Tender 19sep12a

Embed Size (px)

Citation preview

  • 8/11/2019 Tender 19sep12a

    1/8

    BROAD TECHNICAL SPECIFICATIONS

    OF

    BOILER TURBINE GENERATOR (BTG)

    FOR

    2X300 MW COAL BASED THERMAL POWER PROJECT

    AT

    BOTSWANA

  • 8/11/2019 Tender 19sep12a

    2/8

    1.

    INTENT OF SPECIFICATIONS:

    This specifications in intended to cover supply and installation of 2X300 MW Boiler

    island including ESP, Turbine Generator sets and respective auxiliaries associatedintegral and power cycle piping . Scope shall include design, engineering,

    manufacture, procurement, inspection and testing at manufacturers works,

    packing and shipment and delivery at site.

    In addition the bidders scope shall also include erection/installation including

    loading & unloading , storage and handling at site, site testing, commissioning,

    trial run, performance and guarantee tests and other services including supply co-

    ordination, engineering and project management related to equipments/systems,

    liquidation/attending to punch points.

    Bidder shall be responsible for provising all material, equipment and services,

    required to complete the scope and fulfill the intent of ensuring efficiency,

    operatibility, maintainability and reliability of the complete work.

    2.

    DESCRIPTION OF SITE:

    Site Mmamabula, Botswana

    Nearest Town Gaborone (180 km)Mahalapye (70 km)Francistown (250 km)

    Nearest RailwayStation Mookane (25 km)Mahalapye (70 km)

    Nearest Airport Gaborone (180 km)

    Nearest Seaport Botswana doesnt have a seaportWalvis Bay (Namibia) 1600 kmMaputo (Mozambique) 1100 km

    National Highway A1 connecting Gaborone to Francistown passing throughMahalapyeSite is off 23 km from A1 at the Tropic of Capricorn line

    3.

    CODES AND STANDARDS

    3.1.

    Except where otherwise specified, all items under Contractor's scope shall

    comply with the appropriate Indian codes & standards or agreed

    internationally accepted codes & standards as listed below, each

    incorporating the latest revisions at the time of Contract.

    3.2.

    Where the Contractor proposes alternative codes or standards he shall

    include in his bid one copy (in English) of each Standard to which materials

  • 8/11/2019 Tender 19sep12a

    3/8

    offered shall comply. In such case, the adopted alternative standard shall be

    equivalent or superior to the standards mentioned in the specification.

    3.3.

    The Plant shall conform to various statutory regulations prevailing in

    Botswana such as Boiler Regulations, Electricity Rules, Explosives Act,

    Factories Act, Environment (Protection) Act etc. Wherever required,

    approval from statutory authorities for the Plant supplied under the

    specification shall be the responsibility of the Contractor.

    3.4. In the event of any conflict between the codes and standards referred

    above, and the requirements of this specification, the requirements that are

    in this specification shall govern.

    3.5.

    In case of any change of code, standards and regulations between the date

    of award of Contract and the date the Contractor proceeds withmanufacturing, the Owner shall have the option to incorporate the changed

    requirements. It shall be the responsibility of the Contractor to advise Owner

    of the resulting effect.

    3.6. List of Codes & Standards for Reference :

    a) Boiler Regulations Codes & standards prevailing in Botswana (IBR).

    b) Electricity, Explosives, factories Rules prevailing in Botswana.

    c)

    Pollution Control regulations of Botswana.d)

    Any other statutory Codes/ Standards/ Regulations prevailing in

    Botswana.

    e)

    Environment (Protection) Act, USA.

    f)

    International Standards Organization (ISO).

    g)

    International Electro-technical Commission (IEC).

    h)

    American Society of Mechanical Engineers (ASME).

    i) American National Standards Institute (ANSI).

    j) American Society for Testing and Materials (ASTM).

    k) American Institute of Steel Construction (AISC).

    l)

    American Welding Society (AWS).

    m)

    National Fire Protection Association (NFPA), USA.

    n)

    National Electrical Manufacturer's Association (NEMA), USA.

    o)

    Japanese Electro-technical Committee (JEC).

    p)

    Institute of Electrical and Electronics Engineers (IEEE), USA.

    q)

    Federal Occupational Safety and Health Regulations (OSHA), USA.

    r)

    Instrument Society of America (ISA).

    s)

    National Electric Code (NEC), USA.

    t)

    Heat Exchanger Institute (HEI ), USA.

  • 8/11/2019 Tender 19sep12a

    4/8

    u) Tubular Exchanger Manufacturer's Association (TEMA), USA.

    v) Hydraulic Institute Standards (HIS), USA.

    w) International Electro-Technical Commission Publications.

    x)

    Power Test Code for Steam Turbines (PTC), USA.

    y)

    Applicable German Standards (DIN).

    z)

    Applicable British Standards (BS).

    aa)

    Applicable Russian Standards (GOST)

    bb)

    Electric Power Research Institute (EPRI), USA.

    cc)

    Standards of Manufacturer's Standardization Society (MSS), USA.

    dd) American Petroleum Institute (API).

    ee) ICAO.

    4.

    SCOPE OF WORK:

    Scope covers design, engineering, manufacturing, procurement, inspection &

    testing at manufacturers works, supply, insurance, receipt at site, storage and

    preservation at site, intra site transportation, construction, erection, trial run,

    commissioning, performance guarantee testing, handing over to owner, along with

    commissioning & recommended spares for two years operation, catalogues,

    drawings, documents and services including lubricants, transformer oil,

    consumables for the proposed 2X300 MW Thermal power plant.

    Division of work shall be as per attached Annexure A.

    Terminal points shall be as per attached Annexure B

    Analysis of Coal to be utilized is as per attached Annexure - C

    5. BRIEF TECHNICAL REQUIREMENTS:

    STEAM GENERATOR & AUXILIARIES

    Two nos steam generator of 300 MW capacity with an indicative boiler outlet

    pressure 175 Kg/cmsteam temperature of SH and RH 540/540 Deg C to match

    turbine inlet steam parameters including all related auxiliary equipments, control

    & instrumentation. Steam generator shall be sub-critical type, natural circulation,

    double pass/ tower type, single radiant furnace, dry bottom, balanced draft,pulverized coal fired with all auxiliaries, corner fire, ESP, integral piping,

    elevators, coal bunkers and structures, SCAPH,etc.

    Boiler maximum continuous rating (BMCR) shall correspond to at least 103% of

    steam flow at turbine inlet under VWO condition plus continuous steam

    requirement of auxiliary steam systems of the unit.

    Design criteria:

    a) Excess air at economizer outlet at TMCR load: 20% (minimum)

  • 8/11/2019 Tender 19sep12a

    5/8

    b) Flue gas temperature at air-heater outlet at TMCR load: 125 Deg C

    c)

    Loss due to unburnt carbon in ash at all loads: 3%

    Following minimum values of anticipated parameters with respect to ESPs shall be

    considered in steam generator design:

    i)

    Air infiltration in ESP: 1% of ESP inlet gas flow

    ii) Pressure drop in ESP: 20mm WC

    iii)

    Temperature drop in ESP: 2 Deg C

    The design of steam generator shall be such that it does not call for any oil

    support for flame stabilization beyond 40% BMCR load.

    Steam generator shall be designed for continuous operation with all HP heaters out

    of operation. Under above condition the super heater and reheater outlet steam

    temperature shall be maintained at rated values within the whole control range of

    steam generator load.

    When unit trips on full load, HP-LP bypass system will come into operation.

    Design life of the steam generator sets shall be 30 years minimum. However unit

    shall also be capable of operation for two shifting cycle. The design duty for 30

    years shall be as follows (as per IEC 45-1):

    Very hot: 300

    Hot start: 6000

    Warm start: 1000

    Cold start: 300

    Design conditions:

    Main steam line pressure drop, maximum: 7 to 8 bar

    Super heater pressure drop, maximum: 15 bar

    Pressure drop across economizer: 4 bar

    Pressure drop through steam generator from economizer inlet to superheter

    outlet: 20 bar

    Reheater pressure drop maximum: 2 bar

    Fans including drives and controls

    Induced draft system including two nos ID fans, combustion air system including

    two nos. FD fans and two nos PA fans with 2 X 60 % capacity.

  • 8/11/2019 Tender 19sep12a

    6/8

    Air preheaters

    Rotary regenerative trisector type.

    Soot Blower system

    Wall Blower, LRSB and associated complete system required for soot blowing

    system

    Coal feeding Equipment sizing: Steam generator shall be furnished with

    pulverized and raw coal feeder to attain BMCR of steam generator. The pulverizes

    shall be of sufficient capacity to attain BMCR when firing specified range of coal

    and one pulverizer and feeder out of service.(N+1+1 mills).

    Coal feeding system

    Crushed coal from the crusher will be fed to raw coal bunkers/silos. The capacity

    of series of bunkers/silos per unit would be to provide 12 hrs requirements at

    maximum mill capacity of the unit.

    Power cycle piping: piping with hangers & supports.

    Ducting, damper and expansion joints:

    Thermal insulation: All equipments/pipes/ ducts whose surface temperature is

    higher than 60 Deg C shall be provided with thermal insulation along with

    aluminum cladding for personnel protection and heat conservation.

    PG test: as per ASME PTC-4

    Electro Static Precipitators:

    For collection of dust (fly ash), adequately sized outdoor type ESP and fabric bag

    filter shall be installed on the cold end side of regenerative air preheater for each

    unit. The flue gas shall be drawn from air pre heater outlet and guided through

    adequately sized duct work.

    The basic idea of the ESP+FF hybrid filter is to remove the large amount of dust

    (80-90%) by the ESP first to reduce the dust concentration of flue gas, then collectthe residual particulate dust ( 10-20%) from the flue gas by the filter and ensure

    dust emission standard.

    The ESP+Filter will remove particulate from flue gas of the steam generators to

    achieve guaranteed outlet emission of less than 50 mg/Nm.

    Scope of supply for ESP shall include but not limited to followings:

    a)

    Casing and hoppers with required accessories such as heaters, vibrators, level

    detectors, and their controls.

  • 8/11/2019 Tender 19sep12a

    7/8

    b) Structural steel and access stairs, platforms and ladders.

    c) Gas distribution system

    d) Collecting electrodes

    e)

    Discharge electrodes

    f)

    Rapping system with microprocessor based control system

    g)

    Dust hoppers

    h)

    Casing

    i) Opacity monitors

    STEAM TURBINE AND AUXILIARY:

    a)

    Steam turbine shall be reaction type comprised of tandem compound, single

    reheat, regenerative, condensing type, single/ multi cylinder type, with

    separate HP, separate IP and separate LP casing OR combined HP-IP as per

    standard design of manufacturer directly coupled with generator suitable for

    indoor installation.

    Turbine capability/systems

    a)

    Net power output at generator terminals at TMCR: 300 MW each

    b)

    VWO rating: 105 % of TMCR

    c)

    Limitation of variation from rated steam pressure/temp: as per IEC-45

    d)

    Number of extractions: 6 or more

    e)

    Make up : 0%

    f)

    Speed: 3000 RPM

    g)

    operating frequency range: 47.5Hz to 51.5 Hzh)

    type of governing: Throttle

    i)

    type of governor: electronic

    j)

    turbine oil pumps: MOP (1X100% shaft driven), AOP(2X100% one AC+ one

    DC), EOP(1X100%DC),JOP(2X100% -one AC+ one DC)

    k)

    control oil pumps: 2X100% AC

    l)

    oil purification equipment/ oil tank

    m)turning gear: with hand barring facility

    n) bearing cap vibration: ISO-10816

    o)

    shaft vibration: ISO-7919

    p)

    HP/LP Bypass system

    q)

    Integral piping with hangers & supports

    r)

    Drains & valves

    s)

    Noise level: 85 dBA at 1.5 Mtr from outline of Equipment

    t)

    Feed water HP /LP heaters/Dearator for 10 minutes capacity

    u)

    Power cycle pumps ( MDBFP,TDBFP, CEP)

    v)

    Butter fly valves

    w)Air extraction system Vacuum pumps ( 3x50%)

    x) RE Joints

  • 8/11/2019 Tender 19sep12a

    8/8

    y) Condenser: Air cooled

    z) emergency stop and control valves, reheat stop and control valve

    aa)Turbine automation system (ATRS)

    bb)

    Turbine supervisory system

    TURBOGENERATOR

    300 MW Three phase, horizontal mounted, indoor installed, hydrogen cooled, two

    pole, class F winding insulation with temperature rise limited to class B.

    For design opf equipment/systems, ambient temp of 50 Deg C and relative humidity

    of 95% shall be considered.

    Equipment shall be suitable for rated frequency of 50 Hz with a variation of +3% & -

    5%, terminal voltage of +/- 10% and 5% combined variation of voltage & frequency.

    All the equipments shall confirm to latest edition of relevant International codes andstandards. Generator shall conform to IEC-34.

    Rated parameters:

    Power factor: 0.85(lag) to 0.95(lead)

    Terminal voltage: 20 to 22KV

    Frequency: 50 Hz

    Speed: 3000 RPM

    Short circuit ratio: not less than 0.5 (without negative tolerance)

    System of cooling:

    Stator winding: Hydrogen cooled

    Rotor winding; directly hydrogen cooled

    Systems: gas system/ seal oil system/stator water cooling system (if

    applicable)/excitation System (brushless/static)