanction any day

work, additions, alternations, deviations or omissions, or any extra work whatever except in so

far as such authority may be specially conferred by a written order of the Architect.

The Engineer-in-charge or any representative of the Architect shall have to give notice to the

Contractor or to his representative of non-approval of any work or materials and such work shall

be suspended or the use of such materials shall be discontinued until the decision of the

Architect, is obtained. The works will from time to time be examined by the Architect, the

Engineer-in-charge or the Architect’s representative but such examination shall not in any way

exonerate the Contractor from the obligation to remedy any defects which may be found to exist

at any stage of the works or after the same is completed. Subject to the limitation of this clause

the Contractor shall take instructions only from the Architect.

Page 19: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

19

12. Contractors filed organization and Equipment

12(1) Engineer -in-charge: The Contractor shall constantly keep on his work during it’s progress one or more qualified and

competent Engineer-in-Charge who will be responsible for the carrying out of the drawings.

Specifications and Schedule of the Quantities, Architects instructions and directions to the

satisfaction of the Architect / Engineer-in-charge. Any direction or instruction given to him by

the Architect / Engineer-in-charge shall be deemed to have been issued to the Contractor.

Attention is called to the importance of requesting instruction from the Architect before

undertaking an work where Architect’s direction or instructions are required. Any such work

done in advance of such instructions will be liable to be removed.

12(2) Equipment:

The Contractor shall provide and install all necessary concrete misers, vibrators, hosts,

scaffolding, tools, tackles, plants, all transport for labour material and plant necessary for the

proper carrying on execution and completion of the work to the satisfaction of the Architect.

12(3) Storage of Materials:

The Contractor shall provide, erect and maintain proper sheds for the storage and protection of

the materials including owner supplied materials and also for the execution of Work may be

prepared in the Site.

12(4) Sanitary Conveniences:

The Contractor shall provide and erect all necessary sanitary convenience for the Site-staff and

the workmen maintain in a clean orderly condition and clean and deodorize the ground after

removal.

12(5) Scaffolding, Staging, Guard-rails:

The Contractor shall provide scaffolding, staging, guardrails, temporary stair which shall be

required during construction. The support for the scaffolding, staging guard -rails and temporary

stairs shall be strong, adequate for the particular situation. The temporary access to the various

parts of the structure under construction shall be rigid and strong enough to avoid any chance of

mishaps. The arrangement proposed shall be subject to the approval of the Engineer-in-charge.

13. Taxes

The Contractor shall include in the amount of his tender or tender rate the amount of VAT,

works contract tax, Service Tax or any other tax duty/octroi or other duties or taxes legally

payable as on date of tender & these Taxes are to be shown separately in the Tender. However it

shall be assumed that his rates cover for all taxes and duties as applicable till the completion of

work and no claim on this account will be entertained by the owner. All new taxes, levies,

duties imposed after signing the contract shall be reimbursed by the Employer on production of

Page 20: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

20

documentary evidence and only if the contract is fulfilled within the stipulated time period. If

there is any delay on the part of the party, there will be no reimbursement.

14. Statutory obligations, notices, fees and charges

14(1) The Contractor shall comply with and give all notices required by any Government

authority and instrument, rule or order made under any Act of Parliament or any

regulation or Bye-law of any local authority relating to the work or with system the same

is or will be connected.

14(2) The Contractor shall pay and indemnify the Owner / Architect against liability in respect

of any fees or charges (including any rates and taxes) legally demandable under nay Act

of Parliament, instrument, rule or order or any regulation or Bye-law or any local

authority in respect of the work.

15. Royalties and patent rights

All royalties or other sums payable in respect of supply and use in carrying out the Work as

desired by or referred to in the Contract Bills of any patented articles, process or inventions shall

be deemed to have been included in the Contract sum, and the Contractor shall indemnify the

Owner from and against all claims, proceedings, damages, costs and expenses which may be

brought or made against the Owner to which he may be put by reason of the Contractor

infringing or being held to have infringed any patent rights in relation to any such articles,

processes and inventions.

16. Licences and Permits for Materials under Government control

Licences and Permits for all materials under Government control shall be obtained by the

Contractor, the Contractor shall include in his tender all transport charges and other expenses

likely to be incurred to bring the material to the Site.

17. Water for construction Water for construction will be provided by owner at one point anywhere at site. The distribution

of water from source to upper floors shall be done by the contractor at his own cost. Contractor

has to provide pumps. G.I. pipe line, hose pipes etc & maintain them at his cost. Adequate

storage facility shall be made by the contractor for uninterrupted supply of water, however,

incase of shortfall of water from existing sources, the contractor has to arrange water through

tankers at his own cost.

18. Electricity Electricity charges shall be borne by the contractor on actual consumption basis. Electricity will

be provided at one point by the owner. Contractor has to make his own arrangement for further

distribution to upper floors or anywhere at site at his own cost. Contractor has to provide wires.

Main switches, switches and power meter etc. for distribution of power to upper floors &

maintain them at his cost. No loose wires switches are permitted. All cables, controls, light

fittings, safety devices shall be as per local bodies approved norms.

Page 21: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

21

19. Assignment or sub-letting The Contractor shall not without the written consent of the Engineer-in-charge assign this

Contract, and shall not without the written consent of the Engineer-in-charge (which consent

shall not be unreasonably withheld to the prejudice of the Contractor) Sub-let any portion of the

work.

20. Separate contracts The Owner reserves the right to let other Contract (i.e. waterproofing, electrical, air

conditioning, firefighting, painting etc) in connection with his work under similar general

conditions. The Contractor shall afford other contractors reasonable opportunity for the

introduction and storage of their materials and the execution of their work, and shall properly

connect and co-ordinate his work with theirs. If any part of Contractors or Sub-Contractors work

depends for proper execution or results upon the work of any other Contractor shall inspect and

promptly report to the Engineer-in-charge, any defects in such work that render it unsuitable for

such proper execution and results. Failure of the Contractor to so inspect and report shall

constitute an acceptance of the other Contractors work as fit and proper for the reception of his

work, except as to defects which may develop in the other Contractor’s or Sub-Contractors work

after the execution of the work to ensure the proper execution of his subsequent work the

Contractor shall measure work already in place and shall at once report to the Engineer-in-

charge any discrepancy between the executed work and the Drawings. The main contractor has

to work in coordination with other contractors in respect of work schedule, material allowing the

work to be done at site etc.

21. Certificate and payment

21(1) Contractor should maintain the measurement book in triplicate and all the work to be bill

as per the measurements noted in the measurement book. The measurement book to be

signed by the Architect / Engineer-in-Charge. These books are to be maintained till the

completion of the work.

21(2) At the period of interim Certificates named in the appendix to these conditions the

Architects / Engineer-in-charge shall issue a certificate stating the amount due to the

Contractor from the Owner, and the Contractor be entitled to payment therefore within

the period for honoring certificates named in the appendix to these conditions, interim

valuations shall be made whenever the Architects / Engineer-in-charge considers them to

be necessary for the purpose of ascertaining the amount to be stated as due in an interim

Certificates.

21(3) The amount stated as due in an interim Certificates shall subjects to any agreement

between the parties as to stage payments, be the total value of the work executed and of

the materials and goods delivered to or adjacent to the work for use thereon up to and

including a date not more that seven days before the date of the said Certificates less any

amount which may be retained by the Owner (as provided in sub-clause of this

condition) and less any installments previously paid under this Condition, provide that

such certificates shall only include the value of the said materials and goods as and from

such time as they are reasonably, properly and not prematurely brought to or placed

adjacent to the work and then only if adequately protected weather or other causalities.

Page 22: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

22

21(4) The Owner may retain the percentage of the work. Materials and goods referred to in

Sub-Clause of this condition which is named in the appendix to this conditions as

retention percentage. Provide always that when sum of the amount retained equals the

amount named in the said appendix as limit of retain fund or that amount as reduced in

pursuance of clause of these conditions, as the case may be, no further amounts shall be

retained by virtue of this Sub-Clause.

21(5) So soon as is practicable but before the expiration of the period the length of which is

stated in the appendix to these Conditions from the end of the Defects Liability Period

also stated in the said appendix or from completion of making good defects under clause

of these conditions or from receipt by the Architect / Engineer-in-charge of the

Documents whichever is the latest, the Architect / Engineer-in-charge shall issue the

Final Certificate.

22. Claim for Extra When any instruction or decision given at site involves an extra or whereby the Contractor may

plan to claim an extra, it shall be the responsibility of the Contractor to inform the Architect

/Engineer-in-charge of the extra amount and get written authorization from the Owner before

proceeding with the work involved.

Any modification carried out for expending or simplifying work at the request of the Contractor

or his representatives shall not be taken as the basis for claiming an extra. However if such

modification shall also involve an extra, the rate for such modification shall be settled in

advance and written authorization obtained by the Contractor from the Architect / Engineer-in-

charge before proceeding with work involved.

The rate of extra items to be worked out and produced as follows:

a) Cost of actual material (landed at site) & Labour.

b) 15% to cover all overheads; plant & equipment; supervision; profits, texes etc.

23. Deduction for uncorrected work If the Engineer-in-charge deems it inexpedient to correct work damaged or not done in

accordance with the Contract, an equitable deduction from the Contract price shall be made

therefore.

24. Fluctuations The Contractor shall not claim any extras for fluctuation of price and the Contract Price shall not

be subject to any rise or fall prices.

25. Unfixed goods and materials Unfixed materials and goods intended for, delivered to and placed on or adjacent to the work

shall not be removed except for use upon the work unless the Engineer-in-charge has consented

in writing to such removal which consent shall not be unreasonably withheld.

26. Materials and Workmanship

Page 23: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

23

26(1) All material and workmanship shall be as per the relevant code of I.S.I Specification and

of approved type and the Contractor shall immediately remove from the works any

material and / or workmanship which in the opinion of the Engineer-in-charge are

defective or unsuitable and shall substitute proper materials and / or workmanship at his

own cost. The term approval used in connection with this contract shall mean the

approval of the Engineer-in-charge.

26(2) The Contractor shall if required submit satisfactory evidence as to the kind and quality of

material.

26(3) Where special makes or brands are called for they are mentioned as a standard. Others of

equal quality may be used provided approval is first obtained in writing from the

Engineer-in-charge. Unless substitutions are requested no deviation from the

Specifications will be permitted. Failure to propose the substitution of any article within

30 days after signing of the Contract will be deemed sufficient causes for denial of the

request for substitution.

26(4) All materials shall be delivered so as to insure a speedy and uninterrupted progress of the

work. Such material shall be stored so as to cause no obstruction and so as to prevent

overloading of any portion of the structure, and the Contractor shall be entirely

responsible for damage or loss by weather or other cause.

26(5) Within 10 days after signing the Contract, Contractor shall submit for approval of the

Architect / Engineer-in-charge, a complete list of all material he and his Sub-Contractors

propose to use in the work of definite brand or make which differ in any respect from

those specified; also the particular brand of any article where more than one is specified

as a standard. He shall also list items not specifically mentioned in the Specifications but

which are reasonably inferred and necessary for the completion of the work.

27. Inspection

All materials and workmanship shall be subject to inspection, examination, and workmanship

shall be subject to inspection, examination, and test by the Owner at any and all time during

manufactures and / or construction. The Owner shall have the right to reject defective material

and workmanship or require its correction. Rejected workmanship shall be satisfactorily

replaced with proper material without additional charge therefore and the Contractor shall

promptly and remove the rejected material from the works. If the Contractor fails to proceed at

once with the replacement of rejected materials and or the correction of defective workmanship,

Owner will replace the materials or corrective work for defective workmanship, and charge the

cost thereof to the Contractor, or may terminate the right of the Contractor to proceed further

with the work.

Page 24: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

24

The Contractor shall furnish promptly without additional charge all reasonable facilities, labour

and materials necessary for the safe and convenient inspection and test that may be required by

the Owner.

28. Defect

28(1) The Contractor shall promptly make good at his own cost and to the satisfaction of the

Owner/ Engineer-in-charge, all defect, shrinkages or small faults, arising in the opinion

of the Architect / Engineer-in-charge from work or materials not being in accordance

with the Drawings or Specification or Schedule of Quantities or the Instruction of the

Architect, which may appear during construction period & “Defects Liability Period”

refereed to in the appendix.

28(2) Such defects, shrinkages shall upon direction in writing of the Engineer-in-charge, and

within such reasonable time as shall be specified therein be amended and made good by

the Contractor, at his own cost unless the Owner shall decide that he ought to be paid for

such amending and making good and in case of default the Owner may employ and pay

other Contractor to amend and make good such defects, shrinkage, settlement or other

faults and all damages loss and expenses consequent thereto shall be made good and

borne by the Contractor and such damage, loss or expenses shall be recoverable from

him by the Owner or may be deducted by the Owner upon the Architect / Engineer-in-

charges certificates in writing from any amount due amount due or may become due to

the Contractor or the Owner may, in lieu of such amending and making good by the

Contractor deduct from any money’s due to Contractor a sum to be determined by the

Owner as equivalent to the cost of amending such work and in event of the Retention

Amount being insufficient recover the balance from the Contractor, together with any

expenses the Owner may have incurred in connection therewith.

29. Possession completion and postponement

29(1) On the date for commencement stated in the appendix to these conditions possession of

the site shall be given to the Contractor by the Engineer-in-charge, who shall thereupon

being the works and regularly and, diligently proceed with the same, and who shall

complete the same on or before the date for Completion stated in the said appendix

subject nevertheless to the provisions for extension of time contained of these conditions.

29(2) The Owner may issue instruction in regard to the postponement of any work to be

executed under the provisions of this Contract.

29(3) The contractor’s license to enter on site will be automatically seized after completion of

the work or after issuing a letter by the Architect to the contractor to vacate the site under

circumstances.

30. If at any time or times before Virtual Completion of the work the Owner shall take

possession of any part or part of the same for handing over to the finishing Contractor or

Page 25: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

25

other agency, then notwithstanding anything expressed or implied elsewhere in this

Contract:-

30(1) Such part or parts shall not be deemed to be Virtually Complete.

30(2) Virtual Completion of such part or parts would occur on the completion of the last part of

the structure under this Contract.

30(3) The Contractor shall not claim that such part or parts are complete and request refund of

payments in lieu thereof.

Page 26: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

26

31. Extension

Upon it becoming reasonably apparent that the progress of the Works is delayed, the Contractor

shall forthwith give written notice of the cause of the delay to the Owner, and if in the opinion

of the Owner, the completion of the Work is likely to be or has been delayed beyond that date

for completion stated in the appendix to these conditions or beyond any extended time

previously fixed under this clause.

31(1) By force majure. Or

31(2) By reason of any exceptionally inclement weather. Or

31(3) By reason of loss or damage occasioned by any one or more of the contingencies

referred to in clause of these conditions Or.

31(4) By reason of civil commotion, local combination of workmen strike or lockout affecting

any of the trades employed upon the works or any of the trades engaged in the

preparation, manufactures or transportation of any of the gods or material required for the

work. Or

31(5) By reason of Architect’s / Engineer-in-charge’s instruction issued under clauses of these

Conditions. Or

31(6) By reason of the Contractor not having received in due time necessary instructions,

drawings, details or levels from the Engineer-in-charge for which he specially applied in

writing on a date which having regard to the date for completion stated in the appendix to

these conditions or to any extension of time then fixed under this clause was neither

unreasonably distant from nor unreasonably close to the date which it was necessary for

him to receive the same. Or

31(7) By delay on the part of artists, tradesmen or others engaged by the Owner in executing

work not forming part of this Contract. Or

Then the Architect / Engineer-in-charge shall as soon as he is able to estimate the length

of the delay beyond the date or time aforesaid make in writing a fair and reasonable

Extension of Time for completion of the works, provided always that the Contractor shall

use constantly his best Endeavor’s to prevent delay and shall do all that may reasonably

be required to the satisfaction of the Architect / Engineer-in-charge to proceed with the

work.

32. Damages for non-completion

If the Contractor fails to complete the works by the date specified in these Conditions or within

any extended time fixed under clause of these conditions and the Architect / Engineer-in-

charge’s certifies in writing that in opinion the same ought reasonably so to have been

Page 27: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

27

completed, the Contractor shall pay or allow to the owner a sum calculated by the way of

penalty @ ½% of the Contract Price per week of delay, subject to maximum of 10% of the

contract price. As agreed Liquidated Damages for the period during which the said work shall

so remain or have remained incomplete the Owner may deduct such damages from any money

otherwise payable to the Contractor under this Contract.

33. Virtual Completion and Defects Liability Period

33(1) When in the opinion of the Architect / Engineer-in-charge the Works are practically

completed, he shall forthwith issue a certificate to that effect and Virtual Completion of

the Works shall be deemed for all the purpose of this Contract to have taken place on the

day named in such certificate. Date of defect liability period will start after ‘Taking over’

of site by Owner, as described on Page No.10.

33(2) Any defects shrinkage or other faults which shall appear within the “Defects Liability

Period” stated in the appendix to these conditions and which are due to materials and

workmanship not in accordance with this Contract shall be specified by the Engineer-in-

charge in a Schedule of Defects which he shall deliver to the Contractor not later than 14

days after the expiration of the said Defects Liability Period and within a reasonable time

after receipt of such Schedule the Defects Shrinkage and other faults therein specified

shall be made good by the Contractor and (unless the Owner shall otherwise instruct in

which case the Contract Sum shall be adjusted accordingly) entirely at his own cost, risk

& responsibility.

33(3) Notwithstanding sub-clause of this Condition the Engineer-in-charge / Architect may

whenever he considers it necessary so to do, issue instructions requiring any defect,

shrinkages or other fault which shall appear within the Defect Liability Period named in

the appendix to these conditions and which is due to materials and workmanship not in

accordance with this Contract to be made good and the Contractor shall within a

reasonable time after receipt of such instructions comply with the same ( and unless the

Architect / Engineer-in-charge shall otherwise instruct in which case the Contract sum

shall be adjust accordingly) entirely at his own cost, provided that no such instruction

shall be issued after 14 days from the expiration of the said Defects Liability Period.

33(4) When in the opinion of the Owner / Architect any defects shrinkages or other defaults

which he may have required to be made good under sub-clause of this Condition shall

have been made good he shall issue a certificate to that effects shall be deemed for all the

purpose of this Contract to have taken place on the day named in such certificates.

34. Payments withheld The Owner may without or on account of subsequently discovered evidence

nullify the whole or a part of any certificate to such extent as may be necessary in his reasonable

opinion to protect the Owner from loss on account of:

34(1) Defective work not remedied.

34(2) Failure of the Contractor to make payments properly to Sub-Contractor or for materials

or labour.

Page 28: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

28

34(3) A reasonable doubt that the Contract can be completed for the balance then unpaid.

34(3) Damage to another Contractor or Sub-Contractor.

When the above grounds are removed payment shall be made for amount withheld because of

them.

35. Injury to Persons and property Owner

35(1) The Contractor shall be liable for and shall indemnify the Owner against any liability,

loss, claim or proceedings whatsoever arising under any statute or at common law in

respect of personal injury to or the death of any person whomsoever arising out of or in the

course of or in the course of or caused by the carrying out of the works, unless due to any

act or neglect of the Owner or of any person for whom the Owner is responsible.

35(2) Except for such loss or damages as is at the risk of the Owner under clause of these

Conditions ( If applicable) the Contractor shall be liable for and shall indemnify the Owner

against any expense, liability, loss, claim, or proceedings in respect of any injury or

damages whatsoever to any property real or personal in so far as such injury or damage

arises out of or in the course of or by reason of the carrying out of the works, and provided

always that the same is due to any negligence omission or default of the Contractor, his

servant or agents or of any Sub-Contractor, his servant or agent.

36. Insurance against injury to Person and Property

36(1) Without Prejudice to his liability to indemnify the Owner under clause of these

conditions, the Contractor shall maintain and shall cause any Sub-Contractor to maintain

36(A) Such insurance as are necessary to cover the liability of the Contractor or as the case may

be of such Sub-Contractor, in respect of personal injuries or deaths arising out of or in the

course of or caused by the carrying out of the work or incidental to work or stay at work

site; and

36(B) Such insurances as may be specifically required by the Contractor Bills in respect of

injury or damage to property real or personal arising out of or in the course of or by reason

of the carrying out the work or incidental to work or stay at work site, and caused by any

negligence, omission or default of the Contractor, his servants or agents or, as the case may

be of such Sub-Contractor, his servants or agents.

The Contractor shall produce or cause any Sub-Contractor to produce for inspection the

relevant policy or policies of insurance together with the receipt in respect of premiums

paid under such policy or policies as and when required so to do by the Engineer-in-charge

provided always that as and when may be reasonably required by the Engineer-in-charge,

the production by either the Contractor or any Sub-Contractor of a current certificate of

insurance from the company or firm which shall have issued the policy or policies

aforesaid shall be a good discharge of the Contractor’s obligation to produce or to cause

the production of the policy or policies and the receipts in respect of premium paid.

Page 29: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

29

36(2) The Contractor shall maintain in the joint names of the Owner and Contractor such

insurances as may required in respect of any expenses, liability, loss, claim, or proceedings

which the Owner may incur or sustain by reason of injury or damage to property real or

personal arising out of or in the course of or by reason of the carrying out of the work, and

caused otherwise than by the negligence, omission or default of the Contractor, his servant

or agents or any Sub-Contractor, his servants or agents.

36(3) Any such insurance as is referred to in the immediately preceding paragraph shall be

placed with insurers to be approved by the Engineer-in-charge and the Contractor shall

have to deposit with him the policy or policies and the receipts in respect of premium paid.

37. Insurance of the works against fire etc.

37(1) The Contractor shall in the joint names of the Owner and Contractor, insure against loss or

damages by fire, storm. tempest, lighting, flood, earthquake, aircraft or anything dropped

there from, aerial objects, riot and civil commotion for the full value thereof all work

executed and all unfixed materials and goods intended for, delivered to and placed on or

adjacent to the work, labour camps and laborers and their material assets if located at sites

but excluding temporary building plant, tools and equipment owned or hired by the

Contractor or any Sub-Contractor and shall keep such work materials and goods so insured

until Virtual Completion of the work. Such insurance shall be with insurers approved by

the Owner and the Contractor shall deposit with the Owner the policy or policies and the

receipts in respect of premiums paid; and should the Contractor make default in insuring or

continuing to insure as aforesaid the Owner may himself insure against any risk with

respect of which the default shall have occurred and deduct a sum equivalent to the amount

paid by him in respect of premium from any monies due to or to become due to the

Contractor.

Provide always that if the Contractor shall independently of his obligations under this

contract maintain a policy of insurance which covers (inter alia) the said work, materials

and goods against the aforesaid contingencies to the full value thereof then the

maintenance by the Contractor of such policy shall if the Owners interest is endorsed

thereon, be a discharge of the Contractor’s obligation to insure in the joint names of the

Owner and Contractor and the production by the Contractor as and when may reasonably

required by the Owner, of a current certificate of insurance from the company or firm

which shall have issued the said policy shall be a discharge of the Contractors obligation to

deposit with the Owner a policy or policies and the receipts in respect of premiums paid.

37(2) Upon settlement of any claim under the insurances aforesaid the Contractor with due

diligence shall restore work damaged, replace or repair unfixed materials or goods which

have been destroyed or injured, remove or dispose of any debris and proceed with the

carrying out and completion of the work. All money received from such insurances shall

be paid to the Contractor by installments under certificates of the Engineer-in-charge

issued at the period of interim certificates named in the appendix to these conditions. The

Contractor shall not be entitled to payment in respect of the restoration of work damaged,

the replacement and repair of any unfixed materials or goods and the removal and disposal

of debris other than the monies received under the said insurances.

Page 30: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

30

37(3) The contractor is in insured for the labour working at site and copy of the insurance letter

is to be submitted to the owner.

37(4) The contractor has to take all the safety precautions for the workers working at site

including fire safety.

38. Determination by the Owner

38(1) Default: If the Contractor shall make default in any one or more of the following respect,

that is to say:

38(1)A If he without reasonable cause wholly suspended the carrying out of the works before

completion thereof, or

38(2)B If he fails to process regularly with the works, or

38(1)C If he refuse or persistently neglects to comply with a written notice from the Owner /

Arcitect requiing him to remove defective work or improper material or goods and by such

refusal or neglect the work is materially affected or.

38(1) D If he fails to comply with the provision, then the Owner / Architect may give him the

notice by registered post or recorded delivery specifying the default and if the Contractor

either shall continue such a default for 14 days after receipt of such a notice and shall at

any time thereafter repeat such a default ( whether previously repeated or not). Then the

Owner without prejudice to any other rights or remedies may within 10 days after such

continuance or repetition of notice by register post or recorded delivery forth with

terminate not be given unreasonably or vexatious.

38(2) Bankruptcy of Contractor: In the event of the Contractor becoming bankrupt or making

a composition or arrangement with his creditors or being a company having a winding up

order made or (except for purpose of reconstruction) a resolution for voluntary winding

up passed or a received or manager of his business or undertaking duly appointed or

possession taken by or on behalf of the holders of any debentures secured by a floating

charge, of any property comprised in or subject to the floating charges, the employment

of the Contract under this Contract shall be forthwith automatically determined but the

said employment may be reinstated and continued if the Owner and the Contractor, his

trustee in bankruptcy, liquidator, receiver or manager as the case may be shall so agree.

38(3) The Owner shall be entitled to determine the employment of the Contractor under this

Contract, if the Contract shall have offered or given or agreed to give to any person any

gift or consideration of any kind as an inducement or reward for doing or forbearing to

do or for having done or forbore to do any action in relation to the obtaining or execution

of this Contract with the Contract or any other Contract with the Owner, or if the like acts

shall have been done by any person employed by the Contract or acting on his behalf

(whether with or without the knowledge of the Contractor), or if in relation to this

Contract or any other Contract with the Owner the Contractor or any person employed by

him or acting on his behalf shall have committed any offence under the prevention of

corruption act. Or shall have given any fee or reward of which is an offence under the

Local Government Act.

Page 31: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

31

38(4) In the event of the employment of the Contractor being determined as aforesaid and so

long as it has not been reinstated and continued the following shall be the respective

rights ad duties of the Owner and Contractor.

38(4)AThe Owner may employ and pay other persons to carry out and complete the works and

he or they may enter upon the Works and use all temporary buildings, plant, machinery,

appliances, goods and materials intended for, delivered to and placed on or adjacent to

the works and may purchase all materials and goods necessary for the carrying out and

completion of the Works.

38(4)B The Contractor shall if so required by the Owner or Architect within 14 days of the date

of determination, assign to the Owner without payment the benefit of any Agreement for

the supply of materials or goods and / or for the execution of any works for the execution

of any works for the purpose of this Contracts but on the terms that a supplier or Sub-

Contractor shall be entitled to make any reasonable objection to nay further assignment

thereof by the Owner. In any case the Owner may pay any supplier or Sub-Contractor for

any materials or goods delivered or works executed for the purpose of the Contract (

whether before or after the date of determination ) in so far as the price thereof has not

already been paid by the Contractor. The Owners right under this paragraph is in addition

to his rights to pay nominated Sub-Contractors as provided in clause and payments made

under this paragraph may be deducted from any sum due or to become due to the

Contractor.

38(4)C The Contractor shall as and when required in writing by the Engineer-in-charge remove

froms the works any temporary building, plant, tool, equipments, goods and materials

belonging to or hired by him. if within a reasonable time after any such requirements has

been made to the contractor, has not complied therewith, then the owner may (but

without being responsible for any loss or damage) remove and sell any such property of

the contractor, holding the proceeds less all costs incurred to the credit of the contractor.

38(4)D The contractor shall allow or pay to the owner in the manner hereinafter appearing the

amount of any direct loss and/or damage caused to the owner by the determination. Until

after completion of the works under paragraph (a) of this sub-clause the Owner shall not

be bound by any provisions of this Contract to make any further payment to the

Contractor, but upon such completion and the verification within a reasonable time of the

accounts therefore the Engineer – in – charge shall certify the amount of expense

properly incurred by the owner and the amount of any direct loss and/or damage caused

to the Owner by the determination and if such amounts when added to the monies paid to

the Contractor before the date of determination exceed the total amount which would

have been payable to the Owner by the Contractor, and if the said amounts, when added

to the said money be less than said total amounts the difference shall be a debt payable

by the Owner to the contractor.

Determination by the Contractor

39(1) Without prejudice to any other rights and remedies which the Contractor may possess,

if:

Page 32: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

32

39(1) A The carrying out of the whole or the whole of the substantially uncompleted works

(other than the execution of work required under clause of these conditions) is

suspended for a continuous period of the length by reason of:

Force majoure, Or

Loss or damage occasioned by any one or more of the contingencies referred to in

clause of the conditions (if applicable). Or

Civil commotion, Or

Owner/ Architects instructions issued under clause of these conditions, Or

Then Contractor may thereupon notice by registered post or recorded delivery to the

Owner or Architect forthwith to determine the employment of the Contractor under this

Contract; provided to such notice shall not be given unreasonably or vexatiously.

39(2) Upon such determination, then without prejudice to the accrued or remedies of either

party or to any liability of the classes mentioned in clause of these conditions which

may accrue either before the Contractors or any Sub-Contractors shall have removed

his or their temporary buildings, plant, machinery, appliances, goods or materials or by

reason of his or their so removing the same, the respective rights and liabilities of the

Contractor and the Owner shall be as follows that is to say:

39(2) A The Contractor shall with all, reasonable dispatch and in such manner and with such

precautions as will-prevent injury, death or damage of the classes in respect for which

before the date of determination he was liable to indemnify the Owner under clause of

these Conditions remove from site all his temporary buildings, plant, machinery,

appliance, goods and materials and shall give facilities for his Sub-Contractors to do

the same.

39(2) B After taking into account amounts previously paid under this Contract the Contractor

shall be paid by the Owner.

39(2)B(I)The total value of the work completed at the date of determination.

39(2)B(II) The total value of the work begun and executed but not completed at the date of

determination the value being ascertained mutatis in accordance with clause of

these Conditions.

39(2) B (III) The cost of materials and good s properly ordered for the works for which the

Contractor shall have paid or of which the Contractor is legally bound to pay, and

on such payment by the Owner materials or goods so paid for shall become the

property of the Owner.

Page 33: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

33

Provided that in addition to all other remedies the Contractor upon such determination may take

possession of and shall have lien upon all unfixed materials which may have before the property

of the Owner under clause until payment of all monies due to the Contractor from the Owner.

Co-ordination of work At the commencement of work, and from tome to time, the Contractor shall confer with the Sub-

Contractors, persons, engaged on separate contracts in connection with the work, and with the

Architect for the purpose of the Co- ordination and execution of various phases of the work.

Labour The Contractor shall employ no child labour 14years of age on the work. If female labour is

engaged the Contractor shall make necessary provision for safeguarding small children and

keeping them clear of the site of Operations. No labour shall reside within the compound except

the authorized guards. ‘Crèche’ facility shall be provided by the Contractor.

Guarantee

42 (1) Besides guarantees received elsewhere, the Contractor shall guarantee the work in

general for one year as noted under clause of the conditions.

42(2) All required guarantees shall be submitted to the Owner by the Contractor when

requesting certification for accounts for payment by the Owner.

Arbitration:

43(1) Architect is the sole and first arbitrator. His decision is binding upon both the

parties. If both the parties decide, they may appoint a separate arbitrator and

umpire.

43(2) Subject to any dispute between the parties hereto arising out of any notified

claims of the Contractor in his final bill and/or arising out of any claimed by the

owner (whether or not the amount claimed by the Owner or any part thereof shall

have been deducted from the final bill of Contractor or any amount paid by the

Owner to the Contractor in respect of the work) shall be referred to arbitration by

a Sole Arbitrator selected by the Contractor from a panel of three persons

nominated by the Engineer-in-charge.

43(2) The provisions of the Indian Arbitration Act, 1940 and all statutory reenactments

and modifications thereof and the rules made there under shall apply to all such

arbitrations subject further to the following conditions (a) the Arbitrations shall

give has award separately in respect of each claim (b) In so for as any dispute or

difference referred to arbitration shall relate to any matter or thing in respect of

which the decision opinion or determination (howsoever) express of the Owner or

Engineer-in-charge or Site Engineer or any other person has been expressed to be

final in terms of Contract such decision opinion and/or determination , as the case

may be shall be binding upon the arbitrator

Page 34: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

34

Protection and Cleaning

44 (1) The Contractor shall protect and preserve the work from all damage or providing

any temporary roof, window and door coverings, boxing or other construction as

required by the Engineer-in-charge. This protection shall be provided for all

property adjacent to the site as well as on the site.

44 (2) The Contractor shall properly clean the work as it progresses and shall remove all

rubbish and debris from the site from time to time as is necessary and as directed.

On completion the contractor shall ensure that the premises and/or site are cleaned

surplus materials debris, sheds etc. removed, areas under floors cleared of rubbish

gutters and drains cleared, doors and sashes eased, locks and fastenings oiled,

keys clearly labeled and handed to the Engineer-in-Charge co that the whole is

left fit for immediate occupation or use and to the satisfaction of the Owner.

45. Tolerance

The Contractor shall exercise every care to ensure that all structural members are sufficiently

plumb and true to dimensions called for on the drawings to receive prefabricated finishing

elements, such as doors, windows, cabinet work, ceramic work, concrete, tiles etc. Any

variations may require rectification in the structural members or may involve remaking or

replacing the finishing elements, fabricated to fit into the openings or spaces, as called for on the

Drawings, the cost of which will be borne by the contractor.

In all cases , the Contractor whose work does not conform to dimensions called for, shall be

liable for all the expenses which may have to be incurred for rectification or replacement as may

be required by the Architect for the purpose of installation of the finishing elements. The

Architect’s decision in this respect shall be final and binding on the parties concerned.

46. EMD / BID SECURITY AMOUNT

EMD / Bid Security amount should be in shape of Demand Draft from any Nationalized Bank in

favour of the “Institute of Cost Accountants of India’ If any bidder backs out after opening of

Bid, their EMD shall be forfeited, with right of management or any other disciplinary action

against the party. The EMD of the successful bidder may be adjusted against the Security

Deposit.

Earnest Money of unsuccessful bidders shall be refunded not later than 21 days after the expiry

of the bid validity.

Bids without appropriate Bid Security / EMD shall be treated as un-responsive & no further

evaluation of such Bids shall be made.

Page 35: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

35

46. SECURITY DEPOSITE

The value of security money to be deposited by the successful tenderer in the form of Demand

Draft from any nationalized Bank in favour of ‘Institute’ shall be 5% value of the awarded

contract without having any ceiling. This Security Deposit shall be refunded within 30 days of

satisfactory execution of the contract with the approval of tender approving authority. For

successful tenderer, EMD shall be converted to security deposit. In case the firm fails to deposit

the security money, the order shall be cancelled and firms non-performance shall be kept

recorded for future dealings.

Page 36: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

36

SECTION – 6

SPECIAL CONDITIONS OF CONTRACT

THESE CONDITIONS WILL BE READ IN CONJUNCTION WITH RELEVANT

ARTICLES OF GENERAL CONDITONS OF CONTRACT (G.C.C). IN CASE OF

VARIANCE/ DISCREPANCIES BETWEEN S.C.C AND G.C.C THE CONDITIONS

LAID DOWN IN S.C.C. SHALL TAKE PRECEDENCE.

Special conditions of contract shall be read in conjunction with the General Conditions of

Contract, Specifications of work, Drawings and any other documents forming part of this

contract wherever the context so requires.

Notwithstanding, the sub-division of the documents into these separate sections and volumes

every part of each shall be deemed to be supplementary to and complementary of every other

part and shall be read with and into the contract so far as it may be practicable to do so.

Where any portion of the General Conditions of Contract is repugnant to or at variance with any

provisions of the Special Conditions of Contract, then unless a different intention appears, the

provisions of the Special Conditions of Contract, shall to the extent of such repugnancy, or

variance, prevail.

1 The Contractor should note that one connection for water supply shall be given free of

cost at one point inside the plot. The Contractor will lay a suitable size of pump/ pipeline

distribution network for his work at his cost and shall remove the same after the work is

completed. Storage of water will be solely the contractors responsibility and at his

expense. The contractor will not have any claim whatsoever on account of failure of

water supply at any time. Water bill will be paid by the contractor till completion of the

work.

An electric power of 440V - 3 phase shall be made available at one location inside the

plot. Necessary connections/ tapings shall be made by the contractor at his cost. The

contractor shall extend his cable, etc, from this point and shall provide all necessary main

switches, control board-cutouts etc. These equipments shall be protected from weather,

rain etc. and shall conform to normal safety standards. Until power and water is made

available by the owner, contractor shall make his own arrangement of power and water

for the construction work. Civil contactor shall also give power to other contractors from

his distribution board and shall charge them. Electricity bill will be paid by the contractor

till completion of the work

Since there is likelihood of frequent power shutdown from MSEDC, Contractor shall

make adequate standby arrangement with appropriate capacity DG sets to achieve the

target date of stage wise completion of work.

Page 37: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

37

2. The quantities are for piling work for underground tank and compound wall of institute

building. Site is affected by buffer zone from the mangroves. The land under the buffer

zone is marked on site. The originality of the land under the buffer zone is not to be

disturbed even it is not to be leveled. If any concreting or storing of the material is to be

done in the buffer zone it has to be ‘Tadpatri’. Otherwise, the contractor will be liable for

the consequences under CRZ provisions.

3. All materials provided by Contractor shall be new and of approved quality manufactured by

renowned concerns, conforming to Indian Standards or equivalent. The materials shall have

ISI mark as far as possible unless otherwise approved by Architect in writing prior to

procurement and use. The Contractor shall furnish manufacturers certificate for the materials

supplied when asked for.

Further to that he shall get the materials tested from an approved test house as per codal

requirement of relevant IS codes & as per additional test requirement if asked by

ENGINEER INCHARGE/ Architect. The cost of all tests & test certificate shall be borne by

the Contractor. No separate payment shall be made for testing even if the materials are

procured by the owner. Any materials procured or brought to site and not confirming to

specification and satisfaction of the Architect shall be rejected and Contractor shall have to

remove the same immediately from the site at his own expenses and without any claim for

compensation due to such rejection.

4. All the scaffolding/propping material shall be MS tubular which shall be supplied by the

Contractor. All staging platforms shall have hand rails. Wooden planks used for platform to

be 1" thick and firmly secured. Safety regulations and rules shall be strictly observed.

Staging/scaffolding shall be as per IS 3696.

5. All the materials and services issued by the Client to the contractor will not be abused by the

contractor. If such materials and/or services are abused, lost and/or damaged while in the

custody of the contractor the cost of such materials and/or services will be recovered from

the contractor at the rates fixed by the Architect. The decision of the Architect whether any

materials/services are abused, lost and/or damaged will be final and binding on the

contractor.

6. All materials to be used for construction shall be stored by contractor in a manner as directed

by the Architect. Necessary storage sheds and at approved location from time to time shall

be provided by the contractor at his own cost. The security arrangements for such sheds shall

be the responsibility of the Contractor. The Contractor shall remove the above sheds on

completion of the work or as required by the exigency of work.

7. The contractor shall prepare and maintain at his own cost all temporary roads & ramps

within the premises required for transporting materials, equipments and carrying out the

construction activities. Necessary arrangements shall be made by the contractor to drain out

Page 38: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

38

the storm water and keep the site as clean as possible for which no extra payment shall be

made. These accesses for vehicles shall be laid out in concurrence with the Architect.

8. The proposed work to be executed under this contract is in the form of invitation to tender.

The tender is essentially an item rate tender. The items of work and their quantities indicated

in the schedule of quantities are only approximate and for the guidance of the tenderers and

are subject to variation. Measurement shall be carried out as indicated in the tender

specification and as per schedule of quantities and prices. Any claim by the contractor for

such variations and/or deletions of any item shall not be entertained. The Owner does not

bind themselves for any such variations and/or deletion of item of work and its quantities.

9. The price quoted by the contractor shall not be subjected to any change due to increase or

decrease in cost of materials and labour or due to any reasons whatsoever.

10. Tax deduction at source (TDS) at the rate applicable will be deducted from all proceeds and

payments by owner.

11. The drawings if any attached with the tender & forming part of this contract are subject to

additions & alterations to suit the requirements of the Owner for which no extra claim shall

be entertained.

12. The specifications forming part of this contract have been drawn up with all possible care

and are intended to cover the supply of all the materials, tools, plants and equipments labour

in the execution and completing the entire work in all respects under this contract. In case

there are any details of construction or materials which have not been referred to in the

specifications detailed descriptions of items, schedule of quantities, or the drawings but

which have not been referred to in the true completion of the purpose of the work, the same

shall be deemed to have been included in the price quoted by the tenderer. Where ever

specifications are not stipulated, the work shall be as per latest ISI specifications and/or as

directed by the ENGINEER INCHARGE following good Engineering practices.

13. Contractor shall provide at his own expense necessary sanitary and drinking water facilities

for his workers at work site. Contractor shall ensure that no workers move about in areas

other than the work site without prior permission of the Architect. He shall ensure that his

workers shall not commit any nuisance anywhere on the site or in the near-about area.

14. Contractor shall observe all safety precautions during construction work. The contractor

shall ensure that his workers are working in normal safe working conditions. The Contractor

shall take out adequate necessary insurance policies to cover his workmen as per the

Workmen’s Compensation Act. The Contractor shall also take out appropriate third party

insurance.

14.1 Contractor shall provide at his cost safety and security of his workmen, machine and

materials (including those supplied by owners). The owners shall not accept any

responsibilities for the same.

Page 39: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

39

15 The Contractor shall keep necessary number of supervisors and atleast one qualified and

experienced Civil Engineer for full time for execution of work for entire project.

16 The Contractor shall provide free of cost a site office with normal furniture and facilities for

toilet in accordance with Owners Engineers, Architects requirements, for the use of

Owners/Architects and his site Engineer and his staff. He shall maintain these offices properly

during the entire duration of the contract. Contractor should also maintain a triplicate book, Bar

Chart, Set of Drawings etc.

17 Contractor has to provide labour accommodation on his own. Toilets, canteen, crèche, etc. as

required under labour laws shall be provided by the contractor, free of cost, outside the plot

premises.

18 The owner reserves the right to change the name to any other company and sub divide the works

to the other name/s on the same terms and conditions.

19 No extra payment shall be made for removal of water due to sub- soil, rain seepage, or by any

reason, water on ground or floor during all items of construction and at all phases of

construction.

20 SITE : Since the work involves construction of Piling, the Contractor shall visit and examine the site at

the place described in the Appendix to General Instructions to Contractors and satisfy himself as

to the nature of existing roads or other means of communication, the character of the soil and of

the excavations, the correct dimensions of the work and facilities for obtaining materials and

shall obtain generally his own information on all matters affecting the execution of the work.

21 BENCH MARKS :

The Contractor is to construct and maintain proper benchmarks to indicate the intersection of all

main walls in order that the lines and levels may be accurately checked at all times. The

Contractor shall provide suitable stones with flat tops and build the same in concrete for

temporary or permanent bench marks. All the pegs for setting out the work and fixing the

necessary levels required for the execution thereof shall, if desired by the Architect likewise be

built in masonry at such places and in such manner as the Architect may determine. Contractor's

rates shall cover for these factors.

22. PROGRESS CHART :

22.1 The Contractor shall submit time and progress chart and CPM Network fitted within the

specified overall period of completion (as stated in the Conditions of Contract) within 7

days of the communication of acceptance of the Tender, for the approval of the Architect.

22.2.1 Ancillary work should be so started that all such work is completed before the specified

overall contractual period of completion.

Page 40: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

40

22.2.2 Any failure on the part of the Contractor to adhere to the starting and completion dates

of individual items mentioned in the chart shall entail liquidated damages clause in

whole or part at the discretion of the Architect notwithstanding the overall period of

completion stated in the conditions of Contract.

23. MATERIALS AND WORKMANSHIP :

23.1 All the materials, (except those which will be issued free to the Contractor by the owner

for incorporation of work) stores and equipment required for the full performance of the

Contract must be provided through normal trade channels and must include octroi, excise

and import duties, Sales tax payable to all authorities and other charges. They shall be of

approved quality and the Contractor must be entirely responsible for the proper and

efficient carrying out of the work. The Contractor shall order all materials required for

the execution of the work from local/outside sources as early as necessary and to ensure

that such materials are on site well ahead of requirement for use in the work.

23.2 The Contractor shall furnish well in time before work commences, at his own cost, any

samples of materials or workmanship that may be called for by the Architect for his

approval or rejection and any further samples in case of rejection until such samples are

approved. Such samples when approved shall be the minimum standard for the work to

which they apply. In case of items like suspended ceiling, timber partitions, etc. typical

sample panels or prototypes shall be erected in position for approval before undertaking

work. Rates quoted shall cover for such preliminary work.

The work involved calls for a high standard of workmanship combined with speed.

Inferior quality of materials/workmanship will not be permitted under any circumstances

on the pretext of "Prevailing Practice".

Any workmanship or materials not complying with the specific requirements or approved

samples or which have been damaged, contaminated or deteriorated, must be removed

immediately from the site and replaced at the Contractor's expense as directed.

In regard to alternative items if any specified in the Schedule of Quantities, Contractor

should note that the Architect reserves the right to replace the principal item of the

schedule with an alternative.

If the contractor wishes to make bulk-purchases of any item, he shall inform Architect in

this regard, as a safeguard against a probable Design-Change, due to any reasons. No

claim in this regard will be entertained.

Page 41: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

41

24. MATERIAL TESTING :

The quality of all materials proposed to be used in the works will be as per the relevant

Indian Standard Specifications and will be generally in accordance with the provisions of

the Technical Specifications.

The Contractor will carry out routine tests on all building materials for ascertaining the

various qualities of the same as per the relevant tests procedure on samples collected at

intervals stipulated in respective IS codes and submit the reports in triplicate to the

Architects promptly.

The Contractor shall set up a field laboratory with necessary equipments for day to day

testing of materials, like grading of coarse and fine aggregates, silt content and bulkage

of sand etc. and for conducting routine, regular Field Tests like Sieve-Analysis, Silt

Content, Cube-Test, slump cone etc. as directed by the Architect.

25. INTERPRETATIONS:

26.1 Wherever the words "directed”, “as required”, “selected" or words of like effect are used,

it is to be understood that the selection, direction or requirement of the Architect are

intended.

26.2 The words "approved", "satisfactory “or words of like import shall mean "approved by"

or "satisfactory to" the Architect whose approval must first be obtained before the

materials ordered or the works to which the words refer to are put in hand.

The word "allow" shall mean that the Contractor shall include in his rates for the

particular matter referred to.

26.3 The words "as described" shall mean the description in the trade preambles, general

preambles, specifications, general instructions etc.

26.4 The word 'Providing' would mean to include 'Supply' (of approved make size., type,

colour, etc.) unless supply is categorically excluded from the item-description.

27. Proper Execution of Work:

27.1 The Contractor shall at his cost provide any necessary temporary enclosures, gates,

entrances, etc for the protection of the work and materials and for altering and adopting

same as may be required and removing the same at completion of the works and making

good all disturbances caused therefore. During inclement whether the Contractor shall

suspend concreting or plastering for such time as the Architect/Site Engineer may direct

and shall protect from damage such work in course of execution by approved measures.

27.2 Should the work be suspended by reason of rain, strike, lockouts or any other cause, the

Contractor, shall at his cost take all precautions/insurances necessary for the protection of the

work and shall make good any damage arising from any of these causes.

Page 42: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

42

27.3 The Contractor shall at his expense cover up and protect from injury from any cause all

new work and supply all temporary doors, protection to windows, and any other requisite

protection for the whole work executed, whether by himself or special tradesmen or sub-

contractors and any damage caused must be made good by the Contractor at his own

expense.

27.4 All fences, trees, shrubs, grass, lawns and other surfaces around the buildings or

approaches thereto, which are required to be maintained are to be kept free from damage

due to operations in connection with the work, at Contractor's expense.

27.5 The Contractor shall, at his expense protect all projecting sills, jambs, copings, stone or

concrete treads and moldings and all concrete steps, woodwork and joinery and the like from

injury during the progress of the work by rough timber casings securely fixed. The

Contractor shall at his cost protect joinery and make good all damage to same from any

cause whatsoever during the performance of the Contract and leave perfect to the satisfaction

of the Architect at completion. Before giving up possession the Contractor must see that all

doors, windows, and ventilators, etc. work easily and shall make all necessary adjustments.

27.6 Idle-time will not be payable, under any circumstance. The Contractor is expected to

plan his resources, keeping in view site-conditions.

27.7 The contractor shall provide at no extra cost temporary masonry or protective barriers

upto 1200 mm height from the floor level to all lift wells and/or shafts openings on all floors

to safeguard against any accidental fall and maintain them till such time as permanent

enclosures are installed.

27.8 Any instructions given verbally shall be deemed instructions for the proper execution of

the works not involving extra charges.

27.9 The contractor shall not carry out any work between hours of sunset and sunrise without

the permission of the Engineer in charge in writing. However, proper illumination will be

provided during the execution of work by the contractor at his own cost.

28.A ARCHITECT'S REPRESENTATIVES :

The duties of Architect's Representative are to watch and supervise the works and to test

and examine any materials to be used for workmanship employed in connection with the

works. He shall have no authority to relieve the Contractor of any of his duties or

obligations under the Contract nor except as expressly provided hereunder to order any

work involving delay or any extra payment by the Employer nor to take any variation of

or in the works.

Architect may from time to time in writing delegate to Architect's Representative further

powers and authorities and shall furnish to the Contractor a copy of all such written

delegations of powers and authorities. Any written instructions or written approval given

Page 43: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

43

by Architect's Representatives to the Contractor within the terms of such delegation (but

not otherwise) shall bind the Contractor and the Employer as though it had been given by

Architect provided as follows:

1. Failure of Architect's Representative to disapprove any work or materials shall

not prejudice the power of Architect thereafter to disapprove such work or

materials and to order the pulling down, removal or breaking up thereof.

2. If the Contractor shall be dissatisfied by reason of any decision of Architect's

Representative, he shall be entitled to refer the matter to Architect who shall

thereupon confirm, reverse or vary such decision.

The contractor shall on the written request of Architect's representative on the site

immediately dismiss from the works any person employed by him there on who

may in the opinion of the Architect be incompetent or misconduct himself and

such person shall not again be employed on the works without the written

permission of the Architect.

B OWNERS REPRESENTATIVE :

Owners representatives shall be responsible to instruct all the works, materials, checking

and measuring time and materials. He shall have power to give notice to the contractor or

to his representative of non-approval of any work or materials and such work shall be

suspended or the use of such materials shall be discontinued until the decision of the

Architect is obtained.

The Contractor shall assist in any work to be carried out by the owners representative.

29. ACCESS TO WORK :

The Contractors shall at all times give access to authorized representative of the local or

other authorities or any men directly employed by the owner or other agencies or the

consultants and their representatives.

30. SUB-CONTRACTORS :

30.1 CO-ORDINATION:

The Contractor shall be responsible for the Co- ordination of all the work including that of other

sub-contractors and nominated sub-contractors or any other agencies deployed by the owner &

working on the site for arranging runs of all services and working to the requirements and

layouts of the specialist trades, in all matters necessary for the complete execution of the work.

30.2 Rates quoted by the Contractor shall be inclusive of all attendance on sub-contractors or

other contractors nominated by the Architect/Owner. Contractor must allow for provision

of the use of his scaffolding to sub-contractors and for its retention until such time that all

relevant sub-contract works are completed.

Page 44: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

44

30.3 The Contractor shall accept liability for and bear the cost of the supply of all necessary

water, electricity, lighting, security, etc, for the sub-contractors work.

30.4 The contractor must allow in his rates for making good any holes and chases left by the

sub-contractors or other contractors nominated by the Architect before the Contractor's

work is completed and handed over.

30.5 Contractor may appoint a Sub-Contractor if required at his cost after taking prior written

approval from the Architect. The owner shall not be responsible for any liabilities

towards such sub-contractors.

31. WORK COMPLETION : The whole work including all extra and additional items is to be completed in the

completion period stated in the Appendix to conditions of contract and the Contractor

will be required, if necessary to work overtime to fulfill the Architect's instruction to

complete the work by the Contract date. No extra will be allowed on the Contract Sum,

for such overtime work. If part premises are occupied by the owners, contractor shall

provide necessary barricades to ensure that further construction activity does not hamper

and nuisance does not happen in the occupied area.

32. MEASURMENTS :

32.1 The contractor or his representative shall accompany the Site Engineer when required to

do so and assist in taking the measurements and shall agree to the measurements

recorded on the spot.

32.2 If the Contractor fails to accompany the Site Engineer or any other person that has been

duly authorized by the Architect to take measurements then in such a case, the

measurements recorded by the Site Engineer or Architect's representative shall be

binding on the Contractor.

32.3 All measuring tapes shall be of steel and scaffolding and ladders that may be required

for taking measurements shall be supplied by the Contractor at his expense,

Measurements of all items of work including extra items, if any, such as work in

foundations including excavations, plinth filling, masonry concrete etc, steel in all R.C.C

works, pipe to be encased etc. shall be got recorded from the authorized Site Engineer by

the Contractor before they are covered up. Immediately the work is ready for

measurements, Contractor will give specific notice to Architect and Site Engineer for

recording the measurements. If the Site Engineer fails to record the measurements, the

Contractor will refer the matter to the Architect for instructions but in no case shall cover

up the work without his permission.

The measurements for any item shall be as per IS 1200.

The contractor shall provide necessary access and assistant to verify the measurement by

the owner / Architects / ENGINEER INCHARGE.

Page 45: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

45

33. EXTRA WORK & CLAIMS:

It must be clearly understood that the whole of the conditions and specifications are

intended to be strictly enforced, and that no extra charges in respect of extra work will be

allowed unless they are clearly outside the spirit and meaning of the conditions nor

unless such works shall have been ordered in writing by the Architect/Owner.

Rate Analysis must accompany every claim for Extra-work, for scrutiny and

recommendation by Architect/Owner.

No Extra work should be executed, without prior written instructions from

Architect/Owner.

The Contractor is not entitled to refuse to do any Extra-item or Exceeded-item, on the

plea of not being in the existing scope for all such works which are related to this Tender

& akin to the awarded scope.

The intent & spirit of work described is always to be reckoned with, before lodging any

Extra claim.

For extra items, mode of measurements shall be followed as per I.S. 1200.

Rates for non-tendered items of work ordered which cannot be worked out

proportionately shall be settled by the Architect & paid for accordingly by the Owner on

the basis of Actual cost of labour expended, landed cost of materials used, depreciation

charges of equipment plus 15% to cover overheads and profits.

34. MINIMUM WAGES ACT / LABOUR STATUTES : The Contractor shall pay rates of Wages and observe hours of work and conditions of

employment according to existing rules under Minimum Wages Act. Further, it shall be

Contractor's responsibility to ensure that he pays his workmen wages which are not lower

than the minimum prescribed by the Union Government and State Government in which

area this contract is being operated. The contractor shall be responsible to pay all

statutory payments to relevant authorities towards ESI, PF etc., as per the rules in vogue

or amended by government in case of execution of the contract. Contractor shall not

employ any labourer under the age of 18 years.

36. STORAGE OF MATERIALS: The cement issued by owner shall be stored at the site in weatherproof Cement godown

built by the contractor in such a manner so as to prevent deterioration due to moisture or

intrusion of foreign matter.

The aggregate shall be stored in such a way as to prevent admixture of foreign materials.

The heaps of fine and coarse aggregates shall be kept separately. When different sizes of

fine or coarse aggregates are procured separately they shall be stored in separate stock

piles sufficiently away from each other to prevent the material at the edges of the piles

from getting intermixed.

Page 46: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

46

Steel reinforcement shall ordinarily be stored in such a way as to avoid distortion and to

prevent deterioration and corrosion. It is a good practice to coat reinforcement with

cement wash before staking to prevent scale and rust.

All materials shall be so stored as to prevent deterioration or intrusion of foreign matter

and to ensure the preservation of their quality and fitness for the work. Any material,

which has deteriorated or has been damaged or is otherwise considered defective by the

Architect shall not be used for the concrete.

As far as possible contractor should not store the material in buffer zone area, however, if

it is needed, contractor should not disturb the existing ground, its nature, its levels etc.

the contractor should put the wooden planks or tadpatri before storing the material.

37. REINFORCED CEMENT CONCRETE (RCC) WORK

a) Ready mixed concrete ( RMC) of pumpable workability shall be used in the

work. RMC shall be designed to achieve characteristic strength required for the

RCC elements stipulated in Drawings. RMC shall be obtained from approved

manufactures like Larsen & Toubro ( L & T ), ACC, RMC Ltd etc. Admixture of

Fly Ash upto the limit of 15% ( Fifteen percent) of cementations material in RMC

is allowable provided desired strength is achievable. Concrete Pumps from the

said manufacturer shall be obtained for pumping concrete to the required height of

the building. RMC shall be designed to achieve required characteristic strength &

as per Acceptance criteria defined in IS : 456 : 2000. RMC supplied shall

conform to stipulation made in IS:4926:2003. Before placing order for Ready

Mixed Concrete, the following information shall be got approved from

ENGINEER INCHARGE.

a) Physical & Chemical properties of cement

b) Physical & Chemical properties of Fly Ash

c) Sieve Analysis of coarse & fine aggregates

d) Slump of Concrete, both at the time of dispatch at the RMC Plant & at site

when delivered –since concrete is pumpable.

e) Temperature of Concrete at delivered end.

f) Test Report of Water admixed in RMC

g) Mix Design details of RMC – especially Cement content, details of

manufacture of Cement & its cost

h) Taking cubes at site by the RMC manufactures & testing at their

Laboratories & submitting reports -This shall be done every day of supply.

i) In addition, contractor shall take cubes & test the same at site concrete

Laboratory.

Page 47: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

47

The reports shall be obtained from RMC supplier such as material Testing requirements

etc as per Annexure B of IS:4926:2003 to ensure quality of RMC Supplied. All material

including Cement & admixture shall be procured by the Contractor & the Scope of

supply of RMC is inclusive of all materials.

a) Site Mixed Concrete

In some exigencies, site mixed concrete will be permitted to avoid loss of construction

time. In order to ensure quality of work used for site mixed concrete, the contractor shall

carry out Mix Design for concrete as per IS: 456: 2000 & the mix so designed shall be

approved by the ENGINEER INCHARGE. Fine aggregate & stone aggregates to used in

concrete shall conform to IS: 383. Fine aggregate for the concrete shall be ‘River sand’

and shall conform to zone 1 or zone 2 of IS 383.

The concrete shall be so designed as to produce grade of concrete shown in respective

drawings & shall have moderate workability of 75-90 mm slump & characteristic

strength not less than the appropriate value given in IS : 456:2000, Table 2 ‘Acceptance

Criteria’ concrete shall be as defined the IS code.

Suitable water reducing admixture shall be added in green concrete to achieve

workability without disturbing water – cement Ratio. Cement to be used for manufacture

of concrete shall be Port land Puzzolana cement (PPC)

While laying concrete for RCC work either with RMC or site mixed concrete, a bond

coat of polymer SBR of approved manufacturer viz. Sunanda, Pedilite etc. shall be

applied for bonding old concrete to new concrete. Direction for use of such Polymer

application shall be in conformity with the procedure recommended by the Manufacturer.

Contractor shall establish ‘Concrete Testing Laboratory’ at site which shall be furnished

with equipment shown in Annexure - C

For site mixed Concrete only Cement will be issued for incorporation of work, all other

materials including admixtures shall be procured by the contractor.

40. MINIMUM REQUIREMENT OF IMPLEMENTS TO BE MADE AVAILABLE BY THE CONTRACTOR AT SITE.

List of minimum requirement of implements to be made available at site by the contractor is

as below:

1. Two sets of measuring boxes each of capacity 20 Ltrs, 25 ltrs, 30 Ltrs, 40 Ltrs and 45 ltrs

shall be provided.

2. 5 liter can & 1 liter can for measuring water.

3. 2 Nos. of 200 liters capacity drums for storing water near concrete mixer.

Page 48: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

48

4. 500 ml slotted plastic beaker for measuring construction chemicals to be admixed in

concrete.

5. 100 Kg weigh balance for cement weighing.

6. 100 Kg spring weigh balance for weighing fly ash.

7. Black board for writing concrete mix design. Details near the mixer.

8. G.I. Tray for mixing concrete / cement mortar.

9. 15 cm Cube moulds – 16 Nos with 16 mm dia tamping rod.

10. Slump cone.

11. One bucket for storing construction chemical.

12. Half round supra near mixer.

13. Necessary High level tank for storing water for concrete, rubber hose from the tank upto the

mixer and tap.

14. G.I. pan for collecting concrete.

15. Proper shed to be put up for cube curing tanks and over concrete Mixer ( to cover the mixer

hopper and concrete unloading area) & the place where cubes are filled by the Lab-

Technician.

16. Cube Kanda should be available with labours while fixing cube moulds & Set Square should

be available for checking right angle of cubes.

17. Permanent Bins with separators should be made by constructing partitions from UCR

Masonry for stacking of aggregates separately.

18. Calibrated weigh balance for weighing Cubes of 10 kg capacity with weights varying from 5

kg to 5 gram.

19. Hand pump for removing construction chemicals from drum.

41. QUALITY NORMS TO BE ADHERED DURING EXECUTION OF

CONCRETING WORK

A) Shuttering/ Scaffolding

1) Shuttering Oil should be of good quality. Motor waste oil should not be used. Excess oil

should not be applied over slab shuttering.

Page 49: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

49

2) Staging/ Platform made for concreting of columns shall not touch to the column

shuttering to avoid disturbing the plumb / alignment of columns.

3) Damaged, distorted shuttering plates / planks shall not be used so that proper line, level

& finish of the concrete could be achieved.

4) All shuttering materials like acrow spans, props, shuttering plates etc shall be in good

working condition.

5) Masking tape (3” width) shall be affixed on the joints of the MS Plates/ Plywood

shuttering to avoid leakage of slurry during concreting.

6) Staging design required for shuttering for slabs of more heights, shall be got approved

before erecting the same. Necessary hooks in concrete at lower floors for erecting of

staging are to be provided for upper floors if required & for fixing safety nets.

7) In case of MS Plates, cleaning shall be done thoroughly so to remove old skin of

concrete, before erecting same at site. No bent plates shall be used.

B ) Reinforcement Tying

1) Top stirrups of column shall not be buried half inside the concrete & half outside. It shall be

at least 40 mm below top level of concreted column. Same is to be ensured for column

starter also.

2) Winged cover kanda shall be provided to ensure correct cover to rebar.

3) Tying of rebars shall be arranged in such a way that 60/40 mm needle of the vibrator could

go down till bottom of column concrete to ensure complete compaction.

4) Consumption of binding wires should be at least 9 Kg/MT, which shall be procured by the

contractor at his cost

5) Joggling of column reinforcement (Longitudinal steel ) shall not be done within starter. It

shall be at column portion below. Lapping for longitudinal steel & reinforcement tying at

beam –column junctions shall conform to the requirement indicated in RCC

C Concreting

1) Cement slurry with w/c ratio same as that of column/ slab concrete shall be prepared and

splashed over re-bars and at the interface of old and new concrete.

Page 50: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

50

2) Concrete mix for RCC work shall be so designed as to achieve respective grade of concrete

as shown in RCC drawings. The concrete mix is to be designed as per clause 3.23 above.

Gunny bags shall be spread over the slab for the purpose which shall be kept continuously

wet for 24 hours by mist spray of water. After 24 hours, curing shall be done by ponding of

water for 10 days, since Puzzolona admixture is used in concrete.

3) Sequence to be followed for loading material in hopper of mixer shall be as follows:-

CA II + FA + CA I + Cement + Fly ash + CA II + FA + CA I

4) Cement bags shall be weighed periodically to ensure that 50 Kg. of cement is added for the

concrete mix and is not less.

D Good Engineering Practice

1) Chipping shall be done on the top of the columns to remove laitance before de-shuttering

which shall be done taking care that no corners of columns are damaged. Chipping shall be

done on the next day of column casting.

2) Extra vibrator shall always be kept ready as a standby, along with spare needle.

3) Date of casting shall be written on all concrete surfaces to ensure curing regime.

4) Sufficient lighting arrangements shall be done during work done at night.

5) When vertical stopper is required at construction joints, Sausages made out of empty

cement bags is kept below reinforcement to prevent slipping of concrete beyond the joint

at the time of concreting. Above the reinforcement, wooden planks shall be properly fixed

at the joint in a staggered manner, so that the joint is made in two vertical strips of 30 cm

width ( Ell shaped joints)

6) During monsoon, proper covering (pandal) shall be provided to protect from rain fresh

concrete especially over slabs.

7) Gaps between mixer blades and gap between mixer blade & drum shall not be more than

25 mm. (maximum size of aggregate) to ensure proper mixing of concrete. If necessary

mixer blades are to be modified as required by ENGINEER INCHARGE for proper

mixing of concrete.

8) Contractor shall strictly follow Safety Norms as required.

9) Contractor shall always maintain Good House Keeping at site , especially throwing

Page 51: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

51

wooden planks with nails protruding above , cutbits of reinforcement lying scattered etc.

10) Reinforcement steel shall be stacked in raised platform to avoid contact with ground.

11) Hacking of concrete atleast at 2’’ spacing shall be done to ensure adhesion of plaster

12) Waterproofing work shall be got done through Specialized Agencies viz. India

Waterproofing CO. or Likproof

42. PROCEDURE FOR SUBMISSION OF INTERIM & FINAL BILL

The following procedure & shall be strictly followed for submission of Interim bill & the final

bill

a) Measurements shall be recorded in measurement Books jointly

b) Thereafter the same shall also be done on computer Excel Format.

c) Abstract sheet shall also be done on computer Excel Format.

d) 4 copies shall be submitted along with each bills

e) Recording of measurement shall be done in a systematic manner so that no time is lost

not only in verification of R.A. Bills but will also facilitate verification final bill early.

Measurement shall be finalized in stages.

Page 52: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

52

SECTION - 7

STANDARD SPECIFICATION

PART I - LIST OF SPECIFICATIONS

MATERIALS :

Material used shall conform to appropriate standards specified by the Indian Standards

Institution and unless otherwise specified, these standards will form a part of these

specifications. In particular, the following standards have been referred to :

AGGREGATE :

IS : 383 : 1952 : Specifications for coarse & fine aggregates from Natural

Sources for Concrete.

IS : 383 : 1963 : -do-

IS : 515 : 1959 : Specification for natural &manufactured aggregates for use in

mass concrete.

IS : 1542 : 1960 : Specification for sand for plaster.

IS : 1607 : 1960 : Methods for dry sieving method of test for aggregates for

concrete.

IS : 2386 : 1963 : Part-I particles size and shape.

IS : 2386 : 1963 : Estimation of deleterious material Part-Inorganic impurities.

Part II

IS : 2386 : 1963 : Specific gravity, density, voids.

Part-III

IS : 2386 : 1963 : Mechanical properties.

Page 53: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

53

Part-IV

IS : 2386 : 1963 : Soundness.

Part-V

IS : 2386 : 1963 : Measuring mortar making properties of Part-VIfine aggregates.

IS : 2386 : 1963 : Alkali aggregates reactivity.

Part-VII

IS : 2386 : 1963 : Petrographic examination.

Part-VIII

CEMENT :

IS : 269 : 1958 : Specification for ordinary rapid hardening and low heat portland

cement.

IS : 1258 : 1958 : Methods of test for determination of free lime in Portland

Cement.

IS : 1489 : 1962 : Specification for portland pozzolana cement.

IS : 455 : 1962 : Specification for portland blast furnace slag cement.

IS : 4032 : 1968 : Method of Chemical Analysis of Hydraulic cement.

CONCRETE :

IS : 1199 : 1959 : Methods of sampling and analysis of concrete.

IS : 516 : 1959 : Methods of tests for strength of concrete.

REINFORCED CONCRETE :

IS : 456 : 2000 : Code of practice for plain and reinforced concrete for general

building construction (Revised).

PRESTRESSED CONCRETE :

IS : 1345 : 1960 : Code of practice for prestressed concrete.

Page 54: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

54

IS : 2090 : 1962 : Specifications for High Tensile bars used in prestressed concrete

STEEL IN REINFORCEMENT :

IS : 432 : 1960 : Specification for mild steel and medium tensile bars and hard

drawn steel wire for concrete reinforcement.

IS : 432 : 1966 : -do- (Part -I)

IS : 432 : 1966 : -do-

Part-II

IS : 816 : 1956 : Code of practice for use metal are welding for general

construction in mild steel.

IS : 1139 : 1966 : Specification for hot rolled mild steel and medium tensile steel

deformed bars for concrete reinforcement.

IS : 1566 : 1961 : Specification for hard drawn steel wire fabric for concrete

reinforcement.

IS : 1785 : 1967 : Specification for plain hard drawn.

Part -II

IS : 1786 : 1966 : Specification for cold twisted steel bars for concrete

reinforcement (Revised).

IS : 1786 : 1961 : Specification for cold twisted steel bars for concrete

reinforcement.

MISCELLANEOUS :

IS : 1200 : 1962 : Mode of measurement of buildings.

IS : 1255 : 1958 : Code of building by-laws.

IS : 1020 : 1957 : Conversion tables on ordinary

IS : 1256 : 1967 : Code of practice for building

IS : 1200 : 1968 : Method of measurement of building Civil Engineering work

(Part) concrete works -2nd revision.

Page 55: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

55

Signature of the Contractor Signature of the Employer

Place : Place :

Date : Date :

Page 56: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

56

STANDARD SPECIFICATIONS

PART II - MATERIALS AND WORKMANSHIP :

01 GENERAL :

All materials brought on the site of works and meant to be used in the same, shall be the best of their

respective kinds and to the approval of the Architect. The architect or his representative will accept

that the material are really the best of their kinds, when it is approved beyond doubt that no better

materials of the particular kind in question are available in the market.

02 SAMPLES : a) Samples of all materials shall be got approved by the Architect and shall be deposited

with him before the order for the materials is placed with the supplier. The materials

brought on the works shall confirm in every respect to the respective approved samples.

b) Contractors shall make one mock up for Clean Room & other lab after discussing with

the owner / Architect for approval.

03 CHECK :

The contractors shall check each fresh consignment of materials, as it is brought on to the site

of the works, to see that they conform in all respects to the specification and/or the samples

approved by the Architect.

04 TESTING :

The architect will have the option to have any of the materials tested to find whether they are in

accordance with the specification, and the contractors will bear all expenses in that connection.

All bills vouchers and test certificate which, in the opinion of the Architect or his representatives

are necessary to convince him as to the quality of the materials or their suitability shall be

produced for his inspection on requisition.

05 REJECTION :

Any material that have not been found to conform to the specifications will be rejected

forthwith and shall be removed from the site by the contractors at their own cost.

06 STORING : The materials shall be stored or stocked on the site as directed by the Architect and if any

additional space is to be hired for this purpose, the contractors will do so at their own expense

07 PURCHASE : The Architect shall have power to cause the contractor to purchase and use such materials from

any particular source as may in his opinion be necessary for the proper execution of the work.

Page 57: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

57

08 SPECIAL MATERIALS : Any special materials that may be required on the works which are supplied by any other

person or firm selected by the employers or by the architect on their behalf shall be taken over in

writing by the contractors for safe custody until they are required on the works when called

upon to do so by the Architect. The contractors will be responsible for all special materials or

articles which may be supplied by specialists.

09 CEMENT : a) The cement used throughout the work shall be ordinary portland cement of an approved

manufacture and shall comply in every respect with the conditions, analysis and tests laid

down in the latest I.S.S. Quick-setting cement should not be used without the special

permission of the Architect.

b) Any particular consignment of cement from which the sample has been taken shall not be

used on the works till the test certificate is received. If the cement is found no the

conform to the latest I.S.S. by the test, it will be rejected and shall be removed forthwith

from the works.

c) The Architect reserves to himself the option to have every consignment of cement

tested before use if he thinks it desirable in view of the varying qualities of the cement

used on the works from whatever cause such variance may be.

d) the cement shall be stored in a weather proof shed on dry wooden platform floor at least

a foot above ground level and an equal distance from any wall so that fee circulation of

air shall take place. The cement shall be stored in such a manner as to prevent

deterioration or contamination and to permit easy access for inspection.

e) No cement that has been kept stored for too long a period to deteriorate in quality or that

has become caked or damaged by dampness or otherwise, shall under any circumstances

be used on the works but shall be removed from the works. If cement is stored in high

stacks for a long period causing the lower layer to harden on account of pressure this so

called "Warehouse set" shall be no reason for rejection.

f) If a clogged bag of cement after dropping on a solid floor becomes thoroughly reduced to

power again the hardening shall be considered "warehouse set". Whether the hardening is

caused by dampness or by "warehouse set", shall be decided by the Architect.

10 CEMENT MORTAR :

a. The cement mortar shall be in the exact proportion of the mix as specified for that

particular item of work in the schedule of quantities and rates. The cement and sand to be

used for cement mortar shall be carefully gauged in suitable sized boxes thoroughly

mixed in a dry state on a clean wooden platform or masonry plastered over specially

constructed for the purpose by the contractor as instructed by the Architect, and mixed

again after the addition of the requisite quantity of fresh water. It shall be prepared in

Page 58: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

58

such quantity as can readily be used up and mortar which has partially set shall under no

circumstance be re-tempered by being mixed with additional material or water.

11 SAND :

a) The sand used shall be river or pit sand free from any clay, loan earth or vegetable matter

and shall be clean and fir for use in the opinion of the Architect or his representative. The

same shall be screened or washed in clean water if necessary as directed by the Architect

or his representative.

b) The sand used for concrete shall be of sharp, angular, grit type, and well graded and shall

pass through a sieve having meshes 3/16" square measured in the clear. Fine sand will

not under any circumstances be used for the concrete or mortar.

c) The sand for the first coat of plaster mortar shall pass through a sieve of 64 meshes per

square-inch and for the 2nd and 3rd coats of plastering, pointing etc. shall be clean, sharp

and gritty to the touch and shall pass through 324 meshes to the square-inch.

d) The sand will not contain any trace of salt or other harmful matter and it shall be tested

for its sand contents, when the architect chooses at the expenses of the contractors. The

contractors shall provide for this purpose measuring glasses dilute nitric acid, silver

nitrate solution etc. all as required by the architect or his representative. Sand containing

any trace of salt will be rejected at the option of the architect.

12 AGGREGATE :

a) The aggregate for the works shall be blue stone. It shall be obtained form sources

approved by the Architect. It shall be angular and with sharp corners and well graded and

shall have granular or crystalline (not glossy) non-powdery surfaces. The aggregate

should be clean and free from all clay or loamy admixtures or any vegetable matter and

will be gauge specified. All coarse aggregate shall be stored in the works in such a

manner as to prevent the introduction of foreign matter. If not perfectly clean and found

not to conform fully to the gauge specified it shall be washed and screened before use.

b) For all reinforced concrete work the aggregate shall pass through 3/4" gauge for no. 1

metal and 1" gauge for no.2 metal. If any rounded peddles flaky or decayed stones are

found in the aggregate the whole consignment is liable to be rejected. The architect

reserves the right to vary the gradion as stated above.

c) The grading of the aggregate will be down in accordance with the specification issued by

the concrete association of India and the said specification shall be followed in regard to

samples of test, requirements of screens, sieves etc. and as instructed by the architect. All

Page 59: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

59

sieves, screens, etc., that may be necessary to carry out any tests as to ascertaining the

suitability of the aggregate for that particular work in hand will be provided by the

contractor at his own expense.

13 WATER :

Water shall be clean and free from oil, acid , alkali, earthy or organic matter and other

deleterious substances & generally fit for drinking, Water shall be taken from the Municipal

main. Arrangement for storing of water if necessary in drums or tanks shall be made. Due care

shall be exercised to see that water is not contaminated in any way.

14 REINFORCEMENT :

a) Unless otherwise specified in writing by the Architect all reinforcing steel used on the

works shall be Fe 500 conforming in every respect to the latest "ISI" for Fe 415/Fe 500.

b) The Architect reserves to himself the right to have any test pieces taken from the steel

that is brought to be used on the works, and tested in the recognized test house at the

contractors expenses to see whether the steel used really conforms to the latest I.S.S.

c) The steel reinforcement used for the reinforced concrete work shall be free

from any scales of rust, oil, grease, or other coating of any character which would reduce

or destroy the bond and shall be of the size and length as specified. Too many lap joints

will not be allowed and the architect or his representative will reject all such

reinforcement.

d) All other steel works shall also conform to the relevant I.S.S.

16 WORKMANSHIP

a) All works shall be of level, plumb and square, and corners, edges and arises in all cases

shall be unbroken & finished neat.

b) Any workmanship not to the satisfaction of the architect or his representative will be

rejected and the same shall be removed and replaced with works of the required standard

workmanship at no extra cost.

17 CHECKING : Skilled masteries for the respective traders shall be employed by the contractor to check the

work of the bricklayers, plasterers, joiners or any other tradesmen as the work is in progress and

to instruct and extract the right kind of workmanship from the men employed on the works.

Instructions given to such masteries by the architect or his representative shall be carried out

with a view to get the works executed in a neat and workmanlike manner, according to these

specifications.

Page 60: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

60

18 TESTING : The architect may order the testing of any finished work as he chooses and in a manner he

decides and the contractor shall bear all expenses in that connection. If the results of such tests

prove that the workmanship is not of the standard required, the total work will be rejected and

removed forthwith and be replaced by the works of the acceptable standard of quality.

Read and confirmed as above

Signature of the Contractor

Page 61: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

61

PART III - STRUCTURAL / CONCRETE WORK

01 GENERAL :

a) All concrete work shall be done as per the drawings and the instruction of supervising

officer.

b) Concrete work shall be carried out under the direct supervision of capable foreman,

experienced in reinforced concrete construction. The clerk-of-works shall watch and

supervise all stages of the work. No concrete shall be prepared or placed in the absence

of the clerk-of-works.

c) The proportioning of ingredients for concrete shall be such as to ensure that the resultant

concrete will be sound, dense, durable and of the strength and have the other properties

as specified.

d) All concrete should be machine mixed and vibrated immediately after placing in the

position.

2 MATERIALS :

a) AGGREGATES: All aggregates shall conform to IS : 383-1970. The maximum size of

coarse aggregate should be as large as possible within the limits specified but restricted

to one fourths of the minimum thickness of the member or such that the concrete can be

placed without difficulty so as to surround all reinforcement thoroughly and fill the

corner of the form. Fine aggregates shall be natural sand free from salt, dust and other

impurities. 25% of the total requirement of the sand can be replaced by stone dust with

the approval of Engineer-in-charge.

b) WATER : Water used for both mixing and curing shall be free from injurious amounts

of deleterious materials. Potable water will be considered satisfactory for mixing and

curing concrete.

c) ADMIXTURES : Admixtures may be used in concrete only with the approval of the

ENGINEER-IN-CHARGE based upon evidence that with the passage of time neither the

compressive strength of concrete is impaired nor other requisite qualities of concrete and

steel impaired by the use of such admixture. Calcium chloride or any other corrosive

admixture should not be used.

d) REINFORCEMENT : The reinforcement shall be (a) Fe415/Fe 500 and medium

tensile steel bars and hard drawn steel wire conforming to IS : 432-1979 (b) Cold twisted

bars conforming to IS : 1786-1979. All reinforcement shall be cleaned and free from

Page 62: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

62

loose mill scales, dust, loose rust and coats of paints, oil or other coatings which may

destroy or reduce bond. Welded joints in reinforcement may be used but in all cases of

important connections, tests shall be made to prove that the joints have atleast full

strength of bars connected. Welding of reinforcement shall be done in accordance with

the recommendations of relevant Indian Standard for welding of mild steel bars used in

reinforced concrete construction.

03 TESTS :

Appropriate tests as per codal requirement are required to ascertain that the materials used in

Construction conform to these specifications. Wherever there is a change in size or proportion

of materials tests should be carried out for materials. It is to be noted that cement is stored for

more than three months or is affected by moisture, it shall be tested before use.

04 WORKMANSHIP – FIXING OF REINFORCEMENT:

a) The contractor shall assemble all reinforcement in accordance with the drawings by

binding wire. Cover shall be maintained by the proper use of chairs, spacers or non-

porous concrete blocks.

b) A steel fixer shall be in attendance during concreting to rectify any unavoidable

displacement as the concrete is placed.

c) Column starter bars shall be held accurately in position with suitable template. Placement

of reinforcement alongside with the concreting shall not be permitted.

d) Where splices are provided in the reinforcement they shall be away from the sections of

maximum stress and shall be staggered. For compression members such as columns the

splice shall be at floor level unless mentioned otherwise. Lap strength shall be provided

as follows - compression member : 40 x dia of bar-tension member : 60 x dia of bar or as

directed by the structural consultants.

05 - WORKMANSHIP - FORMWORK :

a) The responsibility for the safety and adequacy of the formwork shall rest entirely

with the contractor.

b) The Contractor shall give 24 hours minimum notice when formwork is ready for

inspection and allow a sufficient time for inspection and adjustment.

c) The ENGINEER-IN-CHARGE may reject formwork which in his opinion is

unsatisfactory either in construction or finish but this shall in no way diminish or

relieve the contractors responsibility.

d) Form linings shall be such as to produce concrete to the shapes, lines, levels and

dimensions required by the contract drawings and with the surface finish and

Page 63: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

63

within the tolerance specified. Form lining joints shall be kept to a minimum.

Lining edges shall be smooth even and tightly butted and sealed with water

proofed sensitive tape.

e) Form work shall be constructed from sound material, properly supported and

braced or tied so as to maintain the true position and shape of form linings during

and after the placing of the concrete.

f) M S Tabular vertical supports shall be sufficient in number and shall be

wedged or adjustable to allow lowering of form work before stripping and shall

have sole plates of adequate bearing area to prevent any settlement after loading.

g) The contractor shall remove all debris from the interior of form lining before

concrete is placed. The surface which are to be in contact with concrete shall be

cleaned and wetted or treated with an approved form releasing agent before

placing reinforcement.

06 - WORKMANSHIP - DESIGNED MIX CONCRETE :

a) Concrete mixes for various specified characteristic strength shall be worked out by the

contractor by any of the recognized methods of design concrete grades 15, 20, 25, 30

shall be comprised of not less than 270 kg. 350 kg. 400 kg. and 450 kg. of cement per

cu.m. of concrete respectively. Maximum aggregate size shall not exceed 20 mm.

b) The water cement ratio and the proportions by weight of fine to coarse aggregate and of

cement of aggregate shall be such that the concrete produced is homogeneous free from

voids watertight and of maximum density consistent with proper workability. Both

possible to minimize shrinkage. Six preliminary laboratory cubes shall be made and

tested for each mix and shall have a mean 28 days cube strength of not less than 25 N/m.

Sq.mtrs., 30 N/m. Sq.mtrs., 35 N/m. Sq.mtrs. & 40 N/m/ Sq.mtrs. for concrete grades 15,

20, 25, and 30 This is based on standard deviation of +/- 5%

c) Full information regarding the materials their sources and mix design shall be forwarded

to the consultant for his approval before placing concrete on site. However it shall be

clearly understood that such approval shall not absolve the contractor of his

responsibility for compliance of works test results.

d) All designed mix concrete shall be prepared by weigh- batching.

e) If the design mix concrete cannot be used nominal mix may be use in compliance with IS

: 456-1978. Concrete mixed in the proportion stated would have compressive strength at

28 days after placing not less than the following :

07 - WORKMANSHIP - CONCRETE MIXING : Concrete shall be mixed in a mechanical mixer. The mixer should comply with IS : 1791-

1968. The mixing shall be continued until there is a uniform in colour and consistency.

Maximum time for mixing shall be 2 min. The mixer shall at all times be kept free from set or

partially set concrete.

Page 64: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

64

08 - WORKMANSHIP - CONCRETE PLACING :

a) All concrete shall be placed under the direct supervision of a engineer-in-charge. All

concrete shall be vibrated with mechanical or electrical vibrators.

b) The contractor shall maintain on the site one spare mechanical vibrators over and above

those in use.

c) Concrete shall not be placed at any time under conditions which would prevent the

standard of concrete required from being attained.

d) Concrete shall be conveyed to final position and deposited in formwork by methods

which will prevent segregation or loss of materials. For high-rise building concrete shall

be transported at higher level by mechanical hoisting. In thin walls or columns over 1200

mm. high concrete shall be purred through enclosed chutes kept as vertical as possible

during placing.

e) Concrete shall be deposited continuously in such a manner so as to maintain a wet edge.

Uncompleted edges shall not be left for longer than 30 min.

f) Construction joints shall be formed where indicated and to detail on Structural

Engineering Drawings. Where it is necessary to form construction joints other than those

indicated their location shall be to the approval of engineer-in-charge.

g) Hardened concrete surface shall be kept ready to receive fresh concrete by cleaning to

remove all loose or soft materials, foreign matter and laitance and roughened for key.

Immediately before depositing fresh concrete a coat of neat cement slurry shall be

applied to the surface. Concrete shall be deposited before the slurry dries out.

h) Immediately after depositing the concrete shall be compacted by means of a mechanical

vibrator (having not less than 6000 vibrations per min.) carefully worked around the

reinforcement and embedded fixtures etc.

i) The coarse aggregate shall be worked back from the forms so as to bring a full surface of

mortar against the form without the formation of excessive surface voids.

J) The compaction shall be such that all air or stone pockets which may cause honey

combing, pitting or places of weakness are eliminated.

Page 65: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

65

09 - CUBE TESTS :

a) The contractor shall ensure that the crushing of the concrete when tested within twenty-

eight days after mixing in accordance with IS : 156-1959 shall not be less than that

specified in the drawings.

b) The crushing strength of the concrete used in the works shall be determined by means of

works cube tests which shall be taken from samples as before specified and tested in

accordance with the procedure laid down in IS :516 and complete records relating to the

samples and test cubes shall be made by the contractor in accordance with this

specification. A slump test shall be carried out on each sample. The works test cubes

shall be of 150 mm std. size and shall be made in batches of four from each selected

concrete sample. Two cubes from each set of four shall be tested at seven days and two at

twenty-eight days. Each cube shall be marked with the date of casting and a reference

number from which its position of origin in the works can be clearly identified.

c) The crushing strength of work cubes tested at seven days after mixing shall be not less

than two-thirds of the required crushing strength of the concrete at twenty-eight days

shall however be accepted as true works cube strengths at twenty -eight days. The

crushing strength of the works test cubes at 28 days shall be not less than the specified

minimum crushing strength of the corresponding grade of concrete. If the results of tests

show crushing strength less than those specified all concrete work may be stopped by the

consultant. The contractor may be required to cut out and re-execute or otherwise rectify

to the satisfaction of engineer-in-charge at his own expenses any work failing to comply

with this specification.

d) Concreting shall not proceed until the engineer-in-charge is satisfied that all necessary

remedial measures have been taken to ensure that the specified strength of the concrete

will be consistently attained. All such remedial measures shall be at the contractors

expenses.

THE CONTRACTOR SHALL : a) In addition to testing of concrete cubes at the site Laboratory set up by the Contractor, he

shall at his own expenses supply concrete for test specimen, provide cubes and cylinders,

labours and materials required in preparing the test specimens for testing at external

Laboratory chosen by Owner.

b) He shall also pay for all costs and charges involved in dispatching the test specimens to

the said external testing laboratory.

c) He shall pay for all fees charged by the external Testing Laboratory for testing and

issuing of certificates.

Page 66: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

66

STANDARD SPECIFICATIONS

PART IV - PREAMBLES

SECTION A : EARTH WORK

Rates for respective items shall include for these specifications

1. Existing ground levels shall be taken jointly and recorded before commencing the excavation

work. Depth of excavation in cutting shall be computed from these spot levels. For pits at least

five spot levels shall be recorded, four at the corners and one at the centre of the pit. Average of

these five readings shall be taken as the average ground level for the pit. For trenches, spot

levels spaced at every 1.500 metre centres along the centre line of the trench shall be taken as

the average ground level for the sectional lengths of the trenches.

2. Bottom width for excavation shall be measured as given in the foundation drawings and details

showing the width of bedding concrete only and hence side clearance if any will not be

measured separately. The contractor shall cover for this in his rates.

3. Battering of benching of excavation sides if required to be done shall not be measured

separately, that is the sides of excavation shall be treated as vertical for computing the quantity o

excavation. Contractor should cover for this in his rates

4. The following shall not be measured and the allowance for the same shall be made by the

Contractor

I Setting out of work and site clearance removal of shrubs etc.

Ii Excavation for insertion of planking and strutting.

Iii Removal of slips or falls in excavation due to any reason

whatsoever.

Iv Forming steps in the sides of excavation and their removal.

v Bailing or pumping out water in excavation from rains, springs,

underground water sources, underground pipe lines, etc., for keeping it dry

during excavation and construction upto ground level.

Vi Refilling the excavated materials in all sides of foundations and filling on

top of foundations upto required level including consolidation by ramming

and watering.

Page 67: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

67

Vii Carting away of excavated materials if ordered to be removed away from

site (excavated materials will be given free of cost to the Contractor for

this purpose).

Viii Stacking of excavated materials within site as directed.

5 Where individual boulders of any kind of rock are found in the soil and which can

be separated from the parent matrix by crow bars without breaking the boulders

such boulders shall be removed from the excavation and stacked separately on site

within a lead of 1.50 feet as directed. Removal of such individual boulders from

the excavation shall not be paid for separately and therefore will be considered

only as the excavation in "any kind of soil" and not as the excavation in any kind

of rock.

6 a) Where ordinary rock and hard rock are mixed, the two kinds of rocks shall

be stacked separately on even and level ground and measured in stacks. The net

measurement of the two kinds of rocks shall be arrived at by applying deduction

at 40% (forty percent) for voids. If the total of the net measurement of two kinds

of rock exceeds the measurement of mixture assessed by means of cross sectional

measurement then the volume of mixture shall be apportioned in the proportion of

the net measurements of two kinds of rock.

b) Where soil, ordinary rock and hard rock are mixed the ordinary rock and

hard rock shall be stacked separately and measured in stacks and their net

quantities determined as mentioned in 6 (a) above.

The measurement of the soil shall then be arrived at by deducting the net

measurement of rock from the total measurement of cutting.

7 Deductions in the case of fills :

Deductions in the case of fills shall be made as follows :

a) Ten percent deductions shall be made from actual measured cubic contents in all

cases of consolidated fills to arrive at net cubic measurements, except where the

consolidations is done by heavy mechanical machinery, in which case the

deduction shall be five percent.

b) No deduction shall be made in the case of consolidated fills in confined situations

like plinth filling below floors.

8 All excavated materials will be the property of the Owner.

Page 68: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

68

9 If the excavated materials, rock, etc., obtained from the excavation are allowed to

be used in the work, the Contractor shall pay to the Owner at the market rate the

cost of such materials, unless otherwise mentioned "Free of Cost to the

Contractor" in particular items.

10 All kinds of fillings and re-fillings in the sides of foundations, in pits, trenches,

plinth etc., and the fillings shall be thoroughly consolidated layer by layer (not

exceeding 200m thick) ramming with heavy cast iron rammers with optimum

moisture in soil and watering upto saturation.

11 Work of pre-construction anti-termite treatment should be carried out through

renowned agency and member of Pest Control Association with guarantee period

of 10 years.

The name of the Pest Control agency proposed for pre-constructional anti-termite

treatment, should be mentioned.

12 Particular attention of the Contractor is drawn to the thorough consolidation in

layers required in back filling in sides and top of foundations within the building

area, as the heights of fillings further required on top of low lying areas in the plot

range upto 3.0 m underneath the plinth area of the building. Item (9) of Section

'K': "Work Outside the Building " deal with the filling and consolidation in the

plot area underneath the plinth as well as in areas outside the plinth.

Page 69: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

69

SECTION "B" : R.C.C. WORK

(Concrete plain and reinforced, Form work, Reinforcement, Structural Steel Work)

PREAMBLES : Rates for respective items shall include for these additional specifications.

1 1.01 Specifications to be followed for items of concrete work, Reinforced

cement concrete work, prestressed concrete work shall be the specifications for

these work as enclosed with the tender. These specifications and specific

provisions in the wordings of the items in the schedule of quantities shall be

precedence over relevant ISI specifications.

1.02 However relevant I.S.I. specifications shall be followed if not covered by the

specifications stated in para 1.01 above.

2 All RCC work shall be executed in strict accordance with the instructions, drawings and

details forwarded for the work by the Architect.

3 The rate of RCC items shall include for all labour, material, binding wire 18 Gauge

equipment gangways required, tools and all the operations, involved but shall exclude

Form Work and reinforcement, which shall be measured and paid for separately.

4 Rates quoted for reinforcement bars shall include for providing cutting and bending of

reinforcement bars in any size and shape and placing in any position as per the detailed

drawings including providing precast cement concrete cover blocks of required thickness

for keeping reinforcement bars in position. Cutting and bar bending schedule should be

submitted by the Contractor for reinforcement steel. Binding wire for tying of

reinforcement, shall be 18 gauge and shall be provided by the Contractor, but will not be

measured and hence will not be paid. The Contractor should cover for this in his overall

rate for the reinforcement bars. Spacer bars, pins, chairs, etc., required for keeping the

reinforcement bars in position shall be provided by the Contractor and the same will be

measured for payment.

5 Rates quoted for Form Work shall include shuttering, centering, propping, bracing,

tightening with nuts and bolts staging, providing camber etc. Form Work shall be

measured for the area actually in contact with in-sit concrete laid. Lapping of form work

with previously laid and set concrete will not be measured and will not be paid for Form

Work design should be submitted by the Contractor for approval of the R.C.C.

Consultants. Shuttering made from new plywood will be allowed for use upto nine

repetitions only.

6. Items given in the schedule of this section applies to all positions and in all floors and at

all heights-lift or materials will not form any criteria for extra payment.

Page 70: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

70

7. Minimum cement content per cubic meter of cement concrete has been specified in each

item of cement work. However, if extra cement is required to be used so as to obtain the

minimum strength specified for the grade of cement concrete the Contractor will not be

paid for extra cement used.

Page 71: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

71

SECTION 8

SAFETY SPECIFICATION

INTRODUCTION

This specification provides amplification of certain aspects of safety procedures and

requirements covered within the General conditions of contract.

1 SCOPE

The requirements of this specifications shall apply equally to Contractors and Sub-Contractors.

Where the word "Contractor" is used this shall be taken to include "Sub-Contractors".

Contractors shall be responsible for ensuring that their Sub-Contractors are notified of and

comply with these requirements.

2 REQUIREMENTS

Throughout the course of the Contract the Contractor shall assure and demonstrate to the

Engineers Representative on site that he has suitable and sufficient knowledge, experience,

procedures and resources to carry out the works safely. The contractor shall demonstrate that his

employees are suitably trained in the above procedures and are aware of potential hazards.

2.1 Personal Protective Equipment

The Contractor shall ensure that the following items of personal protective equipment are

available to all his employees :

a Safety helmets (to BS 5240)

b Safety footwear (to BS 1870) (+over protection where required).

c Overalls (Either disposable or with suitable laundry arrangements)

d Light eye protection (to BS 2092 "General Purpose")

e Safety goggles (to BS 2092 "Grade 1")

f Hearing Protectors (to BS 6344)

g Appropriate Protective Gloves.

h Safety Belts

The Contractor shall ensure that safety helmets, safety footwear, Safety Belts overalls and light

eye protection are worn by all his employees at all times whilst on the site.

Deviation from the above requirements shall only be permitted with the prior written agreement

of the Construction site Manager responsible for the site in question.

Page 72: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

72

The Contractor shall further ensure that safety goggles, hearing protectors and protective

gloves are worn in areas where such protection is a statutory requirement, a plant

requirement or where it is judged that the risk of injury during the execution of a

construction task would be reduced.

The Contractor shall list in A.1 of this specification any other personal protective

clothing that he shall provide which is a trade requirement and any specialized personal

protective equipment he deems necessary to execute the work safely.

3 Control of Hazards to Others

Where the work activities of the Contractor produce risk to others, the Contractors shall

take all reasonably practicable, steps to remove the hazard. Where this is not possible, the

Contractor shall list in A.2 of this specification those arrangements he shall make to

minimize the risks arising from such hazard, for example, erection of protective screens

and barriers or location of the area.

4 Contract Safety Plan

The Contractor shall provide in A.3 of this specification a safety plan for the Contract

which is based on his Company’s safety policy. If the contractor is registered with the

construction Groups Safety Award Scheme, his safety plan may be related to his safety

action plan.

5 Cleanliness of the Site and contractor establishment.

Knowing the work content and the consequent debris produced, the contractor shall

unless otherwise instructed by the Engineers Representative on site :

a) Establish, at strategic points, suitable rubbish bags and/or bins, ensure

their correct use and arrange for the removal and disposal of the same.

b) State the frequency and method of site and Contractors establishment

cleaning in A.4 of this specification.

c) Provide for the safe stacking and storage of materials, fuel and consumables.

Page 73: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

73

SECTION 9

SAFETY INSTRUCTION

A. Contractor's Barricades :

Contractor shall erect and maintain barricades required in connection with his operation

to guard or protect.

(a) Excavations and blasting work (if permitted by the Owner) (necessary permission

for

blasting to be taken by contractor from local authorities)

(b) Hoisting areas.

(c) Areas adjudged hazardous by Contractor or Owner's inspectors

(d) Owner's existing property subject to damage by Contractor's operations.

(e) Road unloading spots if provided.

Contractor's employees and those of its sub-contractors shall become acquainted with

barricading practice and shall respect the provisions thereof.

Barricades and hazardous areas adjacent to, but not located, in normal routes of travel

shall be marked by red flasher lanterns at nights.

B. Excavation and Trenching :

All trenches 1.2 metres or more in depth, shall at all times be supplied with at least one ladder

for each 50 metres length or fraction thereof. Ladder shall be extended from bottom of the

trench to atleast 1 metre above the surface of the ground. The sides of the trenches which are 1.5

metres in depth shall be stepped back to give suitable slope or securely held by timber bracing,

so as to avoid the danger of sides to collapse. The excavated materials shall not be placed within

1.5 metres of the edge of the trench or half of the trench width whichever is more. Cutting shall

be done from top to bottom. Under no circumstances undermining or under cutting shall be

done.

C. Demolition : Before any demolition work is commenced and also during the progress of the work

(a) All roads and open areas adjacent to the work site shall either be closed or

suitably protected.

(b) No electric cable or apparatus which is liable to be a source of danger shall

remain electrically charged.

(c) All practical steps shall be taken to prevent danger to persons employed from

risks of fire or explosion or flooding. No floor, roof or other part of the building

shall be so overloaded with debris or materials as to render it unsafe.

Page 74: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

74

D. All necessary personal safety equipment as considered adequate by the Architect, should

be kept available for the use of persons employed on the site and maintained in condition

suitable for immediate use, and the Contractor shall take adequate steps to ensure proper

use of equipment by those concerned.

(a) Workers employed on mixing asphaltic material, cement and lime mortars shall

be provided with protective footwear and protective gloves.

(b) Those engaged in white washing and mixing or stacking of cement bags or any

materials which are injurious to the eyes shall be provided with protective

goggles.

(c) Those engaged in welding and cutting works shall be provided with protective

face and eye-shields, hand gloves etc.

(d) Stone breakers shall be provided with protective goggles and protective clothing

and seated at sufficiently safe intervals.

(e) When workers are employed in sewers and manholes, which are in use, the

contractor shall ensure that the manhole covers are opened and are ventilated at

least for an hour before the workers are allowed to get into the manholes, and the

manholes so opened shall be cordoned off with suitable railing and provided with

warning signals or board to prevent accident to the public.

(f) The Contractor shall not employ men below the age of 18 years and women on

the work of painting with products containing lead in any form. Wherever men

above the age of 18 years are employed on the work of lead painting, the

following precautions should be taken :-

(1) No paint containing lead or lead product shall be used except in the form of paste

or readymade paint.

(2) Suitable face masks should be supplied for use by the workers when paint is

applied in the form of spray or a surface having lead paint dry rubbed and

scrapped.

(3) Overalls shall be supplied by the Contractor to the workmen and adequate

facilities shall be provided to enable the working painters to wash them during

and on cessation of work.

E. Use of hoisting machines and tackles including their attachments, anchorage and

supports shall conform to the following standard or conditions :-

(a) These shall be of good mechanical construction, sound materials and adequate

strength and free from patent defect and shall be kept in good working order.

Page 75: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

75

(b) Every rope used in hoisting or lowering materials or as means of suspension shall

be of durable quality and adequate strength and free from patent defects.

(c) Every crane driver or hoisting appliance operator shall be properly qualified and

no person under the age of 21 years should be in charge of any hoisting machine

including scaffolding winch or give signals to the operator.

(d) In case of every hoisting machine and of every chain ring hook, shackle swivel

and pulley block used in hoisting or lowering or as means of suspension, the safe

working load shall be ascertained by adequate means. Every hoisting machine and

all gears referred to above shall be plainly marked with the safe working load of

the conditions under which it is applicable which shall be clearly indicated. No

part of any machine or any gear referred to above in this paragraph shall be

loaded beyond the safe working load except for the purpose of testing.

F. In case of departmental machine, the safe working load shall be notified by the

Architect. As regards Contractor's machines, the Contractor shall notify the safe

working load of the machine to the Architect when ever he brings any machinery

to site of work and get it verified by the Engineer concerned.

G. Motors, gearing transmission, electric wiring, electrical gadgets and other

dangerous parts of hoisting appliances should be provided with efficient safety-

guards. Hoisting appliances should be provided with such means as to reduce to

the minimum the accidental descent of the load, adequate precautions should be

taken to reduce to the minimum the risk of any part or any part of a suspended

load becoming accidentally displaced. When workers are employed on electrical

installations which are already energized, insulating mats, wearing apparel, such

as gloves, sleeves, and boots as may be necessary should be provided. The

workers shall not wear any rings, watches and carry keys or other materials which

are good conductors of electricity.

H. All scaffolds, ladders and other safety devices mentioned or described herein

shall be maintained in safe conditions and no scaffold, ladder or equipment shall

be altered or removed while it is in use. Adequate washing facilities should be

provided at or near places of work.

I. These safety provisions should be brought to the notice of all concerned by

displaying on notice boards at a prominent places at the work site. The person

responsible for compliance of the safety code shall be named therein by the

Contractor.

J. To ensure effective enforcement of the rules and regulations relating to the safety

precautions. the arrangements made by the Contractor shall be open to inspection

by the Owner or Architect or their representatives.

Page 76: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

76

K. There shall be maintained in a readily accessible place first aid appliance

including adequate supply of sterilized dressings and cotton wool.

L. An injured person shall be first taken to the nearest Medical Centre without loss

of time and in cases where the injury necessities hospitalization, patient should be

taken to public hospital on advice from Medical Officer.

M. Contractor shall provide safety Belts to all the workers, craftsmen, and Engineers

who are engaged in working on any external face or openings above ground floor

level. Similarly, helmets shall be provided to workers in areas where head injuries

may be expected.

N. Notwithstanding the above clauses there is nothing in these to exempt the

Contractor from the operations of any other Act or rules in force in the Republic

of India. The works throughout including any temporary works shall be carried

out in such a manner as not to interfere in any way whatsoever with the traffic on

any roads or footpaths at the site or in the vicinity thereto or any existing works

whether the property of the Owner or of a third party.

O. Government Regulations

(1) The contractor shall comply and ensure strict compliance by his employees and

subcontractor's employees, if approved, of all applicable Central and State laws

and regulations and undertake to indemnify The Institute Of Cost Accountants Of

India from and against all levies, damages, penalties and payments whatsoever as

may be imposed by reasons of any breach or violation of any law, rules.

(2) Before starting any job, please ensure that the Contractors fulfill all statutory

requirements in consultation with our Personnel Department.

(3) Contractor proposing to employ 20 or more employees shall obtain Registration

Number given by the Deputy Commissioner as a licensed contractor and submit a

copy before starting the job.

(4) All the workmen employed by the contractor, before entering the site, must be

covered under the provisions of Employees State Insurance Act, Provident Fund

Act. All entries to the site of persons/materials shall be through a system of gate

passes.

(5) The contractor shall ensure to keep and maintain all the statutory registers,

records as required under provisions of Contract Labour (R&A) Act 1970,

Minimum Wages Act and the rule made there under, Employees Provident Fund

Page 77: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

77

Act, 1952 and keep the same available at the work site for inspection by

Company's representatives and Government authorities.

(6) The contractor, will ensure that necessary contributions towards PF are deposited

with the authorities concerned. Also all the records as per provisions of ESIS Act

are maintained.

(7) The Contractor shall be solely responsible for safety of workmen and to provide

them required personal protective equipments (safety shoes, helmets, safety belt

etc.) and shall ensure to have all his workmen properly covered under the

insurance policy for liability under Workmen Compensation Act. The Institute Of

Cost Accountants Of India will not be liable for any injury or loss of life of the

contractor's personnel.

(8) The contractor shall strictly follow the rules relating to engaging female workers

at site.

P. Safety Training of Contractor's Supervisor/PPE

Before starting the job, every supervisor of the Contractor shall undergo a safety

training conducted by the Safety Officer. The availability and use of personal protective

equipment (safety shoes and helmet etc.) will be clearly emphasized in this training.

Q. Work Clearance Certificate

(1) No job will be started without a proper clearance certificate, issued by competent

authorities and accepted by construction engineer or his nominee.

(2) A separate clearance certificate will be taken for digging/ excavation jobs, duly

signed by electrical supervisor.

(3) A separate clearance certificate will be taken for hot/ welding jobs in each area.

(4) For working at height (3 M and above), the clearance certificate will have to be

authorized by ENGINEER-IN-CHARGE before starting the job.

(5) All the clearance certificates shall be renewed next day morning on revalidation

sheet and kept available in construction office.

R. Inspection of Electrical Tools & Lifting Tackles

All the electrical tools, welding machines and cable etc. shall be offered to. for checking

before any use at site. All the lifting tackles and tools shall be brought with certificates

and offered to ENGINEER-IN-CHARGE representative for checking before any use at

site.

Page 78: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

78

The responsibility to ensure above shall lie with Contractor.

In addition to the above, the Contractor shall abide by the Safety Code provision as per

Indian Standard Safety Code framed from time to time.

Contractor Architect

Page 79: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

79

SECTION 10

ANTI-TERMITE TREATMENT

1. CHEMICALS: The chemicals used for the soil treatment shall be any one or a combination of the

following the concentration shown against each in aquous emulsion:

Chemicals (EC's) Concentration

Chlorpyriphos 1.0% (by weight)

2. TREATMENT OF COLUMN PITS, WALL TRENCHES AND BASEMENT

EXCAVATIONS: The bottom surface and sides (upto a height of 30 cm. from the bottom) of the excavation

made for column pits, trenches and basements shall be treated with the chemical

emulsion mentioned above at 5 litres per Sq.mtrs of surface area.

3. TREATEMENT TO BACKFILL EARTH

After the column foundations, wall foundations and retaining walls of the basement come

up, the back filling immediate contact with the foundation structure shall be treated with

the chemical emulsion at the rate of 7.5 litre/Sqm of the vertical surface of the

substructure of each side. The earth is usually returned in layers and treatment shall be

carried our in similar stages. The chemical emulsion shall be directed towards the

concrete or masonry surface of the columns and walls so that the earth in contact with

these surfaces is well treated with chemicals.

4. TREATMENT TO R.C.C. FRAMED STRUCTURES: The treatment in 2 and 3 above applies essentially to masonry foundations where there

are voids through which termites an seek entry in to the superstructure. Hence the

foundations require to be completely enveloped by a chemical barrier. In the case of

R.C.C. framed structures with columns and plinth beams and R.C.C. basements the

concrete mix is rich and dense (being 1:2:4 or M. 150 or richer), the termites are unable

to penetrate it. It is therefore unnecessary to start the treatment from the bottom of

excavation the treatment shall start at a dept of 50 cm .below ground level, except when

ground level is raised or lowered by filling or cutting after the foundations have been cast

in such cases the dept of 50 cm shall be determined from the new soil level resulting

from filling or cutting mentioned above and soil in immediate contact with the vertical

surface of RCC foundations. From this depth, the backfill around the columns, beams

and RCC basement walls shall be treated at the rate 7.5 litres Sq.mtrs. The other details

of the treatment shall be as laid down in 3 above.

5. TREATMENT TO SOIL ALONG EXTERNAL PERIMETER OF BUILDING : After the building is complete, the earth along the external perimeter of the building

should be rodded at intervals of 15 cm and to a depth of 30 cm. The rods should be

moved backward and forward, parallel to the wall to break up the earth and emulsion

Page 80: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

80

poured along the wall at the rate of 7.5 litres per sq. m. of vertical surfaces. After the

treatment, the earth should be tamped back into place. Should the earth outside the

building be graded on completion of building, this treatment should be carried out on the

completion of such grading. In the event of filling more than 30 cm the external

perimeter shall extended to the full depth of filling up the ground level so as to ensure

continuity of the chemical barrier.

6 TREATMENT OF SOIL UNDER APRON ALONG EXTERNAL PERIMETER

OF BUILDING Top surface of the consolidated earth over which the aprom is to laid shall be treated with

chemical emulsion at the rate of 5 litres per Sq.mtrs. of the vertical surface before the

aporn laid. If consolidated earth does not allow emulsion to seep through holes upto 50 to

75 mm deep at 150 mm centres both ways may be made with 12 mm dia mild steel rod

on the surface to facilitate saturation of the soil with the chemical emulsion.

7 TREATMENT OF SOIL SURROUNDING PIPES,WASTES AND CONDUITS :

When pipes, wastes and conduits enter the soil inside the area of the foundations, the soil

surrounding the point of entry must be loosened around each such pipe, waste or conduits

for a distance of 15 cm. and upto a depth of 7.5 cm. before treatment is commenced.

When they enter the soil external to the foundations, they shall be similarly treated,

unless they stand clear of the walls of the building by about 7.5 cm. for a distance of over

30 cm.

11. TREATMENT FOR EXPANSION JOINTS

Expansion joints at ground floor level are one of the biggest hazards for termite

infestation. The soil beneath these joints should receive special attention when the

treatment under 5 is carried out. This treatment should be supplemented by treating the

expansion joints after the subgrade has been laid, at the rate of 2 litres per linear metre.

12. SPRAYING EQUIPMENT A Pressure pump shall be used to carry out spraying operations to facilitate proper

penetration of chemical into the earth.

13. The above specifications are in line the I.S. Code of practice for Antitermite Measures in

Building, IS 6313 (Part-II)-1981 (First Revision)

Page 81: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

81

SECTION 11

SPECIFICATION FOR PILING WORK (Bored Precast RCC Piles) (R1)

(I) MATERIALS:

1. Materials shall be of the best approved quality obtainable and they shall comply with the

respective Indian Standard Specifications which are inforce during construction.

2. Samples of all materials shall be got approved before placing order and the approved

sample shall be deposited with the Site Incharge.

3. If directed, materials shall be tested in any approved testing laboratory and the test

Certificate in original shall be submitted to the Structural Engineer and the entire charges

for repeated tests, if ordered, will be borne by the Contractor.

4. It shall be obligatory for the Contractor to furnish certificate, if demanded by the Site

Incharge, from the Manufacturer or the material supplier that the work has been carried

out by using their material and as per their recommendations.

5. Unless otherwise shown on the Drawings or mentioned in the Schedule of Quantities or

Special Specifications, the quality of materials, workmanship, etc. shall be specified

hereunder.

6. All equipment and facilities for carrying field tests on materials shall be provided by the

Contractor without any extra cost.

A) CEMENT:

Cement shall comply in every respect with the requirements in the latest publication of IS:

269 and, unless otherwise specified, Portland blended cement shall be used.

The weight of ordinary Portland cement shall be taken as 1440 kg per Cu.m Cement shall be

measured by weight and in whole bags, and each undisturbed and sealed 50 kg bag being

considered equivalent to 35 liters in volume. Care should be taken to see each bag contains

full quantity of cement. When part bag is required, cement shall be taken by weight or

measured in measuring boxes.

No other make of cement, but that approved by the Structural Engineer, will be allowed on

works and the source of supply shall not be changed without approval of the Structural

Engineer in writing.

Test Certificate to show that cement is fully complying the specifications shall be submitted to

the Structural Engineer and not withstanding this, the Structural Engineer may at his

Page 82: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

82

discretion, order that the cement brought on site and which he may consider damaged or of

doubtful quality for any reason whatsoever, shall be retested in an approved testing laboratory

and fresh certificate of its soundness shall be produced. Cement ordered for re-testing shall not

be used for any work, pending result of retest.

Cement shall be stored in waterproof shed with raised wooden flooring to prevent

deterioration by dampness or intrusion of foreign matter. It shall be stored in such a way as

allows removal and use of cement in chronological order of receipt i.e. first received being

first used. Cement deteriorated and / or clodded shall not be used on work but shall be

removed at once from the site. However allowing use of warehouse set cement shall be

determined by the Structural Engineer.

Weekly record of cement received and consumed shall be maintained by the contractor in an

approved form and submitted to the Structural Engineer.

B) FINE AGGREGATE:

Sand shall conform to IS 383 and relevant portion of IS 515. It shall pass through a IS sieve

4.75 mm (3/16 B.S.) test sieve, leaving a residue of not more than 5%. It shall be from natural

source or crushed stone screenings (if allowed), chemically inert, clean sharp, hard, durable,

well graded and free from impurities like dust, clay , shale, large pebbles, salt, organic matter,

loam or other deleterious substances. The sum of % of such deleterious materials shall be

within acceptable limits. Sand shall not contain any trace of salt and it shall be tested and

sand containing any trace of salt shall be rejected.

The fine aggregate for concrete shall be graded within limits as specified in IS 383 and the

fineness modules may range between 2.60 to 3.20.

The fine aggregate shall be stacked carefully on a clean hard dry surface so that it will not get

mixed up with deleterious foreign materials. If a such a surface is not available, a platform of

planks or corrugated iron sheets or brick floor or a thin layer of lean concrete shall be

prepared.

C) COARSE AGGREGATE: Coarse aggregate shall consist of broken stone 95% of, which shall be retained on 4.75 mm IS

test sieve. It shall be obtained from crushing Granite, Quartzite, Trap, Basalt or similar

approved stone quarry and shall conform to IS: 383 and IS :515 Coarse aggregate shall be

chemically inert when mixed with cement and shall be cubical in shape and free from soft,

tribal, thin porous, laminated or flaky pieces. It shall be free from dust and any other foreign

matter.

Gravel / Shingle of desired grading may be permitted as a substitute in part or full in plain

cement concrete if the Structural Engineer is otherwise satisfied about the quality of the

aggregate. For all RCC works the size of coarse aggregate shall be 20 mm and down gauge.

Page 83: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

83

D) REINFORCEMENT:

Reinforcement shall be of or deformed bars conforming to IS: 1786 and IS: 1139 All finished

bars shall be free from cracks, surface flaws, laminations, jagged and important edges.

E) WATER:

Water for mixing Cement/Lime/ Surkhi mortar or concrete shall not be salty or blackish and

shall be clean, reasonably clear and free from objectionable quantities of silt and traces of oil,

acid and injurious alkali, salt , organic matter and other deleterious material which will either

weaken the mortar or concrete. Water shall be obtained from sources approved by the

Structural Engineer. Potable water is generally considered satisfactory for mixing and curing

concrete, mortar, masonry etc. Where water other than main source is used, this shall be

tested in an approved testing laboratory to establish its suitability. All charges connected

therewith shall be borne by the Contractor.

(II) CONCRETE PLAIN OR REINFORCED:

The materials, workmanship, inspection and testing of plain and reinforced concrete shall be

in accordance with IS:456 – 2000 and additionally as described in following sections and as

directed by the Structural Engineer from time to time.

(A) MIX, PROPORTION, PRODUCTION, CONTROL, TRANSPORT, PLACING

AND CURING OF CONCREATE:

The mix proportions shall be selected to ensure that the workability of fresh concrete is

suitable for the conditions of handling and placing, so that after compaction, it surrounds all

reinforcement and completely fill the formwork and when the concrete is hardened, it shall

have reached the required strength, durability and surface finish.

The determination of proportions of cement aggregates and water shall be made either with

design mix concrete or nominal mix concrete which shall be approved be approved by the

Structural Engineer. Unless otherwise specified, the concrete shall be of M-30 grade and shall

have minimum cement content as per HIL specs. Even if the strength of concrete is found to

be more during the execution of work, minimum cement content criteria shall apply. The

water cement ratio if required to be changed for the workability requirement, the same shall

be got approved by the Structural Engineer. It shall be advisable to keep the same source of

fine and coarse aggregates with constant grading of materials to keep proper control on mix

proportioning.

All the concrete shall be machine mixed and mechanically vibrated. The water cement ratio,

aggregate cement ratio, fine to coarse aggregate ratio shall be maintained as per instructions

from the Structural Engineer throughout the process of concreting.

Page 84: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

84

The machine mixing shall be carried out for 2 minutes so as to give uniform distribution of

materials and mass in uniform in color and consistency. The fresh concrete shall be placed

before 30 minutes from mixing of the same. No hand mixing of the concrete shall be

permitted. All concrete shall be placed from maximum height of 1.2m to avoid segregation.

The honey-combed concrete shall be completely removed and replaced at the cost of the

Tenderer. The construction joints during construction shall be treated as per IS: 456-2000.

The concrete shall be cured for the period specified in IS 456.

B) SAMPLING & TESTING OF CONCRETE:

The Tenderer at his own cost shall bring on site a cub crushing strength machine, nine

number of 150” x 150” cube moulds, set of sieves, and weighing machine to check the

grading of fine and coarse aggregates, Samples from the fresh concrete being used shall be

taken and cubes shall be casted and tested in the following manner;

i) 3 cubes after 7 days

ii) 3 cubes after 28 days

In all cases the result of 28 days compressive strength specified in IS: 456-2000 shall alone

be the criteria for acceptance or rejection of the concrete. Frequency of the sampling test

strength and acceptance criteria shall be as per IS: 456-2000.

No extra payment shall be made for sampling, testing and keeping records of the same as

directed by the Structural Engineer.

D. REINFORCEMENT DETAILING & ASSEMBLY:

All the reinforcement shall be placed and maintained in position as per the structural drawing

with the help of cover blocks of specified thickness. The detailing shall be carried out strictly

as per schedules and details shown on Structural Drawings or as instructed by Structural

Engineer. No lap shall be provided without approval of the Structural Engineer. The top

holding bars shall be continuous over continuous supports. Chairs shall be provided in

sufficient numbers to hold top bars in position. No concrete shall be placed into formwork

unless the entire assembly of reinforcement detailing is completed and checked by the

Structural Engineer.

E. PRECAST BORED RCC PILES

i) Standard- The requirement of IS-2911 (part- I) shall generally apply in respect of the

piles.

ii) Plant – The tenderer shall furnish for the approval of the Structural Engineer the

details of plants and equipment which he intends to use for installation of the piles.

iii) Boring – The boring may be done by any of the approved methods found suitable for

the strata conditions prevalent on the site. The Structural Engineer shall decide the

depth at which boring should stop and the extent to which casings or Bentonite slurry

Page 85: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

85

should be used. Distributed samples shall be collected and preserved from 5% of the

pile bores for classification as directed by the Structural Engineer.

iv) Driving – The tenderer shall get approved from the Structural Engineer the method of

driving tubes, types and weight of hammer, type of cushioning etc. No two piles shall

be driven closer than 2.5 times dia. of piles and also within 48 hours of placing of

adjacent pile. Adequate measures shall be taken to overcome detrimental effect of

ground have no piles.

v) Concreting – Concrete shall be of M-30 grade as per BOQ with minimum cement

content as per HIL. Concrete shall conform to IS 456-2000 as described in

‘CONCRETE’ part hereinbefore. The slump of concrete shall be 60 mm

Special plasticizing admixtures may be added to improve the slump without

Extra cost if approved by the Structural Engineer.

vi) Reinforcement : The cages of reinforcement shall be well wired or spot welded

to withstand handling without damage. Proper care shall be taken to maintain

Uniform specified cover. (75 mm unless otherwise shown on drawings)

And alignment of the reinforcement.

vii) Tolerances : Precautions shall be taken to maintain positional accuracy and

Strict verticality of the permissible tolerance as under:-

a) Position deviation – 75 mm at cut-off level

b) Vertically - 2 degrees

If the above tolerances are exceeded, either modification may be made in design or actual

rectification carried out, or the piles shall be entirely rejected at the discretion of the Structural

Engineer

viii) Pile Heads: The top of the piles shall be brought up sufficiently above the finishing

level to permit all laitance and weak concrete to be removed. The reinforcement in the pile

shall be sufficiently exposed to permit specified lapping in pile cap.

iv) Pile Records: The Contractor shall submit to the Engineer for his information and use

four copies of piling record for each pile. Such record shall include details as follows –

A) Structure ------------------------------- Ref. Drg.

No--------------- Pile Designation ---------------------------------

B) Pile ----------

i) Dia. Nominal------------------------------

ii) RL of ground ----------------------------------

iii) RL at bottom of pile------------------------

iv) RL at cut-off-----------------------------------

v) Grade of Concrete-----------------------

vi) Concrete volume--------------------------

vii) Reinforcement-----------------------------

C) Operation Start Complete

Page 86: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

86

i) Boring ----------------------at ------------------------------at----------------

ii) Chiseling-----------------at--------------------------------at-------------

(Indicate weight of chisel ---------------------------------------)

D) Pile Records –

Final set ---------------------------------- (for driven piles)

Wt. Of hammer ------------------------Drop of hammer -----------------

E) Any special feature ------------------------------ obstructions

(V) LOAD TEST ON PILES:

The contractor shall submit the details of his proposal for carrying out the load test for approval

of the Structural Engineer.

(a) Non – Destructive Test : (NDT) on piles

NDT on piles may be carried out as follows:

a) Pile integrity Test - 50% of Total piles

b) Pile dynamic Test - 2% of Total piles

These Tests to be carried as per the guidance of Structural Engineer

(b) Arrangement for Test:

i) Pile to be tested shall have been cast at least 28 days before the testing unless

otherwise directed by the Structural Engineer.

ii) All the arrangement for conducting the load test including surface preparation etc.

Shall be arranged for by the Contractor at his own cost. The equipment and

instruments shall be got approved by the Structural Engineer prior to taking up the

test in hand.

iii) Load tests shall be made under the supervision of the Structural Engineer.

(c) If the tested pile does not satisfy the specified requirements of a successful and if the

failure is attributable to defective workmanship or negligence on the part of the Contractor, all

costs of the load test, the cost of providing and Installing additional piles, cost of additional or

enlarged pile caps and other work necessitated because of the defective pile shall be at the cost

of the Contractor.

Page 87: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

87

SECTION 12

Annexure I

Contractor to Submit Along with Tender :-

1. List of similar jobs executed in the last 2 years.

2. List of Manpower Proposed to be deployed for the job.

3. List of Equipment/Machinery proposed to be deployed for the job

4. I.T Clearance certificate for the last 3 years.

5. Partnership Deed.

6. Power -of - Attorney, in favour of person signing the Bid/Contract

7. Business Turnover Details of organization for last 2 years.

8. List of Senior-Permanent Staff, in the employment of the organization.

9. Solvency Certificate from your bankers.

10. Current Order-Booking and Order-backing.

Page 88: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

88

Annexure II

Contractor to Submit the Following Documents After Receipt of Letter of -Intent, within 15

days.

1. Proposed construction Schedule (progress chart and CPM net work) for timely

completion for acceptance by Architect.

2. Lay-out showing places for stacking construction materials, Location of cement-

Godown, Stores, Site-Office, Labour-Hutments, Temporary water-tanks, laboratory,

owners representatives office etc, so as not to foul with future permanent construction.

3. Manpower planning, month to month, of important, skilled category.

4. Site organization chart with Bio-data of site-in-charge.

5. A phased indication of requirement by you, of Owners' materials, if and as applicable,

to be issued to you on free/ chargeable basis.

6. A rough Schedule, indicating the peak Months.

7. Following Insurance-Policies, to adequately cover, as advised by Architect.

(a) Men, Machineries, equipment of project

(b) Group Personal Accident Insurance

(c) Fire/Theft/All risk

(d) Third party

(e) Complete building in all stages of construction.

8 Planning of Excavation in phases for.

Page 89: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

89

Annexure III

Apart from other factors mentioned elsewhere in the Tender, RATES SHALL INCLUDE, the

following, unless specifically excluded from item-description,

1. All works at all height/depths, all floors and all leads within battery limit of project site.

2. Conducting tests of all construction materials, concrete, steel, aggregates, bricks etc.

3. Maintaining all records and preparing progress reports as advised.

4. Providing all necessary consumables, tools, tackles, machineries equipment, instruments,

as the job quantum/quality/urgency may demand.

5. Compliance of all local, regional, state and central laws of land, as applicable in

relation to place of work, of all authorities, having jurisdiction in the areas.

6. Compliance of standard safety-practices and fire-protection.

7. Premium for various insurance-policies.

8. Fetching water by tankers from approved sources, if situation so demands.

9. General house-keeping, cleanliness, hygienic work environment.

10. Construction of all enabling works(and dismantling after work completion and

removal of debris) including access road, cement godown, site office, labour colonies,

etc.

11 Employing only licensed workers for blasting, electrical, plumbing and similar other

works.

12. All taxes, levies, royalties, duties, octroi, etc. as may applicable during the tenure of

the Contract including sales tax.

13. Buying items from open market, for urgent works

14. Working in monsoons, Sundays, holidays, overt-time & extra shifts.

15. Barricading work areas for safety reasons and suitable displaying warning

notices/signals.

16 Setting-out of works and maintaining Bench-marks.

Page 90: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

90

17. Satisfactory accounting of Materials issued by Owner either as Free issue or

chargeable basis. Wastage allowable for cement = 5%. For steel 3%.

18. Making, providing Cover-blocks to match with main concrete-grade.

19. Supply & application of primer coats as specified by Manufactures/Architect as per

specification.

20. Maintaining line level, slope, plumb and dimensions of all works as per

Drawing/instructions.

21. Shifting away immediately from place to work, all rejected materials and ensure its non-

use in permanent works.

22. Guarantees/ Warranties

23. Supply and fixing sleeves/conduits etc. in position and grouting as directed.

24. Liosoning with the Authorities for getting municipal connection for water, drainage,

electricity.

25. All wastage-allowance, scrap allowance, cutting allowance, variation in Rolling-Margin,

breakages etc. (Wastage of Materials, supplied by owner should be returned to owner).

26. Compliance of

a) Minimum Wages Act

b) Equal Remuneration Act

c) Contract Labour

d) Workmen's Compensation Act

e) P.F

f) E S I S

g) Labour Inspector's Regulations and other relevant and applicable Acts of the land

27. Preparation of As-Built Drawings for all Civil, Structural works.

28. Bailing out water due to seepage/leakage/broken mains/Tidal action/water table/springs

etc. & keeping work area dry at all times, till the works in contractors scope is completed

29. Producing Test Certificates for steel & other materials as required. (The test fees shall be

reimbursed to the contractor).

30. Scaffolding, Re-scaffolding, Single-stage and double-stage.

Page 91: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

91

31. Construction of all enabling sheds like cement godown, stores, site office, Temporary

water tanks etc. & dismantle the same, on work completion remove debris as directed

and level the areas, to match with surroundings.

32. Wet materials for excavation.

33. Curing of concrete, masonry, plaster etc, including wetting the surface before plaster

coats.

34. Labour cost for reinforcement fixing in position, in half brick walls.

35. Shifting & stacking of materials, dispatched by Owner/Architect to site, pertaining to the

contractors scope of work.

36. Scaffolding work for lift-erection is included in civil-Contractor's scope.

37. Providing Chicken wire mesh on inside and outside, at all junctions of masonry and

concrete, as per specification.

38. Drawing temporary electrical/waterlines beyond the feeder provided by the owner for

equipment, lighting/captive use respectively (limited to civil work requirement).

Page 92: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

92

Annexure IV

QUOTED RATES ONLY:

The contractor may at his option, quote Rates only, for all such items, which in his opinion are

likely to be operative, but for which rates are not specifically invited.

Soon after award of work, the Contractor will however have to back-up all such rates, by a

proper Rate-Analysis, for approval by Architect/owner and definitely before commencement of

activity.

All extra-claims are liable to be summarily rejected, for which rates are not approved in writing,

prior to work commencement.

SL Probable Extra-item Units Rate in Rate in words

No Brief Description figures

Page 93: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

93

ANNEXURE V

LIST OF MATERIALS OF APPROVED BRAND AND/OR MANUFACTURE

Regarding use of materials of approved brand/manufacture wherever specified in the contract,

the order of preference for selection of materials of approved brand/ manufacture shall rest with

the Architect. The contractor shall obtain in writing the approval of Architect regarding this

before arranging/procuring the materials.

1. CEMENT

43 & 53 grade ordinary portland

cement

ACC, Ultratech, Gujarat Ambuja,

Birla Gold.

2 REINFORCEMENT TISCO

6 WATERPROOF CEMENT PAINTS Sandtex matt or any other brand

CEMENT PAINTS with ISI mark.

9 ANTITERMITE PCI, EXPRESS PESTICIDE,

GODREJ.

10 ANTITERMITE PAINT SOLIGNUM - BERGER PAINTS

Page 94: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

94

SECTION 13

BASIC RATES OF MATERIALS AT SITE

SR

NO. MATERIAL UNIT

RATE

(Rs.)

1 CEMENT BAG 325.00

2 REINFORCEMENT STEEL MT 45000.00

3 SAND (NATURAL ) BRASS 8000.00

4 SAND (CRUSHED) BRASS 3500.00

Page 95: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

95

Project Project Project Project –––– PROPOSED ICWAI BUILDINPROPOSED ICWAI BUILDINPROPOSED ICWAI BUILDINPROPOSED ICWAI BUILDING ON PLOT NO. 97, SECTOR NO.15, AT CBD BELAPUR, NAVI G ON PLOT NO. 97, SECTOR NO.15, AT CBD BELAPUR, NAVI G ON PLOT NO. 97, SECTOR NO.15, AT CBD BELAPUR, NAVI G ON PLOT NO. 97, SECTOR NO.15, AT CBD BELAPUR, NAVI MUMBAI.MUMBAI.MUMBAI.MUMBAI. BILL OF QUANTITIES FOR PILING WORK BILL OF QUANTITIES FOR PILING WORK BILL OF QUANTITIES FOR PILING WORK BILL OF QUANTITIES FOR PILING WORK (Micro Pile work) Sr.No.Sr.No.Sr.No.Sr.No. DescriptionDescriptionDescriptionDescription UnitUnitUnitUnit QntyQntyQntyQnty RateRateRateRate Amt.Amt.Amt.Amt. 1 Mobilisation charges for Micro Pile Machine including labours, hutments and allied equipments all complete. Per Rig 1 2 Boring & Constructing Cast - In - Situ bored piles in M:30M:30M:30M:30 grade concrete by using Ready Mix Concrete with Micro Micro Micro Micro Pilling rig machine, Pilling rig machine, Pilling rig machine, Pilling rig machine, setting out cardinal points, driving 4mm thickness of permanent steel casing up to non – collapsible strata, boring in overburden through whatever strata encountered up to weathered rock, all as directed by RCC Consultant & Site In Charge - in soft soil, soft weathered rock or locally encountered boulders including dewatering, placing concrete by tremie pipe method, compacting of concrete, withdrawal of steel casing, mobilization of Micro Pile Machine and other equipments, necessary personnel and erecting them etc complete. On completion of piling work, demobilizing all the equipments including cleaning and reinstating the site to original condition as acceptable by the site in charge. (Length of pile shall be measured from bottom of the pile to (Length of pile shall be measured from bottom of the pile to (Length of pile shall be measured from bottom of the pile to (Length of pile shall be measured from bottom of the pile to cut off level for payment)cut off level for payment)cut off level for payment)cut off level for payment) 300mm dia. @ 39 nos. approx.

Rm

500

3 Extra over Item no. 2 for Drilling in Hard rock up to the desired depth as per the requirement of the structural drawing. Rm 60 4 Reinforcement steel : Decoiling, straightening, cutting, bending and placing in position (Lowering) at all levels and binding with approved quality GI binding wire (18g G.I. / M.S. ) Quantity of steel as per structural drawing and including concrete cover blocks etc. complete (Only approved overlaps shall be measured and paid for) MT .

4.5 5 Removal and disposal of muck generated while piling and disposing it out of the site. L/s 6 Applying Epoxy coating to surface of permanent steel casing. Sqm 400 7 Casting of RCC coping beam with M: 30 M: 30 M: 30 M: 30 grade concrete using

Page 96: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

96

RMC and including form work, adequate cover blocks etc. complete. Cum 5 TOTAL Note:Note:Note:Note: 1 These quantities are tentative. Any variation in quantities shall be acceptable to the contractor. 2 The rates shall be exclusive of all taxes, levies, octrai, work contract tax etc. and all statutory requirements such as labour insurance, ESIS etc. 3 The contractor shall bear the cost of water, electricity and other services required for the construction purpose. 4 Disposal of the bored muck is the responsibility of the Piling Contractor. No separate payment shall be made on this account.

Page 97: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

97

BILL OF QUANTITIES FOR PILING WORK (BORED PRECAST PILES)

PROPOSED BLDG. ON PLOT NO.96, SECTOR 15, AT BELAPUR, NAVI MUMBAI

(By Conventional Method)

Sr.No.

Description

Quantity

Unit

Rate

Amount

1 Mobilization and demobilization of rigs with all equipment, tools tackle in good working condition.

a) For 600 dia. (4 Nos.)

1

Nos.

2 Providing, laying and fixing in position reinforcement as per RCC drawings for precast piles including cutting, bending and binding with 16 gauge MS annealed binding wire including placing of proper concrete cover/ plastic cover blocks, chair supports etc. Only as laid weight will be measured .The rate to include all cuts, chairs, and support and wastage etc.compite as specified and directed. a) High Yield Deformed Bars Grade Fe:415

1

MT

3 Providing and laying in position RCC M:30 Grade for casting of precast piles using 20 mm and down grade aggregate (unless otherwise specified) including form work, machine mixing, consolidating with mechanical vibrators, ramming with iron rods, curing, (excluding Steel reinforcement) etc. complete as directed and instructed.

a) For 600 dia. (4 Nos.)

50

R.M.

4 Applying Epoxy paint to surface of precast pile such as Nitocoat (Fosroc)

100

Sqm.

5 Taking bore of specified diameter for precast RCC piles using conventional method, including withdrawal of shell, removal of earth/ muck and disposal muck etc. complete.

a) For 600 dia. Pile (4 Nos.)

50

R.M.

6 Carrying out chiseling work in hard strata like boulders, soft and hard rock including removing and stacking the loose material etc. by conventional method

4

Cum.

Page 98: TENDER FOR PROPOSED PILING WORK OF ......1 TENDER FOR PROPOSED PILING WORK OF UNDERGROUND TANK & COMPOUND WALL OF INSTITUTIONAL BUILDING At Navi Mumbai FOR THE INSTITUTE OF COST ACCOUNTANTS

98

7 Erecting the precast piles (approx. 10 to 12 m long) and placing it in required bore hole, including flushing of bore hole, etc. complete.

a) For 600 dia. Pile (4 Nos.)

4

Nos.

Sr.No

Description

Quantity

Unit

Rate

Amount

8 Providing and carrying of grouting work for the pile using cement : Quartz sand (1:1) and FOSROC Cebex 100 admixture

5

Cu.m.

9 Chipping and dressing of precast RCC piles including cleaning reinforcement and removal of dismantled material etc.

1

Cum.

10 Carrying out NDT on piles through the approved testing agency

a) Pile integrity test (4 Nos.)

4

Nos.

TOTAL FOR PILING WORK

Note 1 These quantities are tentative. Any variation in quantities shall be acceptable to the

contractor. 2 The time limit for completion shall be 45 days from the date of commencement of

work.

3 The rates shall be inclusive of cost of material, labour, tools & equipments, all taxes, levies, octrai, work contract tax etc. all statutory requirements such as labour insurance, ESIS etc.

4 The contractor shall bear the cost of water, electricity and other services required for the construction purpose.