8/2/2019 Tender Evaluation Report for Bank of Gisenyi
1/9
Bank of Gisenyi
Tender Evaluation Report
Proposed Bank of Gisenyi (BG)
8/2/2019 Tender Evaluation Report for Bank of Gisenyi
2/9
Bank of Gisenyi P a g e | II Proposed Bank of Gisenyi (BG),Gisenyi City Tower (GCT) Branch FitOut
Archus AssociatesArchitectural & Urban Solutions
REPUBLIC OF THE RWANDA
BANK OF GISENYI
Tender Evaluation Report
Proposed Bank of Gisenyi (BG), Gisenyi City
Tower (GCT) Branch Fit Out
Title of Tender: Proposed Bank of Gisenyi
(BG), Gisenyi City Tower
(GCT) Branch Fit Out
Tender Reference Number: -
Procurement Method: Selective Tendering
Date of Issue: July 2011
8/2/2019 Tender Evaluation Report for Bank of Gisenyi
3/9
Bank of Gisenyi P a g e | III Proposed Bank of Gisenyi (BG),Gisenyi City Tower (GCT) Branch FitOut
Archus AssociatesArchitectural & Urban Solutions
Proposed Bank of Gisenyi (BG), Gisenyi City
Tower (GCT) Branch Fit Out
Table of Contents
Cover .......................................................................................................- II -
Report Control Form ........................................................................... - III -
Table Of Contents ................................................................................. - IV -
1 INTRODUCTION .................................................................................. - 1 -2 PROJECT DATA.................................................................................... - 1 -3 LIST OF CONTRACTORS WHO RESPONDED TO THE TENDER.................. - 2 -4 SUMMARY OF BID OPENING ................................................................ - 2 -5 PRELIMINARY EVALUATION OF BIDS .................................................... - 4 -6
DETAILED TECHNICAL EVALUATION
..................................................... - 4 -7 FINANCIAL EVALUATION ..................................................................... - 5 -8 CONCLUSION & RECOMMENDATION FOR TENDER AWARD .................. - 5 -ANNEX I: TENDER OPENING FORM ................................................................ - 6 -ANNEX II: TENDER OPENING ATTENDANCE RECORD ...................................... - 6 -ANNEX III: LETTER OF INVITATION TO TENDER............................................... - 6 -ANNEX IV: MINUTES OF PRE-BID MEETING .................................................... - 6 -ANNEX V: PAGES SHOWING SOURCES OF ARITHMETIC ERRORS
...................... - 6 -
8/2/2019 Tender Evaluation Report for Bank of Gisenyi
4/9
Bank of Gisenyi P a g e | - 1 - Proposed Bank of Gisenyi (BG), Gisenyi CityTower (GCT) Branch Fit Out
1 IntroductionThis report follows the submission of tenders for the proposed fit out of the GCT
Bank of Gisenyi Branch project.
The project comprises taking possession of the GCT branch and completing the fit
out which consists of but not limited to construction of walling of various sizes,
cladding, aluminium internal partitioning, fixing aluminium and mahogany doors and
frames, fixing teller cubicles and cash tills, fixing various cabinets and joinery fittings,
tiling the floors and walls, fixing acoustic ceilings and electrical and mechanical
installations including but not limited to lighting installations, power installations,
power controls, data cabling, fire detection systems, air-conditioning, sanitary ware
and gas piping.
The report is presented in eight sections commencing with this introduction and
eventually terminating with the conclusion and recommendation for award of the
Contract. In between the report provides a history of the tendering procedure, makes
a preliminary and detailed evaluation of the bids and provides a financial analysis of
the responsive bids.
2 Project DataTitle of Tender: Proposed Bank of Gisenyi (BG), Gisenyi City
Tower (GCT) Branch Fit Out
Source of Funding: Internal Funds
Date of Invitation For Bids: Wednesday, 29 June 2011
Date of Pre-Bid Conference: Tuesday, 5 July 2011
Date of Opening Of Bids: Thursday, 15 July 2011
Number of Bidders Who
Responded:
4 out of 5
Start of Evaluation: Friday 16 July 2011
End Of Evaluation: Tuesday 19 July 2011
8/2/2019 Tender Evaluation Report for Bank of Gisenyi
5/9
Bank of Gisenyi P a g e | - 2 - Proposed Bank of Gisenyi (BG), Gisenyi CityTower (GCT) Branch Fit Out
3 List of Contractors Who Responded to the Tender
4 Summary of Bid Opening
Name of bidders Contact person Full Address
1. Roko Construction(Rwanda) Sarl
Nigel Done Plot 4148, Gikondo
B.P 323 Gisenyi, Rwanda
Tel: +250 830 4181
e-mail: [email protected]
2. China Civil EngineeringConstruction Corporation
Han Ping P.B 6788 Gisenyi Rwanda
Tel: +250 788 30 1062e-mail: [email protected]
3. Thomas & Piron GrandLACS.
Kenneth Andoh Gikondo Gisenyi
P.B 6589 Gisenyi Rwanda
Tel: +250 788 30 5076
e-mail: [email protected]
4. Real Contractors Ltd Charles Lugira Gikondo GisenyiP.B 4374 Gisenyi Rwanda
Tel: +250 788 51 8686
website: www.realcontractors.net
Name of Bidder Price without taxes
(RWF)
Price with taxes
(RWF)
Completion Period
(weeks)Roko Construction
(Rwanda) Sarl226,779,620 267,599,952 28
China Civil Engineering
Construction Corporation103,034,047 121,580,176 7
Thomas & Piron Grand
LACS.309,012,809 364,635,115 20
Real Contractors Ltd 243,464,123 287,287,665 8
8/2/2019 Tender Evaluation Report for Bank of Gisenyi
6/9
Bank of Gisenyi P a g e | - 3 - Proposed Bank of Gisenyi (BG), Gisenyi CityTower (GCT) Branch Fit Out
Before the opening of the bids, one of the bidders queried why four bids were due to
be opened yet at dead line of submission apparently only three bids had been
submitted.
The other bidders were asked about their opinion on the matter and it was
established that this could have been caused by the confusion between the dead line
for submission of the bid (Thursday, 14 July 2011 at 10.00 a.m.) and the time for
opening of the bids (same day but at 3.00 p.m.). So before the opening, the other
bidders allowed the bid opening ceremony to proceed and the matter to be decided
by the evaluating consultants.
Having opened all the bids in a public ceremony attended by all the competing
bidders, the evaluating consultants decided to subject the apparent late bid to
evaluation as well, because of the difficulty of dismissing a bid that has already been
opened and the results known to public. The only way such a bid could have been
excluded is if it was not received in the first place.
-
50,000,000
100,000,000
150,000,000
200,000,000
250,000,000
300,000,000
350,000,000
400,000,000
Roko Construction(Rwanda) Sarl
China CivilEngineeringConstruction
Corporation
Thomas & PironGrand LACS.
Real ContractorsLtd
8/2/2019 Tender Evaluation Report for Bank of Gisenyi
7/9
Bank of Gisenyi P a g e | - 4 - Proposed Bank of Gisenyi (BG), Gisenyi CityTower (GCT) Branch Fit Out
5 Preliminary Evaluation of BidsAll bids were subjected to a preliminary evaluation to determine whether they are
complete and substantially responsive. Since this was a restricted tender where onlyfive (05) firms were invited, the preliminary evaluation restricted itself to the
completeness of bid, proof of payment of the non-refundable tender fees and
signing of the Contractors form. The table below summarises the findings of the
preliminary evaluation.
Criteria for Preliminary Evaluation BiddersRoko CCECC Thomas Real
Bid Form duly completed and signed by
the Bidder, Bid validity period shall be 90
days.
Pass Pass Pass Pass
Bill of Quantity duly completed by the
BidderPass Pass Pass Pass
Contractors Form duly completed Pass Pass Pass Pass
Evidence of purchase of tender
document providedPass Pass Pass Pass
Acceptance for Detailed technical
evaluation Yes Yes Yes Yes
The preliminary evaluation did not find anything to warrant the disqualification of
any bidder and therefore all submitted bids were accepted for detailed evaluation.
6 Detailed Technical EvaluationSince the short listed bidders capacity to undertake the project is undoubted, the
Companies having completed some of the landmark projects in Gisenyi, qualification
information was not required.
The bidders were deemed to have sufficient capacity in terms of technical personnel,
equipment and financial capability. In addition, the bidders were expected to confirm
that ability by submitting their bids quickly as the Employer is desirous of completing
the project expeditiously.
8/2/2019 Tender Evaluation Report for Bank of Gisenyi
8/9
Bank of Gisenyi P a g e | - 5 - Proposed Bank of Gisenyi (BG), Gisenyi CityTower (GCT) Branch Fit Out
7 Financial EvaluationAll the bids were submitted in Rwanda Francs (RWF) and therefore there was no need
for foreign currency adjustments / conversion in order to put them on the same
basis.
An arithmetic check was however carried out on all the tenders. The table below
summarises the findings.
Note: Refer to Annex V for details of arithmetic errors.
8
Conclusion & Recommendation for Tender Award
Having evaluated the bids submitted for the proposed fit-out of the Bank of Gisenyi,
Gisenyi City Tower Branch, and having conducted a preliminary and detailed analysis
of the bids including the financial analysis, and being convinced about the ability of
the bidder to execute the works and being cognisant of the Clients need to have the
project completed expeditiously, we hereby recommend the award of this tender to
China Civil Engineering Construction Company for total consideration of RWF
124,000,000= (One hundred twenty four million Rwandese Francs), and a
completion period of7 weeks subject to:-
1) Submission of an acceptable Performance Bond2) Submission of a fully resourced Work Programme with clearly identifiable
milestones.
Bidder Amount before
correction of errors
Amount after
correction of errors
Rank
Roko 267,599,952 279,435,584 2
CCECC 121,580,176 123,940,175 1
Thomas & Piron 364,635,115 364,635,115 4
Real 287,287,665 287,287,665 3
8/2/2019 Tender Evaluation Report for Bank of Gisenyi
9/9
Bank of Gisenyi P a g e | - 6 - Proposed Bank of Gisenyi (BG), Gisenyi CityTower (GCT) Branch Fit Out
Annex I: Tender Opening Form
Annex II: Tender Opening Attendance Record
Annex III: Letter of Invitation to Tender
Annex IV: Minutes of Pre-bid Meeting
Annex V: Pages Showing Sources of Arithmetic Errors